SlideShare une entreprise Scribd logo
1  sur  23
SUMMER TRAINING
LAYING OF SEWER LINE
RAMPUR SEWERAGE SCHEME ZONE (V)
UTTAR PRADESH JAL NIGAM, A U.P GOVT. UNDERTAKING
CONT: M/s LARSEN & TOUBRO
RAMPUR
 Small city in the north western zone of Uttar Pradesh.
 Population of almost 2,80,000.
 Ramganga, a subsidiary of Ganga River passes through the city.
 Approximately 11,000 million liters per year waste water from
Rampur is directly disposed into Ramganga river which is
indirectly transferred to Ganga river.
 Under the new development scheme of Uttar Pradesh
government, the state will make around 200 small/ big sewage
treatment plants in the near future.
 Works have started in major cities like Agra, Moradabad, Rampur,
Varanasi and many more.
BASICS
 Worked as an industrial trainee under Uttar Pradesh Jal Nigam
for a tenure of almost 6 weeks.
 To lay 14.5 km sewer line throughout rampur.
 Construction of 5 mld sewage treatement plant based on SBR
( sequential batch reactor) technology.
 Initial project cost: 58 crores
 Project tenure: 14 months
 Contractor: M/s Larsen & Toubro
SCHEMATICS
PLANT
 Based on SBR technology. Maximum capacity of 5mld
 SBR tech provides highest treatment efficiency in a single step
biological process
 No additional settling unit or secondary clarifier is required.
 SBR technology has a good operating flexibility and control
 Due to its compact design, it requires very less area as
compared to other conventional STP’s.
 Highly economical, eliminates the cost of clarifiers and other
equipment.
ZONE V
 Zone V was a 4.5 km stretch
 With the help of population forecasting for the next 30 years,
the discharge was calculated and according to that the
diameter of the pipes used and design capacity of the plant
was selected
 Manning's equation was used
to determine the required slope.
 With the help of the equation and discharge to be carried a
slope of 1:800 was to be provided in the 4.5 km stretch
 This implies that for every 800m a drop of 1m was to be given.
SPECIFICATIONS
• As per the design, pipe selected were of 2.5m in length and
600mm in diameter.
• For the zone V stretch of 4.5 km , if we do the math…….
• No of pipes needed = 1800 pipes
• For the slope of 1:800, each pipe would go a 3mm drop .
PIPES
• Made of Reinforced cement concrete as per Indian Standards
• Pipe length= 2.5m
• Inner diameter = 600mm
• Thickness = 85mm
• Head thickness = 85mm
• Total thickness at the head = 85+85+600 =770mm
• Total thickness at tail = 600+85 = 685mm
ADVANTAGES:
• Equally efficient in handling tension & compression
• Long service period
• Can be casted of desired strength
PROCESS
Approach, population forecasting, design & calculations
Taking
levels
Excavation
Bedding material, ramming, laying of pipes, joining of pipes
Manholes, filling back the trench
LEVELS
• Simple Auto Level and a telescopic staff were used
• Levels were taken for
1. Natural ground level
2. Depth of trench
3. Top of bedding material
4. Top of pipe surface
EXCAVATION
• Use of Komatsu excavator with a bucket capacity of 1 cubic
meter to dig trenches
• 30-40 cm spacing on either side of pipe is ensured for the
labors to work
• If depth of trench marginally increases use of telescopic
excavation is done for economical purposes.
SHORING BOX
• Stabilizes the trench walls from collapsing
• Can withstand high earth pressure and drastically reduces the
probability for any accident due to trench wall instability
• Helps protect adjacent structures and their foundations
• Helps in controlling GW seepage thus aiding in progress of work
MOULD AND MATERIAL
• To provide a strong base for the pipe a concrete mix of
192mm height was provided
• Wooden mould: 1x1m with 192 mm depth
• Bedding material was being prepared in a electrical concrete
mixer
• Mix used was of 1:2:4 ratio i.e. 1 part of cement with 2 part of
sand and 4 parts of coarse aggregate.
• Material was prepared by a handful of labors not too far away
from the excavation site.
PROCESS
PLACING OF PIPES
• After bedding material was placed readings were taken to
ensure correct bed depth else more ramming was done to
ensure that.
• Pipes were lifted and placed with the help of excavators
• Placed on the bed and then readings were again taken of the
top of pipe after joining with the existing section
• Readings were taken to ensure the 3mm drop per pipe
• The pipes were pressed by the help of excavator to make any
changes in the readings
PROCESS
JOINTS
• Pipes were sealed with the help of a rubber gasket
• Rubber gasket provides adequate water tight sealing solution.
• External sealing was done with jute ropes dipped in liquid
cement solution.
• Jutes ropes are cheap, easily available and no additional
skilled labor is required for the job
• The cement dipped jute rope hardens with time to provide
excellent sealing properties.
MANHOLES
• In the Zone V manholes were provided at every 30m interval.
• Manholes are basically provided when
• Change in diameter
• Change in alignment
• Change in slope
• Maintenance purposes
• Manholes are also used as inspection chambers .
• In case of clogging of the pipe manholes play a important role
in making the line operational again.
• In Zone V, the manholes were constructed by the masons.
MANHOLES
ADDITIONALS
• Other than on site work, I was also introduced to rate analysis
of the work, the charges , contractor profit sums etc.
• All the readings of the level were carefully noted in a
maintained register.
• All the calculations were done mostly on site by the Junior
Engineer from both L&T and U.P Jal Nigam.
• The materials used were also inspected thoroughly by the
engineers on site before use to ensure quality.
SAFETY
• Complete barricading of the road was done with TIN sheets
and plastic tapes so as to provide a safe environment both for
the workers and traffic around the site
• Caution boards, sign plates, night flood lights were used as
additional safety features.
• Safety jackets safety boots and safety helmets was must for
every worker on the site.
CONCLUDING……
• Introduced to the process of design of sewerage scheme for a
town or a city
• Developed a good skill in taking readings from the auto level
• Learnt how to lay sewer pipes
• Also learnt about site safety and precaution measures
• Learnt about use of moulds, shoring boxes, manholes etc.
• Was also introduced to office rate analysis work
• Learnt how to maintain a measurement book
• At last It was a good learning environment as it helped me
improving my skills.
THANK YOU

