SlideShare une entreprise Scribd logo
1  sur  25
Creating a Task List SUST-CSIT Ahmed Hamza
Objective Enter task information. Estimate and enter how long each task should last. Create a milestone to track an important event. Organize tasks into phases. Create task relationships by linking tasks. Record task details in notes and insert a hyperlink to content on the Internet. Check a project plan’s overall duration. SUST-CSIT Ahmed Hamza
Entering Tasks Tasks are the most basic building blocks of any project-tasks Tasks describe project work in terms of sequence, duration, and resource requirements SUST-CSIT Ahmed Hamza
How to Enter Task In the first cell directly below the Task Name column heading, type Pre-Production, and then press  The task you entered is given an ID number. Each task has a unique ID number, but it does not necessarily represent the order in which tasks occur. Project assigns a duration of one day to the new task the question mark indicates that this is an estimated duration By default, the task start date is the same as the project start date SUST-CSIT Ahmed Hamza
Cont>> Enter the following task names below the Pre-Production task name, pressing after Entereach task name Develop script Develop production boards Pick locations Hold auditions Production Rehearse Shoot video Log footage SUST-CSIT Ahmed Hamza
Every project has an ultimate goal or intent: the reason that the project was started. This is called the project deliverable. This deliverable is usually a product Defining the right tasks to create the right deliverable is an essential skill for a project manager The task lists you create in Project should describe all of the work required, and only the work required, to complete the project successfully SUST-CSIT Ahmed Hamza  Project Management Focus: Defining the Right Tasks for the Right Deliverable
Estimating Durations A task’s duration is the amount of time you expect it will take to complete the task Project can work with task durations that range from minutes to months For example, a project might have a project calendar with working time defined as 8 A.M. through 5 P.M. with a one-hour lunch break Monday through Friday SUST-CSIT Ahmed Hamza
Cont>> you estimate that a task will take 16 hours of working time, you could enter its duration as 2d to schedule work over two eight-hour workdays. By starting the task at 8 A.M. on a Thursday, you should then expect that it wouldn’t be completed until 5 P.M. on the following Sunday. No work would be scheduled over the weekend because Friday and Saturday have been defined as nonworking time. SUST-CSIT Ahmed Hamza
Tip You determine the overall duration of a project by calculating the difference between the earliest start date and the latest finish date of the tasks that compose it. SUST-CSIT Ahmed Hamza
Cont>> Click the cell below the Duration column heading for task 2, Develop script. The Duration field for task 2 is selected.  Type 5d, and then press Enter The value 5 days appears in the Duration field. Enter the following durations for the remaining tasks. SUST-CSIT Ahmed Hamza
Cont>> SUST-CSIT Ahmed Hamza
You should consider two general rules when estimating task durations Overall project duration often correlates to task duration; long projects tend to have tasks with longer durations than do tasks in short projects If you track progress against your project plan you must consider the level of detail you want to apply to your project’s tasks. If you have a multi-year project, for example, it might not be practical or even possible to track tasks that are measured in minutes or hours SUST-CSIT Ahmed Hamza  How Do You Come Up with Accurate Task Durations?
For your real-world projects, you will often estimate task durations. Good sources of task duration estimates include: Historical information from previous, similar projects. Estimates from the people who will complete the tasks. Expert judgment of those who have managed similar projects. Standards of professional or industrial organizations that undertake projects similar to yours SUST-CSIT Ahmed Hamza  Cont>>
For complex projects, you probably would combine these and other sources to estimate task durations. Because inaccurate task duration estimates are a major source of risk in any project, making good estimates is well worth the effort expended SUST-CSIT Ahmed Hamza  Cont>>
