Residential
Construction
Practices
Let’s Build a House Together!
(3) Credit Continuing Education Course
…and a great class!
Continuing Education Providers
are subject to audit by the State of Connecticut
Please:
Mute your cell phone
Use electronic devices judiciously
Remain in attendance until the
end of the class (or we can’t issue
your credits)
Thank you!
Your Credits….
Are submitted electronically to the State of Connecticut
by Tiger Real Estate School
Tiger Real Estate School will email you a
Certificate of Completion within 14 days
Please make sure we don’t land in “spam” and be sure
to save your Certificate where you can find it
There is a $25.00 fee to reissue a Certificate
Startling Statistics!
How many Jobs are created for each single
family home built? (According to NAHB)
Five?
Seven?
One?
Three?
Tax Revenue
How much government tax revenue
is created for each single family
home built?
$ 24,000?
$ 110,000?
$ 74,000?
$ 58,000?
$ 90,000?
Annual Housing Starts
How many national housing starts do
we need to accommodate growing
population and older
housing stock?
950,000?
1.7 million?
3 million?
1.2 million?
2.1 million?
10 Year U.S. Housing Starts
Connecticut Housing Permits
1st
Q 2016 1,088
2015 6,077
2014 5,329
2013 5,424
2012 4,669
2011 3,173
2010 3,932
2005 11,885
CONTENTS
Building codes
Foundation systems
Loads on buildings
Floor systems
Wall systems
Roof systems
Roofing
Siding
Decks
Insulation
Finish work
Doors and windows
Special construction
Heating systems
Cooling
Air quality
Water and Waste
Electrical
Building Codes
Regulate:
 design
 construction
 alteration
 repair of buildings
in order to protect the public
safety, health, and welfare
Major Model Codes
The National Building Code
 BOCA (Building Officials and Code Administrators)
The Uniform Building Code (UBC)
 ICBO (International Conference of Building Officials)
The Standard Building Code
International Building Code
 IBC
 Publication in 2003
International Energy Conservation Code
Companion Codes
Developed to govern other more
specific aspects of construction
such as plumbing and mechanical work.
May be developed by states or local
municipalities, most are published by the same
groups that publish the model codes.
The 2016 CONNECTICUT STATE BUILDING CODE
has been approved and will be effective for all permit
applications on or after OCTOBER 1, 2016.
The 2016 CONNECTICUT FIRE SAFETY CODE
has been approved and will be effective for all permit
applications on or after OCTOBER 1, 2016
Connecticut Building Codes
Electrical Code 2011 NEC (NFPA-70)
Accessibility Code ICC/ANSI A117.1 2003
Elevator Code 2005 CT State Elevator Code (ASME A17.1-1996 with 1997 &
1998 Addenda)
Gas Code CT State Regulations Boiler Code ASME Boiler & Pressure Vessel
Code; NBIC
Energy Code 2009 International Energy Conservation Code (re-adopted with
changes)
Let’s Build A House!
Basic 2400 sq ft colonial
 Not a lot of “bells &
whistles”
 Costs a/o August
2016
 Average
construction quality
 Located in
subdivision – land
price not included
Construction Cost
Estimate based on the
book
National Building
Cost Manual
published by Craftsman
Book Company
Single family residence built under competitive
conditions in or near Fairfield County
 Foundation for normal soil conditions
 Excavation for foundation and piers on a prepared
building pad
 Floor, wall, interior and exterior finishes, roof cover,
interior partitions, doors, windows, trim
 Electric wiring and fixtures
 Rough and finish plumbing, built-in appliances
 Supervision, design fees, permits, utility hook-ups, the
contractor's contingency, overhead and profit.
*Add the cost of the land, government-mandated site development
fees and the cost of bringing utility lines to the site
2400 Square Feet
What’s This?
4 BR, 2.5 Baths, Masonry Fireplace, Full Basement
http://www.building-cost.net/CornersType.asp
Site Preparation
Protecting the Environment
Foundation Systems
Foundation Footing
Footing Drainage
Foundation Walls
Damp Sealing
Insulation & Vapor
Barriers
Insulated concrete
forms
Radon Resistant
New Construction
Footing & Drain Details
Prefabricated Foundations
Insulated Concrete Forms
Poured Concrete Foundation
Foundation Insulation
Alternative to our selection
Slab insulation detail
Pre-Slab & Finish Details
Radon Resistant New Construction
Are You Ready….
It’s
time
for…
Which of the following most
closely reflects the cost of
equipment and labor for:
Excavation:
1. Labor $5,143 Equipment $1,332
Excavation Total $6,475
2. Labor $2,050, Equipment $1,062,
Excavation Total $3,112
Which of the following most
closely reflects the cost of
materials, equipment and labor
for:
Foundation, Piers,
Flatwork:
1. Materials $4,639, Labor $9,050, Equipment $1,062
Foundation, Piers, Flatwork Total $14,751
2. Material $11,152, Labor $17,426, Equipment $2,709
Foundation, Piers, Flatwork Total $31,287
Which of the following most
closely reflects the cost of
materials and labor for:
Rough Carpentry:
1. Materials $41,953, Labor $27,935,
Rough Carpentry Total $69,888
2. Material $36,060, Labor $52,886,
Rough Carpentry Total $88,946
How much have we spent so
far…
Excavation $6,475
Foundation, Piers, Flatwork $31,287
Rough Hardware $3,060*
Rough Carpentry $88,946
$129,768
Structural and Exterior Building Systems
Floor System Components
Engineered Systems Basement Insulation
Wood Joists
Wood Stud
Framing
System
Double Top Plate
Cripple Studs
Headers
King Stud
Jack Stud
Window Sill
Bottom Plate
Window & Door
R.O.
Engineered Framing Systems
The Role of
Mechanical Fasteners
Mechanical Fasteners
Understanding the Importance of Proper
Mechanical Connections
Sheathing Options
Oriented Strand Board or Plywood
Have been common choices.
A whole new sheathing system is
available now.
The Huber Zip System:
Structural
Insulated
Panels (SIPS)
Eliminates the
thermal bridge
that occurs
with
conventional
frame
construction.
SIP houses are
very tight and
insulate
extremely well.
SIPS Truss Framing
SIPS
Roof Systems
Rooflines
Roof Terminology
Ridge
Dormer
Eave
Gable
Ridge Board
Ridge Beam
Knee Wall
Engineered Roofing System
Material Costs Excluding Labor
Roof Flashing & Drainage
Most Popular Roofing Material
PV Roofing protects from
the elements and also
generates electricity
Newest solar
product
Pleasing to
Homeowners
Not as visually
apparent as
standard solar
electric
modules
Dow Solar Roof
The Savings
Doors & Windows
To Finish the Close-In
 Masonry Veneer
 Exterior Plywood Finishes
 Wood Shingles/Shakes
 Board Siding
 Stucco Finishes
 Synthetic Products
 Wood or Composite Trim
 Flashing
Siding & Trim
Air & Vapor Barriers
Siding & Trim
No Shortage
of Siding or
Trim Options
For The Home
Wood
Vinyl
Cement
PVC
LVL
Poly-foam
Hardboard
Finger-
jointed
Wood
• Foundation
• Framing
• Flashing
• Stairs & Railings
• Finish Materials
Decks
Deck Support Method
Flashing for pressure-treated wood
Contains higher
concentrations of
copper
Could quickly corrode
the critical aluminum
flashings, fasteners, and
connectors
Use stainless steel or
copper to prevent
galvanic reaction
Handrails and Decking Materials
Composite decking
combines recycled
plastic and wood fiber
Ensuring Deck Safety
Critical Deck Connections
1. Ledger Attachment
2. Joist-to-Ledger
3. Joist-to-Beam
4. Beam-to-Post
5. Railing Post-to-Deck Framing
6. Stair Stringer-to-Deck Framing
7. Stair Tread-to-Stringer
8. Post-to-Concrete
Let’s Review…
Top 10 New Construction Defects
1. No insulation installed in the attic
2. Missing proper roof vents, or vent holes cut, but roofed over
3. Windows installed improperly
4. Hot and Cold water reversed at faucets, tubs, and showers
5. Drains clogged with debris from construction process
6. Inoperable or missing GFCI’s in required areas
7. Heat vents missing, not connected
8. Cut trusses in roof or floor trusses
9. Tempered glass missing in required areas
10. Improperly installed roofing, flashing, or roof jacks
Are Your Ready?
Let’s Play…….
Name That Defect!!
Name that Defect!
Name that Defect!
Name that Defect!
Name that Defect!
Name that Defect!
Name that Defect!
Name that Defect(s)!
Name that Defect!
Name that Defect!
B R E A KB R E A K
15 MINUTE15 MINUTE
2016 – 2018
(3) Credit Continuing Education Courses
 Don’t Let Water Intrusion Sink Your Deal!
 Smart Energy Updates for Existing Homes
 Innovation in Sustainable Housing – Green Building Best Practices
This Old Connecticut House
 Minimize Your Risk, Maximize Your Earnings
 Environmental Issues – Evolution to Resolution
 What to Expect When We’re Inspecting!
 Mold to Sold!
 Residential Building Practices
Your Opinion Matters….
Before the end of
class, please take a
moment to complete
our evaluation form…
Energy Conservation in
New Construction
 Energy Use And Code Considerations
 Doors And Windows
 Insulation And The Building Envelope
 Conservation Systems
 Mechanical Systems
 Indoor Air Quality
 Finishing The Interior
Energy Use Breakdown
better codes mean better
benefits.
Doors and Windows
DOOR & WINDOW SELECTION
Solar gain rating
Window orientation
What to look for in
windows
 Glazing
 Sashes and frames
 Performance ratings
Energy-Efficient design
Building Envelope Specific Requirements
Conditioned space
Building Envelope consists of:
Fenestration
Ceilings
Walls
Above grade
Below grade
Mass walls
Floors
Slab
Crawl space
Areas for Air Leakage (Infiltration)
Windows and doors
Between sole plates
Floors and exterior wall panels
Plumbing
Electrical
Service access doors or hatches
Recessed light fixtures
How to Air Seal an Attic
Super-insulated, Airtight
Envelope
Insulation materials
Thermal mass
Air tightness
Moisture control
Too tight
Common Insulation Types
Spray-In Insulation