Contenu connexe

Tendances

Chapter 7 conveyance of water
Chapter 7 conveyance of waterChapter 7 conveyance of water
Chapter 7 conveyance of water
Gokul Saud
 
Water demand and factor affecting water demand
Water demand and factor affecting water demandWater demand and factor affecting water demand
Water demand and factor affecting water demand
Ankit Gola
 
House connection from mains, laying and joints in pipes
House connection from mains, laying and joints in pipesHouse connection from mains, laying and joints in pipes
House connection from mains, laying and joints in pipes
krishnacp
 

Tendances (20)

Water supply appurtenances
Water supply appurtenancesWater supply appurtenances
Water supply appurtenances
 
House Drainage System
House Drainage SystemHouse Drainage System
House Drainage System
 
PIPES , PIPE FITTINGS,PIPE JOINTS & LAYING OF PIPELINES
PIPES , PIPE FITTINGS,PIPE JOINTS & LAYING OF PIPELINESPIPES , PIPE FITTINGS,PIPE JOINTS & LAYING OF PIPELINES
PIPES , PIPE FITTINGS,PIPE JOINTS & LAYING OF PIPELINES
 
Cross section of the canal, balancing depth and canal fsl
Cross section of the canal, balancing depth  and canal fslCross section of the canal, balancing depth  and canal fsl
Cross section of the canal, balancing depth and canal fsl
 
Laying and Testing of sewer
Laying and Testing of sewerLaying and Testing of sewer
Laying and Testing of sewer
 
Chapter 7 conveyance of water
Chapter 7 conveyance of waterChapter 7 conveyance of water
Chapter 7 conveyance of water
 
Building drainage system
Building drainage systemBuilding drainage system
Building drainage system
 
