SlideShare une entreprise Scribd logo
1  sur  20
Simple example of EVM in action
© 2014 Planisware
The plan
• Our team has been tasked with planting the trees on
the plot of land behind our company’s new factory
• The plan:
– 30 batches of 20 trees (600 trees)
– 5 batches per day (100 trees)
– budgeted cost per tree 2.90$ (2.5$ per baby tree / 0.40$
for the slow release fertiliser)
→ total budget 1,740$
© 2014 Planisware 2
After the first day…
• 70 trees were planted (the team hit a patch with
stones that had to be removed before the trees
could be planted)
• Total cost was 350 $ (we had to rent a special
machine to help remove the stones which cost 147$
for the day)
• Simple EVM calculation:
– Earned Value = 70 trees planted  2.90$ = 203$
– Budgeted Cost = 100 trees planned per day  2.90$ = 290$
– Actual Cost = 70 trees planted  2.90$ + 147$ for the machine = 350$
© 2014 Planisware 3
Visually…
0
50
100
150
200
250
300
350
400
Start 1st day
Actual cost = 350$
Budgeted cost = 290$
Earned Value = 203$
© 2014 Planisware 4
Regarding cost…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 5
We are here
Regarding cost…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 6
We are here
We should have been here
Regarding cost…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 7
Cost variance = EV – AC
= 203$ – 350$ = -147$ < 0
Regarding cost…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 8
Cost variance = EV – AC
We’re over budget,
and have spent
203  350 = 58%
more budget than
anticipated (our cost
performance index)
= 203$ – 350$ = -147$ < 0
Regarding schedule…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 9
We are here
Regarding schedule…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 10
We are here
Which is where we
should have been then
Regarding schedule…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 11
Schedule variance
in hours
Regarding schedule…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 12
Schedule variance
in hours
= 203$ – 290$ = = -87$ < 0
Schedule variance
in dollars = EV – BC
Regarding schedule…
0
50
100
150
200
250
300
350
400
Start 1st day
EV
AC
BC
© 2014 Planisware 13
Schedule variance
in hours
We’re late and
have only performed
203/290 = 70% of
the work planned
(our schedule
performance index)
= 203$ – 290$ = = -87$ < 0
Schedule variance
in dollars = EV – BC
The consequences
0
500
1000
1500
2000
2500
3000
Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th
© 2014 Planisware 14
Earned Value
today
Estimate at Completion
EAC = 3,000$
Budget at Completion
BAC = 1,740$
Extending the
Actual Cost
into the future
gives us the end
result if we do
not modify the
performance of
the project
The consequences
0
500
1000
1500
2000
2500
3000
Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th
© 2014 Planisware 15
Earned Value
today
Estimate at Completion
EAC = 3,000$
Budget at Completion
BAC = 1,740$
Cost Overrun
The consequences
0
500
1000
1500
2000
2500
3000
Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th
© 2014 Planisware 16
Earned Value
today
Planned end date
= 6 days
Estimate at completion
= 8.57 days
Project Slip
Estimate at Completion
EAC = 3,000$
Budget at Completion
BAC = 1,740$
Cost Overrun
The consequences
→ If we continue at this rate, we will need: 1,740$  58% = 3,000 $
(cost estimate at completion)
and 6 days  70% = 8.57 days (schedule estimate at completion)
to finish the work.
→ If we want to finish on budget, we need to work at
(planned remaining budget)  (actual remaining budget)
(1,740 – 290)  (1740 – 350) = 104.3% of the originally planned
performance
→ If we want to finish on time, we need to work at
(actual remaining work)  (planned remaining work)
(600 – 70)  (600 – 100) = 106% of the originally planned
performance
© 2014 Planisware 17
In technical terms…
In real life, the elements we calculated have slightly
different names:
• The Actual Cost is usually referred to as the Actual
Cost of Works Performed (ACWP)
• The Planned Cost = Budgeted Cost for Work
Scheduled (BCWS)
• The Earned Value = Budgeted Cost for Work
Performed (BCWP)
© 2014 Planisware 18
Summary
© 2014 Planisware 19
today
time
cost
ACWP
(Actual Cost of
Work Performed)
BCWS
(Budgeted Cost of
Work Scheduled)
BCWP
(Budgeted Cost of
Work Performed)
completion
date
Budget at
Completion (BAC)
Estimate at
Completion (EAC)
Schedule variance in $
SV = BCWS - BCWP
Cost variance in $
CV = ACWP - BCWP
Cost Overrun
Project SlipSchedule variance
in hours
To learn more about EVM and tools to
help manage it, visit our glossary:
www.planisware.com/glossary/earned-
value-management
© 2014 Planisware 20

