SlideShare une entreprise Scribd logo
1  sur  50
LEAD TIME REDUCTION VIA
VALUE STREAM MAPPING
FINAL YEAR PROJECT IN PARTIAL FULFILMENT OF REQUIREMENT FOR DEGREE OF
INDUSTRIAL ENGINEERING AND MANAGEMENT
PROJECT TEAM
STUDENTS
 UMAR YAZDANI D 11 IN 05
 AFSAAR ALI D 11 IN 27
 MALIKAH IBRAHIM D 11 IN 41
 MUHAMMAD HANIF D 11 IN 39
 ZULFIQAR ALI D 11 IN 37
SUPERVISOR
 ENGR. SHAHAB AFROZE
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
2
PROJECT OBJECTIVES
The primary objective of the project was to reduce the production lead time,
for this purpose the team selected lean manufacturing tool Value Stream
Mapping.
In addition to reduction of lead time, following benefits were expected after
the completion of the project.
 Improved productivity
 Determination of Value stream
 Better understanding of Wastes and their causes
 A roadmap towards an efficient, lean production line
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
3
PROJECT METHODOLOGY
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
4 Data
Collection
Drawing
Current State
Map
Muda
Identification
Future State
Map
Recommend
ations
COMPANY PROFILE
The Printech Packages was established in 2010 in SITE area. Printech currently
provides services for printing substrates for FMCG companies such as candy
land, Mayfair, Danpak, Pakistan beverages etc.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
5
STATE-OF-THE-ART EQUIPMENT
PTP is well equipped with some of the latest machines available in the market
today. The infrastructure comprises:
 Rotogravure printing machine 8colours
 Rotogravure printing machine 7colours
 Dry lamination
 solvent less lamination machine
 High end converting equipment like slitting, seaming, cutting, pouching,
bag making
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
6
GRAVURE PRINTING DEFINITION
Gravure Printing or rotogravure printing is a printing process which is used to
produce very high quality printing on flexible mediums such as films sheets
made up of materials like aluminum foil etc. The layout of a gravure printing
press follows an in-line arrangement where the required number of printing
units is installed along a horizontal plane. In a conventional gravure printing
press, each unit comprises of:
Printing cylinder: a seamless tubular sleeve or full cylinder, made from either
steel, aluminum, plastic, or composite material, which is engraved with the
image to be printed.
Doctor blade: the device that removes ink from the non-engraved portions of
the printing cylinder and also removes excess ink from the engraved sections
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
7
GRAVURE PRINTING (CONTD.)
Impression roller: (called rubber roller in Printech) a rubber covered sleeve that
is mounted on a steel mandrel. Its primary purpose is to press the substrate
against the printing cylinder
Inking system: Typically consisting of an ink pan, ink holding tank, and ink
pump with supply and return ink pipes.
Drying system: consisting of a chamber which dries the ink once it is on the
substrate and prior to it reaching the next printing unit. Drier capacities are
determined based on the required printing speed, ink type (solvent or water
based), and ink lay down volume, normally a shaft containing hot water was
used for this purpose in Printech.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
8
GRAVURE PRINTING PROCESS
DESCRIPTION
During the gravure printing process, the engraved cylinder on which the
pattern to be printed has already been engraved (via an outside vendor)
rotates and sinks in the ink fountain , cells are filled with the ink, as the cylinder
rotates clear off the fountain the doctor blade removes all the excess ink on
the cylinder. Further around, the cylinder is brought into contact with the
substrate, which is pressed against it by the rubber covered impression roller
(rubber roller). The pressure of rubber roller along with capillary draw of the
substrate results into the impression on the substrate and as the cylinder rotates
back into the ink fountain the substrate goes through the drying unit and then
the substrate passes on to the next unit which is mostly another color ink or a
varnish, in Printech the team observed as many as 8 color units In Printech
after printing of all colors the substrate are rewound into a finished roll.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
9
PROJECT BACKGROUND
A shorter lead time results into better utilization of
manufacturing resources, quick adaptation to customer’s
demand, reduced cost and better products. Today
companies are intensively indulging in activities to reduce
their production lead times.
The project team, keeping in mind, the importance of a
short lead time, worked in Printech Packages with the
intention to reduce Production Lead time. Technique that
the team adopted was Value Stream Mapping
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
10
VALUE STREAM MAPPING
Value stream mapping is a relatively new concept in Lean, it is not as old and
renowned as JIT or Kaizen but it is no way less in proving to be effective than
other tools. This tool at Toyota Japan was called material and information flow.
It was given its present name by Mike Rother and John Shook in their book
Learning to see.
Value stream mapping refers to process of tracing the value stream of a
product which it goes through from start to end. And ultimately differentiating
between value added and non value added activities. A great thing about
VSM is that it also helps to identify sources of wastes which other tools don’t.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
11
VALUE STREAM CYCLE
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
12
DATA COLLECTION AT PRINTECH
