Critical Path Analysis
Critical path analysis (“CPA”) CPA is a  project analysis  and  planning  method that allows a project to completed in the shortest possible time
The need to plan complex projects ,[object Object],[object Object]
Information needed for CPA ,[object Object],[object Object],[object Object]
CPA calculates… ,[object Object],[object Object],[object Object]
What is the critical path? The sequence of project activities which add up to the  longest overall duration The critical path determines the shortest time possible to complete the project
Why is the critical path so important? Any delay of an activity on the critical path directly impacts the planned project completion date (i.e. there is no float on the critical path)
Drawing the network Component Description Node A  circle  that represents a point in time where an activity is started or finished.  The node (circle) is split into three sections: The left half of the circle is the  unique node (activity) number  – the network diagram draws these in order The top right section shows the  earliest start time (EST)  that an activity can commence based on the completion of the previous activity The bottom right section shows the  latest finish time (LFT)  by which the previous activity must be completed Activities An activity is something that takes time.  An activity is shown on the network as a  line , linking the nodes (circles).  A description of the activity, or a letter representing the activity, is usually shown above the relevant line  Duration The length of time it takes to complete an activity – shown as a number of the relevant units (e.g. hours, days)  under the activity line
The network diagram - layout 4 7 10 EST LFT Activity H 8 Activity Duration
Simple project example – revising for exams Task Activity Dependent on Duration (hours) A Gather lesson notes and read through Starting activity 10 B Identify gaps in knowledge Completion of task A 3 C Research online sources Completion of task B 5 D Procrastinate and browse Facebook Completion of task B 30 E Write revision plan & revision notes Completion of task B & C 12 F Practice past exam papers Begin when E complete 8 G Complete last minute cramming 15
Calculating ESTs ,[object Object],[object Object],[object Object],[object Object]
Calculating ESTs – Exam Project 3 13 0 1 0 0 A 10 2 10 0 B 3 C 5 D 30 4 18 0 E 12 5 30 0 F 8 6 43 0 G 15 7 58 0
Calculating LFTs ,[object Object],[object Object],[object Object]
Calculating LFTs – Exam Project 3 13 13 1 0 0 A 10 2 10 10 B 3 C 5 D 30 4 18 23 E 12 5 30 35 F 8 6 43 43 G 15 7 58 58
Calculating the float The  float  is the duration an activity can be extended or postponed so that the project still finishes within the minimum time Calculated as: LFT  less Activity Duration less  EST
Calculated float – Exam Project Activity LFT Duration EST Total Float A 10 10 0 0 B 13 3 10 0 C 23 5 13 5 D 43 30 13 0 E 35 12 18 5 F 43 8 30 5 G 58 15 43 0
Identifying the critical path ,[object Object],[object Object],[object Object]
Identifying the critical path Represents the Critical Path for this Project 3 13 13 1 0 0 A 10 2 10 10 B 3 C 5 D 30 4 18 23 E 12 5 30 35 F 8 6 43 43 G 15 7 58 58
Uses of critical path analysis ,[object Object],[object Object],[object Object],[object Object],[object Object]
Benefits and drawbacks of CPA Advantages Disadvantages Most importantly – helps reduce the risk and costs of complex projects Reliability of CPA largely based on accurate estimates and assumptions made Encourages careful assessment of the requirements of each activity in a project CPA does not guarantee the success of a project Help spot which activities have some slack (“float”) and could therefore transfer some resources = better allocation of resources Resources may not actually be as flexible as management hope when they come to address the network float A decision-making tool and a planning tool – all in one! Too many activities may the network diagram too complicated. Activities might themselves have to be broken down into mini-projects Provides managers with a useful overview of a complex project Links well with other aspects of business planning, including cash flow forecasting and budgeting
Keep up-to-date with business stories, resources, quizzes and worksheets for your business course.  Click the logo!
Follow tutor2u on Twitter tutor2u tutor2u_econ
Become a fan of tutor2u on Facebook! tutor2u on Facebook

