Procurement of Raw Materials
• Procurement in manufacturing sector refers to the method of
purchase of raw materials from an external source.
• Raw material procurement process involves researching, selecting,
ordering, and paying for raw materials required for a business.
• Identifying and selecting vendors, negotiating prices and terms,
and awarding contracts are some steps in the procurement
process.
• Raw material selection involves several factors that includes cost,
quality, availability, and delivery time.
Procurement of Raw Materials
• Raw material procurement is the process of identifying and
acquiring the necessary materials to support production activities.
• Materials may be purchased in bulk, such as commodities or
manufactured goods, or they may be purchased separately, such
as components or subassemblies.
Procurement of Raw Materials
• The role of raw material procurement is vital for profitability and
overall success of a business.
• In order to ensure a smooth supply chain management of raw
materials, business can adopt strategies like building a distribution
network, sourcing locally, etc.
• Demand collection can prove to be highly beneficial in
procurement for large businesses.
Procurement of Raw Materials
Procurement of Raw Materials
• The material procurement process consists of seven main process
steps.
• The key steps in the procurement of raw materials include the
following:
Procurement of Raw Materials
1.Need analysis
• Assessing the need is the first crucial step in procurement where
the company takes stock of the raw materials required from
different teams and separate out the list depending on the priority
of the needs.
• At this stage, the team handling procurement also determines the
best way to procure raw materials in terms of cost saving and
logistics.
Procurement of Raw Materials
2.Contract negotiation and approval
• Once the list of procurement is decided, the procurement
department identifies vendors and requests for quotes.
• At least three quotes are sourced as a practice, but it depends on
the organization.
• The vendor with the lowest quotation is selected and post
approval of the quote, the raw materials are transported to the
manufacturing units.
Procurement of Raw Materials
3.Purchase requisition
• Once the list of procurement is decided, the procurement team
seeks approval for the purchase.
• They also cross verify the list with different teams and the raw
materials are approved as per their operational priority.
Procurement of Raw Materials
4.Purchase order review
• Prior to the final approval of the order, the senior procurement
manager does one final review before approval.
• Once the approval is obtained from the procurement manager, the
list is sent to the accounts department.
Procurement of Raw Materials
5.Funds for raw materials are verified
• Based on the list, the accounts department issues a purchase
order to the vendor and releases the funds.
• That purchase order is an indication to the vendor that the
request has been approved and that they can proceed with the
request.
Procurement of Raw Materials
6. Shipping of raw materials
• While in selected cases, the vendors arrange for the
transportation of raw materials, it does not always happen in the
case of all suppliers.
• In most cases, businesses need to arrange for their own
transportation to transfer the raw materials from suppliers to the
manufacturing units.
Procurement of Raw Materials
7.Invoice approval and payment
• Once the raw materials reach the manufacturing unit, the
products are cross verified against the bill and the invoice is
approved and the payment is transferred to the suppliers.
Procurement of Raw Materials
Procurement of raw Materials Strategies
• Source locally