VSM is ideally suited to high production low variety production facilities.
Unfortunately it was not the case in the printech packages. Every job was
different and due to lack of standardization, the work and it’s time were
unpredictable. The team chose 3 of Printech's most in demand products and
worked on them. The results drawn from these 3 products will act as a model
for other products. Those jobs were;
 Chini Mini
Chini mini is a product of Danpak food industries. Its packing is printed at
Printech Packages. The printing substrate is BOPP of 20 microns and the
lamination substrate is W.CPP of 50 microns. It is reverse printed therefore it
needs to be re-winded before lamination. It is one of the most in demand job
of Printech Packages. The team selected this job due to its large production.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
13
DATA COLLECTION(CONTD.)
 Chili Milli
Chili Milli Jelly is a confectionary product of Candy Land. Its packaging is
printed at Printech Packages. The printing substrate is PET of 12 microns while
the lamination substrate is CPP of 30 microns.it is also reverse printed therefore
it is also needed to be re-winded before going for Lamination. This job also
comprises of large production volumes at Printech Packages.
 Bunta Chocolate
Bunta chocolate is a product of Danpak food industries. Its packaging is
printed at printech packages. The printing substrate is M.PET. Like above two
products it is also one of the most in demand job of Printech. Like other food
items it is reverse printed therefore it is also needed to be rewinded.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
14
CRITICAL INPUTS FOR VALUE STREAM
MAPPING
The following data are considered to be important in a value stream mapping
project.
 Cycle Time
 Changeover Time
 Machine Uptime
 # of Operators
 Queue Size
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
15
DATA TABLE FOR PRINTING
DEPARTMENT
The team collected following data on production floor of Printech Packages.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
16
Observation no.
1 2 3 4 5
Printing film material
used
BOPP PET PET PET PET
Thickness of the film
(In microns)
20 18 12 12 12
Colors used 8 3 7 5 7
Length of substrate 61057 m 61057 m 19228 m 34880 m 31134 m
Area of substrate 42740 𝑚2 51593 𝑚2 9748 𝑚2 3000 𝑚2 26775 𝑚2
Time taken 360 min 540 min 90 min 300 min 240 min
Weight inserted 800 kg 1813 kg 202 kg 508 kg 457 kg
Weight obtained 810 kg 2037 kg 213 kg 509 kg 510 kg
Machine output 170m/min 113m/min 213m/min 116m/min 130m/min
DATA TABLE FOR DRY LAMINATION
MACHINE
Observation no.
1 2 3 4 5
Printing film
material used
PET PET PET PET PET
Thickness of the film
(In microns)
12 12 12 12 12
Lamination Film
Material
ALUMINUM FOIL M.CPP PE M.PET PE.WHITE
Length of substrate 21179 49603 2538 8231 10426
Thickness of
Lamination film
52 microns 25 microns 55 microns 12 microns 60 microns
Area of substrate 13766 𝑚2 25297 𝑚2 1522 𝑚2 6584 𝑚2 7037 𝑚2
Time taken 65 min 640 min 40 min 100 min 140 min
Weight inserted
Print + Lamination
250+255 kg 459+597 kg 35+83 kg 130+114 kg 125+410 kg
Machine output 325m/min 77m/min 63m/min 82m/min 74m/min
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
17
Data Sheet for Solvent less Lamination:
Observation no.
1 2 3 4 5
Printing film material
used
BOPP BOPP PET PET BOPP
Thickness of the film
(In microns)
20 20 12 12 15
Lamination Film
Material
M.BOPP M.BOPP M.CPP PE.WHITE BOPP
Length of substrate 26890 25250 34367 21275 51559
Thickness of
Lamination film
20 microns 20 microns 25 microns 40 microns 30 microns
Area of substrate 24739 𝑚2 23230 𝑚2 25260 𝑚2 17020 𝑚2 37895 𝑚2
Time taken 180 min 170 min 180 min 90 min 300 min
Weight inserted Print
+ Lamination
500+500 kg 500+500kg 461+592kg 300+663kg 549+839kg
Machine output 150m/min 148m/min 190m/min 236m/min 171m/min
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
18
RESULTS OF DATA TABLES
Following conclusions were drawn from the data tables of different
departments.
 Processes are highly unstable
 Results are unpredictable
 Work is not standardized
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
19
1ST CURRENT STATE MAP
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
20
FINDINGS OF 1ST CURRENT STATE MAP
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
21
 PRODUCTION LEAD
TIME: 3.5 DAYS
 VALUE ADDED TIME:
28 HOURS
Non Value
Added Time
67%
Value added
time
33%
Time
Non Value Added Time Value added time
2ND CURRENT STATE MAP
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
22
FINDINGS OF 2ND CURRENT STATE MAP
 PRODUCTION
LEAD TIME: 7
DAYS
 VALUE ADDED
TIME: 48 HOURS
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
23 Non Value
Added Time
71%
Value added
time
29%
Time
Non Value Added Time Value added time
3RD CURRENT STATE MAP
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
24
FINDINGS OF 3RD CURRENT STATE MAP
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
25
 PRODUCTION
LEAD TIME: 8.5
DAYS
 VALUE ADDED
TIME: 52
HOURS
Non Value
Added Time
75%
Value added
time
25%
Time
Non Value Added Time Value added time
MAJOR SOURCES OF MUDA I.E. WASTES
AND NON VALUE ADDED ACTIVITIES
The major wastes which team found with the help of current state map are as
follows;
 Defects were not found on the production floor.
 Overproduction was not an issue either, on the contrary, underproduction
was an issue at the printech packages, the team witnessed many situations
when production was done less than the required quantity due to various
factors such as shortage of substrate, inks or other materials, or due to gas
load shedding.
 Transportation, the 3rd waste identified in Lean philosophy was also present
at the printech packages, persons pulling, loading and unloading is a
