SlideShare une entreprise Scribd logo
1  sur  4
Télécharger pour lire hors ligne
TEMPORARY SITE CABLES
KEEPING ELECTRICITY
AVAILABLE
exa n s
THE FLEXIBILITY TO ACT
MORE QUICKLY
Construction within
substations
•	 Ideal tool for installing temporaries in transformer 		
	substations
• 	Reducing the disconnecting times of transmission 		
	 lines during conversion
• 	Flexible terminations can be installed quickly and in 	
	 a small space
• 	The cables can be rechecked for partial discharge 		
	 after beeing used
Replacing temporary
overhead lines
• 	Replacing the temporary installation of overhead 		
	lines
• 	Provisional connection of existing overhead lines if 		
	 new ones have to cross
• 	Depending on length required, the cables will be 		
	 simply rolled out and connected
• 	Reduce risk of recourse claims
The construction of new power plants and the growing demand for renewable energy sources has increased
the need to expand and/or convert networks into transformer substations or onto overhead line towers.
As a key player in the energy industry, Nexans is pleased to offer a safe and flexible component for such
projects – pre terminated temporary site cables. These cables can be used to temporarily connect equipment
in a high voltage network, e.g. as a bypass during construction or repair and servicing work, or during
emergencies such as natural disasters or severe weather. When faults occur in overhead or underground
lines, temporary site cables make it possible to restore energy transmission rapidly. While modification work
is underway in a transformer station, temporary connections can be rapidly installed between transformers
and switchgear systems or overhead lines.
Temporary site cables are available from stock or can be manufactured to meet your specific requirements.
PERFECT SOLUTION FOR TEMPORARY USE
At home, at work,
out and about –
there is no life without electrical energy. Electricity is
available at any time; this goes without saying. To ensure
that this remains the case, overhead lines and transformer
substations must always be ready for operation, even if
the transmission grids have to be adapted. Temporary site
cables are perfect for reducing the disconnecting times
of transmission paths during conversion. The cables are
a practical and simple solution as they make it easier
modernize switching sections in substations.
BENEFITS FOR CUSTOMERS
Temporary site cables have
the same design as high
voltage cables but with a
reduced insulation thickness.
This makes them easier to
handle on the construction
site. The cables have a
standardized conductor
cross section of 150 mm2
(300 kcmil) or 300 mm2
(600 kcmil). Depending on customer
requirements, the length can vary between 50 m (65 ft) and
500 m (1640 ft) or more. They are delivered on a special
single chamber or three chamber drum. This special drum
design facilitates safe winding and unwinding of the cable
and the pre-installed terminations.
DESIGN
In case of emergencies
• 	Can be used immediately
• 	The energy supply can be quickly restored, even in
	 emergencies and malfunctions
• 	Can be installed regardless of weather conditions 		
	 including friged temperatures
• 	Temporary site 	cables are save and easy to use and 	
	 secure the supply
Pre-installed flexible silicone rubber
terminations for easy handling
Due to the conditions under which temporary site cables
are installed, the accessories must be easy to use and
have a wide range of possible applications. Nexans’
pre-installed flexible silicone rubber terminations
facilitate use in any position. Thanks to their low weight,
the terminations can operate without any additional
support structures. Their monobloc design makes the
terminations suitable for all voltages from 72.5 kV to
230 kV and up to 750 A per system. Two systems in
parallel double capacity to 1500 A. This setup offers
maximum flexibility and operational reliability.
Advantages of temporary
site cables and accessories
•	Optimized cable design for small bending radii
•	Reduced insulation thickness in order to reduce 		
	 weight and to improve handling
•	The pre-installed silicone rubber terminations are
	 maintenance free and routine tested for partial 		
	 discharge up to a test voltage of 2.5 x U0
. Following 	
	 every use, a new partial discharge measurement 		
	 can be performed on the cables in order to rule out 		
	 possible damage.
•	Special single or three chamber drums make
	 transportation and handling much easier
Mr. Schindelbauer:
Westnetz
„The disconnect times of the
electrical systems are frequently
only short and timed Precisely.
It is a major advantage here
that temporary site cables can
be installed regardless of the
weather Conditions as well as
at minus temperatures.“
„Thanks to their ease of use,
temporary site cables allow the
supply to be restored quickly
and safely if faults arise
in the grid or transformer
station.“
REFERENCES
ACTUAL REFERENCE LIST AVAILABLE UPON REQUEST
Nexans Deutschland GmbH
Land High Voltage Contracting
Kabelkamp 20 · 30179 Hannover · Tel. +49 511 676-3364 · Fax +49 511 676-2254
eMail: hv-team.nd@nexans.com · www.nexans.com
exa n s
Global expert in cables and cabling systems
About Nexans
Nexans brings energy to life through an extensive range of cables and cabling
solutions that deliver increased performance for our customers worldwide. Nexans’
teams are committed to a partnership approach that supports customers in four main
business areas: Power transmission and distribution (submarine and land), Energy
resources (Oil & Gas, Mining and Renewables), Transportation (Road, Rail, Air, Sea)
and Building (Commercial, Residential and Data Centers). Nexans’ strategy is founded
on continuous innovation in products, solutions and services, employee development,
customer training and the introduction of safe, low -environmental- impact industrial
processes.
More information on www.nexans.com
November2015·Copyright©NEXANS

