SECTION 106
  CONSIDERATIONS FOR
ELECTRIC INFRASTRUCTURE
       PROJECTS




                              TM
     Moving Power. Moving Forward
Overview
• Introduction to VELCO
• What are historic,
  architectural, archaeological
  and cultural resources?
• Preparing for Assessments
• Defining Area of Potential
  Effects (APE)
• Identify and Evaluate
• Data Collection
  Considerations
• Determining Effects
• Mitigation and Compliance
• Post Construction
  Considerations
VELCO
• Founded 1956 as nation’s first “transmission only” company
    • Assures competitive, equal access for energy providers and our
      owners

• Owned by Vermont’s electric distribution utilities

• Project work driven by federally enforceable reliability standards

• Recent electric reliability projects include numerous substations and
  high-voltage transmission lines

• VELCO’s transmission system includes:
    • Over 700 miles of transmission lines
    • 51 transmission facilities (substations, switching stations, etc)
    • 12,250 acres of managed ROW
    • 600 miles of fiber optic system
Cultural Resources
Preparing for an Archaeological
                Assessment
• Comprehensive Project Understanding
   –   Route alignment
   –   Access constraints
   –   Anticipated impacts
   –   Schedule and budget
• Have a clear understanding of the regulatory requirements
   – Understand the rules and regulations
   – Know the regulatory staff and SHPOs
   – Have a clear understanding of expectations and requirements
• Evaluate archaeological consulting firms
   –   Ensure availability of field crews
   –   Relevant project experience
   –   Review and understand overall approach
   –   Develop a team
Section 106 Process

•   An "undertaking" means a
    project, activity, or program
    funded in whole or in part under
    the direct or indirect jurisdiction of
    a federal agency. "Federal"
    means under the jurisdiction of a
    federal agency


•   Make sure you know if your
    project requires a Federal
    undertaking and what Federal
    agency is the “Lead Agency”
Defining the
         Area of Potential Effects (APE)
•   Geographic area or areas
    within which an undertaking
    may directly or indirectly cause
    alterations to the character of
    historic sites and/or properties,
    if any such areas exist.

•   Seek input from project team in
    the development of the APE to
    ensure that it is accurate and
    will meet all project needs.
     – Include all project areas

•   Changes to the APE during
    permitting and/or construction
    can be costly and cause
    delays.
Identify and Evaluate
• “Scoping” or “accessing
  information needs.”
• Seek information from
  knowledgeable individuals,
  organizations and tribes.
• Make a “reasonable and
  good faith effort” to identify
  historic properties.
• Determine whether historic
  properties are eligible for
  the National Register.
Evaluate risk of encountering
archaeological resources when making
           siting decisions
Data Collection Considerations
•   Use all project data to support archaeological SOW
    development/assessment
     – Environmental data
     – Accurate topographic information
     – Information from company files

•   Data collection must be phased so that it can “build” upon itself
     – Topographic surveys will support wetland and stream assessments
     – Wetland, stream and topographic information is then provided to
        archaeologists to support the sensitivity assessments
     – Resource assessment scheduling and data management is critical

• Why is this important?
– Develop a comprehensive and accurate SOW
– Ultimately reduces costs and time associated with archaeological
  assessments
Cultural Resource Field Surveys
•   Level of effort
     – Time & Costs
     – Use company staff to support (e.g.
         reviews of access, etc.)
•   Field Work Considerations
     – Scheduling and field conditions
     – Access Constraints
     – Capabilities of work crews
•   Data collection
     – Develop standards
     – Accurate data is extremely
         important
•   Reporting & Management
•   Reviews of reports and other
    deliverables
•   Early and frequent coordination with
    regulatory agencies
Determining Effect
• Consult with Lead
  Federal Agency
   – Comments from SHPO,
     tribes, regulators, and
     interested parties
• Make finding – no historic
  properties affected or no
  adverse effect
• Federal Agency (as
  appropriate) makes the
  final judgment
• Document results
• Involve the public and
  make findings available
Site Avoidance
Impact Mitigation
• Seek agreements on how
  adverse effects will be
  resolved
• Memorandum of
  Agreement executed upon
  signature of consulting
  parties
• Negotiating Reasonable
  Permit Conditions
• Consider on-going work
  practices associated with
  maintenance crews
• Control and track
  commitments
Construction and Compliance
• Managing Identified
  Cultural Resources
• Project Trainings
• Implement Impact
  Mitigation Measures
   – Matting, suitable ground
     conditions, etc.
• Vehicular Barriers
• Monitoring/Oversight
• Reporting and Agency
  Inspections
• Establish company
  procedures
Compliance Plans
Final Thoughts and Questions
• Consult early and
  often
• Be engaged
• Clearly define the APE
• Quality data is a
  necessity
• Avoidance is preferred
  – Be creative
• Consider maintenance
  constraints