Good R-values-up to 6.5
per inch-do an
exceptionally good job
of air sealing
Best product to stop air
movement through
walls
Available in both low-
density, open-cell and
high-density, closed-cell
varieties
Applied with specialized
spray equipment
Low-density foams are
more vapor permeable
than high-density
foams, but they both
form extremely effective
air barriers
Wall Insulation and Installation
Ceiling Insulation and
Installation
Thermal By-pass sealing
Is critical for maintenance
of the Building Envelope
Basement and Crawlspace
(Insulation and Installation)
Foundation and Floor Framing
Both Require Good Insulation
Fiberglass/Cellulose Spray foam
Approximately
$1.50 - $2.00
per square foot
$6.00 - $7.00
per square foot
R49 Standard Insulation Costs
Air Sealing for New Home
Construction
Blending
Air- Sealing
and a variety
of insulation
Materials for
an air-tight
Home
Duct Insulation and Sealing
Duct Tightness Testing
Building Cavities as
Supply Ducts
No, No, No, No!!!!
Putting all of the sealing
Activities in place before
Testing the home
Blower Door
Are You Ready….
It’s
time
for…
Which of the following most
closely reflects the cost of
materials and labor for:
Roofing, Flashing,
Fascia:
1. Material $9,967, Labor $11,680
Roofing, Flashing, Fascia Total $21,647
2. Material $15,077, Labor $12,564
Roofing, Flashing, Fascia Total $27,641
Which of the following most
closely reflects the cost of
materials and labor for:
Exterior Trim and
Finish:
1. Material $15,559, Labor $10,434, Equipment $1,343
Exterior Trim and Finish Total $27,336
2. Material $25,648, Labor $15,879, Equipment $1,370
Exterior Trim and Finish Total $42,897
Which of the following most
closely reflects the cost of
materials and labor for:
Insulation:
1. Material $6,231, Labor $2,638,
Insulation Total $8,869
2. Material $6,753, Labor $4,586,
Insulation Total $11,339
Which of the following most
closely reflects the cost of
materials and labor for:
Doors(including garage)
Windows:
1. Materials $5,720, Labor $8,155
Door/Window Total $13,875
2. Materials $10,528 Labor $7,211,
Door/Window Total $17,739
How much have we spent so
far…
Excavation $6,475
Foundation, Piers, Flatwork $31,287
Rough Hardware $3,060*
Rough Carpentry $88,946
Roof, Flashing, & Fascia $27,641
Insulation $11,339
Exterior Trim & Finish $35,639
Doors/Windows $17,739
Finish Hardware* $1,007
$223,133
Lighting Compliance Requirements
Compact Fluorescent Bulbs - CFL
Light Emitting Diode Bulbs – LED
Sealed Recessed Lighting
RESPECTING and CONSERVING
WATER
Home Water Conservation
Water-efficient plumbing
fixtures and appliances
Hot water distribution
Design landscape to
conserve water
Home Run
Plumbing
Newest Supply Systems
Include:
CPVC Piping
Manifold Distribution
Individual Shut Offs
PEX Tubing
Minimal Joints
Labeled Distribution
Hot Water
Re-circulation
with timer
controls
Toilets, Showerheads, Faucets
1992 conservation act
mandated water
conserving plumbing
fixtures
1.6 gallons per flush,
many are less than 1.3
gallons
Saves 30,000 gallons
per year – over $100
Electrical
Conventional Service
Circuits
Wiring
GFCI
AFCI
GFI Tester
Ground Fault Interrupter Arc Fault Interrupter
Electrical
PHOTOVOLTAICS (PV)
Direct conversion of
sunlight
Utilizes a
semiconductor to
create electron flow
Water Heating
Heating
Supply
Supply systems
Hybrid & On Demand Water Heating
How does an on demand tankless water heater
work?
Solar Hot Water Heating
Heating & Cooling Systems
• Forced Air Heating
• Hot Water & Steam Heating
• Electric Heating
• Radiant Heating
• Geothermal Heating
• Heat Pump
• Active Solar Energy
• Passive Solar
• HRV
• Air Conditioning Condenser
• Heat Pump in Cooling Mode
• Split ductless Systems
High Efficiency Heating Systems
How boilers work
Wall Mounted Condensing Gas
Boiler
Radiant Heat
Dual Mode Heating & Cooling Systems
Split Cooling Systems
Heat Pumps and
Ductless Systems
Differentiating High Efficiency HVAC
Systems
A split HVAC system - multiple sections
Indoor coil section in the ductwork
Outdoor coil section (compressor/condenser) installed on the outside of
the home
Inside the home (attic, basement, closet) there may be a combined fan
and air conditioning coil in one box or separate coil and fan sections
which can house a gas or oil heating furnace
 Package system contains all components in one box
(compressor, condenser, fan) typically found installed outside the
home, in some cases on the roof and ducted into the home
Two Configurations for AC or Heat
Pumps
Ductless Mini Split Heat Pump
Ground Source Heat Pump
Basement Geothermal Equipment
Air Quality
Night flushing – Attic Fan
Heat Recovery Ventilators
Ventilators – Kitchen/Bath
Balanced Ventilation
System
Incoming and
outgoing
airstreams
balance one
another
Heat in the
outgoing
airstream can
be captured
with an HRV or
ERV
Improve Air Quality Duct Configuration
Heat Recovery Ventilation
(HRV)
Video Heat Recovery Ventilation
Interior Components
Stair Requirements
Wood Stairs
Spiral Stairs
Fireplaces
Fireplace Requirements
Masonry Chimneys
Prefab Fireplaces & Stoves
Efficient Fireplaces and Gas, Propane,
or Pellet Type Burning Appliances
One Minute Break –
Your Opinion Matters….
Please take a moment
to complete our
evaluation form…
Finish Work
•Gypsum Board
•Ceramic Tile
•Countertops
•Cabinetry
•Hardware/Metals
•Wood Flooring
•Wood Moldings & Trim
Gypsum Board Application
Drywall Preparation
Hanging/Fastening
Taping and Finishing
Ceramic Tile
Please refer to your handout
Cabinetry &Hardware
Wood
Thermofoil
Painted MDF
Stainless
Veneer
Materials used for box construction
Wood Moldings and Trim
Cove moldings
Crown moldings
Cornice
 Cornice is a molded
projection that crowns a
wall
 Picture molding is a
horizontal molding
Rails
 Plate rail is a narrow shelf
fixed along a wall and
grooved to hold plates for
ornament or display
Baseboard
 Baseboards conceal and
finish the joints where
sidewalls meet the floors
Molding – Wood/Composite
Cost comparisons of
Different materials
Labor costs largely
unaffected
Flooring Options (per square foot, installed)
Carpet ($2.00 - $15.00 )
Wood ($6.00 - $15.00)
Engineered Wood ($4.00 - $18.00)
Stone ($8.00 - $50.00)
Ceramic/Porcelain ($4.00 - $12.00)
Laminate ($3.00 - $7.00)
Bamboo ($4.00 - $8.00)
Vinyl ($1.00 - $7.00)
Linoleum ($2.00 - $9.00)
Cork ($3.00 - $7.00)
Source – World Flooring Association
Accessible Design
 Wider doors
 Entry without stairs
 Barrier free shower
 Key services on
first floor
 Sinks/Countertops
wheelchair friendly
 Transfer ledge/grab bars in
bathroom
Are You Ready….
It’s
time
for…
Which of the following most
closely reflects the cost of
materials and labor for:
Plumbing Rough In,
Connection & Fixtures:
1. Material $18,588, Labor $18,716,
Plumbing Total $37,309
2. Material $9,740, Labor $9,080,
Plumbing Total $18,820
Which of the following most
closely reflects the cost of
materials and labor for:
Heating & Cooling:
1. Material $6,204, Labor $9,305
Heating and Cooling Systems Total $15,509
2. Material $20,055, Labor $6,080
Heating and Cooling Systems Total $26,135
Which of the following most
closely reflects the cost of
materials and labor for:
Interior Wall Finish:
1. Material $9,605, Labor $14,737
Interior Wall Finish Total $24,342
2. Material $2,441, Labor $7,564
Interior Wall Finish Total $10,005
Masonry Fireplace in
First Floor Family
Room
Brick Fireplace (and Chimney)
without a raised hearth. Is the
Labor and Material Cost for the
Fireplace higher or lower than
$7,250 ??
$12,11
0
Which of the following most
closely reflects the cost of
materials and labor for:
Wiring and Light
Fixtures:
1. Labor $9,557, Material $7,739, Total $17,296
2. Labor $4,050, Material $5,752, Total $9,802
Finish
Carpentry
Is the Labor and Material Cost for
Finish Carpentry higher or lower
than
$4,250 ??
$9,303
Painting
Is the Labor and Material
Cost for Painting higher
or lower than
$10,750 ??
$19,052
Finishes (builder grade)
The following are approximate budget guidelines for our New Build:
Cabinets……………….. $17,625
Countertops…………… $7,486
Flooring………………… $10,343
Carpeting………………. $11,567
Appliances……………… $7,440
Bath Accessories, Tub/Shower Enclosure… $5,885
Are you ready?
Let’s play…
What’s HOT…….What’s NOT!!!What’s HOT…….What’s NOT!!!
2016 Building Trends
(according to National Association of Home Builders
And National Kitchen & Bath Association)
According to NAHB, what
is the biggest change in
residential construction?
Homes are getting bigger
Homes are getting smaller
What rooms are being
left out of home design?
3rd
bathroom
Formal dining Room
Mudroom
All of the above
What is the number 1 choice
for kitchen flooring?
Tile
Hardwood
Tile that looks like hardwood
Marble
What countertop material
is most popular?
Marble
Wood
Granite
Quartz/Engineered Stone
Concrete
Stainless Steel
What home features are both
Boomers and Millenials
looking for?
1.Large, spacious interiors
2.High Tech features
3.Open floor plans
4.Outdoor spaces
5.Access to shopping
6.Located near major highways
What home features are least
important to Millenials?
1.Separate Laundry Room
2.Walk in closets
3.Energy efficiency
4.Family Rooms
5.Outdoor kitchens
How Much did
our New Build
Cost???
Subtotal Direct Job Costs
Material ……………………….. $199,228
Labor …………………………. $221,048
Equipment …………………… $6,903
Total $427,179
The Cost of
“Doing
Business..”
Indirect Job Costs
Final Cleanup Total ………..$1,760
Insurance Total……………..$12,322
Permits & Utilities Total…… $7,481
Plans & Specs Total……….. $1,760
Total $23,323
Are we going to make
any money??
Contractor Markup Total $55,008
Grand Total……$505,510
Plus cost of land!
Complete & Ready For Sale
Thank You!!
Questions??
www.tigerinspect.com
Thank you!

