GDAS PM Professions:
PMP Study Group
                                           Session #6: Cost Management




Monique Howard
November 13, 2008

© 2005 Hewlett-Packard Development Company, L.P.
The information contained herein is subject to change without notice
1.   As a project manager, you are aware that estimating schedule activity costs involves
     developing an approximation of the costs of the resources needed to complete each schedule
     activity.

     In approximating costs, the estimator considers the possible causes of variation of the cost
     estimates, including risks. Cost estimating includes identifying and considering various
     costing alternatives. For example, in most application areas, additional work during a design
     phase is widely held to have the potential for reducing the cost of the execution and product
     operations.

     The cost estimating process considers whether the expected savings can offset the cost of
     additional design work. Cost estimates are generally expressed in units of currency to
     facilitate comparisons both within and across projects. Cost estimates can also benefit from
     refinement during the course of the project to reflect on the additional detail available.

     For your project, which is in the initial phases, your team suggested a rough order of
     magnitude estimate - this could be in the range of :

A.   -75 to +125%
B.   -50 to +100%
C.   -25 to +50%
D.   None of the above
1.   As a project manager, you are aware that estimating schedule activity costs involves
     developing an approximation of the costs of the resources needed to complete each schedule
     activity.

     In approximating costs, the estimator considers the possible causes of variation of the cost
     estimates, including risks. Cost estimating includes identifying and considering various
     costing alternatives. For example, in most application areas, additional work during a design
     phase is widely held to have the potential for reducing the cost of the execution and product
     operations.

     The cost estimating process considers whether the expected savings can offset the cost of
     additional design work. Cost estimates are generally expressed in units of currency to
     facilitate comparisons both within and across projects. Cost estimates can also benefit from
     refinement during the course of the project to reflect on the additional detail available.

     For your project, which is in the initial phases, your team suggested a rough order of
     magnitude estimate - this could be in the range of :

A. -75 to +125%
B. -50 to +100%
C. -25 to +50%
D. None of the above
 Correct Choice: B
 Justification: A project in the initiation phase could have a rough order of magnitude (ROM) estimate in the
   range of -50 to 100%
 Reference: PMBOK Third Edition, Page Number: 161
2. Your Director is proactive in trying to identify all the projects in his portfolio which are
    going over budget. For this, he requests every project manager in his group to provide a:

A.   Performance Report
B.   Cost Management Plan
C.   Cost Baseline
D.   Performance Measure
2. Your Director is proactive in trying to identify all the projects in his portfolio which are
    going over budget. For this, he requests every project manager in his group to provide a:

A.   Performance Report
B.   Cost Management Plan
C.   Cost Baseline
D.   Performance Measure




 Correct Choice:     A  
 Justification:     Performance reports provide information on the project scope and cost
 performance, such as which budgets have been met and which have not - Performance Reports
 also alert the project team to issues that may cause problems in the future.

 Reference: PMBOK Third Edition, Page Number: 153
3. All the following statements about Cost Baseline are correct EXCEPT:

A.   It is a time phased budget
B.   To measure disbursements, a spending plan can be used as a cost-baseline
C.   It is used to measure and monitor project performance
D.   All projects have one cost baseline
3. All the following statements about Cost Baseline are correct EXCEPT:

A.   It is a time phased budget
B.   To measure disbursements, a spending plan can be used as a cost-baseline
C.   It is used to measure and monitor project performance
D.   All projects have one cost baseline




Correct Choice:    D  
Justification:     Many projects, especially large ones may have multiple cost and resource baselines, and
consumables production baselines to measure different aspects of project performance.

Reference: PMBOK Third Edition, Page Number: 170
4. If cost variance is negative, but schedule variance is positive, then this indicates:

A.   Cost and schedule are not dependent on each other
B.   The project is under budget and behind schedule
C.   The project is over budget and ahead of schedule
D.   Crashing may be recommended to make the cost variance positive
4. If cost variance is negative, but schedule variance is positive, then this indicates:

A.   Cost and schedule are not dependent on each other
B.   The project is under budget and behind schedule
C.   The project is over budget and ahead of schedule
D.   Crashing may be recommended to make the cost variance positive




 Correct Choice:     C
5. Physical Work Actually accomplished is also called

A.Planned Value
B.Earned Value
C.Actual Cost
D.Budgeted Cost for Work Scheduled (BCWS)
5. Physical Work Actually accomplished is also called

A.Planned Value
B.Earned Value
C.Actual Cost
D.Budgeted Cost   for Work Scheduled (BCWS)




 Correct Choice:     B

 Justification:

  




 Reference: pmstudy.com notes as mentioned above

 pmstudy.com comments: Also, please refer to PMBOK page 173
6. In your project, you are using Most Likely, Optimistic and Pessimistic activity duration
     estimates (for activity duration estimating). The technique that you are using is:

A.   PERT
B.   CPM
C.   Parametric Estimating
D.   None of the above
6. In your project, you are using Most Likely, Optimistic and Pessimistic activity duration
     estimates (for activity duration estimating). The technique that you are using is:

