SlideShare une entreprise Scribd logo
1  sur  1
Télécharger pour lire hors ligne
Activity
ID
Activity
Description
Orig
Dur
Rem
Dur
Early
Start
Early
Finish
Predecessors Resource Budgeted
Cost
101 Site Cleaning 1 1 17DEC12 17DEC12 LABOUR 800.00
111 Excavation 2 2 18DEC12 19DEC12 101* EXCAVATR 2,000.00
121 PCC 2 2 20DEC12 21DEC12 111* CONCRETE 17,700.00
131 Foundation 4 4 24DEC12 27DEC12 121* RCC 20,000.00
141 Plinth Column 4 4 28DEC12 02JAN13 131* RCC 10,000.00
151 Plinth Beam 5 5 03JAN13 09JAN13 141* RCC 28,000.00
161 Filling 1 1 10JAN13 10JAN13 151* SAND 36,000.00
171 GL Column 5 5 11JAN13 17JAN13 161* RCC 20,700.00
181 GL Beam and GL Slab 5 5 18JAN13 24JAN13 171* RCC 82,000.00
191 FL Column 6 6 25JAN13 01FEB13 181* RCC 20,700.00
211 GL Brickwork 4 4 25JAN13 30JAN13 181* BRICK 98,502.00
201 FL Beam and FL Slab 6 6 04FEB13 11FEB13 191* RCC 83,000.00
261 Window Steel Mesh 10 10 04FEB13 15FEB13 191* STEEL 40,000.00
221 FL Brickwork 4 4 12FEB13 15FEB13 201* BRICK 102,000.00
251 Electricity Fitting 5 5 12FEB13 18FEB13 201* WIRE 68,000.00
351 Plumbing 4 4 18FEB13 21FEB13 221* PIPE 68,220.00
331 Compond Wall 5 5 18FEB13 22FEB13 221* BRICK 3,500.00
281 External Plastering 9 9 22FEB13 06MAR13 351* CEMENT 25,800.00
291 Tiles & Dadoo 14 14 25FEB13 14MAR13 331* TILES 56,020.00
271 FL Internal Plastering 6 6 22FEB13 01MAR13 351* CEMENT 12,000.00
341 GL Internal Plastering 5 5 14FEB13 20FEB13 351* CEMENT 10,000.00
301 Kitchen Otta 3 3 25FEB13 27FEB13 331* MARBLE 25,800.00
311 Doors and Window 6 6 07MAR13 14MAR13 281* WOOD 85,000.00
321 Colouring 7 7 11MAR13 19MAR13 311* PAINT 89,500.00
2012 2013
DEC JAN FEB MAR APR MAY
17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13
Site Cleaning
Excavation
PCC
Foundation
Plinth Column
Plinth Beam
Filling
GL Column
GL Beam and GL Slab
FL Column
GL Brickwork
FL Beam and FL Slab
Window Steel Mesh
FL Brickwork
Electricity Fitting
Plumbing
Compond Wall
External Plastering
Tiles & Dadoo
FL Internal Plastering
GL Internal Plastering
Kitchen Otta
Doors and Window
Colouring
© Primavera Systems, Inc.
Start Date 17DEC12
Finish Date 27MAR13
Data Date 17DEC12
Run Date 30APR13 15:46
Early Bar
Float Bar
Progress Bar
Critical Activity
ABCD
Project complete
rahu Kish Nikh Sank Ashu
Classic Schedule Layout
Sheet 1 of 1
Date Revision Checked Approved

Contenu connexe

En vedette

Metodologia six sigma
Metodologia  six sigmaMetodologia  six sigma
Metodologia six sigmatakabu
 
P6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsP6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsInSync Conference
 
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14p6academy
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricksp6academy
 

En vedette (6)

Metodologia six sigma
Metodologia  six sigmaMetodologia  six sigma
Metodologia six sigma
 
Brickwork wikipedia
Brickwork   wikipediaBrickwork   wikipedia
Brickwork wikipedia
 
P6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsP6 Version 7 Tricks and Traps
P6 Version 7 Tricks and Traps
 
