SlideShare une entreprise Scribd logo
1  sur  8
Gas Research: 
Scenario 1 
100% Gas 
• 100 % supply (226 
340kWh per year) from 
gas generation, total 
removal from the 
electricity grid. 
Scenario 2 
52% Gas 
48% 
Electricity 
Grid 
• 52 % supply (117 618 kWh per 
year) from gas generation, 
replacing Tariff 37 
• 48 % supply (108 722 kWh per 
year) from the electricity grid 
(Tariff 22). 
Perry Street natural gas pipeline 
Proposed location of generators 
Distance Team 2 1
Distance Team 2 
Feasibility of the project was determined by: 
• Cost 
• Payback period 
• Energy efficiency 
• Life expectancy 
• Maintenance 
• Installation time 
• Environmental impact 
• Social impact 
• Government grants 
2
Gas Results: Cost 
Scenario 1 
Item Cost (over a 4 year period) 
Gas Generators, Diesel, Transformers 
etc. 
30,000 per week (6,240,000 for 4 
years) 
Commissioning 28,000 
Transport and Craneage to site 32,000 
Transport and Craneage from site 20,000 
Decommissioning 20,000 
Earth Works for Pad for generators 62,400 
Earth Grid and fencing 12,000 
Gas Connection Unknown 
HV connection to switch room 50,000 
Diesel consumption Minimal – approximately 1000 for 4 
years 
Gas consumption 1,274,596 for 4 years (318,649 per 
year) 
Total 7,739,996 for 4 years 
Per Year 1,934,999 
Comparison of electricity cost per year 
Gas Generators, Diesel, Transformers 
etc. 
Commissioning 20,000 
Transport and Craneage to site 22,000 
Transport and Craneage from site 16,000 
Decommissioning 15,000 
Earth Works for Pad for generators 62,400 
Earth Grid and fencing 12,000 
Gas Connection Unknown 
HV connection to switch room 50,000 
Diesel consumption 6,056 
Gas consumption 920,212 for 4 years (230,053 per 
Electricity Consumption Tariff 22 7,047,112 for 4 years (1,761,778 per 
Total 12,330,780 for 4 years 
Per Year 3,082,697 
Electricity Grid Scenario 1 Scenario 2 
$3,997,158 $1,934,999 $3,082,697 
Scenario 2 
Item Cost (over a 4 year period) 
20,000 per week (4,160,000 for 4 
years) 
year) 
year) 
Price Difference over 4 year period compared to 
the electricity grid 
Scenario 1: $8,248,636 
Scenario 2: $3,657,852 
Distance Team 2 3
Gas Results: 
Comparison of electricity cost per year 
Payback period 
Electricity Grid Scenario 1 Scenario 2 
$3,997,158 $1,934,999 $3,082,697 
• Scenario 1: 6 months 
• Scenario 2: 10 months 
Energy Efficiency 
• No improvement in energy reduction 
Life expectancy 
• Contract period of 4 years 
• Potential of 15 -20 years (feasibility influenced by gas prices) 
Distance Team 2 4
Gas Results: Environmental impact 
Current BWEL emissions from electricity consumption 
Resource Percentage CO2 
Emissions 
(kg/MJ) 
BWEL amount 
(814 824 MJ) 
Coal 74% 0.288 173 655 kg of 
CO2 emissions 
Gas 15% 0.069 8433 kg of CO2 
emissions 
Renewabl 
es 
8% 0.005 326 kg of CO2 
emissions 
Others 3% 0.078 1906 kg of CO2 
emissions 
Total CO2 Emissions of BWEL Facility 
based on electricity consumption 
184 320 kg of 
CO2 emissions 
per year 
• BWEL emissions from electricity consumption Scenario 1: 56 222 kg of CO2 emissions per year 
BWEL emissions from electricity consumption Scenario 2 
Resource Percentage CO2 Emissions (kg/MJ) BWEL amount at (391 400 MJ) 
Coal 74% 0.288 83 415 kg of CO2 emissions 
Gas 15% 0.069 4050 kg of CO2 emissions 
Renewables 8% 0.005 156 kg of CO2 emissions 
Others 3% 0.078 915 kg of CO2 emissions 
Total CO2 Emissions of BWEL Facility based on electricity consumption 
88 536 kg of CO2 emissions per 
year 
• Scenario 1: emissons reduction of 128 098 kg of CO2 emissions per year 
• Scenario 2: emissions reduction of 66 568 kg of CO2 emissions per year 
Distance Team 2 5
Gas Results: 
Social impact 
• Minimal 
• Designated area for installation is within the BWEL boundary 
• Noise output level of 73 dB from 15 metres away 
Government grants 
• Nil 
• The Queensland Gas Scheme finished on 31 December 2013 
Distance Team 2 6
Research revealed: 
• Gas – uncertainty of gas line connection from gas authority 
• Diesel – suitable with environmental disadvantages 
• Solar – unable to supply infrequent peak demand of tariff 37 
• Wind – Land zoning issues combined with social impact 
• Hybrid – Battery storage capability required too expensive 
• Waste Heat extraction – Only increases efficiency of furnace, minimal 
energy reduction/replacement 
• Millaquin mill – Not enough fuel supply (bagasse) 
Distance Team 2 7
Distance Team 2 determined the most suitable application to 
be: cope; 
• Diesel Generation 
• Not a renewable energy, but suits the proposed requirements 
for the BWEL energy demand 
• Future improvements may prove the Hybrid system to be of 
greater economical advantage 
Distance Team 2 8

