SlideShare une entreprise Scribd logo
1  sur  29
SAJJAD KHUDHUR ABBAS
Chemical Engineering , Al-Muthanna University, Iraq
Oil & Gas Safety and Health Professional – OSHACADEMY
Trainer of Trainers (TOT) - Canadian Center of Human
Development
Episode 26 : Project
Management Costs
1. In order to know about the profit possibilities, we need todetermine the
manufacturing cost.
Manufacturing
cost
Investment cost :
• Non‐recurring procurement
costof the plant.
• Provided by bank orproject
investor
Operating cost :
•Continuous arising cost
necessary for keeping the
plant in operation
•Raw material cost, utility
cost, labourcostand
maintenance cost
Costs
Investment Cost
1. methods todetermine the investment cost : (a) Index Method
(b) Degression Method
(c) Cost Factors
Index Method
1. This method is used when the new plant is a replacementof theolder plant
 new

 old 
 I 
C  Ci,oldi,new
I
Where C is thecapital costand I is the price index.
Degression Method
1. It applies toan almostsimilarplant with highercapacity.
m
 old 
 X new 
Ci,new  Ci,old
X 
Where m is called degression exponent and normally
range from 0.32 to 0.87
Costs
Cost Method
1. If there is lack of information regarding theexisting plant, investment costcan be
estimated by using cost factor. It requires theexistenceof a processconcept and the
rough layoutof the main equipment in order todetermine thecostof the main
processing unit.
Operating Cost
1. Consists of (a) Cost of raw material
(b) Utilitycost
(c) Labourcost
(d) Maintenancecost
Utility Cost
1. It is quantity based and consisted of electricpower, steam and coolantconsumption,
heating media such ascoal and otherenergysources like hydrogen.
Costs
Labour Cost
1. Depend on the sizeof the plant. The larger the plant, the smallerthe portion of the
employment cost in relation to the manufacturing cost because large plant is usually
highlyautomated.
Maintenance Cost
1. Divided into 2 types : (a) Preventive maintenance
(b) Failure ‐ oriented maintenance
2. Failure ‐ oriented maintenance : cost for upkeep and inspection do not arise,
maintenance costonlyarise in caseof failures.
Storekeeping of spare part is important.
It might affect production since maintenance
only being carried out in thecaseof failures
3. Preventive maintenance : provides moreoperational reliability.
: if inspection strategy is applied  higher inspection cost
: if exchange strategy is applied  higherrepaircost
What is Tender Process?
 an offer todowork orsupplygoodsata fixed price
 Getting goodsorservices is also knownas
'procurement'.
Types of Procurement
• Works
• Supplies
• Services
Types of Tenders
• Open Tender
• Restricted Tender
• Direct Negotiation
Decision
Presentation
Evaluation
Tender Activities
Preparation
Advertisement
Prepare Tender Specification
Advertise Tender
Technical
Evaluation
Compile
evaluation(Tender
Report)
Present to Tender Board
Decision on Successful
Tenderer by Tender
Board
Costing
Evaluation
Tender: Guiding Principles
 Crystal clear Specification
– Match Functional Requirementswith Technical Specifications
– Avoid ““Grey”areas
 Be fairto tenderers
- providesame info & sameopportunity toall
 Not bias towardsany Brand/Tenderer
 Specify Mandatory Requirements
- useas criteria forevaluation
 Do not reveal Budget
 Observe Confidentiality
 Allow reasonable time forTenderers to respond
 Preference to Local CompaniesPreference
RISK ANALYSIS
10
i)Customer
 Paying Habits & Solvency
 Debt ‐ ridden customerscertainly represent a higher
risk than customerswithoutdebts
 Somecustomersare famous for interfering in
everything, thuscomplicating theexecution of the
project forthe plant manufacturer
 Customerprefers certain competing companies
when awarding thecontract, possibly because he is
holding a share in them
RISK ANALYSIS
ii)Customer specification: specifications often contain data and requirements
that have a considerable impact on the costs
iii)Location: legislation, infrastructure, working conditions, language difficulties
political risks (terrorism, war risk, corruption)
iv)Commercial part: High contractual penalties, liability claim for lost profit
v) Deadline situation (specified rather short):
 Low risk ‐ For project already been realized several times under similar
condition
 High Risk – New plant concept abroad
RISK ANALYSIS
vi) Processengineering:
 New process engineering concepts – very high
 Operatordemands corresponding process
engineering guarantees regarding on quantityand
qualityof products
 Retrofitting‐ increase thecapacity and product
 Rescission – Include refund of the paymentalready
madeand expiry of purchase moneyclaims
Process Development
Process Development
 Def: The process determines the kind and orderof the “
unit operations ”
 Steps to find the ideal process for the manufacturing of a
new product:
 Laboratory development
 Pilot plant station
 Pilot plant
 First large‐ scale plant
 If a new process is finally found, thecompanywill protect
itself against thecompetition by means of corresponding
licenses
CENTRAL TASK OF A PROCESS ENGINEER
The designing of the plant in a way that investment and operating costs for
the inquired plant are minimized, while the required product features with
regard to quantity and quality are complied with. Only then will the plant
be marketable.
BALANCING
Defined the MASS AND ENTHALPY BALANCES for individual processas