Design of sewers
Design of sewersDesign of sewers
Design of sewers
 
Water demand and factor affecting water demand
Water demand and factor affecting water demandWater demand and factor affecting water demand
Water demand and factor affecting water demand
 
WATER SUPPLY AND DRAINAGE SERVICE FOR BUILDING
WATER SUPPLY AND DRAINAGE SERVICE FOR BUILDINGWATER SUPPLY AND DRAINAGE SERVICE FOR BUILDING
WATER SUPPLY AND DRAINAGE SERVICE FOR BUILDING
 
House connection from mains, laying and joints in pipes
House connection from mains, laying and joints in pipesHouse connection from mains, laying and joints in pipes
House connection from mains, laying and joints in pipes
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
 
Design and construction of sewer
Design and construction of sewer Design and construction of sewer
Design and construction of sewer
 
materials of sewer
materials of sewermaterials of sewer
materials of sewer
 
Sewer appurtenances
Sewer appurtenancesSewer appurtenances
Sewer appurtenances
 
Water supply
Water supplyWater supply
Water supply
 
House Drainage System
House Drainage SystemHouse Drainage System
House Drainage System
 
Canal outlets and modules
Canal outlets and modulesCanal outlets and modules
Canal outlets and modules
 
WATER SUPPLY AND PLUMBING SERVICES
WATER SUPPLY AND PLUMBING SERVICESWATER SUPPLY AND PLUMBING SERVICES
WATER SUPPLY AND PLUMBING SERVICES
 
presentation : cross drainage work
presentation : cross drainage workpresentation : cross drainage work
presentation : cross drainage work
 

En vedette

sewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenancesewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenance
Manish Goyal
 
BS 2 Fire protection 4
BS 2 Fire protection 4BS 2 Fire protection 4
BS 2 Fire protection 4
Est
 
S2 8 construction surveys
S2 8 construction surveysS2 8 construction surveys
S2 8 construction surveys
Est
 
BS2 Fire protection 2
BS2 Fire protection 2BS2 Fire protection 2
BS2 Fire protection 2
Est
 
MSBC Secure Presentation - FRD
MSBC Secure Presentation - FRDMSBC Secure Presentation - FRD
MSBC Secure Presentation - FRD
MSBC Secure
 
Blackboard IM
Blackboard IMBlackboard IM
Blackboard IM
dsosa83
 
Rupee voltility, twin deficits and exchange rate policy
Rupee voltility, twin deficits and exchange rate policyRupee voltility, twin deficits and exchange rate policy
Rupee voltility, twin deficits and exchange rate policy
arnadkarni
 

En vedette (16)

Hydraulic design of sewer
Hydraulic design of sewerHydraulic design of sewer
Hydraulic design of sewer
 
Sewer Appurtenances
Sewer AppurtenancesSewer Appurtenances
Sewer Appurtenances
 
Sewerage design
Sewerage designSewerage design
Sewerage design
 
sewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenancesewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenance
 
Dual Plumbed Systems and Cross Connection Control (California Department of P...
Dual Plumbed Systems and Cross Connection Control (California Department of P...Dual Plumbed Systems and Cross Connection Control (California Department of P...
Dual Plumbed Systems and Cross Connection Control (California Department of P...
 
BS 2 Fire protection 4
BS 2 Fire protection 4BS 2 Fire protection 4
BS 2 Fire protection 4
 
S2 8 construction surveys
S2 8 construction surveysS2 8 construction surveys
S2 8 construction surveys
 
BS2 Fire protection 2
BS2 Fire protection 2BS2 Fire protection 2
BS2 Fire protection 2
 
MSBC Secure Presentation - FRD
MSBC Secure Presentation - FRDMSBC Secure Presentation - FRD
MSBC Secure Presentation - FRD
 
Blackboard IM
Blackboard IMBlackboard IM
Blackboard IM
 
Case Study: #MustiXiGO Pinterest Contest for iXiGO.com
Case Study: #MustiXiGO Pinterest Contest for iXiGO.comCase Study: #MustiXiGO Pinterest Contest for iXiGO.com
Case Study: #MustiXiGO Pinterest Contest for iXiGO.com
 
