SlideShare une entreprise Scribd logo
1  sur  36
G.RAMKUMAR,
ASSISTANT PROFESSOR,
DMSSVHCE,
MACHILIPATNAM
 Removal and replacement
 In-situ densification
 Precompression / Pre loading
 Vertical drains-1.Sand drains 2.Geo drains
 Stone columns
 Dewatering
 Stabilization using admixtures
 Reinforcement
 Geosynthetics
 Grouting
 One of oldest and simplest methods is
simply to remove and replace the soil
 Soils that will have to be replaced
include contaminated soils or organic
soils
 Method is usually practical only above
the groundwater table
 Most effective in sands
 Methods used in conventional earthwork
are only effective to about 2 m below the
surface
 In-situ methods like dynamic deep
compaction are for soils deeper than can
be compacted from the surface
 Probe includes the vibrator mechanism and
water jets
 Probe is lowered into the ground using a crane
 Vibratory eccentric force induces densification
and water jets assist in insertion and extraction
 Vibratory probe compaction is effective if silt
content is less than 12-15% and clay is less than
3%
 Probes inserted in grid pattern at a spacing of
1.5 to 3 m
 A compaction technique employed mostly for
cohesion-less soils.
 The essence of the equipment is the vibroflot
probe. It consists of a cylindrical tubular section
that houses eccentrically rotating weights that
induce horizontal vibratory motion.
 While vibrating and water jetting , the probe is
lowered down under its own weight to the
required penetration depth
 Suitable granular material is shoveled in to the
hole and compacted by vibrating the probe at
each incremental position for a certain time.
 Sutability number for filling material
Ground Type
Relative
Effectiveness
Sands Excellent
Silty Sands Marginal to Good
Silts Poor
Clays Not applicable
Mine Spoils Good (if granular)
Dumped Fill
Depends upon nature
of fill
Garbage Not Applicable
 Similar to vibro-float
 The extraction rate for the terra probe is
higher than that for the vibro-float
 Consists of dropping a heavy weight from
designated height repeatedly on the ground at
regular intervals to achieve densification of
loose cohesionless soils or fills.
 Uses a special crane to lift 80-360 KN to
heights of 7.5 to 30.5 m then drop these
weights onto the ground
 Cost effective method of densifying loose
sands and silty soils up to 15 to 30 feet
deep
 Used for the densification of granular soils
 Detonation of explosive charges such as
60% dynamite at a certain depth below
the ground surface in saturated soil
 The lateral spacing of the charges varies
from 3 to 10 m( 10-30 feet). Three to five
successful detonations are usually
necessary to achieve the desired
compaction
 Compaction up to a relative density of about
80% and up to a depth of about 20 m (60 ft)
over a large area can easily be achieved by
using this process
 The explosive charges are placed at a depth
of about 2/3 rds of the thickness of the soil
layer desired to be compacted
 Precompression / Pre loading
 Vertical drains-
1.Sand drains
2.Geo drains/Wick drains
 Stone columns
 Simply place a surcharge fill on top of the soil
that requires consolidation
 Once sufficient consolidation has taken place,
the fill can be removed and construction takes
place
 Surcharge fills are typically 10-25 feet thick and
generally produces settlement of 1 to 3 feet.
 Most effective in clay soil
 Requires only conventional earthmoving
equipment
 Any grading contractor can perform the
work
 Long track record of success
 Surcharge fill must extend horizontally at
least 10 m beyond the perimeter of the
planned construction, which may not be
possible at confined sites
 Transport of large quantities of soil
required
 Surcharge must remain in place for
months or years, thus delaying
construction
 Vertical drains are installed under a surcharge
load to accelerate the drainage of impervious
soils and thus speed up consolidation
 These drains provide a shorter path for the
water to flow through to get away from the soil
 Time to drain clay layers can be reduced from
years to a couple of months
 Geosynthetics used
as a substitute to
sand columns
 Installed by being
pushed or vibrated
into the ground
 Most are about 100
mm wide and 5 mm
thick
 Typically spaced 3
m centers
 Vibro-Replacement extends the range of
soils that can be improved by vibratory
techniques to include cohesive soils.
Reinforcement of the soil with compacted
granular columns or "stone columns" is
accomplished by the top-feed method.
Top-feed vibroflot rig
Adding stone in top-feed installation Bottom-feed vibroflot rig
GROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODS

Contenu connexe

Tendances

Irc method of design of flexible pavement 1
Irc method of design of flexible pavement 1Irc method of design of flexible pavement 1
Irc method of design of flexible pavement 1GARRE RAVI KUMAR
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentationPawan Kumar
 
Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavementspradip dangar
 
Vibration method for ground improvement technique
Vibration method for ground improvement techniqueVibration method for ground improvement technique
Vibration method for ground improvement techniqueABHISHEK THAKKAE
 
Ground Improvement Techniques
Ground Improvement TechniquesGround Improvement Techniques
Ground Improvement TechniquesNilesh Bhosale
 
Study of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsStudy of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsNatarajaSaiCharan1
 
Types of joints in rigid pavement
Types of joints in rigid pavementTypes of joints in rigid pavement
Types of joints in rigid pavementBhavya Jaiswal
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniquesjamali husain
 
Types of samplers used in soil sampling
Types of samplers used in soil samplingTypes of samplers used in soil sampling
Types of samplers used in soil samplingAna Debbarma
 
Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL) Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL) Imran Nawaz
 
Case study on effect of water table on bearing capacity
Case study on effect of water table on bearing capacityCase study on effect of water table on bearing capacity
Case study on effect of water table on bearing capacityAbhishek Mangukiya
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniquesRakesh Reddy
 
Pavement failures and maintenance
Pavement failures and maintenancePavement failures and maintenance
Pavement failures and maintenanceSatyapal Singh
 
ELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERINGELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERINGTejaswiniNarayane
 
Field compaction methods
Field compaction methodsField compaction methods
Field compaction methodsShivarajteggi
 
Ground Improvement Techniques
Ground Improvement TechniquesGround Improvement Techniques
Ground Improvement TechniquesLokeswar
 
Soil stabilisation (1)
Soil stabilisation (1)Soil stabilisation (1)
Soil stabilisation (1)Safiullah Khan
 

Tendances (20)

Well foundation
Well foundationWell foundation
Well foundation
 
Irc method of design of flexible pavement 1
Irc method of design of flexible pavement 1Irc method of design of flexible pavement 1
Irc method of design of flexible pavement 1
 
Pile load test
Pile load testPile load test
Pile load test
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentation
 
Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavements
 
Vibration method for ground improvement technique
Vibration method for ground improvement techniqueVibration method for ground improvement technique
Vibration method for ground improvement technique
 
Ground Improvement Techniques
Ground Improvement TechniquesGround Improvement Techniques
Ground Improvement Techniques
 
Study of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsStudy of Prefabricated Vertical Drains
Study of Prefabricated Vertical Drains
 
Types of joints in rigid pavement
Types of joints in rigid pavementTypes of joints in rigid pavement
Types of joints in rigid pavement
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
Types of samplers used in soil sampling
Types of samplers used in soil samplingTypes of samplers used in soil sampling
Types of samplers used in soil sampling
 
Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL) Determining equivalent single wheel load.(ESWL)
Determining equivalent single wheel load.(ESWL)
 
Case study on effect of water table on bearing capacity
Case study on effect of water table on bearing capacityCase study on effect of water table on bearing capacity
Case study on effect of water table on bearing capacity
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
 
Pavement failures and maintenance
Pavement failures and maintenancePavement failures and maintenance
Pavement failures and maintenance
 
ELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERINGELECTRO OSMOSIS METHOD OF DEWATERING
ELECTRO OSMOSIS METHOD OF DEWATERING
 
Types of pavements
Types of pavementsTypes of pavements
Types of pavements
 
Field compaction methods
Field compaction methodsField compaction methods
Field compaction methods
 
Ground Improvement Techniques
Ground Improvement TechniquesGround Improvement Techniques
Ground Improvement Techniques
 
Soil stabilisation (1)
Soil stabilisation (1)Soil stabilisation (1)
Soil stabilisation (1)
 

Similaire à GROUND IMPROVEMENT-DENSIFICATION METHODS

mordern soil_improvement.ppt
mordern soil_improvement.pptmordern soil_improvement.ppt
mordern soil_improvement.pptHabibFatimi
 
Soil improvement
Soil improvementSoil improvement
Soil improvementMithra G
 
Chapter 6.0 modern foundation tech. & ground improvement
Chapter 6.0   modern foundation tech. & ground improvement Chapter 6.0   modern foundation tech. & ground improvement
Chapter 6.0 modern foundation tech. & ground improvement DYPCET
 
Soil improvement Methods.pptx
Soil improvement Methods.pptxSoil improvement Methods.pptx
Soil improvement Methods.pptxFlittiAbdelhamid
 