well as for thewholeplant Thiswill served in determining the raw material
and energyconsumption.
Within the plant, the BALANCES define the mass flow and their
physical/chemical states.
The resultsof the balancing are recorded in called MEDIA DATA SHEETS .
Media Data Sheet for Saline Solution
Thedivision of the load cases resulting
from the balancing
often even physical and chemical data like
temperature, pressure and the composition
of the mass flow.
indication of material and quantityy.
The minimum and maximum load cases
should be balanced, since not only do the
mass flows depend on the load case, but
Theoperator is interested in a broad control range to beable to
face the f luctuating demand withvariableproduction.
With continuously low demand the production will have to be cut
back as well some time or other, since otherwise the store capacity
for the product will not besufficient.
Media Data Sheet for Low Pressure Steam
Safety ‐R
elevant
Massdataareoften the basis for
thedesign of apparatus.
Data
Concentration data together
with thedesign temperatureare thedecisive
parameters regarding corrosion
Thedetermination of suchdatadoes not
occur by means of process balancing, but by
means of the safety ‐ related
design of the plant.
Here, not
operated
only the load case
at can
the plant is
vary, but also the
thermodynamic condition of the live steam due
to f luctuations during the operation of the
corresponding steam generatororpowerstation
Materials Concept
 Aspects to beconsidered in material selection
 • compositionof the media, corrosionaspect
 • design pressures and temperatures
 • hydrodynamicaspects
 • costs
 • strength
 • delivery times
 • producibility
 • weldability
 • dimensions available
 • production ‐ related aspects
 • price f l uctuations
 • guarantees
 • f l exibility regarding modifi cations (e.g. laterfixing of nozzles)
Design of Main Equipment/Appratus
 Process design
 Process f low diagram (PFD)
 Technical data sheet
 Mechanical design
 Wall thickness
 Mechanical drawing
 Production design
 details like fi xing devices, insulation fastener, eyeboltsetc.
 The resultsare the productiondrawingsand the related bills
of materials .
20
Depending on thestructureand available resourcesof the plant
manufacturer thedesign steps described above can be carried out
either in ‐ house or assigned to subcontractors. The process ‐ related
design is usuallyup to the plant manufacturer, since here his special
know ‐ how is required. In individual cases, however, the process ‐
related design can be passed on to the subcontractor. Manufacturers
of, forexample, heatexchangersorcolumns disposeof own design
programs tocalculatethe required heatexchange surfaceor the
numberof trays. The plant manufacturer ’ s task is then limited to
the specifi cation of the technical task.
Layout
 For the projectplanning phase, usually layouts in the
form of simple topviewsand sideviewsare sufficient.
In order to provide thecustomerwith a
better impression of thedesigned plant,
graphicallyprocessed three ‐
dimensional views of the layoutscan be
generated with suitable CAD systems
Based on the layout, the space required
for the plantcan bedetermined, which
– forcost reasons – is to be minimized
Quotation/Tender Document
Comprise of:
 General part : introduction to the project, indication of benchmark data such as project name,
location etc.
 Basic fl ow diagram
 Process fl ow diagram : often with so ‐ called mass fl ux bars, containing data on volume fl ow,
parameters etc. for the main mass fl ux of the plant.
 Layout
 Documented procedure : verbal description of function and operating method of the plant
 Indication of products and residuals
 Consumption of operating resources : e nergy, live steam, chemicals etc.
 Scope of supply
 Scope of services
 Options : additional supplyand services
 Supply schedule : technical data as e.g. main dimensions, weights, operating data, insulation, power
input etc. of the main components
 Commercial part : commercial data
 Framework time scheduling
 Prices
 Price maintenance
Cost to be
considered for
quotation
purpose
Main equipment
Civil works
• engineering
• transport costs
• assembly
• commissioning
• expert services
•travel expenses (particularly in case of
projects abroad)
•insurance costs (e.g. transport, site,
planning and liability
insurancesetc.)
•hedging costs (for the coverage of
currency risks)
• guarantees (costs for bank guarantees)
•overheads (internal costs of the
company)
•fittings
• pipes
• measurement instrumentation
•control and communication
systems
Quote price = Profit margin + total cost
Theoperatoranalyzes the incoming quotations both technically and
commercially. Depending on theanalysiscriteriasome competitors
will already be ruled out here. Often 3 – 5 remaining suppliers will
then be shortlisted. Theseplant manufacturers are invited to
contract negotiations . Usually, a technical presentation of the plant
manufacturerwill take place. Furthermore, commercial detailsand
unsolved issuesarediscussed. After thesettlementof all technical
and commercial aspects, thecontract negotiations are focussed on
the purchaseprice and thedateof completion, whereat thedate of
completion may beas important as the purchaseprice.
Thanks for Watching
Please follow me / SAJJAD KHUDHUR ABBAS