Contenu connexe

Tendances

Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysisHarinadh Karimikonda
 
Project management Using Pert
Project management Using PertProject management Using Pert
Project management Using PertVishnu RC Vijayan
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)chandkec
 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertDagnaygebawGoshme
 
Activity Based Costing
Activity Based CostingActivity Based Costing
Activity Based CostingVikas Gupta
 
ACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxssuser85ddaa
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-controlJatindra Malik
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERTPulchowk Campus
 
Simulation technique in OR
Simulation technique in ORSimulation technique in OR
Simulation technique in ORSarabjeet Kaur
 
Generation & Screening of Project Idea
Generation & Screening of Project IdeaGeneration & Screening of Project Idea
Generation & Screening of Project IdeaMOHAMMAD IQBAL
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path MethodSimplilearn
 
Forecasting and methods of forecasting
Forecasting and methods of forecastingForecasting and methods of forecasting
Forecasting and methods of forecastingMilind Pelagade
 
Social Cost Benefit Analysis
Social Cost Benefit AnalysisSocial Cost Benefit Analysis
Social Cost Benefit AnalysisSaurabh Sood
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysisNikhil Raj
 
Market and demand analysis
Market and demand analysisMarket and demand analysis
Market and demand analysisMeenakshi Gautam
 

Tendances (20)

Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
 
Project management Using Pert
Project management Using PertProject management Using Pert
Project management Using Pert
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Forecasting Methods
Forecasting MethodsForecasting Methods
Forecasting Methods
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Network analysis
Network analysisNetwork analysis
Network analysis
 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pert
 
Activity Based Costing
Activity Based CostingActivity Based Costing
Activity Based Costing
 
ACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptx
 
Strategic drift
Strategic driftStrategic drift
Strategic drift
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Simulation technique in OR
Simulation technique in ORSimulation technique in OR
Simulation technique in OR
 
Generation & Screening of Project Idea
Generation & Screening of Project IdeaGeneration & Screening of Project Idea
Generation & Screening of Project Idea
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Forecasting and methods of forecasting
Forecasting and methods of forecastingForecasting and methods of forecasting
Forecasting and methods of forecasting
 
Social Cost Benefit Analysis
Social Cost Benefit AnalysisSocial Cost Benefit Analysis
Social Cost Benefit Analysis
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Market and demand analysis
Market and demand analysisMarket and demand analysis
Market and demand analysis
 

En vedette

En vedette (16)

Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Critical Path Ppt
Critical Path PptCritical Path Ppt
Critical Path Ppt
 
Critical analysis of e-commerce and m-commerce
Critical analysis of e-commerce and m-commerceCritical analysis of e-commerce and m-commerce
Critical analysis of e-commerce and m-commerce
 
Financial Reporting
Financial ReportingFinancial Reporting
Financial Reporting
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Static Noise margin
Static Noise margin Static Noise margin
Static Noise margin
 
Power consumption
Power consumptionPower consumption
Power consumption
 
Power dissipation cmos
Power dissipation cmosPower dissipation cmos
Power dissipation cmos
 
اسرع طريقة لاحتراف برمجة المايكروكنترولر
اسرع طريقة لاحتراف برمجة المايكروكنترولراسرع طريقة لاحتراف برمجة المايكروكنترولر
اسرع طريقة لاحتراف برمجة المايكروكنترولر
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
555 Timer IC
555 Timer IC555 Timer IC
555 Timer IC
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
 
INTRODUCTION_TO_IC
INTRODUCTION_TO_ICINTRODUCTION_TO_IC
INTRODUCTION_TO_IC
 
Financial Statement
Financial StatementFinancial Statement
Financial Statement
 

Similaire à Critical Path Analysis

Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesSAJID ALI RUK
 
Lec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project schedulingLec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project schedulingSyed Hamza
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxTecnicoItca
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementAmit Kumbar
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
L05 time management
L05 time managementL05 time management
L05 time managementAsa Chan
 
Critical path presentation for timely project completion
Critical path presentation for timely project completionCritical path presentation for timely project completion
Critical path presentation for timely project completionAniruddha Kulkarni
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateSHAZEBALIKHAN1
 