Introduction and comparison of ground improvement techniques
Introduction and comparison of ground improvement techniquesIntroduction and comparison of ground improvement techniques
Introduction and comparison of ground improvement techniquesNouman Ijaz Chatha
 
Dewatering process and control in building projects
Dewatering process and control in building projectsDewatering process and control in building projects
Dewatering process and control in building projectsUmar Faruk
 
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITY
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITYBc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITY
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITYSukhvinder Singh
 
Roads in desert, swamp & black cotton
Roads in desert, swamp & black cottonRoads in desert, swamp & black cotton
Roads in desert, swamp & black cottonpradip dangar
 
Soil Bearing Capacity and Case study of Black Cotton Soil
Soil Bearing Capacity and Case study of Black Cotton SoilSoil Bearing Capacity and Case study of Black Cotton Soil
Soil Bearing Capacity and Case study of Black Cotton SoilPraveen S.K
 
Civil Engineering-Dewatering
Civil Engineering-DewateringCivil Engineering-Dewatering
Civil Engineering-DewateringMoe Abadla
 
Grouting various techniques of grouting.pptx
Grouting various techniques of grouting.pptxGrouting various techniques of grouting.pptx
Grouting various techniques of grouting.pptxUmarSaba1
 
Dynamic compaction
Dynamic compactionDynamic compaction
Dynamic compactionGaurav Verma
 
CTRS unit 2_Lect 1.pptx
CTRS unit 2_Lect 1.pptxCTRS unit 2_Lect 1.pptx
CTRS unit 2_Lect 1.pptxSwapnilGorade1
 
Compaction of soil (for civil engineering)
Compaction of soil (for civil engineering)Compaction of soil (for civil engineering)
Compaction of soil (for civil engineering)laxman singh
 

Similaire à GROUND IMPROVEMENT-DENSIFICATION METHODS (20)

mordern soil_improvement.ppt
mordern soil_improvement.pptmordern soil_improvement.ppt
mordern soil_improvement.ppt
 
Soil improvement
Soil improvementSoil improvement
Soil improvement
 
Chapter 6.0 modern foundation tech. & ground improvement
Chapter 6.0   modern foundation tech. & ground improvement Chapter 6.0   modern foundation tech. & ground improvement
Chapter 6.0 modern foundation tech. & ground improvement
 
Soil improvement Methods.pptx
Soil improvement Methods.pptxSoil improvement Methods.pptx
Soil improvement Methods.pptx
 
Introduction and comparison of ground improvement techniques
Introduction and comparison of ground improvement techniquesIntroduction and comparison of ground improvement techniques
Introduction and comparison of ground improvement techniques
 
Dewatering process and control in building projects
Dewatering process and control in building projectsDewatering process and control in building projects
Dewatering process and control in building projects
 
Grouting
GroutingGrouting
Grouting
 
1.9 GROUTING.ppt
1.9 GROUTING.ppt1.9 GROUTING.ppt
1.9 GROUTING.ppt
 
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITY
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITYBc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITY
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITY
 
Roads in desert, swamp & black cotton
Roads in desert, swamp & black cottonRoads in desert, swamp & black cotton
Roads in desert, swamp & black cotton
 
Soil Bearing Capacity and Case study of Black Cotton Soil
Soil Bearing Capacity and Case study of Black Cotton SoilSoil Bearing Capacity and Case study of Black Cotton Soil
Soil Bearing Capacity and Case study of Black Cotton Soil
 
Foundations.pptx
Foundations.pptxFoundations.pptx
Foundations.pptx
 
Civil Engineering-Dewatering
Civil Engineering-DewateringCivil Engineering-Dewatering
Civil Engineering-Dewatering
 
Grouting various techniques of grouting.pptx
Grouting various techniques of grouting.pptxGrouting various techniques of grouting.pptx
Grouting various techniques of grouting.pptx
 
Grouting
GroutingGrouting
Grouting
 
GUNITING
GUNITINGGUNITING
GUNITING
 
Compaction Of Soil
Compaction Of SoilCompaction Of Soil
Compaction Of Soil
 
Dynamic compaction
Dynamic compactionDynamic compaction
Dynamic compaction
 
CTRS unit 2_Lect 1.pptx
CTRS unit 2_Lect 1.pptxCTRS unit 2_Lect 1.pptx
CTRS unit 2_Lect 1.pptx
 
Compaction of soil (for civil engineering)
Compaction of soil (for civil engineering)Compaction of soil (for civil engineering)
Compaction of soil (for civil engineering)
 