• Build a list of locally sources
• Increase inventory
• Connect with a distributor
Classification of Engineering materials
Most of the Engineering materials can be classified into main
following categories :
1. Metallic materials (Metals, Non-metals)
2. Polymeric materials
3. Ceramic materials
4. Composite materials
5. Electronic materials
6. Advance materials
Classification, cont.
• Metals
• Steel, Cast Iron,
Aluminum, Copper,
Titanium, many others
• Ceramics
• Glass, Concrete, Brick,
Alumina, Zirconia, SiN,
SiC
• Polymers
• Plastics, Wood, Cotton
(rayon, nylon), “glue”
• Composites
• Glass Fiber-reinforced
polymers, Carbon Fiber-
reinforced polymers, Metal
Matrix Composites, etc.
Material Requirement Planning
• Material requirements planning (MRP) is a system for calculating
the materials and components needed to manufacture a product.
• MRP helps to develop a production plan for finished goods by
defining inventory requirements for components and raw
materials.
Material Requirement Planning
• MRP system determines item by item, what is to be processed and
when, as well as what is to be manufactured when.
• This is based on order priorities and available capacities.
Material Requirement Planning
• MRP consists of three primary steps:
i. taking inventory of the materials and components on hand,
ii. identifying which additional ones are needed and
iii. then scheduling their production or purchase
Overview of MRP System
Product Structure File
BOM
• A bill of materials (BOM) is a comprehensive inventory of the
raw materials, assemblies, subassemblies, parts
and components, as well as the quantities of each needed to
manufacture a product.
• It is the complete list of all the items that are required to build
a product.
• BOMs also include the instructions for procuring and using the
materials.
Master production Schedule
• As the name implies, a master production schedule determines
what products are manufactured, when they are produced, and in
what quantities.
• The required raw materials are identified by the finished goods
BOM, the data from which is integrated with current inventory
data to create the MRP for raw materials procurement
MRP Example 1
Compute the MRP plan for the Item x shown below. Note that the
item has an independent demand that requires a safety stock of 40
units to be maintained.
Order Quantity = 70
Lead Time = 4 weeks
Safety Stock = 40
Weeks
1 2 3 4 5 6 7 8 9 10 11 12
Project requirement 20 20 25 20 20 25 20 20 30 25 25 25
Schedule Receipts 70
On hand at the end of
period
65
Planned order
released
MRP Example
Solution:
Order Quantity = 70
Lead Time = 4 weeks
Safety Stock = 40
Weeks
1 2 3 4 5 6 7 8 9 10 11 12
Project requirement 20 20 25 20 20 25 20 20 30 25 25 25
Schedule Receipts 70 70 70 70
On hand at the end of
period
65 45
95
25
70 50
100
30
75 55
105
35
75 50
95
25
70
Planned order
released
70 70 70
MRP Example 2
Compute the MRP plan for the component shown below. Use lot size
of 60 and lead time of 1 week and a safety stock of 10 units to be
maintained.
Order Quantity = 60
Lead Time = 1 week
Safety Stock = 10
Weeks
1 2 3 4 5 6 7 8
Gross requirement 60 140 30 130
Schedule Receipts 50 50 50
On hand at the end of
period
20
Planned order
released
MRP Example 2
Solution:
Order Quantity = 60
Lead Time = 1 week
Safety Stock = 10
Weeks
1 2 3 4 5 6 7 8
Gross requirement 60 140 30 130
Schedule Receipts 50 50 60 60 60 50
60
On hand at the end of
period
20 70 70 60
10
120
60
40
180
70
10
50
180
50
Planned order
released
60 60 60 60
MRP Benefits
• MRP assures that materials and components will be available when
needed, minimizes inventory levels, production planning,
purchase planning, recourse planning, reduces customer lead
times, and improves customer satisfaction.
The End

