Probable Maximum Loss Evaluation
Probable Maximum Loss (PML)
What is:
An estimate of the maximum loss which could be sustained by the insurers as a result of
any one occurrence considered by the underwriter to be within the realms of probability.
Objective:
To support the decision about how much of a risk they the underwriters can retain, and whether they need to
purchase reinsurance for their share of that risk.
When applied:
For construction projects, PML assessments are normally made for four covers provided:
• Contractors All Risks cover
• Existing Structures cover
• Non-Negligent Damage cover
• Advance Loss of Profits cover
BRG´s PML structured evaluation
process
The method is quantitative and BRG uses a structured PML evaluation process based on expert opinion.
This method is employed because BRG´s experts know that constructs have unique, where historical data is not
always available, and dynamic, because the configuration of the site changes as the physical progress of the
construction changes, conditions in case of accidents occur:
• The nature and extent of damage is often difficult to predict:
No examples of previous, similar failures or events to use as a
guide
• The cost of repairing damage is often difficult to predict:
o The cost of building something for the first time is an
estimate.
o The actions required to rectify damage can sometimes
bear no similarity to the work that was done to build the
thing that has been damaged. This makes estimating
costs even more difficult.
• The conditions that will operate to create the event that will
produce the PML scenario loss are not evident at the
underwriting stage, or even when Risk Engineering surveys are
carried out, and so are not capable of evaluation by direct
inspection.
Source: AACE - Recommended Practice No. 18R-97
BRG´s PML structured evaluation
process
Information
Collection
• Geographical situation
• Map
• Plot Plan and project areas´ layouts
• Construction Plan
• Commissioning Plan
• Schedule
• Contracting packages
• Construction utilities, storage, etc.
• Traffic data
• Climate data
• Specs
• Physical and Chemical data of construction materials, feeds, fuel, etc.
Target Risks and
PML Scenarios
specification
Base-value at risk
definition
Consequence
analysis
BRG´s PML structured evaluation
process
Information
Collection
Target Risk is most easily defined as that part of the insured property that is
judged to be at risk of damage in the loss scenario being considered.
Constructions have a number of characteristics that should be considered
in the definition of the target risk:
• Scaffolding on the outside face of buildings
• Temporary buildings placed between buildings being worked on
• Storage of combustible materials, combustible waste, plant, fuel/oil, gas
bottles etc. in the gaps between buildings
• Combustible materials incorporated in fixtures and fittings installed during
erection stage
• Buildings with high inherent fire loads – e.g. timber-framed buildings
• Existence of common basements beneath groups of buildings, etc.
Target Risks and
PML Scenarios
specification
Base-value at risk
definition
Consequence
analysis
Input: Collected information, BRG´s construction expert judgment
Output: Target Risks Register, Set of PML Scenarios
Examples:
• Belt fire in belt conveyor hot commissioning tests
• Fire welding in the final erection of the mill building´s metallic structure
BRG´s PML structured evaluation
process
Information
Collection
Analysis of the cost of construction for the areas and structures involved in
the set of specified PML scenarios.
BRG's construction experts have the experience and knowledge to
identify the plots that are or are not subject to the target risk specified,
considering only the construction cost of the affected plots and consider cost
estimates related to damages recovery actions for the Target Risk specified.
The experts also consider the possibility of the construction costs growth
for each area involved in the PML scenario specified as a function of the
precision associated with the estimation method and the advance of the
engineering project.
Target Risks and
PML Scenarios
specification
Base-value at risk
definition
Consequence
analysis
Input: Project´s Cost Breakdown Structure (CBS), costed Bill of Quantities
Output: Base-value cost of the Target Risk = Largest possible loss that can
be incurred from the Target Risk
BRG´s PML structured evaluation
process
Information
Collection
Assessment of the likely extent of damage (% of base-value) for the Target
Risk and PML Scenario specified
Given the PML scenario, the BRG´s estimate of extent of damage uses factors
that consider:
• Proximity and isolation between adjacent constructions
• Height of buildings
• Materials involved
• Contractor´s H&S practices and site control: compliance with regulations and
procedures, material storage, electrical installations, etc.
• Level of passive fire protection
• Structure and response of the fire brigade and fire-fighting water supplies
• Etc.
Target Risks and
PML Scenarios
specification
Base-value at risk
definition
Consequence
analysis
Input: Target Risks Register, Set of PML Scenarios, Base-value cost of the
Target Risk
Assessment Output: Material damage PML = Base-value cost adjusted
downwards to become the largest probable loss for the Target Risk
Final PML = Material damage PML, which Underwriters then amend by adding
other costs (debris removal, inflation, price escalation, etc.), as determined by
the applicable insurance policy.
Contact information
cgraeff@thinkbrg.com
+55 11 94550-3892
www.thinkbrg.com
www.linkedin.com/company/berkeley-research-group-llc
Berkeley Research Group
THINK TANK