Contenu connexe

Similaire à Section 106 Considerations for Electric Infrastructure Projects

Mine planning feasibility report
Mine planning feasibility reportMine planning feasibility report
Mine planning feasibility reportJignesh Ruperi
 
The Basics of Urban Planning - Lecture 6.pptx
The Basics of Urban Planning - Lecture 6.pptxThe Basics of Urban Planning - Lecture 6.pptx
The Basics of Urban Planning - Lecture 6.pptxIftikhar Ahmad Mukhtar
 
RUPH121 Environmental Design-1.pptx
RUPH121 Environmental Design-1.pptxRUPH121 Environmental Design-1.pptx
RUPH121 Environmental Design-1.pptxAbelTomondo
 
The Value of Infrastructure Asset Management
The Value of Infrastructure Asset ManagementThe Value of Infrastructure Asset Management
The Value of Infrastructure Asset ManagementC.S. Davidson
 
Presentation to Charles County, MD Commisioners on Environmental Consideratio...
Presentation to Charles County, MD Commisioners on Environmental Consideratio...Presentation to Charles County, MD Commisioners on Environmental Consideratio...
Presentation to Charles County, MD Commisioners on Environmental Consideratio...Andrew T. Der & Associates, LLC
 
Pete day resume 8 2010
Pete day resume 8 2010Pete day resume 8 2010
Pete day resume 8 2010Pete Day
 
How Strategic Alliances and Alternative Delivery Models Drive Project Success...
How Strategic Alliances and Alternative Delivery Models Drive Project Success...How Strategic Alliances and Alternative Delivery Models Drive Project Success...
How Strategic Alliances and Alternative Delivery Models Drive Project Success...Aconex
 
Urban Planning Site Analysis and Selection
Urban Planning Site Analysis and SelectionUrban Planning Site Analysis and Selection
Urban Planning Site Analysis and SelectionJahh Lavz
 
Christian B Wunsch - Resume V2.1 Linked In
Christian B Wunsch - Resume V2.1 Linked InChristian B Wunsch - Resume V2.1 Linked In
Christian B Wunsch - Resume V2.1 Linked InChristian Wunsch
 
CSA S250 STANDARD MAPPING OF UNDERGROUND UTILITY INFRASTRUCTURE
CSA S250 STANDARDMAPPING OF UNDERGROUND UTILITY INFRASTRUCTURECSA S250 STANDARDMAPPING OF UNDERGROUND UTILITY INFRASTRUCTURE
CSA S250 STANDARD MAPPING OF UNDERGROUND UTILITY INFRASTRUCTUREBob Gaspirc
 
Facilities Assessment Panel Presentation
Facilities Assessment Panel PresentationFacilities Assessment Panel Presentation
Facilities Assessment Panel PresentationMeg Thompson
 
Boomtowns: Planning for Resource Regions in Northern Canada
Boomtowns: Planning for Resource Regions in Northern CanadaBoomtowns: Planning for Resource Regions in Northern Canada
Boomtowns: Planning for Resource Regions in Northern Canadamikelcg
 
feasibilityreport-131027121529-phpapp01 (1).pdf
feasibilityreport-131027121529-phpapp01 (1).pdffeasibilityreport-131027121529-phpapp01 (1).pdf
feasibilityreport-131027121529-phpapp01 (1).pdfJainishBhagat2
 
Actors and factors of a project sofoline interchange
Actors and factors of a project sofoline interchangeActors and factors of a project sofoline interchange
Actors and factors of a project sofoline interchangeAdu Boaz Obeng
 
Akpobaro Lincoln CV 27-09-2015
Akpobaro Lincoln CV 27-09-2015Akpobaro Lincoln CV 27-09-2015
Akpobaro Lincoln CV 27-09-2015Akpobaro Lincoln
 

