Primavera project planner
- 1. Activity
ID
Activity
Description
Orig
Dur
Rem
Dur
Early
Start
Early
Finish
Predecessors Resource Budgeted
Cost
101 Site Cleaning 1 1 17DEC12 17DEC12 LABOUR 800.00
111 Excavation 2 2 18DEC12 19DEC12 101* EXCAVATR 2,000.00
121 PCC 2 2 20DEC12 21DEC12 111* CONCRETE 17,700.00
131 Foundation 4 4 24DEC12 27DEC12 121* RCC 20,000.00
141 Plinth Column 4 4 28DEC12 02JAN13 131* RCC 10,000.00
151 Plinth Beam 5 5 03JAN13 09JAN13 141* RCC 28,000.00
161 Filling 1 1 10JAN13 10JAN13 151* SAND 36,000.00
171 GL Column 5 5 11JAN13 17JAN13 161* RCC 20,700.00
181 GL Beam and GL Slab 5 5 18JAN13 24JAN13 171* RCC 82,000.00
191 FL Column 6 6 25JAN13 01FEB13 181* RCC 20,700.00
211 GL Brickwork 4 4 25JAN13 30JAN13 181* BRICK 98,502.00
201 FL Beam and FL Slab 6 6 04FEB13 11FEB13 191* RCC 83,000.00
261 Window Steel Mesh 10 10 04FEB13 15FEB13 191* STEEL 40,000.00
221 FL Brickwork 4 4 12FEB13 15FEB13 201* BRICK 102,000.00
251 Electricity Fitting 5 5 12FEB13 18FEB13 201* WIRE 68,000.00
351 Plumbing 4 4 18FEB13 21FEB13 221* PIPE 68,220.00
331 Compond Wall 5 5 18FEB13 22FEB13 221* BRICK 3,500.00
281 External Plastering 9 9 22FEB13 06MAR13 351* CEMENT 25,800.00
291 Tiles & Dadoo 14 14 25FEB13 14MAR13 331* TILES 56,020.00
271 FL Internal Plastering 6 6 22FEB13 01MAR13 351* CEMENT 12,000.00
341 GL Internal Plastering 5 5 14FEB13 20FEB13 351* CEMENT 10,000.00
301 Kitchen Otta 3 3 25FEB13 27FEB13 331* MARBLE 25,800.00
311 Doors and Window 6 6 07MAR13 14MAR13 281* WOOD 85,000.00
321 Colouring 7 7 11MAR13 19MAR13 311* PAINT 89,500.00
2012 2013
DEC JAN FEB MAR APR MAY
17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13
Site Cleaning
Excavation
PCC
Foundation
Plinth Column
Plinth Beam
Filling
GL Column
GL Beam and GL Slab
FL Column
GL Brickwork
FL Beam and FL Slab
Window Steel Mesh
FL Brickwork
Electricity Fitting
Plumbing
Compond Wall
External Plastering
Tiles & Dadoo
FL Internal Plastering
GL Internal Plastering
Kitchen Otta
Doors and Window
Colouring
© Primavera Systems, Inc.
Start Date 17DEC12
Finish Date 27MAR13
Data Date 17DEC12
Run Date 30APR13 15:46
Early Bar
Float Bar
Progress Bar
Critical Activity
ABCD
Project complete
rahu Kish Nikh Sank Ashu
Classic Schedule Layout
Sheet 1 of 1
Date Revision Checked Approved