Contenu connexe

Tendances

Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9Moustafa Ismail Abu Dief
 
Facility planning
Facility planningFacility planning
Facility planningMANJUNATH N
 
Process design synthesis, intensification, and integration of chemical processes
Process design synthesis, intensification, and integration of chemical processesProcess design synthesis, intensification, and integration of chemical processes
Process design synthesis, intensification, and integration of chemical processesUp Seven
 
My Role In Industry as Process Engineer
My Role In Industry as Process EngineerMy Role In Industry as Process Engineer
My Role In Industry as Process EngineerSushant Labhasetwar
 
1 2 chem plantdesign-intro to plant design economics
1 2 chem plantdesign-intro to plant design  economics1 2 chem plantdesign-intro to plant design  economics
1 2 chem plantdesign-intro to plant design economicsayimsevenfold
 
Ch18 Managerial accounting aiou mba mcom 8508
Ch18 Managerial accounting aiou mba mcom 8508Ch18 Managerial accounting aiou mba mcom 8508
Ch18 Managerial accounting aiou mba mcom 8508Ali Imran Awan MBA (IT)
 
Sushil Kumar Jain resume (International) mod 3
Sushil Kumar Jain resume (International) mod 3Sushil Kumar Jain resume (International) mod 3
Sushil Kumar Jain resume (International) mod 3Sushil Kumar Jain
 
Construction quality control site inspection training (2) pages-deleted
Construction quality control  site inspection training (2) pages-deletedConstruction quality control  site inspection training (2) pages-deleted
Construction quality control site inspection training (2) pages-deletedSanjana Khound
 
Construction quality control inspection program (qcip)
Construction quality control inspection program (qcip)Construction quality control inspection program (qcip)
Construction quality control inspection program (qcip)Mital Damani
 
The function of management should focus on getting people to work towards and...
The function of management should focus on getting people to work towards and...The function of management should focus on getting people to work towards and...
The function of management should focus on getting people to work towards and...Saif al-din ali
 
4.types of manufacturing system and layouts
4.types of manufacturing system and layouts4.types of manufacturing system and layouts
4.types of manufacturing system and layoutsAkash Bakshi
 

Tendances (19)

(CAPACITY PLANNIG)
(CAPACITY PLANNIG)(CAPACITY PLANNIG)
(CAPACITY PLANNIG)
 
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
 
Facility planning
Facility planningFacility planning
Facility planning
 
Process design synthesis, intensification, and integration of chemical processes
Process design synthesis, intensification, and integration of chemical processesProcess design synthesis, intensification, and integration of chemical processes
Process design synthesis, intensification, and integration of chemical processes
 
My Role In Industry as Process Engineer
My Role In Industry as Process EngineerMy Role In Industry as Process Engineer
My Role In Industry as Process Engineer
 
Updated resume 31 may 15
Updated resume 31 may 15Updated resume 31 may 15
Updated resume 31 may 15
 
1 2 chem plantdesign-intro to plant design economics
1 2 chem plantdesign-intro to plant design  economics1 2 chem plantdesign-intro to plant design  economics
1 2 chem plantdesign-intro to plant design economics
 
Ch18 Managerial accounting aiou mba mcom 8508
Ch18 Managerial accounting aiou mba mcom 8508Ch18 Managerial accounting aiou mba mcom 8508
Ch18 Managerial accounting aiou mba mcom 8508
 
kushal kumar srivastava
kushal kumar srivastavakushal kumar srivastava
kushal kumar srivastava
 
Sushil Kumar Jain resume (International) mod 3
Sushil Kumar Jain resume (International) mod 3Sushil Kumar Jain resume (International) mod 3
Sushil Kumar Jain resume (International) mod 3
 
Resume
ResumeResume
Resume
 
Plant location & layout
Plant location & layoutPlant location & layout
Plant location & layout
 
Construction quality control site inspection training (2) pages-deleted
Construction quality control  site inspection training (2) pages-deletedConstruction quality control  site inspection training (2) pages-deleted
Construction quality control site inspection training (2) pages-deleted
 
Plant location and layout
Plant location and layout Plant location and layout
Plant location and layout
 
Construction quality control inspection program (qcip)
Construction quality control inspection program (qcip)Construction quality control inspection program (qcip)
Construction quality control inspection program (qcip)
 
The function of management should focus on getting people to work towards and...
The function of management should focus on getting people to work towards and...The function of management should focus on getting people to work towards and...
The function of management should focus on getting people to work towards and...
 
