Installation Instruction
Heatshrink Termination For 3 Core
Polymeric Cables 7.2kV to 36kV
* PLEASE READ INSTRUCTIONS THOROUGHLY BEFORE PROCEEDING *
UNITS E3 CROWN WAY CROWN PARK INDUSTRIAL ESTATE RUSHDEN NORTHANTS NN10 6FD
TEL: +44(0) 1933 356758 FAX: +44(0) 1933 413821 E-MAIL:info@shrinkpolymersystems.co.uk
WEB: www.shrinkpolymersystems.co.uk
INDOOR OUTDOOR
ISSUE DATE: 21.02.17
Download free QR code scanning software
on your smartphone and scan to see a jointer
training video on a termination with earthing
VOLTAGE
INDOOR
L
OUTDOOR
L
X
7.2kV 650mm 700mm
12kV 650mm 700mm LENGTH OF LUG
17.5kV 650mm 700mm BARREL + 5mm
24kV 700mm 800mm
36kV 800mm 900mm
Remove Outer Cable Sheath:
3 Core Cable With Armour
If the cable is armoured, bonding of the armours must be completed using the appropriate
armour earthing kit.
A) For indoor terminations (cable end box) - Order kits Ref: SPS 180, SPS 193 *
B) For outdoor terminations (pole top) - Please advise conductor size and voltage.
2
* SPS 180 - 16-95mm at 7.2 to 17.5kV
2
SPS 193 - 120-300mm at 7.2 to 17.5kV
(For other voltages see selection chart in general catalogue)
IMPORTANT NOTICE TO PURCHASER:- Sellers and Manufacturere’s only obligation shall be to replace such quantity of the product proved to be defective. Neither the Seller nor
Manufacturer shall be liable for any injury, loss or damage, direct or consequential, arising out of the use or inability to use the product. Before using, User shall determine the
suitability of the product for his or her intended use and User assumes all risk and liability whatsoever in connection therewith.
Table 1
General Fitting Instructions
* It is highly recommended that a tool suitable for the removal of the
semi-conductive screen is used to provide a reliable discharge free
termination screen point. See our website for training videos.
* Use a propane gas torch with a soft flame
* Avoid a pencil like blue flame which is caused by unregulated supply
* Keep the flame on the move to ensure even shrinkage of all the
materials and also helps to reduce scorching
* Ensure that all components are kept clean and grease free during
installation
* Allow to cool before applying any mechanical strain
Note:- Dimension “L” is a guide only. The actual
length is determined by the overall geometry of the
equipment.
1. Installation
Prepare the cable as shown.
Note:- The “L” dimension should not be
longer than the distance between bushing
centres and base plate.
De-grease and abrade the cable for a
distance of 100mm below the outer
sheath cut.
Note:- User may wish to alter bedding
and armour dimensions to suit the type of
gland/earthing arrangement to be used.
2. Screen Preparation
Copper Wire Screen
Apply one layer of sealant tape around the
outer cable sheath 30mm below the
sheath cut.
Bend back each screen wires and press
them into the sealant tape. Apply another
layer of tape over the bent back wires.
Twist together to form a conductor and
bond to a suitable earth point.
Note:- If cable has copper screen wires
on each core, bend these back and press
into the mastic tape. Just like the overall
copper screen wires, twist together and
bond to earth.
Copper Tape Screen
Secure the earth braids to the copper tape
screens so that the solder block is
positioned upon the cable bedding. A turn
of mastic sealant tape should be applied
beneath and on top of the solder block.
If a constant force spring is used to
connect the earth braids, the spring
should preferably be positioned above the
fingers of the breakout boot.
These braids will either be bonded to the
earth gland or other suitable earth point.
30mm
SEALANT TAPE
ROLL
SPRINGS
SEALANT TAPE
COPPER
BRAIDS
COPPER TAPE
SCREEN
Bushing centre
100mm
Armours
100mm
Bedding
L
X
100mm
Fig 1
Fig 2
Fig 3
Remove the copper tape screen to length
A+X as indicated in Table 2.
Note:- If the cores are to be crossed the
copper screen should be removed after
the initial setting of the cores.
It may be necessary to temporarily secure
the copper tapes to prevent them from
unwinding.
3. Conductive Layer Treatment
Extruded Conductive Screen Layer
Remove the semi-conductive screen layer
using a suitable tool to dimension B+X as
indicated in Table 2.
Note:- It is very important that the
screen is removed leaving a clean straight
cut and that no scoring or damage is done
to the primary insulation. We highly
recommend the use of approved screen
removal tools (see our website for tools
and demonstration videos). It is good
practice to flame brush the primary
insulation and conductive screen cut, this
has the effect of removing any minor
surface irregularities or burrs that may be
present.
Apply Stress Control Tape
De-grease the insulation and screen using
the solvent tissues provided.
Remove the release paper from the yellow
stress control tape. Stretch to approx.
50% width and apply the tape around the
end of each core screen. Extend onto the
primary insulation by 10mm and about
5mm onto the copper tape screens.
Note: It may not be necessary to use all
of the tape supplied.
B
10mm
5mm
COPPER TAPE
SCREEN
YELLOW STRESS
CONTROL TAPE
X
A
B
Fig 4
Fig 5
Fig 6
Table 2
Voltage
7.2kV
12kV
17.5kV
24kV
36kV
130mm
185mm
240mm
310mm
500mm
A B X
110mm
165mm
220mm
290mm
480mm
Lug Barrel
Length
+ 5mm
4. Stress Control Tubes
Position the stress control tubes onto each
core so that the bottom of each tube
extends past the yellow mastic by a
maximum of 10mm.
Starting at the end closest to the cable
crutch, Shrink each tube one at a time
keep the flame on the move to ensure an
even wall thickness.
5. Installing Cable Lugs
Remove the insulation from each core to
the X dimension in Table 1.
Install cable lug and remove any burrs or
sharp points that may be present.
Preheat each Lug and wrap two layers of
Red Sealant Tape over the Lug barrel and
extend onto the Insulation by approx
10mm. Ensure the Tape is applied as
shown. Important:- use more tape to
build up the diameter to ensure tube
recovers upon it and creates a moisture
seal.
6. Installing The Breakout Boot
Slide the three legged boot over the cores
and push down into the crutch of the
cable. Shrink from the shoulder of the
breakout and down to the cable sheath,
then from the shoulder to the cores.
Apply a turn of red sealant tape around
each breakout turret as shown.
7. Installing The Anti-Track Tube
Position the anti-track tubes so that they
cover the turrets of the breakout boot and
the barrels of the lugs.
Starting from the cable crutch area,
Shrink the tubes in place. Keeping the
flame moving to ensure an even wall
thickness, ensure the tubes are fully
recovered and wrinkle free.
Allow the tubes to cool to hand hot and
trim at the lug end with a sharp knife if
necessary.
ROLL
SPRINGS
X
ANTI-TRACK
TUBE
RED SEALANT
TAPE
Fig 7
Fig 8
Fig 9
Indoor Terminations
To ensure long term performance of
medium voltage terminations, certain
separation distances are required as
indicated in Table 3.
Note:- Bushing protection boots will be
required for the majority of installations.
If it is necessary to cross the cores, the
cross MUST be in a screened area as
shown.
8. Installation Of Rain Sheds
On outdoor terminations the sheds should
be fitted from the bottom up as indicated
in the drawing opposite.
Indoor 36kV terminations are supplied
with one shed per phase and four sheds
per phase for outdoor.
Table 3
NUMBER OF SHEDS PER PHASE
VOLTAGE INDOOR OUTDOOR
7.2kV - 1
12kV - 2
17.5kV - 2
24kV - 3
36kV 1 4
Table 4
The first shed should be fitted at a
distance 200mm from the lower edge of
the anti-track tube to the edge of the
shed. All subsequent sheds should be
fitted at a distance of 80mm from edge to
edge.
Note:- It is advisable not to position rain
sheds at the top of stress control tubes,
re-position if necessary.
d
E
d
AIR CLEARANCE TO
LOCAL SPEC
80mm
200mm
d = SEE
TABLE 4
Fig 10
Fig 11
Fig 12
Distance (d) Phase/Phase
& Phase/Ground
Top of Stress Control Tube
To Bottom of Lug Barrel
Voltage d=(mm) E
7.2kV 15mm
12kV 20mm
17.5kV 20mm
24kV 40mm
36kV 50mm
30mm
50mm
75mm
95mm
250mm
MIN BENDING
RADIUS r = 15xD
D
Inverted Connections
If a termination is to mounted for
connection from above the equipment i.e
in the inverted position, sheds should be
installed through 180° as shown
Cable Bending Radius
During installation care should be taken
not to over bend the cable. In cold
condition it may be necessary to gently
heat the cable to prevent damage whilst
bending.
Fig 13
Fig 14

