2. Note For clarification..
3/20/2016
The 11 modules divided into 7 parts due to the
similarity of some disciplines in the activity:
Quality contain: M1+M5
Mechanical Pipeline: M2+M3
Mechanical Piping: M4+M9
Mechanical Static& Rotating Equipment: M7+M8
NDT: M6
Painting & insulation:M10
Commissioning: M11
3. Quality: its fitness or suitable for the intended purpose
It’s the part which deal to
control such a of
contract documents &
drawings The control of
document is with
reference to ISO
9001:2008. which is
mention in the project
contract and the
procedure
Are documents related
to material and how to
manage them, and its
validating and how it is
stored and where you
store.
3/20/2016
Drawing & document control Material Management
4. M1/Quality/ Drawing & Document control
3/20/2016
The control of documents with reference to
ISO 9001:2008 are:
Contract Quality Plan (CQP).
SP-1171: specification for quality assurance
for product and service.
SP-1122: Project quality assurance.
SP-1131: Specification for handover As-Built
document.
DEPs: Design and Engineering Practice.
5. M1/Quality/ Drawing & Document control
3/20/2016
Order of precedence of documents:(in Ascending order)
Code Of Practice (COP): its contain policy approval,
document of measurement, national stuff, financial stuff, etc.
Guidelines (GUs): the applicable guidelines, ex:
GU 611: PDO engineering standard and procedures, GU556:
guideline for vendor project document deliverable, GU 459:
guideline for storing & searching information, etc.
Policy (PL’s): the applicable policy, ex: PL1029: competency
assessment and assurance, PL 1233 contracting &
procurement procedure, PL 1866: quality audit procedure.
Specifications (SP’s)
6. M1/Quality/ Drawing & Document control
Controlled/Uncontroll
ed copy of document.
Codes
Standard
Drawings/Document
control register.
Control of obsolete
document.
Drawings: there are
3 types of drawings:
AFC Drawings
Red mark up drawing
As-Build drawing
Storage/Retrieval
document
Project Close Out
3/20/2016
7. M1/Quality/ Material Management
Company approved
vendor list.
Material Certificates.
TPI Release note
Special storage
condition of
consumables.
Safety Data Sheet
SHOC Card
Stock/Inventory
Control.
3/20/2016
8. M5/Quality
3/20/2016
Is contain 3 main topic:
Non-Conformance Report (NCR)
Field Change Control
Calibration of Measurement Tools.
9. M5/Quality/NCR
3/20/2016
NCR: Is violation of against written requirement.
There are two stage of NCR
Corrective action
RFI
Preservation action
RE Isometric Drawing
Photograph of material after modification
Fit up& welding report (Activity) after modification
Quality induction training report
RFI cleared after issue of NCR
10. M5/Quality/field change controls
Site Changes Request (SCR): it
raised In case of changes which
affects design were engineering,
requirements of material are
required.
Work Discussion Memorandum
(WDM):it can be raised due
change of scope, additional
materials requirement, technical
field issues for review record and
action propose.
Standard Variance
Calibration: is process to check
and conform that the instrument
used is able to give correct
readings.
Once the gauge is calibrated, the
details are intended into a work
register of lab, subsequently
calibration certificate is
prepared for record.
Calibrations are done as per
approved procedure by
competent technicians.
3/20/2016
field change controls Calibration of Equipment
11. M2/ Mechanical/ CS Pipeline construction &
Production Welding
Material Handling & control.
Pipe stacking.
Surveying & Right of Way pipeline.
Traceability.
For example:
Type of pipe: CS pipe
“Carbon Steel”
Grade: ISO 3183 L 450
Pipe Size : Diameter 8in”
“219.1*6.35” thickness
Length : 11.58 m
Pipe number :93145
Stringing.
Trenching.
Prepadding
3/20/2016
12. M2/ Mechanical/ CS Pipeline construction &
Production Welding
Holiday detection
Peel test
3/20/2016
Pipe Bending
Shrink Sleeve
13. M2/ Mechanical/ CS Pipeline construction &
Production Welding
Lowering of pipe
Post padding
Backfilling
3/20/2016
14. M2/ Mechanical/ CS Pipeline construction &
Production Welding
Welding: is carry out as approved
AFC WPS which is indicate the
material diameter of the pipe,
position, progression, current type,
electrode and filler wire type, bevel
and groove type, cleaning method
etc.