Contenu connexe

Tendances

PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1Anand Bobade
 
Earned value management
Earned value managementEarned value management
Earned value managementAshif AR
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...Fahad Ali
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation TafseerKishan Solankimbaccepmp
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to PracticeFiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to PracticeCCT International
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve Satish Yadavalli
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and AgileGlen Alleman
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoringharoldtaylor1113
 

Tendances (20)

PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to PracticeFiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
PROJECT SCHEDULING
PROJECT SCHEDULINGPROJECT SCHEDULING
PROJECT SCHEDULING
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 

Similaire à A simple example of Earned Value Management (EVM) in action

October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6HARDIK PARIKH
 
Homework chapter 7
Homework chapter 7Homework chapter 7
Homework chapter 7Miles Nowak
 
Culture Check on using Earned Value in Organization
Culture Check on using Earned Value in OrganizationCulture Check on using Earned Value in Organization
Culture Check on using Earned Value in OrganizationGhassan Kabbara
 
Earned value management
Earned value managementEarned value management
Earned value managementwhizkris
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Vivek Prakash
 
Earnvalue analysis in Software engineering
Earnvalue analysis in Software engineeringEarnvalue analysis in Software engineering
Earnvalue analysis in Software engineeringNitish Kumar
 
How Celoxis Helps in Budgeting & Costing
How Celoxis Helps in Budgeting & Costing How Celoxis Helps in Budgeting & Costing
How Celoxis Helps in Budgeting & Costing Nikhil Daddikar
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfNabeel Ahmad
 
Time value of money- TVM ( Discouting and Compounding)
Time value of money- TVM ( Discouting and Compounding)Time value of money- TVM ( Discouting and Compounding)
Time value of money- TVM ( Discouting and Compounding)Sweetp999
 
Earned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptxEarned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptxssuser5fc1e7
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
Padgett.sam
Padgett.samPadgett.sam
Padgett.samNASAPMC
 
7.4 Forecasting Techniques
7.4 Forecasting Techniques7.4 Forecasting Techniques
7.4 Forecasting TechniquesDavidMcLachlan1
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIDavidMcLachlan1
 
Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptvitumbikokhoswe1
 

Similaire à A simple example of Earned Value Management (EVM) in action (20)

October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
October 2012-webinar-calculating-earned-value-and-estimate-to-complete-in-p6
 
Homework chapter 7
Homework chapter 7Homework chapter 7
Homework chapter 7
 
Culture Check on using Earned Value in Organization
Culture Check on using Earned Value in OrganizationCulture Check on using Earned Value in Organization
Culture Check on using Earned Value in Organization
 
Chapter 9 q&p
Chapter 9 q&pChapter 9 q&p
Chapter 9 q&p
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
 
Earnvalue analysis in Software engineering
Earnvalue analysis in Software engineeringEarnvalue analysis in Software engineering
Earnvalue analysis in Software engineering
 
How Celoxis Helps in Budgeting & Costing
How Celoxis Helps in Budgeting & Costing How Celoxis Helps in Budgeting & Costing
How Celoxis Helps in Budgeting & Costing
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
Time value of money- TVM ( Discouting and Compounding)
Time value of money- TVM ( Discouting and Compounding)Time value of money- TVM ( Discouting and Compounding)
Time value of money- TVM ( Discouting and Compounding)
 
Earned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptxEarned Value Management - Project Controls - Schedule Only.pptx
Earned Value Management - Project Controls - Schedule Only.pptx
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Padgett.sam
Padgett.samPadgett.sam
Padgett.sam
 
7.4 Forecasting Techniques
7.4 Forecasting Techniques7.4 Forecasting Techniques
7.4 Forecasting Techniques
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.ppt
 
Project Control Process
Project Control ProcessProject Control Process
Project Control Process
 

Dernier

Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGpr788182
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Timegargpaaro
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecZurliaSoop
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...ssuserf63bd7
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Adnet Communications
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGpr788182
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAITim Wilson
 
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptxQSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptxDitasDelaCruz
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Falcon Invoice Discounting
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingNauman Safdar
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptxRoofing Contractor
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGpr788182
 
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistanvineshkumarsajnani12
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateCannaBusinessPlans
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon investment
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptxnandhinijagan9867
 

Dernier (20)

HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024HomeRoots Pitch Deck | Investor Insights | April 2024
HomeRoots Pitch Deck | Investor Insights | April 2024
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
WheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond InsightsWheelTug Short Pitch Deck 2024 | Byond Insights
WheelTug Short Pitch Deck 2024 | Byond Insights
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptxQSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
QSM Chap 10 Service Culture in Tourism and Hospitality Industry.pptx
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Pre Engineered Building Manufacturers Hyderabad.pptx
Pre Engineered  Building Manufacturers Hyderabad.pptxPre Engineered  Building Manufacturers Hyderabad.pptx
Pre Engineered Building Manufacturers Hyderabad.pptx
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck Template
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 