Cep 812 Flipped PD ppt
Cep 812 Flipped PD pptCep 812 Flipped PD ppt
Cep 812 Flipped PD ppt
 
Rupee voltility, twin deficits and exchange rate policy
Rupee voltility, twin deficits and exchange rate policyRupee voltility, twin deficits and exchange rate policy
Rupee voltility, twin deficits and exchange rate policy
 
Motivation quotes
Motivation quotes Motivation quotes
Motivation quotes
 
Never hear "I don't have anything to write about" again!
Never hear "I don't have anything to write about" again!Never hear "I don't have anything to write about" again!
Never hear "I don't have anything to write about" again!
 
Selenium ff
Selenium ffSelenium ff
Selenium ff
 

Similaire à Laying of Sewer Line

Pipeline Construct.pptx
Pipeline Construct.pptxPipeline Construct.pptx
Pipeline Construct.pptx
ssuserfc98db
 

Similaire à Laying of Sewer Line (20)

Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road construction
 
A project report on nagpur metro rail corporation
A project report on nagpur metro rail corporationA project report on nagpur metro rail corporation
A project report on nagpur metro rail corporation
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drill
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptx
 
Multi story building construction anshul
Multi story building construction anshulMulti story building construction anshul
Multi story building construction anshul
 
Glass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panelsGlass fibre reinforced gypsum panels
Glass fibre reinforced gypsum panels
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
 
Pipeline Construct.pptx
Pipeline Construct.pptxPipeline Construct.pptx
Pipeline Construct.pptx
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine Planning
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Mahi ppt suez (2)
Mahi ppt suez (2)Mahi ppt suez (2)
Mahi ppt suez (2)
 
Peter Dowd: Remote Removal of Damaged Steel Liner From Vent Shaft
Peter Dowd: Remote Removal of Damaged Steel Liner From Vent ShaftPeter Dowd: Remote Removal of Damaged Steel Liner From Vent Shaft
Peter Dowd: Remote Removal of Damaged Steel Liner From Vent Shaft
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul IslamGlass Fibre Reinforced Gypsum Panels By Raijul Islam
Glass Fibre Reinforced Gypsum Panels By Raijul Islam
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
 
Trenchless technolgy
Trenchless technolgyTrenchless technolgy
Trenchless technolgy
 
Types of Pipes & There Applications
Types of Pipes & There ApplicationsTypes of Pipes & There Applications
Types of Pipes & There Applications
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
 
Site Report
Site ReportSite Report
Site Report
 

Plus de sumitvikram (6)

Bio gas plant
Bio gas plantBio gas plant
Bio gas plant
 
Application of gis in indian railways
Application of gis in indian railwaysApplication of gis in indian railways
Application of gis in indian railways
 
Foundation design of burj khalifa (deep foundation<piles>)
Foundation design of burj khalifa (deep foundation<piles>)Foundation design of burj khalifa (deep foundation<piles>)
Foundation design of burj khalifa (deep foundation<piles>)
 
Indian summer monsoon
Indian summer monsoonIndian summer monsoon
Indian summer monsoon
 
Detailed analysis of plane table surveying
Detailed analysis of plane table surveyingDetailed analysis of plane table surveying
Detailed analysis of plane table surveying
 
Ios vs android
Ios vs androidIos vs android
Ios vs android
 

Dernier

Environmental Science - Nuclear Hazards and Us.pptx
Environmental Science - Nuclear Hazards and Us.pptxEnvironmental Science - Nuclear Hazards and Us.pptx
Environmental Science - Nuclear Hazards and Us.pptx
hossanmdjobayer103
 

Dernier (20)

Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Jejuri Call Me 7737669865 Budget Friendly No Advance Booking
 
Green Marketing
Green MarketingGreen Marketing
Green Marketing
 
RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995
 
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Hadapsar ( Pune ) Call ON 8005736733 Starting From 5K to...
 