The process/ passes of welding in CS
pipeline are:
Root pass
Hot pass
Fill up pass
Capping pass
For example:
Type of pipe: CS pipe “Carbon
Steel”
Grade: ISO 3183 L 450
Pipe Size : Diameter 8in”
“219.1*6.35” thickness
Length : 11.58 m
Pipe number :93145
Process: SMAW “Shield Metal Arc
Welding”
Thickness Range: 4.8mm to 9.5mm
Position of welding : 5G
Type of electrode: E 6010, E 8010-P1
Type of current: DC-EN
Ampere Range: 110-126.5A
Volts Range: 27.6-31.8V
Travel speed: 6.11-7.02 mm/sec
Heat input :0.498-0.572 (KJ/mm)
3/20/2016
Welding
15. M2/ Mechanical/ CS Pipeline construction &
Production Welding
AFC WPS shall be used for Tie-in
Welds Welder qualification Accordance
with ASME Section IX & SP 1177.
Electrode storage:
E 7018-1 H5
E : Electrode
70: strength (70000 psi)
1: Position
1. Flat
2. Horizontal
3. Vertical
4. Overhead
8: Penetration (A/V)
1: Impact value (J)
H5: Hydrogen
Electrode can be verified by
patch no. and article no.
Electrodes which are not
hermetically sealed packing or
vacuum requires to be
maintaining from humidity.
Temperature need to be
monitored.
Electrode shall be preheated
before it used.
SDSS red color used for filler
wire.
DSS yellow color used for filler
wire.
3/20/2016
16. M2/ Mechanical/ CS Pipeline construction &
Production Welding
3/20/2016
Tie-In
welding
Tie-in welding (SMAW) done after lowering the Pipe
Section in the trench.
Tie-in welding should be done inside the trench with more
precaution of protection
Tie-in welding process interruption shall be avoided if any
interruption exists the welding process shall be stopped.
Tie-in welding for 8” CS pipeline the welding shall be
done in 4 passes Root pass, hot pass, fill pass, capping
pass.
Alignment shall be done to the pipeline before start the
Tie-in welding.
The alignment of the pipeline shall be supported by side
boom/ Crain.
Clamper removal it’s a tool that hold the end side of
pipelines in case of welding alignment purpose and to
give the required root gap as per AFC WPS.
17. M2/ Mechanical/ CS Pipeline construction &
Production Welding
3/20/2016
Tie-In
welding
Weld cleaning. Weld cleaning by, wire
brush, power brush, grinding wheel &
file.
The after complete weld shall be
inspected visually before it offered to
NDT inspection.
The Method used in NDT to inspect
the CS Pipeline to the complete weld
is MPT “Magnetic Particle Testing”.
Then it Evaluate for Acceptance
criteria.
18. M2/ Mechanical/ CS Pipeline construction &
Production Welding
3/20/2016
Hydrostatic
test
Hydrostatic test. To detect the Weld
integrity and pipeline yield strength
Hydrostatic test: Should be 1.5 times
of Operating Pressure.
Dewatering - this involves pushing
pigs through the pipeline propelled by
a gas to remove the water prior to
start-up.
Drying &preservation: Dew Point it’s
a measurement of moisture inside the
pipe or pipeline for the end of the
drying process
19. M3/ Mechanical/ GRE Pipeline construction off
plot
GRE: Glass Reinforced Epoxy
Control document is SP-1208: Pipeline
construction specification for CS and
GRE pipeline and procedure handling
and storage.
For SNCP Project GRE Pipes comes in
different pressure such as
PN112: indicate pressure of 112 bars.
PN50: indicate pressure of 50 Bars.
PN16: indicate pressure of 16 Bars.
Each type having different color, size,
diameter, and function.
Material receipt: It’s a document shows
the details of materials such as: MRR
Number, Order Number, Heat number,
Supplier, Size, and Statue Location.
Storage & handling: transportation,
handling and storage of pipes fitting and
adhesives.
3/20/2016
20. M3/ Mechanical/ GRE Pipeline construction off
plot
Storage of adhesive kits:
the adhesive kit should be
store cool and isolated
from the temperature as
per the standard.
Self life should be kept in
mind for all consumables.