CV_Pooranpr
CV_PooranprCV_Pooranpr
CV_Pooranpr
 
Bhattacharyya_Keya-Elec.Eng
Bhattacharyya_Keya-Elec.EngBhattacharyya_Keya-Elec.Eng
Bhattacharyya_Keya-Elec.Eng
 
4.types of manufacturing system and layouts
4.types of manufacturing system and layouts4.types of manufacturing system and layouts
4.types of manufacturing system and layouts
 

Similaire à Episode 27 : Project Management Costs

Unit ii Process Planning
Unit ii Process PlanningUnit ii Process Planning
Unit ii Process PlanningAsha A
 
Manufacturing equipment new vs. remanufacturing
Manufacturing equipment  new vs. remanufacturingManufacturing equipment  new vs. remanufacturing
Manufacturing equipment new vs. remanufacturingAntonio Reis
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & ControlKunalJagtap5
 
Chemical Engineering Apparatus Design, ChEg4191-1.pptx
Chemical Engineering Apparatus Design, ChEg4191-1.pptxChemical Engineering Apparatus Design, ChEg4191-1.pptx
Chemical Engineering Apparatus Design, ChEg4191-1.pptxWendeDegefu
 
03. 333333333333333333333Capacity Planning.ppt
03. 333333333333333333333Capacity Planning.ppt03. 333333333333333333333Capacity Planning.ppt
03. 333333333333333333333Capacity Planning.pptDarrajBrahim1
 
Production managment
Production managmentProduction managment
Production managmentAamir Shaikh
 
Product and process planning
Product and process planningProduct and process planning
Product and process planningzimbar
 
Robust Algorithm Development for Application of Pinch Analysis on HEN
Robust Algorithm Development for Application of Pinch Analysis on HENRobust Algorithm Development for Application of Pinch Analysis on HEN
Robust Algorithm Development for Application of Pinch Analysis on HENIJERA Editor
 
Chapter Seven - Process selection and Analysis.ppt
Chapter Seven - Process selection and Analysis.pptChapter Seven - Process selection and Analysis.ppt
Chapter Seven - Process selection and Analysis.pptAmman8
 
DFM Design Principles
DFM Design PrinciplesDFM Design Principles
DFM Design PrinciplesNIELITA
 
Process design layout
Process design layoutProcess design layout
Process design layoutAL Kindi
 
Design and Engineering Module 3: Prototype to Product
Design and Engineering Module 3: Prototype to ProductDesign and Engineering Module 3: Prototype to Product
Design and Engineering Module 3: Prototype to ProductNaseel Ibnu Azeez
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation Prabhu Bose
 
LECTURE 6 - PROCESS & CAPACITY DESIGN.ppt
LECTURE 6 - PROCESS & CAPACITY DESIGN.pptLECTURE 6 - PROCESS & CAPACITY DESIGN.ppt
LECTURE 6 - PROCESS & CAPACITY DESIGN.pptMehrNawaz1
 
Production and operation management
Production and operation managementProduction and operation management
Production and operation managementHarsha Mathad
 

Similaire à Episode 27 : Project Management Costs (20)

Unit ii Process Planning
Unit ii Process PlanningUnit ii Process Planning
Unit ii Process Planning
 
Manufacturing equipment new vs. remanufacturing
Manufacturing equipment  new vs. remanufacturingManufacturing equipment  new vs. remanufacturing
Manufacturing equipment new vs. remanufacturing
 
Presentation on Activity-Based Costing.pptx
Presentation on Activity-Based Costing.pptxPresentation on Activity-Based Costing.pptx
Presentation on Activity-Based Costing.pptx
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
 
PEPD MODULE 1.pdf
PEPD MODULE 1.pdfPEPD MODULE 1.pdf
PEPD MODULE 1.pdf
 
Chemical Engineering Apparatus Design, ChEg4191-1.pptx
Chemical Engineering Apparatus Design, ChEg4191-1.pptxChemical Engineering Apparatus Design, ChEg4191-1.pptx
Chemical Engineering Apparatus Design, ChEg4191-1.pptx
 
03. 333333333333333333333Capacity Planning.ppt
03. 333333333333333333333Capacity Planning.ppt03. 333333333333333333333Capacity Planning.ppt
03. 333333333333333333333Capacity Planning.ppt
 
Production managment
Production managmentProduction managment
Production managment
 
Engineering
EngineeringEngineering
Engineering
 
Product and process planning
Product and process planningProduct and process planning
Product and process planning
 