Contenu connexe

Tendances

Carbon Saving Ctg Factory
Carbon Saving Ctg FactoryCarbon Saving Ctg Factory
Carbon Saving Ctg Factory
Moinul Hossain
 
Sdge Cypress Cool Gas Seminar 6 17 09 Pk
Sdge Cypress Cool Gas Seminar 6 17 09 PkSdge Cypress Cool Gas Seminar 6 17 09 Pk
Sdge Cypress Cool Gas Seminar 6 17 09 Pk
Paul Kuhlman
 
ICEEE Poster_YoannGuinard
ICEEE Poster_YoannGuinardICEEE Poster_YoannGuinard
ICEEE Poster_YoannGuinard
Yoann Guinard
 

Tendances (20)

Scenario analysis of data centres in the Irish energy system
Scenario analysis of data centres in the Irish energy systemScenario analysis of data centres in the Irish energy system
Scenario analysis of data centres in the Irish energy system
 
Project on SOFC system in a multi-family household
Project on SOFC system in a multi-family householdProject on SOFC system in a multi-family household
Project on SOFC system in a multi-family household
 
Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power
Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable PowerFeasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power
Feasibility Assessment: Proposed B.C. LNG Facilities and Renewable Power
 
"Proposed British Columbia LNG Facilities and Renewable Power: A Feasibility ...
"Proposed British Columbia LNG Facilities and Renewable Power: A Feasibility ..."Proposed British Columbia LNG Facilities and Renewable Power: A Feasibility ...
"Proposed British Columbia LNG Facilities and Renewable Power: A Feasibility ...
 
Ap -carty_and_oregon
Ap  -carty_and_oregonAp  -carty_and_oregon
Ap -carty_and_oregon
 
Carbon Saving Ctg Factory
Carbon Saving Ctg FactoryCarbon Saving Ctg Factory
Carbon Saving Ctg Factory
 
Green Heat - renewable energies for appropriate applications
Green Heat - renewable energies for appropriate applicationsGreen Heat - renewable energies for appropriate applications
Green Heat - renewable energies for appropriate applications
 
Modelling different Thermal Energy Storage (TES) options in a TIMES model
Modelling different Thermal Energy Storage (TES) options in a TIMES modelModelling different Thermal Energy Storage (TES) options in a TIMES model
Modelling different Thermal Energy Storage (TES) options in a TIMES model
 