Contenu connexe

Tendances

Customize Modular Homes Fayetteville NC
Customize Modular Homes Fayetteville NCCustomize Modular Homes Fayetteville NC
Customize Modular Homes Fayetteville NCgoodlife123
 
Construction technology
Construction technologyConstruction technology
Construction technologyChristy Brewer
 
Tim dettlaff presentation fmli nov 13 2014
Tim dettlaff presentation   fmli nov 13 2014Tim dettlaff presentation   fmli nov 13 2014
Tim dettlaff presentation fmli nov 13 2014MikeWorsfold
 
Home Insulation Tips for Renovators
Home Insulation Tips for RenovatorsHome Insulation Tips for Renovators
Home Insulation Tips for RenovatorsJay Schultz
 
Rotary District Conference Presentation
Rotary District Conference Presentation Rotary District Conference Presentation
Rotary District Conference Presentation SisalHouse
 
Andersen 100 Series Commercial Project Case Studies
Andersen 100 Series Commercial Project Case StudiesAndersen 100 Series Commercial Project Case Studies
Andersen 100 Series Commercial Project Case StudiesAndersen Windows
 
Silverton-en
Silverton-enSilverton-en
Silverton-enlibnam
 
Building an A-rated Home - Back to the Future
Building an A-rated Home - Back to the FutureBuilding an A-rated Home - Back to the Future
Building an A-rated Home - Back to the FutureEd O'Donoghue
 
Wood in Buildings: Steps to Durability and Longevity
Wood in Buildings: Steps to Durability and LongevityWood in Buildings: Steps to Durability and Longevity
Wood in Buildings: Steps to Durability and LongevityThink Wood
 
2014 updated portfolio of Riaan de Villiers
2014 updated portfolio of Riaan de Villiers2014 updated portfolio of Riaan de Villiers
2014 updated portfolio of Riaan de VilliersRiaan De Villiers
 
Airtight Construction - Step 1 of The Seven Steps of Building a Synergy Home
Airtight Construction - Step 1 of The Seven Steps of Building a Synergy HomeAirtight Construction - Step 1 of The Seven Steps of Building a Synergy Home
Airtight Construction - Step 1 of The Seven Steps of Building a Synergy HomeTodd Witt
 