Introduction to Project Management
Introduction to Project Management Introduction to Project Management
Introduction to Project Management Joshua Miranda
 
C10 project management
C10 project managementC10 project management
C10 project managementhakimizaki
 
C10 project management
C10 project managementC10 project management
C10 project managementhakimizaki
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managersNaganna Chetty
 
SPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptxSPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptxMuhammadAbubakar114879
 
Project management - CPA
Project management - CPA Project management - CPA
Project management - CPA Martino Ayala
 

Similaire à Critical Path Analysis (20)

Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
 
Lec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project schedulingLec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project scheduling
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
Chapter 3
Chapter 3Chapter 3
Chapter 3
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
L05 time management
L05 time managementL05 time management
L05 time management
 
Critical path presentation for timely project completion
Critical path presentation for timely project completionCritical path presentation for timely project completion
Critical path presentation for timely project completion
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 
Introduction to Project Management
Introduction to Project Management Introduction to Project Management
Introduction to Project Management
 
Nce603 mod unit2
Nce603 mod unit2Nce603 mod unit2
Nce603 mod unit2
 
C10 project management
C10 project managementC10 project management
C10 project management
 
C10 project management
C10 project managementC10 project management
C10 project management
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
02-Key Definitions .pdf
02-Key Definitions .pdf02-Key Definitions .pdf
02-Key Definitions .pdf
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
SPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptxSPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptx
 
Project management - CPA
Project management - CPA Project management - CPA
Project management - CPA
 
Lecture 6
Lecture 6Lecture 6
Lecture 6
 

Plus de tutor2u

Economics Enrichment Activities
Economics Enrichment ActivitiesEconomics Enrichment Activities
Economics Enrichment Activitiestutor2u
 
Trade Unions - Revision Evaluation
Trade Unions - Revision EvaluationTrade Unions - Revision Evaluation
Trade Unions - Revision Evaluationtutor2u
 
Revision on Economics of Public Goods
Revision on Economics of Public GoodsRevision on Economics of Public Goods
Revision on Economics of Public Goodstutor2u
 
Poverty Reduction Policies in Low Income Countries
Poverty Reduction Policies in Low Income CountriesPoverty Reduction Policies in Low Income Countries
Poverty Reduction Policies in Low Income Countriestutor2u
 
20 Key Facts on the UK Economy in 2019
20 Key Facts on the UK Economy in 201920 Key Facts on the UK Economy in 2019
20 Key Facts on the UK Economy in 2019tutor2u
 
Quantitative easing advantages_disadvantages
Quantitative easing advantages_disadvantagesQuantitative easing advantages_disadvantages
Quantitative easing advantages_disadvantagestutor2u
 
Monetary union
Monetary unionMonetary union
Monetary uniontutor2u
 
UK Economy Update_2019
UK Economy Update_2019UK Economy Update_2019
UK Economy Update_2019tutor2u
 
Supply-Side Policies (2019 Examples Update)
Supply-Side Policies (2019 Examples Update)Supply-Side Policies (2019 Examples Update)
Supply-Side Policies (2019 Examples Update)tutor2u
 
Applied Macro Examples for Economics Exams
Applied Macro Examples for Economics ExamsApplied Macro Examples for Economics Exams
Applied Macro Examples for Economics Examstutor2u
 
Microeconomics - Great Applied Examples for Exams
Microeconomics - Great Applied Examples for ExamsMicroeconomics - Great Applied Examples for Exams
Microeconomics - Great Applied Examples for Examstutor2u
 
Business Objectives and Stakeholders
Business Objectives and StakeholdersBusiness Objectives and Stakeholders
Business Objectives and Stakeholderstutor2u
 
Profit Satisficing
Profit SatisficingProfit Satisficing
Profit Satisficingtutor2u
 
Why Businesses Grow
Why Businesses GrowWhy Businesses Grow
Why Businesses Growtutor2u
 
Sizes and Types of Firms
Sizes and Types of FirmsSizes and Types of Firms
Sizes and Types of Firmstutor2u
 