Contenu connexe

Tendances

Electrical wiring BY Jemish
Electrical wiring BY JemishElectrical wiring BY Jemish
Electrical wiring BY JemishGoti Jemish
 
Design considerations of electrical installations
Design considerations of electrical installationsDesign considerations of electrical installations
Design considerations of electrical installationsvishalgohel12195
 
Building electric circuit
Building electric circuitBuilding electric circuit
Building electric circuiteddie fonte
 
Electrical Systems in a Building
Electrical Systems in a BuildingElectrical Systems in a Building
Electrical Systems in a BuildingGAURAV. H .TANDON
 
ppt on fuse by madhav chhabra
ppt on fuse by madhav chhabrappt on fuse by madhav chhabra
ppt on fuse by madhav chhabraMadhav Chhabra
 
Hospital wiring SYSTEM
Hospital wiring SYSTEMHospital wiring SYSTEM
Hospital wiring SYSTEMAISWARYA TV
 
Distribution boards & switch gears by v guard
Distribution boards & switch gears by v guardDistribution boards & switch gears by v guard
Distribution boards & switch gears by v guardV-GUARD INDUSTRIES LTD
 
Transmission lines of Electrical powe
Transmission lines of Electrical poweTransmission lines of Electrical powe
Transmission lines of Electrical poweDarya khan
 
Mechanical Design of Overhead Lines
Mechanical Design of Overhead LinesMechanical Design of Overhead Lines
Mechanical Design of Overhead LinesRanjeet Kumar
 
Comparison of overhead and underground transmission lines
Comparison of overhead and underground transmission linesComparison of overhead and underground transmission lines
Comparison of overhead and underground transmission linesahmed usama
 
Building Services Engg. (Electrical installations)
Building Services Engg. (Electrical installations)Building Services Engg. (Electrical installations)
Building Services Engg. (Electrical installations)Ritesh Ambadkar
 
insulators, conductors, transformer and ac motors
insulators, conductors, transformer and ac motorsinsulators, conductors, transformer and ac motors
insulators, conductors, transformer and ac motorsChippa Srikanth
 

Tendances (20)

Electrical wiring BY Jemish
Electrical wiring BY JemishElectrical wiring BY Jemish
Electrical wiring BY Jemish
 
Electrical System Design
Electrical System Design Electrical System Design
Electrical System Design
 
Design considerations of electrical installations
Design considerations of electrical installationsDesign considerations of electrical installations
Design considerations of electrical installations
 
Insulators
InsulatorsInsulators
Insulators
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Building electric circuit
Building electric circuitBuilding electric circuit
Building electric circuit
 
Electrical Systems in a Building
Electrical Systems in a BuildingElectrical Systems in a Building
Electrical Systems in a Building
 
ppt on fuse by madhav chhabra
ppt on fuse by madhav chhabrappt on fuse by madhav chhabra
ppt on fuse by madhav chhabra
 
Hospital wiring SYSTEM
Hospital wiring SYSTEMHospital wiring SYSTEM
Hospital wiring SYSTEM
 
Distribution boards & switch gears by v guard
Distribution boards & switch gears by v guardDistribution boards & switch gears by v guard
Distribution boards & switch gears by v guard
 
Transmission lines of Electrical powe
Transmission lines of Electrical poweTransmission lines of Electrical powe
Transmission lines of Electrical powe
 