The Self life of adhesive kit
is having 9 month
Pot life: it’s the expected
life of the mixture or things
to be used
3/20/2016
21. M3/ Mechanical/ GRE Pipeline
construction off plot
There are 3 types of
GRE Joints:
1. Threaded Joint
Hi pro plus
L.C Area
2.Lamination Joint
Epoxy kits
3. Flanged joint
3/20/2016
22. M3/ Mechanical/ GRE Pipeline
construction off plot
Field thread fabrication: pipe
preparation, tapering, cleaning, mold
preparation, epoxy thread paste
preparation, threading, curing, mold
removal and thread inspection.
Wadi crossing: there are four type
Wadi:
Flood plains
Wadi type A
Wadi type B
Wadi type C
Road crossing
3/20/2016
23. M4/ Mechanical/Piping construction &
Production Welding (on plot)
Handling & storage of DSS, SS
material:
Nylon slings shall be used for lifting
and handling of DSS & SS material.
Welding inspection :
Before (Prior)
During
After
Inspection of weld repairs & acceptance
checks
Pre-test line check & punch list:
checking all construction activities
completed including support and
attachment welding under the piping
and all NDT are completed and all
necessary report are available-list out
all record non compliance during line
check
CCMS: completion certificate
mechanical system. It has two type :
Design stage
Construction stage
Once system complete, it will clearance
another system. Like mechanical
construction check sheet completed.
Then pre-commissioning system start to
gives unique number to any system.
QC release of test-Package for hydro
test: This sheet which must be done
before hydro test its shows all complete
document (welding report, NDE report,
PWHT and NCR closeout).
3/20/2016
24. M4/ Mechanical/Piping construction &
Production Welding (on plot)
Hydro test preparation: [PIPING]
Approved hydro test procedure & ITP, mark
& identify test limits, check all ‘A’ punch
list items completed, line walk completed,
record ‘B’ punch items, witness line
flushing, check pressure gauges calibration,
testing manifold is approved, check vents
& drains points, check water certificate
chloride content not exceed 200ppm, check
chart pressure recorder, check relief valve
calibration, before starting of test – line test
pack is released for testing
Check test pack is prepared as per approved
formats, & as per approved index, all
relevant check sheets signed, record valves
details, check for line list, mark up PEFS,
check for punch list items recorded.
Weld history sheet is updated with all joints
covered along with suitable NDT &
acceptance.
Correct PEFS or P & ID and
isometric drawings.
Check visually damage. During
hydro test check for any leaks check
for pressure drops if any, check
chart recorder
[This is separate subject related to
mechanical motor alignment] -
write method statement details, ITP
details, DEP & SP details.
Provide Separate heading required
& date required
Test witnessing & acceptance :
check all gauge calibration done or
not and chart record , always check
PRV pressure relive value calibration
and check at latest 3 times.
3/20/2016
25. M4/ Mechanical/Piping construction &
Production Welding (on plot)
3/20/2016
Piping re-instatement: this the last step for piping that insulate all pipes, flange, gasket, alignment,
support and slop if required. As per the latest REV, correct stud bolts to be installed and torque to be
done as per SP 2020, and fittings also to be installed such as gauges, flange, vessel, pressure vessel,
etc.
Flange management: as per SP 2020
Flange must always visually inspect of the surface finish. & rating
Ensure the correct size bolts and nuts material is used. As per drawing.
Check the type, class, size and material specification of the gasket before using and ensure the gasket fits
correctly.
Always use a new insulation kit freshly removed from manufacturer package and follow the instruction.
Check torque values as per vendor recommendations
Follow required torque values procedure. Approved by company
Tie-in welding (shutdown): its when existing line is connected with new line (by needs of break up
flange fitting or pipe seems spools, certain spools can be hydrotest. this one type of new connection
making point on alive pipe which have isolation valve shutdown will be done the pipe will cut by cold
cutting machine from tow proposed marked area then they will make bevel surface preparation welding
will be done to installed breakup flange connection required NDT & inspection shall be done and they
fabricated & tested spool will be installed final inspection & box up will be done with required torque
values. And test pack shall be prepared for quality documentation.
Golden joint: when new break up connection is help of flange fitting where hydrotest cannot be done
only NDT is applicable.
26. M4/ Mechanical/Piping construction &
Production Welding (on plot)
3/20/2016
Hot Tap: Welding on pressurized pipes (live lines): If there is a pipe (live) which have
no valve they will fabric a pipe which have value and cut half of fabric pipe and weld
it in the pipe (live) and they make cold drilling. Guideline of hot tapping in general:
Confirm that the installation site meets the minimum upstream and downstream pipe
diameter requirements.