Sdge Cypress Cool Gas Seminar 6 17 09 Pk
Sdge Cypress Cool Gas Seminar 6 17 09 PkSdge Cypress Cool Gas Seminar 6 17 09 Pk
Sdge Cypress Cool Gas Seminar 6 17 09 Pk
 
Zero carbon projects
Zero carbon projectsZero carbon projects
Zero carbon projects
 
Energy efficiency of qantas by myassignmenthelp
Energy efficiency of qantas by myassignmenthelpEnergy efficiency of qantas by myassignmenthelp
Energy efficiency of qantas by myassignmenthelp
 
Development of a Low-Carbon Furnace for Industrial-Scale Grid Balancing
Development of a Low-Carbon Furnace for Industrial-Scale Grid BalancingDevelopment of a Low-Carbon Furnace for Industrial-Scale Grid Balancing
Development of a Low-Carbon Furnace for Industrial-Scale Grid Balancing
 
Residential heat pumps in the future Danish energy system
Residential heat pumps in the future Danish energy systemResidential heat pumps in the future Danish energy system
Residential heat pumps in the future Danish energy system
 
Energy Technology Perspectives 2016 - Towards Sustainable Urban Energy System
Energy Technology Perspectives 2016 - Towards Sustainable Urban Energy SystemEnergy Technology Perspectives 2016 - Towards Sustainable Urban Energy System
Energy Technology Perspectives 2016 - Towards Sustainable Urban Energy System
 
ICEEE Poster_YoannGuinard
ICEEE Poster_YoannGuinardICEEE Poster_YoannGuinard
ICEEE Poster_YoannGuinard
 
Findings of the IPCC
Findings of the IPCCFindings of the IPCC
Findings of the IPCC
 
Energize - Renewable Energy Sources
Energize - Renewable Energy SourcesEnergize - Renewable Energy Sources
Energize - Renewable Energy Sources
 
Power-to-gas storing renewable energy in the gas grid
Power-to-gas storing renewable energy in the gas gridPower-to-gas storing renewable energy in the gas grid
Power-to-gas storing renewable energy in the gas grid
 
UK Government Policy on CCS - Matthew Billson, U. Sheffield, at the UKCCSRC E...
UK Government Policy on CCS - Matthew Billson, U. Sheffield, at the UKCCSRC E...UK Government Policy on CCS - Matthew Billson, U. Sheffield, at the UKCCSRC E...
UK Government Policy on CCS - Matthew Billson, U. Sheffield, at the UKCCSRC E...
 
Presentation D Urosevic Iasme 08
Presentation D Urosevic Iasme 08Presentation D Urosevic Iasme 08
Presentation D Urosevic Iasme 08
 

En vedette

Adobe acrobat-405-for-macintosh-readme1239
Adobe acrobat-405-for-macintosh-readme1239Adobe acrobat-405-for-macintosh-readme1239
Adobe acrobat-405-for-macintosh-readme1239
Haris Ahmadilapa
 
Ximen Corporate Presentation September 10 2014
Ximen Corporate Presentation September 10 2014Ximen Corporate Presentation September 10 2014
Ximen Corporate Presentation September 10 2014
Ximen Mining Corp.
 
Rodriguezm telefoniamovil
Rodriguezm telefoniamovilRodriguezm telefoniamovil
Rodriguezm telefoniamovil
Norma Rodriguez
 

En vedette (18)

Adobe acrobat-405-for-macintosh-readme1239
Adobe acrobat-405-for-macintosh-readme1239Adobe acrobat-405-for-macintosh-readme1239
Adobe acrobat-405-for-macintosh-readme1239
 
Ximen Corporate Presentation September 10 2014
Ximen Corporate Presentation September 10 2014Ximen Corporate Presentation September 10 2014
Ximen Corporate Presentation September 10 2014
 
Surveys ready to go
Surveys ready to goSurveys ready to go
Surveys ready to go
 
TAM Media Kit
TAM Media KitTAM Media Kit
TAM Media Kit
 
Survmetrics i phone6 giveaway
Survmetrics i phone6 giveawaySurvmetrics i phone6 giveaway
Survmetrics i phone6 giveaway
 