The UK Productivity Gap
The UK Productivity GapThe UK Productivity Gap
The UK Productivity Gaptutor2u
 
Trade Unions with a Monopsony Employer
Trade Unions with a Monopsony EmployerTrade Unions with a Monopsony Employer
Trade Unions with a Monopsony Employertutor2u
 
Labour Market Failure (2019 Update)
Labour Market Failure (2019 Update)Labour Market Failure (2019 Update)
Labour Market Failure (2019 Update)tutor2u
 
Behavioural Economics Update 2019
Behavioural Economics Update 2019Behavioural Economics Update 2019
Behavioural Economics Update 2019tutor2u
 
Consumer surplus and price changes
Consumer surplus and price changesConsumer surplus and price changes
Consumer surplus and price changestutor2u
 

Plus de tutor2u (20)

Economics Enrichment Activities
Economics Enrichment ActivitiesEconomics Enrichment Activities
Economics Enrichment Activities
 
Trade Unions - Revision Evaluation
Trade Unions - Revision EvaluationTrade Unions - Revision Evaluation
Trade Unions - Revision Evaluation
 
Revision on Economics of Public Goods
Revision on Economics of Public GoodsRevision on Economics of Public Goods
Revision on Economics of Public Goods
 
Poverty Reduction Policies in Low Income Countries
Poverty Reduction Policies in Low Income CountriesPoverty Reduction Policies in Low Income Countries
Poverty Reduction Policies in Low Income Countries
 
20 Key Facts on the UK Economy in 2019
20 Key Facts on the UK Economy in 201920 Key Facts on the UK Economy in 2019
20 Key Facts on the UK Economy in 2019
 
Quantitative easing advantages_disadvantages
Quantitative easing advantages_disadvantagesQuantitative easing advantages_disadvantages
Quantitative easing advantages_disadvantages
 
Monetary union
Monetary unionMonetary union
Monetary union
 
UK Economy Update_2019
UK Economy Update_2019UK Economy Update_2019
UK Economy Update_2019
 
Supply-Side Policies (2019 Examples Update)
Supply-Side Policies (2019 Examples Update)Supply-Side Policies (2019 Examples Update)
Supply-Side Policies (2019 Examples Update)
 
Applied Macro Examples for Economics Exams
Applied Macro Examples for Economics ExamsApplied Macro Examples for Economics Exams
Applied Macro Examples for Economics Exams
 
Microeconomics - Great Applied Examples for Exams
Microeconomics - Great Applied Examples for ExamsMicroeconomics - Great Applied Examples for Exams
Microeconomics - Great Applied Examples for Exams
 
Business Objectives and Stakeholders
Business Objectives and StakeholdersBusiness Objectives and Stakeholders
Business Objectives and Stakeholders
 
Profit Satisficing
Profit SatisficingProfit Satisficing
Profit Satisficing
 
Why Businesses Grow
Why Businesses GrowWhy Businesses Grow
Why Businesses Grow
 
Sizes and Types of Firms
Sizes and Types of FirmsSizes and Types of Firms
Sizes and Types of Firms
 
The UK Productivity Gap
The UK Productivity GapThe UK Productivity Gap
The UK Productivity Gap
 
Trade Unions with a Monopsony Employer
Trade Unions with a Monopsony EmployerTrade Unions with a Monopsony Employer
Trade Unions with a Monopsony Employer
 
Labour Market Failure (2019 Update)
Labour Market Failure (2019 Update)Labour Market Failure (2019 Update)
Labour Market Failure (2019 Update)
 
Behavioural Economics Update 2019
Behavioural Economics Update 2019Behavioural Economics Update 2019
Behavioural Economics Update 2019
 
Consumer surplus and price changes
Consumer surplus and price changesConsumer surplus and price changes
Consumer surplus and price changes
 

Dernier

Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
DEPED Work From Home WORKWEEK-PLAN.docx
DEPED Work From Home  WORKWEEK-PLAN.docxDEPED Work From Home  WORKWEEK-PLAN.docx
DEPED Work From Home WORKWEEK-PLAN.docxRodelinaLaud
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfOrient Homes
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 

