SlideShare une entreprise Scribd logo
1  sur  19
Presented by Varal Suyesh
Context
 Introduction
 Materials used
 Principle used for Construction an (SFT)
 Need for Submerged Floating Tunnels (SFT)
 Parameters of an SFT
 Construction procedure
 Advantages
 Transatlantic Tunnels
 Conclusion
INTRODUCTION
 Submerged floating tunnel is basically making a tunnel to
float underwater which is balanced by its buoyancy, self
weight and constraint forces resulted from cable system
and thus submerged to a certain depth underwater.
 It is basically tube like structure floating at some depth
below water surface and fixed against excessive
movements. The tube is designed to accommodate road
and or rail traffic.
MATERIAL USED:-
 As the tunnel is situated at a depth of 30m, it should be
perfectly water tight and secondly it should resist the salty sea
water and thirdly it should be withstand against hydrostatic
forces coming on it.
 It is made of 4 layers. Outermost layer is constructed of
aluminium to resist the salty sea water. Second and third layer
is made of the foam to float the tunnel easily in water. Fourth
layer is of concrete which gives strength to the tunnel.
“ARCHIMEDES PRINCIPLE”
 Any object wholly or partially immersed in an
fluid, is buoyed up by a force equal to the
weight of the fluid displaced by the object.
 this means if more surface area exposed to
water surface more are the chances of floating
it.
 Ships, submarines, offshore oil rigs etc. work
on this principle.
 Research shows that the buoyancy to weight
ratio for the tunnel to float should be less than
one and between 0.5 to 0.8
PRESENT SCENARIO
 They are considered to built when the
underneath ground surface is shallow and the
tunnel can be placed directly on sea bed and can
be covered by sand and backfill material so as to
avoid their movement.
NEED FOR SUBMERGED FLOATING TUNNEL
 A “SFT” is considered when the depth of sea or ocean
is too deep so that no tunnel or any solid body could
sustain the pressure acting on it at such a deep level.
 In that case the tunnel is lifted up such as about 30
to 100m deep from the sea surface where the water
pressure is comparatively lower than what is at the
bottom depth.
PARAMETERS OF AN “SFT”
An SFT basically consists of four parts
1) The tunnel structure which is made of different
segments
2) The shore connection structure which connects it
to shores.
3) The cable systems which are anchored to the
waterbeds to balance net buoyancy.
4) The foundation structure which are constructed at
waterbed to install cable system.
Step by step procedure
1) Construction of tunnel segments on dry dock.
2) Transporting the tunnel segments to their final
places and placing them underwater.
3) Joining of different tunnel segments by using
rubber gasket.
4) Anchoring the tunnel to the cables.
STEP ONE (PRECASTING)
 Huge tunnel sections are constructed on dry dock.
 The procedure consists same as that of precast
construction.
 Dry dock is flooded and the panels are transported to
their respective places.
 Sinking of the panel is controlled by the use of ballast
tank as in case of submarines.
STEP TWO (JOINTS)
 After the submersion of different panels in water they are
connected with one another by using a rubber gasket.
 Another procedure includes trapping of water between
the joints and then removing it afterwards.
STEP THREE (FOUNDATIONS)
 The application consists same as that of in caisson
foundation.
 A hollow chamber is penetrated down the sea bed as
shown which evacuates the water trapped inside it by a
valve present on its top surface.
 Such type of foundations are been used for the offshore
oil rig plants.
STEP FOUR (ANCHORING OF CABLES)
 After the foundation work is completed the cables
are anchored to the floating tunnel which will avoid
its movement and will place it firmly in alignment.
 This operation can be carried out by divers.
 Finally the tunnel will be in position and ready to
use.
Advantages of “SFT”
 Allows construction of tunnel in extremely deep
water, where conventional bridges or tunnels are
technically difficult or prohibitively expensive.
 Any type of cross sectional area can be provided
since being prefabricated.
 No obstruction to navigational routes as compared to
conventional bridges since all of the tunnel being
placed underwater.
 Construction activities has less harmful effects on
aquatic life.
 No harmful environmental effects such as fog or
storm since the whole structure is covered and is
present inside the water.
 Low energy consumption due to more gentle
gradient.
 Vehicular emission can be collected at one end of
the tunnel thus reducing the air pollution.
 Tremendous speed for trains could be obtained by
creating a vacuum inside the tunnel since it will
result in negligible air resistance.
Advantages of “SFT”
TRANSATLANTIC TUNNEL
 AIM- to join north America to west Europe via a
submerged floating tunnel present in the Atlantic
ocean.
 Will require 54000 prefabricated tunnel segments.
 Use of maglev trains for fast travel.
 Maintaining perfect vacuum to avoid air resistance.
 Could travel from New York to London within 54
minutes with a tremendous speed of 8000km/h.
CONCLUSION:-
The submerged floating tunnel will set up new trends in
transportation engineering and which shows with the advances in
technology that will reduce the time required for travelling. And
make the transportation more effective by hiding the traffic under
water by which the beauty of landscape is maintained and valuable
land is available for other purposes. Benefits can be obtained with
respect to less energy consumption, air pollution and reduced
noise emmission.For wide and deep crossings the submerged
floating tunnel may be the only feasible fix link, replacing present
day ferries and providing local communities with new
opportunities for improved communication and regional
development.
PPT