Contenu connexe

Tendances

7. Heat Shrink Cable Joint (HV) - 11kV Trifurcating (3 Core XLPE to 3 x Sing...
7. Heat Shrink Cable Joint (HV) - 11kV Trifurcating (3 Core XLPE  to 3 x Sing...7. Heat Shrink Cable Joint (HV) - 11kV Trifurcating (3 Core XLPE  to 3 x Sing...
7. Heat Shrink Cable Joint (HV) - 11kV Trifurcating (3 Core XLPE to 3 x Sing...Thorne & Derrick International
 
UNIT - 04 POWER INSTALLATIONS
UNIT - 04 POWER INSTALLATIONSUNIT - 04 POWER INSTALLATIONS
UNIT - 04 POWER INSTALLATIONSPremanandDesai
 
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...Thorne & Derrick International
 
Epp 0317-4 08 solder less(2)
Epp 0317-4 08 solder less(2)Epp 0317-4 08 solder less(2)
Epp 0317-4 08 solder less(2)AKBAR TRADING
 
Nexans Euromold AIN Slip-On Indoor High Voltage HV Cable Termination 33kV 36k...
Nexans Euromold AIN Slip-On Indoor High Voltage HV Cable Termination 33kV 36k...Nexans Euromold AIN Slip-On Indoor High Voltage HV Cable Termination 33kV 36k...
Nexans Euromold AIN Slip-On Indoor High Voltage HV Cable Termination 33kV 36k...Thorne & Derrick International
 
6. Heat Shrink Cable Joint (HV) - 11kV Trifurcating Transition (3 Core PILC t...
6. Heat Shrink Cable Joint (HV) - 11kV Trifurcating Transition (3 Core PILC t...6. Heat Shrink Cable Joint (HV) - 11kV Trifurcating Transition (3 Core PILC t...
6. Heat Shrink Cable Joint (HV) - 11kV Trifurcating Transition (3 Core PILC t...Thorne & Derrick International
 