Contenu connexe

Tendances

Industrial Accident, Safety and Health
Industrial Accident, Safety and HealthIndustrial Accident, Safety and Health
Industrial Accident, Safety and Health
Mainak Ghosh
 
Near miss awareness for petroleum oil refinery
Near miss awareness  for petroleum oil refineryNear miss awareness  for petroleum oil refinery
Near miss awareness for petroleum oil refinery
ASHOK KUMAR SINGH
 
Risk Assessment
Risk AssessmentRisk Assessment
Risk Assessment
RaviPrashant5
 
Pakistan industries and health hazards
Pakistan industries and health hazardsPakistan industries and health hazards
Pakistan industries and health hazards
Usman Dawood Barry
 
December -15 Daily Observation Report
December -15 Daily Observation ReportDecember -15 Daily Observation Report
December -15 Daily Observation Report
Mohammed Mubasheeruddin
 
Risk assessment presentation
Risk assessment presentationRisk assessment presentation
Risk assessment presentation
mmagario
 
Fukushima nuclear disaster in japan
Fukushima nuclear disaster in japan Fukushima nuclear disaster in japan
Fukushima nuclear disaster in japan
Mahendra Poudel
 
Risk Assessment and Management
Risk Assessment and ManagementRisk Assessment and Management
Risk Assessment and Management
Haythem A. El-Wassif
 
Occupational Safety And Health
Occupational Safety And HealthOccupational Safety And Health
Occupational Safety And Health
Bhawna Gupta
 
Electrical Safety by Industrial Safety Institute
Electrical Safety by Industrial Safety InstituteElectrical Safety by Industrial Safety Institute
Electrical Safety by Industrial Safety Institute
Atlantic Training, LLC.
 
Risk assessment
Risk assessmentRisk assessment
Risk assessment
Shehnaz Alam
 
Electrical Risk Management
Electrical Risk ManagementElectrical Risk Management
Electrical Risk Management
guest81e1c7
 
Disaster management basic concepts
Disaster management basic concepts Disaster management basic concepts
Disaster management basic concepts
PREM N. MISHRA
 
Disaster management
Disaster managementDisaster management
Environmental Disasters
Environmental DisastersEnvironmental Disasters
Environmental Disasters
GAURAV. H .TANDON
 
Contractors all risk insurance
Contractors all risk insuranceContractors all risk insurance
Contractors all risk insurance
Salum Mlaponi-Dip CII
 
Incident investigation
Incident investigationIncident investigation
Incident investigation
aufumy
 
Risks Associated to Combustible Dust Handling
Risks Associated to Combustible Dust Handling Risks Associated to Combustible Dust Handling
Risks Associated to Combustible Dust Handling
Atlantic Training, LLC.
 
The Keys to Unlocking Safety Culture
The Keys to Unlocking Safety CultureThe Keys to Unlocking Safety Culture
The Keys to Unlocking Safety Culture
Medgate Inc.
 