Organizing Tasks into Phases It is helpful to organize groups of closely related tasks that represent a major portion of the project’s work into phases For example, it is common to divide a film or video project into major phases of work such as pre-production, production, and post-production In Project, phases are represented by summary tasks A summary task behaves differently from other tasks You can’t edit its duration, start date, or other calculated values directly because this information is derived or “rolled up” from the detail tasks SUST-CSIT Ahmed Hamza
The two most common approaches to developing tasks and phases are top-down and bottom-up planning. Top-down planning. Identifies major phases or products of the project before filling in the tasks required to complete those phases. Complex projects can have several layers of phases. This approach works from general to specific. Bottom-up planning. Identifies as many bottom-level detailed tasks as possible before organizing them into logical groups, called phases or summary tasks. This approach works from specific to general. SUST-CSIT Ahmed Hamza  Top-Down and Bottom-Up Planning
Cont>> create two summary tasks by indenting tasks Select the names of tasks 2 through 6. On the Project menu, point to Outline, and then click Indent Next, select the names of tasks 8 through 10. On the Project menu, point to Outline, and then click Indent. Task 7 becomes a summary task, and a summary task bar for it appears in the Gantt chart.  SUST-CSIT Ahmed Hamza
Linking Tasks Projects require tasks to be performed in a specific order If we have tow task that have a finish-to-start relationship (also called a link or dependency) that has two aspects: The second task must occur later than the first task; this is a sequence. The second task can occur only if the first task is completed; this is a dependency. SUST-CSIT Ahmed Hamza
Cont>> In Project, the first task (“film the scene”) is called the predecessor because it precedes tasks that depend on it. The second task (“edit the filmed scene”) is called the successor because it succeeds tasks on which it is dependent. Any task can be a predecessor for one or more successor tasks. Likewise, any task can be a successor to one or more predecessor tasks SUST-CSIT Ahmed Hamza
Cont>> You create task relationships by creating links between tasks First you’ll create a finish-to-start dependency between two tasks. Select the names of tasks 2 and 3. On the Edit menu, click Link Tasks. When working with summary tasks, you can either link summary tasks directly (as you did above) or link the latest task in the first phase with the earliest task in the second phase SUST-CSIT Ahmed Hamza
Cont>> You can also create a finish-to-start relationship between tasks right in the Gantt chart. Point to the task bar of the predecessor task until the pointer changes to a four-pointed star. Then, drag the mouse pointer up or down to the task bar of the successor task. While you’re dragging the mouse pointer to create a task SUST-CSIT Ahmed Hamza
Documenting Tasks You can record additional information about a task in a note There are three types of notes: task notes, resource notes, and assignment notes Select the name of task 4, Pick locations On the Project menu, click Task Notes. In the Notes box, type Includes exterior street scene and indoor studio scenes SUST-CSIT Ahmed Hamza
Checking the Plan’s Duration At this point, you might want to know how long the project is expected to take. You haven’t directly entered a total project duration or finish date, but Project has calculated these values based on individual task durations and task relationships An easy way to view the project’s scheduled finish date is via the Project Information dialog box. SUST-CSIT Ahmed Hamza
Cont>> On the Project menu, click Project Information SUST-CSIT Ahmed Hamza
Key Points Essential aspects of tasks in a project plan include their duration and order of occurrence. Task links, or relationships, cause the start or end of one task to affect the start or end of another task. A common task relationship is a finish-to-start relationship in which the completion of one task controls the start of another task. In Project, phases of a schedule are represented as summary tasks. You can document additional details using task notes and create hyperlinks to the Internet. The Project Information dialog box (Project menu) is an excellent way to observe the key values of a project plan, such as its scheduled finish date and duration. SUST-CSIT Ahmed Hamza