Weld a two inch mounting adapter on the pipe. Make sure the mounting adapter is
within ± 5° perpendicular to the pipe centerline (see previous page). The pipe
opening must be at least 1.875 inches in diameter.
Connect a two inch process connection on the mounting adapter.
Connect an isolation valve on the process connection. The valve's full open bore
must be at least 1.875 inches in diameter.
Hot tap the pipe.
Close the isolation valve. Run a static pressure check on the welds. If Pressure loss
or leaks are detected, repair the joint and re-test.
Connect the flow meter to the isolation valve.
Calculate the sensor probe insertion depth as described on the following pages.
Insert the sensor probe assembly into the pipe
27. M9/ Mechanical/ GRE U/G piping (on plot)
Storage of adhesive kits
Trench preparation
Special tools: tools that especially
used in different process of GRE
pipe such as:
M86, M86XL shaver.
C/W arbors.
Pipe shavers
Flapper sander
Hack saw
Saber saw
Abrasive wheel
Pipe cutting
Edge preparation
Trial assembly
Surface preparation
Adhesive band kit 3/20/2016
28. M9/ Mechanical/ GRE U/G piping (on plot)
Hydro test preparation: hydro test
package it’s to collect all the details which
is required for starting hydro test example:
Daily report
Method of statement
Heat number.
Gauge report: gauge calibration by third
party.
Test manifold
Hose pipe (Tested one)
Water test report
Hydro test procedure (Approved)
ITP/ QCP (Latest Revision)
Air compressor
Dead weight center: Recheck the gauge
calibration.
P& ID diagram
Test limit
Hydro test:
Dewatering
Drying
Reinstatement
CCMS
3/20/2016
29. M7/ Mechanical/mechanical static equipment:
stabilizer column, pressure vessel, re-boilers,
HTF heaters, Air fin cooler, AP/HP flare
3/20/2016
DEP 61.10.08.11: field inspection prior to commissioning of mechanical equipment. The
Information in this DEP has been arranged type of equipment such as: columns, furniture,
bumps, etc.
MS: MMS-016 for erection installation & Alignment of static equipment.
SP for pressure vessel plate, carbon steel for moderate and lower Temp. Service.
QCP: quality control plane, it’s a document provided by the contractor in the a process of
checking the equipment in sequence of activity and inspection (Receive of material, Pre-
installation, during installation) it contain : activity, type of test, controlling document,
acceptance criteria, frequency of inspection, Responsible person in location, verification
document, inspection stages.
Lifting plane: it’s a document generated by contractor for installation and lifting of
equipment.
Bill of materials (BOM): its document table specified list of materials used such as plate,
pipe, flange, elbow, dish, pad, nuts, poles, rings, lifting lugs, and list of internal materials.
Vendor manual: it’s a document provided by the manufacturer where it states operation
sequence, controlling, treble shooting, rectification, maintenance sequence.
30. M7/ Mechanical/mechanical static equipment:
stabilizer column, pressure vessel, re-boilers,
HTF heaters, Air fin cooler, AP/HP flare
3/20/2016
Installation of static equipment: when the equipment arrive
at the site based on the weight mention in GA drawings and
data sheet lifting plane is generated by contractor and
submitted to client for review and approval and this process
type of rigger lifting supervisors, Approval required, verifying
location of installation, positioning, clearance and weather
condition are important factors of any installation of static
equipment.
Foundation release
Erection of Equipment
Alignment & leveling
Installation of access ladder & plate form
Clearance for grouting
31. M7/ Mechanical/mechanical static equipment:
stabilizer column, pressure vessel, re-boilers, HTF
heaters, Air fin cooler, AP/HP flare
Stabilizer column
Re-boiler
HTF heater
AP/HP flare
Air fin cooler/fin fan cooler
Pressure Vessel
Vessel internal installation: it’s a
part of vessel internal structure used
for separation and filtration of vapor
and liquid, internals such as:
Demister pad with 100 mm
thickness.
Wire mesh used for vapor
filtration.
Scopentoeter: is SS plate
material used for crude inlet
deflection.
Collection dray: its used as
collection and distribution of liquid
through internal pipe connection
of bottom of the vessel.
Vortex breaker: its deflected
plate material installed at the
bottom of nozzle outlet
connection, its helps the liquid to
restricted flow.