Dernier

Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf203318pmpc
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...soginsider
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 

Dernier (20)

Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 

GROUND IMPROVEMENT-DENSIFICATION METHODS

  • 2.  Removal and replacement  In-situ densification  Precompression / Pre loading  Vertical drains-1.Sand drains 2.Geo drains  Stone columns  Dewatering  Stabilization using admixtures  Reinforcement  Geosynthetics  Grouting
  • 3.  One of oldest and simplest methods is simply to remove and replace the soil  Soils that will have to be replaced include contaminated soils or organic soils  Method is usually practical only above the groundwater table
  • 4.
  • 5.  Most effective in sands  Methods used in conventional earthwork are only effective to about 2 m below the surface  In-situ methods like dynamic deep compaction are for soils deeper than can be compacted from the surface
  • 6.
  • 7.
  • 8.  Probe includes the vibrator mechanism and water jets  Probe is lowered into the ground using a crane  Vibratory eccentric force induces densification and water jets assist in insertion and extraction  Vibratory probe compaction is effective if silt content is less than 12-15% and clay is less than 3%  Probes inserted in grid pattern at a spacing of 1.5 to 3 m
  • 9.  A compaction technique employed mostly for cohesion-less soils.  The essence of the equipment is the vibroflot probe. It consists of a cylindrical tubular section that houses eccentrically rotating weights that induce horizontal vibratory motion.  While vibrating and water jetting , the probe is lowered down under its own weight to the required penetration depth
  • 10.  Suitable granular material is shoveled in to the hole and compacted by vibrating the probe at each incremental position for a certain time.  Sutability number for filling material
  • 11. Ground Type Relative Effectiveness Sands Excellent Silty Sands Marginal to Good Silts Poor Clays Not applicable Mine Spoils Good (if granular) Dumped Fill Depends upon nature of fill Garbage Not Applicable
  • 12.  Similar to vibro-float  The extraction rate for the terra probe is higher than that for the vibro-float
  • 13.
  • 14.
  • 15.
  • 16.  Consists of dropping a heavy weight from designated height repeatedly on the ground at regular intervals to achieve densification of loose cohesionless soils or fills.  Uses a special crane to lift 80-360 KN to heights of 7.5 to 30.5 m then drop these weights onto the ground  Cost effective method of densifying loose sands and silty soils up to 15 to 30 feet deep
  • 17.
  • 18.
  • 19.  Used for the densification of granular soils  Detonation of explosive charges such as 60% dynamite at a certain depth below the ground surface in saturated soil  The lateral spacing of the charges varies from 3 to 10 m( 10-30 feet). Three to five successful detonations are usually necessary to achieve the desired compaction
  • 20.  Compaction up to a relative density of about 80% and up to a depth of about 20 m (60 ft) over a large area can easily be achieved by using this process  The explosive charges are placed at a depth of about 2/3 rds of the thickness of the soil layer desired to be compacted
  • 21.
  • 22.
  • 23.  Precompression / Pre loading  Vertical drains- 1.Sand drains 2.Geo drains/Wick drains  Stone columns
  • 24.  Simply place a surcharge fill on top of the soil that requires consolidation  Once sufficient consolidation has taken place, the fill can be removed and construction takes place  Surcharge fills are typically 10-25 feet thick and generally produces settlement of 1 to 3 feet.  Most effective in clay soil
  • 25.  Requires only conventional earthmoving equipment  Any grading contractor can perform the work  Long track record of success
  • 26.  Surcharge fill must extend horizontally at least 10 m beyond the perimeter of the planned construction, which may not be possible at confined sites  Transport of large quantities of soil required  Surcharge must remain in place for months or years, thus delaying construction
  • 27.  Vertical drains are installed under a surcharge load to accelerate the drainage of impervious soils and thus speed up consolidation  These drains provide a shorter path for the water to flow through to get away from the soil  Time to drain clay layers can be reduced from years to a couple of months
  • 28.
  • 29.
  • 30.  Geosynthetics used as a substitute to sand columns  Installed by being pushed or vibrated into the ground  Most are about 100 mm wide and 5 mm thick
  • 31.
  • 32.  Typically spaced 3 m centers
  • 33.  Vibro-Replacement extends the range of soils that can be improved by vibratory techniques to include cohesive soils. Reinforcement of the soil with compacted granular columns or "stone columns" is accomplished by the top-feed method.
  • 34. Top-feed vibroflot rig Adding stone in top-feed installation Bottom-feed vibroflot rig