Contenu connexe

Tendances

Submerged tunnel technical seminar
Submerged tunnel technical seminarSubmerged tunnel technical seminar
Submerged tunnel technical seminar
Prashant Ojha
 

Tendances (20)

Transatlantic tunnel-floating-tunnel
Transatlantic tunnel-floating-tunnelTransatlantic tunnel-floating-tunnel
Transatlantic tunnel-floating-tunnel
 
Submerged tunnel ppt
Submerged tunnel pptSubmerged tunnel ppt
Submerged tunnel ppt
 
Transparent concrete
Transparent concreteTransparent concrete
Transparent concrete
 
Pervious concrete
Pervious concretePervious concrete
Pervious concrete
 
Pervious pavement
Pervious pavementPervious pavement
Pervious pavement
 
types of coffer dam
types of coffer dam types of coffer dam
types of coffer dam
 
Creep and shrinkage
Creep and shrinkageCreep and shrinkage
Creep and shrinkage
 
Submerged tunnel technical seminar
Submerged tunnel technical seminarSubmerged tunnel technical seminar
Submerged tunnel technical seminar
 
Pumping of concrete
Pumping of concretePumping of concrete
Pumping of concrete
 
Immersed tunnels
Immersed tunnelsImmersed tunnels
Immersed tunnels
 
Diaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By GaganDiaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By Gagan
 
Underwater concrete
Underwater concreteUnderwater concrete
Underwater concrete
 
NATM ppt sumit
NATM ppt sumitNATM ppt sumit
NATM ppt sumit
 
Construction of diaphragm wall
Construction of diaphragm wallConstruction of diaphragm wall
Construction of diaphragm wall
 
Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
 
Under water concreting
Under water concretingUnder water concreting
Under water concreting
 
PERVIOUS CONCRETE by DEEPAK TIWARI
PERVIOUS CONCRETE by DEEPAK TIWARI PERVIOUS CONCRETE by DEEPAK TIWARI
PERVIOUS CONCRETE by DEEPAK TIWARI
 
Self compaction concrete
Self compaction concreteSelf compaction concrete
Self compaction concrete
 
Immersed tunnels Proposal Mumbai, India
Immersed tunnels Proposal Mumbai, IndiaImmersed tunnels Proposal Mumbai, India
Immersed tunnels Proposal Mumbai, India
 
Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
 

Similaire à PPT

TRANSATLANTIC-TUNNEL-Floating-Tunnel.pptx
TRANSATLANTIC-TUNNEL-Floating-Tunnel.pptxTRANSATLANTIC-TUNNEL-Floating-Tunnel.pptx
TRANSATLANTIC-TUNNEL-Floating-Tunnel.pptx
SoulLoad
 