3/20/2016
32. M7/ Mechanical/mechanical static equipment:
stabilizer column, pressure vessel, re-boilers, HTF
heaters, Air fin cooler, AP/HP flare
3/20/2016
Presser vessel: its an equipment used in process plant purpose of separation, there
are two type of vessels orientation:
Vertical
Horizontal
Also there process is of two types:
Two stage vessel its for liquid and vapor
Three stage vessel its for liquid and vapor and hydrocarbon.
Vessels either can be:
Above the ground vessel which usually used for process.
Below the ground vessel which for drain & hydrocarbon collection.
Attachment (internal and external parts)
External: demister, scheopentoeter, vortex breaker, collection dray, wire
mesh, internal rungs & lugs, swivel deck, etc.
External: nozzles, plate form, hinges, manway, relief valve, lifting lug, gas
outlet, liquid outlet, etc.
Fabrication of vessel:
33. M8/ Mechanical/ Mechanical Rotating equipments:
Flash Gas Compressors, Process Pumps
Rotating equipment: it’s
basically contain rotating part
and add kinetic energy to the
process. Such as: Motors,
Pumps, Compressor.
Installation of Rotating
equipment
Foundation release
Erection of Equipment
Preliminary alignment: it’s a
process which is been carryout
for the pump skid initial
installation on concrete
foundation anchor bolts once
arrested after securing motor and
pump and leg base. Alignment
will be adjusted based on shims
as supplies by vendor, initial
readings will be recorded.
Further Distance between Shaft
Ends “DBSE” will be noted and
skid will be release for grouting.
Check for elevation
Level
Position
Orientation
3/20/2016
34. M8/ Mechanical/ Mechanical Rotating equipments:
Flash Gas Compressors, Process Pumps
Axial & Radial alignments: Normally we
are using rim and face methods. There are
two types (1) Two dial indicator method
and (2) Three dial indicator method. In two
dial indicator method put one dial indicator
in the radial portion of motor shaft and
other in the axial portion (face portion) of
the motor shaft. Set the dial in zero at zero
degree. Then rotate the shaft at 0, 90, 180
and 270 degrees. The readings in each
turn must be within plus or minus 0.05mm.
In three dial indicator method fix one in the
radial and two in axial. Then rotate the
shaft at 0, 90, 180 and 270 degrees. The
radial reading in each turn must be within
plus or minus 0.05mm.The axial reading
can be determined by taking the average
of two dial indicators. The other methods
are rotalign, laser alignment and reverse
dial indicator method. In reverse dial
indicator method in which two dial
indicators will be fixed in the radial of
motor. The other steps and tolerances are
same.
Gap for grouting are Ok
Check for Equipment Preservation
Topping up preservation oil
Alignment of Driver and Driven unit
with piping Connected
Alignment of Driver & Driven unit
without piping connected
Final Inspection & Compilation of QC
Dossier including CCMS Check Sheets:
Motors: A machine especially one
powered by electricity or internal
combustion (combustible), that supplies
motive power for a vehicle or some other
device with motion power. It’s produced or
imparts motion. Or (it’s a device that
converts any form of energy into
mechanical energy).
3/20/2016
35. M8/ Mechanical/ Mechanical Rotating equipments:
Flash Gas Compressors, Process Pumps
Pumps: it’s a device that moves fluid (liquids,
and gases) or sometimes, slurries, by
mechanical action. Usually in SNCP two types
of pumps are used which are: centrifugally
pumps, and reciprocating pumps. Which are
used for transferring liquids (condensate&
water).
Major classifications of pumps are:
dynamic pumps and positive
displacement pumps. Centrifugally type
is dynamic, where as reciprocating pumps
are positive displacement pumps.
Centrifugally pumps: it’s a sub-class of
dynamic types of pumps its used to
transport fluid by the conversion of
rotating kinetic energy to the dynamic
energy of the fluid flow. The rotational
energy typically comes from engine or
electric motor.( giving the same volume
and pressure flowing)
Reciprocating pumps: it’s a class of
positive displacement pumps which
includes the piston pump, plunger pump,
and diaphragm pump. It’s often used
where a relatively small quantity of liquid
is to be handled and where a delivery
pressure is quite large. (its to take liquids
with low pressure and pump it with more
pressure).
Compressor: is a mechanical device
that increases the pressure of the
gas by reducing it volume.
An air compressor is a specific
type of gas compressor.