Environmental Disaster
Environmental DisasterEnvironmental Disaster
Environmental Disaster
VivekPrasad64
 

Tendances (20)

Industrial Accident, Safety and Health
Industrial Accident, Safety and HealthIndustrial Accident, Safety and Health
Industrial Accident, Safety and Health
 
Near miss awareness for petroleum oil refinery
Near miss awareness  for petroleum oil refineryNear miss awareness  for petroleum oil refinery
Near miss awareness for petroleum oil refinery
 
Risk Assessment
Risk AssessmentRisk Assessment
Risk Assessment
 
Pakistan industries and health hazards
Pakistan industries and health hazardsPakistan industries and health hazards
Pakistan industries and health hazards
 
December -15 Daily Observation Report
December -15 Daily Observation ReportDecember -15 Daily Observation Report
December -15 Daily Observation Report
 
Risk assessment presentation
Risk assessment presentationRisk assessment presentation
Risk assessment presentation
 
Fukushima nuclear disaster in japan
Fukushima nuclear disaster in japan Fukushima nuclear disaster in japan
Fukushima nuclear disaster in japan
 
Risk Assessment and Management
Risk Assessment and ManagementRisk Assessment and Management
Risk Assessment and Management
 
Occupational Safety And Health
Occupational Safety And HealthOccupational Safety And Health
Occupational Safety And Health
 
Electrical Safety by Industrial Safety Institute
Electrical Safety by Industrial Safety InstituteElectrical Safety by Industrial Safety Institute
Electrical Safety by Industrial Safety Institute
 
Risk assessment
Risk assessmentRisk assessment
Risk assessment
 
Electrical Risk Management
Electrical Risk ManagementElectrical Risk Management
Electrical Risk Management
 
Disaster management basic concepts
Disaster management basic concepts Disaster management basic concepts
Disaster management basic concepts
 
Disaster management
Disaster managementDisaster management
Disaster management
 
Environmental Disasters
Environmental DisastersEnvironmental Disasters
Environmental Disasters
 
Contractors all risk insurance
Contractors all risk insuranceContractors all risk insurance
Contractors all risk insurance
 
Incident investigation
Incident investigationIncident investigation
Incident investigation
 
Risks Associated to Combustible Dust Handling
Risks Associated to Combustible Dust Handling Risks Associated to Combustible Dust Handling
Risks Associated to Combustible Dust Handling
 
The Keys to Unlocking Safety Culture
The Keys to Unlocking Safety CultureThe Keys to Unlocking Safety Culture
The Keys to Unlocking Safety Culture
 
Environmental Disaster
Environmental DisasterEnvironmental Disaster
Environmental Disaster
 

Similaire à Probable Maximum Loss (PML) Evaluation

SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
Ar Naveen Naveen
 
Ddg architecture
Ddg architectureDdg architecture
Ddg architecture
Eelyn Cheong
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
Pankaj K Sinha
 
Pmc hitesh
Pmc hiteshPmc hitesh
Pmc hitesh
Hitesh Sunny
 
Modified Risk Analysis Model APRAM
Modified Risk Analysis Model APRAMModified Risk Analysis Model APRAM
Modified Risk Analysis Model APRAM
nadeemovic
 
Capital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectCapital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of Project
ArvinThamsir1
 
Capital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .pptCapital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .ppt
ArvinThamsir1
 
Project Cost Management for IEM talk on 13 January 2018.
Project Cost Management  for IEM talk on 13 January 2018.Project Cost Management  for IEM talk on 13 January 2018.
Project Cost Management for IEM talk on 13 January 2018.
Ir.Noor Iziddin,PMP, P.Eng,REEM,CCPM,TTT.
 
17 mse003 pv plant devlopement
17 mse003 pv plant devlopement17 mse003 pv plant devlopement
17 mse003 pv plant devlopement
paneliya sagar
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project delivery
MECandPMV
 
Total-Project-Cost.pptx
Total-Project-Cost.pptxTotal-Project-Cost.pptx
Total-Project-Cost.pptx
MaryqueenieVillaflor
 
lecture ppt for contract administration and governing
lecture ppt for contract administration and governinglecture ppt for contract administration and governing
lecture ppt for contract administration and governing
2cd
 
CPM 1 .pdf
CPM 1 .pdfCPM 1 .pdf
CPM 1 .pdf
MD RUKHASAR ALAM
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
HASMANIRA
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
HASMANIRA
 
Estimation
EstimationEstimation
Estimation
Khaled Eid
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf
JunaidMughal34
 
Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...
Amir Mohammed
 
PROJECT RISK MANAGEMENT
PROJECT  RISK  MANAGEMENTPROJECT  RISK  MANAGEMENT
PROJECT RISK MANAGEMENT
Neenu Babu
 
Ensuring Safety and Compliance with 3D Laser Scanning in Construction Site In...
Ensuring Safety and Compliance with 3D Laser Scanning in Construction Site In...Ensuring Safety and Compliance with 3D Laser Scanning in Construction Site In...
Ensuring Safety and Compliance with 3D Laser Scanning in Construction Site In...
Michael William
 

Similaire à Probable Maximum Loss (PML) Evaluation (20)

SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
Ddg architecture
Ddg architectureDdg architecture
Ddg architecture
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
 
Pmc hitesh
Pmc hiteshPmc hitesh
Pmc hitesh
 
Modified Risk Analysis Model APRAM
Modified Risk Analysis Model APRAMModified Risk Analysis Model APRAM
Modified Risk Analysis Model APRAM
 
Capital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectCapital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of Project
 
Capital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .pptCapital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .ppt
 
Project Cost Management for IEM talk on 13 January 2018.
Project Cost Management  for IEM talk on 13 January 2018.Project Cost Management  for IEM talk on 13 January 2018.
Project Cost Management for IEM talk on 13 January 2018.
 
17 mse003 pv plant devlopement
17 mse003 pv plant devlopement17 mse003 pv plant devlopement
17 mse003 pv plant devlopement
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project delivery
 
Total-Project-Cost.pptx
Total-Project-Cost.pptxTotal-Project-Cost.pptx
Total-Project-Cost.pptx
 
lecture ppt for contract administration and governing
lecture ppt for contract administration and governinglecture ppt for contract administration and governing
lecture ppt for contract administration and governing
 
CPM 1 .pdf
CPM 1 .pdfCPM 1 .pdf
CPM 1 .pdf
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
 
Estimation
EstimationEstimation
Estimation
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf
 
Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...Curriculum vitae of civil engineer for construction manager or Sr. project en...
Curriculum vitae of civil engineer for construction manager or Sr. project en...
 
PROJECT RISK MANAGEMENT
PROJECT  RISK  MANAGEMENTPROJECT  RISK  MANAGEMENT
PROJECT RISK MANAGEMENT
 
Ensuring Safety and Compliance with 3D Laser Scanning in Construction Site In...
Ensuring Safety and Compliance with 3D Laser Scanning in Construction Site In...Ensuring Safety and Compliance with 3D Laser Scanning in Construction Site In...
Ensuring Safety and Compliance with 3D Laser Scanning in Construction Site In...
 

Plus de Tito Livio M. Cardoso

Tito Cardoso - Resumo - EN Junho-2023
Tito Cardoso - Resumo - EN Junho-2023Tito Cardoso - Resumo - EN Junho-2023
Tito Cardoso - Resumo - EN Junho-2023
Tito Livio M. Cardoso
 
Tito Cardoso - Resumo - PT Junho-2023
Tito Cardoso - Resumo - PT Junho-2023Tito Cardoso - Resumo - PT Junho-2023
Tito Cardoso - Resumo - PT Junho-2023
Tito Livio M. Cardoso
 
Estimativa Parametrica de Custo de Transportador de Correia
Estimativa Parametrica de Custo de Transportador de CorreiaEstimativa Parametrica de Custo de Transportador de Correia
Estimativa Parametrica de Custo de Transportador de Correia
Tito Livio M. Cardoso
 
Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...
Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...
Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...
Tito Livio M. Cardoso
 
Analise de riscos das alternativas
Analise de riscos das alternativasAnalise de riscos das alternativas
Analise de riscos das alternativas
Tito Livio M. Cardoso
 
Certificado DIO Especialaista Inovação Digital AD0B801B.pdf
Certificado DIO Especialaista Inovação Digital AD0B801B.pdfCertificado DIO Especialaista Inovação Digital AD0B801B.pdf
Certificado DIO Especialaista Inovação Digital AD0B801B.pdf
Tito Livio M. Cardoso
 