Mechanical Design of Overhead Lines
Mechanical Design of Overhead LinesMechanical Design of Overhead Lines
Mechanical Design of Overhead Lines
 
Comparison of overhead and underground transmission lines
Comparison of overhead and underground transmission linesComparison of overhead and underground transmission lines
Comparison of overhead and underground transmission lines
 
Building Services Engg. (Electrical installations)
Building Services Engg. (Electrical installations)Building Services Engg. (Electrical installations)
Building Services Engg. (Electrical installations)
 
Electrical services
Electrical servicesElectrical services
Electrical services
 
Choosing Electrical Panels
Choosing Electrical PanelsChoosing Electrical Panels
Choosing Electrical Panels
 
Electrical wiring
Electrical wiringElectrical wiring
Electrical wiring
 
insulators, conductors, transformer and ac motors
insulators, conductors, transformer and ac motorsinsulators, conductors, transformer and ac motors
insulators, conductors, transformer and ac motors
 
ELECTRICAL WIRING
ELECTRICAL WIRINGELECTRICAL WIRING
ELECTRICAL WIRING
 
Eat105 chapter 2
Eat105 chapter 2Eat105 chapter 2
Eat105 chapter 2
 

En vedette

Pfisterer ESF & Pfisterer EST - High Voltage Dry Outdoor Cable Terminations
Pfisterer ESF & Pfisterer EST - High Voltage Dry Outdoor Cable TerminationsPfisterer ESF & Pfisterer EST - High Voltage Dry Outdoor Cable Terminations
Pfisterer ESF & Pfisterer EST - High Voltage Dry Outdoor Cable TerminationsThorne & Derrick International
 
Perennial Dilemmas in English Education
Perennial Dilemmas in English EducationPerennial Dilemmas in English Education
Perennial Dilemmas in English EducationDiane Phelps, PhD
 
Pozoblanco Patricia Molina Palma
 Pozoblanco Patricia Molina Palma  Pozoblanco Patricia Molina Palma
Pozoblanco Patricia Molina Palma iesalonsocano
 
POSHAN District Nutrition Profile_Aurangabad_Bihar
POSHAN District Nutrition Profile_Aurangabad_BiharPOSHAN District Nutrition Profile_Aurangabad_Bihar
POSHAN District Nutrition Profile_Aurangabad_BiharPOSHAN
 
KQ 1Q 2015 FINALFinal
KQ 1Q 2015 FINALFinalKQ 1Q 2015 FINALFinal
KQ 1Q 2015 FINALFinalBrent Keeter
 
Don't quit your day job: Finding the right balance for you - David Brodie & C...
Don't quit your day job: Finding the right balance for you - David Brodie & C...Don't quit your day job: Finding the right balance for you - David Brodie & C...
Don't quit your day job: Finding the right balance for you - David Brodie & C...TBEX
 
Informe semestral ene octubre 2015 proyectos promovidos.
Informe  semestral ene octubre 2015 proyectos promovidos.Informe  semestral ene octubre 2015 proyectos promovidos.
Informe semestral ene octubre 2015 proyectos promovidos.Hermel Cabrera
 
Pathways and Signposts
Pathways and SignpostsPathways and Signposts
Pathways and SignpostsTony Crispino
 
Couponomy handout
Couponomy handoutCouponomy handout
Couponomy handoutMike Taylor
 
ANWR - Oil or Wilderness?
ANWR - Oil or Wilderness?  ANWR - Oil or Wilderness?
ANWR - Oil or Wilderness? Eva Do
 
Linked Data Experiences at Springer Nature
Linked Data Experiences at Springer NatureLinked Data Experiences at Springer Nature
Linked Data Experiences at Springer NatureMichele Pasin
 
Rryma elektrike
Rryma elektrikeRryma elektrike
Rryma elektrikeflori daut
 
Solving Today's B2B Multi-channel Marketing Challenges
Solving Today's B2B Multi-channel Marketing ChallengesSolving Today's B2B Multi-channel Marketing Challenges
Solving Today's B2B Multi-channel Marketing ChallengeseMarketing Strategy
 
Sources of electricity маслей дарья блажковавероника 10 кл
Sources of electricity маслей дарья  блажковавероника 10 клSources of electricity маслей дарья  блажковавероника 10 кл
Sources of electricity маслей дарья блажковавероника 10 клVictorushka
 