Contenu connexe

Similaire à Lect 3_Procurement of Raw materials & MRP.pptx

Presentation2 mrp
Presentation2 mrpPresentation2 mrp
Presentation2 mrpgsuicmez
 
Supply chain management
Supply chain managementSupply chain management
Supply chain managementPRIYABAMBALE
 
Ppt of purchase cycle chandra 12mt07ind008
Ppt of purchase cycle chandra 12mt07ind008Ppt of purchase cycle chandra 12mt07ind008
Ppt of purchase cycle chandra 12mt07ind008samjune
 
Material management
Material managementMaterial management
Material managementvruti patel
 
Chapter 03 Material Costing
Chapter 03   Material CostingChapter 03   Material Costing
Chapter 03 Material Costingayanthimadhumali
 
MATERIAL MANAGEMENT IN SUPPLY CHAIN.pptx
MATERIAL MANAGEMENT IN SUPPLY CHAIN.pptxMATERIAL MANAGEMENT IN SUPPLY CHAIN.pptx
MATERIAL MANAGEMENT IN SUPPLY CHAIN.pptxKULDEEPSINGH637195
 
Materials management
Materials managementMaterials management
Materials managementdeepthipgdm
 
MATERIAL COSTING.pptx
MATERIAL COSTING.pptxMATERIAL COSTING.pptx
MATERIAL COSTING.pptxRaysaFara
 
Materialmanagement&inventorycontrol
Materialmanagement&inventorycontrolMaterialmanagement&inventorycontrol
Materialmanagement&inventorycontrolManish Pandey
 
Inventory fundamental powerpoint
Inventory fundamental powerpointInventory fundamental powerpoint
Inventory fundamental powerpointekramkhan
 
Material Requirement planning (factors,inputs,outputs,benifits)
Material Requirement planning  (factors,inputs,outputs,benifits)Material Requirement planning  (factors,inputs,outputs,benifits)
Material Requirement planning (factors,inputs,outputs,benifits)razinbabaria786
 
CE4250 CPM Lecture 4 Store Management.pdf
CE4250 CPM Lecture 4 Store Management.pdfCE4250 CPM Lecture 4 Store Management.pdf
CE4250 CPM Lecture 4 Store Management.pdfssusercbae26
 
material-management-1.pptxInternal corrosion prevention:Internal corrosion pr...
material-management-1.pptxInternal corrosion prevention:Internal corrosion pr...material-management-1.pptxInternal corrosion prevention:Internal corrosion pr...
material-management-1.pptxInternal corrosion prevention:Internal corrosion pr...Mekine
 
Foodhall purchase dept
Foodhall purchase deptFoodhall purchase dept
Foodhall purchase deptSneha Nair
 

Similaire à Lect 3_Procurement of Raw materials & MRP.pptx (20)

Presentation2 mrp
Presentation2 mrpPresentation2 mrp
Presentation2 mrp
 
Supply chain management
Supply chain managementSupply chain management
Supply chain management
 
Ppt of purchase cycle chandra 12mt07ind008
Ppt of purchase cycle chandra 12mt07ind008Ppt of purchase cycle chandra 12mt07ind008
Ppt of purchase cycle chandra 12mt07ind008
 
Material management
Material managementMaterial management
Material management
 
Chapter 03 Material Costing
Chapter 03   Material CostingChapter 03   Material Costing
Chapter 03 Material Costing
 
Assignment 2 2
Assignment 2 2Assignment 2 2
Assignment 2 2
 
MATERIAL MANAGEMENT IN SUPPLY CHAIN.pptx
MATERIAL MANAGEMENT IN SUPPLY CHAIN.pptxMATERIAL MANAGEMENT IN SUPPLY CHAIN.pptx
MATERIAL MANAGEMENT IN SUPPLY CHAIN.pptx
 
Supply Chain Management
Supply Chain ManagementSupply Chain Management
Supply Chain Management
 
Materials management
Materials managementMaterials management
Materials management
 
MATERIAL COSTING.pptx
MATERIAL COSTING.pptxMATERIAL COSTING.pptx
MATERIAL COSTING.pptx
 
Materialmanagement&inventorycontrol
Materialmanagement&inventorycontrolMaterialmanagement&inventorycontrol
Materialmanagement&inventorycontrol
 
Inventory fundamental powerpoint
Inventory fundamental powerpointInventory fundamental powerpoint
Inventory fundamental powerpoint
 
Material Requirement planning (factors,inputs,outputs,benifits)
Material Requirement planning  (factors,inputs,outputs,benifits)Material Requirement planning  (factors,inputs,outputs,benifits)
Material Requirement planning (factors,inputs,outputs,benifits)
 
Module 2
Module 2Module 2
Module 2
 
CE4250 CPM Lecture 4 Store Management.pdf
CE4250 CPM Lecture 4 Store Management.pdfCE4250 CPM Lecture 4 Store Management.pdf
CE4250 CPM Lecture 4 Store Management.pdf
 
Aishh mm
Aishh mmAishh mm
Aishh mm
 
material-management-1.pptxInternal corrosion prevention:Internal corrosion pr...
material-management-1.pptxInternal corrosion prevention:Internal corrosion pr...material-management-1.pptxInternal corrosion prevention:Internal corrosion pr...
material-management-1.pptxInternal corrosion prevention:Internal corrosion pr...
 