Robust Algorithm Development for Application of Pinch Analysis on HEN
Robust Algorithm Development for Application of Pinch Analysis on HENRobust Algorithm Development for Application of Pinch Analysis on HEN
Robust Algorithm Development for Application of Pinch Analysis on HEN
 
Chapter Seven - Process selection and Analysis.ppt
Chapter Seven - Process selection and Analysis.pptChapter Seven - Process selection and Analysis.ppt
Chapter Seven - Process selection and Analysis.ppt
 
DFM Design Principles
DFM Design PrinciplesDFM Design Principles
DFM Design Principles
 
Process design layout
Process design layoutProcess design layout
Process design layout
 
Design and Engineering Module 3: Prototype to Product
Design and Engineering Module 3: Prototype to ProductDesign and Engineering Module 3: Prototype to Product
Design and Engineering Module 3: Prototype to Product
 
Production checklist for biotech startups
Production checklist for biotech startupsProduction checklist for biotech startups
Production checklist for biotech startups
 
Process Planning & Cost Estimation
Process Planning & Cost Estimation Process Planning & Cost Estimation
Process Planning & Cost Estimation
 
LECTURE 6 - PROCESS & CAPACITY DESIGN.ppt
LECTURE 6 - PROCESS & CAPACITY DESIGN.pptLECTURE 6 - PROCESS & CAPACITY DESIGN.ppt
LECTURE 6 - PROCESS & CAPACITY DESIGN.ppt
 
Production and operation management
Production and operation managementProduction and operation management
Production and operation management
 
10656595.ppt
10656595.ppt10656595.ppt
10656595.ppt
 

Plus de SAJJAD KHUDHUR ABBAS

PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECT
PROJECT MANAGEMENT PLAN OF  WHITE PORTLAND CEMENT  PLANT PROJECTPROJECT MANAGEMENT PLAN OF  WHITE PORTLAND CEMENT  PLANT PROJECT
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECTSAJJAD KHUDHUR ABBAS
 
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...
  DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT  (SIMULATION PROCE...  DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT  (SIMULATION PROCE...
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...SAJJAD KHUDHUR ABBAS
 
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...
  DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT  (SIMULATION PROCE...  DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT  (SIMULATION PROCE...
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...SAJJAD KHUDHUR ABBAS
 
‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...
‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...
‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...SAJJAD KHUDHUR ABBAS
 
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...SAJJAD KHUDHUR ABBAS
 
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...SAJJAD KHUDHUR ABBAS
 
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENTUSING INTEGRATED BIO...SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENTUSING INTEGRATED BIO...
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...SAJJAD KHUDHUR ABBAS
 
Production of 100 mt distilled monoglyceride (dmg)
Production of 100 mt distilled monoglyceride (dmg)Production of 100 mt distilled monoglyceride (dmg)
Production of 100 mt distilled monoglyceride (dmg)SAJJAD KHUDHUR ABBAS
 
Episode 66 : Renewable Energy Technologies
Episode 66 :  Renewable Energy TechnologiesEpisode 66 :  Renewable Energy Technologies
Episode 66 : Renewable Energy TechnologiesSAJJAD KHUDHUR ABBAS
 
Episode 65 : Membrane separation processes
Episode 65 :  Membrane separation processesEpisode 65 :  Membrane separation processes
Episode 65 : Membrane separation processesSAJJAD KHUDHUR ABBAS
 
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENTUSING INTEGRATED BIO...SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENTUSING INTEGRATED BIO...
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...SAJJAD KHUDHUR ABBAS
 
Episode 62 : MATERIAL BALANCE FOR REACTING SYSTEM
Episode 62 :  MATERIAL BALANCE FOR REACTING SYSTEM Episode 62 :  MATERIAL BALANCE FOR REACTING SYSTEM
Episode 62 : MATERIAL BALANCE FOR REACTING SYSTEM SAJJAD KHUDHUR ABBAS
 
Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM
Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM
Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM SAJJAD KHUDHUR ABBAS
 
Episode 60 : Pinch Diagram and Heat Integration
Episode 60 :  Pinch Diagram and Heat IntegrationEpisode 60 :  Pinch Diagram and Heat Integration
Episode 60 : Pinch Diagram and Heat IntegrationSAJJAD KHUDHUR ABBAS
 
Episode 59 : Introduction of Process Integration
Episode 59 :  Introduction of Process IntegrationEpisode 59 :  Introduction of Process Integration
Episode 59 : Introduction of Process IntegrationSAJJAD KHUDHUR ABBAS
 
Episode 58 : Tools Integration Examples
Episode 58 :  Tools Integration ExamplesEpisode 58 :  Tools Integration Examples
Episode 58 : Tools Integration ExamplesSAJJAD KHUDHUR ABBAS
 