common sight at printech packages, the company consists of 8 floors and
it results into a very inefficient system of material handling.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
26
MUDA IN CURRENT STATE
MAPS(CONTD.)
 Waiting, the 4th waste identified in lean methodology was also present at
printech packages, but this waiting was in form of starvation i.e. machines
were waiting for feeds from previous in-line machines and as a result
accumulating wastes.
 Inventory waste was also accumulated in printech packages as finished
products were kept for longer periods of time without any reason and there
were also cases of under inventory when the company ran out of stocks
and production had to be stopped.
 Motion waste was also present at the printech, it is ironic to suggest it as a
waste because there was such lack of standardization that motion
elimination could not be done immediately.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
27
FUTURE STATE MAP
The team addressed all the problems discussed in the previous sections. A
future state map was drawn after some brainstorming sessions.
Note: only one future state map was drawn, unlike current state maps, where
there were separate current state maps for each product.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
28
FUTURE STATE MAP
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
29
CHANGES PROPOSED IN FUTURE STATE
MAPS
The kaizen bursts on a future
state map represent kaizen
opportunities which ,if
implemented, will result into
an overall improvement of
the system. The team placed
6 kaizen bursts on the future
state map. Following will be
a description of all those
kaizen bursts.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
30
KAIZEN BURSTS
 1ST KAIZEN BURST(FORECASTING)
The first kaizen burst placed on the FSM was forecasting. There is no forecasting
done in printech, as a result there are incidents where order is not met. A
proper forecasting method should be adopted.
 2ND KAIZEN BURST(RELOCATION OF THE ELEVATOR)
The 2nd kaizen burst suggests relocation of the elevator, which is currently
outside the production hall, it should ne relocated into production hall, it will
not only save the time but will also eliminate the need of a human operator.
 3RD KAIZEN BURST(SMED)
Quick changeover techniques should be practiced in all the departments of
printech i.e. printing, lamination, rewinding etc.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
31
KAIZEN BURSTS(CONTD.)
 4TH KAIZEN BURST(Operator Sharing)
There is a huge difference between cycle times of printing and rewinding and
also lamination and slitting, which can result into inventory piling up at those
station. To avoid this situation, the team recommends a sharing of workers
between printing and rewinding and slitting and packing.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
32
OTHER IMPROVEMENTS IN FUTURE STATE
MAP
SUPERMARKET System at the Stores
Department:
A supermarket symbol is inserted beside the
store department it suggests a setup in which
the relevant departments can draw whatever
they need and in whichever quantity. The
kanban signaling system shows that
production department will be alerted when
supermarket runs low on stocks.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
33
OTHER IMPROVEMENTS IN FUTURE STATE
MAP
FIFO lane between the departments: The
team recommends use of a FIFO lane
between all the departments The usage of
these FIFO lanes will also mean that there
will be very little waiting time and very little
bottlenecking as well. Material handling will
also be improved. It should be kept in mind
that production scheduling will only be
done at the printing department and it will
get its daily schedule from production
department and all the other departments
will process on the jobs they get from their
previous in line departments, this will result
into the overall smoothness of the
operations.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
34
OTHER IMPROVEMENTS IN FUTURE STATE
MAP
 Supermarket system after Packing:
The team proposes a supermarket system at the packing end as well. All the
finished and packed substrate would go to the supermarket where they will be
retrieved and shipped accordingly. This system will ensure a smooth
dispatching of finished goods materials.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
35
RESULTS OF FUTURE STATE MAP
 The data for the
designing of future
state map was taken
from the 3rd current
state map, here is a
comparison of the two
maps i.e. current state
and future state
maps.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
36
210
52
158
115
49
66
PRODUCTION LEAD TIME VALUE ADDED TIME NON VALUE ADDED TIME
COMPARISON OF CSM & FSM
CURRENT STATE MAP FUTURE STATE MAP
TIME REDUCTION TABLE
ACTIVITY PREVIOUS TIME NEW TIME REASON
CHANGEOVER
IN PRINT
DEPARTMENT
1-3 HOURS 30 MIN SMED
WAITING BEFORE
REWINDING
2 HOURS 10 MIN PROPER
SCHEDULING
WAITING BEFORE
LAMINATION
4 DAYS 2 DAYS PROPER
SCHEDULING
LAMINATION
CHANGEOVER
1 HOUR 30 MIN SMED
WAITING BEFORE
PACKING
2 DAYS 1 HOUR PROPER
SCHEDULING
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
37
DOWNTIME REPORT OF PRINTING
MACHINES
 THE TEAM
ALSO
COLLECTED
SOME DATA
REGARDING
DOWNTIMES
OF PRINTING
MACHINES.
THE RESULT IS AS
UNDER.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
38
Changeover, 2145,
58%
Power failure, 750,
20%
No Production Plan,
615, 17%
Technical Issues, 180,
5%
Downtimes
Changeover Power failure No Production Plan Technical Issues
DOWNTIMES
 It is evident from the previous cart that major cause of downtime of printing
machines is “long changeover process”. 55% of the total down time in 15
days, was due to changeover, followed by power crisis and no production
plan with 20% and 17% respectively.