Material management
Material managementMaterial management
Material management
 
Foodhall purchase dept
Foodhall purchase deptFoodhall purchase dept
Foodhall purchase dept
 
MATERIAL HANDLING
MATERIAL HANDLINGMATERIAL HANDLING
MATERIAL HANDLING
 

Dernier

Lesson no16 application of Induction Generator in Wind.ppsx
Lesson no16 application of Induction Generator in Wind.ppsxLesson no16 application of Induction Generator in Wind.ppsx
Lesson no16 application of Induction Generator in Wind.ppsxmichaelprrior
 
Operating System chapter 9 (Virtual Memory)
Operating System chapter 9 (Virtual Memory)Operating System chapter 9 (Virtual Memory)
Operating System chapter 9 (Virtual Memory)NareenAsad
 
Attraction and Repulsion type Moving Iron Instruments.pptx
Attraction and Repulsion type Moving Iron Instruments.pptxAttraction and Repulsion type Moving Iron Instruments.pptx
Attraction and Repulsion type Moving Iron Instruments.pptxkarthikeyanS725446
 
Software Engineering - Modelling Concepts + Class Modelling + Building the An...
Software Engineering - Modelling Concepts + Class Modelling + Building the An...Software Engineering - Modelling Concepts + Class Modelling + Building the An...
Software Engineering - Modelling Concepts + Class Modelling + Building the An...Prakhyath Rai
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdfInvolute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdfJNTUA
 
Multivibrator and its types defination and usges.pptx
Multivibrator and its types defination and usges.pptxMultivibrator and its types defination and usges.pptx
Multivibrator and its types defination and usges.pptxalijaker017
 
DR PROF ING GURUDUTT SAHNI WIKIPEDIA.pdf
DR PROF ING GURUDUTT SAHNI WIKIPEDIA.pdfDR PROF ING GURUDUTT SAHNI WIKIPEDIA.pdf
DR PROF ING GURUDUTT SAHNI WIKIPEDIA.pdfDrGurudutt
 
E-Commerce Shopping using MERN Stack where different modules are present
E-Commerce Shopping using MERN Stack where different modules are presentE-Commerce Shopping using MERN Stack where different modules are present
E-Commerce Shopping using MERN Stack where different modules are presentjatinraor66
 
Intelligent Agents, A discovery on How A Rational Agent Acts
Intelligent Agents, A discovery on How A Rational Agent ActsIntelligent Agents, A discovery on How A Rational Agent Acts
Intelligent Agents, A discovery on How A Rational Agent ActsSheetal Jain
 
Lab Manual Arduino UNO Microcontrollar.docx
Lab Manual Arduino UNO Microcontrollar.docxLab Manual Arduino UNO Microcontrollar.docx
Lab Manual Arduino UNO Microcontrollar.docxRashidFaridChishti
 
SLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptxSLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptxCHAIRMAN M
 
Research Methodolgy & Intellectual Property Rights Series 2
Research Methodolgy & Intellectual Property Rights Series 2Research Methodolgy & Intellectual Property Rights Series 2
Research Methodolgy & Intellectual Property Rights Series 2T.D. Shashikala
 
Electrical shop management system project report.pdf
Electrical shop management system project report.pdfElectrical shop management system project report.pdf
Electrical shop management system project report.pdfKamal Acharya
 
ChatGPT Prompt Engineering for project managers.pdf
ChatGPT Prompt Engineering for project managers.pdfChatGPT Prompt Engineering for project managers.pdf
ChatGPT Prompt Engineering for project managers.pdfqasastareekh
 