Dernier (20)

Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
DEPED Work From Home WORKWEEK-PLAN.docx
DEPED Work From Home  WORKWEEK-PLAN.docxDEPED Work From Home  WORKWEEK-PLAN.docx
DEPED Work From Home WORKWEEK-PLAN.docx
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 

Critical Path Analysis

  • 2. Critical path analysis (“CPA”) CPA is a project analysis and planning method that allows a project to completed in the shortest possible time
  • 3.
  • 4.
  • 5.
  • 6. What is the critical path? The sequence of project activities which add up to the longest overall duration The critical path determines the shortest time possible to complete the project
  • 7. Why is the critical path so important? Any delay of an activity on the critical path directly impacts the planned project completion date (i.e. there is no float on the critical path)
  • 8. Drawing the network Component Description Node A circle that represents a point in time where an activity is started or finished. The node (circle) is split into three sections: The left half of the circle is the unique node (activity) number – the network diagram draws these in order The top right section shows the earliest start time (EST) that an activity can commence based on the completion of the previous activity The bottom right section shows the latest finish time (LFT) by which the previous activity must be completed Activities An activity is something that takes time. An activity is shown on the network as a line , linking the nodes (circles). A description of the activity, or a letter representing the activity, is usually shown above the relevant line Duration The length of time it takes to complete an activity – shown as a number of the relevant units (e.g. hours, days) under the activity line
  • 9. The network diagram - layout 4 7 10 EST LFT Activity H 8 Activity Duration
  • 10. Simple project example – revising for exams Task Activity Dependent on Duration (hours) A Gather lesson notes and read through Starting activity 10 B Identify gaps in knowledge Completion of task A 3 C Research online sources Completion of task B 5 D Procrastinate and browse Facebook Completion of task B 30 E Write revision plan & revision notes Completion of task B & C 12 F Practice past exam papers Begin when E complete 8 G Complete last minute cramming 15
  • 11.
  • 12. Calculating ESTs – Exam Project 3 13 0 1 0 0 A 10 2 10 0 B 3 C 5 D 30 4 18 0 E 12 5 30 0 F 8 6 43 0 G 15 7 58 0
  • 13.
  • 14. Calculating LFTs – Exam Project 3 13 13 1 0 0 A 10 2 10 10 B 3 C 5 D 30 4 18 23 E 12 5 30 35 F 8 6 43 43 G 15 7 58 58
  • 15. Calculating the float The float is the duration an activity can be extended or postponed so that the project still finishes within the minimum time Calculated as: LFT less Activity Duration less EST
  • 16. Calculated float – Exam Project Activity LFT Duration EST Total Float A 10 10 0 0 B 13 3 10 0 C 23 5 13 5 D 43 30 13 0 E 35 12 18 5 F 43 8 30 5 G 58 15 43 0
  • 17.
  • 18. Identifying the critical path Represents the Critical Path for this Project 3 13 13 1 0 0 A 10 2 10 10 B 3 C 5 D 30 4 18 23 E 12 5 30 35 F 8 6 43 43 G 15 7 58 58
  • 19.
  • 20. Benefits and drawbacks of CPA Advantages Disadvantages Most importantly – helps reduce the risk and costs of complex projects Reliability of CPA largely based on accurate estimates and assumptions made Encourages careful assessment of the requirements of each activity in a project CPA does not guarantee the success of a project Help spot which activities have some slack (“float”) and could therefore transfer some resources = better allocation of resources Resources may not actually be as flexible as management hope when they come to address the network float A decision-making tool and a planning tool – all in one! Too many activities may the network diagram too complicated. Activities might themselves have to be broken down into mini-projects Provides managers with a useful overview of a complex project Links well with other aspects of business planning, including cash flow forecasting and budgeting
  • 21. Keep up-to-date with business stories, resources, quizzes and worksheets for your business course. Click the logo!
  • 22. Follow tutor2u on Twitter tutor2u tutor2u_econ
  • 23. Become a fan of tutor2u on Facebook! tutor2u on Facebook