Tomorrow's homes... today!, constructores
Tomorrow's homes... today!, constructoresTomorrow's homes... today!, constructores
Tomorrow's homes... today!, constructoresSunwayHomes
 

Tendances (20)

Customize Modular Homes Fayetteville NC
Customize Modular Homes Fayetteville NCCustomize Modular Homes Fayetteville NC
Customize Modular Homes Fayetteville NC
 
Construction technology
Construction technologyConstruction technology
Construction technology
 
Tim dettlaff presentation fmli nov 13 2014
Tim dettlaff presentation   fmli nov 13 2014Tim dettlaff presentation   fmli nov 13 2014
Tim dettlaff presentation fmli nov 13 2014
 
Home building guide
Home building guideHome building guide
Home building guide
 
CAD SGP
CAD SGPCAD SGP
CAD SGP
 
Blakely2007
Blakely2007Blakely2007
Blakely2007
 
New Material_naked green materials
New Material_naked green materialsNew Material_naked green materials
New Material_naked green materials
 
Home Insulation Tips for Renovators
Home Insulation Tips for RenovatorsHome Insulation Tips for Renovators
Home Insulation Tips for Renovators
 
Insurend Brochure
Insurend BrochureInsurend Brochure
Insurend Brochure
 
Rotary District Conference Presentation
Rotary District Conference Presentation Rotary District Conference Presentation
Rotary District Conference Presentation
 
Andersen 100 Series Commercial Project Case Studies
Andersen 100 Series Commercial Project Case StudiesAndersen 100 Series Commercial Project Case Studies
Andersen 100 Series Commercial Project Case Studies
 
Silverton-en
Silverton-enSilverton-en
Silverton-en
 
Sdumo Trust
Sdumo  TrustSdumo  Trust
Sdumo Trust
 
Reducing Home Energy Costs
Reducing Home Energy CostsReducing Home Energy Costs
Reducing Home Energy Costs
 
Building an A-rated Home - Back to the Future
Building an A-rated Home - Back to the FutureBuilding an A-rated Home - Back to the Future
Building an A-rated Home - Back to the Future
 
Powerworx really Works
Powerworx really WorksPowerworx really Works
Powerworx really Works
 
Wood in Buildings: Steps to Durability and Longevity
Wood in Buildings: Steps to Durability and LongevityWood in Buildings: Steps to Durability and Longevity
Wood in Buildings: Steps to Durability and Longevity
 
2014 updated portfolio of Riaan de Villiers
2014 updated portfolio of Riaan de Villiers2014 updated portfolio of Riaan de Villiers
2014 updated portfolio of Riaan de Villiers
 
Airtight Construction - Step 1 of The Seven Steps of Building a Synergy Home
Airtight Construction - Step 1 of The Seven Steps of Building a Synergy HomeAirtight Construction - Step 1 of The Seven Steps of Building a Synergy Home
Airtight Construction - Step 1 of The Seven Steps of Building a Synergy Home
 
Tomorrow's homes... today!, constructores
Tomorrow's homes... today!, constructoresTomorrow's homes... today!, constructores
Tomorrow's homes... today!, constructores
 

En vedette

Good construction practices - Part 2 - ACC
Good construction practices - Part 2 - ACCGood construction practices - Part 2 - ACC
Good construction practices - Part 2 - ACCKeto Diet Active
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphbhlksd
 
Best Practices: Project Documentation and Construction Management
Best Practices: Project Documentation and Construction ManagementBest Practices: Project Documentation and Construction Management
Best Practices: Project Documentation and Construction ManagementSmith Cashion & Orr PLC
 
Beam and slab design
Beam and slab designBeam and slab design
Beam and slab designIvan Ferrer
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailingAli Ishaqi
 
Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Lamdade Akhil
 

En vedette (7)

Good construction practices - Part 2 - ACC
Good construction practices - Part 2 - ACCGood construction practices - Part 2 - ACC
Good construction practices - Part 2 - ACC
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphb
 
Sample report residential 1[1]
Sample report residential 1[1]Sample report residential 1[1]
Sample report residential 1[1]
 
Best Practices: Project Documentation and Construction Management
Best Practices: Project Documentation and Construction ManagementBest Practices: Project Documentation and Construction Management
Best Practices: Project Documentation and Construction Management
 
Beam and slab design
Beam and slab designBeam and slab design
Beam and slab design
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailing
 
Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Bar bending schedule(by akhil)
Bar bending schedule(by akhil)
 

Similaire à Residential Construction Practices

Enercept Power Point[1]
Enercept Power Point[1]Enercept Power Point[1]
Enercept Power Point[1]cezitelli
 
Enercept Structural Insulated Panels
Enercept Structural Insulated PanelsEnercept Structural Insulated Panels
Enercept Structural Insulated Panelsjrquinn57
 
Energy Efficient Building Enclosure Design Guidelines for Wood-Frame Buildings
Energy Efficient Building Enclosure Design Guidelines for Wood-Frame BuildingsEnergy Efficient Building Enclosure Design Guidelines for Wood-Frame Buildings
Energy Efficient Building Enclosure Design Guidelines for Wood-Frame BuildingsRDH Building Science
 
New Commercial Presentation 2009
New Commercial Presentation 2009New Commercial Presentation 2009
New Commercial Presentation 2009MikeRussell
 
Enviro Board Power Point Presentation
Enviro Board Power Point PresentationEnviro Board Power Point Presentation
Enviro Board Power Point PresentationPamelaE
 
Building emvelopes and thermal mass walls
Building emvelopes and thermal mass wallsBuilding emvelopes and thermal mass walls
Building emvelopes and thermal mass wallsnuform
 
NET-ZERO home presentation
NET-ZERO home presentationNET-ZERO home presentation
NET-ZERO home presentationColin4184
 
Stemming the Tide of Housing Shortages Around the World
Stemming the Tide of Housing Shortages Around the WorldStemming the Tide of Housing Shortages Around the World
Stemming the Tide of Housing Shortages Around the Worldsoonemedia
 
Stemming the Tide of Housing Shortages Around the World
Stemming the Tide of Housing Shortages Around the WorldStemming the Tide of Housing Shortages Around the World
Stemming the Tide of Housing Shortages Around the Worldsoonermedia
 
Bpi accredited training, john jones
Bpi accredited training, john jonesBpi accredited training, john jones
Bpi accredited training, john jonesJen Boudrie
 
Ccse Net Zero Energy
Ccse Net Zero EnergyCcse Net Zero Energy
Ccse Net Zero Energyccseerc
 
Building Officers Sustainability Nbt Final
Building Officers Sustainability Nbt FinalBuilding Officers Sustainability Nbt Final
Building Officers Sustainability Nbt FinalMatt Robinson
 
Net Zero Building Enclosure Retrofits for Houses
Net Zero Building Enclosure Retrofits for HousesNet Zero Building Enclosure Retrofits for Houses
Net Zero Building Enclosure Retrofits for HousesRDH Building Science
 

Similaire à Residential Construction Practices (20)

Enercept Power Point[1]
Enercept Power Point[1]Enercept Power Point[1]
Enercept Power Point[1]
 
Enercept Structural Insulated Panels
Enercept Structural Insulated PanelsEnercept Structural Insulated Panels
Enercept Structural Insulated Panels
 
Energy Efficient Building Enclosure Design Guidelines for Wood-Frame Buildings
Energy Efficient Building Enclosure Design Guidelines for Wood-Frame BuildingsEnergy Efficient Building Enclosure Design Guidelines for Wood-Frame Buildings
Energy Efficient Building Enclosure Design Guidelines for Wood-Frame Buildings
 
Assemble homes like cars
Assemble homes like carsAssemble homes like cars
Assemble homes like cars
 
New Commercial Presentation 2009
New Commercial Presentation 2009New Commercial Presentation 2009
New Commercial Presentation 2009
 
Enviro Board Power Point Presentation
Enviro Board Power Point PresentationEnviro Board Power Point Presentation
Enviro Board Power Point Presentation
 
Building emvelopes and thermal mass walls
Building emvelopes and thermal mass wallsBuilding emvelopes and thermal mass walls
Building emvelopes and thermal mass walls
 
NET-ZERO home presentation
NET-ZERO home presentationNET-ZERO home presentation
NET-ZERO home presentation
 
Building Codes and Zoning
Building Codes and ZoningBuilding Codes and Zoning
Building Codes and Zoning
 
Stemming the Tide of Housing Shortages Around the World
Stemming the Tide of Housing Shortages Around the WorldStemming the Tide of Housing Shortages Around the World
Stemming the Tide of Housing Shortages Around the World
 
Stemming the Tide of Housing Shortages Around the World
Stemming the Tide of Housing Shortages Around the WorldStemming the Tide of Housing Shortages Around the World
Stemming the Tide of Housing Shortages Around the World
 
Bpi accredited training, john jones
Bpi accredited training, john jonesBpi accredited training, john jones
Bpi accredited training, john jones
 
Getting to Net Zero Energy Buildings with Solar Energy
Getting to Net Zero Energy Buildings with Solar EnergyGetting to Net Zero Energy Buildings with Solar Energy
Getting to Net Zero Energy Buildings with Solar Energy
 
Ccse Net Zero Energy
Ccse Net Zero EnergyCcse Net Zero Energy
Ccse Net Zero Energy
 
Building Officers Sustainability Nbt Final
Building Officers Sustainability Nbt FinalBuilding Officers Sustainability Nbt Final
Building Officers Sustainability Nbt Final
 
Pacific Homes
Pacific HomesPacific Homes
Pacific Homes
 
ACH 122 Lecture 01 (Bldg Codes)
ACH 122 Lecture 01 (Bldg Codes)ACH 122 Lecture 01 (Bldg Codes)
ACH 122 Lecture 01 (Bldg Codes)
 
ACH 122 Lecture 01 (Bldg Codes)
ACH 122 Lecture 01 (Bldg Codes)ACH 122 Lecture 01 (Bldg Codes)
ACH 122 Lecture 01 (Bldg Codes)
 
ACH 122 Lecture 01 (Bldg Codes)
ACH 122 Lecture 01 (Bldg Codes)ACH 122 Lecture 01 (Bldg Codes)
ACH 122 Lecture 01 (Bldg Codes)
 
Net Zero Building Enclosure Retrofits for Houses
Net Zero Building Enclosure Retrofits for HousesNet Zero Building Enclosure Retrofits for Houses
Net Zero Building Enclosure Retrofits for Houses
 

Plus de tigerrealestate

Minimize Your Risk, Maximize Your Earnings!
Minimize Your Risk, Maximize Your Earnings!Minimize Your Risk, Maximize Your Earnings!
Minimize Your Risk, Maximize Your Earnings!tigerrealestate
 
Innovations in Sustainable Housing/Green Building Best Practices
Innovations in Sustainable Housing/Green Building Best PracticesInnovations in Sustainable Housing/Green Building Best Practices
Innovations in Sustainable Housing/Green Building Best Practicestigerrealestate
 
Minimize Your Risk, Maximize Your Earnings!
Minimize Your Risk, Maximize Your Earnings!Minimize Your Risk, Maximize Your Earnings!
Minimize Your Risk, Maximize Your Earnings!tigerrealestate
 
Mold to Sold - Fact vs. Fiction
Mold to Sold - Fact vs. FictionMold to Sold - Fact vs. Fiction
Mold to Sold - Fact vs. Fictiontigerrealestate
 
Environment Issues From Evolution to Resolution
Environment Issues From Evolution to ResolutionEnvironment Issues From Evolution to Resolution
Environment Issues From Evolution to Resolutiontigerrealestate
 
Don't let Water Intrusion Sink Your Deal
Don't let Water Intrusion Sink Your DealDon't let Water Intrusion Sink Your Deal
Don't let Water Intrusion Sink Your Dealtigerrealestate
 
This Old Connecticut House CE Course
This Old Connecticut House CE CourseThis Old Connecticut House CE Course
This Old Connecticut House CE Coursetigerrealestate
 

Plus de tigerrealestate (10)

2016 1 hr min max
2016 1 hr min max2016 1 hr min max
2016 1 hr min max
 
Minimize Your Risk, Maximize Your Earnings!
Minimize Your Risk, Maximize Your Earnings!Minimize Your Risk, Maximize Your Earnings!
Minimize Your Risk, Maximize Your Earnings!
 