Cable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - ExampleCable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - ExampleLeonardo ENERGY
 
2. Heat Shrink Cable Termination (HV) - 11kV 33kV Single Core XLPE BS6622 Cables
2. Heat Shrink Cable Termination (HV) - 11kV 33kV Single Core XLPE BS6622 Cables2. Heat Shrink Cable Termination (HV) - 11kV 33kV Single Core XLPE BS6622 Cables
2. Heat Shrink Cable Termination (HV) - 11kV 33kV Single Core XLPE BS6622 CablesThorne & Derrick International
 
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) |AKBAR TRADING EST. SAUDI ARABIA...
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) |AKBAR TRADING EST. SAUDI ARABIA...RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) |AKBAR TRADING EST. SAUDI ARABIA...
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) |AKBAR TRADING EST. SAUDI ARABIA...AKBAR TRADING
 
Pfisterer Connex - Cable Connectors & Systems For Medium Voltage Networks
Pfisterer Connex - Cable Connectors & Systems For Medium Voltage NetworksPfisterer Connex - Cable Connectors & Systems For Medium Voltage Networks
Pfisterer Connex - Cable Connectors & Systems For Medium Voltage NetworksThorne & Derrick UK
 
Technical presentation on modern earthing
Technical presentation on modern earthingTechnical presentation on modern earthing
Technical presentation on modern earthingPankaj Chakraborty
 
Nexans Cable Terminations - Heat Shrink, Cold Shrink, Slip-On
Nexans Cable Terminations - Heat Shrink, Cold Shrink, Slip-OnNexans Cable Terminations - Heat Shrink, Cold Shrink, Slip-On
Nexans Cable Terminations - Heat Shrink, Cold Shrink, Slip-OnThorne & Derrick International
 
EPP-0843-10/11 RAYCHEM JOINT KIT | AKBAR TRADING EST. SAUDI ARABIA|
EPP-0843-10/11 RAYCHEM JOINT KIT | AKBAR TRADING EST. SAUDI ARABIA|EPP-0843-10/11 RAYCHEM JOINT KIT | AKBAR TRADING EST. SAUDI ARABIA|
EPP-0843-10/11 RAYCHEM JOINT KIT | AKBAR TRADING EST. SAUDI ARABIA|AKBAR TRADING
 
UKPN 11kV 6.6kV HV Cable Jointing, Preparation & Installation Manual (Uncontr...
UKPN 11kV 6.6kV HV Cable Jointing, Preparation & Installation Manual (Uncontr...UKPN 11kV 6.6kV HV Cable Jointing, Preparation & Installation Manual (Uncontr...
UKPN 11kV 6.6kV HV Cable Jointing, Preparation & Installation Manual (Uncontr...Thorne & Derrick International
 
Power cable technology in cesc ltd
Power cable technology in cesc ltdPower cable technology in cesc ltd
Power cable technology in cesc ltdAritra Sarkar
 
11kV Heat Shrink Cable Terminations - Prysmian HIT3XC11 3 Core 95-240sqmm 11k...
11kV Heat Shrink Cable Terminations - Prysmian HIT3XC11 3 Core 95-240sqmm 11k...11kV Heat Shrink Cable Terminations - Prysmian HIT3XC11 3 Core 95-240sqmm 11k...
11kV Heat Shrink Cable Terminations - Prysmian HIT3XC11 3 Core 95-240sqmm 11k...Thorne & Derrick International
 

Tendances (20)

Power cables
Power cablesPower cables
Power cables
 
7. Heat Shrink Cable Joint (HV) - 11kV Trifurcating (3 Core XLPE to 3 x Sing...
7. Heat Shrink Cable Joint (HV) - 11kV Trifurcating (3 Core XLPE  to 3 x Sing...7. Heat Shrink Cable Joint (HV) - 11kV Trifurcating (3 Core XLPE  to 3 x Sing...
7. Heat Shrink Cable Joint (HV) - 11kV Trifurcating (3 Core XLPE to 3 x Sing...
 
Cable and laying
Cable and layingCable and laying
Cable and laying
 
UNIT - 04 POWER INSTALLATIONS
UNIT - 04 POWER INSTALLATIONSUNIT - 04 POWER INSTALLATIONS
UNIT - 04 POWER INSTALLATIONS
 
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
Instruction- 3 Core Polymeric (XLPE EPR) 6.6kV-7.2kV Heat Shrink Cable Termin...
 
Epp 0317-4 08 solder less(2)
Epp 0317-4 08 solder less(2)Epp 0317-4 08 solder less(2)
Epp 0317-4 08 solder less(2)
 
3m termination
3m termination3m termination
3m termination
 
Nexans Euromold AIN Slip-On Indoor High Voltage HV Cable Termination 33kV 36k...
Nexans Euromold AIN Slip-On Indoor High Voltage HV Cable Termination 33kV 36k...Nexans Euromold AIN Slip-On Indoor High Voltage HV Cable Termination 33kV 36k...
Nexans Euromold AIN Slip-On Indoor High Voltage HV Cable Termination 33kV 36k...
 