Contenu connexe

Tendances

2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)douggillis
 
Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016Rajeev Sharma
 
09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details09 Fine-tuning Assignment Details
09 Fine-tuning Assignment DetailsSoe Naing Win
 
Ms project working example
Ms project working exampleMs project working example
Ms project working exampleKushal Patel
 
MICROSOFT PROJECT
MICROSOFT PROJECTMICROSOFT PROJECT
MICROSOFT PROJECTSmit Patel
 
How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010Ong-Art Sanpinit
 
Ms project 2000 tutorial
Ms project 2000 tutorialMs project 2000 tutorial
Ms project 2000 tutorialpaolocollector
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iitKushal Patel
 
Ms project 2010 level 1&2
Ms project 2010 level 1&2 Ms project 2010 level 1&2
Ms project 2010 level 1&2 Rolf Kühnast
 
Microsoft® project painting exercise cpmgt303 version 111
Microsoft® project painting exercise cpmgt303 version 111Microsoft® project painting exercise cpmgt303 version 111
Microsoft® project painting exercise cpmgt303 version 111amit657720
 
10 Fine-tuning Project Plan
10 Fine-tuning Project Plan10 Fine-tuning Project Plan
10 Fine-tuning Project PlanSoe Naing Win
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project WorkshopEder Alves
 
Project management with ms project 2007
Project management with ms project 2007Project management with ms project 2007
Project management with ms project 2007Fasil Ayele
 
Project management by MS Project 2010
Project management by MS Project 2010Project management by MS Project 2010
Project management by MS Project 2010Wadhwani Foundation
 
Introduction to Primavera Reflections
Introduction to Primavera ReflectionsIntroduction to Primavera Reflections
Introduction to Primavera Reflectionsp6academy
 

Tendances (20)

Ms project lectures
Ms project lecturesMs project lectures
Ms project lectures
 
2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)
 
Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016
 
Microsoft project 2010
Microsoft project 2010Microsoft project 2010
Microsoft project 2010
 
09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details
 
Ms project working example
Ms project working exampleMs project working example
Ms project working example
 
MS Project
MS ProjectMS Project
MS Project
 
MICROSOFT PROJECT
MICROSOFT PROJECTMICROSOFT PROJECT
MICROSOFT PROJECT
 
MS Project
MS Project MS Project
MS Project
 
How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010
 
Ms project 2000 tutorial
Ms project 2000 tutorialMs project 2000 tutorial
Ms project 2000 tutorial
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iit
 
Ms project 2010 level 1&2
Ms project 2010 level 1&2 Ms project 2010 level 1&2
Ms project 2010 level 1&2
 
Microsoft® project painting exercise cpmgt303 version 111
Microsoft® project painting exercise cpmgt303 version 111Microsoft® project painting exercise cpmgt303 version 111
Microsoft® project painting exercise cpmgt303 version 111
 
10 Fine-tuning Project Plan
10 Fine-tuning Project Plan10 Fine-tuning Project Plan
10 Fine-tuning Project Plan
 
Omni plan 2-manual
Omni plan 2-manualOmni plan 2-manual
Omni plan 2-manual
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
Project management with ms project 2007
Project management with ms project 2007Project management with ms project 2007
Project management with ms project 2007
 
Project management by MS Project 2010
Project management by MS Project 2010Project management by MS Project 2010
Project management by MS Project 2010
 
Introduction to Primavera Reflections
Introduction to Primavera ReflectionsIntroduction to Primavera Reflections
Introduction to Primavera Reflections
 

En vedette

Network Diagrams
Network DiagramsNetwork Diagrams
Network DiagramsNicola2903
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project ManagementShyam Kerkar
 
Lisa Pattyn - Student Entrepreneurship Program
Lisa Pattyn - Student Entrepreneurship ProgramLisa Pattyn - Student Entrepreneurship Program
Lisa Pattyn - Student Entrepreneurship Programimec.archive
 
Presentation5
Presentation5Presentation5
Presentation5TELICIA
 
Искусственный камень от "Арт-Кам"
Искусственный камень от "Арт-Кам"Искусственный камень от "Арт-Кам"
Искусственный камень от "Арт-Кам"Андрей Соколов
 
M3m urbana (2)
M3m urbana (2)M3m urbana (2)
M3m urbana (2)kalra_8
 
Computer consulting project cowens
Computer consulting project cowensComputer consulting project cowens
Computer consulting project cowenscodyowens
 
Convergence: End User Files
Convergence: End User FilesConvergence: End User Files
Convergence: End User Filesphotizo1
 
Module 2 - Life Cycle of a Lesson
Module 2 - Life Cycle of a LessonModule 2 - Life Cycle of a Lesson
Module 2 - Life Cycle of a LessonJoAnn Corley
 
Linkare TI - Company Profile 2012 (En) V 2.0
Linkare TI - Company Profile   2012 (En)   V 2.0Linkare TI - Company Profile   2012 (En)   V 2.0
Linkare TI - Company Profile 2012 (En) V 2.0Sergio_Fonseca
 

En vedette (20)

COLETIVO COCA COLA - SIMOES
COLETIVO COCA COLA - SIMOESCOLETIVO COCA COLA - SIMOES
COLETIVO COCA COLA - SIMOES
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project Management
 