Fib2010 article260 design & construction_rev_a
Fib2010 article260 design & construction_rev_aFib2010 article260 design & construction_rev_a
Fib2010 article260 design & construction_rev_a
gefyra-rion
 

Similaire à PPT (20)

Floating tunnel
Floating tunnelFloating tunnel
Floating tunnel
 
409967709-Submerged-Floating-tunnel.pptx
409967709-Submerged-Floating-tunnel.pptx409967709-Submerged-Floating-tunnel.pptx
409967709-Submerged-Floating-tunnel.pptx
 
Tunneling
TunnelingTunneling
Tunneling
 
TRANSATLANTIC-TUNNEL-Floating-Tunnel.pptx
TRANSATLANTIC-TUNNEL-Floating-Tunnel.pptxTRANSATLANTIC-TUNNEL-Floating-Tunnel.pptx
TRANSATLANTIC-TUNNEL-Floating-Tunnel.pptx
 
Submerged floating tunnel
Submerged floating tunnel Submerged floating tunnel
Submerged floating tunnel
 
SUBMERGED FLOATING TUNNEL Civil engineering presentation
SUBMERGED FLOATING TUNNEL Civil engineering presentationSUBMERGED FLOATING TUNNEL Civil engineering presentation
SUBMERGED FLOATING TUNNEL Civil engineering presentation
 
1115
11151115
1115
 
Eurasia tunnel1
Eurasia tunnel1Eurasia tunnel1
Eurasia tunnel1
 
Underwater Tunnels
Underwater TunnelsUnderwater Tunnels
Underwater Tunnels
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING
 
Fib2010 article260 design & construction_rev_a
Fib2010 article260 design & construction_rev_aFib2010 article260 design & construction_rev_a
Fib2010 article260 design & construction_rev_a
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling exploration
 
Offshore Structures Presentation
Offshore Structures PresentationOffshore Structures Presentation
Offshore Structures Presentation
 
Offshore 187
Offshore 187Offshore 187
Offshore 187
 
Under ground railway
Under ground railwayUnder ground railway
Under ground railway
 
Underwater construction
Underwater constructionUnderwater construction
Underwater construction
 
The Akashi-Kaikyo Suspension Bridge
The Akashi-Kaikyo Suspension BridgeThe Akashi-Kaikyo Suspension Bridge
The Akashi-Kaikyo Suspension Bridge
 
Group 5 1
Group 5 1Group 5 1
Group 5 1
 
Tunnel boring machines123
Tunnel boring machines123Tunnel boring machines123
Tunnel boring machines123
 
Nikhil Gopi.doc.pptx
Nikhil Gopi.doc.pptxNikhil Gopi.doc.pptx
Nikhil Gopi.doc.pptx
 