Compressors are similar to
pumps both increases the
pressure on fluid and both can
transport the fluid through a pipe.
3/20/2016
36. M6/ Mechanical/ Non Destructive Testing
Type of NDT methods:
Visual testing (VT)
Direct: Visual
Inspection by Direct
Remote: Inspection
thru records
example binocular,
videos, Boroscope.
3/20/2016
37. M6/ Mechanical/ Non Destructive Testing
Radiography testing: it was
discovered by Wilhelm Rontgen.
There are three type of radiography
uses:
Medical
Industrial
Agree cultural
There are two type of radiography: X-
Ray & Gamma Ray
X-ray: There is two types of X Ray
Machines.1 Stationary 2 Portable type,
High Energy X-Ray Machines: eg.
LINAC, (Linear Accelerator) & Van De
Craft generator
Gamma ray: 1.Stationary 2. Portable
Type. Ex: Iridium 192, Cesium130,
Yetterbium 169 Cobalt 60, Selenium 75.
& Thulium 170
X-ray Operating by battery current or
current, Gamma ray producing by
isotope.
Exposure time Calculated by
Distance, Strength of Isotope or
X-Ray, Film Types and material
thickness.
The Measurement unit of
radiation is Curie Or Becquerel
The unit of measuring expose is
mR or Sievert
3/20/2016
38. M6/ Mechanical/ Non Destructive Testing
Films: there are three types of films:
Monochromatic Medical X-Ray Films
Dichromatic : Industrial use”
Panchromatic “ Photography &
cinematography use”
Types Of Films
Class 1: slow film, fine grain structure.
Class 2: medium grain structure.
Class 3: fast film, coarse grain
structure.
Films made from polyester base with silver
bromide or silver halide; they Protecting
Layers by gelatin.
Film processing:
There are three stage of developing:
Developing: Alkaline Solution ( Hydro quinine,
metol,)
Stop bath: Water & 5% Glacial Acetic Acid.
Fixing & cleaning: Sodium Thio Sulfate
Cleaning
Film drying
Film Density:
Based upon darkness.
The density require for X-ray is 1.8-3.5.
The density require for Gamma ray is 2-3.5.
Density measured by densitometer or
density strip.
The Illumination for viewing the film we need
30-300 foot candles Light equalant.
Film Sensitivity:
S= least wire thickness / job thickness
x100
IQI: image quality indicator.
Type of IQI:
3/20/2016
39. M6/ Mechanical/ Non Destructive Testing
3/20/2016
MPT: Magnetic Particle Testing using only in ferrous materials, the principle of MPT
is magnetic field or magnetism
The types of magnet:
Diamagnetic.
Paramagnetic
Electromagnetic: AC, DC, Half way AC & Half Way DC.
AC Yoke lifting power is 4.5 Kg
DC Yoke lifting power is 18 Kg or 40 LPS.
DC magnet / prod type: using by dry particle method, and AC used for wet
particle method.
Types of Testing by Half Way AC & DC Method
Head Shot Methods
Coil Shot method.
Central conductor method
MPT not applicable for SS materials.
Pie indicator checks the existing of flux line.
Burma Castrol strip: checking the sensitivity of the Flaw
Gauss Testing for the Flux leakage
Demagnetization:
40. M6/ Mechanical/ Non Destructive Testing
3/20/2016
Liquid Penatrant Testing
The Principal of Liquid penatrant test by Capillary Action
LPT just applicable for non-porous materials.
To deduct only surface defects.
Type of LPT:
Aqueous
Non- Aqueous
Fluorescent
Penetrate, cleaner, developer are used in the procedure of LPT.
Types of penetrate :
Water washable: it washed by water.
Solvent based: it cleaned by solvent.
Emulsifier usually used to control non-relevant. indications
Method A: Water-Washable
Method B: Post-Emulsifiable, Lipophilic
Method C: Solvent Removable
Method D: Post-Emulsifiable, Hydrophilic
Developer should be free from Chlorine contain.
Defect: the discontinuity exceeding the Acceptable Limit so it will be rejected.
Discontinuity: is a Smallest Flaw.
41. M6/ Mechanical/ Non Destructive Testing
UT: ultrasonic testing, its using ultrasound
waves which is having frequency sound waves
to detect volumetric defects “internal or
subsurface defects”.
The sound waves measured by Decibel dB
Particle Movement is from its rest position.