 These long changeovers made printech a strong candidate for adoption of
SMED. The team gave detailed recommendation regarding SMED in
printing department.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
39
SINGLE MINUTE EXCHANGE OF DIES
 Step 1: Creating the SMED Team:
 Step 2: Select the Equipment:
 Step 3: Document Every Step of the Changeover:
 Step 4: Define the Target Time for the Changeover
 Step 5: Differentiate between Internal and External Steps:
 Step 6: Convert Internal Elements to External
 Step 7: Streamline Remaining Elements:
 Step 8: Implement the new method and check for results:
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
40
CHANGEOVER PROCESS AT PRINTING
DEPARTMENT OF PRINTECH PACKAGES
Steps involved in Changeover
 Winding of the substrate. Mounting rubber rollers.
 Emptying color tray. Mounting dr. blade.
 Washing color tray. Running the test run
 Dismounting the rubber rollers
 Cleaning the rubber rollers.
 Removing dr. blade.
 Bringing rubber roller, cylinder and inks on the site.
 Pouring the inks
 Mounting the substrate roll.
 Mixing different inks and solvents.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
41
PROPOSED CHANGEOVER METHOD
 Washing color tray.
 Cleaning the rubber rollers.
 Bringing rubber roller, cylinder and inks on the site.
 Mixing different Inks and solvents
(these are external steps which should be performed before stopping
the machine for changeover)
 Winding of the substrate.
 Emptying color tray.
 dismounting the rubber rollers
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
42
PROPOSED CHANGEOVER(CONTD.)
 Removing dr. blade
 Pouring the inks
 Mounting the substrate roll
 Mounting rubber rollers.
 Mounting dr. blade.
(Internal setup activities that should be performed as quickly as possible,
during this the machine is stopped)
 Running the test run
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
43
BENEFITS EXPECTED OF THE NEW
CHANGEOVER
If the above stated sequence is followed and the
continuous efforts are made to reduce the changeover
times, the ultimate goal of changing over in single minute
i.e. less than ten minutes can be achieved. Regular drills
and workshops regarding quick changeover should be
arranged and every worker should be made aware about
how important it is to have a short changeover time.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
44
CONCLUSION
 This was the presentation about the project under the title Lead Time
reduction Value Stream Mapping, the team drew current state maps and
identified the sources of wastes and gave means to eliminate the wastes in
the form of Future State Map. It should be noted that Printech Packages
needs to bring basic stability in their processes before they can run on the
road to Lean.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
45
RECOMMENDATIONS
The detailed recommendations have been given in future state map and now
they are being listed again below.
 Standardized Working:
every job must be documented and all the work elements be defined and
documented. Standard operating procedures be developed and followed.
 A Proper Forecasting Method:
A proper forecasting method is recommended for printech packages. On
numerous occasions it was observed that the production had to be stopped
because of unavailability of one or two materials.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
46
RECOMMENDATIONS(CONTD.)
 A feasibility of Cellular Manufacturing:
There is a feasibility of a cellular type manufacturing layout in the printech facility,
with every job passing through almost the same machines and steps , the condition
is ideally suited for a cellular manufacturing system, they have space, they have
machines and they are willing to bring the change. A try should be given to cellular
manufacturing system as well.
 Measuring in the right unit:
All the measurements of outputs of all machines should be taken in meters or in
meter2 because this is how the true output of the machine may be found out. Also
right type of equipment should be used to measure the quantity of inks being
poured into the trays, this measurement should be in litres and not in kilograms
(which is operating practice at printech). This right measurement and accurate
record will help making decisions in future and a better understanding of
profitability will be developed among the personnel concerned
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
47
RECOMMENDATIONS(CONTD.)
 Adoption of SAP ERP application.
This adoption can help overcome scheduling problems and will eliminate situations
where no production is run or the inventory is out of stock. This type of application
can also act as a database management application which is very necessary at
Printech packages. An accurate record is what acts as information in a decision
making process.
 Health, Safety &Environment:
Due care should be given to consideration of a proper HSE method to ensure the
maintenance of health of operators. All the chemicals and all the fumes produces
during the printing should be dealt accordingly. Masks and gloves should be used
when working in the print department. Fire safety system were observed but the
exhaustion of fumes was not satisfactory. A better system of exhausting fumes is
recommended.
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
48
RECOMMENDATIONS(CONTD.)
 Future State Map:
In addition with these guidelines, recommendations given in the Future State
Map should also be followed. If implemented properly, these steps will result
into a better, adaptive, agile, productive and profitable company
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
49
THANKS A LOT FOR YOUR
KIND PRESENCE
2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI
50