S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6
 
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
 

Similaire à Primavera project planner

28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimationimaduddin91
 
Final year Revit project
Final year Revit projectFinal year Revit project
Final year Revit projectMark Thornton
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Allan Leyte
 
Royal Museum Alor Setar
Royal Museum Alor SetarRoyal Museum Alor Setar
Royal Museum Alor Setarshacjhow
 
Measured drawings
Measured drawingsMeasured drawings
Measured drawingsjiuaN59
 
Typical Project Format.pptx
Typical Project Format.pptxTypical Project Format.pptx
Typical Project Format.pptxLokeswarSaha1
 
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CAPITA
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CAPITASAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CAPITA
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CAPITASunit Dhingra
 
John Curry 26.05.2015 Final BIM Submission merged pdfs
John Curry 26.05.2015 Final BIM Submission merged pdfsJohn Curry 26.05.2015 Final BIM Submission merged pdfs
John Curry 26.05.2015 Final BIM Submission merged pdfsJohn Curry
 
KASSIN TRELLIS
KASSIN TRELLISKASSIN TRELLIS
KASSIN TRELLISSean Roper
 
Drawing set for building complex - Three building and swimming poll
Drawing set for building complex - Three building and swimming pollDrawing set for building complex - Three building and swimming poll
Drawing set for building complex - Three building and swimming pollAripSuhariyanto1
 
Project of construction management
Project of construction managementProject of construction management
Project of construction managementMuhammad Umar Hayat
 
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5192 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5192 11001 &...Bobcat 773 g series skid steer loader parts catalogue manual (sn 5192 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5192 11001 &...fjjkefkksem
 
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5176 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5176 11001 &...Bobcat 773 g series skid steer loader parts catalogue manual (sn 5176 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5176 11001 &...fjjsefkksemm
 
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5176 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5176 11001 &...Bobcat 773 g series skid steer loader parts catalogue manual (sn 5176 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5176 11001 &...fjjkekfksemmm
 
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5180 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5180 11001 &...Bobcat 773 g series skid steer loader parts catalogue manual (sn 5180 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5180 11001 &...fjjkskekfsxswamem
 
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5180 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5180 11001 &...Bobcat 773 g series skid steer loader parts catalogue manual (sn 5180 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5180 11001 &...fjjkskekfsmem
 
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5181 11004 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5181 11004 &...Bobcat 773 g series skid steer loader parts catalogue manual (sn 5181 11004 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5181 11004 &...jfjkskekfsmem
 

Similaire à Primavera project planner (20)

28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation
 
Final year Revit project
Final year Revit projectFinal year Revit project
Final year Revit project
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
 
Royal Museum Alor Setar
Royal Museum Alor SetarRoyal Museum Alor Setar
Royal Museum Alor Setar
 
Measured drawings
Measured drawingsMeasured drawings
Measured drawings
 
GP Report
GP ReportGP Report
GP Report
 
Typical Project Format.pptx
Typical Project Format.pptxTypical Project Format.pptx
Typical Project Format.pptx
 
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CAPITA
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CAPITASAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CAPITA
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - CAPITA
 
John Curry 26.05.2015 Final BIM Submission merged pdfs
John Curry 26.05.2015 Final BIM Submission merged pdfsJohn Curry 26.05.2015 Final BIM Submission merged pdfs
John Curry 26.05.2015 Final BIM Submission merged pdfs
 
KASSIN TRELLIS
KASSIN TRELLISKASSIN TRELLIS
KASSIN TRELLIS
 
Drawing set for building complex - Three building and swimming poll
Drawing set for building complex - Three building and swimming pollDrawing set for building complex - Three building and swimming poll
Drawing set for building complex - Three building and swimming poll
 
Construction Management Project
Construction Management ProjectConstruction Management Project
Construction Management Project
 
Project of construction management
Project of construction managementProject of construction management
Project of construction management
 
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5192 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5192 11001 &...Bobcat 773 g series skid steer loader parts catalogue manual (sn 5192 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5192 11001 &...
 
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5176 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5176 11001 &...Bobcat 773 g series skid steer loader parts catalogue manual (sn 5176 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5176 11001 &...
 
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5176 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5176 11001 &...Bobcat 773 g series skid steer loader parts catalogue manual (sn 5176 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5176 11001 &...
 