16 18 ny1 hr min max
16 18 ny1 hr min max16 18 ny1 hr min max
16 18 ny1 hr min max
 
Innovations in Sustainable Housing/Green Building Best Practices
Innovations in Sustainable Housing/Green Building Best PracticesInnovations in Sustainable Housing/Green Building Best Practices
Innovations in Sustainable Housing/Green Building Best Practices
 
Minimize Your Risk, Maximize Your Earnings!
Minimize Your Risk, Maximize Your Earnings!Minimize Your Risk, Maximize Your Earnings!
Minimize Your Risk, Maximize Your Earnings!
 
Mold to Sold - Fact vs. Fiction
Mold to Sold - Fact vs. FictionMold to Sold - Fact vs. Fiction
Mold to Sold - Fact vs. Fiction
 
Environment Issues From Evolution to Resolution
Environment Issues From Evolution to ResolutionEnvironment Issues From Evolution to Resolution
Environment Issues From Evolution to Resolution
 
Don't let Water Intrusion Sink Your Deal
Don't let Water Intrusion Sink Your DealDon't let Water Intrusion Sink Your Deal
Don't let Water Intrusion Sink Your Deal
 
Smart energyce
Smart energyceSmart energyce
Smart energyce
 
This Old Connecticut House CE Course
This Old Connecticut House CE CourseThis Old Connecticut House CE Course
This Old Connecticut House CE Course
 

Dernier

Escort—>Call GiRls In Mori Gate Delhi —>8447779280—Service Escorts In South D...
Escort—>Call GiRls In Mori Gate Delhi —>8447779280—Service Escorts In South D...Escort—>Call GiRls In Mori Gate Delhi —>8447779280—Service Escorts In South D...
Escort—>Call GiRls In Mori Gate Delhi —>8447779280—Service Escorts In South D...asmaqueen5
 
Acibadem Konaklari Uskudar - Listin Turkey
Acibadem Konaklari Uskudar - Listin TurkeyAcibadem Konaklari Uskudar - Listin Turkey
Acibadem Konaklari Uskudar - Listin TurkeyListing Turkey
 
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...asmaqueen5
 
Nyati Elite NIBM Road Pune E Brochure.pdf
Nyati Elite NIBM Road Pune E Brochure.pdfNyati Elite NIBM Road Pune E Brochure.pdf
Nyati Elite NIBM Road Pune E Brochure.pdfabbu831446
 
Vanam At Purva Soukhyam Guduvanchery.pdf.pdf
Vanam At Purva Soukhyam Guduvanchery.pdf.pdfVanam At Purva Soukhyam Guduvanchery.pdf.pdf
Vanam At Purva Soukhyam Guduvanchery.pdf.pdfkratirudram
 
Real Estate Finance and Investments (2019).pdf
Real Estate Finance and Investments (2019).pdfReal Estate Finance and Investments (2019).pdf
Real Estate Finance and Investments (2019).pdfZahraYusuf9
 
Yashwin Enchante Uppar Kharadi Pune E-Brochue.pdf
Yashwin Enchante Uppar Kharadi Pune  E-Brochue.pdfYashwin Enchante Uppar Kharadi Pune  E-Brochue.pdf
Yashwin Enchante Uppar Kharadi Pune E-Brochue.pdfManishSaxena95
 
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...asmaqueen5
 
Parksville 96 Surrey Floor Plans May 2024
Parksville 96 Surrey Floor Plans May 2024Parksville 96 Surrey Floor Plans May 2024
Parksville 96 Surrey Floor Plans May 2024VickyAulakh1
 
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhiasmaqueen5
 
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)delhi24hrs1
 
SVN Live 5.6.24 Weekly Property Broadcast
SVN Live 5.6.24 Weekly Property BroadcastSVN Live 5.6.24 Weekly Property Broadcast
SVN Live 5.6.24 Weekly Property BroadcastSVN International Corp.
 
Ganga Platinum Kharadi Pune brochure.pdf
Ganga Platinum Kharadi Pune brochure.pdfGanga Platinum Kharadi Pune brochure.pdf
Ganga Platinum Kharadi Pune brochure.pdfsabhyara24
 
Low Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 21 (Gurgaon)
Low Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 21 (Gurgaon)Low Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 21 (Gurgaon)
Low Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 21 (Gurgaon)delhi24hrs1
 
Kohinoor Teiko Hinjewadi Phase 2 Pune E-Brochure.pdf
Kohinoor Teiko Hinjewadi Phase 2 Pune  E-Brochure.pdfKohinoor Teiko Hinjewadi Phase 2 Pune  E-Brochure.pdf
Kohinoor Teiko Hinjewadi Phase 2 Pune E-Brochure.pdfManishSaxena95
 
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...ApartmentWala1
 
Eldeco Dwarka Project In Delhi-brochure.pdf.pdf
Eldeco Dwarka Project In Delhi-brochure.pdf.pdfEldeco Dwarka Project In Delhi-brochure.pdf.pdf
Eldeco Dwarka Project In Delhi-brochure.pdf.pdfkratirudram
 
Madhugiri Boucher Managed Farmland (knx)
Madhugiri Boucher Managed Farmland (knx)Madhugiri Boucher Managed Farmland (knx)
Madhugiri Boucher Managed Farmland (knx)knoxdigital1
 
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...ApartmentWala1
 
Listing Turkey - 2024 - May Featured Portfolio
Listing Turkey - 2024 - May Featured PortfolioListing Turkey - 2024 - May Featured Portfolio
Listing Turkey - 2024 - May Featured PortfolioListing Turkey
 

Dernier (20)

Escort—>Call GiRls In Mori Gate Delhi —>8447779280—Service Escorts In South D...
Escort—>Call GiRls In Mori Gate Delhi —>8447779280—Service Escorts In South D...Escort—>Call GiRls In Mori Gate Delhi —>8447779280—Service Escorts In South D...
Escort—>Call GiRls In Mori Gate Delhi —>8447779280—Service Escorts In South D...
 
Acibadem Konaklari Uskudar - Listin Turkey
Acibadem Konaklari Uskudar - Listin TurkeyAcibadem Konaklari Uskudar - Listin Turkey
Acibadem Konaklari Uskudar - Listin Turkey
 
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
 
Nyati Elite NIBM Road Pune E Brochure.pdf
Nyati Elite NIBM Road Pune E Brochure.pdfNyati Elite NIBM Road Pune E Brochure.pdf
Nyati Elite NIBM Road Pune E Brochure.pdf
 
Vanam At Purva Soukhyam Guduvanchery.pdf.pdf
Vanam At Purva Soukhyam Guduvanchery.pdf.pdfVanam At Purva Soukhyam Guduvanchery.pdf.pdf
Vanam At Purva Soukhyam Guduvanchery.pdf.pdf
 
Real Estate Finance and Investments (2019).pdf
Real Estate Finance and Investments (2019).pdfReal Estate Finance and Investments (2019).pdf
Real Estate Finance and Investments (2019).pdf
 
Yashwin Enchante Uppar Kharadi Pune E-Brochue.pdf
Yashwin Enchante Uppar Kharadi Pune  E-Brochue.pdfYashwin Enchante Uppar Kharadi Pune  E-Brochue.pdf
Yashwin Enchante Uppar Kharadi Pune E-Brochue.pdf
 
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
 
Parksville 96 Surrey Floor Plans May 2024
Parksville 96 Surrey Floor Plans May 2024Parksville 96 Surrey Floor Plans May 2024
Parksville 96 Surrey Floor Plans May 2024
 
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
 
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
 
SVN Live 5.6.24 Weekly Property Broadcast
SVN Live 5.6.24 Weekly Property BroadcastSVN Live 5.6.24 Weekly Property Broadcast
SVN Live 5.6.24 Weekly Property Broadcast
 
Ganga Platinum Kharadi Pune brochure.pdf
Ganga Platinum Kharadi Pune brochure.pdfGanga Platinum Kharadi Pune brochure.pdf
Ganga Platinum Kharadi Pune brochure.pdf
 
Low Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 21 (Gurgaon)
Low Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 21 (Gurgaon)Low Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 21 (Gurgaon)
Low Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 21 (Gurgaon)
 
Kohinoor Teiko Hinjewadi Phase 2 Pune E-Brochure.pdf
Kohinoor Teiko Hinjewadi Phase 2 Pune  E-Brochure.pdfKohinoor Teiko Hinjewadi Phase 2 Pune  E-Brochure.pdf
Kohinoor Teiko Hinjewadi Phase 2 Pune E-Brochure.pdf
 
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
 
Eldeco Dwarka Project In Delhi-brochure.pdf.pdf
Eldeco Dwarka Project In Delhi-brochure.pdf.pdfEldeco Dwarka Project In Delhi-brochure.pdf.pdf
Eldeco Dwarka Project In Delhi-brochure.pdf.pdf
 
Madhugiri Boucher Managed Farmland (knx)
Madhugiri Boucher Managed Farmland (knx)Madhugiri Boucher Managed Farmland (knx)
Madhugiri Boucher Managed Farmland (knx)
 
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
 
Listing Turkey - 2024 - May Featured Portfolio
Listing Turkey - 2024 - May Featured PortfolioListing Turkey - 2024 - May Featured Portfolio
Listing Turkey - 2024 - May Featured Portfolio
 