Hertwich_EnvironmentalImpacts_BuildingsGRO.pptx
Hertwich_EnvironmentalImpacts_BuildingsGRO.pptxHertwich_EnvironmentalImpacts_BuildingsGRO.pptx
Hertwich_EnvironmentalImpacts_BuildingsGRO.pptx
 
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Ramtek Call Me 7737669865 Budget Friendly No Advance Booking
 
Plastic Bank Beyond EPR - Sustainability Programs
Plastic Bank Beyond EPR - Sustainability ProgramsPlastic Bank Beyond EPR - Sustainability Programs
Plastic Bank Beyond EPR - Sustainability Programs
 
VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...
VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...
VVIP Pune Call Girls Vishal Nagar WhatSapp Number 8005736733 With Elite Staff...
 
Kondhwa ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Kondhwa ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Kondhwa ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Kondhwa ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
Get Premium Hoskote Call Girls (8005736733) 24x7 Rate 15999 with A/c Room Cas...
 
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Talegaon Dabhade Call Me 7737669865 Budget Friendly No Advance Boo...
 
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Wagholi ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024
 
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
VIP Model Call Girls Viman Nagar ( Pune ) Call ON 8005736733 Starting From 5K...
 
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
GENUINE Babe,Call Girls IN Chhatarpur Delhi | +91-8377877756
 
Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Attur Layout Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
 
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...
Call Girls in Sakinaka Agency, { 9892124323 } Mumbai Vashi Call Girls Serivce...
 
Environmental Science - Nuclear Hazards and Us.pptx
Environmental Science - Nuclear Hazards and Us.pptxEnvironmental Science - Nuclear Hazards and Us.pptx
Environmental Science - Nuclear Hazards and Us.pptx
 
Alandi Road ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready ...
Alandi Road ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready ...Alandi Road ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready ...
Alandi Road ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready ...
 