A.   PERT
B.   CPM
C.   Parametric Estimating
D.   None of the above



 Correct Choice:     4  

 Justification:     Three point estimates: The accuracy of the activity duration estimate can be improved by
 considering the amount of risk in the original estimate. Three point estimates are based on determining
 three types of estimates i.e. Most Likely, Optimistic and Pessimistic

 Reference: PMBOK Third Edition, Page Number: 142

 pmstudy.com comments: Although PERT uses Mostly, Optimistic and Pessimistic values, it is used for
 Schedule estimates and not for activity duration estimates.
7. Resource calendars affect a specific resource or category of resources. They reflect how some
    resources work only during normal business hours, while others work three full shifts, how a
    project team member might be unavailable(on vacation or in a training program), or how a
    labor contract can limit certain workers to certain days of the week. Resource calendars are
    valuable inputs for:

A. Developing an approximation of the costs of the resources needed to complete each schedule
   activity.
B. Aggregating the estimated costs of individual schedule activities or work packages to establish a
   total cost baseline for project performance
C. Searching the cause of positive and negative variances as part of Integrated Change Control
   process
D. Assuring that potential cost overruns do not exceed the authorized funding periodically and in
   total for the project.
7. Resource calendars affect a specific resource or category of resources. They reflect how some
    resources work only during normal business hours, while others work three full shifts, how a
    project team member might be unavailable(on vacation or in a training program), or how a
    labor contract can limit certain workers to certain days of the week. Resource calendars are
    valuable inputs for:

A. Developing an approximation of the costs of the resources needed to complete each schedule
   activity.
B. Aggregating the estimated costs of individual schedule activities or work packages to establish a
   total cost baseline for project performance
C. Searching the cause of positive and negative variances as part of Integrated Change Control
   process
D. Assuring that potential cost overruns do not exceed the authorized funding periodically and in
   total for the project.



  Correct Choice:     2  

  Justification:      Cost budgeting involves aggregating the estimated costs of individual
  schedule activities or work packages to establish a total cost baseline for project
  performance. (Resource calendars are an input to Cost budgeting - Figure 7-4)

  Option 1 refers to Cost Estimating; Option 3 and Option 4 refer to Cost Control.

  Reference: PMBOK Third Edition, Page Number: 167
8. You have recently taken over a new project when the previous project manager resigned.
    While studying the project information, you find out that cost variances are very severe.
    To provide a realistic basis for performance measurement, you should recommend:

A.   Issuing budget updates
B.   Revising the cost baseline
C.   Corrective action e.g. adjusting schedule activity budgets
D.   Closing the project
8. You have recently taken over a new project when the previous project manager resigned.
    While studying the project information, you find out that cost variances are very severe.
    To provide a realistic basis for performance measurement, you should recommend:

A.   Issuing budget updates
B.   Revising the cost baseline
C.   Corrective action e.g. adjusting schedule activity budgets
D.   Closing the project




Correct Choice:     2  

Justification:     In some cases, cost variances can be so severe that a revised cost baseline is
needed to provide a realistic basis for performance measurement.

Reference: PMBOK Third Edition, Page Number: 177
9. To define variance thresholds at the designated time points over the duration of a
    project, you will use:

A.   Units of Measure
B.   Precision Level
C.   Organizational Procedure Links
D.   Control Thresholds
9. To define variance thresholds at the designated time points over the duration of a
    project, you will use:

A.   Units of Measure
B.   Precision Level
C.   Organizational Procedure Links
D.   Control Thresholds




Correct Choice:     4  

Justification:     Control Thresholds: Variance thresholds for costs or other indicators (e.g. person-days, volume
or product) at designated time points over the duration of the project can be defined to indicate the agreed
amount of variation allowed.

Reference: PMBOK Third Edition, Page Number: 158
10. Earned Value Technique(EVT) is a tool and technique to measure project performance. In EVT,
     BCWP refers to:

A.   Physical work actually accomplished, including the estimated value of this work
B.   Physical work scheduled to be performed, including the estimated value of this work
C.   Actual cost incurred to accomplish the earned value
D.   Resource plan for the project
10. Earned Value Technique(EVT) is a tool and technique to measure project performance. In EVT,
     BCWP refers to:

A.   Physical work actually accomplished, including the estimated value of this work
B.   Physical work scheduled to be performed, including the estimated value of this work
C.   Actual cost incurred to accomplish the earned value
D.   Resource plan for the project




 Correct Choice:     1  

 Justification:     Earned Value (EV): The value of the completed work expressed in terms of the
 approved budget assigned to that work for a schedule activity or work breakdown structure
 component. Also referred to as Budgeted Cost of Work Performed (BCWP)

 Reference: PMBOK Third Edition, Page Number: 359
11. In your construction project, the CPI is 1.30 and SPI is 0.85. What could be the possible reason ?

A. A critical resource went on sick leave for a long period of time, which had not been anticipated
   earlier.
B. The cost of raw materials required for construction increased by 10%
C. You had not taken into account the inflation rate.
D. There was four days waiting time in the curing of cement, and work could not be done during that
   time
11. In your construction project, the CPI is 1.30 and SPI is 0.85. What could be the possible reason ?