Similaire à Section 106 Considerations for Electric Infrastructure Projects (20)

Mine planning feasibility report
Mine planning feasibility reportMine planning feasibility report
Mine planning feasibility report
 
August 31 - 0216 - Clare Lindahl
August 31 - 0216 - Clare LindahlAugust 31 - 0216 - Clare Lindahl
August 31 - 0216 - Clare Lindahl
 
The Basics of Urban Planning - Lecture 6.pptx
The Basics of Urban Planning - Lecture 6.pptxThe Basics of Urban Planning - Lecture 6.pptx
The Basics of Urban Planning - Lecture 6.pptx
 
RUPH121 Environmental Design-1.pptx
RUPH121 Environmental Design-1.pptxRUPH121 Environmental Design-1.pptx
RUPH121 Environmental Design-1.pptx
 
The Value of Infrastructure Asset Management
The Value of Infrastructure Asset ManagementThe Value of Infrastructure Asset Management
The Value of Infrastructure Asset Management
 
Watershedplanwebinarv2
Watershedplanwebinarv2Watershedplanwebinarv2
Watershedplanwebinarv2
 
Presentation to Charles County, MD Commisioners on Environmental Consideratio...
Presentation to Charles County, MD Commisioners on Environmental Consideratio...Presentation to Charles County, MD Commisioners on Environmental Consideratio...
Presentation to Charles County, MD Commisioners on Environmental Consideratio...
 
Pete day resume 8 2010
Pete day resume 8 2010Pete day resume 8 2010
Pete day resume 8 2010
 
How Strategic Alliances and Alternative Delivery Models Drive Project Success...
How Strategic Alliances and Alternative Delivery Models Drive Project Success...How Strategic Alliances and Alternative Delivery Models Drive Project Success...
How Strategic Alliances and Alternative Delivery Models Drive Project Success...
 
Urban Planning Site Analysis and Selection
Urban Planning Site Analysis and SelectionUrban Planning Site Analysis and Selection
Urban Planning Site Analysis and Selection
 
Christian B Wunsch - Resume V2.1 Linked In
Christian B Wunsch - Resume V2.1 Linked InChristian B Wunsch - Resume V2.1 Linked In
Christian B Wunsch - Resume V2.1 Linked In
 
CSA S250 STANDARD MAPPING OF UNDERGROUND UTILITY INFRASTRUCTURE
CSA S250 STANDARDMAPPING OF UNDERGROUND UTILITY INFRASTRUCTURECSA S250 STANDARDMAPPING OF UNDERGROUND UTILITY INFRASTRUCTURE
CSA S250 STANDARD MAPPING OF UNDERGROUND UTILITY INFRASTRUCTURE
 
Facilities Assessment Panel Presentation
Facilities Assessment Panel PresentationFacilities Assessment Panel Presentation
Facilities Assessment Panel Presentation
 
Boomtowns: Planning for Resource Regions in Northern Canada
Boomtowns: Planning for Resource Regions in Northern CanadaBoomtowns: Planning for Resource Regions in Northern Canada
Boomtowns: Planning for Resource Regions in Northern Canada
 
feasibilityreport-131027121529-phpapp01 (1).pdf
feasibilityreport-131027121529-phpapp01 (1).pdffeasibilityreport-131027121529-phpapp01 (1).pdf
feasibilityreport-131027121529-phpapp01 (1).pdf
 
Planning for Watershed Restoration by Neil Stichert
Planning for Watershed Restoration by Neil StichertPlanning for Watershed Restoration by Neil Stichert
Planning for Watershed Restoration by Neil Stichert
 
Coastal Road Project
Coastal Road ProjectCoastal Road Project
Coastal Road Project
 
Actors and factors of a project sofoline interchange
Actors and factors of a project sofoline interchangeActors and factors of a project sofoline interchange
Actors and factors of a project sofoline interchange
 
Akpobaro Lincoln CV 27-09-2015
Akpobaro Lincoln CV 27-09-2015Akpobaro Lincoln CV 27-09-2015
Akpobaro Lincoln CV 27-09-2015
 
