1. SHAIK MOHAMMAD KARIMULLA
Email: kareemshah.06@gmail.com
Mobile: +971 55 2596976 / +91 9885275048
Personal Details
PROFESSION : Senior Electrical Engineer
NATIONALITY : Indian
Date of Birth : 16-07-1985
Passport : H5168208
Skype ID : shaikmohammadkarimulla
Marital status : Married
LANGUAGES: English, Urdu, Hindi, Telugu and Arabic(Basic)
EDUCATION: B.E in Electrical Engineering in the year 2006,
Post-Graduation Diploma in Project Management 2012.
KEY EXPERIENCE:
Complete Erection, installation, earthing, testing of Electrical equipment’s, panels, transformers and
implementing the Substations, Power plants & Traffic signals.
Handel the projects, and supervising the team of technicians.
Meeting with Consultants / clients for resolving site issues technically to reach the standards.
Cable Laying, Jointing, termination and testing of HV/LV Power cables, control and power cables.
Study and execution of project specification and BOQ of materials.
Handling of Electrical & Civil Works from Initial stage to Final stage of the project.
Analyzing the site and plan according to the material availability.
Implementation of the Inspection/ Test plans and confirmation with the specification requirements.
Operation and Maintenance of HV, MV, LV electrical equipments and utility systems (Authorized O&M
Engineer).
Conduct all Routine tests for transformer as per Customer specifications
Review of Submittals/Shop drawings and As-built drawings.
Study and execution of project specification and checking/ approving bills.
Maintain project correspondences/ documentations and produce for auditing as required.
Coordinates with the inspection procedures along with (Abu Dhabi Distribution Company) ADDC Engineers.
Prepare the documents for carrying out the approval of drawings and finally achieving the connection from
ADDC for the electrical systems.
2. PROFESSIONAL HISTORY
DEC 2014 – PRESENT ELECTRO MECHANICAL CO L.L.C (Agents for SIEMENS), ABU DHABI,U.A.E
SENIOR ELECTRICAL ENGINEER
NOV 2013 – NOV 2014 MEGHA ENGINEERING & INFRASTRUCTURE LTD, HYDERABAD, INDIA
SITE MANAGER
JAN 2011 – OCT 2013 PnU ENGINEERING PVT LTD, HYDERABAD, INDIA
SENIOR ELECTRICAL ENGINEER
AUG 2008 – DEC 2010 SRI RAYALASEEMA GREEN ENERGY LTD, ANDHRA PRADESH, INDIA
TESTING ENGINEER
JUN 2006 – JUL 2008 THULASI PROJECTS PVT LTD, HYDERABAD, INDIA
SITE ENGINEER-ELECTRICAL
DETAILED EXPERIENCE
DEC 2014 – PRESENT ELECTRO MECHANICAL CO L.L.C (Agents for SIEMENS), ABU DHABI,U.A.E
SENIOR ELECTRICAL ENGINEER
Projects: Infrastructure works at Saadiyat Island phase I&II, Al Raha Beach Development,Al DanaPhase II- Abu
Dhabi
Project Details:
Cultural District, Marina District, Al Raha & Al Dana- Infrastructure works - Intelligent Transportation Systems
(ITS), Distribution substations. Supply, Erection, installation, testing, commissioning & energization of Traffic
signals- C900V controller, change over, FEC, UPS system & CCTV cameras, distribution substations- (22/0.415KV)
complete with distribution transformers,22KV switchgears (9 panel arrangement), LV switchgears, telephone
outlets, auxiliary AC and DC power supplies, DMS interface, grounding, lighting, ventilation, 415volt, 8ways feeder
pillars, associated civil work and all required accessories, 22KV/415V cable laying including joints and termination.
Construction, testing and commissioning of traffic signals, distribution substations. Testing commissioning and
Plug in termination of 22KV cables to the primary substations. Fiber optic cable laying (FOC) connecting all
junctions and from primary substations to distribution 22KV substations, splicing and terminations to the FOTB.