Certificado DIO Front-End Angular 1E8E60C7.pdf
Certificado DIO Front-End Angular 1E8E60C7.pdfCertificado DIO Front-End Angular 1E8E60C7.pdf
Certificado DIO Front-End Angular 1E8E60C7.pdf
Tito Livio M. Cardoso
 
Certificado DIO Fullstack developer - Banco carrefour 7B553D75.pdf
Certificado DIO Fullstack developer - Banco carrefour 7B553D75.pdfCertificado DIO Fullstack developer - Banco carrefour 7B553D75.pdf
Certificado DIO Fullstack developer - Banco carrefour 7B553D75.pdf
Tito Livio M. Cardoso
 
Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...
Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...
Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...
Tito Livio M. Cardoso
 
DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...
DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...
DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...
Tito Livio M. Cardoso
 
Desenvolvimento de projetos em baixa das commodities
Desenvolvimento de projetos em baixa das commoditiesDesenvolvimento de projetos em baixa das commodities
Desenvolvimento de projetos em baixa das commodities
Tito Livio M. Cardoso
 
Riscos relacionadas a extensao de cronogramas - Schedule extension related risks
Riscos relacionadas a extensao de cronogramas - Schedule extension related risksRiscos relacionadas a extensao de cronogramas - Schedule extension related risks
Riscos relacionadas a extensao de cronogramas - Schedule extension related risks
Tito Livio M. Cardoso
 
Leasing de equipamentos industriais
Leasing de equipamentos industriaisLeasing de equipamentos industriais
Leasing de equipamentos industriais
Tito Livio M. Cardoso
 
Otimização da configuração do banco de baterias para navio híbrido
Otimização da configuração do banco de baterias para navio híbridoOtimização da configuração do banco de baterias para navio híbrido
Otimização da configuração do banco de baterias para navio híbrido
Tito Livio M. Cardoso
 
Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018
Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018
Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018
Tito Livio M. Cardoso
 
Estratégia de Autofinanciamento de Projetos
Estratégia de Autofinanciamento de ProjetosEstratégia de Autofinanciamento de Projetos
Estratégia de Autofinanciamento de Projetos
Tito Livio M. Cardoso
 
Critério de decisão para implantação da infraestrutura em projetos implantado...
Critério de decisão para implantação da infraestrutura em projetos implantado...Critério de decisão para implantação da infraestrutura em projetos implantado...
Critério de decisão para implantação da infraestrutura em projetos implantado...
Tito Livio M. Cardoso
 
Decision criterion for anticipation of the infrastructure in staged projects
Decision criterion for anticipation of the infrastructure in staged projectsDecision criterion for anticipation of the infrastructure in staged projects
Decision criterion for anticipation of the infrastructure in staged projects
Tito Livio M. Cardoso
 
Analise de riscos da aplicação de novas tecnologias
Analise de riscos da aplicação de novas tecnologiasAnalise de riscos da aplicação de novas tecnologias
Analise de riscos da aplicação de novas tecnologias
Tito Livio M. Cardoso
 
Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...
Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...
Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...
Tito Livio M. Cardoso
 

Plus de Tito Livio M. Cardoso (20)

Tito Cardoso - Resumo - EN Junho-2023
Tito Cardoso - Resumo - EN Junho-2023Tito Cardoso - Resumo - EN Junho-2023
Tito Cardoso - Resumo - EN Junho-2023
 
Tito Cardoso - Resumo - PT Junho-2023
Tito Cardoso - Resumo - PT Junho-2023Tito Cardoso - Resumo - PT Junho-2023
Tito Cardoso - Resumo - PT Junho-2023
 
Estimativa Parametrica de Custo de Transportador de Correia
Estimativa Parametrica de Custo de Transportador de CorreiaEstimativa Parametrica de Custo de Transportador de Correia
Estimativa Parametrica de Custo de Transportador de Correia
 
Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...
Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...
Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...
 
