Lucknow 💋 Escort Service in Lucknow (Adult Only) 8923113531 Escort Service 2...
P mpriniciples&practicefor managers
1. Office of Innovations and Solution
ACB-1
Project Management
Principles and Practice for Managers
Presented by: Pat A. Eigbe, PMP®
Office of Innovations and Solutions, ATO-P
February 17, 2004
2. February 17, Pat A. Eigbe, 2
Briefing Outline
Project Management (PM) as a Tool
Project Management Terminology
PM Relationship to other Disciplines
Project Management Processes
Project Management Tools & Techniques
Summary/Conclusion
Questions
3. February 17, Pat A. Eigbe, 3
Project Management as a Tool
Minimize Fire Drills
Efficient Use of Resources
Develop Better Metrics
On-time and On-budget Product Delivery
Apply Lessons Learned
Better Communications Between
Stakeholders
Make Proactive Decisions
4. February 17, Pat A. Eigbe, 4
Project Management (PM) Terms
Project - A temporary endeavor
undertaken to create a unique product or
service.
ATOP or VSCS - Project has a specific
purpose with a start and an end date.
Project Management - the Application of
Knowledge, Skills, Tools, and Techniques
to Project Activities to Meet Project
Requirements.
5. February 17, Pat A. Eigbe, 5
Project Management Terms II
Program - A group of related projects
managed in a coordinated way. Programs
usually include an element of ongoing
activity.
CPDLC, SMA, URET CCLD, pFAST,as FFP1
PM Tools Development as part of Program
Management
A Project/Program Manager (PM) - The
Individual Responsible for Managing a
Project/Program.
6. February 17, Pat A. Eigbe, 6
Project Management Terms III
Work Breakdown Structure (WBS) -
“A deliverable-oriented grouping of
project elements that organizes and
defines the total scope of the project.
Each descending level represents an
increasingly detailed definition of a
project work.
7. February 17, Pat A. Eigbe, 7
Project Management Terms IV
FAA standard wbs1-0.ppt
WBS Dictionary 3.1
Requirement to use FAA Standard
WBS – Mandatory
8. February 17, Pat A. Eigbe, 8
Project Management Terms V
Deliverable – Tangible, verifiable work product or service.
Work Package – A deliverable at the lowest level of the
work breakdown structure. A work package may be
divided into activities.
Activity - Work elements with expected duration, cost, &
resources that may be subdivided into tasks.
9. February 17, Pat A. Eigbe, 9
Project Management Terms – VI
Stakeholder – Individuals or Organizations
that will be Impacted by the Outcome of a
Project.
OBS: An Organizational Chart Relating
Work Packages to Organization Units.
Responsibility Matrix: Relates Organization
Structure to WBS & Ensures that each
Element of the Project’s Scope is Assigned
to a Responsible Individual(s).
10. February 17, Pat A. Eigbe, 10
Project Management:
Relationship to Others Disciplines
Project Management
Knowledge and
Practice
General Management
Knowledge and
Practice
Application Area
Knowledge and
Practice
The PMBOK™
Figure is conceptual and overlaps are NOT proportionalFigure is conceptual and overlaps are NOT proportional
11. February 17, Pat A. Eigbe, 11
Systems Engineering/PM
Relationship – I
PM Needs SE for
Integrated PM System Design
Requirements for HW and SW Tools
SE Needs PM for
Planning and tracking
Managing Resources
PM System Designer Must Understand both
SE Not Necessary for PM Practitioners
12. February 17, Pat A. Eigbe, 12
Systems Engineering/PM
Relationship - II
Risk Management
PM - Schedule, Cost & Technical/Quality
SE – Compatibility of Components of a System
or Sub-System
Quality Management
PM - Process for Producing the Product
SE - Ensure Product Meets the Quality
Specifications
13. February 17, Pat A. Eigbe, 13
Systems Engineering/PM
Relationship - III
Configuration Management
PM - Ensure Integrity of Schedule and System for
Schedule Management
SE - Ensure Integrity of the System as Designed
Change Management
PM - Changes to Project Scope
SE - Changes to System Requirement
Measurement
PM – Program cost & schedule performance
SE – Technical Performance
14. February 17, Pat A. Eigbe, 14
PMI Certification
What is PMP®
What PMP®
is not
PMP®
Value to Holder & Employer
PMP®
Certification Process link – visit
http://pm.act.faa.gov
15. February 17, Pat A. Eigbe, 15
PM Process Groups
Initiating
Processes Planning
Processes
Control
Processes
Executing
Processes
Closing
Processes
Project Information Flow
16. February 17, Pat A. Eigbe, 16
Start
Create Project Agreement/PD/SLA
1.5.1.5
PD/SLA OK?