Work Term Report
Work Term ReportWork Term Report
Work Term Report
 

Plus de preservationcombination

Emerging Middle Class in Urban Pittsburgh
Emerging Middle Class in Urban PittsburghEmerging Middle Class in Urban Pittsburgh
Emerging Middle Class in Urban Pittsburghpreservationcombination
 
Integrating Historic Preservation into Disaster Planning and Recovery
Integrating Historic Preservation into Disaster Planning and RecoveryIntegrating Historic Preservation into Disaster Planning and Recovery
Integrating Historic Preservation into Disaster Planning and Recoverypreservationcombination
 
Starch Grain and Phytolith Evidence of Seed and Tuber Processing
Starch Grain and Phytolith Evidence of Seed and Tuber ProcessingStarch Grain and Phytolith Evidence of Seed and Tuber Processing
Starch Grain and Phytolith Evidence of Seed and Tuber Processingpreservationcombination
 
Identifying and Evaluating Historic Significance of Post-WWII Housing
Identifying and Evaluating Historic Significance of Post-WWII HousingIdentifying and Evaluating Historic Significance of Post-WWII Housing
Identifying and Evaluating Historic Significance of Post-WWII Housingpreservationcombination
 
Case Study Bridge Relocation Project: Van Wert-Wall Street Bridge
Case Study Bridge Relocation Project: Van Wert-Wall Street BridgeCase Study Bridge Relocation Project: Van Wert-Wall Street Bridge
Case Study Bridge Relocation Project: Van Wert-Wall Street Bridgepreservationcombination
 
Speaking of Historic Preservation... Concepts, Terms, and Options
Speaking of Historic Preservation... Concepts, Terms, and OptionsSpeaking of Historic Preservation... Concepts, Terms, and Options
Speaking of Historic Preservation... Concepts, Terms, and Optionspreservationcombination
 
Section 106 Review for Energy Projects: Issues and Recommendations
Section 106 Review for Energy Projects: Issues and RecommendationsSection 106 Review for Energy Projects: Issues and Recommendations
Section 106 Review for Energy Projects: Issues and Recommendationspreservationcombination
 
Historic Metal Truss Bridge Management Plan
Historic Metal Truss Bridge Management Plan Historic Metal Truss Bridge Management Plan
Historic Metal Truss Bridge Management Plan preservationcombination
 
A FHWA National Perspective on Risky Archaeological Practices
A FHWA National Perspective on Risky Archaeological PracticesA FHWA National Perspective on Risky Archaeological Practices
A FHWA National Perspective on Risky Archaeological Practicespreservationcombination
 
Integrating Historic Preservation into Disaster Planning and Recovery
Integrating Historic Preservation into Disaster Planning and RecoveryIntegrating Historic Preservation into Disaster Planning and Recovery
Integrating Historic Preservation into Disaster Planning and Recoverypreservationcombination
 
Moving Ahead for Progress in the 21st Century Act and Beyond
Moving Ahead for Progress in the 21st Century Act and BeyondMoving Ahead for Progress in the 21st Century Act and Beyond
Moving Ahead for Progress in the 21st Century Act and Beyondpreservationcombination
 
Funding for Preservation and Transportation
Funding for Preservation and Transportation Funding for Preservation and Transportation
Funding for Preservation and Transportation preservationcombination
 
Long Range Transportation Planning Partnership
Long Range Transportation Planning PartnershipLong Range Transportation Planning Partnership
Long Range Transportation Planning Partnershippreservationcombination
 

Plus de preservationcombination (20)

Emerging Middle Class in Urban Pittsburgh
Emerging Middle Class in Urban PittsburghEmerging Middle Class in Urban Pittsburgh
Emerging Middle Class in Urban Pittsburgh
 
Integrating Historic Preservation into Disaster Planning and Recovery
Integrating Historic Preservation into Disaster Planning and RecoveryIntegrating Historic Preservation into Disaster Planning and Recovery
Integrating Historic Preservation into Disaster Planning and Recovery
 
Life on the Riverfront: 1800 to 1900
Life on the Riverfront: 1800 to 1900Life on the Riverfront: 1800 to 1900
Life on the Riverfront: 1800 to 1900
 
Starch Grain and Phytolith Evidence of Seed and Tuber Processing
Starch Grain and Phytolith Evidence of Seed and Tuber ProcessingStarch Grain and Phytolith Evidence of Seed and Tuber Processing
Starch Grain and Phytolith Evidence of Seed and Tuber Processing
 