Innovation training and development 3
Innovation training and development 3Innovation training and development 3
Innovation training and development 3
 
www.formatgrow.com
www.formatgrow.comwww.formatgrow.com
www.formatgrow.com
 
Germany
GermanyGermany
Germany
 
Only daughter
Only daughterOnly daughter
Only daughter
 
семинар по вр
семинар по врсеминар по вр
семинар по вр
 
игровые технологии Grow в ресторанном бизнесе
игровые технологии Grow в ресторанном бизнесеигровые технологии Grow в ресторанном бизнесе
игровые технологии Grow в ресторанном бизнесе
 
Surfing Spots
Surfing SpotsSurfing Spots
Surfing Spots
 
Health in the Workplace Report 2016 - Ireland
Health in the Workplace Report 2016 - IrelandHealth in the Workplace Report 2016 - Ireland
Health in the Workplace Report 2016 - Ireland
 
Flowlla unelmatyohon
Flowlla unelmatyohonFlowlla unelmatyohon
Flowlla unelmatyohon
 
Analisis de centimetraje Reiber Ortegana
Analisis de centimetraje Reiber OrteganaAnalisis de centimetraje Reiber Ortegana
Analisis de centimetraje Reiber Ortegana
 
Rodriguezm telefoniamovil
Rodriguezm telefoniamovilRodriguezm telefoniamovil
Rodriguezm telefoniamovil
 
Unit plan pp ci 350
Unit plan pp ci 350Unit plan pp ci 350
Unit plan pp ci 350
 
A Tempest” as a Postcolonial play
A Tempest” as a Postcolonial playA Tempest” as a Postcolonial play
A Tempest” as a Postcolonial play
 

Similaire à Gas3 joel 2

Similaire à Gas3 joel 2 (20)

Heating Homes in Britain and Ireland - is there a long term future for fossil...
Heating Homes in Britain and Ireland - is there a long term future for fossil...Heating Homes in Britain and Ireland - is there a long term future for fossil...
Heating Homes in Britain and Ireland - is there a long term future for fossil...
 
Solar photovoltaic savings
Solar photovoltaic savingsSolar photovoltaic savings
Solar photovoltaic savings
 
BHESCo Presentation - Low-Carbon Litlington & Lullington - Jan 2023.pptx
BHESCo Presentation - Low-Carbon Litlington & Lullington - Jan 2023.pptxBHESCo Presentation - Low-Carbon Litlington & Lullington - Jan 2023.pptx
BHESCo Presentation - Low-Carbon Litlington & Lullington - Jan 2023.pptx
 
2016 02-24 smart klub lcc tower blocks + rfk (1)
2016 02-24 smart klub lcc tower blocks + rfk (1)2016 02-24 smart klub lcc tower blocks + rfk (1)
2016 02-24 smart klub lcc tower blocks + rfk (1)
 
01 Green Power.ppt form uit rgpv very important topic
01 Green Power.ppt form uit rgpv very important topic01 Green Power.ppt form uit rgpv very important topic
01 Green Power.ppt form uit rgpv very important topic
 
Energy systems & power systems modelling, Comparing Experiences in Ireland an...
Energy systems & power systems modelling, Comparing Experiences in Ireland an...Energy systems & power systems modelling, Comparing Experiences in Ireland an...
Energy systems & power systems modelling, Comparing Experiences in Ireland an...
 
Carbon footprint of_euro_village_compound
Carbon footprint of_euro_village_compoundCarbon footprint of_euro_village_compound
Carbon footprint of_euro_village_compound
 
GreenBuild Seminar
GreenBuild SeminarGreenBuild Seminar
GreenBuild Seminar
 
Roadmap for achieving the 70% 2030 greenhouse gas emission reduction target i...
Roadmap for achieving the 70% 2030 greenhouse gas emission reduction target i...Roadmap for achieving the 70% 2030 greenhouse gas emission reduction target i...
Roadmap for achieving the 70% 2030 greenhouse gas emission reduction target i...
 