Identify Project & Sponsor
1.5.1.1
Review/ Revise Plan (PMIP)
1.5.2
Execute Plan & Create Deliverables
1.5.3
Need Changes/
Corrective Action?
Deliver Final Deliverables/
1.5.4.5
Deliverables
Accepted?
Perform Post Project Evaluation & Prepare Close-Out report
1.5.5
Report
OK?
Project
Completed!!!
Plan OK?
No
Yes
Yes
No
Yes
No
No
Yes
No Yes
Create the Project Plan (PMIP)
1.5.2
Create Project Team & Team Contract
1.5.1.6
Monitor/Review Progress & Deliver Products
1.5.4
InitiationPlanningExecutionControlClosing
PM Process Flow
17. February 17, Pat A. Eigbe, 17
Initiation Processes
Identify project and sponsor
Appoint Project Manager
Train team on
Project Management Process
Project Plan (PMIP)
Develop Program Directive to Include
WBS that Covers the Scope
High-level Milestones
Budget resources
18. February 17, Pat A. Eigbe, 18
Planning Processes I
Identify Life Cycle approach
Evolutionary (AMS 6101, Section 2.2)
Incremental
Waterfall
Risk Management plan
19. February 17, Pat A. Eigbe, 19
Planning Processes II
Get approval for Program Directive
Identify quality standards - use specs,
IEEE, ISO, PMBOK®
Organizational structure
Communications - who needs, what
Acquire human resources for projects
20. February 17, Pat A. Eigbe, 20
Planning Processes III (Schedule
Development)
Update & Decompose WBS
Identify activities
Sequence
Estimate duration
Estimate cost
Allocate resources to work packages
Baseline schedule
21. February 17, Pat A. Eigbe, 21
Planning Processes IV
Risk management detail:
Identification
Analysis
Response
Procurement
22. February 17, Pat A. Eigbe, 22
Implementation/Execution
Processes
Use the PMIP to execute project activities
Assess Technical Performance to assure
product acceptance
Distribute project information
Make purchases
Develop team skills/competencies
Develop a Change Management plan
23. February 17, Pat A. Eigbe, 23
Performance Measurement Tools
Variances
Performance Indices
Schedule performance Index (SPI)
Cost performance Index (CPI)
Earned Value Management System
(EVMS)
24. February 17, Pat A. Eigbe, 24
Earned Value Management System
Highlights
What is EVMS
Planning for EVMS
Tracking & Analysis
Elements of EV Analysis
Project Cost & Schedule Forecasting
EV Reporting
25. February 17, Pat A. Eigbe, 25
Earned Value Management
System (EVMS) - I
EV - Tool for Measuring Project
Performance
Integrates Cost, Scope & Schedule
measurements
Compares work actually accomplished to
work planned
EV is an Early Warning System
Helps management make proactive
decisions to keep projects on course
26. February 17, Pat A. Eigbe, 26
Earned Value Management
System (EVMS) - II
Involves Calculating 3 key Elements
Budget - BCWS
Actual Cost - ACWP
Earned Value/Physical Progress - BCWP
Basis for variance analysis
27. February 17, Pat A. Eigbe, 27
Planning for EVMS - I
Create a work breakdown structure
Organize work into discrete work packages
and activities
Allocate a budget to each of the activities
Develop a schedule and Assign resources
Must include all project work in the
schedule
Establish the Project Baseline
28. February 17, Pat A. Eigbe, 28
Planning for EVMS - II
Award performance credit for physical %
complete:
0-100
Short duration tasks < 160 hours
EV is Zero until activity is complete
50-100
Duration less than 600 hours
50% at start of activity & 50% at completion
29. February 17, Pat A. Eigbe, 29
Planning for EVMS - III
Interim milestone;
Duration less than 600 hours
Based on completed milestone for task
Level of Effort (LOE)
Long duration & consistent tasks
Difficult to measure - no tangible deliverables
Measured by duration of time used e.g. 10
weeks support is 50% complete at 5 weeks
30. February 17, Pat A. Eigbe, 30
Tracking & Analysis
Each update cycle/Reporting Period:
Obtain physical % complete for each task
Calculate EV for each task
Sum up EV for all tasks as project EV
Calculate actual expenditure for actual work
completed during the period
Compare the Cumulative EV to Actual
expenditure
31. February 17, Pat A. Eigbe, 31
Elements of EV Analysis - I
Performance indices relate value of work
performed to dollar spent. e.g. CPI = 0.65
means that for every dollar spent, actual
value of the work performed is $0.65.