Identifying and Evaluating Historic Significance of Post-WWII Housing
Identifying and Evaluating Historic Significance of Post-WWII HousingIdentifying and Evaluating Historic Significance of Post-WWII Housing
Identifying and Evaluating Historic Significance of Post-WWII Housing
 
The Architecture of Consumerism
The Architecture of ConsumerismThe Architecture of Consumerism
The Architecture of Consumerism
 
Case Study Bridge Relocation Project: Van Wert-Wall Street Bridge
Case Study Bridge Relocation Project: Van Wert-Wall Street BridgeCase Study Bridge Relocation Project: Van Wert-Wall Street Bridge
Case Study Bridge Relocation Project: Van Wert-Wall Street Bridge
 
Speaking of Historic Preservation... Concepts, Terms, and Options
Speaking of Historic Preservation... Concepts, Terms, and OptionsSpeaking of Historic Preservation... Concepts, Terms, and Options
Speaking of Historic Preservation... Concepts, Terms, and Options
 
Section 106 Review for Energy Projects: Issues and Recommendations
Section 106 Review for Energy Projects: Issues and RecommendationsSection 106 Review for Energy Projects: Issues and Recommendations
Section 106 Review for Energy Projects: Issues and Recommendations
 
Engaging Non-Resident Tribes
Engaging Non-Resident TribesEngaging Non-Resident Tribes
Engaging Non-Resident Tribes
 
Intro to Best Practices
Intro to Best PracticesIntro to Best Practices
Intro to Best Practices
 
Historic Metal Truss Bridge Management Plan
Historic Metal Truss Bridge Management Plan Historic Metal Truss Bridge Management Plan
Historic Metal Truss Bridge Management Plan
 
A FHWA National Perspective on Risky Archaeological Practices
A FHWA National Perspective on Risky Archaeological PracticesA FHWA National Perspective on Risky Archaeological Practices
A FHWA National Perspective on Risky Archaeological Practices
 
Integrating Historic Preservation into Disaster Planning and Recovery
Integrating Historic Preservation into Disaster Planning and RecoveryIntegrating Historic Preservation into Disaster Planning and Recovery
Integrating Historic Preservation into Disaster Planning and Recovery
 
The Surface Transportation Board
The Surface Transportation BoardThe Surface Transportation Board
The Surface Transportation Board
 
Moving Ahead for Progress in the 21st Century Act and Beyond
Moving Ahead for Progress in the 21st Century Act and BeyondMoving Ahead for Progress in the 21st Century Act and Beyond
Moving Ahead for Progress in the 21st Century Act and Beyond
 
Funding for Preservation and Transportation
Funding for Preservation and Transportation Funding for Preservation and Transportation
Funding for Preservation and Transportation
 
Our New Transportation Legislation
Our New Transportation LegislationOur New Transportation Legislation
Our New Transportation Legislation
 
Lancaster Central Market
Lancaster Central MarketLancaster Central Market
Lancaster Central Market
 
Long Range Transportation Planning Partnership
Long Range Transportation Planning PartnershipLong Range Transportation Planning Partnership
Long Range Transportation Planning Partnership
 

Dernier

Google AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGGoogle AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGSujit Pal
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 

Dernier (20)

Google AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGGoogle AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAG
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 