Circuit Breaker arc phenomenon.pdf engineering
Circuit Breaker arc phenomenon.pdf engineeringCircuit Breaker arc phenomenon.pdf engineering
Circuit Breaker arc phenomenon.pdf engineeringKanchhaTamang
 
ALCOHOL PRODUCTION- Beer Brewing Process.pdf
ALCOHOL PRODUCTION- Beer Brewing Process.pdfALCOHOL PRODUCTION- Beer Brewing Process.pdf
ALCOHOL PRODUCTION- Beer Brewing Process.pdfMadan Karki
 
Electrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission lineElectrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission lineJulioCesarSalazarHer1
 
Artificial Intelligence Bayesian Reasoning
Artificial Intelligence Bayesian ReasoningArtificial Intelligence Bayesian Reasoning
Artificial Intelligence Bayesian Reasoninghotman30312
 
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...Roi Lipman
 

Dernier (20)

Lesson no16 application of Induction Generator in Wind.ppsx
Lesson no16 application of Induction Generator in Wind.ppsxLesson no16 application of Induction Generator in Wind.ppsx
Lesson no16 application of Induction Generator in Wind.ppsx
 
Operating System chapter 9 (Virtual Memory)
Operating System chapter 9 (Virtual Memory)Operating System chapter 9 (Virtual Memory)
Operating System chapter 9 (Virtual Memory)
 
Attraction and Repulsion type Moving Iron Instruments.pptx
Attraction and Repulsion type Moving Iron Instruments.pptxAttraction and Repulsion type Moving Iron Instruments.pptx
Attraction and Repulsion type Moving Iron Instruments.pptx
 
Software Engineering - Modelling Concepts + Class Modelling + Building the An...
Software Engineering - Modelling Concepts + Class Modelling + Building the An...Software Engineering - Modelling Concepts + Class Modelling + Building the An...
Software Engineering - Modelling Concepts + Class Modelling + Building the An...
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
 
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdfInvolute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
 
Multivibrator and its types defination and usges.pptx
Multivibrator and its types defination and usges.pptxMultivibrator and its types defination and usges.pptx
Multivibrator and its types defination and usges.pptx
 
DR PROF ING GURUDUTT SAHNI WIKIPEDIA.pdf
DR PROF ING GURUDUTT SAHNI WIKIPEDIA.pdfDR PROF ING GURUDUTT SAHNI WIKIPEDIA.pdf
DR PROF ING GURUDUTT SAHNI WIKIPEDIA.pdf
 
E-Commerce Shopping using MERN Stack where different modules are present
E-Commerce Shopping using MERN Stack where different modules are presentE-Commerce Shopping using MERN Stack where different modules are present
E-Commerce Shopping using MERN Stack where different modules are present
 
Intelligent Agents, A discovery on How A Rational Agent Acts
Intelligent Agents, A discovery on How A Rational Agent ActsIntelligent Agents, A discovery on How A Rational Agent Acts
Intelligent Agents, A discovery on How A Rational Agent Acts
 
Lab Manual Arduino UNO Microcontrollar.docx
Lab Manual Arduino UNO Microcontrollar.docxLab Manual Arduino UNO Microcontrollar.docx
Lab Manual Arduino UNO Microcontrollar.docx
 
SLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptxSLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptx
 
Research Methodolgy & Intellectual Property Rights Series 2
Research Methodolgy & Intellectual Property Rights Series 2Research Methodolgy & Intellectual Property Rights Series 2
Research Methodolgy & Intellectual Property Rights Series 2
 
Electrical shop management system project report.pdf
Electrical shop management system project report.pdfElectrical shop management system project report.pdf
Electrical shop management system project report.pdf
 
ChatGPT Prompt Engineering for project managers.pdf
ChatGPT Prompt Engineering for project managers.pdfChatGPT Prompt Engineering for project managers.pdf
ChatGPT Prompt Engineering for project managers.pdf
 
Circuit Breaker arc phenomenon.pdf engineering
Circuit Breaker arc phenomenon.pdf engineeringCircuit Breaker arc phenomenon.pdf engineering
Circuit Breaker arc phenomenon.pdf engineering
 