6. Heat Shrink Cable Joint (HV) - 11kV Trifurcating Transition (3 Core PILC t...
6. Heat Shrink Cable Joint (HV) - 11kV Trifurcating Transition (3 Core PILC t...6. Heat Shrink Cable Joint (HV) - 11kV Trifurcating Transition (3 Core PILC t...
6. Heat Shrink Cable Joint (HV) - 11kV Trifurcating Transition (3 Core PILC t...
 
raychem saudi arabia - terminations
raychem saudi arabia - terminations raychem saudi arabia - terminations
raychem saudi arabia - terminations
 
Cable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - ExampleCable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - Example
 
2. Heat Shrink Cable Termination (HV) - 11kV 33kV Single Core XLPE BS6622 Cables
2. Heat Shrink Cable Termination (HV) - 11kV 33kV Single Core XLPE BS6622 Cables2. Heat Shrink Cable Termination (HV) - 11kV 33kV Single Core XLPE BS6622 Cables
2. Heat Shrink Cable Termination (HV) - 11kV 33kV Single Core XLPE BS6622 Cables
 
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) |AKBAR TRADING EST. SAUDI ARABIA...
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) |AKBAR TRADING EST. SAUDI ARABIA...RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) |AKBAR TRADING EST. SAUDI ARABIA...
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) |AKBAR TRADING EST. SAUDI ARABIA...
 
Pfisterer Connex - Cable Connectors & Systems For Medium Voltage Networks
Pfisterer Connex - Cable Connectors & Systems For Medium Voltage NetworksPfisterer Connex - Cable Connectors & Systems For Medium Voltage Networks
Pfisterer Connex - Cable Connectors & Systems For Medium Voltage Networks
 
Technical presentation on modern earthing
Technical presentation on modern earthingTechnical presentation on modern earthing
Technical presentation on modern earthing
 
Nexans Cable Terminations - Heat Shrink, Cold Shrink, Slip-On
Nexans Cable Terminations - Heat Shrink, Cold Shrink, Slip-OnNexans Cable Terminations - Heat Shrink, Cold Shrink, Slip-On
Nexans Cable Terminations - Heat Shrink, Cold Shrink, Slip-On
 
EPP-0843-10/11 RAYCHEM JOINT KIT | AKBAR TRADING EST. SAUDI ARABIA|
EPP-0843-10/11 RAYCHEM JOINT KIT | AKBAR TRADING EST. SAUDI ARABIA|EPP-0843-10/11 RAYCHEM JOINT KIT | AKBAR TRADING EST. SAUDI ARABIA|
EPP-0843-10/11 RAYCHEM JOINT KIT | AKBAR TRADING EST. SAUDI ARABIA|
 
UKPN 11kV 6.6kV HV Cable Jointing, Preparation & Installation Manual (Uncontr...
UKPN 11kV 6.6kV HV Cable Jointing, Preparation & Installation Manual (Uncontr...UKPN 11kV 6.6kV HV Cable Jointing, Preparation & Installation Manual (Uncontr...
UKPN 11kV 6.6kV HV Cable Jointing, Preparation & Installation Manual (Uncontr...
 
Power cable technology in cesc ltd
Power cable technology in cesc ltdPower cable technology in cesc ltd
Power cable technology in cesc ltd
 
11kV Heat Shrink Cable Terminations - Prysmian HIT3XC11 3 Core 95-240sqmm 11k...
11kV Heat Shrink Cable Terminations - Prysmian HIT3XC11 3 Core 95-240sqmm 11k...11kV Heat Shrink Cable Terminations - Prysmian HIT3XC11 3 Core 95-240sqmm 11k...
11kV Heat Shrink Cable Terminations - Prysmian HIT3XC11 3 Core 95-240sqmm 11k...
 

Similaire à 11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A

3. Heat Shrink Cable Joint (HV) - 11kV 3 Core XLPE BS6622 Cables
3. Heat Shrink Cable Joint (HV) - 11kV 3 Core XLPE BS6622 Cables3. Heat Shrink Cable Joint (HV) - 11kV 3 Core XLPE BS6622 Cables
3. Heat Shrink Cable Joint (HV) - 11kV 3 Core XLPE BS6622 CablesThorne & Derrick International
 
Heat shrink cable joint (hv) 11k v 3 core xlpe bs6622 cables
Heat shrink cable joint (hv)   11k v 3 core xlpe bs6622 cablesHeat shrink cable joint (hv)   11k v 3 core xlpe bs6622 cables
Heat shrink cable joint (hv) 11k v 3 core xlpe bs6622 cablesThorne & Derrick International
 
Heat Shrink Cable Joints - 11kV 3 Core XLPE SWA (HV Cable Joints) - SPS SPAJ ...
Heat Shrink Cable Joints - 11kV 3 Core XLPE SWA (HV Cable Joints) - SPS SPAJ ...Heat Shrink Cable Joints - 11kV 3 Core XLPE SWA (HV Cable Joints) - SPS SPAJ ...
Heat Shrink Cable Joints - 11kV 3 Core XLPE SWA (HV Cable Joints) - SPS SPAJ ...Thorne & Derrick International
 
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...Thorne & Derrick International
 