Lisa Pattyn - Student Entrepreneurship Program
Lisa Pattyn - Student Entrepreneurship ProgramLisa Pattyn - Student Entrepreneurship Program
Lisa Pattyn - Student Entrepreneurship Program
 
Presentation5
Presentation5Presentation5
Presentation5
 
CS Education Event - Mathspace
CS Education Event - MathspaceCS Education Event - Mathspace
CS Education Event - Mathspace
 
Books in my life
Books in my lifeBooks in my life
Books in my life
 
Искусственный камень от "Арт-Кам"
Искусственный камень от "Арт-Кам"Искусственный камень от "Арт-Кам"
Искусственный камень от "Арт-Кам"
 
Word press in 60 minutes
Word press in 60 minutesWord press in 60 minutes
Word press in 60 minutes
 
M3m urbana (2)
M3m urbana (2)M3m urbana (2)
M3m urbana (2)
 
CS Education Event - Bitscope Designs
CS Education Event - Bitscope DesignsCS Education Event - Bitscope Designs
CS Education Event - Bitscope Designs
 
CS Education Event - Intersective
CS Education Event - IntersectiveCS Education Event - Intersective
CS Education Event - Intersective
 
Computer consulting project cowens
Computer consulting project cowensComputer consulting project cowens
Computer consulting project cowens
 
Convergence: End User Files
Convergence: End User FilesConvergence: End User Files
Convergence: End User Files
 
Chapinero
ChapineroChapinero
Chapinero
 
Glaciers AyRo
Glaciers AyRoGlaciers AyRo
Glaciers AyRo
 
Bosa
BosaBosa
Bosa
 
Module 2 - Life Cycle of a Lesson
Module 2 - Life Cycle of a LessonModule 2 - Life Cycle of a Lesson
Module 2 - Life Cycle of a Lesson
 
Linkare TI - Company Profile 2012 (En) V 2.0
Linkare TI - Company Profile   2012 (En)   V 2.0Linkare TI - Company Profile   2012 (En)   V 2.0
Linkare TI - Company Profile 2012 (En) V 2.0
 
CS Education Event - State Library NSW
CS Education Event - State Library NSWCS Education Event - State Library NSW
CS Education Event - State Library NSW
 

Similaire à Creating a task list

Getting started with project
Getting started with projectGetting started with project
Getting started with projectahmed hamza
 
Ms project presentation
Ms project presentationMs project presentation
Ms project presentationKhem Singh
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentationFarrukh Raja
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project PresentationKhem Singh
 
dokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptxdokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptxSunilHotkar2
 
ms-project-presentation.pptx
ms-project-presentation.pptxms-project-presentation.pptx
ms-project-presentation.pptxSunilHotkar2
 
Project 2007 full handout
Project 2007 full handoutProject 2007 full handout
Project 2007 full handoutZenawi Mehari
 
Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010Bhishma Bhatti
 
CSCI 714 Software Project Planning and EstimationLec.docx
CSCI 714 Software Project Planning and EstimationLec.docxCSCI 714 Software Project Planning and EstimationLec.docx
CSCI 714 Software Project Planning and EstimationLec.docxmydrynan
 
Project control tools by Samuel obino mokaya
Project control tools by Samuel obino mokayaProject control tools by Samuel obino mokaya
Project control tools by Samuel obino mokayaDiscover JKUAT
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorialRonald Oroya
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?Kenny Hirschmann
 
Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-scheduleRaaz Karkee
 
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docxevonnehoggarth79783
 
Scrum With Ms Project
Scrum With Ms ProjectScrum With Ms Project
Scrum With Ms Projectbobby
 

Similaire à Creating a task list (20)

Getting started with project
Getting started with projectGetting started with project
Getting started with project
 
Ms project presentation
Ms project presentationMs project presentation
Ms project presentation
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentation
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
 
dokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptxdokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptx
 
ms-project-presentation.pptx
ms-project-presentation.pptxms-project-presentation.pptx
ms-project-presentation.pptx
 
Project Management
Project ManagementProject Management
Project Management
 
Project 2007 full handout
Project 2007 full handoutProject 2007 full handout
Project 2007 full handout
 
Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010
 
CSCI 714 Software Project Planning and EstimationLec.docx
CSCI 714 Software Project Planning and EstimationLec.docxCSCI 714 Software Project Planning and EstimationLec.docx
CSCI 714 Software Project Planning and EstimationLec.docx
 
BhadaniS Microsoft Project Manual Training
BhadaniS Microsoft Project Manual TrainingBhadaniS Microsoft Project Manual Training
BhadaniS Microsoft Project Manual Training
 
Project control tools by Samuel obino mokaya
Project control tools by Samuel obino mokayaProject control tools by Samuel obino mokaya
Project control tools by Samuel obino mokaya
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorial
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?
 
Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-schedule
 
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
 
Gantt charts
Gantt chartsGantt charts
Gantt charts
 
Scrum With Ms Project
Scrum With Ms ProjectScrum With Ms Project
Scrum With Ms Project
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Msp presentation
Msp presentationMsp presentation
Msp presentation
 

Dernier

9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...Pooja Nehwal
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajanpragatimahajan3
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 

Dernier (20)

9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 💞 Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 💞 Full Nigh...
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 

Creating a task list

  • 1. Creating a Task List SUST-CSIT Ahmed Hamza
  • 2. Objective Enter task information. Estimate and enter how long each task should last. Create a milestone to track an important event. Organize tasks into phases. Create task relationships by linking tasks. Record task details in notes and insert a hyperlink to content on the Internet. Check a project plan’s overall duration. SUST-CSIT Ahmed Hamza
  • 3. Entering Tasks Tasks are the most basic building blocks of any project-tasks Tasks describe project work in terms of sequence, duration, and resource requirements SUST-CSIT Ahmed Hamza
  • 4. How to Enter Task In the first cell directly below the Task Name column heading, type Pre-Production, and then press The task you entered is given an ID number. Each task has a unique ID number, but it does not necessarily represent the order in which tasks occur. Project assigns a duration of one day to the new task the question mark indicates that this is an estimated duration By default, the task start date is the same as the project start date SUST-CSIT Ahmed Hamza
  • 5. Cont>> Enter the following task names below the Pre-Production task name, pressing after Entereach task name Develop script Develop production boards Pick locations Hold auditions Production Rehearse Shoot video Log footage SUST-CSIT Ahmed Hamza
  • 6. Every project has an ultimate goal or intent: the reason that the project was started. This is called the project deliverable. This deliverable is usually a product Defining the right tasks to create the right deliverable is an essential skill for a project manager The task lists you create in Project should describe all of the work required, and only the work required, to complete the project successfully SUST-CSIT Ahmed Hamza Project Management Focus: Defining the Right Tasks for the Right Deliverable
  • 7. Estimating Durations A task’s duration is the amount of time you expect it will take to complete the task Project can work with task durations that range from minutes to months For example, a project might have a project calendar with working time defined as 8 A.M. through 5 P.M. with a one-hour lunch break Monday through Friday SUST-CSIT Ahmed Hamza
  • 8. Cont>> you estimate that a task will take 16 hours of working time, you could enter its duration as 2d to schedule work over two eight-hour workdays. By starting the task at 8 A.M. on a Thursday, you should then expect that it wouldn’t be completed until 5 P.M. on the following Sunday. No work would be scheduled over the weekend because Friday and Saturday have been defined as nonworking time. SUST-CSIT Ahmed Hamza
  • 9. Tip You determine the overall duration of a project by calculating the difference between the earliest start date and the latest finish date of the tasks that compose it. SUST-CSIT Ahmed Hamza
  • 10. Cont>> Click the cell below the Duration column heading for task 2, Develop script. The Duration field for task 2 is selected. Type 5d, and then press Enter The value 5 days appears in the Duration field. Enter the following durations for the remaining tasks. SUST-CSIT Ahmed Hamza
  • 12. You should consider two general rules when estimating task durations Overall project duration often correlates to task duration; long projects tend to have tasks with longer durations than do tasks in short projects If you track progress against your project plan you must consider the level of detail you want to apply to your project’s tasks. If you have a multi-year project, for example, it might not be practical or even possible to track tasks that are measured in minutes or hours SUST-CSIT Ahmed Hamza How Do You Come Up with Accurate Task Durations?
  • 13. For your real-world projects, you will often estimate task durations. Good sources of task duration estimates include: Historical information from previous, similar projects. Estimates from the people who will complete the tasks. Expert judgment of those who have managed similar projects. Standards of professional or industrial organizations that undertake projects similar to yours SUST-CSIT Ahmed Hamza Cont>>