A. A critical resource went on sick leave for a long period of time, which had not been anticipated
   earlier.
B. The cost of raw materials required for construction increased by 10%
C. You had not taken into account the inflation rate.
D. There was four days waiting time in the curing of cement, and work could not be done during that
   time
 Correct Choice: 1

 Justification: Option 2 and Option 3 increase the costs - but since the project cost is not a problem (i.e CPI
 is > 1), we can ignore these answers. Choice 4 was a known factor, and provision should have been made in
 the project schedule for it. Choice 1 is the only alternative that could have increased the schedule time and
 made SPI < 1.




 Reference: pmstudy.com notes as mentioned above, pmstudy.com commments: Also, please refer to PMBOK
 page 173, 174
12. All the following statements relating to Cost Management Plan are accurate EXCEPT:

A.   Specifies the precision level to which the schedule activity cost estimates will adhere to.
B.   Establishes variance thresholds for costs or other indicators
C.   Defines formats for various cost reports
D.   Specifies preferred tools to be used for cost estimating
12. All the following statements relating to Cost Management Plan are accurate EXCEPT:

A.   Specifies the precision level to which the schedule activity cost estimates will adhere to.
B.   Establishes variance thresholds for costs or other indicators
C.   Defines formats for various cost reports
D.   Specifies preferred tools to be used for cost estimating




Correct Choice:     4  

Justification:     Cost management plan does not specify preferred tools to be used for cost estimating

Reference: pmstudy.com notes as mentioned above

pmstudy.com commments: Also, please refer to PMBOK page 158, 159
13. In your project, there have been several changes in the cost and schedule estimates and the
   original estimating assumptions are no longer valid. What is the Estimate at Complete for your
   project?

     * BAC = $ 300,000
     * AC = $ 100,000
     * EV = $ 150,000
     * CPI = $ 1.2
     * ETC = $ 120,000


A.   $ 250,000
B.   $ 220,000
C.   $ 280,000
D.   $ 300,000
13. In your project, there have been several changes in the cost and schedule estimates and the
   original estimating assumptions are no longer valid. What is the Estimate at Complete for your
   project?

     * BAC = $ 300,000
     * AC = $ 100,000
     * EV = $ 150,000
     * CPI = $ 1.2
     * ETC = $ 120,000


A.   $ 250,000
B.   $ 220,000
C.   $ 280,000
D.   $ 300,000

Correct Choice: 2

Justification: Since Original Estimating Assumptions are no longer
valid, EAC = AC + ETC = $ 100,000 + $ 120,000 = $ 220,000


Reference: pmstudy.com notes as mentioned above
14. When deciding which project to select,

A.   Select the project with higher Life Cycle Cost
B.   Select the project with lower Life Cycle Cost
C.   Select the project with higher Sunk Cost
D.   Select the project with lower Sunk Cost
14. When deciding which project to select,

A.   Select the project with higher Life Cycle Cost
B.   Select the project with lower Life Cycle Cost
C.   Select the project with higher Sunk Cost
D.   Select the project with lower Sunk Cost




     Correct Choice:     2  

     Justification:     Sunk costs are already incurred, so they cannot be avoided and hence should not be taken
     into account in project selection.

     Reference: pmstudy.com notes as mentioned above
15. A project has the following characteristics:

     * Payback of $ 2,000
     * Profit of $ 1,000
     * Project Cost of $ 800
     * Life Cycle Cost of $ 1200

     What is the Benefit Cost Ratio of the project?
A.   2.50
B.   1.25
C.   1.67
D.   0.83
15. A project has the following characteristics:

     * Payback of $ 2,000
     * Profit of $ 1,000
     * Project Cost of $ 800
     * Life Cycle Cost of $ 1200

     What is the Benefit Cost Ratio of the project?
A.   2.50
B.   1.25
C.   1.67
D.   0.83




Correct Choice:     1  

Justification:     BCR = Payback/Project Cost =
2000/800 = 2.50



Reference: pmstudy.com notes as mentioned above
16. In your project, you have reason to believe that the current variances occurred because of
   extraneous factors, and you do not expect similar variances to happen in the future. What
   should be the Estimate at Complete for your project?

  * BAC = $ 300,000
  * AC = $ 100,000
  * EV = $ 150,000
  * CPI = $ 1.5


$ 250,000
$ 220,000
$ 280,000
$ 200,000
16. In your project, you have reason to believe that the current variances occurred because of
    extraneous factors, and you do not expect similar variances to happen in the future. What should be
    the Estimate at Complete for your project?

    * BAC = $ 300,000
    * AC = $ 100,000
    * EV = $ 150,000
    * CPI = $ 1.5


 $ 250,000
 $ 220,000
 $ 280,000
 $ 200,000


Correct Choice: 1

Justification: Since current variances are atypical,
Estimate at Complete, EAC = AC + (BAC - EV) = $ 100,000
+ ($ 300,000 - $ 150,000) = $ 250,000


Reference: pmstudy.com notes as mentioned above
17. Please refer to the following diagram:




      What is the status of the project?