El camino del héroe clase 1
El camino del héroe   clase 1El camino del héroe   clase 1
El camino del héroe clase 1cursavirtual
 

En vedette (20)

Pfisterer ESF & Pfisterer EST - High Voltage Dry Outdoor Cable Terminations
Pfisterer ESF & Pfisterer EST - High Voltage Dry Outdoor Cable TerminationsPfisterer ESF & Pfisterer EST - High Voltage Dry Outdoor Cable Terminations
Pfisterer ESF & Pfisterer EST - High Voltage Dry Outdoor Cable Terminations
 
Cablesafe Cable Hooks - Presentation
Cablesafe Cable Hooks - PresentationCablesafe Cable Hooks - Presentation
Cablesafe Cable Hooks - Presentation
 
Perennial Dilemmas in English Education
Perennial Dilemmas in English EducationPerennial Dilemmas in English Education
Perennial Dilemmas in English Education
 
Hans schaffers smartcities
Hans schaffers smartcitiesHans schaffers smartcities
Hans schaffers smartcities
 
IPTeL Overview
IPTeL OverviewIPTeL Overview
IPTeL Overview
 
Pozoblanco Patricia Molina Palma
 Pozoblanco Patricia Molina Palma  Pozoblanco Patricia Molina Palma
Pozoblanco Patricia Molina Palma
 
POSHAN District Nutrition Profile_Aurangabad_Bihar
POSHAN District Nutrition Profile_Aurangabad_BiharPOSHAN District Nutrition Profile_Aurangabad_Bihar
POSHAN District Nutrition Profile_Aurangabad_Bihar
 
KQ 1Q 2015 FINALFinal
KQ 1Q 2015 FINALFinalKQ 1Q 2015 FINALFinal
KQ 1Q 2015 FINALFinal
 
Don't quit your day job: Finding the right balance for you - David Brodie & C...
Don't quit your day job: Finding the right balance for you - David Brodie & C...Don't quit your day job: Finding the right balance for you - David Brodie & C...
Don't quit your day job: Finding the right balance for you - David Brodie & C...
 
Informe semestral ene octubre 2015 proyectos promovidos.
Informe  semestral ene octubre 2015 proyectos promovidos.Informe  semestral ene octubre 2015 proyectos promovidos.
Informe semestral ene octubre 2015 proyectos promovidos.
 
Detection of vulnerable plaque by nis
Detection of vulnerable plaque by nisDetection of vulnerable plaque by nis
Detection of vulnerable plaque by nis
 
Pathways and Signposts
Pathways and SignpostsPathways and Signposts
Pathways and Signposts
 
Couponomy handout
Couponomy handoutCouponomy handout
Couponomy handout
 
ANWR - Oil or Wilderness?
ANWR - Oil or Wilderness?  ANWR - Oil or Wilderness?
ANWR - Oil or Wilderness?
 
Lactancia Materna
Lactancia MaternaLactancia Materna
Lactancia Materna
 
Linked Data Experiences at Springer Nature
Linked Data Experiences at Springer NatureLinked Data Experiences at Springer Nature
Linked Data Experiences at Springer Nature
 
Rryma elektrike
Rryma elektrikeRryma elektrike
Rryma elektrike
 
Solving Today's B2B Multi-channel Marketing Challenges
Solving Today's B2B Multi-channel Marketing ChallengesSolving Today's B2B Multi-channel Marketing Challenges
Solving Today's B2B Multi-channel Marketing Challenges
 
Sources of electricity маслей дарья блажковавероника 10 кл
Sources of electricity маслей дарья  блажковавероника 10 клSources of electricity маслей дарья  блажковавероника 10 кл
Sources of electricity маслей дарья блажковавероника 10 кл
 
El camino del héroe clase 1
El camino del héroe   clase 1El camino del héroe   clase 1
El camino del héroe clase 1
 

Similaire à Nexans Cable Leads Keep High Voltage Energy Transmission Flowing - 110kV, 132kV & 220kV

Sam cables presentation
Sam cables presentation Sam cables presentation
Sam cables presentation Ankit Joshi
 
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWARFACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWARashwini kumar
 
InnovAction reinforced Ground-check conductor
InnovAction reinforced Ground-check conductorInnovAction reinforced Ground-check conductor
InnovAction reinforced Ground-check conductorJorge Cofr
 
PPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptxPPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptxayazkhan261
 
PPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptxPPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptxayazkhan261
 
3M Medium Voltage Cold Shrink Cable Joints & Terminations
3M Medium Voltage Cold Shrink Cable Joints & Terminations3M Medium Voltage Cold Shrink Cable Joints & Terminations
3M Medium Voltage Cold Shrink Cable Joints & TerminationsThorne & Derrick International
 
Transformer Designing
Transformer Designing Transformer Designing
Transformer Designing Praveen Sharma
 
Flexible Cables Solution
Flexible Cables SolutionFlexible Cables Solution
Flexible Cables Solutionprysmianaus
 
Wiring system building services
Wiring system building servicesWiring system building services
Wiring system building servicesManishaBisht26
 
report on electrical wiring
report on electrical wiringreport on electrical wiring
report on electrical wiringAbhidada123
 
Underground cables/sanjeet-1308143
Underground cables/sanjeet-1308143Underground cables/sanjeet-1308143
Underground cables/sanjeet-1308143sanjeet kumar
 
8-step-by-step-processes.9772018.pptx
8-step-by-step-processes.9772018.pptx8-step-by-step-processes.9772018.pptx
8-step-by-step-processes.9772018.pptxPTD QUYCOCTU
 
8 step-by-step processes of manufacturing of electrical cable
8 step-by-step processes of manufacturing of electrical cable8 step-by-step processes of manufacturing of electrical cable
8 step-by-step processes of manufacturing of electrical cableDevanshVarma1
 

Similaire à Nexans Cable Leads Keep High Voltage Energy Transmission Flowing - 110kV, 132kV & 220kV (20)

Conductix Wampfler Product Overview Cables
Conductix Wampfler Product Overview CablesConductix Wampfler Product Overview Cables
Conductix Wampfler Product Overview Cables
 
Gis4
Gis4Gis4
Gis4
 
How expulsion fuses enhance
How expulsion fuses enhanceHow expulsion fuses enhance
How expulsion fuses enhance
 
Sam cables presentation
Sam cables presentation Sam cables presentation
Sam cables presentation
 
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWARFACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
 
cables.pptx
cables.pptxcables.pptx
cables.pptx
 
InnovAction reinforced Ground-check conductor
InnovAction reinforced Ground-check conductorInnovAction reinforced Ground-check conductor
InnovAction reinforced Ground-check conductor
 
PPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptxPPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptx
 
PPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptxPPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptx
 
Gagan
GaganGagan
Gagan
 
3M Medium Voltage Cold Shrink Cable Joints & Terminations
3M Medium Voltage Cold Shrink Cable Joints & Terminations3M Medium Voltage Cold Shrink Cable Joints & Terminations
3M Medium Voltage Cold Shrink Cable Joints & Terminations
 
Ca vd4 50k-a(en)y_1vcp000001
Ca vd4 50k-a(en)y_1vcp000001Ca vd4 50k-a(en)y_1vcp000001
Ca vd4 50k-a(en)y_1vcp000001
 
Nexans WINDLINK Cable Solutions For Wind Turbines
Nexans WINDLINK Cable Solutions For Wind TurbinesNexans WINDLINK Cable Solutions For Wind Turbines
Nexans WINDLINK Cable Solutions For Wind Turbines
 
Transformer Designing
Transformer Designing Transformer Designing
Transformer Designing
 
Flexible Cables Solution
Flexible Cables SolutionFlexible Cables Solution
Flexible Cables Solution
 
Wiring system building services
Wiring system building servicesWiring system building services
Wiring system building services
 
report on electrical wiring
report on electrical wiringreport on electrical wiring
report on electrical wiring
 
Underground cables/sanjeet-1308143
Underground cables/sanjeet-1308143Underground cables/sanjeet-1308143
Underground cables/sanjeet-1308143
 
8-step-by-step-processes.9772018.pptx
8-step-by-step-processes.9772018.pptx8-step-by-step-processes.9772018.pptx
8-step-by-step-processes.9772018.pptx
 
8 step-by-step processes of manufacturing of electrical cable
8 step-by-step processes of manufacturing of electrical cable8 step-by-step processes of manufacturing of electrical cable
8 step-by-step processes of manufacturing of electrical cable
 

Plus de Thorne & Derrick International

Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Thorne & Derrick International
 
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical EqptTHORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical EqptThorne & Derrick International
 