Residential Construction Practices

  • 1. P R E S E N T S Residential Construction Practices Let’s Build a House Together! (3) Credit Continuing Education Course
  • 2. …and a great class! Continuing Education Providers are subject to audit by the State of Connecticut Please: Mute your cell phone Use electronic devices judiciously Remain in attendance until the end of the class (or we can’t issue your credits) Thank you!
  • 3. Your Credits…. Are submitted electronically to the State of Connecticut by Tiger Real Estate School Tiger Real Estate School will email you a Certificate of Completion within 14 days Please make sure we don’t land in “spam” and be sure to save your Certificate where you can find it There is a $25.00 fee to reissue a Certificate
  • 4. Startling Statistics! How many Jobs are created for each single family home built? (According to NAHB) Five? Seven? One? Three?
  • 5. Tax Revenue How much government tax revenue is created for each single family home built? $ 24,000? $ 110,000? $ 74,000? $ 58,000? $ 90,000?
  • 6. Annual Housing Starts How many national housing starts do we need to accommodate growing population and older housing stock? 950,000? 1.7 million? 3 million? 1.2 million? 2.1 million?
  • 7. 10 Year U.S. Housing Starts
  • 8. Connecticut Housing Permits 1st Q 2016 1,088 2015 6,077 2014 5,329 2013 5,424 2012 4,669 2011 3,173 2010 3,932 2005 11,885
  • 9. CONTENTS Building codes Foundation systems Loads on buildings Floor systems Wall systems Roof systems Roofing Siding Decks Insulation Finish work Doors and windows Special construction Heating systems Cooling Air quality Water and Waste Electrical
  • 10. Building Codes Regulate:  design  construction  alteration  repair of buildings in order to protect the public safety, health, and welfare
  • 11. Major Model Codes The National Building Code  BOCA (Building Officials and Code Administrators) The Uniform Building Code (UBC)  ICBO (International Conference of Building Officials) The Standard Building Code International Building Code  IBC  Publication in 2003 International Energy Conservation Code
  • 12. Companion Codes Developed to govern other more specific aspects of construction such as plumbing and mechanical work. May be developed by states or local municipalities, most are published by the same groups that publish the model codes.
  • 13. The 2016 CONNECTICUT STATE BUILDING CODE has been approved and will be effective for all permit applications on or after OCTOBER 1, 2016. The 2016 CONNECTICUT FIRE SAFETY CODE has been approved and will be effective for all permit applications on or after OCTOBER 1, 2016
  • 14. Connecticut Building Codes Electrical Code 2011 NEC (NFPA-70) Accessibility Code ICC/ANSI A117.1 2003 Elevator Code 2005 CT State Elevator Code (ASME A17.1-1996 with 1997 & 1998 Addenda) Gas Code CT State Regulations Boiler Code ASME Boiler & Pressure Vessel Code; NBIC Energy Code 2009 International Energy Conservation Code (re-adopted with changes)
  • 15. Let’s Build A House!
  • 16. Basic 2400 sq ft colonial  Not a lot of “bells & whistles”  Costs a/o August 2016  Average construction quality  Located in subdivision – land price not included Construction Cost Estimate based on the book National Building Cost Manual published by Craftsman Book Company
  • 17. Single family residence built under competitive conditions in or near Fairfield County  Foundation for normal soil conditions  Excavation for foundation and piers on a prepared building pad  Floor, wall, interior and exterior finishes, roof cover, interior partitions, doors, windows, trim  Electric wiring and fixtures  Rough and finish plumbing, built-in appliances  Supervision, design fees, permits, utility hook-ups, the contractor's contingency, overhead and profit. *Add the cost of the land, government-mandated site development fees and the cost of bringing utility lines to the site
  • 18. 2400 Square Feet What’s This? 4 BR, 2.5 Baths, Masonry Fireplace, Full Basement http://www.building-cost.net/CornersType.asp
  • 19.
  • 20.
  • 23. Foundation Systems Foundation Footing Footing Drainage Foundation Walls Damp Sealing Insulation & Vapor Barriers Insulated concrete forms Radon Resistant New Construction
  • 24. Footing & Drain Details
  • 28. Foundation Insulation Alternative to our selection Slab insulation detail
  • 29. Pre-Slab & Finish Details
  • 30. Radon Resistant New Construction
  • 32. Which of the following most closely reflects the cost of equipment and labor for: Excavation: 1. Labor $5,143 Equipment $1,332 Excavation Total $6,475 2. Labor $2,050, Equipment $1,062, Excavation Total $3,112
  • 33. Which of the following most closely reflects the cost of materials, equipment and labor for: Foundation, Piers, Flatwork: 1. Materials $4,639, Labor $9,050, Equipment $1,062 Foundation, Piers, Flatwork Total $14,751 2. Material $11,152, Labor $17,426, Equipment $2,709 Foundation, Piers, Flatwork Total $31,287
  • 34. Which of the following most closely reflects the cost of materials and labor for: Rough Carpentry: 1. Materials $41,953, Labor $27,935, Rough Carpentry Total $69,888 2. Material $36,060, Labor $52,886, Rough Carpentry Total $88,946
  • 35. How much have we spent so far… Excavation $6,475 Foundation, Piers, Flatwork $31,287 Rough Hardware $3,060* Rough Carpentry $88,946 $129,768
  • 36. Structural and Exterior Building Systems
  • 38. Engineered Systems Basement Insulation Wood Joists
  • 39. Wood Stud Framing System Double Top Plate Cripple Studs Headers King Stud Jack Stud Window Sill Bottom Plate Window & Door R.O.
  • 43. Understanding the Importance of Proper Mechanical Connections
  • 44. Sheathing Options Oriented Strand Board or Plywood Have been common choices. A whole new sheathing system is available now. The Huber Zip System:
  • 45. Structural Insulated Panels (SIPS) Eliminates the thermal bridge that occurs with conventional frame construction. SIP houses are very tight and insulate extremely well.
  • 46.
  • 47.
  • 49. SIPS
  • 55. Roof Flashing & Drainage
  • 57. PV Roofing protects from the elements and also generates electricity Newest solar product Pleasing to Homeowners Not as visually apparent as standard solar electric modules
  • 60. Doors & Windows To Finish the Close-In
  • 61.  Masonry Veneer  Exterior Plywood Finishes  Wood Shingles/Shakes  Board Siding  Stucco Finishes  Synthetic Products  Wood or Composite Trim  Flashing Siding & Trim
  • 62. Air & Vapor Barriers
  • 64. No Shortage of Siding or Trim Options For The Home Wood Vinyl Cement PVC LVL Poly-foam Hardboard Finger- jointed Wood
  • 65. • Foundation • Framing • Flashing • Stairs & Railings • Finish Materials Decks
  • 67. Flashing for pressure-treated wood Contains higher concentrations of copper Could quickly corrode the critical aluminum flashings, fasteners, and connectors Use stainless steel or copper to prevent galvanic reaction
  • 68. Handrails and Decking Materials Composite decking combines recycled plastic and wood fiber
  • 70. Critical Deck Connections 1. Ledger Attachment 2. Joist-to-Ledger 3. Joist-to-Beam 4. Beam-to-Post 5. Railing Post-to-Deck Framing 6. Stair Stringer-to-Deck Framing 7. Stair Tread-to-Stringer 8. Post-to-Concrete
  • 71.
  • 73. Top 10 New Construction Defects 1. No insulation installed in the attic 2. Missing proper roof vents, or vent holes cut, but roofed over 3. Windows installed improperly 4. Hot and Cold water reversed at faucets, tubs, and showers 5. Drains clogged with debris from construction process 6. Inoperable or missing GFCI’s in required areas 7. Heat vents missing, not connected 8. Cut trusses in roof or floor trusses 9. Tempered glass missing in required areas 10. Improperly installed roofing, flashing, or roof jacks
  • 74. Are Your Ready? Let’s Play……. Name That Defect!!
  • 84. B R E A KB R E A K 15 MINUTE15 MINUTE
  • 85. 2016 – 2018 (3) Credit Continuing Education Courses  Don’t Let Water Intrusion Sink Your Deal!  Smart Energy Updates for Existing Homes  Innovation in Sustainable Housing – Green Building Best Practices This Old Connecticut House  Minimize Your Risk, Maximize Your Earnings  Environmental Issues – Evolution to Resolution  What to Expect When We’re Inspecting!  Mold to Sold!  Residential Building Practices
  • 86. Your Opinion Matters…. Before the end of class, please take a moment to complete our evaluation form…
  • 87. Energy Conservation in New Construction  Energy Use And Code Considerations  Doors And Windows  Insulation And The Building Envelope  Conservation Systems  Mechanical Systems  Indoor Air Quality  Finishing The Interior
  • 89. better codes mean better benefits.
  • 91. DOOR & WINDOW SELECTION Solar gain rating Window orientation What to look for in windows  Glazing  Sashes and frames  Performance ratings Energy-Efficient design
  • 92. Building Envelope Specific Requirements Conditioned space Building Envelope consists of: Fenestration Ceilings Walls Above grade Below grade Mass walls Floors Slab Crawl space
  • 93. Areas for Air Leakage (Infiltration) Windows and doors Between sole plates Floors and exterior wall panels Plumbing Electrical Service access doors or hatches Recessed light fixtures
  • 94. How to Air Seal an Attic
  • 95. Super-insulated, Airtight Envelope Insulation materials Thermal mass Air tightness Moisture control Too tight
  • 97. Spray-In Insulation Good R-values-up to 6.5 per inch-do an exceptionally good job of air sealing Best product to stop air movement through walls Available in both low- density, open-cell and high-density, closed-cell varieties Applied with specialized spray equipment Low-density foams are more vapor permeable than high-density foams, but they both form extremely effective air barriers
  • 98. Wall Insulation and Installation
  • 99. Ceiling Insulation and Installation Thermal By-pass sealing Is critical for maintenance of the Building Envelope
  • 100. Basement and Crawlspace (Insulation and Installation) Foundation and Floor Framing Both Require Good Insulation
  • 101.
  • 102. Fiberglass/Cellulose Spray foam Approximately $1.50 - $2.00 per square foot $6.00 - $7.00 per square foot R49 Standard Insulation Costs
  • 103. Air Sealing for New Home Construction Blending Air- Sealing and a variety of insulation Materials for an air-tight Home
  • 105. Duct Tightness Testing Building Cavities as Supply Ducts No, No, No, No!!!!
  • 106. Putting all of the sealing Activities in place before Testing the home
  • 109. Which of the following most closely reflects the cost of materials and labor for: Roofing, Flashing, Fascia: 1. Material $9,967, Labor $11,680 Roofing, Flashing, Fascia Total $21,647 2. Material $15,077, Labor $12,564 Roofing, Flashing, Fascia Total $27,641
  • 110. Which of the following most closely reflects the cost of materials and labor for: Exterior Trim and Finish: 1. Material $15,559, Labor $10,434, Equipment $1,343 Exterior Trim and Finish Total $27,336 2. Material $25,648, Labor $15,879, Equipment $1,370 Exterior Trim and Finish Total $42,897
  • 111. Which of the following most closely reflects the cost of materials and labor for: Insulation: 1. Material $6,231, Labor $2,638, Insulation Total $8,869 2. Material $6,753, Labor $4,586, Insulation Total $11,339
  • 112. Which of the following most closely reflects the cost of materials and labor for: Doors(including garage) Windows: 1. Materials $5,720, Labor $8,155 Door/Window Total $13,875 2. Materials $10,528 Labor $7,211, Door/Window Total $17,739
  • 113. How much have we spent so far… Excavation $6,475 Foundation, Piers, Flatwork $31,287 Rough Hardware $3,060* Rough Carpentry $88,946 Roof, Flashing, & Fascia $27,641 Insulation $11,339 Exterior Trim & Finish $35,639 Doors/Windows $17,739 Finish Hardware* $1,007 $223,133
  • 114. Lighting Compliance Requirements Compact Fluorescent Bulbs - CFL Light Emitting Diode Bulbs – LED Sealed Recessed Lighting
  • 115. RESPECTING and CONSERVING WATER Home Water Conservation Water-efficient plumbing fixtures and appliances Hot water distribution Design landscape to conserve water
  • 116. Home Run Plumbing Newest Supply Systems Include: CPVC Piping Manifold Distribution Individual Shut Offs PEX Tubing Minimal Joints Labeled Distribution
  • 118. Toilets, Showerheads, Faucets 1992 conservation act mandated water conserving plumbing fixtures 1.6 gallons per flush, many are less than 1.3 gallons Saves 30,000 gallons per year – over $100
  • 120. Ground Fault Interrupter Arc Fault Interrupter Electrical
  • 121. PHOTOVOLTAICS (PV) Direct conversion of sunlight Utilizes a semiconductor to create electron flow
  • 123. Hybrid & On Demand Water Heating
  • 124. How does an on demand tankless water heater work?
  • 125. Solar Hot Water Heating
  • 126. Heating & Cooling Systems • Forced Air Heating • Hot Water & Steam Heating • Electric Heating • Radiant Heating • Geothermal Heating • Heat Pump • Active Solar Energy • Passive Solar • HRV • Air Conditioning Condenser • Heat Pump in Cooling Mode • Split ductless Systems
  • 127. High Efficiency Heating Systems How boilers work
  • 128. Wall Mounted Condensing Gas Boiler
  • 130. Dual Mode Heating & Cooling Systems Split Cooling Systems Heat Pumps and Ductless Systems
  • 131. Differentiating High Efficiency HVAC Systems A split HVAC system - multiple sections Indoor coil section in the ductwork Outdoor coil section (compressor/condenser) installed on the outside of the home Inside the home (attic, basement, closet) there may be a combined fan and air conditioning coil in one box or separate coil and fan sections which can house a gas or oil heating furnace  Package system contains all components in one box (compressor, condenser, fan) typically found installed outside the home, in some cases on the roof and ducted into the home
  • 132. Two Configurations for AC or Heat Pumps
  • 133. Ductless Mini Split Heat Pump
  • 136. Air Quality Night flushing – Attic Fan Heat Recovery Ventilators Ventilators – Kitchen/Bath
  • 137. Balanced Ventilation System Incoming and outgoing airstreams balance one another Heat in the outgoing airstream can be captured with an HRV or ERV
  • 138. Improve Air Quality Duct Configuration Heat Recovery Ventilation (HRV)
  • 139. Video Heat Recovery Ventilation
  • 140. Interior Components Stair Requirements Wood Stairs Spiral Stairs Fireplaces Fireplace Requirements Masonry Chimneys Prefab Fireplaces & Stoves
  • 141. Efficient Fireplaces and Gas, Propane, or Pellet Type Burning Appliances
  • 142. One Minute Break – Your Opinion Matters…. Please take a moment to complete our evaluation form…
  • 143. Finish Work •Gypsum Board •Ceramic Tile •Countertops •Cabinetry •Hardware/Metals •Wood Flooring •Wood Moldings & Trim
  • 144. Gypsum Board Application Drywall Preparation Hanging/Fastening Taping and Finishing
  • 146. Please refer to your handout
  • 148. Wood Moldings and Trim Cove moldings Crown moldings Cornice  Cornice is a molded projection that crowns a wall  Picture molding is a horizontal molding Rails  Plate rail is a narrow shelf fixed along a wall and grooved to hold plates for ornament or display Baseboard  Baseboards conceal and finish the joints where sidewalls meet the floors
  • 149. Molding – Wood/Composite Cost comparisons of Different materials Labor costs largely unaffected
  • 150. Flooring Options (per square foot, installed) Carpet ($2.00 - $15.00 ) Wood ($6.00 - $15.00) Engineered Wood ($4.00 - $18.00) Stone ($8.00 - $50.00) Ceramic/Porcelain ($4.00 - $12.00) Laminate ($3.00 - $7.00) Bamboo ($4.00 - $8.00) Vinyl ($1.00 - $7.00) Linoleum ($2.00 - $9.00) Cork ($3.00 - $7.00) Source – World Flooring Association
  • 151. Accessible Design  Wider doors  Entry without stairs  Barrier free shower  Key services on first floor  Sinks/Countertops wheelchair friendly  Transfer ledge/grab bars in bathroom
  • 153. Which of the following most closely reflects the cost of materials and labor for: Plumbing Rough In, Connection & Fixtures: 1. Material $18,588, Labor $18,716, Plumbing Total $37,309 2. Material $9,740, Labor $9,080, Plumbing Total $18,820
  • 154. Which of the following most closely reflects the cost of materials and labor for: Heating & Cooling: 1. Material $6,204, Labor $9,305 Heating and Cooling Systems Total $15,509 2. Material $20,055, Labor $6,080 Heating and Cooling Systems Total $26,135
  • 155. Which of the following most closely reflects the cost of materials and labor for: Interior Wall Finish: 1. Material $9,605, Labor $14,737 Interior Wall Finish Total $24,342 2. Material $2,441, Labor $7,564 Interior Wall Finish Total $10,005
  • 156. Masonry Fireplace in First Floor Family Room Brick Fireplace (and Chimney) without a raised hearth. Is the Labor and Material Cost for the Fireplace higher or lower than $7,250 ?? $12,11 0
  • 157. Which of the following most closely reflects the cost of materials and labor for: Wiring and Light Fixtures: 1. Labor $9,557, Material $7,739, Total $17,296 2. Labor $4,050, Material $5,752, Total $9,802
  • 158. Finish Carpentry Is the Labor and Material Cost for Finish Carpentry higher or lower than $4,250 ?? $9,303
  • 159. Painting Is the Labor and Material Cost for Painting higher or lower than $10,750 ?? $19,052
  • 160. Finishes (builder grade) The following are approximate budget guidelines for our New Build: Cabinets……………….. $17,625 Countertops…………… $7,486 Flooring………………… $10,343 Carpeting………………. $11,567 Appliances……………… $7,440 Bath Accessories, Tub/Shower Enclosure… $5,885
  • 161. Are you ready? Let’s play… What’s HOT…….What’s NOT!!!What’s HOT…….What’s NOT!!! 2016 Building Trends (according to National Association of Home Builders And National Kitchen & Bath Association)
  • 162. According to NAHB, what is the biggest change in residential construction? Homes are getting bigger Homes are getting smaller
  • 163. What rooms are being left out of home design? 3rd bathroom Formal dining Room Mudroom All of the above
  • 164. What is the number 1 choice for kitchen flooring? Tile Hardwood Tile that looks like hardwood Marble
  • 165. What countertop material is most popular? Marble Wood Granite Quartz/Engineered Stone Concrete Stainless Steel
  • 166. What home features are both Boomers and Millenials looking for? 1.Large, spacious interiors 2.High Tech features 3.Open floor plans 4.Outdoor spaces 5.Access to shopping 6.Located near major highways
  • 167. What home features are least important to Millenials? 1.Separate Laundry Room 2.Walk in closets 3.Energy efficiency 4.Family Rooms 5.Outdoor kitchens
  • 168. How Much did our New Build Cost??? Subtotal Direct Job Costs Material ……………………….. $199,228 Labor …………………………. $221,048 Equipment …………………… $6,903 Total $427,179
  • 169. The Cost of “Doing Business..” Indirect Job Costs Final Cleanup Total ………..$1,760 Insurance Total……………..$12,322 Permits & Utilities Total…… $7,481 Plans & Specs Total……….. $1,760 Total $23,323
  • 170. Are we going to make any money?? Contractor Markup Total $55,008 Grand Total……$505,510 Plus cost of land!
  • 171. Complete & Ready For Sale