      A.Behind Schedule, Under Budget
      B.Ahead of Schedule, Under Budget
      C.Ahead of Schedule, Over Budget
      D.Behind Schedule, Over Budget
Correct Choice: 3

Justification:
Earned Value (EV)
= The sum of the approved cost estimates for activities completed
during a given period
= Estimated cost of work that is completed after day 11
= $ 5,000 + $ 5,000 + $5,000*.50 = $ 12,500 (because Task A,
Task B are complete, Task C is 50% complete)

Present Value(PV)
= Present work to be completed after day 11
= $ 5,000 + $ 5,000 + $ 5,000 * (1/5) (because at end of day 11,
according to our plan, Task A, Task B should be complete; Task C
only one day out of 5 days should be complete i.e. 20% complete
i.e. $ 1,000 of work should be done)
= $ 11,000

Actual Cost (AC)
= Actual Cost of work completed
= $ 13,000

Schedule Variance(SV)
= EV - PV = $ 12,500 - $ 11,000 = $ 1,500
Since SV is positive, we are Ahead of Schedule

Cost Variance(CV)
= EV - AC = $ 12,500 - $ 13,000 = - $ 500
Since CV is negative, we are Over Budget

Reference: pmstudy.com notes as mentioned above
18. In your project, if the Benefit Cost Ratio is greater than 1, it means that

A.   The ratio of profits to cost is greater than 1
B.   The ratio of revenue to cost is greater than 1
C.   You should select this project from all other competing alternatives
D.   Appropriate project management processes have not been used during project planning
18. In your project, if the Benefit Cost Ratio is greater than 1, it means that

A.   The ratio of profits to cost is greater than 1
B.   The ratio of revenue to cost is greater than 1
C.   You should select this project from all other competing alternatives
D.   Appropriate project management processes have not been used during project planning




     Correct Choice: 2

     Justification:




     Please note that Option 3 is not valid because you do not know about other competing alternatives. The competing alternatives may have a greater
     Benefit Cost Ratio than this project.

     Reference: pmstudy.com notes as mentioned above
19. A project was expected to cost $ 6 million for three months. At the end of one month, you
    use Earned Value as a performance management tool and get the following information:

     * BCWP = $ 1.5 million
     * BCWS = $ 2.5 million
     * ACWP = $ 2.2 million

     What is the Schedule Variance?

A.   -0.3 Million
B.   -1 Million
C.   1 Million
D.   0.7 Million
19. A project was expected to cost $ 6 million for three months. At the end of one month, you
    use Earned Value as a performance management tool and get the following information:

     * BCWP = $ 1.5 million
     * BCWS = $ 2.5 million
     * ACWP = $ 2.2 million

     What is the Schedule Variance?

A.   -0.3 Million
B.   -1 Million
C.   1 Million
D.   0.7 Million

Correct Choice: 2

Justification:
Schedule Variance
= Earned Value - Present Value
= BCWP - BCWS
= $ 1.5 Million - $ 2.5 Million
= $ - 1 Million

Negative schedule variance means that the project is behind
schedule

Reference: pmstudy.com notes as mentioned above
Wrap Up
    Conference Number: 547-941-6414 or 866-547-8978
    Passcode: Leader – 844306338, Participant – 370670831


8     Procurement Management and      November 20   2:00pm   Presenter:      https://
      Tips & Tricks (PMBOK Chapters                 EST
                                                             www.rooms.hp.com/attend/default.aspx?key=EH629P4V3N
      12)                                                    Participant:    https://
                                                             www.rooms.hp.com/attend/default.aspx?key=EPKZ32VF62

Contenu connexe

Tendances

ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2
ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2
ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2
Anne Arundel Community College
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
PMI Chennai Chapter
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Charlie Jackson
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 

Tendances (20)

08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management exam
 
Account in PWD.pptx
Account in PWD.pptxAccount in PWD.pptx
Account in PWD.pptx
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
VALUE ENGINEERING CONCEPT-A BRIEF IN CONSTRUCTION INDUSTRY
VALUE ENGINEERING CONCEPT-A BRIEF IN CONSTRUCTION INDUSTRYVALUE ENGINEERING CONCEPT-A BRIEF IN CONSTRUCTION INDUSTRY
VALUE ENGINEERING CONCEPT-A BRIEF IN CONSTRUCTION INDUSTRY
 
ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2
ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2
ACH 231 Lecture 08 (Submittals And Shop Drawings) Part 2
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
 
Pm study project risk management test
Pm study project  risk management testPm study project  risk management test
Pm study project risk management test
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
Importance of Communication in Project Managment
Importance of Communication in Project ManagmentImportance of Communication in Project Managment
Importance of Communication in Project Managment
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Contract management sys
Contract management sysContract management sys
Contract management sys
 

Similaire à Session 6 gdas pmp study group presentation

1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
Baskar El
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
selinasimpson1601
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
Daniel Hucks
 
L03 integration management
L03 integration managementL03 integration management
L03 integration management
Asa Chan
 
1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdf1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdf
suhshbhosale
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
Asa Chan
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
reddvise
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
sheryl90
 
Part 11) You are providing a revie.docx
Part 11) You are providing a revie.docxPart 11) You are providing a revie.docx
Part 11) You are providing a revie.docx
karlhennesey
 
EM660 PROJECT MANAGEMENTClass 6Class 6 Agenda Fi.docx
EM660 PROJECT MANAGEMENTClass 6Class 6 Agenda Fi.docxEM660 PROJECT MANAGEMENTClass 6Class 6 Agenda Fi.docx
EM660 PROJECT MANAGEMENTClass 6Class 6 Agenda Fi.docx
jack60216
 