The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018Thorne & Derrick International
 
3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick InternationalThorne & Derrick International
 
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-AThorne & Derrick International
 
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...Thorne & Derrick International
 
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...Thorne & Derrick International
 
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam RowePepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam RoweThorne & Derrick International
 
Ultrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification DemandUltrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification DemandThorne & Derrick International
 
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282DSIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282DThorne & Derrick International
 
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...Thorne & Derrick International
 
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec SheetFiloform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec SheetThorne & Derrick International
 

Plus de Thorne & Derrick International (20)

Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...Isolation procedures for safe working on electrical systems and equipment by ...
Isolation procedures for safe working on electrical systems and equipment by ...
 
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical EqptTHORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
THORNE & DERRICK LV MV HV Jointing, Earthing, Substation & Electrical Eqpt
 
The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018The Children North East Annual Golf Day Wednesday 9th May 2018
The Children North East Annual Golf Day Wednesday 9th May 2018
 
3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International3M Electrical Products Stocked By Thorne & Derrick International
3M Electrical Products Stocked By Thorne & Derrick International
 
CATU Electrical Safety Catalogue
CATU Electrical Safety CatalogueCATU Electrical Safety Catalogue
CATU Electrical Safety Catalogue
 
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
11kV Cable Termination Heat Shrink Kits 3 Core 16-25sqmm SPS 3TIS-12X-A
 
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
THORNE + DERRICK : LV, MV & HV Cable Installation, Jointing, Substation & Ele...
 
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
Ex d Enclosures - Explosion Proof Hazardous Area Technor EJB Galvanised Steel...
 
Roxtec Cable Transit - B Frame Dimensional Drawing
Roxtec Cable Transit - B Frame Dimensional DrawingRoxtec Cable Transit - B Frame Dimensional Drawing
Roxtec Cable Transit - B Frame Dimensional Drawing
 
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam RowePepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
Pepperl & Fuchs SIL Training Certificate - T&D Adam Rowe
 
T&D Experts In Equipment For Explosive Atmospheres
T&D Experts In Equipment For Explosive AtmospheresT&D Experts In Equipment For Explosive Atmospheres
T&D Experts In Equipment For Explosive Atmospheres
 
Ultrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification DemandUltrasonic Flow Meters - Customer Specification Demand
Ultrasonic Flow Meters - Customer Specification Demand
 
Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016Emtelle Fibre Optic Cables - Product Catalogue 2016
Emtelle Fibre Optic Cables - Product Catalogue 2016
 
Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick Process Heating Brochure 2016Thorne & Derrick Process Heating Brochure 2016
Thorne & Derrick Process Heating Brochure 2016
 
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282DSIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
SIRAI ASCO Numatics Solenoid Valves WRAS Approved - SIRAI L182D L282D
 
Ripley Utility Tool Cable Preparation Tools
Ripley Utility Tool Cable Preparation ToolsRipley Utility Tool Cable Preparation Tools
Ripley Utility Tool Cable Preparation Tools
 
RIDGID micro CD100 Combustible Gas Detector
RIDGID micro CD100 Combustible Gas DetectorRIDGID micro CD100 Combustible Gas Detector
RIDGID micro CD100 Combustible Gas Detector
 
Itron Fact Sheet
Itron Fact SheetItron Fact Sheet
Itron Fact Sheet
 
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
United Nations Environment Programme (UNEP) ‘2006 Report of the Refrigeration...
 
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec SheetFiloform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
Filoform FiloSeal+HD Reenterable LV HV Power Cable Duct Seal System - Spec Sheet
 

Dernier

Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAndikSusilo4
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?XfilesPro
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 

Dernier (20)

Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping Elbows
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
Azure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & ApplicationAzure Monitor & Application Insight to monitor Infrastructure & Application
Azure Monitor & Application Insight to monitor Infrastructure & Application
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 

Nexans Cable Leads Keep High Voltage Energy Transmission Flowing - 110kV, 132kV & 220kV