Types of waves:
Longitudinal waves:
Shear waves
Compression waves
Lamb waves
Rayleigh waves
Reflection and refraction
There are 4 types of probe Techniques:
Lateral
Transverse
Orbital
Rotational.
UT tools contain:
Probe: searching unit ( transducer
Piezoelectricity: it’s producing waves by
converting a electrical energy to mechanical
energy. Therefore echo is produced.
Type of probes:
Normal probe
Angle probe
Single crystal probe
Dual crystal probe
Equipment Calibration
3/20/2016
42. M6/ Mechanical/ Non Destructive Testing
Hardness: its property of
materials that enable to resist
plastic deformation by
penetration and its resist
bending, cutting, scratching.
Definition: fundamental units of
mass, length, and time. Usually
used for CS, SS, and DSS
materials. AS per ASTM E734.
Type of Hardness:
Rockwell “HR
Brinell hardness “HBW”:
Vickers hardness “HV
Knoop Hardness “HK
Ferrite hardness test
PMI: positive materials
identification, its an
instrument analysis the
elements in the materials.
Example CS, and SS material. In
DSS the chromium percentage is
22%, and 25% , and 27%. And
the Nickel percentage is 0.5%-
5%. PMI identify the percentage
of the element in the material.
DSS = 2205
SDSS =2505
SDSS= 2705
UNS Unified Numbering System:
UNS of DSS = 31803
3/20/2016
43. M6/ Mechanical/Painting & Insulation
Define painting: paint is a mixture of
binder pigment and solvent.
Binder: its ability to bind with surface at
the condition of the surface preparation &
shall be free of dust.
Pigment: Its element adds color to the
paint
Type of pigment:
Synthetic or artificial: its extracted from
petrochemicals, coaltar for black,
phosphar for yellow, zinc phosphate for
red.
Natural color: its organic color like
limestone for white, fruit skin extracts
colors.
Solvent: its an element add to the paint
to keep it in liquid stage of temperature
set by manufacturer
Category of paint:
Organic paint Epoxy polymers: ex.
Phinollic, polyester, polyurethane,
polyureas.
Inorganic paint: are zinc silicates, zinc
phosphate, and aluminum base paint.
Uses of paint:
For protection.
For reflection
For marine service protection
Leak protection.
Weather proofing
Type of paint application technique:
Brushing
Rolling
Spraying
Powder type
3/20/2016
44. M6/ Mechanical/Painting & Insulation
Solvent: solvent are made from petrochemicals
process such as, mineral spiret, lower alcohol,
oxidizing chemicals, which evaporate above
normal temperature.
Polyurethane: its also known as PU paint/
coating.
Epoxy is a term used to denote both the basic
components of epoxy resins, as well as colloquial
name for epoxide. Epoxy resins also known as
polyepoxides are a class of reactive pre polymers
& polymers which contain epoxide. Epoxy resins
may be reacted either with themselves through
polymerization, or with a wide range of co-
reactants including polyfunctional amines acids,
phenols, alcohols & thiols. These co-reactants are
often referred to as hardeners or curatives, and
the cross-linking reaction is commonly referred to
as curing. Reaction of poly epoxides themselves
or with polyfunctional hardeners forms a
thermosetting polymer, often with high mechanical
properties, temperature and chemical resistance.
Epoxy has a wide range of applications, including
metal coatings, used in electronics/electrical
components, fiber-reinforced plastic materials &
structural adhesives it is non glossy & UV
protective.
Zinc phosphate: It is an inorganic chemical
compound used as a corrosion resistant coating on
metal surfaces either as part of an electroplating
process or applied as a primer pigment
Metallic paint:
Aluminum based paint: its contain metallic
pigment aluminum, its extracted from aluminum,
cure at high temperature.
Mixing ratio:
Single pack paint: (metallic paints) which are
ready to use, and it doesn’t have hardener, and
its cure at high temperature.
Two pack system: it’s a paint component which
has a base and hardener, where MSDS (material
safety data sheet) specified the mixing ratio
application during pot life.
Storage of paint container:
Data sheet requirement
Definition of pot life:
Shelf life:
Specific gravity (SP)
Volume solid
Surface or component in painting terminology
Volatile organic component (V.O.C):
Flash point
3/20/2016
45. M6/ Mechanical/Painting & Insulation
Construction of painting yard:
Rust Grades
Grade A Steel with mill scale layer
intact and very minor, or no rusting
Grade B Steel with spreading
surface rust and the mill scale
commenced flaking
Grade C Rusty steel with mill scale
layer flaked and loose or lost but only
minor Occurrence of pitting
Grade D Very rusty steel with mill
scale layer all rusted and extensive
occurrence Of pitting.