A simple example of Earned Value Management (EVM) in action

  • 1. Simple example of EVM in action © 2014 Planisware
  • 2. The plan • Our team has been tasked with planting the trees on the plot of land behind our company’s new factory • The plan: – 30 batches of 20 trees (600 trees) – 5 batches per day (100 trees) – budgeted cost per tree 2.90$ (2.5$ per baby tree / 0.40$ for the slow release fertiliser) → total budget 1,740$ © 2014 Planisware 2
  • 3. After the first day… • 70 trees were planted (the team hit a patch with stones that had to be removed before the trees could be planted) • Total cost was 350 $ (we had to rent a special machine to help remove the stones which cost 147$ for the day) • Simple EVM calculation: – Earned Value = 70 trees planted  2.90$ = 203$ – Budgeted Cost = 100 trees planned per day  2.90$ = 290$ – Actual Cost = 70 trees planted  2.90$ + 147$ for the machine = 350$ © 2014 Planisware 3
  • 4. Visually… 0 50 100 150 200 250 300 350 400 Start 1st day Actual cost = 350$ Budgeted cost = 290$ Earned Value = 203$ © 2014 Planisware 4
  • 5. Regarding cost… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 5 We are here
  • 6. Regarding cost… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 6 We are here We should have been here
  • 7. Regarding cost… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 7 Cost variance = EV – AC = 203$ – 350$ = -147$ < 0
  • 8. Regarding cost… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 8 Cost variance = EV – AC We’re over budget, and have spent 203  350 = 58% more budget than anticipated (our cost performance index) = 203$ – 350$ = -147$ < 0
  • 9. Regarding schedule… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 9 We are here
  • 10. Regarding schedule… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 10 We are here Which is where we should have been then
  • 11. Regarding schedule… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 11 Schedule variance in hours
  • 12. Regarding schedule… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 12 Schedule variance in hours = 203$ – 290$ = = -87$ < 0 Schedule variance in dollars = EV – BC
  • 13. Regarding schedule… 0 50 100 150 200 250 300 350 400 Start 1st day EV AC BC © 2014 Planisware 13 Schedule variance in hours We’re late and have only performed 203/290 = 70% of the work planned (our schedule performance index) = 203$ – 290$ = = -87$ < 0 Schedule variance in dollars = EV – BC
  • 14. The consequences 0 500 1000 1500 2000 2500 3000 Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th © 2014 Planisware 14 Earned Value today Estimate at Completion EAC = 3,000$ Budget at Completion BAC = 1,740$ Extending the Actual Cost into the future gives us the end result if we do not modify the performance of the project
  • 15. The consequences 0 500 1000 1500 2000 2500 3000 Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th © 2014 Planisware 15 Earned Value today Estimate at Completion EAC = 3,000$ Budget at Completion BAC = 1,740$ Cost Overrun
  • 16. The consequences 0 500 1000 1500 2000 2500 3000 Start 1st 2nd 3rd 4th 5th 6th 7th 8th 9th © 2014 Planisware 16 Earned Value today Planned end date = 6 days Estimate at completion = 8.57 days Project Slip Estimate at Completion EAC = 3,000$ Budget at Completion BAC = 1,740$ Cost Overrun
  • 17. The consequences → If we continue at this rate, we will need: 1,740$  58% = 3,000 $ (cost estimate at completion) and 6 days  70% = 8.57 days (schedule estimate at completion) to finish the work. → If we want to finish on budget, we need to work at (planned remaining budget)  (actual remaining budget) (1,740 – 290)  (1740 – 350) = 104.3% of the originally planned performance → If we want to finish on time, we need to work at (actual remaining work)  (planned remaining work) (600 – 70)  (600 – 100) = 106% of the originally planned performance © 2014 Planisware 17
  • 18. In technical terms… In real life, the elements we calculated have slightly different names: • The Actual Cost is usually referred to as the Actual Cost of Works Performed (ACWP) • The Planned Cost = Budgeted Cost for Work Scheduled (BCWS) • The Earned Value = Budgeted Cost for Work Performed (BCWP) © 2014 Planisware 18
  • 19. Summary © 2014 Planisware 19 today time cost ACWP (Actual Cost of Work Performed) BCWS (Budgeted Cost of Work Scheduled) BCWP (Budgeted Cost of Work Performed) completion date Budget at Completion (BAC) Estimate at Completion (EAC) Schedule variance in $ SV = BCWS - BCWP Cost variance in $ CV = ACWP - BCWP Cost Overrun Project SlipSchedule variance in hours
  • 20. To learn more about EVM and tools to help manage it, visit our glossary: www.planisware.com/glossary/earned- value-management © 2014 Planisware 20