5. Heat Shrink Cable Joint (HV) - 11kV Triplex BS7870 Cables
5. Heat Shrink Cable Joint (HV) - 11kV Triplex BS7870 Cables5. Heat Shrink Cable Joint (HV) - 11kV Triplex BS7870 Cables
5. Heat Shrink Cable Joint (HV) - 11kV Triplex BS7870 CablesThorne & Derrick International
 
Heat Shrink Rail Cable Joints - LSF Zero Halogen Cable Joints - SPS (Installa...
Heat Shrink Rail Cable Joints - LSF Zero Halogen Cable Joints - SPS (Installa...Heat Shrink Rail Cable Joints - LSF Zero Halogen Cable Joints - SPS (Installa...
Heat Shrink Rail Cable Joints - LSF Zero Halogen Cable Joints - SPS (Installa...Thorne & Derrick International
 
Cable Joint Instruction - Zero Halogen Fire Resistant Power Cable Joint (BS7846)
Cable Joint Instruction - Zero Halogen Fire Resistant Power Cable Joint (BS7846)Cable Joint Instruction - Zero Halogen Fire Resistant Power Cable Joint (BS7846)
Cable Joint Instruction - Zero Halogen Fire Resistant Power Cable Joint (BS7846)Thorne & Derrick International
 
25kV Cable Termination - 3M Cold Shrink 95-EP-631-2 - Network Rail PADS Approved
25kV Cable Termination - 3M Cold Shrink 95-EP-631-2 - Network Rail PADS Approved25kV Cable Termination - 3M Cold Shrink 95-EP-631-2 - Network Rail PADS Approved
25kV Cable Termination - 3M Cold Shrink 95-EP-631-2 - Network Rail PADS ApprovedThorne & Derrick International
 
CCG Cable Terminations E1EX-QS Corrosion Guard Cable Glands For Steel / Alumi...
CCG Cable Terminations E1EX-QS Corrosion Guard Cable Glands For Steel / Alumi...CCG Cable Terminations E1EX-QS Corrosion Guard Cable Glands For Steel / Alumi...
CCG Cable Terminations E1EX-QS Corrosion Guard Cable Glands For Steel / Alumi...Thorne & Derrick International
 
3M Scotch 70 Self-Fusing Silicone Rubber Electrical Tape - 3M Self Amalgamati...
3M Scotch 70 Self-Fusing Silicone Rubber Electrical Tape - 3M Self Amalgamati...3M Scotch 70 Self-Fusing Silicone Rubber Electrical Tape - 3M Self Amalgamati...
3M Scotch 70 Self-Fusing Silicone Rubber Electrical Tape - 3M Self Amalgamati...Thorne & Derrick International
 
EtisalatTelecom Model 2016 modified.pptx
EtisalatTelecom Model 2016 modified.pptxEtisalatTelecom Model 2016 modified.pptx
EtisalatTelecom Model 2016 modified.pptxssuser8298f2
 
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE SWA 3 ...
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE SWA 3 ...11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE SWA 3 ...
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE SWA 3 ...Thorne & Derrick International
 
Installation instruction Mineral wool sandwich panels
Installation instruction Mineral wool sandwich panelsInstallation instruction Mineral wool sandwich panels
Installation instruction Mineral wool sandwich panelsMot panels
 
Hawke Universal Cable Glands - Installation Instruction
Hawke Universal Cable Glands - Installation InstructionHawke Universal Cable Glands - Installation Instruction
Hawke Universal Cable Glands - Installation InstructionThorne & Derrick International
 
STI 7554 Instruction Manual
STI 7554 Instruction ManualSTI 7554 Instruction Manual
STI 7554 Instruction ManualJMAC Supply
 
STI 7555AED Instruction Manual
STI 7555AED Instruction ManualSTI 7555AED Instruction Manual
STI 7555AED Instruction ManualJMAC Supply
 
Heat Shrink Cable Joints Instruction - Low Voltage XLPE SWA 0.6kV-3.3kV SPS H...
Heat Shrink Cable Joints Instruction - Low Voltage XLPE SWA 0.6kV-3.3kV SPS H...Heat Shrink Cable Joints Instruction - Low Voltage XLPE SWA 0.6kV-3.3kV SPS H...
Heat Shrink Cable Joints Instruction - Low Voltage XLPE SWA 0.6kV-3.3kV SPS H...Thorne & Derrick International
 
Nexans Euromold Interface F 900 Series Cable Connectors
Nexans Euromold Interface F 900 Series Cable Connectors Nexans Euromold Interface F 900 Series Cable Connectors
Nexans Euromold Interface F 900 Series Cable Connectors Thorne & Derrick International
 

Similaire à 11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A (20)

3. Heat Shrink Cable Joint (HV) - 11kV 3 Core XLPE BS6622 Cables
3. Heat Shrink Cable Joint (HV) - 11kV 3 Core XLPE BS6622 Cables3. Heat Shrink Cable Joint (HV) - 11kV 3 Core XLPE BS6622 Cables
3. Heat Shrink Cable Joint (HV) - 11kV 3 Core XLPE BS6622 Cables
 
Heat shrink cable joint (hv) 11k v 3 core xlpe bs6622 cables
Heat shrink cable joint (hv)   11k v 3 core xlpe bs6622 cablesHeat shrink cable joint (hv)   11k v 3 core xlpe bs6622 cables
Heat shrink cable joint (hv) 11k v 3 core xlpe bs6622 cables
 
Heat Shrink Cable Joints - 11kV 3 Core XLPE SWA (HV Cable Joints) - SPS SPAJ ...
Heat Shrink Cable Joints - 11kV 3 Core XLPE SWA (HV Cable Joints) - SPS SPAJ ...Heat Shrink Cable Joints - 11kV 3 Core XLPE SWA (HV Cable Joints) - SPS SPAJ ...
Heat Shrink Cable Joints - 11kV 3 Core XLPE SWA (HV Cable Joints) - SPS SPAJ ...
 