Street lighting works – 10m, 14m and high mast light poles LED luminaries with dimmer controller technology.
Responsibilities:
Study and execution of project specification and checking BOQ of material.
Review of Submittals/Shop drawings according to the specifications/standards.
Ensure the work is being performed at the most compliance to specification, international standards and time
schedule.
3. Promote and ensure the use of safe work practices to provide a safe work environment to all personnel as
well as equipment’s.
Prepare and communicate work progress reports.
Providing the safety reports weekly
Spot and immediately report any deviations to the engineering-specifications, inputs or targets, plan
corrective actions and realize them in co- operation with all the related staff.
Inspect materials, work activities and witness testing and commissioning.
Recognize and communicate scope and design changes promptly.
Provide on-site technical assistance as needed.
Coordinate work activities with other staff members, contractors and end users.
Produce new and modified technical applications for the progress of work.
Prepare snag list and ensure the snag clearance.
Check and correct Bills of payment and Record drawings.
Develop schematics, equipment layouts, procedures and schedules for the smooth handing over of project.
Familiarize with the client’s expectations, scope, budget, and schedule for assigned tasks.
Prepare the Documentations for carrying out Abu Dhabi Distribution Company (ADDC) Approval procedures.
Co-ordinates with the Inspection Procedures along with Abu Dhabi Distribution Company (ADDC) Engineers.
NOV 2013 – NOV 2014 MEGHA ENGINEERING & INFRASTRUCTURE LTD, HYDERABAD, INDIA
SITE MANAGER
Project Details:
765/400/220 KV SS at WUPPTCL Project, Greater Noida- Substation Supply, Erection, Installation, Cabling,
Earthing, Testing & Commissioning of 220/400/765 KV SS with AIS Equipment’s like CT, CVT, LA, ISO, Shunt
reactors, Wave trappers & Transformers. Supervision and quality checking of all civil activities.
JAN 2011 – OCT 2013 PnU ENGINEERING PVT LTD, HYDERABAD, INDIA
SENIOR ELECTRICAL ENGINEER
Project Details:
220KV-15 Bay Switch Yard & 3X75MW Aluminum Refinery/Power plant at Anrak Aluminum Ltd – Supply,
Erection, Installation, Cabling, Testing & Commissioning of 220 KV SS 15 Bay with AIS Equipment’s like CT, CVT,
LA, ISO, Wave trappers & Transformers.
110kV SS Bay Extension at AERL 12X8.75 Gas Based Cyclic power Plant – Supply, Erection, Installation,
Cabling, and Testing & Commissioning of 110 KV SS with AIS Equipment’s like CT, CVT, LA and ISO.
132kV SS Bay Extension & 50MW Thermal Power Plant at Raasi Cements (ICL) - Supply, Erection, Installation,
Cabling, Testing & Commissioning of 132 KV SS Bay extension with AIS Equipment’s like CT, CVT, LA, ISO &
Transformer. 50 MW TPP HT Cable laying, Termination, Erection & Installation of Electrical Panels, HT Bus bars,
Bus Ducts and Transformers erection, Installation & Commissioning.
4. 11/33kv ss at 128 MW Wind Energy at Fortune Five Hydel Projects, Bijapur – Supply, Erection, Installation,
caballing, Testing & Commissioning of 11/33 KV SS Equipment’s like Kiosk Panels equipped with CT, PT, Breaker
and C&R panel. LA, ISO and Transformers are out door.
Responsibilities:
Major work is to manage the site comfortably by fulfilling the site requirements and reporting
customer for the daily work progress.
Complete erection work in a 765/400/220/132/110/33KV Switch yard in Substation (Including Equipment
Erection and Installation, Earthling, Cable laying, panel, Transformer, Shunt Reactors erection, etc.)
Main responsibility is to inspect the site for clearance and update our daily progress to the HO.