PPT

  • 2.
  • 3. Context  Introduction  Materials used  Principle used for Construction an (SFT)  Need for Submerged Floating Tunnels (SFT)  Parameters of an SFT  Construction procedure  Advantages  Transatlantic Tunnels  Conclusion
  • 4. INTRODUCTION  Submerged floating tunnel is basically making a tunnel to float underwater which is balanced by its buoyancy, self weight and constraint forces resulted from cable system and thus submerged to a certain depth underwater.  It is basically tube like structure floating at some depth below water surface and fixed against excessive movements. The tube is designed to accommodate road and or rail traffic.
  • 5. MATERIAL USED:-  As the tunnel is situated at a depth of 30m, it should be perfectly water tight and secondly it should resist the salty sea water and thirdly it should be withstand against hydrostatic forces coming on it.  It is made of 4 layers. Outermost layer is constructed of aluminium to resist the salty sea water. Second and third layer is made of the foam to float the tunnel easily in water. Fourth layer is of concrete which gives strength to the tunnel.
  • 6. “ARCHIMEDES PRINCIPLE”  Any object wholly or partially immersed in an fluid, is buoyed up by a force equal to the weight of the fluid displaced by the object.  this means if more surface area exposed to water surface more are the chances of floating it.  Ships, submarines, offshore oil rigs etc. work on this principle.  Research shows that the buoyancy to weight ratio for the tunnel to float should be less than one and between 0.5 to 0.8
  • 7. PRESENT SCENARIO  They are considered to built when the underneath ground surface is shallow and the tunnel can be placed directly on sea bed and can be covered by sand and backfill material so as to avoid their movement.
  • 8. NEED FOR SUBMERGED FLOATING TUNNEL  A “SFT” is considered when the depth of sea or ocean is too deep so that no tunnel or any solid body could sustain the pressure acting on it at such a deep level.  In that case the tunnel is lifted up such as about 30 to 100m deep from the sea surface where the water pressure is comparatively lower than what is at the bottom depth.
  • 9. PARAMETERS OF AN “SFT” An SFT basically consists of four parts 1) The tunnel structure which is made of different segments 2) The shore connection structure which connects it to shores. 3) The cable systems which are anchored to the waterbeds to balance net buoyancy. 4) The foundation structure which are constructed at waterbed to install cable system.
  • 10. Step by step procedure 1) Construction of tunnel segments on dry dock. 2) Transporting the tunnel segments to their final places and placing them underwater. 3) Joining of different tunnel segments by using rubber gasket. 4) Anchoring the tunnel to the cables.
  • 11. STEP ONE (PRECASTING)  Huge tunnel sections are constructed on dry dock.  The procedure consists same as that of precast construction.  Dry dock is flooded and the panels are transported to their respective places.  Sinking of the panel is controlled by the use of ballast tank as in case of submarines.
  • 12. STEP TWO (JOINTS)  After the submersion of different panels in water they are connected with one another by using a rubber gasket.  Another procedure includes trapping of water between the joints and then removing it afterwards.
  • 13. STEP THREE (FOUNDATIONS)  The application consists same as that of in caisson foundation.  A hollow chamber is penetrated down the sea bed as shown which evacuates the water trapped inside it by a valve present on its top surface.  Such type of foundations are been used for the offshore oil rig plants.
  • 14. STEP FOUR (ANCHORING OF CABLES)  After the foundation work is completed the cables are anchored to the floating tunnel which will avoid its movement and will place it firmly in alignment.  This operation can be carried out by divers.  Finally the tunnel will be in position and ready to use.
  • 15. Advantages of “SFT”  Allows construction of tunnel in extremely deep water, where conventional bridges or tunnels are technically difficult or prohibitively expensive.  Any type of cross sectional area can be provided since being prefabricated.  No obstruction to navigational routes as compared to conventional bridges since all of the tunnel being placed underwater.  Construction activities has less harmful effects on aquatic life.
  • 16.  No harmful environmental effects such as fog or storm since the whole structure is covered and is present inside the water.  Low energy consumption due to more gentle gradient.  Vehicular emission can be collected at one end of the tunnel thus reducing the air pollution.  Tremendous speed for trains could be obtained by creating a vacuum inside the tunnel since it will result in negligible air resistance. Advantages of “SFT”
  • 17. TRANSATLANTIC TUNNEL  AIM- to join north America to west Europe via a submerged floating tunnel present in the Atlantic ocean.  Will require 54000 prefabricated tunnel segments.  Use of maglev trains for fast travel.  Maintaining perfect vacuum to avoid air resistance.  Could travel from New York to London within 54 minutes with a tremendous speed of 8000km/h.
  • 18. CONCLUSION:- The submerged floating tunnel will set up new trends in transportation engineering and which shows with the advances in technology that will reduce the time required for travelling. And make the transportation more effective by hiding the traffic under water by which the beauty of landscape is maintained and valuable land is available for other purposes. Benefits can be obtained with respect to less energy consumption, air pollution and reduced noise emmission.For wide and deep crossings the submerged floating tunnel may be the only feasible fix link, replacing present day ferries and providing local communities with new opportunities for improved communication and regional development.