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 MBA 6951, Managing Complex Projects 1 Course Learning.docx MBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docx
aryan532920
 
1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx
dorishigh
 

Similaire à Session 6 gdas pmp study group presentation (20)

1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
engineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptxengineering economics lect 8-10 final.pptx
engineering economics lect 8-10 final.pptx
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
 
L03 integration management
L03 integration managementL03 integration management
L03 integration management
 
1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdf1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdf
 
Project Management Process
Project Management ProcessProject Management Process
Project Management Process
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Chap 5 Estimating Project Times
Chap 5 Estimating Project TimesChap 5 Estimating Project Times
Chap 5 Estimating Project Times
 
Introduction to cost management &amp; control in construction projects
Introduction to cost management &amp; control in construction projectsIntroduction to cost management &amp; control in construction projects
Introduction to cost management &amp; control in construction projects
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
Part 11) You are providing a revie.docx
Part 11) You are providing a revie.docxPart 11) You are providing a revie.docx
Part 11) You are providing a revie.docx
 
EM660 PROJECT MANAGEMENTClass 6Class 6 Agenda Fi.docx
EM660 PROJECT MANAGEMENTClass 6Class 6 Agenda Fi.docxEM660 PROJECT MANAGEMENTClass 6Class 6 Agenda Fi.docx
EM660 PROJECT MANAGEMENTClass 6Class 6 Agenda Fi.docx
 
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 MBA 6951, Managing Complex Projects 1 Course Learning.docx MBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 
Project Mangement
Project MangementProject Mangement
Project Mangement
 
1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx
 

Plus de Tu Nguyen, PMP®,PMI-RMP® (20)

4.contracting
4.contracting4.contracting
4.contracting
 
3.estimating
3.estimating3.estimating
3.estimating
 
2.tendering
2.tendering2.tendering
2.tendering
 
1.introduction
1.introduction1.introduction
1.introduction
 
Session 8 gdas pmp study group presentation
Session 8   gdas pmp study group presentationSession 8   gdas pmp study group presentation
Session 8 gdas pmp study group presentation
 
Session 7 gdas pmp study group presentation
Session 7   gdas pmp study group presentationSession 7   gdas pmp study group presentation
Session 7 gdas pmp study group presentation
 
Session 4 gdas pmp study group presentation
Session 4   gdas pmp study group presentationSession 4   gdas pmp study group presentation
Session 4 gdas pmp study group presentation
 
Session 10 gdas pmp study group presentation
Session 10   gdas pmp study group presentationSession 10   gdas pmp study group presentation
Session 10 gdas pmp study group presentation
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
 
Session 2 gdas pmp study group presentation
Session 2   gdas pmp study group presentationSession 2   gdas pmp study group presentation
Session 2 gdas pmp study group presentation
 