Contenu connexe

Tendances

DFMA -Design For Manufacturing and Assembly
DFMA -Design For Manufacturing and AssemblyDFMA -Design For Manufacturing and Assembly
DFMA -Design For Manufacturing and AssemblySunith Guraddi
 
Seven wastes of lean operations management
Seven wastes of lean operations managementSeven wastes of lean operations management
Seven wastes of lean operations managementHriday Bora
 
Jidoka PowerPoint Presentation Slides
Jidoka PowerPoint Presentation SlidesJidoka PowerPoint Presentation Slides
Jidoka PowerPoint Presentation SlidesSlideTeam
 
Toyota production system
Toyota production systemToyota production system
Toyota production systemAkshay Jain
 
Lean Strategy Implementation Methodology.
Lean Strategy Implementation Methodology.Lean Strategy Implementation Methodology.
Lean Strategy Implementation Methodology.Yadhu Gopinath
 
Report on Solution for reduction of cycle time in the manufacturing of Al Wheels
Report on Solution for reduction of cycle time in the manufacturing of Al WheelsReport on Solution for reduction of cycle time in the manufacturing of Al Wheels
Report on Solution for reduction of cycle time in the manufacturing of Al WheelsLAVA KUMAR ADDEPALLI
 
Toyota Production System
Toyota Production SystemToyota Production System
Toyota Production SystemGurpreet Singh
 
Toyota Production System
 Toyota Production System Toyota Production System
Toyota Production SystemAmol Shah
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTFASI93
 
Applying lean thinking in the food supply chain presentation
Applying lean thinking in the food supply chain presentationApplying lean thinking in the food supply chain presentation
Applying lean thinking in the food supply chain presentationFayssal AL-KILANI
 
Lean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation SampleLean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation SampleAndrew Schwartz
 
Lean manufacturing in automobile industry
Lean manufacturing in automobile industryLean manufacturing in automobile industry
Lean manufacturing in automobile industryMAX GALARZA HERNANDEZ
 
Lean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training ModuleLean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training ModuleFrank-G. Adler
 
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSMSedhuSiddarth
 

Tendances (20)

LEAN MANUFACTURING USES
LEAN MANUFACTURING USESLEAN MANUFACTURING USES
LEAN MANUFACTURING USES
 
DFMA -Design For Manufacturing and Assembly
DFMA -Design For Manufacturing and AssemblyDFMA -Design For Manufacturing and Assembly
DFMA -Design For Manufacturing and Assembly
 
Seven wastes of lean operations management
Seven wastes of lean operations managementSeven wastes of lean operations management
Seven wastes of lean operations management
 
Lean Manufacturing Training
Lean Manufacturing TrainingLean Manufacturing Training
Lean Manufacturing Training
 
Jidoka PowerPoint Presentation Slides
Jidoka PowerPoint Presentation SlidesJidoka PowerPoint Presentation Slides
Jidoka PowerPoint Presentation Slides
 
Toyota production system
Toyota production systemToyota production system
Toyota production system
 
Lean Strategy Implementation Methodology.
Lean Strategy Implementation Methodology.Lean Strategy Implementation Methodology.
Lean Strategy Implementation Methodology.
 
Toyota production system
Toyota production systemToyota production system
Toyota production system
 
Report on Solution for reduction of cycle time in the manufacturing of Al Wheels
Report on Solution for reduction of cycle time in the manufacturing of Al WheelsReport on Solution for reduction of cycle time in the manufacturing of Al Wheels
Report on Solution for reduction of cycle time in the manufacturing of Al Wheels
 
Toyota Production System
Toyota Production SystemToyota Production System
Toyota Production System
 
Qc story
Qc storyQc story
Qc story
 
Toyota Production System
 Toyota Production System Toyota Production System
Toyota Production System
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPT
 
Applying lean thinking in the food supply chain presentation
Applying lean thinking in the food supply chain presentationApplying lean thinking in the food supply chain presentation
Applying lean thinking in the food supply chain presentation
 
Lean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation SampleLean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation Sample
 
Toyota production system
Toyota production systemToyota production system
Toyota production system
 
Lean Manufacturing
Lean ManufacturingLean Manufacturing
Lean Manufacturing
 
Lean manufacturing in automobile industry
Lean manufacturing in automobile industryLean manufacturing in automobile industry
Lean manufacturing in automobile industry
 
Lean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training ModuleLean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training Module
 