Preparation grades Scraping and
wire-brushing
St 2 Thorough scraping
St 3 Very thorough scraping
Preparation grades. Blast cleaning
Sa 1 Light blast cleaning
Sa 2 Thorough blast cleaning.
Sa 2½ Very thorough blast cleaning.
Sa 3 Blast cleaning to pure metal
Abrasive type of materials:
Garnet
Copper slag
Metal shot
Crushed glass
3/20/2016
46. M6/ Mechanical/Painting & Insulation
Garnet: it’s a natural element
extracted from the stone, it has
calcium carbonate crystal
structure diamond shape,
Copper slag: its granulated slag
made from metal smelting process. It
iron ore exposed to high temperature in
Furness, impurities are removed or
separated, and all slag component
removed oxides are added
Metal shot:: companion of metal
steel balls, it size will be less than
1mm, it has spherical shape, it can
be reused up to 20 times, it used in
closed chambers, it doesn’t have any
dust.
Crushed glass: its
mixture of crushed
glass, basically its
used in glass
chamber, its has
low surface profile
(roughness).
3/20/2016
Industrial Application Non industrial application
47. M6/ Mechanical/Painting & Insulation
3/20/2016
Storing place for paints
Painters’ qualification
Spray painting types & technique:
Pressure type – LVLP .
HVLP type .
Brush painter.
Profile preparation
Quantitative test:
Bresle patch test
Qualitative test: its done by several tests like: bend test, knife cross test,
impact test, peel test, adhesion test, push test.
Bend test
Knife cross cut
Push test
Peel test
48. M6/ Mechanical/Painting & Insulation
Insulation: In securing inner
component by placing or adding
a layer of mineral fiber or glass
wool or layer of ceramic, or foam
type material which prevent or
protect loss of inner temperature
and shielding from external
weather condition.
Major aim of insulation is
personnel protection, hot loss,
weather condition. mostly its
used in the process plants for
maintaining temperature in
process vessels & equipments
and related piping, for example:
Hot & Cold Insulation.
Type of Insulation:
Cold insulation
Hot insulation
Personnel protection
Zinc protection
The common materials
used to protection are:
Cellular
Mineral wool
Ceramic wool
Rigid polyurethane foam
polyisocyanurate foam “PIR”
Application of insulation
3/20/2016
49. M11/ Commissioning / SNGP, SNDC&
SNCP Process overview
3/20/2016
SNGP process block diagram: its shows the whole process
of the gas in SNGP, each process explained in details.
RMS: remote manifold station, which they collect far wells
and in one pipeline then send it to SNOS.
Dehydration: it’s a process which its remove all the
condensate from the gas and produce dry gas.
TEG regeneration: tri ethylene glycol, glycol system the main
purpose of it, is to all contamination of water (moisture) from
the gas during dehydration process.
SNDC: Saih Nihayda Depletion Compressors, the main aim
of SNDC was to increase the Gas pressure in SNGP after it
was reduced from wells. It consist of three Reciprocating
Compressors inside the SNGP and its on the begin of the
process.
50. M11/ Commissioning / SNGP, SNDC&
SNCP Process overview
SNCP: Saih Nihayda Condensate Plant.
Instrument Air System
Fuel Gas
Flare system: to have safe area for
releasing excess gas and also for blow
down of the plant. It usually burns the
excess air. The main factor of it to
collected the hydrocarbon relieve form
the plant, it has two type:
HP: high pressure.
AP: Atmospheric Pressure
Knockout Drum
Open Hazardous drain
Closed drain
Slug Catcher V-6901
Scopentoeter Device
Mismat
Plate Pack coaleser
HP inlet flash vessel V-6902
LP inlet flash vessel V-6903
Dry condensate flash vessel V-6904
Water coalecer A-6940
Condensate stabilizer C-6901
Stabilizer Side Heater E-6901
Stabilizer Re-boiler E-6902:
Bottom heat exchanger E-6904:
Top Heat exchanger E-6903
Flash Gas compressor
SNCP (HTF) Heat Transfer Fuel:
After cooling
Exporting of stabilized condensate
3/20/2016