  • 1. TEMPORARY SITE CABLES KEEPING ELECTRICITY AVAILABLE exa n s
  • 2. THE FLEXIBILITY TO ACT MORE QUICKLY Construction within substations • Ideal tool for installing temporaries in transformer substations • Reducing the disconnecting times of transmission lines during conversion • Flexible terminations can be installed quickly and in a small space • The cables can be rechecked for partial discharge after beeing used Replacing temporary overhead lines • Replacing the temporary installation of overhead lines • Provisional connection of existing overhead lines if new ones have to cross • Depending on length required, the cables will be simply rolled out and connected • Reduce risk of recourse claims The construction of new power plants and the growing demand for renewable energy sources has increased the need to expand and/or convert networks into transformer substations or onto overhead line towers. As a key player in the energy industry, Nexans is pleased to offer a safe and flexible component for such projects – pre terminated temporary site cables. These cables can be used to temporarily connect equipment in a high voltage network, e.g. as a bypass during construction or repair and servicing work, or during emergencies such as natural disasters or severe weather. When faults occur in overhead or underground lines, temporary site cables make it possible to restore energy transmission rapidly. While modification work is underway in a transformer station, temporary connections can be rapidly installed between transformers and switchgear systems or overhead lines. Temporary site cables are available from stock or can be manufactured to meet your specific requirements. PERFECT SOLUTION FOR TEMPORARY USE At home, at work, out and about – there is no life without electrical energy. Electricity is available at any time; this goes without saying. To ensure that this remains the case, overhead lines and transformer substations must always be ready for operation, even if the transmission grids have to be adapted. Temporary site cables are perfect for reducing the disconnecting times of transmission paths during conversion. The cables are a practical and simple solution as they make it easier modernize switching sections in substations. BENEFITS FOR CUSTOMERS
  • 3. Temporary site cables have the same design as high voltage cables but with a reduced insulation thickness. This makes them easier to handle on the construction site. The cables have a standardized conductor cross section of 150 mm2 (300 kcmil) or 300 mm2 (600 kcmil). Depending on customer requirements, the length can vary between 50 m (65 ft) and 500 m (1640 ft) or more. They are delivered on a special single chamber or three chamber drum. This special drum design facilitates safe winding and unwinding of the cable and the pre-installed terminations. DESIGN In case of emergencies • Can be used immediately • The energy supply can be quickly restored, even in emergencies and malfunctions • Can be installed regardless of weather conditions including friged temperatures • Temporary site cables are save and easy to use and secure the supply Pre-installed flexible silicone rubber terminations for easy handling Due to the conditions under which temporary site cables are installed, the accessories must be easy to use and have a wide range of possible applications. Nexans’ pre-installed flexible silicone rubber terminations facilitate use in any position. Thanks to their low weight, the terminations can operate without any additional support structures. Their monobloc design makes the terminations suitable for all voltages from 72.5 kV to 230 kV and up to 750 A per system. Two systems in parallel double capacity to 1500 A. This setup offers maximum flexibility and operational reliability. Advantages of temporary site cables and accessories • Optimized cable design for small bending radii • Reduced insulation thickness in order to reduce weight and to improve handling • The pre-installed silicone rubber terminations are maintenance free and routine tested for partial discharge up to a test voltage of 2.5 x U0 . Following every use, a new partial discharge measurement can be performed on the cables in order to rule out possible damage. • Special single or three chamber drums make transportation and handling much easier Mr. Schindelbauer: Westnetz „The disconnect times of the electrical systems are frequently only short and timed Precisely. It is a major advantage here that temporary site cables can be installed regardless of the weather Conditions as well as at minus temperatures.“ „Thanks to their ease of use, temporary site cables allow the supply to be restored quickly and safely if faults arise in the grid or transformer station.“ REFERENCES ACTUAL REFERENCE LIST AVAILABLE UPON REQUEST
  • 4. Nexans Deutschland GmbH Land High Voltage Contracting Kabelkamp 20 · 30179 Hannover · Tel. +49 511 676-3364 · Fax +49 511 676-2254 eMail: hv-team.nd@nexans.com · www.nexans.com exa n s Global expert in cables and cabling systems About Nexans Nexans brings energy to life through an extensive range of cables and cabling solutions that deliver increased performance for our customers worldwide. Nexans’ teams are committed to a partnership approach that supports customers in four main business areas: Power transmission and distribution (submarine and land), Energy resources (Oil & Gas, Mining and Renewables), Transportation (Road, Rail, Air, Sea) and Building (Commercial, Residential and Data Centers). Nexans’ strategy is founded on continuous innovation in products, solutions and services, employee development, customer training and the introduction of safe, low -environmental- impact industrial processes. More information on www.nexans.com November2015·Copyright©NEXANS