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
 

Similaire à Final year project report on Value stream mapping and Smed

IRJET- Design of Spoon Mold using Flow Analysis and Higher End Design Software
IRJET- Design of Spoon Mold using Flow Analysis and Higher End Design SoftwareIRJET- Design of Spoon Mold using Flow Analysis and Higher End Design Software
IRJET- Design of Spoon Mold using Flow Analysis and Higher End Design SoftwareIRJET Journal
 
Additive manufacturing 3D Printing technology
Additive manufacturing 3D Printing technologyAdditive manufacturing 3D Printing technology
Additive manufacturing 3D Printing technologySTAY CURIOUS
 
3d printer project report
3d printer project report3d printer project report
3d printer project reportsubhashis das
 
Enhancing PLA Material Performance in FDM 3D Printing: Investigating Tensile ...
Enhancing PLA Material Performance in FDM 3D Printing: Investigating Tensile ...Enhancing PLA Material Performance in FDM 3D Printing: Investigating Tensile ...
Enhancing PLA Material Performance in FDM 3D Printing: Investigating Tensile ...IRJET Journal
 
project presentation 2.pptx
project presentation 2.pptxproject presentation 2.pptx
project presentation 2.pptxGooglyRocky
 
Rapid injection moulding
Rapid injection mouldingRapid injection moulding
Rapid injection mouldinganil mangalan
 
Additive Manufacturing Impact on Supply Chain and Production Scheduling
Additive Manufacturing Impact on Supply Chain and Production SchedulingAdditive Manufacturing Impact on Supply Chain and Production Scheduling
Additive Manufacturing Impact on Supply Chain and Production SchedulingVarun Patel
 
applicationof vsm
applicationof vsmapplicationof vsm
applicationof vsmAro Ephrem
 
Additive manufacturing in the automotive industry
 Additive manufacturing in the automotive industry Additive manufacturing in the automotive industry
Additive manufacturing in the automotive industryRahulkhandelwal120
 
Design and Developing of Two Wheeler Handle Gripper Using 3D Printing Technology
Design and Developing of Two Wheeler Handle Gripper Using 3D Printing TechnologyDesign and Developing of Two Wheeler Handle Gripper Using 3D Printing Technology
Design and Developing of Two Wheeler Handle Gripper Using 3D Printing Technologyijtsrd
 
RAPID PROTOTYPING(RPT)
RAPID PROTOTYPING(RPT)RAPID PROTOTYPING(RPT)
RAPID PROTOTYPING(RPT)Manoj Gowda K
 
A Design and Analysis of Two Plate Injection Mould Tool For Wi-Fi RouterTherm...
A Design and Analysis of Two Plate Injection Mould Tool For Wi-Fi RouterTherm...A Design and Analysis of Two Plate Injection Mould Tool For Wi-Fi RouterTherm...
A Design and Analysis of Two Plate Injection Mould Tool For Wi-Fi RouterTherm...EditorJST
 
thesis-presentation (1)
thesis-presentation (1)thesis-presentation (1)
thesis-presentation (1)Asim Aslam
 
Printing the Future: From Prototype to Production
Printing the Future: From Prototype to ProductionPrinting the Future: From Prototype to Production
Printing the Future: From Prototype to ProductionCognizant
 
MIM04_Lean Product Design of Complex Products_Doubravka Vodárková_591551
MIM04_Lean Product Design of Complex Products_Doubravka Vodárková_591551MIM04_Lean Product Design of Complex Products_Doubravka Vodárková_591551
MIM04_Lean Product Design of Complex Products_Doubravka Vodárková_591551Doubravka Vodárková
 

Similaire à Final year project report on Value stream mapping and Smed (20)

IRJET- Design of Spoon Mold using Flow Analysis and Higher End Design Software
IRJET- Design of Spoon Mold using Flow Analysis and Higher End Design SoftwareIRJET- Design of Spoon Mold using Flow Analysis and Higher End Design Software
IRJET- Design of Spoon Mold using Flow Analysis and Higher End Design Software
 
paper-presentation
paper-presentationpaper-presentation
paper-presentation
 
Additive manufacturing 3D Printing technology
Additive manufacturing 3D Printing technologyAdditive manufacturing 3D Printing technology
Additive manufacturing 3D Printing technology
 
3d printer project report
3d printer project report3d printer project report
3d printer project report
 
Enhancing PLA Material Performance in FDM 3D Printing: Investigating Tensile ...
Enhancing PLA Material Performance in FDM 3D Printing: Investigating Tensile ...Enhancing PLA Material Performance in FDM 3D Printing: Investigating Tensile ...
Enhancing PLA Material Performance in FDM 3D Printing: Investigating Tensile ...
 
project presentation 2.pptx
project presentation 2.pptxproject presentation 2.pptx
project presentation 2.pptx
 
Rapid injection moulding
Rapid injection mouldingRapid injection moulding
Rapid injection moulding
 
Additive Manufacturing Impact on Supply Chain and Production Scheduling
Additive Manufacturing Impact on Supply Chain and Production SchedulingAdditive Manufacturing Impact on Supply Chain and Production Scheduling
Additive Manufacturing Impact on Supply Chain and Production Scheduling
 
applicationof vsm
applicationof vsmapplicationof vsm
applicationof vsm
 
3 d printing revised
3 d printing revised3 d printing revised
3 d printing revised
 