Cumulative CPI used to forecast project
cost at completion
Cumulative SPI used to forecast project
completion date
32. February 17, Pat A. Eigbe, 32
Elements of EV Analysis - II
Cost Variance - Difference between
budgeted cost of an activity & actual cost of
that activity
CV = EV - ACWP
Schedule Variance - Difference between
scheduled completion & actual completion
of an activity
SV = EV - BCWS
33. February 17, Pat A. Eigbe, 33
Elements of EV Analysis - III
SPI – EV/Planned Value
SPI => 1.0, Project Schedule performing as
planned or better
SPI < 1.0, Project not performing as
planned - needs help
34. February 17, Pat A. Eigbe, 34
Elements of EV Analysis - IV
CPI – EV/Actual Cost
CPI => 1.0, Project Cost performing as
planned or better
CPI < 1.0, Project Cost not performing as
planned - needs help
% Over/Under Budget = CAC - BCWS
35. February 17, Pat A. Eigbe, 35
Project Cost & Schedule Forecast
Methods
Estimate at Completion (EAC) is total cost
to complete an activity, work package, or a
project expressed as:
EAC = Actuals-to-date + Estimate to complete
(ETC)
Cost EAC = BAC/CPI
36. February 17, Pat A. Eigbe, 36
EV Reporting
Interpret the output of EV calculations
Take corrective action as necessary
Recommend or take corrective action as
necessary
37. February 17, Pat A. Eigbe, 37
Control Processes I
Coordinate and control changes to project
scope/requirements
schedule
budget
Monitor and manage product quality
Measure progress and report performance
38. February 17, Pat A. Eigbe, 38
Control Processes II
Monitor and control risks
keep track of identified risks
monitor residual risks
identify new risks
ensure execution of risk plans
assess effectiveness in reducing risk
39. February 17, Pat A. Eigbe, 39
Closing Processes
Close out contracts
Resolve any outstanding issues
Document lessons learned
Evaluate project
Archive all project documents
40. February 17, Pat A. Eigbe, 40
Conclusion
Defined Frequently used PM Terminologies
Discussed Objectives of Adopting Project
Management Principles.
Discussed PM Processes, Tools &
Techniques
Discussed EVMS Overview
Questions
41. February 17, Pat A. Eigbe, 41
References
Project Management Institute (PMI), 2000. A Guide to the
Project Management Body of Knowledge (the PMBOK®
Guide)
Stratton R. W., 1999. Improving SPI and CPI Calculations
on LOE Heavy Programs, Proceedings of the 30th Annual
PMI Seminars & Symposium
Fleming and Koppeman, 1996. Earned Value Project
Management.
Ibbs W & Reginato J., 2002. Quantifying the Value of
Project Management
Kerzner H, 2003. Project Management: A Systems
Approach to Planning, Scheduling, and Controlling.
FAST @ http://fast.faa.gov/wbs/wbssec.htm
42. February 17, Pat A. Eigbe, 42
Questions/Need Help?
http://pm.act.faa.gov
Pat A. Eigbe, PMP®
Ext. 5-7857
patrick.eigbe@faa.gov