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5180 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5180 11001 &...Bobcat 773 g series skid steer loader parts catalogue manual (sn 5180 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5180 11001 &...
 
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5180 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5180 11001 &...Bobcat 773 g series skid steer loader parts catalogue manual (sn 5180 11001 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5180 11001 &...
 
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5181 11004 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5181 11004 &...Bobcat 773 g series skid steer loader parts catalogue manual (sn 5181 11004 &...
Bobcat 773 g series skid steer loader parts catalogue manual (sn 5181 11004 &...
 
Elsegundopor tbinder008
Elsegundopor tbinder008Elsegundopor tbinder008
Elsegundopor tbinder008
 

Plus de Rahul

ACEP Magazine 3.pdf
ACEP Magazine 3.pdfACEP Magazine 3.pdf
ACEP Magazine 3.pdfRahul
 
ACEP Magazine 2.pdf
ACEP Magazine 2.pdfACEP Magazine 2.pdf
ACEP Magazine 2.pdfRahul
 
GECA Water Magazine Edition one.pdf
GECA Water Magazine Edition one.pdfGECA Water Magazine Edition one.pdf
GECA Water Magazine Edition one.pdfRahul
 
ACEP Magazine.pdf
ACEP Magazine.pdfACEP Magazine.pdf
ACEP Magazine.pdfRahul
 
Scope of geology in engineering
Scope of geology in engineeringScope of geology in engineering
Scope of geology in engineeringRahul
 
Engineering project writing
Engineering project writingEngineering project writing
Engineering project writingRahul
 
Wce agronomic water conservation measures
Wce agronomic water conservation measuresWce agronomic water conservation measures
Wce agronomic water conservation measuresRahul
 
WCE -- watershed management
WCE -- watershed managementWCE -- watershed management
WCE -- watershed managementRahul
 
Unit i gel space ratio rpa
Unit i gel space ratio rpaUnit i gel space ratio rpa
Unit i gel space ratio rpaRahul
 
Unit vi ferro cement rpa
Unit vi ferro cement rpaUnit vi ferro cement rpa
Unit vi ferro cement rpaRahul
 
Acem water cement ratio MCQ
Acem water cement ratio MCQAcem water cement ratio MCQ
Acem water cement ratio MCQRahul
 
Formwork
FormworkFormwork
FormworkRahul
 
April bulletin
April bulletinApril bulletin
April bulletinRahul
 
Construction equpiment
Construction equpimentConstruction equpiment
Construction equpimentRahul
 
Egrm
EgrmEgrm
EgrmRahul
 
Retaining walls
Retaining wallsRetaining walls
Retaining wallsRahul
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteRahul
 
Multistorey building
Multistorey buildingMultistorey building
Multistorey buildingRahul
 
Indiandrinking
IndiandrinkingIndiandrinking
IndiandrinkingRahul
 
Circular slabs
Circular slabsCircular slabs
Circular slabsRahul
 

Plus de Rahul (20)

ACEP Magazine 3.pdf
ACEP Magazine 3.pdfACEP Magazine 3.pdf
ACEP Magazine 3.pdf
 
ACEP Magazine 2.pdf
ACEP Magazine 2.pdfACEP Magazine 2.pdf
ACEP Magazine 2.pdf
 
GECA Water Magazine Edition one.pdf
GECA Water Magazine Edition one.pdfGECA Water Magazine Edition one.pdf
GECA Water Magazine Edition one.pdf
 
ACEP Magazine.pdf
ACEP Magazine.pdfACEP Magazine.pdf
ACEP Magazine.pdf
 
Scope of geology in engineering
Scope of geology in engineeringScope of geology in engineering
Scope of geology in engineering
 
Engineering project writing
Engineering project writingEngineering project writing
Engineering project writing
 
Wce agronomic water conservation measures
Wce agronomic water conservation measuresWce agronomic water conservation measures
Wce agronomic water conservation measures
 
WCE -- watershed management
WCE -- watershed managementWCE -- watershed management
WCE -- watershed management
 
Unit i gel space ratio rpa
Unit i gel space ratio rpaUnit i gel space ratio rpa
Unit i gel space ratio rpa
 