Section 106 Considerations for Electric Infrastructure Projects

  • 1. SECTION 106 CONSIDERATIONS FOR ELECTRIC INFRASTRUCTURE PROJECTS TM Moving Power. Moving Forward
  • 2. Overview • Introduction to VELCO • What are historic, architectural, archaeological and cultural resources? • Preparing for Assessments • Defining Area of Potential Effects (APE) • Identify and Evaluate • Data Collection Considerations • Determining Effects • Mitigation and Compliance • Post Construction Considerations
  • 3. VELCO • Founded 1956 as nation’s first “transmission only” company • Assures competitive, equal access for energy providers and our owners • Owned by Vermont’s electric distribution utilities • Project work driven by federally enforceable reliability standards • Recent electric reliability projects include numerous substations and high-voltage transmission lines • VELCO’s transmission system includes: • Over 700 miles of transmission lines • 51 transmission facilities (substations, switching stations, etc) • 12,250 acres of managed ROW • 600 miles of fiber optic system
  • 4.
  • 6. Preparing for an Archaeological Assessment • Comprehensive Project Understanding – Route alignment – Access constraints – Anticipated impacts – Schedule and budget • Have a clear understanding of the regulatory requirements – Understand the rules and regulations – Know the regulatory staff and SHPOs – Have a clear understanding of expectations and requirements • Evaluate archaeological consulting firms – Ensure availability of field crews – Relevant project experience – Review and understand overall approach – Develop a team
  • 7. Section 106 Process • An "undertaking" means a project, activity, or program funded in whole or in part under the direct or indirect jurisdiction of a federal agency. "Federal" means under the jurisdiction of a federal agency • Make sure you know if your project requires a Federal undertaking and what Federal agency is the “Lead Agency”
  • 8. Defining the Area of Potential Effects (APE) • Geographic area or areas within which an undertaking may directly or indirectly cause alterations to the character of historic sites and/or properties, if any such areas exist. • Seek input from project team in the development of the APE to ensure that it is accurate and will meet all project needs. – Include all project areas • Changes to the APE during permitting and/or construction can be costly and cause delays.
  • 9. Identify and Evaluate • “Scoping” or “accessing information needs.” • Seek information from knowledgeable individuals, organizations and tribes. • Make a “reasonable and good faith effort” to identify historic properties. • Determine whether historic properties are eligible for the National Register.
  • 10. Evaluate risk of encountering archaeological resources when making siting decisions
  • 11. Data Collection Considerations • Use all project data to support archaeological SOW development/assessment – Environmental data – Accurate topographic information – Information from company files • Data collection must be phased so that it can “build” upon itself – Topographic surveys will support wetland and stream assessments – Wetland, stream and topographic information is then provided to archaeologists to support the sensitivity assessments – Resource assessment scheduling and data management is critical • Why is this important? – Develop a comprehensive and accurate SOW – Ultimately reduces costs and time associated with archaeological assessments
  • 12. Cultural Resource Field Surveys • Level of effort – Time & Costs – Use company staff to support (e.g. reviews of access, etc.) • Field Work Considerations – Scheduling and field conditions – Access Constraints – Capabilities of work crews • Data collection – Develop standards – Accurate data is extremely important • Reporting & Management • Reviews of reports and other deliverables • Early and frequent coordination with regulatory agencies
  • 13. Determining Effect • Consult with Lead Federal Agency – Comments from SHPO, tribes, regulators, and interested parties • Make finding – no historic properties affected or no adverse effect • Federal Agency (as appropriate) makes the final judgment • Document results • Involve the public and make findings available
  • 15. Impact Mitigation • Seek agreements on how adverse effects will be resolved • Memorandum of Agreement executed upon signature of consulting parties • Negotiating Reasonable Permit Conditions • Consider on-going work practices associated with maintenance crews • Control and track commitments
  • 16. Construction and Compliance • Managing Identified Cultural Resources • Project Trainings • Implement Impact Mitigation Measures – Matting, suitable ground conditions, etc. • Vehicular Barriers • Monitoring/Oversight • Reporting and Agency Inspections • Establish company procedures
  • 18.
  • 19. Final Thoughts and Questions • Consult early and often • Be engaged • Clearly define the APE • Quality data is a necessity • Avoidance is preferred – Be creative • Consider maintenance constraints

Notes de l'éditeur

  1. Federal undertakings usually take one of four forms: Actions directly carried out by, or on behalf of, a federal agency.   Actions carried out with federal financial assistance. Actions requiring a federal license, permit, or approval. Actions subject to state or local regulation administered pursuant to a delegation or approval by a federal agency. Federal undertakings usually take one of four forms: Actions directly carried out by, or on behalf of, a federal agency.   Actions carried out with federal financial assistance. Actions requiring a federal license, permit, or approval. Actions subject to state or local regulation administered pursuant to a delegation or approval by a federal agency. A state or local government project that is undertaken without federal funding, licensing, or permits is not subject to Section 106 review, even if it affects historic properties. It may, however, be subject to state or local preservation regulations.
  2. Archaeology: ROW; Laydown/Temporary Construction; Access Roads; Mitigation Plantings Architecture: Viewshed; 0.5-mile