Episode 57 : Simulation for Design and Analysis
Episode 57 : Simulation for Design and AnalysisEpisode 57 : Simulation for Design and Analysis
Episode 57 : Simulation for Design and AnalysisSAJJAD KHUDHUR ABBAS
 
Episode 56 : Simulation for design and analysis
Episode 56 :  Simulation for design and analysis Episode 56 :  Simulation for design and analysis
Episode 56 : Simulation for design and analysis SAJJAD KHUDHUR ABBAS
 
Episode 55 : Conceptual Process Synthesis-Design
Episode 55 :  Conceptual Process Synthesis-DesignEpisode 55 :  Conceptual Process Synthesis-Design
Episode 55 : Conceptual Process Synthesis-DesignSAJJAD KHUDHUR ABBAS
 

Plus de SAJJAD KHUDHUR ABBAS (20)

PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECT
PROJECT MANAGEMENT PLAN OF  WHITE PORTLAND CEMENT  PLANT PROJECTPROJECT MANAGEMENT PLAN OF  WHITE PORTLAND CEMENT  PLANT PROJECT
PROJECT MANAGEMENT PLAN OF WHITE PORTLAND CEMENT PLANT PROJECT
 
Electric cars
Electric carsElectric cars
Electric cars
 
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...
  DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT  (SIMULATION PROCE...  DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT  (SIMULATION PROCE...
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...
 
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...
  DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT  (SIMULATION PROCE...  DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT  (SIMULATION PROCE...
DRYING PROCESS OF BERRY FRUIT BY VACUUM DRYING EQUIPMENT (SIMULATION PROCE...
 
‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...
‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...
‘Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bi...
 
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
 
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
Sustainable Approach Of Recycling Palm Oil Mill Effluent Using Integrated Bio...
 
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENTUSING INTEGRATED BIO...SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENTUSING INTEGRATED BIO...
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...
 
Production of 100 mt distilled monoglyceride (dmg)
Production of 100 mt distilled monoglyceride (dmg)Production of 100 mt distilled monoglyceride (dmg)
Production of 100 mt distilled monoglyceride (dmg)
 
Episode 66 : Renewable Energy Technologies
Episode 66 :  Renewable Energy TechnologiesEpisode 66 :  Renewable Energy Technologies
Episode 66 : Renewable Energy Technologies
 
Episode 65 : Membrane separation processes
Episode 65 :  Membrane separation processesEpisode 65 :  Membrane separation processes
Episode 65 : Membrane separation processes
 
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENTUSING INTEGRATED BIO...SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENTUSING INTEGRATED BIO...
SUSTAINABLE APPROACH OF RECYCLING PALM OIL MILL EFFLUENT USING INTEGRATED BIO...
 
Episode 62 : MATERIAL BALANCE FOR REACTING SYSTEM
Episode 62 :  MATERIAL BALANCE FOR REACTING SYSTEM Episode 62 :  MATERIAL BALANCE FOR REACTING SYSTEM
Episode 62 : MATERIAL BALANCE FOR REACTING SYSTEM
 
Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM
Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM
Episode 61 : MATERIAL BALANCE FOR REACTING SYSTEM
 
Episode 60 : Pinch Diagram and Heat Integration
Episode 60 :  Pinch Diagram and Heat IntegrationEpisode 60 :  Pinch Diagram and Heat Integration
Episode 60 : Pinch Diagram and Heat Integration
 
Episode 59 : Introduction of Process Integration
Episode 59 :  Introduction of Process IntegrationEpisode 59 :  Introduction of Process Integration
Episode 59 : Introduction of Process Integration
 
Episode 58 : Tools Integration Examples
Episode 58 :  Tools Integration ExamplesEpisode 58 :  Tools Integration Examples
Episode 58 : Tools Integration Examples
 
Episode 57 : Simulation for Design and Analysis
Episode 57 : Simulation for Design and AnalysisEpisode 57 : Simulation for Design and Analysis
Episode 57 : Simulation for Design and Analysis
 
Episode 56 : Simulation for design and analysis
Episode 56 :  Simulation for design and analysis Episode 56 :  Simulation for design and analysis
Episode 56 : Simulation for design and analysis
 
Episode 55 : Conceptual Process Synthesis-Design
Episode 55 :  Conceptual Process Synthesis-DesignEpisode 55 :  Conceptual Process Synthesis-Design
Episode 55 : Conceptual Process Synthesis-Design
 

Dernier

ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 

Dernier (20)

ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 

Episode 27 : Project Management Costs

  • 1. SAJJAD KHUDHUR ABBAS Chemical Engineering , Al-Muthanna University, Iraq Oil & Gas Safety and Health Professional – OSHACADEMY Trainer of Trainers (TOT) - Canadian Center of Human Development Episode 26 : Project Management Costs
  • 2. 1. In order to know about the profit possibilities, we need todetermine the manufacturing cost. Manufacturing cost Investment cost : • Non‐recurring procurement costof the plant. • Provided by bank orproject investor Operating cost : •Continuous arising cost necessary for keeping the plant in operation •Raw material cost, utility cost, labourcostand maintenance cost
  • 3. Costs Investment Cost 1. methods todetermine the investment cost : (a) Index Method (b) Degression Method (c) Cost Factors Index Method 1. This method is used when the new plant is a replacementof theolder plant  new   old   I  C  Ci,oldi,new I Where C is thecapital costand I is the price index. Degression Method 1. It applies toan almostsimilarplant with highercapacity. m  old   X new  Ci,new  Ci,old X  Where m is called degression exponent and normally range from 0.32 to 0.87
  • 4. Costs Cost Method 1. If there is lack of information regarding theexisting plant, investment costcan be estimated by using cost factor. It requires theexistenceof a processconcept and the rough layoutof the main equipment in order todetermine thecostof the main processing unit. Operating Cost 1. Consists of (a) Cost of raw material (b) Utilitycost (c) Labourcost (d) Maintenancecost Utility Cost 1. It is quantity based and consisted of electricpower, steam and coolantconsumption, heating media such ascoal and otherenergysources like hydrogen.
  • 5. Costs Labour Cost 1. Depend on the sizeof the plant. The larger the plant, the smallerthe portion of the employment cost in relation to the manufacturing cost because large plant is usually highlyautomated. Maintenance Cost 1. Divided into 2 types : (a) Preventive maintenance (b) Failure ‐ oriented maintenance 2. Failure ‐ oriented maintenance : cost for upkeep and inspection do not arise, maintenance costonlyarise in caseof failures. Storekeeping of spare part is important. It might affect production since maintenance only being carried out in thecaseof failures 3. Preventive maintenance : provides moreoperational reliability. : if inspection strategy is applied  higher inspection cost : if exchange strategy is applied  higherrepaircost
  • 6.
  • 7. What is Tender Process?  an offer todowork orsupplygoodsata fixed price  Getting goodsorservices is also knownas 'procurement'. Types of Procurement • Works • Supplies • Services Types of Tenders • Open Tender • Restricted Tender • Direct Negotiation
  • 8. Decision Presentation Evaluation Tender Activities Preparation Advertisement Prepare Tender Specification Advertise Tender Technical Evaluation Compile evaluation(Tender Report) Present to Tender Board Decision on Successful Tenderer by Tender Board Costing Evaluation
  • 9. Tender: Guiding Principles  Crystal clear Specification – Match Functional Requirementswith Technical Specifications – Avoid ““Grey”areas  Be fairto tenderers - providesame info & sameopportunity toall  Not bias towardsany Brand/Tenderer  Specify Mandatory Requirements - useas criteria forevaluation  Do not reveal Budget  Observe Confidentiality  Allow reasonable time forTenderers to respond  Preference to Local CompaniesPreference
  • 10. RISK ANALYSIS 10 i)Customer  Paying Habits & Solvency  Debt ‐ ridden customerscertainly represent a higher risk than customerswithoutdebts  Somecustomersare famous for interfering in everything, thuscomplicating theexecution of the project forthe plant manufacturer  Customerprefers certain competing companies when awarding thecontract, possibly because he is holding a share in them
  • 11. RISK ANALYSIS ii)Customer specification: specifications often contain data and requirements that have a considerable impact on the costs iii)Location: legislation, infrastructure, working conditions, language difficulties political risks (terrorism, war risk, corruption) iv)Commercial part: High contractual penalties, liability claim for lost profit v) Deadline situation (specified rather short):  Low risk ‐ For project already been realized several times under similar condition  High Risk – New plant concept abroad
  • 12. RISK ANALYSIS vi) Processengineering:  New process engineering concepts – very high  Operatordemands corresponding process engineering guarantees regarding on quantityand qualityof products  Retrofitting‐ increase thecapacity and product  Rescission – Include refund of the paymentalready madeand expiry of purchase moneyclaims
  • 14. Process Development  Def: The process determines the kind and orderof the “ unit operations ”  Steps to find the ideal process for the manufacturing of a new product:  Laboratory development  Pilot plant station  Pilot plant  First large‐ scale plant  If a new process is finally found, thecompanywill protect itself against thecompetition by means of corresponding licenses
  • 15. CENTRAL TASK OF A PROCESS ENGINEER The designing of the plant in a way that investment and operating costs for the inquired plant are minimized, while the required product features with regard to quantity and quality are complied with. Only then will the plant be marketable. BALANCING Defined the MASS AND ENTHALPY BALANCES for individual processas well as for thewholeplant Thiswill served in determining the raw material and energyconsumption. Within the plant, the BALANCES define the mass flow and their physical/chemical states. The resultsof the balancing are recorded in called MEDIA DATA SHEETS .