Analise de riscos das alternativas
Analise de riscos das alternativasAnalise de riscos das alternativas
Analise de riscos das alternativas
 
Certificado DIO Especialaista Inovação Digital AD0B801B.pdf
Certificado DIO Especialaista Inovação Digital AD0B801B.pdfCertificado DIO Especialaista Inovação Digital AD0B801B.pdf
Certificado DIO Especialaista Inovação Digital AD0B801B.pdf
 
Certificado DIO Front-End Angular 1E8E60C7.pdf
Certificado DIO Front-End Angular 1E8E60C7.pdfCertificado DIO Front-End Angular 1E8E60C7.pdf
Certificado DIO Front-End Angular 1E8E60C7.pdf
 
Certificado DIO Fullstack developer - Banco carrefour 7B553D75.pdf
Certificado DIO Fullstack developer - Banco carrefour 7B553D75.pdfCertificado DIO Fullstack developer - Banco carrefour 7B553D75.pdf
Certificado DIO Fullstack developer - Banco carrefour 7B553D75.pdf
 
Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...
Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...
Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...
 
DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...
DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...
DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...
 
Desenvolvimento de projetos em baixa das commodities
Desenvolvimento de projetos em baixa das commoditiesDesenvolvimento de projetos em baixa das commodities
Desenvolvimento de projetos em baixa das commodities
 
Riscos relacionadas a extensao de cronogramas - Schedule extension related risks
Riscos relacionadas a extensao de cronogramas - Schedule extension related risksRiscos relacionadas a extensao de cronogramas - Schedule extension related risks
Riscos relacionadas a extensao de cronogramas - Schedule extension related risks
 
Leasing de equipamentos industriais
Leasing de equipamentos industriaisLeasing de equipamentos industriais
Leasing de equipamentos industriais
 
Otimização da configuração do banco de baterias para navio híbrido
Otimização da configuração do banco de baterias para navio híbridoOtimização da configuração do banco de baterias para navio híbrido
Otimização da configuração do banco de baterias para navio híbrido
 
Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018
Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018
Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018
 
Estratégia de Autofinanciamento de Projetos
Estratégia de Autofinanciamento de ProjetosEstratégia de Autofinanciamento de Projetos
Estratégia de Autofinanciamento de Projetos
 
Critério de decisão para implantação da infraestrutura em projetos implantado...
Critério de decisão para implantação da infraestrutura em projetos implantado...Critério de decisão para implantação da infraestrutura em projetos implantado...
Critério de decisão para implantação da infraestrutura em projetos implantado...
 
Decision criterion for anticipation of the infrastructure in staged projects
Decision criterion for anticipation of the infrastructure in staged projectsDecision criterion for anticipation of the infrastructure in staged projects
Decision criterion for anticipation of the infrastructure in staged projects
 
Analise de riscos da aplicação de novas tecnologias
Analise de riscos da aplicação de novas tecnologiasAnalise de riscos da aplicação de novas tecnologias
Analise de riscos da aplicação de novas tecnologias
 
Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...
Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...
Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...
 

Dernier

Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
LAXMAREDDY22
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Seminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptxSeminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptx
Madan Karki
 
Introduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptxIntroduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptx
MiscAnnoy1
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
john krisinger-the science and history of the alcoholic beverage.pptx
john krisinger-the science and history of the alcoholic beverage.pptxjohn krisinger-the science and history of the alcoholic beverage.pptx
john krisinger-the science and history of the alcoholic beverage.pptx
Madan Karki
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
TaghreedAltamimi
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
Nada Hikmah
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
Mahmoud Morsy
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
architagupta876
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 

Dernier (20)

Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Seminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptxSeminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptx
 
Introduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptxIntroduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptx
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
john krisinger-the science and history of the alcoholic beverage.pptx
john krisinger-the science and history of the alcoholic beverage.pptxjohn krisinger-the science and history of the alcoholic beverage.pptx
john krisinger-the science and history of the alcoholic beverage.pptx
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 