Arranging manpower from Sub contractor for successful completion of AIS installation and testing of AIS
equipment’s like the Current Transformer SF-6 gas (Siemens), Control Panels (Siemens), Capacitor Voltage
Transformer (CGL), Capacitor Voltage Transformer (SIEMENS), Wave or Line trap (Areva), Capacitor Voltage
Transformer (Areva), Circuit Breaker SF-6 gas (SIEMENS), Isolators and alignments (SIEMENS), Terminal clamps
and connectors as per erection key drawings.
Reviewing the site drawings, before starting a job any modification of erection that discussed with design
engineer/project manager and ensuring corrective action to sub-contractor.
Stringing insulator for twin moose ACSR conductor and quad moose ACSR conductor as per drawings.
Single suspension insulators for twin moose ACSR conductor and quad moose ACSR conductor as per
drawings.
Installation of the Auxiliary Earth mat and Main mat Throughout Substation and Arranging the Earthling for
the all Equipment as Per Design.
Installation of the Lightning Protection and Earth pit for the Substation as per Design.
Coordinating the all power and Control Cable Laying work for the all Equipment as per scheme requires.
Assisting to testing and pre-commissioning activities of various systems in conjunction with customer.
To determine and estimate the needs of additional resources.
To prepare measurement sheet for conductor and aluminum pipe.
Prepare BOM for handover the spares as per technical specification.
Preparing of Cables Schedule as per schematics.
Preparing BOQ for the earth rod, GI & MS earth flat etc.,
Handling of Civil & Electrical Works from Initial stage to Final stage at all Sub Stations
Analyzing the site and plan according to the material availability.
Erection of Cable Trench, Tray Erection, Cable Laying, Installing joint kits & Termination.
Transformer erection, testing and commissioning.
AUG 2008 – DEC 2010 SRI RAYALASEEMA GREEN ENERGY LTD, ANDHRA PRADESH, INDIA
TESTING ENGINEER
Project Details:
Transformer Divison-Worked as Testing Engineer from August-2008 to Dec-2010.
Having 3 years rich experience in transformer testing
Done the testing of the transformers as per IS 2026 – 1997
Conduct all Routine tests for transformer as per Customer specifications
Tested All Ratings of Distribution Transformers & Power Transformers
5. Handling all type of test Equipment
Prepare Final Inspection Plan according to delivery schedule
Inspecting All transformers before offering for Final Inspection
Attended Joint inspection of the Departmental & Third Party at factory
Preparing Joint Inspection Reports & Calculation Sheets
Maintain Calibration Records for test equipment & precious instruments
JUN 2006 – JUL 2008 THULASI PROJECTS PVT LTD, HYDERABAD, INDIA
SITE ENGINEER-ELECTRICAL
Project Details: Corporation Worked as Site Engineer In charge of High Voltage Distribution System (HVDS) at
Rajampet Division-II of Kadapa Dist., from june-2006 to july-2008 and acquired Knowledge in execution of the
works in connection with conversion of LT Network into HT and erection of 3phase 16/25 KVA Distribution
Transformers for individual Agricultural Services in Southern Power Distribution Limited
OUTSTANDING ACHIEVEMENTS
CERTIFICATION: Development of PLC Application programme through SCADA.
(ECIL-Electronics Corporation of India Ltd)
Description- This application programme includes motion control of motors etc., SCADA technology results in
time-saving and efficient performance. Today PLC’s deliver a wide range of complex networking. PLC’s used
to monitor and control a plant or a process distributed over a large geographic area such as power
distribution network.
Holding UAE Driving License.
COMPUTER PROFICIENCY
Packages: MS Office, Auto-CAD.
Operating systems: MS DOS, MS WINDOWS, WINDOWS VISTA & 7.
System trouble shooting, Software/ Hardware Installations & Networking.
DECLARATION
I hereby declare that above stated information is true and correct with best of my knowledge and belief.
Date: Yours Truly,
Place: (Shaik Mohammad Karimulla)