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE AWA Si...
 
5. Heat Shrink Cable Joint (HV) - 11kV Triplex BS7870 Cables
5. Heat Shrink Cable Joint (HV) - 11kV Triplex BS7870 Cables5. Heat Shrink Cable Joint (HV) - 11kV Triplex BS7870 Cables
5. Heat Shrink Cable Joint (HV) - 11kV Triplex BS7870 Cables
 
Foc pulling
Foc pullingFoc pulling
Foc pulling
 
Quick guide
Quick guideQuick guide
Quick guide
 
Heat Shrink Rail Cable Joints - LSF Zero Halogen Cable Joints - SPS (Installa...
Heat Shrink Rail Cable Joints - LSF Zero Halogen Cable Joints - SPS (Installa...Heat Shrink Rail Cable Joints - LSF Zero Halogen Cable Joints - SPS (Installa...
Heat Shrink Rail Cable Joints - LSF Zero Halogen Cable Joints - SPS (Installa...
 
Cable Joint Instruction - Zero Halogen Fire Resistant Power Cable Joint (BS7846)
Cable Joint Instruction - Zero Halogen Fire Resistant Power Cable Joint (BS7846)Cable Joint Instruction - Zero Halogen Fire Resistant Power Cable Joint (BS7846)
Cable Joint Instruction - Zero Halogen Fire Resistant Power Cable Joint (BS7846)
 
25kV Cable Termination - 3M Cold Shrink 95-EP-631-2 - Network Rail PADS Approved
25kV Cable Termination - 3M Cold Shrink 95-EP-631-2 - Network Rail PADS Approved25kV Cable Termination - 3M Cold Shrink 95-EP-631-2 - Network Rail PADS Approved
25kV Cable Termination - 3M Cold Shrink 95-EP-631-2 - Network Rail PADS Approved
 
CCG Cable Terminations E1EX-QS Corrosion Guard Cable Glands For Steel / Alumi...
CCG Cable Terminations E1EX-QS Corrosion Guard Cable Glands For Steel / Alumi...CCG Cable Terminations E1EX-QS Corrosion Guard Cable Glands For Steel / Alumi...
CCG Cable Terminations E1EX-QS Corrosion Guard Cable Glands For Steel / Alumi...
 
3M Scotch 70 Self-Fusing Silicone Rubber Electrical Tape - 3M Self Amalgamati...
3M Scotch 70 Self-Fusing Silicone Rubber Electrical Tape - 3M Self Amalgamati...3M Scotch 70 Self-Fusing Silicone Rubber Electrical Tape - 3M Self Amalgamati...
3M Scotch 70 Self-Fusing Silicone Rubber Electrical Tape - 3M Self Amalgamati...
 
EtisalatTelecom Model 2016 modified.pptx
EtisalatTelecom Model 2016 modified.pptxEtisalatTelecom Model 2016 modified.pptx
EtisalatTelecom Model 2016 modified.pptx
 
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE SWA 3 ...
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE SWA 3 ...11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE SWA 3 ...
11kV 33kV Heat Shrink Terminations - Outdoor Armour Earthing Kits XLPE SWA 3 ...
 
Installation instruction Mineral wool sandwich panels
Installation instruction Mineral wool sandwich panelsInstallation instruction Mineral wool sandwich panels
Installation instruction Mineral wool sandwich panels
 
Hawke Universal Cable Glands - Installation Instruction
Hawke Universal Cable Glands - Installation InstructionHawke Universal Cable Glands - Installation Instruction
Hawke Universal Cable Glands - Installation Instruction
 
STI 7554 Instruction Manual
STI 7554 Instruction ManualSTI 7554 Instruction Manual
STI 7554 Instruction Manual
 
STI 7555AED Instruction Manual
STI 7555AED Instruction ManualSTI 7555AED Instruction Manual
STI 7555AED Instruction Manual
 
Heat Shrink Cable Joints Instruction - Low Voltage XLPE SWA 0.6kV-3.3kV SPS H...
Heat Shrink Cable Joints Instruction - Low Voltage XLPE SWA 0.6kV-3.3kV SPS H...Heat Shrink Cable Joints Instruction - Low Voltage XLPE SWA 0.6kV-3.3kV SPS H...
Heat Shrink Cable Joints Instruction - Low Voltage XLPE SWA 0.6kV-3.3kV SPS H...
 
Nexans Euromold Interface F 900 Series Cable Connectors
Nexans Euromold Interface F 900 Series Cable Connectors Nexans Euromold Interface F 900 Series Cable Connectors
Nexans Euromold Interface F 900 Series Cable Connectors
 

Plus de Thorne & Derrick International

Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Thorne & Derrick International
 
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical EqptTHORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical EqptThorne & Derrick International
 
The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018Thorne & Derrick International
 
3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick InternationalThorne & Derrick International
 
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...Thorne & Derrick International
 
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...Thorne & Derrick International
 
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam RowePepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam RoweThorne & Derrick International
 
Ultrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification DemandUltrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification DemandThorne & Derrick International
 
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282DSIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282DThorne & Derrick International
 
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...Thorne & Derrick International
 
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec SheetFiloform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec SheetThorne & Derrick International
 

Plus de Thorne & Derrick International (20)

Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...
 