Probable Maximum Loss (PML) Evaluation

  • 1. BRG | Construction Probable Maximum Loss Evaluation
  • 2. Probable Maximum Loss (PML) What is: An estimate of the maximum loss which could be sustained by the insurers as a result of any one occurrence considered by the underwriter to be within the realms of probability. Objective: To support the decision about how much of a risk they the underwriters can retain, and whether they need to purchase reinsurance for their share of that risk. When applied: For construction projects, PML assessments are normally made for four covers provided: • Contractors All Risks cover • Existing Structures cover • Non-Negligent Damage cover • Advance Loss of Profits cover
  • 3. BRG´s PML structured evaluation process The method is quantitative and BRG uses a structured PML evaluation process based on expert opinion. This method is employed because BRG´s experts know that constructs have unique, where historical data is not always available, and dynamic, because the configuration of the site changes as the physical progress of the construction changes, conditions in case of accidents occur: • The nature and extent of damage is often difficult to predict: No examples of previous, similar failures or events to use as a guide • The cost of repairing damage is often difficult to predict: o The cost of building something for the first time is an estimate. o The actions required to rectify damage can sometimes bear no similarity to the work that was done to build the thing that has been damaged. This makes estimating costs even more difficult. • The conditions that will operate to create the event that will produce the PML scenario loss are not evident at the underwriting stage, or even when Risk Engineering surveys are carried out, and so are not capable of evaluation by direct inspection. Source: AACE - Recommended Practice No. 18R-97
  • 4. BRG´s PML structured evaluation process Information Collection • Geographical situation • Map • Plot Plan and project areas´ layouts • Construction Plan • Commissioning Plan • Schedule • Contracting packages • Construction utilities, storage, etc. • Traffic data • Climate data • Specs • Physical and Chemical data of construction materials, feeds, fuel, etc. Target Risks and PML Scenarios specification Base-value at risk definition Consequence analysis
  • 5. BRG´s PML structured evaluation process Information Collection Target Risk is most easily defined as that part of the insured property that is judged to be at risk of damage in the loss scenario being considered. Constructions have a number of characteristics that should be considered in the definition of the target risk: • Scaffolding on the outside face of buildings • Temporary buildings placed between buildings being worked on • Storage of combustible materials, combustible waste, plant, fuel/oil, gas bottles etc. in the gaps between buildings • Combustible materials incorporated in fixtures and fittings installed during erection stage • Buildings with high inherent fire loads – e.g. timber-framed buildings • Existence of common basements beneath groups of buildings, etc. Target Risks and PML Scenarios specification Base-value at risk definition Consequence analysis Input: Collected information, BRG´s construction expert judgment Output: Target Risks Register, Set of PML Scenarios Examples: • Belt fire in belt conveyor hot commissioning tests • Fire welding in the final erection of the mill building´s metallic structure
  • 6. BRG´s PML structured evaluation process Information Collection Analysis of the cost of construction for the areas and structures involved in the set of specified PML scenarios. BRG's construction experts have the experience and knowledge to identify the plots that are or are not subject to the target risk specified, considering only the construction cost of the affected plots and consider cost estimates related to damages recovery actions for the Target Risk specified. The experts also consider the possibility of the construction costs growth for each area involved in the PML scenario specified as a function of the precision associated with the estimation method and the advance of the engineering project. Target Risks and PML Scenarios specification Base-value at risk definition Consequence analysis Input: Project´s Cost Breakdown Structure (CBS), costed Bill of Quantities Output: Base-value cost of the Target Risk = Largest possible loss that can be incurred from the Target Risk
  • 7. BRG´s PML structured evaluation process Information Collection Assessment of the likely extent of damage (% of base-value) for the Target Risk and PML Scenario specified Given the PML scenario, the BRG´s estimate of extent of damage uses factors that consider: • Proximity and isolation between adjacent constructions • Height of buildings • Materials involved • Contractor´s H&S practices and site control: compliance with regulations and procedures, material storage, electrical installations, etc. • Level of passive fire protection • Structure and response of the fire brigade and fire-fighting water supplies • Etc. Target Risks and PML Scenarios specification Base-value at risk definition Consequence analysis Input: Target Risks Register, Set of PML Scenarios, Base-value cost of the Target Risk Assessment Output: Material damage PML = Base-value cost adjusted downwards to become the largest probable loss for the Target Risk Final PML = Material damage PML, which Underwriters then amend by adding other costs (debris removal, inflation, price escalation, etc.), as determined by the applicable insurance policy.
  • 8. Contact information cgraeff@thinkbrg.com +55 11 94550-3892 www.thinkbrg.com www.linkedin.com/company/berkeley-research-group-llc Berkeley Research Group THINK TANK