Node
NodeNode
Node
 
Contract
ContractContract
Contract
 
Cash flow
Cash flowCash flow
Cash flow
 
Bar chart
Bar chartBar chart
Bar chart
 
Arrow computation
Arrow computationArrow computation
Arrow computation
 
Arrow
ArrowArrow
Arrow
 
Administration
AdministrationAdministration
Administration
 
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
 
Time cost-control
Time cost-controlTime cost-control
Time cost-control
 
Resources
ResourcesResources
Resources
 

Session 6 gdas pmp study group presentation

  • 1. GDAS PM Professions: PMP Study Group Session #6: Cost Management Monique Howard November 13, 2008 © 2005 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice
  • 2. 1. As a project manager, you are aware that estimating schedule activity costs involves developing an approximation of the costs of the resources needed to complete each schedule activity. In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including risks. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution and product operations. The cost estimating process considers whether the expected savings can offset the cost of additional design work. Cost estimates are generally expressed in units of currency to facilitate comparisons both within and across projects. Cost estimates can also benefit from refinement during the course of the project to reflect on the additional detail available. For your project, which is in the initial phases, your team suggested a rough order of magnitude estimate - this could be in the range of : A. -75 to +125% B. -50 to +100% C. -25 to +50% D. None of the above
  • 3. 1. As a project manager, you are aware that estimating schedule activity costs involves developing an approximation of the costs of the resources needed to complete each schedule activity. In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including risks. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution and product operations. The cost estimating process considers whether the expected savings can offset the cost of additional design work. Cost estimates are generally expressed in units of currency to facilitate comparisons both within and across projects. Cost estimates can also benefit from refinement during the course of the project to reflect on the additional detail available. For your project, which is in the initial phases, your team suggested a rough order of magnitude estimate - this could be in the range of : A. -75 to +125% B. -50 to +100% C. -25 to +50% D. None of the above Correct Choice: B Justification: A project in the initiation phase could have a rough order of magnitude (ROM) estimate in the range of -50 to 100% Reference: PMBOK Third Edition, Page Number: 161
  • 4. 2. Your Director is proactive in trying to identify all the projects in his portfolio which are going over budget. For this, he requests every project manager in his group to provide a: A. Performance Report B. Cost Management Plan C. Cost Baseline D. Performance Measure
  • 5. 2. Your Director is proactive in trying to identify all the projects in his portfolio which are going over budget. For this, he requests every project manager in his group to provide a: A. Performance Report B. Cost Management Plan C. Cost Baseline D. Performance Measure Correct Choice:     A   Justification:     Performance reports provide information on the project scope and cost performance, such as which budgets have been met and which have not - Performance Reports also alert the project team to issues that may cause problems in the future. Reference: PMBOK Third Edition, Page Number: 153
  • 6. 3. All the following statements about Cost Baseline are correct EXCEPT: A. It is a time phased budget B. To measure disbursements, a spending plan can be used as a cost-baseline C. It is used to measure and monitor project performance D. All projects have one cost baseline
  • 7. 3. All the following statements about Cost Baseline are correct EXCEPT: A. It is a time phased budget B. To measure disbursements, a spending plan can be used as a cost-baseline C. It is used to measure and monitor project performance D. All projects have one cost baseline Correct Choice:    D   Justification:     Many projects, especially large ones may have multiple cost and resource baselines, and consumables production baselines to measure different aspects of project performance. Reference: PMBOK Third Edition, Page Number: 170
  • 8. 4. If cost variance is negative, but schedule variance is positive, then this indicates: A. Cost and schedule are not dependent on each other B. The project is under budget and behind schedule C. The project is over budget and ahead of schedule D. Crashing may be recommended to make the cost variance positive
  • 9. 4. If cost variance is negative, but schedule variance is positive, then this indicates: A. Cost and schedule are not dependent on each other B. The project is under budget and behind schedule C. The project is over budget and ahead of schedule D. Crashing may be recommended to make the cost variance positive Correct Choice:     C
  • 10. 5. Physical Work Actually accomplished is also called A.Planned Value B.Earned Value C.Actual Cost D.Budgeted Cost for Work Scheduled (BCWS)
  • 11. 5. Physical Work Actually accomplished is also called A.Planned Value B.Earned Value C.Actual Cost D.Budgeted Cost for Work Scheduled (BCWS) Correct Choice: B Justification:   Reference: pmstudy.com notes as mentioned above pmstudy.com comments: Also, please refer to PMBOK page 173
  • 12. 6. In your project, you are using Most Likely, Optimistic and Pessimistic activity duration estimates (for activity duration estimating). The technique that you are using is: A. PERT B. CPM C. Parametric Estimating D. None of the above
  • 13. 6. In your project, you are using Most Likely, Optimistic and Pessimistic activity duration estimates (for activity duration estimating). The technique that you are using is: A. PERT B. CPM C. Parametric Estimating D. None of the above Correct Choice:     4   Justification:     Three point estimates: The accuracy of the activity duration estimate can be improved by considering the amount of risk in the original estimate. Three point estimates are based on determining three types of estimates i.e. Most Likely, Optimistic and Pessimistic Reference: PMBOK Third Edition, Page Number: 142 pmstudy.com comments: Although PERT uses Mostly, Optimistic and Pessimistic values, it is used for Schedule estimates and not for activity duration estimates.