Clean Coal Technologies
Clean Coal TechnologiesClean Coal Technologies
Clean Coal Technologies
 
ME 499 CSP Project Presentation
ME 499 CSP Project PresentationME 499 CSP Project Presentation
ME 499 CSP Project Presentation
 
Energy production and climate change
Energy production and climate changeEnergy production and climate change
Energy production and climate change
 
Assess the transition to a circular economy for the energy system: Long-term ...
Assess the transition to a circular economy for the energy system: Long-term ...Assess the transition to a circular economy for the energy system: Long-term ...
Assess the transition to a circular economy for the energy system: Long-term ...
 
Planning and sustainable energy (February 2013)
Planning and sustainable energy (February 2013)Planning and sustainable energy (February 2013)
Planning and sustainable energy (February 2013)
 
Impact of technology uncertainty on future low-carbon pathways in the UK
Impact of technology uncertainty on future low-carbon pathways in the UKImpact of technology uncertainty on future low-carbon pathways in the UK
Impact of technology uncertainty on future low-carbon pathways in the UK
 
Bringing new energy to Britain: Policies, pathways and challenges - Steven Fr...
Bringing new energy to Britain: Policies, pathways and challenges - Steven Fr...Bringing new energy to Britain: Policies, pathways and challenges - Steven Fr...
Bringing new energy to Britain: Policies, pathways and challenges - Steven Fr...
 
Capstone Final
Capstone FinalCapstone Final
Capstone Final
 
Korea's energy policies and cooperation opportunities between Australia and K...
Korea's energy policies and cooperation opportunities between Australia and K...Korea's energy policies and cooperation opportunities between Australia and K...
Korea's energy policies and cooperation opportunities between Australia and K...
 
Group 1 TenCate Presentation FINAL
Group 1 TenCate Presentation FINALGroup 1 TenCate Presentation FINAL
Group 1 TenCate Presentation FINAL
 
Sustainable Energy Futures for Michigan
Sustainable Energy Futures for MichiganSustainable Energy Futures for Michigan
Sustainable Energy Futures for Michigan
 

Dernier

Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 

Dernier (20)

Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 

Gas3 joel 2

  • 1. Gas Research: Scenario 1 100% Gas • 100 % supply (226 340kWh per year) from gas generation, total removal from the electricity grid. Scenario 2 52% Gas 48% Electricity Grid • 52 % supply (117 618 kWh per year) from gas generation, replacing Tariff 37 • 48 % supply (108 722 kWh per year) from the electricity grid (Tariff 22). Perry Street natural gas pipeline Proposed location of generators Distance Team 2 1
  • 2. Distance Team 2 Feasibility of the project was determined by: • Cost • Payback period • Energy efficiency • Life expectancy • Maintenance • Installation time • Environmental impact • Social impact • Government grants 2
  • 3. Gas Results: Cost Scenario 1 Item Cost (over a 4 year period) Gas Generators, Diesel, Transformers etc. 30,000 per week (6,240,000 for 4 years) Commissioning 28,000 Transport and Craneage to site 32,000 Transport and Craneage from site 20,000 Decommissioning 20,000 Earth Works for Pad for generators 62,400 Earth Grid and fencing 12,000 Gas Connection Unknown HV connection to switch room 50,000 Diesel consumption Minimal – approximately 1000 for 4 years Gas consumption 1,274,596 for 4 years (318,649 per year) Total 7,739,996 for 4 years Per Year 1,934,999 Comparison of electricity cost per year Gas Generators, Diesel, Transformers etc. Commissioning 20,000 Transport and Craneage to site 22,000 Transport and Craneage from site 16,000 Decommissioning 15,000 Earth Works for Pad for generators 62,400 Earth Grid and fencing 12,000 Gas Connection Unknown HV connection to switch room 50,000 Diesel consumption 6,056 Gas consumption 920,212 for 4 years (230,053 per Electricity Consumption Tariff 22 7,047,112 for 4 years (1,761,778 per Total 12,330,780 for 4 years Per Year 3,082,697 Electricity Grid Scenario 1 Scenario 2 $3,997,158 $1,934,999 $3,082,697 Scenario 2 Item Cost (over a 4 year period) 20,000 per week (4,160,000 for 4 years) year) year) Price Difference over 4 year period compared to the electricity grid Scenario 1: $8,248,636 Scenario 2: $3,657,852 Distance Team 2 3
  • 4. Gas Results: Comparison of electricity cost per year Payback period Electricity Grid Scenario 1 Scenario 2 $3,997,158 $1,934,999 $3,082,697 • Scenario 1: 6 months • Scenario 2: 10 months Energy Efficiency • No improvement in energy reduction Life expectancy • Contract period of 4 years • Potential of 15 -20 years (feasibility influenced by gas prices) Distance Team 2 4
  • 5. Gas Results: Environmental impact Current BWEL emissions from electricity consumption Resource Percentage CO2 Emissions (kg/MJ) BWEL amount (814 824 MJ) Coal 74% 0.288 173 655 kg of CO2 emissions Gas 15% 0.069 8433 kg of CO2 emissions Renewabl es 8% 0.005 326 kg of CO2 emissions Others 3% 0.078 1906 kg of CO2 emissions Total CO2 Emissions of BWEL Facility based on electricity consumption 184 320 kg of CO2 emissions per year • BWEL emissions from electricity consumption Scenario 1: 56 222 kg of CO2 emissions per year BWEL emissions from electricity consumption Scenario 2 Resource Percentage CO2 Emissions (kg/MJ) BWEL amount at (391 400 MJ) Coal 74% 0.288 83 415 kg of CO2 emissions Gas 15% 0.069 4050 kg of CO2 emissions Renewables 8% 0.005 156 kg of CO2 emissions Others 3% 0.078 915 kg of CO2 emissions Total CO2 Emissions of BWEL Facility based on electricity consumption 88 536 kg of CO2 emissions per year • Scenario 1: emissons reduction of 128 098 kg of CO2 emissions per year • Scenario 2: emissions reduction of 66 568 kg of CO2 emissions per year Distance Team 2 5
  • 6. Gas Results: Social impact • Minimal • Designated area for installation is within the BWEL boundary • Noise output level of 73 dB from 15 metres away Government grants • Nil • The Queensland Gas Scheme finished on 31 December 2013 Distance Team 2 6
  • 7. Research revealed: • Gas – uncertainty of gas line connection from gas authority • Diesel – suitable with environmental disadvantages • Solar – unable to supply infrequent peak demand of tariff 37 • Wind – Land zoning issues combined with social impact • Hybrid – Battery storage capability required too expensive • Waste Heat extraction – Only increases efficiency of furnace, minimal energy reduction/replacement • Millaquin mill – Not enough fuel supply (bagasse) Distance Team 2 7
  • 8. Distance Team 2 determined the most suitable application to be: cope; • Diesel Generation • Not a renewable energy, but suits the proposed requirements for the BWEL energy demand • Future improvements may prove the Hybrid system to be of greater economical advantage Distance Team 2 8

Notes de l'éditeur

  1. Investigation revealed that a natural gas pipeline exists just outside of the BWEL boundary. Research revealed unpredictability of gas prices which lead Distance Team 2 to investigate the option of renting the required generation equipment. The company approach for the rental solution was aggreko. 2 scenarios were investigated. Scenario one involved 100% gas supply while scenario 2 involved an almost even split of gas generation and electricity from the grid.
  2. Significant cost reductions were estimated from both scenario 1 & 2
  3. Payback periods were estimated to be minimal With no improvements of energy efficiency Over a 4 year Contract period.
  4. Gas generation shows definite reductions in emissions from energy consumption
  5. Social impact would be minimal with no government grants applicable
  6. The most suitable application was determined to be diesel generation. Distance team 2 believes future improvements in battery capabilities may prove hybrid systems to be of greater advantage than stand alone diesel systems.