Notes de l'éditeur

  1. Marketing: please be sure to remind Attendees that their local Board will not be aware of these credits. Their local Board only tracks credits for Courses that are taken through them.
  2. Today we’re going to make you think. I’m not going to do all the work…so what’s the answer. (Three) What industries benefit most: lumber, concrete, lighting fixtures, heating & cooling, real estate agents, brokers, lawyers. About half of the jobs are created in the construction industry, manufacturing second, then other sectors Residential Construction has a positive, direct impact upon our economy! Housing contributes 15% to GDP!!
  3. $90,000 in government revenue, $67,000 in federal, $23,000 in local and state revenue Income is derived from several sources: workers who are subject to federal, state and social security taxes and business owners whose profits are taxed. States impose sales tax on materials and local jurisdictions levy fees for building permits and extending utility services
  4. 1.7 million. Does any one know how many housing starts we’ve had in the past year? ($500,000) This gap represents more than 3 million untapped jobs
  5. 1st quarter 2016 up 28% from 1st quarter 2015 which only had 845 permits. 9.8% increase in Fairfield County, New Haven County up 22%, Hartford county up 173%
  6. Throughout the day we will incorporate logical “Green” design considerations, but our focus is on mainstream construction details and terminology. We encourage you to learn more about Green Building and do offer a separate course for your future consideration.
  7. Model codes are building codes developed for construction standards by national organizations of building code officials, professional societies, and trade associations for adoption by local communities.
  8. Background: State and Local Adoption of Building Energy Codes The development of the International Energy Conservation Code® is based on experiences gained through decades of code developments. The energy shortages of the 1970’s motivated many states and local jurisdictions to add provisions to building codes to make homes more energy-efficient. State and local building energy codes have proven successful in reducing energy consumption and peak electric demand in residential buildings, through the use of energy-efficient windows, added insulation, and reduced air leakage. These codes have become integral parts of almost every state and local jurisdiction’s building code. States and local jurisdictions most often look to national model energy codes as the starting point for their own codes. Simply adopting model energy codes makes it easier for them to keep current with the most recent building practices and technology. In the 1992 Energy Policy Act (“EPAct”) Congress mandated that all states must review and consider adopting the national model energy standard (at that time, the 1992 Model Energy Code). Since then, new model energy codes have been developed and in 1998 the first International Energy Conservation Code® (IECC®) was released. Since 1998 several improved versions have produced even greater energy savings. All of these have been published by the International Code Council®. The latest version of the IECC was released in early 2009. The 2009 IECC builds on the improvements made in the 2000, 2003 and 2006 IECC and each supplement released in 2001, 2004 and 2007. Relationship Between IRC and IECC IECC addresses only energy IRC addresses all codes (structural, plumbing, etc.) Allows builder to carry only one code book Chapter 11 has energy IECC addresses both residential and commercial; IRC only residential, excludes most apartments IRC references IECC Energy requirements in IRC and IECC almost identical Structure of the IECC Chapter 1Administrative Chapter 2Definitions Chapter 3Climate Zones Chapter 4Residential Energy Efficiency Chapter 5Commercial Energy Efficiency Chapter 6 Referenced Standards Overview of Residential Code Requirements Focus is on building envelope Ceilings, walls, windows, floors, foundations Sets insulation levels, window U-factors and solar heat gain coefficients Infiltration control—caulk and seal to prevent air leaks Ducts – seal and insulate Limited space heating, air conditioning, and water heating requirements Federal law sets most equipment efficiency requirements, not the I-codes No lighting or appliance requirements Climate Specific Requirements: Foundations Basements Slabs Crawlspaces Above grade walls Skylights, windows, and doors Roofs Solar Heat Gain Coefficient in warm climates Vapor retarders in cold climates Universal Requirements (apply everywhere): Duct insulation and sealing Infiltration control Including recessed cans   What is the International Energy Conservation Code®? The IECC® is a model energy building code produced by the International Code Council® (ICC®). It is referred to as a “model” code because it was developed through a public hearing process by national experts under the direction of the ICC. The code contains minimum energy efficiency provisions for residential and commercial buildings, offering both prescriptive- and performance-based approaches. The code also contains building envelope requirements for thermal performance and air leakage. The IECC is part of the International “family” of Codes produced by the International Code Council®, which includes other codes such as the International Building Code® (IBC®), International Residential Code® (IRC®), International Mechanical Code® (IMC®), International Plumbing Code® (IPC®), and more. According to the International Code Council, the intent of the IECC is to establish an energy conservation code that: Effectively conserves energy Minimizes increases in construction costs   Allows the use of new materials, products or methods of construction Eliminates preferential treatment for particular industries or types or classes of materials, products or methods of construction Answers to Common Code Questions: • Why Are Building Codes Important?Building codes, of which building energy codes are an essential part, are important primarily because they work to increase the public safety and result in improved building construction. By providing uniformity in construction laws, building codes set minimum standards that will consistently produce safely constructed buildings. Building codes also promote use of new materials and building techniques.• Why Are Building Energy Codes Important?Building energy codes are important because they set meaningful thresholds for all new construction and existing buildings, such as: Windows: maximum U-factors, SHGCs and air leakage for windows, doors and skylights. Insulation: minimum levels of insulation for walls, ceilings, floors, foundations and ducts. Infiltration: require proper sealing. Equipment: require proper HVAC equipment sizing. In addition, these codes ensure a baseline level of comfort and energy performance for all homes.
  9. The National Electrical Code safeguarding from hazards arising from the use of electricity for light, heat, and power The Life Safety Code minimum requirements for fire safety The Safety Code for Elevators and Escalators
  10. CT Codes are adopted whole or in part (listed as supplements) from newer versions of the national codes After we spend some time on initial construction details, we will review appropriate applications of the 2009 Energy Code, as this will be one of the areas you will focus on when selling new construction.
  11. Southington CT – 2400 square feet
  12. Costs are for home located in subdivision.
  13. Construction Cost Estimate based on the book National Building Cost Manual published by:Craftsman Book CompanyThis is an estimate for a single family residence built under competitive conditions in or near Fairfield County in August 2015. This estimate includes a foundation as required for normal soil conditions, excavation for foundation and piers on a prepared building pad, floor, wall, interior and exterior finishes, roof cover, interior partitions, doors, windows, trim, electric wiring and fixtures, rough and finish plumbing, built-in appliances, supervision, design fees, permits, utility hook-ups, the contractor's contingency, overhead and profit. Highly decorative, starkly original or exceptionally well-appointed residences will cost more. Add the cost of the land, government-mandated site development fees and the cost of bringing utility lines to the site.Total Living Area  2400                                                  
  14. Gutter Drains & Damp Proofing
  15. Slab Edge Insulation and Installation Determine and record the R-value of slab insulation from the label on the insulation or from manufacturer shipping materials available onsite. Slabs are required to be insulated where the floor surface is less than 12 in. below grade. Slab insulation must be inspected prior to pouring the slab—when the insulation installation is completely visible. Insulation location can be vertical or horizontal inside the foundation wall, however, it must start at the top surface the slab and extend downward to completely cover the slab edge. It can also be located outside the foundation wall. Where insulation is located outside the wall and where it extends horizontally away from the building, it must be protected by pavement or at least 10 in. of soil. If the area has been designated as having heavy termite infestation, then insulation is not required and should be so noted. Verify that insulation is installed according to manufacturer’s instructions.
  16. Finishing
  17. The answer is #1
  18. Answer is #2
  19. Answer is #2
  20. *rough hardware was not included in “The price is right”
  21. Platform Framing: Engineered Framing System: Spans for floor joist: Sub floor layout: Joist Definition Flooring Systems Girders & beams Sub-Flooring
  22. Roof Shapes/Styles Different Pitches
  23. Rafter Framing
  24. Zip Roofing System: Roof Sheathing Underlayment for Shingle Roof: Ice and Water Shield, Self Adhering product I-Joist Rafters, Engineered Ridge Truss Types
  25. Flashing Everywhere Roofing Transitions: Roof drainage System:
  26. Asphalt vs. all others Underlayment for Shingle Roofing Wood Shingles & Shakes Composition Shingles Slate Shingles Tile Roofing Metal Roofing Flat Roof Assemblies, Single Ply Roofing Systems Roof Drainage Flashing Roof Penetrations Benefits of metal roofing Fire-rated Moss Free Wind Resistant Snow Slides Off Lightweight Resale Value Cooler in Summer, Warmer in Winter Looks Beautiful Long life
  27. Shingles can be integrated into roofs with standard asphalt shingle material Simultaneously installed by roofer with conventional shingles – reducing installation costs Addresses consumer’s “cost and acceptance” challenges
  28. We will discuss this area after the break as part of an Energy Efficiency Conversation
  29. Air Sealing Vapor Barriers
  30. Vinyl Siding - all shapes and sizes Masonry Veneer Exterior Plywood Finishes Wood Shingles/Shakes Horizontal Board Siding Vertical Board Siding Stucco Finishes Synthetic Products Flashing
  31. Alternatives to Solid Wood Exterior Trim Finger Jointed Wood Laminated Veneer Lumber (LVL) Hardboard Trim Fiber-Cement Cellular PVC Trim
  32. Energy use in buildings makes up a very significant piece of the pie. Some sobering statistics help drive home the reality of building energy use: Nearly 5 million commercial buildings and 115 million residential households in the United States consume nearly 40 percent of the nation’s total primary energy (1) Buildings consume 70 percent of electricity in the United States (2) In 2007, carbon dioxide emissions attributable to lighting, heating, cooling, cooking, refrigeration, water heating, and other building services totaled 2517 million metric tons—40 percent of the U.S. total and 8 percent of the global total. (3) Energy Code 2003 International Energy Conservation Code (re-adopted with changes) International Energy Conservation Code Evaluating the Buildings using the newest code models Completing the General Information Section All inputs at the top of the first page of the checklist should be completed. Some of these inputs are repeated on the beginning of each construction stage. Where a single building is being evaluated for each stage of construction, the duplicate inputs can be ignored. Where different buildings are used for completing different stages of construction, the top portion of each checklist stage must be completed for each different building evaluated. Code Official has final authority Software, worksheets Above Code Programs Electronic media can be used Construction work for which a permit is required is subject to inspection Certificate is required Permanently posted on the electrical distribution panel Shall include the following: R-values of insulation installed for the thermal building envelope including ducts outside conditioned spaces U-factors for fenestration SHGC for fenestration HVAC efficiencies SWH equipment
  33. Other reasons for Building Codes include: Building energy codes set minimum efficiency boundaries that bring about vital, tangible benefits. ● Reduced energy consumption—by approximately 0.5-quadrillion Btu per year by 2015, and 3.5-quadrillion Btu per year by 2030. This is equivalent to the power generated by 260 medium power plants. (2)   ● Rising cost savings—more than $4 billion per year back in homeowners’ pockets by 2015, a figure that could rise to over $30 billion per year by 2030. Even accounting for increased up-front efficiency investment costs, net benefits are quite significant.   ● Reduced CO2 emissions—by roughly 3 percent in terms of the projected national CO2 emissions in 2030.
  34. Energy Performance Testing, Certification and Labeling The National Fenestration Rating Council (NFRC) operates a voluntary program that tests, certifies, and labels windows, doors, and skylights based on their energy performance ratings. The NFRC label provides a reliable way to determine a window's energy properties and to compare products. When properly selected and installed, energy-efficient windows & doors can help minimize your heating, cooling, and lighting costs. Achieving improved window performance in your home involves three steps: Design Consider your home's design and climate in relation to the energy performance of windows. Selection Find windows that meet your energy performance requirements. Installation Ensure proper installation of windows to maximize their energy efficiency.
  35. National Fenestration Rating Council Window Ratings Interpretation U-value – measure of heat transmission Lower the U value – the better Air infiltration cfm/ft² Best < 0.30 cfm/ft² Solar Heat Gain – amount of solar heat transmitted Rating 0 to 1 1= 100% solar gain Visual Transmittance (VT) – amount of light transmitted Percentage of light transmitted through window as compared to no window Clear glass – 90% XV.Energy-Efficient Design WINDOW SELECTION Change layout Next most important consideration Solar Gain or Not“Tune” glazing to the window orientation Example: Passive Solar – cool northern climate South wall – high solar gain East and West – summer heat gain more of a problem North side – no direct solar gain What to Look for in Windows Double- or triple-paned glazing Nonconductive sashes and frames Metal cladding on exterior surfaces Low-e glass Argon-filled air spaces Glazing spacers (warm edges) Low air infiltration
  36. Mandatory Requirements Building Envelope Air leakage Building envelope Sealed with caulking materials or Closed with gasketing systems Joints and seams sealed or taped or covered with a moisture vapor-permeable wrapping material Recessed lighting Moisture control Maximum fenestration U-factor and SHGC
  37. SUPER-INSULATED, AIRTIGHT ENVELOPE Is the number one priority Insulation materials selection/method Insulation is part of a system – insulation + structural support Example: wood frame wall degrades the insulation performance wood insulates to about R- 1 per inch thickness fiberglass insulates to about R- 3.3 per inch thickness whole-wall R value = about 9 instead of R-11 Thermal mass/mass-enhanced R-value Thermal mass – absorbs more heat Mass enhanced R-value – can be 50% more (in certain climates, but no gain in New England) Air tightness – Is the number one priority in designing an energy-efficient house almost as important as insulation methods Moisture control – critical to prevent moisture related damage; including mold Too tight – provide mechanical ventilation