Unit vi ferro cement rpa
Unit vi ferro cement rpaUnit vi ferro cement rpa
Unit vi ferro cement rpa
 
Acem water cement ratio MCQ
Acem water cement ratio MCQAcem water cement ratio MCQ
Acem water cement ratio MCQ
 
Formwork
FormworkFormwork
Formwork
 
April bulletin
April bulletinApril bulletin
April bulletin
 
Construction equpiment
Construction equpimentConstruction equpiment
Construction equpiment
 
Egrm
EgrmEgrm
Egrm
 
Retaining walls
Retaining wallsRetaining walls
Retaining walls
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Multistorey building
Multistorey buildingMultistorey building
Multistorey building
 
Indiandrinking
IndiandrinkingIndiandrinking
Indiandrinking
 
Circular slabs
Circular slabsCircular slabs
Circular slabs
 

Primavera project planner

  • 1. Activity ID Activity Description Orig Dur Rem Dur Early Start Early Finish Predecessors Resource Budgeted Cost 101 Site Cleaning 1 1 17DEC12 17DEC12 LABOUR 800.00 111 Excavation 2 2 18DEC12 19DEC12 101* EXCAVATR 2,000.00 121 PCC 2 2 20DEC12 21DEC12 111* CONCRETE 17,700.00 131 Foundation 4 4 24DEC12 27DEC12 121* RCC 20,000.00 141 Plinth Column 4 4 28DEC12 02JAN13 131* RCC 10,000.00 151 Plinth Beam 5 5 03JAN13 09JAN13 141* RCC 28,000.00 161 Filling 1 1 10JAN13 10JAN13 151* SAND 36,000.00 171 GL Column 5 5 11JAN13 17JAN13 161* RCC 20,700.00 181 GL Beam and GL Slab 5 5 18JAN13 24JAN13 171* RCC 82,000.00 191 FL Column 6 6 25JAN13 01FEB13 181* RCC 20,700.00 211 GL Brickwork 4 4 25JAN13 30JAN13 181* BRICK 98,502.00 201 FL Beam and FL Slab 6 6 04FEB13 11FEB13 191* RCC 83,000.00 261 Window Steel Mesh 10 10 04FEB13 15FEB13 191* STEEL 40,000.00 221 FL Brickwork 4 4 12FEB13 15FEB13 201* BRICK 102,000.00 251 Electricity Fitting 5 5 12FEB13 18FEB13 201* WIRE 68,000.00 351 Plumbing 4 4 18FEB13 21FEB13 221* PIPE 68,220.00 331 Compond Wall 5 5 18FEB13 22FEB13 221* BRICK 3,500.00 281 External Plastering 9 9 22FEB13 06MAR13 351* CEMENT 25,800.00 291 Tiles & Dadoo 14 14 25FEB13 14MAR13 331* TILES 56,020.00 271 FL Internal Plastering 6 6 22FEB13 01MAR13 351* CEMENT 12,000.00 341 GL Internal Plastering 5 5 14FEB13 20FEB13 351* CEMENT 10,000.00 301 Kitchen Otta 3 3 25FEB13 27FEB13 331* MARBLE 25,800.00 311 Doors and Window 6 6 07MAR13 14MAR13 281* WOOD 85,000.00 321 Colouring 7 7 11MAR13 19MAR13 311* PAINT 89,500.00 2012 2013 DEC JAN FEB MAR APR MAY 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 Site Cleaning Excavation PCC Foundation Plinth Column Plinth Beam Filling GL Column GL Beam and GL Slab FL Column GL Brickwork FL Beam and FL Slab Window Steel Mesh FL Brickwork Electricity Fitting Plumbing Compond Wall External Plastering Tiles & Dadoo FL Internal Plastering GL Internal Plastering Kitchen Otta Doors and Window Colouring © Primavera Systems, Inc. Start Date 17DEC12 Finish Date 27MAR13 Data Date 17DEC12 Run Date 30APR13 15:46 Early Bar Float Bar Progress Bar Critical Activity ABCD Project complete rahu Kish Nikh Sank Ashu Classic Schedule Layout Sheet 1 of 1 Date Revision Checked Approved