ALCOHOL PRODUCTION- Beer Brewing Process.pdf
ALCOHOL PRODUCTION- Beer Brewing Process.pdfALCOHOL PRODUCTION- Beer Brewing Process.pdf
ALCOHOL PRODUCTION- Beer Brewing Process.pdf
 
Electrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission lineElectrostatic field in a coaxial transmission line
Electrostatic field in a coaxial transmission line
 
Artificial Intelligence Bayesian Reasoning
Artificial Intelligence Bayesian ReasoningArtificial Intelligence Bayesian Reasoning
Artificial Intelligence Bayesian Reasoning
 
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
The battle for RAG, explore the pros and cons of using KnowledgeGraphs and Ve...
 

Lect 3_Procurement of Raw materials & MRP.pptx

  • 1.
  • 2. Supply Chain Management (MS-409) Lecture – 3 Supply Chain Management Drivers Procurement of Raw Materials and Material Requirement Planning Course Instructor: Dr. Ammar ul Hassan Email Id: amar.hassan@uettaxila.edu.pk Department of Mechanical Engineering, University of Engineering & Technology, Taxila
  • 3. Procurement of Raw Materials • Procurement in manufacturing sector refers to the method of purchase of raw materials from an external source. • Raw material procurement process involves researching, selecting, ordering, and paying for raw materials required for a business. • Identifying and selecting vendors, negotiating prices and terms, and awarding contracts are some steps in the procurement process. • Raw material selection involves several factors that includes cost, quality, availability, and delivery time.
  • 4. Procurement of Raw Materials • Raw material procurement is the process of identifying and acquiring the necessary materials to support production activities. • Materials may be purchased in bulk, such as commodities or manufactured goods, or they may be purchased separately, such as components or subassemblies.
  • 5. Procurement of Raw Materials • The role of raw material procurement is vital for profitability and overall success of a business. • In order to ensure a smooth supply chain management of raw materials, business can adopt strategies like building a distribution network, sourcing locally, etc. • Demand collection can prove to be highly beneficial in procurement for large businesses.
  • 6. Procurement of Raw Materials
  • 7. Procurement of Raw Materials • The material procurement process consists of seven main process steps. • The key steps in the procurement of raw materials include the following:
  • 8. Procurement of Raw Materials 1.Need analysis • Assessing the need is the first crucial step in procurement where the company takes stock of the raw materials required from different teams and separate out the list depending on the priority of the needs. • At this stage, the team handling procurement also determines the best way to procure raw materials in terms of cost saving and logistics.
  • 9. Procurement of Raw Materials 2.Contract negotiation and approval • Once the list of procurement is decided, the procurement department identifies vendors and requests for quotes. • At least three quotes are sourced as a practice, but it depends on the organization. • The vendor with the lowest quotation is selected and post approval of the quote, the raw materials are transported to the manufacturing units.
  • 10. Procurement of Raw Materials 3.Purchase requisition • Once the list of procurement is decided, the procurement team seeks approval for the purchase. • They also cross verify the list with different teams and the raw materials are approved as per their operational priority.
  • 11. Procurement of Raw Materials 4.Purchase order review • Prior to the final approval of the order, the senior procurement manager does one final review before approval. • Once the approval is obtained from the procurement manager, the list is sent to the accounts department.
  • 12. Procurement of Raw Materials 5.Funds for raw materials are verified • Based on the list, the accounts department issues a purchase order to the vendor and releases the funds. • That purchase order is an indication to the vendor that the request has been approved and that they can proceed with the request.