  38. Wall Insulation and Installation Determine and record the R-value(s) of insulation applied to wood-framed, steel-framed, and mass walls that are above grade and associated with the building thermal envelope. An above grade wall is one that is less than 50% below grade. Mass walls are those of concrete block, concrete, ICFs, masonry cavity, brick (non-veneer), earth/adobe, and solid timber/logs. If continuous insulation is installed, record the R-value of foam board insulation from the label on the insulation or from manufacturer shipping materials available onsite. This inspection must be done prior to application of interior finish and after service systems are installed within the wall and/or before exterior finish that would hide the insulation from inspection. Determine that wall insulation is installed in accordance with the manufacturer’s installation instructions and all places in the wall that will accommodate insulation are insulated. Verify the instructions are onsite or are readily available to the insulation contractors/installers. If the insulation is integral to a masonry wall (e.g., applied to concrete masonry unit open areas or integral to insulated concrete forms), verify that the insulation is uniformly applied throughout the wall. Insulation Labeling Verify that all insulation installed in the building thermal envelope is labeled as to the tested R-value Verify that the label is visible for inspection If no label, verify that the insulation contractor/installer has provided a certificate verifying the thickness installed and the delivered R-value as installed.
  39. Ceiling Insulation and Installation Determine and record the R-value(s) of insulation applied to any framed ceiling. For blown-in attic insulation, verify that the thickness of the insulation is written on markers at a rate of one every 300 ft2 of attic space and compare this with the insulation certificate. This inspection must be done prior to application of interior finish and after service systems installed within the ceiling and/or before exterior finish that would hide the insulation from inspection. If credit is taken for a raised heel, energy or oversized truss rafter system, verify such a system has been installed. Verify that insulation is installed in accordance with the manufacturer’s installation instructions. Attic Access Insulation Determine and record the R-value(s) of insulation applied to any attic access hatches and doors.
  40. Basement Insulation and Installation Determine and record the R-value of exterior insulation applied to a wall associated with a conditioned basement or a basement that is unconditioned but does not have the floor above and other components separating the basement from the rest of the building insulated as part of the building envelope. A basement wall is one that is at least 50% below grade. This inspection must be done immediately prior to backfilling when the insulation installation is completely visible. Verify that the insulation is installed according to manufacturer’s instructions. Floor Insulation R-Value and Installation Determine and record the R-value(s) of insulation applied to any wood-framed, steel-framed, or raised (e.g., not slab on grade) concrete floor associated with the building thermal envelope. If continuous insulation is installed, record the R-value of foam board insulation from the label on the insulation or from manufacturer shipping materials available onsite. Verify that floor insulation is installed in accordance with the manufacturer’s installation instructions, that all places in the floor that will accommodate insulation are insulated, and that the insulation is installed in direct contact with the underside of the subfloor decking. Verify the installation instructions are onsite or are readily available to the insulation contractors/installers. This inspection must be done prior to completion of subsequent construction that would make the insulation inaccessible. Vapor Retarders – Code Requirements Requirements Install on “warm-in-winter side” of insulation Use in unvented framed walls, floors, and ceilings Exceptions In construction where moisture or its freezing won’t damage materials If other approved means to avoid condensation are provided Basement Wall Interior Insulation and Installation Determine and record the R-value(s) of insulation applied to the interior of a wall associated with a conditioned basement or a basement that is unconditioned but does not have the floor above and other components separating the basement from the rest of the building insulated as part of the building envelope. A basement wall is one that is at least 50% below grade. Determine that basement wall insulation is installed in accordance with the manufacturer’s installation instructions and all places in the wall that will accommodate insulation are insulated. Verify the instructions are onsite or are readily available to the insulation contractors/installers. This inspection must be done prior to application of interior finish and after service systems are within the wall and/or before exterior finish that would hide the insulation from inspection. If the insulation is integral to a masonry basement wall (e.g., applied to CMU open areas or integral to insulated concrete forms), verify that the insulation is uniformly applied throughout the basement wall. Crawl Space Wall Insulation and Installation Determine and record the R-value of insulation applied to the interior or exterior of walls associated with crawl spaces that are not ventilated to the outside. If the crawl space is ventilated, the floor above the crawl space must be insulated instead of insulating the crawl space walls. Insulation installed on the exterior of the foundation wall must be inspected when the insulation is completely visible, immediately prior to backfilling. Insulation installed on the interior of the foundation wall will typically be inspected during the insulation inspection, in which case this checklist item may be left blank until that inspection stage. Insulation must be installed according to manufacturer’s instructions. Insulation must maintain permanent contact with underside of subfloor When crawlspace walls are insulated, the space should be mechanically vented or conditioned. See Section R408 of the IRC. Vented Crawlspace Requirements: The raised floor over the crawlspace must be insulated. A vapor retarder may be required as part of the floor assembly. Ventilation openings must exist that are equal to at least 1 square foot for each 150 square feet of crawlspace area and be placed to provide cross-flow (IRC 408.1, may be less if ground vapor retarder is installed). Ducts in crawlspace must be sealed and have R-8 insulation. Unvented Crawlspace Requirements: The crawlspace ground surface must be covered with an approved vapor retarder (e.g., plastic sheeting). Crawlspace walls must be insulated to the R-value requirements specific for crawlspace walls (IECC Table 402.1). Crawlspace wall insulation must extend from the top of the wall to the inside finished grade and then 24” vertically or horizontally. Crawlspaces must be mechanically vented (1 cfm exhaust per 50 square feet) or conditioned (heated and cooled as part of the building envelope).
  41. Air Sealing for New Home Construction Air sealing is an important factor when constructing an energy-efficient home. These are some air sealing techniques and materials: Air barriers Airtight Drywall, and Simple Caulk and Seal Caulking Weatherstripping. Before developing an air sealing strategy, you should also consider the interaction between any air sealing materials and techniques with other building components, including the following: Insulation Moisture control Ventilation. This is called the whole-house systems approach.
  42. Duct Insulation Determine and record the R-value(s) of insulation applied to, or used in, the manufacture of heating and/or cooling ducts that are not completely inside the building thermal envelope (e.g., are located outside the conditioned space). Duct Sealing Verify that all ducts, air handlers, filter boxes, and building cavities used as return air ducts have joints and seams sealed. Verify before application of any duct insulation and before the ducts are made inaccessible for inspection by subsequent construction. Where flexible ducts are installed, containing insulation as an integral component of the duct, conduct the inspection for duct sealing before the connections of the flex duct are taped. Insulation Ducts outside the building envelope shall be insulated to R-8 R-6 allowed for ducts in floor trusses Sealing Joints and seams shall comply with IRC, Section M1601.3.1 Building framing cavities shall not be used as supply ducts
  43. Duct Tightness Testing Verify that the ducts and air handler, if not completely located inside the conditioned spaces, were tested for tightness. If tested: Record when the test was conducted (pre-construction or rough in) The leakage rate from the test The specifications under which the test was administered. This information should be available on a test report by the entity conducting the test. Building Cavities as Supply Ducts Verify that no building cavities are used as supply ducts (e.g., function to actually form the duct).
  44. Air Sealing Determine compliance with the air sealing requirements via testing or visual inspection of select components of the building. If testing was performed, record when the test was conducted (after rough-in and installation of penetrations), the leakage rate from the test, and the specifications under which the test was administered. This information should be available on a test report by the entity conducting the test. If testing was not performed, conduct a visual inspection of all components listed in the code and determine if they were satisfied. The building is deemed to comply only if all applicable criteria are satisfied. Air Sealing Data Collection Checklist The checklist will assist you in making sure all requirements are inspected. If testing was performed, record when the test was conducted (after rough-in and installation of penetrations), the leakage rate from the test, and the specifications under which the test was administered. This information should be available on a test report by the entity conducting the test. Door U-Factor Determine and record the U-factor(s) for the door assemblies installed in the building envelope. This information should be available from one of the following: A label applied to the assembly Packaging associated with the product By recording the manufacturer make and model number and frame type and looking up the information from the manufacturer’s web site www.nfrc.org. Under the prescriptive approach only, up to 24 ft2 of side-hinged door need not meet the specified U-factor in the code. Indicate in the comments the total area of any non-complying products.
  45. Answer is #2
  46. Answer #1
  47. Answer is #2
  48. Answer is #2
  49. *finish hardware and rough hardware was not included in “The price is right”
  50. Recessed Lighting Fixtures Identify all recessed lighting fixtures installed in the building envelope Verify that they are IC rated and labeled as meeting the code requirements Verify that they have a gasket or caulk applied between the fixture housing and the interior finish of the space where they are located. Type IC rated and labeled in a sealed or gasketed enclosure Type IC rated and labeled as meeting ASTM E 283 with no more than 2.0 cfm of air movement Located inside an airtight box with clearances of at least 0.5 inch from combustible material and 3 inches from insulation Lighting Determine how many permanently installed lamps there are in the dwelling unit Determine how many of those have high efficacy lamps (>=60 lumens per watt when over 40 watts, 50 for over 15 to 40, and 40 for 15 or less) One fixture may have multiple lamps The building must have at least 50% high-efficacy lamps to be deemed compliant.
  51. Change layoutRESPECTING AND CONSERVING WATER In-home water conservation Water-efficient plumbing fixtures and appliances Toilets - <1.6 gallons/flush (1994 Fed. Std.) Showerhead Faucet screens Hot water distribution On demand Home-run plumbing 3/8“ tubing
  52. Clean up slide on right separate screen
  53. Circulating Hot-Water Piping Insulation Determine and record the R-value(s) of insulation applied to circulating service hot water piping, regardless of location. Inspect prior to application of additional pipe coatings or subsequent construction that would make the piping inaccessible for inspection. Identify all pumps associated with the circulating service hot water system. Verify that pumps have an automatic or readily accessible manual control that can turn the unit off when not in use. This inspection should be done by loading (e.g., turning on) each affected system and observing pump operation. Service Water Piping System Controls Verify that circulating service hot water systems have controls to allow manually or automatically turning off the pump(s) when the system is not in use. R-2 required on HVAC systems Exception: Piping that conveys fluids between 55 and 105°F All circulating domestic hot water systems
  54. Change layout Treatment series to follow
  55. PHOTOVOLTAICS (PV) Direct conversion of sunlight Makes no use of a rotating dynamo – all others do Utilizes a semiconductor to create electron flow
  56. Bill sent clearer pictures
  57. Tank-less unit cut-away
  58. Insert slides series Gas Systems, Oil Systems, Electric Systems
  59. Mandatory Requirements Systems - Equipment efficiency set by Federal law, not the I-Codes Controls Heat pump supplementary heat Ducts Sealing Insulation HVAC piping insulation Circulating hot water systems Ventilation Equipment Sizing Heating Equipment Identify each piece of heating, cooling and heating/cooling equipment by manufacturer name and model number. Where multiple components are provided (e.g., split system heat pump or gas furnace/electric air conditioner) the model number of each component should be recorded. This information should be verified against the information identified in Checklist Item PR5. Programmable Thermostat Verify that each dwelling unit has a programmable thermostat for each forced air furnace that can control the heating and cooling system to allow heating temperatures down to 55 °F and cooling temperatures at least 85 °F. Heat Pump Thermostat Verify that heat pumps have a thermostat that will prevent backup heating from operating when the heating load can be satisfied by the heat pump.
  60. Add to HVAC Section
  61. Add to Ductless Mini Section
  62. Ground Source Heat Pump draws heat from the ground during the winters months and transfers the heat to the interior of the home. There is no combustion and very little energy use In the summer, it draws heat from the building and transfers it to the earth, cooling the interior of the home
  63. Change color
  64. Add to HRV Section before video?
  65. Stair Notes: Chimney Notes:
  66. Gas vented/vent-less Wood and Pellet stoves Fireplaces, Inserts and stoves Verify that all new wood burning fireplaces have outside combustion air and Gasketed doors.
  67. Wood is by far the preferred choice because of variety and cost. Oak, although very hard and durable, has lost it’s appeal. Cherry, birch, maple, hickory, alder and mahogony are most often used. In general, maple is used for painted cabinetry. Current emphasis on mixing finishes and using furniture styles. MDF is material of choice for eco conscious consumers. Stainless is generally as accent cabinetry with an industrial look. Veneer is very expensive, used only in very high end kitchen. (European influence). Shiny brass fallen out of favor Nickel, Stainless, Pewter, Steel Oil rubbed bronze Cleaner sleeker look. Door knobs, hinges, cabinet pulls are in silver or very dark finishes. No more gold. Shower enclosures are frameless. The gold shower enclosure with matching gold faucets are “home suicide/homicide.” The same silver or dark finishes are carried through with light fixtures. No more shiny brass. If brass is used it is very muted. Oil rubbed bronze very popular.
  68. Expand upon
  69. Answer #1
  70. Answer #1
  71. Answer #1
  72. higher- Fireplace and ChimneyMaterial $4,844Labor $7,266Fireplace and Chimney Total $12,110
  73. Answer #1
  74. Higher - Finish CarpentryMaterial $1,519Labor $7,784Finish Carpentry Total $9,303
  75. Higher - PaintingMaterial $4,356Labor $10,348Painting Total $14,704
  76. Finish costs listed are very low – a little bit above builder grade and are generally selected by builder. If Buyer selects finishes, costs may escalate by 20-50%.
  77. The biggest change that has been noticed by the National Association of Home Builders is that houses are getting smaller. The most likely explanation for this trend seems to be the economy. While the economy and the housing market has improved since the late 2000’s the market is still not as strong as it once was. By shifting to smaller houses the market will be able to accommodate more home buyers.
  78. As house sizes decrease it is expected that formal dining rooms, third bathrooms, and mudrooms will begin to be left out of house designs.
  79. Hardwood
  80. 1. quartz, silestone, engineered stone 2. Granite 3. Wood (generally used on island or small sections in perimeter)Black walnut most popular 4. Marble 5. Concrete 6. Stainless Steel Also glass as a countertop material is starting to show up.
  81. Boomers & Millenials both want 2, 3, 4 Neither want large spacious interiors, both prefer smaller spaces Neither want access to shopping or highways – they would rather be near walking trails, parks, nature
  82. Of the Top 10 features mentioned by home builders, four have to do with energy efficiency: Low-E windows, Energy Star-rated appliances and windows and programmable thermostats. The top features: master bedroom walk-in closets and a separate laundry room