  • 16. Media Data Sheet for Saline Solution Thedivision of the load cases resulting from the balancing often even physical and chemical data like temperature, pressure and the composition of the mass flow. indication of material and quantityy. The minimum and maximum load cases should be balanced, since not only do the mass flows depend on the load case, but Theoperator is interested in a broad control range to beable to face the f luctuating demand withvariableproduction. With continuously low demand the production will have to be cut back as well some time or other, since otherwise the store capacity for the product will not besufficient.
  • 17. Media Data Sheet for Low Pressure Steam Safety ‐R elevant Massdataareoften the basis for thedesign of apparatus. Data Concentration data together with thedesign temperatureare thedecisive parameters regarding corrosion Thedetermination of suchdatadoes not occur by means of process balancing, but by means of the safety ‐ related design of the plant. Here, not operated only the load case at can the plant is vary, but also the thermodynamic condition of the live steam due to f luctuations during the operation of the corresponding steam generatororpowerstation
  • 18. Materials Concept  Aspects to beconsidered in material selection  • compositionof the media, corrosionaspect  • design pressures and temperatures  • hydrodynamicaspects  • costs  • strength  • delivery times  • producibility  • weldability  • dimensions available  • production ‐ related aspects  • price f l uctuations  • guarantees  • f l exibility regarding modifi cations (e.g. laterfixing of nozzles)
  • 19. Design of Main Equipment/Appratus  Process design  Process f low diagram (PFD)  Technical data sheet  Mechanical design  Wall thickness  Mechanical drawing  Production design  details like fi xing devices, insulation fastener, eyeboltsetc.  The resultsare the productiondrawingsand the related bills of materials .
  • 20. 20
  • 21.
  • 22. Depending on thestructureand available resourcesof the plant manufacturer thedesign steps described above can be carried out either in ‐ house or assigned to subcontractors. The process ‐ related design is usuallyup to the plant manufacturer, since here his special know ‐ how is required. In individual cases, however, the process ‐ related design can be passed on to the subcontractor. Manufacturers of, forexample, heatexchangersorcolumns disposeof own design programs tocalculatethe required heatexchange surfaceor the numberof trays. The plant manufacturer ’ s task is then limited to the specifi cation of the technical task.
  • 23. Layout  For the projectplanning phase, usually layouts in the form of simple topviewsand sideviewsare sufficient.
  • 24.
  • 25. In order to provide thecustomerwith a better impression of thedesigned plant, graphicallyprocessed three ‐ dimensional views of the layoutscan be generated with suitable CAD systems Based on the layout, the space required for the plantcan bedetermined, which – forcost reasons – is to be minimized
  • 26. Quotation/Tender Document Comprise of:  General part : introduction to the project, indication of benchmark data such as project name, location etc.  Basic fl ow diagram  Process fl ow diagram : often with so ‐ called mass fl ux bars, containing data on volume fl ow, parameters etc. for the main mass fl ux of the plant.  Layout  Documented procedure : verbal description of function and operating method of the plant  Indication of products and residuals  Consumption of operating resources : e nergy, live steam, chemicals etc.  Scope of supply  Scope of services  Options : additional supplyand services  Supply schedule : technical data as e.g. main dimensions, weights, operating data, insulation, power input etc. of the main components  Commercial part : commercial data  Framework time scheduling  Prices  Price maintenance
  • 27. Cost to be considered for quotation purpose Main equipment Civil works • engineering • transport costs • assembly • commissioning • expert services •travel expenses (particularly in case of projects abroad) •insurance costs (e.g. transport, site, planning and liability insurancesetc.) •hedging costs (for the coverage of currency risks) • guarantees (costs for bank guarantees) •overheads (internal costs of the company) •fittings • pipes • measurement instrumentation •control and communication systems Quote price = Profit margin + total cost
  • 28. Theoperatoranalyzes the incoming quotations both technically and commercially. Depending on theanalysiscriteriasome competitors will already be ruled out here. Often 3 – 5 remaining suppliers will then be shortlisted. Theseplant manufacturers are invited to contract negotiations . Usually, a technical presentation of the plant manufacturerwill take place. Furthermore, commercial detailsand unsolved issuesarediscussed. After thesettlementof all technical and commercial aspects, thecontract negotiations are focussed on the purchaseprice and thedateof completion, whereat thedate of completion may beas important as the purchaseprice.
  • 29. Thanks for Watching Please follow me / SAJJAD KHUDHUR ABBAS