  • 14. For complex projects, you probably would combine these and other sources to estimate task durations. Because inaccurate task duration estimates are a major source of risk in any project, making good estimates is well worth the effort expended SUST-CSIT Ahmed Hamza Cont>>
  • 15. Organizing Tasks into Phases It is helpful to organize groups of closely related tasks that represent a major portion of the project’s work into phases For example, it is common to divide a film or video project into major phases of work such as pre-production, production, and post-production In Project, phases are represented by summary tasks A summary task behaves differently from other tasks You can’t edit its duration, start date, or other calculated values directly because this information is derived or “rolled up” from the detail tasks SUST-CSIT Ahmed Hamza
  • 16. The two most common approaches to developing tasks and phases are top-down and bottom-up planning. Top-down planning. Identifies major phases or products of the project before filling in the tasks required to complete those phases. Complex projects can have several layers of phases. This approach works from general to specific. Bottom-up planning. Identifies as many bottom-level detailed tasks as possible before organizing them into logical groups, called phases or summary tasks. This approach works from specific to general. SUST-CSIT Ahmed Hamza Top-Down and Bottom-Up Planning
  • 17. Cont>> create two summary tasks by indenting tasks Select the names of tasks 2 through 6. On the Project menu, point to Outline, and then click Indent Next, select the names of tasks 8 through 10. On the Project menu, point to Outline, and then click Indent. Task 7 becomes a summary task, and a summary task bar for it appears in the Gantt chart. SUST-CSIT Ahmed Hamza
  • 18. Linking Tasks Projects require tasks to be performed in a specific order If we have tow task that have a finish-to-start relationship (also called a link or dependency) that has two aspects: The second task must occur later than the first task; this is a sequence. The second task can occur only if the first task is completed; this is a dependency. SUST-CSIT Ahmed Hamza
  • 19. Cont>> In Project, the first task (“film the scene”) is called the predecessor because it precedes tasks that depend on it. The second task (“edit the filmed scene”) is called the successor because it succeeds tasks on which it is dependent. Any task can be a predecessor for one or more successor tasks. Likewise, any task can be a successor to one or more predecessor tasks SUST-CSIT Ahmed Hamza
  • 20. Cont>> You create task relationships by creating links between tasks First you’ll create a finish-to-start dependency between two tasks. Select the names of tasks 2 and 3. On the Edit menu, click Link Tasks. When working with summary tasks, you can either link summary tasks directly (as you did above) or link the latest task in the first phase with the earliest task in the second phase SUST-CSIT Ahmed Hamza
  • 21. Cont>> You can also create a finish-to-start relationship between tasks right in the Gantt chart. Point to the task bar of the predecessor task until the pointer changes to a four-pointed star. Then, drag the mouse pointer up or down to the task bar of the successor task. While you’re dragging the mouse pointer to create a task SUST-CSIT Ahmed Hamza
  • 22. Documenting Tasks You can record additional information about a task in a note There are three types of notes: task notes, resource notes, and assignment notes Select the name of task 4, Pick locations On the Project menu, click Task Notes. In the Notes box, type Includes exterior street scene and indoor studio scenes SUST-CSIT Ahmed Hamza
  • 23. Checking the Plan’s Duration At this point, you might want to know how long the project is expected to take. You haven’t directly entered a total project duration or finish date, but Project has calculated these values based on individual task durations and task relationships An easy way to view the project’s scheduled finish date is via the Project Information dialog box. SUST-CSIT Ahmed Hamza
  • 24. Cont>> On the Project menu, click Project Information SUST-CSIT Ahmed Hamza
  • 25. Key Points Essential aspects of tasks in a project plan include their duration and order of occurrence. Task links, or relationships, cause the start or end of one task to affect the start or end of another task. A common task relationship is a finish-to-start relationship in which the completion of one task controls the start of another task. In Project, phases of a schedule are represented as summary tasks. You can document additional details using task notes and create hyperlinks to the Internet. The Project Information dialog box (Project menu) is an excellent way to observe the key values of a project plan, such as its scheduled finish date and duration. SUST-CSIT Ahmed Hamza