Climate Change
Climate ChangeClimate Change
Climate Change
 

Laying of Sewer Line

  • 1. SUMMER TRAINING LAYING OF SEWER LINE RAMPUR SEWERAGE SCHEME ZONE (V) UTTAR PRADESH JAL NIGAM, A U.P GOVT. UNDERTAKING CONT: M/s LARSEN & TOUBRO
  • 2. RAMPUR  Small city in the north western zone of Uttar Pradesh.  Population of almost 2,80,000.  Ramganga, a subsidiary of Ganga River passes through the city.  Approximately 11,000 million liters per year waste water from Rampur is directly disposed into Ramganga river which is indirectly transferred to Ganga river.  Under the new development scheme of Uttar Pradesh government, the state will make around 200 small/ big sewage treatment plants in the near future.  Works have started in major cities like Agra, Moradabad, Rampur, Varanasi and many more.
  • 3. BASICS  Worked as an industrial trainee under Uttar Pradesh Jal Nigam for a tenure of almost 6 weeks.  To lay 14.5 km sewer line throughout rampur.  Construction of 5 mld sewage treatement plant based on SBR ( sequential batch reactor) technology.  Initial project cost: 58 crores  Project tenure: 14 months  Contractor: M/s Larsen & Toubro
  • 5. PLANT  Based on SBR technology. Maximum capacity of 5mld  SBR tech provides highest treatment efficiency in a single step biological process  No additional settling unit or secondary clarifier is required.  SBR technology has a good operating flexibility and control  Due to its compact design, it requires very less area as compared to other conventional STP’s.  Highly economical, eliminates the cost of clarifiers and other equipment.
  • 6. ZONE V  Zone V was a 4.5 km stretch  With the help of population forecasting for the next 30 years, the discharge was calculated and according to that the diameter of the pipes used and design capacity of the plant was selected  Manning's equation was used to determine the required slope.  With the help of the equation and discharge to be carried a slope of 1:800 was to be provided in the 4.5 km stretch  This implies that for every 800m a drop of 1m was to be given.
  • 7. SPECIFICATIONS • As per the design, pipe selected were of 2.5m in length and 600mm in diameter. • For the zone V stretch of 4.5 km , if we do the math……. • No of pipes needed = 1800 pipes • For the slope of 1:800, each pipe would go a 3mm drop .
  • 8. PIPES • Made of Reinforced cement concrete as per Indian Standards • Pipe length= 2.5m • Inner diameter = 600mm • Thickness = 85mm • Head thickness = 85mm • Total thickness at the head = 85+85+600 =770mm • Total thickness at tail = 600+85 = 685mm ADVANTAGES: • Equally efficient in handling tension & compression • Long service period • Can be casted of desired strength
  • 9. PROCESS Approach, population forecasting, design & calculations Taking levels Excavation Bedding material, ramming, laying of pipes, joining of pipes Manholes, filling back the trench
  • 10. LEVELS • Simple Auto Level and a telescopic staff were used • Levels were taken for 1. Natural ground level 2. Depth of trench 3. Top of bedding material 4. Top of pipe surface
  • 11. EXCAVATION • Use of Komatsu excavator with a bucket capacity of 1 cubic meter to dig trenches • 30-40 cm spacing on either side of pipe is ensured for the labors to work • If depth of trench marginally increases use of telescopic excavation is done for economical purposes.
  • 12. SHORING BOX • Stabilizes the trench walls from collapsing • Can withstand high earth pressure and drastically reduces the probability for any accident due to trench wall instability • Helps protect adjacent structures and their foundations • Helps in controlling GW seepage thus aiding in progress of work
  • 13. MOULD AND MATERIAL • To provide a strong base for the pipe a concrete mix of 192mm height was provided • Wooden mould: 1x1m with 192 mm depth • Bedding material was being prepared in a electrical concrete mixer • Mix used was of 1:2:4 ratio i.e. 1 part of cement with 2 part of sand and 4 parts of coarse aggregate. • Material was prepared by a handful of labors not too far away from the excavation site.
  • 15. PLACING OF PIPES • After bedding material was placed readings were taken to ensure correct bed depth else more ramming was done to ensure that. • Pipes were lifted and placed with the help of excavators • Placed on the bed and then readings were again taken of the top of pipe after joining with the existing section • Readings were taken to ensure the 3mm drop per pipe • The pipes were pressed by the help of excavator to make any changes in the readings
  • 17. JOINTS • Pipes were sealed with the help of a rubber gasket • Rubber gasket provides adequate water tight sealing solution. • External sealing was done with jute ropes dipped in liquid cement solution. • Jutes ropes are cheap, easily available and no additional skilled labor is required for the job • The cement dipped jute rope hardens with time to provide excellent sealing properties.
  • 18. MANHOLES • In the Zone V manholes were provided at every 30m interval. • Manholes are basically provided when • Change in diameter • Change in alignment • Change in slope • Maintenance purposes • Manholes are also used as inspection chambers . • In case of clogging of the pipe manholes play a important role in making the line operational again. • In Zone V, the manholes were constructed by the masons.
  • 20. ADDITIONALS • Other than on site work, I was also introduced to rate analysis of the work, the charges , contractor profit sums etc. • All the readings of the level were carefully noted in a maintained register. • All the calculations were done mostly on site by the Junior Engineer from both L&T and U.P Jal Nigam. • The materials used were also inspected thoroughly by the engineers on site before use to ensure quality.
  • 21. SAFETY • Complete barricading of the road was done with TIN sheets and plastic tapes so as to provide a safe environment both for the workers and traffic around the site • Caution boards, sign plates, night flood lights were used as additional safety features. • Safety jackets safety boots and safety helmets was must for every worker on the site.
  • 22. CONCLUDING…… • Introduced to the process of design of sewerage scheme for a town or a city • Developed a good skill in taking readings from the auto level • Learnt how to lay sewer pipes • Also learnt about site safety and precaution measures • Learnt about use of moulds, shoring boxes, manholes etc. • Was also introduced to office rate analysis work • Learnt how to maintain a measurement book • At last It was a good learning environment as it helped me improving my skills.