  • 14. 7. Resource calendars affect a specific resource or category of resources. They reflect how some resources work only during normal business hours, while others work three full shifts, how a project team member might be unavailable(on vacation or in a training program), or how a labor contract can limit certain workers to certain days of the week. Resource calendars are valuable inputs for: A. Developing an approximation of the costs of the resources needed to complete each schedule activity. B. Aggregating the estimated costs of individual schedule activities or work packages to establish a total cost baseline for project performance C. Searching the cause of positive and negative variances as part of Integrated Change Control process D. Assuring that potential cost overruns do not exceed the authorized funding periodically and in total for the project.
  • 15. 7. Resource calendars affect a specific resource or category of resources. They reflect how some resources work only during normal business hours, while others work three full shifts, how a project team member might be unavailable(on vacation or in a training program), or how a labor contract can limit certain workers to certain days of the week. Resource calendars are valuable inputs for: A. Developing an approximation of the costs of the resources needed to complete each schedule activity. B. Aggregating the estimated costs of individual schedule activities or work packages to establish a total cost baseline for project performance C. Searching the cause of positive and negative variances as part of Integrated Change Control process D. Assuring that potential cost overruns do not exceed the authorized funding periodically and in total for the project. Correct Choice:     2   Justification:      Cost budgeting involves aggregating the estimated costs of individual schedule activities or work packages to establish a total cost baseline for project performance. (Resource calendars are an input to Cost budgeting - Figure 7-4) Option 1 refers to Cost Estimating; Option 3 and Option 4 refer to Cost Control. Reference: PMBOK Third Edition, Page Number: 167
  • 16. 8. You have recently taken over a new project when the previous project manager resigned. While studying the project information, you find out that cost variances are very severe. To provide a realistic basis for performance measurement, you should recommend: A. Issuing budget updates B. Revising the cost baseline C. Corrective action e.g. adjusting schedule activity budgets D. Closing the project
  • 17. 8. You have recently taken over a new project when the previous project manager resigned. While studying the project information, you find out that cost variances are very severe. To provide a realistic basis for performance measurement, you should recommend: A. Issuing budget updates B. Revising the cost baseline C. Corrective action e.g. adjusting schedule activity budgets D. Closing the project Correct Choice:     2   Justification:     In some cases, cost variances can be so severe that a revised cost baseline is needed to provide a realistic basis for performance measurement. Reference: PMBOK Third Edition, Page Number: 177
  • 18. 9. To define variance thresholds at the designated time points over the duration of a project, you will use: A. Units of Measure B. Precision Level C. Organizational Procedure Links D. Control Thresholds
  • 19. 9. To define variance thresholds at the designated time points over the duration of a project, you will use: A. Units of Measure B. Precision Level C. Organizational Procedure Links D. Control Thresholds Correct Choice:     4   Justification:     Control Thresholds: Variance thresholds for costs or other indicators (e.g. person-days, volume or product) at designated time points over the duration of the project can be defined to indicate the agreed amount of variation allowed. Reference: PMBOK Third Edition, Page Number: 158
  • 20. 10. Earned Value Technique(EVT) is a tool and technique to measure project performance. In EVT, BCWP refers to: A. Physical work actually accomplished, including the estimated value of this work B. Physical work scheduled to be performed, including the estimated value of this work C. Actual cost incurred to accomplish the earned value D. Resource plan for the project
  • 21. 10. Earned Value Technique(EVT) is a tool and technique to measure project performance. In EVT, BCWP refers to: A. Physical work actually accomplished, including the estimated value of this work B. Physical work scheduled to be performed, including the estimated value of this work C. Actual cost incurred to accomplish the earned value D. Resource plan for the project Correct Choice:     1   Justification:     Earned Value (EV): The value of the completed work expressed in terms of the approved budget assigned to that work for a schedule activity or work breakdown structure component. Also referred to as Budgeted Cost of Work Performed (BCWP) Reference: PMBOK Third Edition, Page Number: 359
  • 22. 11. In your construction project, the CPI is 1.30 and SPI is 0.85. What could be the possible reason ? A. A critical resource went on sick leave for a long period of time, which had not been anticipated earlier. B. The cost of raw materials required for construction increased by 10% C. You had not taken into account the inflation rate. D. There was four days waiting time in the curing of cement, and work could not be done during that time
  • 23. 11. In your construction project, the CPI is 1.30 and SPI is 0.85. What could be the possible reason ? A. A critical resource went on sick leave for a long period of time, which had not been anticipated earlier. B. The cost of raw materials required for construction increased by 10% C. You had not taken into account the inflation rate. D. There was four days waiting time in the curing of cement, and work could not be done during that time Correct Choice: 1 Justification: Option 2 and Option 3 increase the costs - but since the project cost is not a problem (i.e CPI is > 1), we can ignore these answers. Choice 4 was a known factor, and provision should have been made in the project schedule for it. Choice 1 is the only alternative that could have increased the schedule time and made SPI < 1. Reference: pmstudy.com notes as mentioned above, pmstudy.com commments: Also, please refer to PMBOK page 173, 174
  • 24. 12. All the following statements relating to Cost Management Plan are accurate EXCEPT: A. Specifies the precision level to which the schedule activity cost estimates will adhere to. B. Establishes variance thresholds for costs or other indicators C. Defines formats for various cost reports D. Specifies preferred tools to be used for cost estimating