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical EqptTHORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
 
The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018
 
3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International
 
CATU Electrical Safety Catalogue
CATU Electrical Safety CatalogueCATU Electrical Safety Catalogue
CATU Electrical Safety Catalogue
 
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
 
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
 
Roxtec Cable Transit - B Frame Dimensional Drawing
Roxtec Cable Transit - B Frame Dimensional DrawingRoxtec Cable Transit - B Frame Dimensional Drawing
Roxtec Cable Transit - B Frame Dimensional Drawing
 
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam RowePepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
 
T&D Experts In Equipment For Explosive Atmospheres
T&D Experts In Equipment For Explosive AtmospheresT&D Experts In Equipment For Explosive Atmospheres
T&D Experts In Equipment For Explosive Atmospheres
 
Ultrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification DemandUltrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification Demand
 
Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016
 
Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick Process Heating Brochure 2016Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick Process Heating Brochure 2016
 
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282DSIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
 
Ripley Utility Tool Cable Preparation Tools
Ripley Utility Tool Cable Preparation ToolsRipley Utility Tool Cable Preparation Tools
Ripley Utility Tool Cable Preparation Tools
 
RIDGID micro CD100 Combustible Gas Detector
RIDGID micro CD100 Combustible Gas DetectorRIDGID micro CD100 Combustible Gas Detector
RIDGID micro CD100 Combustible Gas Detector
 
Itron Fact Sheet
Itron Fact SheetItron Fact Sheet
Itron Fact Sheet
 
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
 
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec SheetFiloform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
 
Eltherm Self-Regulating Trace Heating Cables
Eltherm Self-Regulating Trace Heating CablesEltherm Self-Regulating Trace Heating Cables
Eltherm Self-Regulating Trace Heating Cables
 

Dernier

Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 

Dernier (20)

Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 

11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A

  • 1. Installation Instruction Heatshrink Termination For 3 Core Polymeric Cables 7.2kV to 36kV * PLEASE READ INSTRUCTIONS THOROUGHLY BEFORE PROCEEDING * UNITS E3 CROWN WAY CROWN PARK INDUSTRIAL ESTATE RUSHDEN NORTHANTS NN10 6FD TEL: +44(0) 1933 356758 FAX: +44(0) 1933 413821 E-MAIL:info@shrinkpolymersystems.co.uk WEB: www.shrinkpolymersystems.co.uk INDOOR OUTDOOR ISSUE DATE: 21.02.17 Download free QR code scanning software on your smartphone and scan to see a jointer training video on a termination with earthing
  • 2. VOLTAGE INDOOR L OUTDOOR L X 7.2kV 650mm 700mm 12kV 650mm 700mm LENGTH OF LUG 17.5kV 650mm 700mm BARREL + 5mm 24kV 700mm 800mm 36kV 800mm 900mm Remove Outer Cable Sheath: 3 Core Cable With Armour If the cable is armoured, bonding of the armours must be completed using the appropriate armour earthing kit. A) For indoor terminations (cable end box) - Order kits Ref: SPS 180, SPS 193 * B) For outdoor terminations (pole top) - Please advise conductor size and voltage. 2 * SPS 180 - 16-95mm at 7.2 to 17.5kV 2 SPS 193 - 120-300mm at 7.2 to 17.5kV (For other voltages see selection chart in general catalogue) IMPORTANT NOTICE TO PURCHASER:- Sellers and Manufacturere’s only obligation shall be to replace such quantity of the product proved to be defective. Neither the Seller nor Manufacturer shall be liable for any injury, loss or damage, direct or consequential, arising out of the use or inability to use the product. Before using, User shall determine the suitability of the product for his or her intended use and User assumes all risk and liability whatsoever in connection therewith. Table 1 General Fitting Instructions * It is highly recommended that a tool suitable for the removal of the semi-conductive screen is used to provide a reliable discharge free termination screen point. See our website for training videos. * Use a propane gas torch with a soft flame * Avoid a pencil like blue flame which is caused by unregulated supply * Keep the flame on the move to ensure even shrinkage of all the materials and also helps to reduce scorching * Ensure that all components are kept clean and grease free during installation * Allow to cool before applying any mechanical strain Note:- Dimension “L” is a guide only. The actual length is determined by the overall geometry of the equipment.
  • 3. 1. Installation Prepare the cable as shown. Note:- The “L” dimension should not be longer than the distance between bushing centres and base plate. De-grease and abrade the cable for a distance of 100mm below the outer sheath cut. Note:- User may wish to alter bedding and armour dimensions to suit the type of gland/earthing arrangement to be used. 2. Screen Preparation Copper Wire Screen Apply one layer of sealant tape around the outer cable sheath 30mm below the sheath cut. Bend back each screen wires and press them into the sealant tape. Apply another layer of tape over the bent back wires. Twist together to form a conductor and bond to a suitable earth point. Note:- If cable has copper screen wires on each core, bend these back and press into the mastic tape. Just like the overall copper screen wires, twist together and bond to earth. Copper Tape Screen Secure the earth braids to the copper tape screens so that the solder block is positioned upon the cable bedding. A turn of mastic sealant tape should be applied beneath and on top of the solder block. If a constant force spring is used to connect the earth braids, the spring should preferably be positioned above the fingers of the breakout boot. These braids will either be bonded to the earth gland or other suitable earth point. 30mm SEALANT TAPE ROLL SPRINGS SEALANT TAPE COPPER BRAIDS COPPER TAPE SCREEN Bushing centre 100mm Armours 100mm Bedding L X 100mm Fig 1 Fig 2 Fig 3
  • 4. Remove the copper tape screen to length A+X as indicated in Table 2. Note:- If the cores are to be crossed the copper screen should be removed after the initial setting of the cores. It may be necessary to temporarily secure the copper tapes to prevent them from unwinding. 3. Conductive Layer Treatment Extruded Conductive Screen Layer Remove the semi-conductive screen layer using a suitable tool to dimension B+X as indicated in Table 2. Note:- It is very important that the screen is removed leaving a clean straight cut and that no scoring or damage is done to the primary insulation. We highly recommend the use of approved screen removal tools (see our website for tools and demonstration videos). It is good practice to flame brush the primary insulation and conductive screen cut, this has the effect of removing any minor surface irregularities or burrs that may be present. Apply Stress Control Tape De-grease the insulation and screen using the solvent tissues provided. Remove the release paper from the yellow stress control tape. Stretch to approx. 50% width and apply the tape around the end of each core screen. Extend onto the primary insulation by 10mm and about 5mm onto the copper tape screens. Note: It may not be necessary to use all of the tape supplied. B 10mm 5mm COPPER TAPE SCREEN YELLOW STRESS CONTROL TAPE X A B Fig 4 Fig 5 Fig 6 Table 2 Voltage 7.2kV 12kV 17.5kV 24kV 36kV 130mm 185mm 240mm 310mm 500mm A B X 110mm 165mm 220mm 290mm 480mm Lug Barrel Length + 5mm
  • 5. 4. Stress Control Tubes Position the stress control tubes onto each core so that the bottom of each tube extends past the yellow mastic by a maximum of 10mm. Starting at the end closest to the cable crutch, Shrink each tube one at a time keep the flame on the move to ensure an even wall thickness. 5. Installing Cable Lugs Remove the insulation from each core to the X dimension in Table 1. Install cable lug and remove any burrs or sharp points that may be present. Preheat each Lug and wrap two layers of Red Sealant Tape over the Lug barrel and extend onto the Insulation by approx 10mm. Ensure the Tape is applied as shown. Important:- use more tape to build up the diameter to ensure tube recovers upon it and creates a moisture seal. 6. Installing The Breakout Boot Slide the three legged boot over the cores and push down into the crutch of the cable. Shrink from the shoulder of the breakout and down to the cable sheath, then from the shoulder to the cores. Apply a turn of red sealant tape around each breakout turret as shown. 7. Installing The Anti-Track Tube Position the anti-track tubes so that they cover the turrets of the breakout boot and the barrels of the lugs. Starting from the cable crutch area, Shrink the tubes in place. Keeping the flame moving to ensure an even wall thickness, ensure the tubes are fully recovered and wrinkle free. Allow the tubes to cool to hand hot and trim at the lug end with a sharp knife if necessary. ROLL SPRINGS X ANTI-TRACK TUBE RED SEALANT TAPE Fig 7 Fig 8 Fig 9
  • 6. Indoor Terminations To ensure long term performance of medium voltage terminations, certain separation distances are required as indicated in Table 3. Note:- Bushing protection boots will be required for the majority of installations. If it is necessary to cross the cores, the cross MUST be in a screened area as shown. 8. Installation Of Rain Sheds On outdoor terminations the sheds should be fitted from the bottom up as indicated in the drawing opposite. Indoor 36kV terminations are supplied with one shed per phase and four sheds per phase for outdoor. Table 3 NUMBER OF SHEDS PER PHASE VOLTAGE INDOOR OUTDOOR 7.2kV - 1 12kV - 2 17.5kV - 2 24kV - 3 36kV 1 4 Table 4 The first shed should be fitted at a distance 200mm from the lower edge of the anti-track tube to the edge of the shed. All subsequent sheds should be fitted at a distance of 80mm from edge to edge. Note:- It is advisable not to position rain sheds at the top of stress control tubes, re-position if necessary. d E d AIR CLEARANCE TO LOCAL SPEC 80mm 200mm d = SEE TABLE 4 Fig 10 Fig 11 Fig 12 Distance (d) Phase/Phase & Phase/Ground Top of Stress Control Tube To Bottom of Lug Barrel Voltage d=(mm) E 7.2kV 15mm 12kV 20mm 17.5kV 20mm 24kV 40mm 36kV 50mm 30mm 50mm 75mm 95mm 250mm
  • 7. MIN BENDING RADIUS r = 15xD D Inverted Connections If a termination is to mounted for connection from above the equipment i.e in the inverted position, sheds should be installed through 180° as shown Cable Bending Radius During installation care should be taken not to over bend the cable. In cold condition it may be necessary to gently heat the cable to prevent damage whilst bending. Fig 13 Fig 14