  • 13. Procurement of Raw Materials 6. Shipping of raw materials • While in selected cases, the vendors arrange for the transportation of raw materials, it does not always happen in the case of all suppliers. • In most cases, businesses need to arrange for their own transportation to transfer the raw materials from suppliers to the manufacturing units.
  • 14. Procurement of Raw Materials 7.Invoice approval and payment • Once the raw materials reach the manufacturing unit, the products are cross verified against the bill and the invoice is approved and the payment is transferred to the suppliers.
  • 15. Procurement of Raw Materials Procurement of raw Materials Strategies • Source locally • Build a list of locally sources • Increase inventory • Connect with a distributor
  • 16. Classification of Engineering materials Most of the Engineering materials can be classified into main following categories : 1. Metallic materials (Metals, Non-metals) 2. Polymeric materials 3. Ceramic materials 4. Composite materials 5. Electronic materials 6. Advance materials
  • 17. Classification, cont. • Metals • Steel, Cast Iron, Aluminum, Copper, Titanium, many others • Ceramics • Glass, Concrete, Brick, Alumina, Zirconia, SiN, SiC • Polymers • Plastics, Wood, Cotton (rayon, nylon), “glue” • Composites • Glass Fiber-reinforced polymers, Carbon Fiber- reinforced polymers, Metal Matrix Composites, etc.
  • 18. Material Requirement Planning • Material requirements planning (MRP) is a system for calculating the materials and components needed to manufacture a product. • MRP helps to develop a production plan for finished goods by defining inventory requirements for components and raw materials.
  • 19. Material Requirement Planning • MRP system determines item by item, what is to be processed and when, as well as what is to be manufactured when. • This is based on order priorities and available capacities.
  • 20. Material Requirement Planning • MRP consists of three primary steps: i. taking inventory of the materials and components on hand, ii. identifying which additional ones are needed and iii. then scheduling their production or purchase
  • 21.
  • 22. Overview of MRP System
  • 23.
  • 24. Product Structure File BOM • A bill of materials (BOM) is a comprehensive inventory of the raw materials, assemblies, subassemblies, parts and components, as well as the quantities of each needed to manufacture a product. • It is the complete list of all the items that are required to build a product. • BOMs also include the instructions for procuring and using the materials.
  • 25.
  • 26. Master production Schedule • As the name implies, a master production schedule determines what products are manufactured, when they are produced, and in what quantities. • The required raw materials are identified by the finished goods BOM, the data from which is integrated with current inventory data to create the MRP for raw materials procurement
  • 27.
  • 28.
  • 29.
  • 30.
  • 31.
  • 32.
  • 33. MRP Example 1 Compute the MRP plan for the Item x shown below. Note that the item has an independent demand that requires a safety stock of 40 units to be maintained. Order Quantity = 70 Lead Time = 4 weeks Safety Stock = 40 Weeks 1 2 3 4 5 6 7 8 9 10 11 12 Project requirement 20 20 25 20 20 25 20 20 30 25 25 25 Schedule Receipts 70 On hand at the end of period 65 Planned order released
  • 34. MRP Example Solution: Order Quantity = 70 Lead Time = 4 weeks Safety Stock = 40 Weeks 1 2 3 4 5 6 7 8 9 10 11 12 Project requirement 20 20 25 20 20 25 20 20 30 25 25 25 Schedule Receipts 70 70 70 70 On hand at the end of period 65 45 95 25 70 50 100 30 75 55 105 35 75 50 95 25 70 Planned order released 70 70 70
  • 35. MRP Example 2 Compute the MRP plan for the component shown below. Use lot size of 60 and lead time of 1 week and a safety stock of 10 units to be maintained. Order Quantity = 60 Lead Time = 1 week Safety Stock = 10 Weeks 1 2 3 4 5 6 7 8 Gross requirement 60 140 30 130 Schedule Receipts 50 50 50 On hand at the end of period 20 Planned order released
  • 36. MRP Example 2 Solution: Order Quantity = 60 Lead Time = 1 week Safety Stock = 10 Weeks 1 2 3 4 5 6 7 8 Gross requirement 60 140 30 130 Schedule Receipts 50 50 60 60 60 50 60 On hand at the end of period 20 70 70 60 10 120 60 40 180 70 10 50 180 50 Planned order released 60 60 60 60