  • 25. 12. All the following statements relating to Cost Management Plan are accurate EXCEPT: A. Specifies the precision level to which the schedule activity cost estimates will adhere to. B. Establishes variance thresholds for costs or other indicators C. Defines formats for various cost reports D. Specifies preferred tools to be used for cost estimating Correct Choice:     4   Justification:     Cost management plan does not specify preferred tools to be used for cost estimating Reference: pmstudy.com notes as mentioned above pmstudy.com commments: Also, please refer to PMBOK page 158, 159
  • 26. 13. In your project, there have been several changes in the cost and schedule estimates and the original estimating assumptions are no longer valid. What is the Estimate at Complete for your project? * BAC = $ 300,000 * AC = $ 100,000 * EV = $ 150,000 * CPI = $ 1.2 * ETC = $ 120,000 A. $ 250,000 B. $ 220,000 C. $ 280,000 D. $ 300,000
  • 27. 13. In your project, there have been several changes in the cost and schedule estimates and the original estimating assumptions are no longer valid. What is the Estimate at Complete for your project? * BAC = $ 300,000 * AC = $ 100,000 * EV = $ 150,000 * CPI = $ 1.2 * ETC = $ 120,000 A. $ 250,000 B. $ 220,000 C. $ 280,000 D. $ 300,000 Correct Choice: 2 Justification: Since Original Estimating Assumptions are no longer valid, EAC = AC + ETC = $ 100,000 + $ 120,000 = $ 220,000 Reference: pmstudy.com notes as mentioned above
  • 28. 14. When deciding which project to select, A. Select the project with higher Life Cycle Cost B. Select the project with lower Life Cycle Cost C. Select the project with higher Sunk Cost D. Select the project with lower Sunk Cost
  • 29. 14. When deciding which project to select, A. Select the project with higher Life Cycle Cost B. Select the project with lower Life Cycle Cost C. Select the project with higher Sunk Cost D. Select the project with lower Sunk Cost Correct Choice:     2   Justification:     Sunk costs are already incurred, so they cannot be avoided and hence should not be taken into account in project selection. Reference: pmstudy.com notes as mentioned above
  • 30. 15. A project has the following characteristics: * Payback of $ 2,000 * Profit of $ 1,000 * Project Cost of $ 800 * Life Cycle Cost of $ 1200 What is the Benefit Cost Ratio of the project? A. 2.50 B. 1.25 C. 1.67 D. 0.83
  • 31. 15. A project has the following characteristics: * Payback of $ 2,000 * Profit of $ 1,000 * Project Cost of $ 800 * Life Cycle Cost of $ 1200 What is the Benefit Cost Ratio of the project? A. 2.50 B. 1.25 C. 1.67 D. 0.83 Correct Choice:     1   Justification:     BCR = Payback/Project Cost = 2000/800 = 2.50 Reference: pmstudy.com notes as mentioned above
  • 32. 16. In your project, you have reason to believe that the current variances occurred because of extraneous factors, and you do not expect similar variances to happen in the future. What should be the Estimate at Complete for your project? * BAC = $ 300,000 * AC = $ 100,000 * EV = $ 150,000 * CPI = $ 1.5 $ 250,000 $ 220,000 $ 280,000 $ 200,000
  • 33. 16. In your project, you have reason to believe that the current variances occurred because of extraneous factors, and you do not expect similar variances to happen in the future. What should be the Estimate at Complete for your project? * BAC = $ 300,000 * AC = $ 100,000 * EV = $ 150,000 * CPI = $ 1.5 $ 250,000 $ 220,000 $ 280,000 $ 200,000 Correct Choice: 1 Justification: Since current variances are atypical, Estimate at Complete, EAC = AC + (BAC - EV) = $ 100,000 + ($ 300,000 - $ 150,000) = $ 250,000 Reference: pmstudy.com notes as mentioned above
  • 34. 17. Please refer to the following diagram: What is the status of the project? A.Behind Schedule, Under Budget B.Ahead of Schedule, Under Budget C.Ahead of Schedule, Over Budget D.Behind Schedule, Over Budget
  • 35. Correct Choice: 3 Justification: Earned Value (EV) = The sum of the approved cost estimates for activities completed during a given period = Estimated cost of work that is completed after day 11 = $ 5,000 + $ 5,000 + $5,000*.50 = $ 12,500 (because Task A, Task B are complete, Task C is 50% complete) Present Value(PV) = Present work to be completed after day 11 = $ 5,000 + $ 5,000 + $ 5,000 * (1/5) (because at end of day 11, according to our plan, Task A, Task B should be complete; Task C only one day out of 5 days should be complete i.e. 20% complete i.e. $ 1,000 of work should be done) = $ 11,000 Actual Cost (AC) = Actual Cost of work completed = $ 13,000 Schedule Variance(SV) = EV - PV = $ 12,500 - $ 11,000 = $ 1,500 Since SV is positive, we are Ahead of Schedule Cost Variance(CV) = EV - AC = $ 12,500 - $ 13,000 = - $ 500 Since CV is negative, we are Over Budget Reference: pmstudy.com notes as mentioned above
  • 36. 18. In your project, if the Benefit Cost Ratio is greater than 1, it means that A. The ratio of profits to cost is greater than 1 B. The ratio of revenue to cost is greater than 1 C. You should select this project from all other competing alternatives D. Appropriate project management processes have not been used during project planning
  • 37. 18. In your project, if the Benefit Cost Ratio is greater than 1, it means that A. The ratio of profits to cost is greater than 1 B. The ratio of revenue to cost is greater than 1 C. You should select this project from all other competing alternatives D. Appropriate project management processes have not been used during project planning Correct Choice: 2 Justification: Please note that Option 3 is not valid because you do not know about other competing alternatives. The competing alternatives may have a greater Benefit Cost Ratio than this project. Reference: pmstudy.com notes as mentioned above
  • 38. 19. A project was expected to cost $ 6 million for three months. At the end of one month, you use Earned Value as a performance management tool and get the following information: * BCWP = $ 1.5 million * BCWS = $ 2.5 million * ACWP = $ 2.2 million What is the Schedule Variance? A. -0.3 Million B. -1 Million C. 1 Million D. 0.7 Million
  • 39. 19. A project was expected to cost $ 6 million for three months. At the end of one month, you use Earned Value as a performance management tool and get the following information: * BCWP = $ 1.5 million * BCWS = $ 2.5 million * ACWP = $ 2.2 million What is the Schedule Variance? A. -0.3 Million B. -1 Million C. 1 Million D. 0.7 Million Correct Choice: 2 Justification: Schedule Variance = Earned Value - Present Value = BCWP - BCWS = $ 1.5 Million - $ 2.5 Million = $ - 1 Million Negative schedule variance means that the project is behind schedule Reference: pmstudy.com notes as mentioned above
  • 40. Wrap Up Conference Number: 547-941-6414 or 866-547-8978 Passcode: Leader – 844306338, Participant – 370670831 8 Procurement Management and November 20 2:00pm Presenter: https:// Tips & Tricks (PMBOK Chapters EST www.rooms.hp.com/attend/default.aspx?key=EH629P4V3N 12) Participant: https:// www.rooms.hp.com/attend/default.aspx?key=EPKZ32VF62