Advantages of 3D Printing
Advantages of 3D PrintingAdvantages of 3D Printing
Advantages of 3D Printing
 
Additive manufacturing in the automotive industry
 Additive manufacturing in the automotive industry Additive manufacturing in the automotive industry
Additive manufacturing in the automotive industry
 
Additive Manufacturing or 3D Printing Presentation
Additive Manufacturing or 3D Printing PresentationAdditive Manufacturing or 3D Printing Presentation
Additive Manufacturing or 3D Printing Presentation
 
Design and Developing of Two Wheeler Handle Gripper Using 3D Printing Technology
Design and Developing of Two Wheeler Handle Gripper Using 3D Printing TechnologyDesign and Developing of Two Wheeler Handle Gripper Using 3D Printing Technology
Design and Developing of Two Wheeler Handle Gripper Using 3D Printing Technology
 
THURMER 27 IDA notes
THURMER 27 IDA notesTHURMER 27 IDA notes
THURMER 27 IDA notes
 
RAPID PROTOTYPING(RPT)
RAPID PROTOTYPING(RPT)RAPID PROTOTYPING(RPT)
RAPID PROTOTYPING(RPT)
 
A Design and Analysis of Two Plate Injection Mould Tool For Wi-Fi RouterTherm...
A Design and Analysis of Two Plate Injection Mould Tool For Wi-Fi RouterTherm...A Design and Analysis of Two Plate Injection Mould Tool For Wi-Fi RouterTherm...
A Design and Analysis of Two Plate Injection Mould Tool For Wi-Fi RouterTherm...
 
thesis-presentation (1)
thesis-presentation (1)thesis-presentation (1)
thesis-presentation (1)
 
Printing the Future: From Prototype to Production
Printing the Future: From Prototype to ProductionPrinting the Future: From Prototype to Production
Printing the Future: From Prototype to Production
 
MIM04_Lean Product Design of Complex Products_Doubravka Vodárková_591551
MIM04_Lean Product Design of Complex Products_Doubravka Vodárková_591551MIM04_Lean Product Design of Complex Products_Doubravka Vodárková_591551
MIM04_Lean Product Design of Complex Products_Doubravka Vodárková_591551
 

Dernier

MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 

Dernier (20)

MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 

Final year project report on Value stream mapping and Smed

  • 1. LEAD TIME REDUCTION VIA VALUE STREAM MAPPING FINAL YEAR PROJECT IN PARTIAL FULFILMENT OF REQUIREMENT FOR DEGREE OF INDUSTRIAL ENGINEERING AND MANAGEMENT
  • 2. PROJECT TEAM STUDENTS  UMAR YAZDANI D 11 IN 05  AFSAAR ALI D 11 IN 27  MALIKAH IBRAHIM D 11 IN 41  MUHAMMAD HANIF D 11 IN 39  ZULFIQAR ALI D 11 IN 37 SUPERVISOR  ENGR. SHAHAB AFROZE 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 2
  • 3. PROJECT OBJECTIVES The primary objective of the project was to reduce the production lead time, for this purpose the team selected lean manufacturing tool Value Stream Mapping. In addition to reduction of lead time, following benefits were expected after the completion of the project.  Improved productivity  Determination of Value stream  Better understanding of Wastes and their causes  A roadmap towards an efficient, lean production line 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 3
  • 4. PROJECT METHODOLOGY 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 4 Data Collection Drawing Current State Map Muda Identification Future State Map Recommend ations
  • 5. COMPANY PROFILE The Printech Packages was established in 2010 in SITE area. Printech currently provides services for printing substrates for FMCG companies such as candy land, Mayfair, Danpak, Pakistan beverages etc. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 5
  • 6. STATE-OF-THE-ART EQUIPMENT PTP is well equipped with some of the latest machines available in the market today. The infrastructure comprises:  Rotogravure printing machine 8colours  Rotogravure printing machine 7colours  Dry lamination  solvent less lamination machine  High end converting equipment like slitting, seaming, cutting, pouching, bag making 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 6
  • 7. GRAVURE PRINTING DEFINITION Gravure Printing or rotogravure printing is a printing process which is used to produce very high quality printing on flexible mediums such as films sheets made up of materials like aluminum foil etc. The layout of a gravure printing press follows an in-line arrangement where the required number of printing units is installed along a horizontal plane. In a conventional gravure printing press, each unit comprises of: Printing cylinder: a seamless tubular sleeve or full cylinder, made from either steel, aluminum, plastic, or composite material, which is engraved with the image to be printed. Doctor blade: the device that removes ink from the non-engraved portions of the printing cylinder and also removes excess ink from the engraved sections 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 7
  • 8. GRAVURE PRINTING (CONTD.) Impression roller: (called rubber roller in Printech) a rubber covered sleeve that is mounted on a steel mandrel. Its primary purpose is to press the substrate against the printing cylinder Inking system: Typically consisting of an ink pan, ink holding tank, and ink pump with supply and return ink pipes. Drying system: consisting of a chamber which dries the ink once it is on the substrate and prior to it reaching the next printing unit. Drier capacities are determined based on the required printing speed, ink type (solvent or water based), and ink lay down volume, normally a shaft containing hot water was used for this purpose in Printech. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 8
  • 9. GRAVURE PRINTING PROCESS DESCRIPTION During the gravure printing process, the engraved cylinder on which the pattern to be printed has already been engraved (via an outside vendor) rotates and sinks in the ink fountain , cells are filled with the ink, as the cylinder rotates clear off the fountain the doctor blade removes all the excess ink on the cylinder. Further around, the cylinder is brought into contact with the substrate, which is pressed against it by the rubber covered impression roller (rubber roller). The pressure of rubber roller along with capillary draw of the substrate results into the impression on the substrate and as the cylinder rotates back into the ink fountain the substrate goes through the drying unit and then the substrate passes on to the next unit which is mostly another color ink or a varnish, in Printech the team observed as many as 8 color units In Printech after printing of all colors the substrate are rewound into a finished roll. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 9
  • 10. PROJECT BACKGROUND A shorter lead time results into better utilization of manufacturing resources, quick adaptation to customer’s demand, reduced cost and better products. Today companies are intensively indulging in activities to reduce their production lead times. The project team, keeping in mind, the importance of a short lead time, worked in Printech Packages with the intention to reduce Production Lead time. Technique that the team adopted was Value Stream Mapping 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 10
  • 11. VALUE STREAM MAPPING Value stream mapping is a relatively new concept in Lean, it is not as old and renowned as JIT or Kaizen but it is no way less in proving to be effective than other tools. This tool at Toyota Japan was called material and information flow. It was given its present name by Mike Rother and John Shook in their book Learning to see. Value stream mapping refers to process of tracing the value stream of a product which it goes through from start to end. And ultimately differentiating between value added and non value added activities. A great thing about VSM is that it also helps to identify sources of wastes which other tools don’t. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 11
  • 12. VALUE STREAM CYCLE 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 12
  • 13. DATA COLLECTION AT PRINTECH VSM is ideally suited to high production low variety production facilities. Unfortunately it was not the case in the printech packages. Every job was different and due to lack of standardization, the work and it’s time were unpredictable. The team chose 3 of Printech's most in demand products and worked on them. The results drawn from these 3 products will act as a model for other products. Those jobs were;  Chini Mini Chini mini is a product of Danpak food industries. Its packing is printed at Printech Packages. The printing substrate is BOPP of 20 microns and the lamination substrate is W.CPP of 50 microns. It is reverse printed therefore it needs to be re-winded before lamination. It is one of the most in demand job of Printech Packages. The team selected this job due to its large production. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 13
  • 14. DATA COLLECTION(CONTD.)  Chili Milli Chili Milli Jelly is a confectionary product of Candy Land. Its packaging is printed at Printech Packages. The printing substrate is PET of 12 microns while the lamination substrate is CPP of 30 microns.it is also reverse printed therefore it is also needed to be re-winded before going for Lamination. This job also comprises of large production volumes at Printech Packages.  Bunta Chocolate Bunta chocolate is a product of Danpak food industries. Its packaging is printed at printech packages. The printing substrate is M.PET. Like above two products it is also one of the most in demand job of Printech. Like other food items it is reverse printed therefore it is also needed to be rewinded. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 14
  • 15. CRITICAL INPUTS FOR VALUE STREAM MAPPING The following data are considered to be important in a value stream mapping project.  Cycle Time  Changeover Time  Machine Uptime  # of Operators  Queue Size 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 15
  • 16. DATA TABLE FOR PRINTING DEPARTMENT The team collected following data on production floor of Printech Packages. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 16 Observation no. 1 2 3 4 5 Printing film material used BOPP PET PET PET PET Thickness of the film (In microns) 20 18 12 12 12 Colors used 8 3 7 5 7 Length of substrate 61057 m 61057 m 19228 m 34880 m 31134 m Area of substrate 42740 𝑚2 51593 𝑚2 9748 𝑚2 3000 𝑚2 26775 𝑚2 Time taken 360 min 540 min 90 min 300 min 240 min Weight inserted 800 kg 1813 kg 202 kg 508 kg 457 kg Weight obtained 810 kg 2037 kg 213 kg 509 kg 510 kg Machine output 170m/min 113m/min 213m/min 116m/min 130m/min
  • 17. DATA TABLE FOR DRY LAMINATION MACHINE Observation no. 1 2 3 4 5 Printing film material used PET PET PET PET PET Thickness of the film (In microns) 12 12 12 12 12 Lamination Film Material ALUMINUM FOIL M.CPP PE M.PET PE.WHITE Length of substrate 21179 49603 2538 8231 10426 Thickness of Lamination film 52 microns 25 microns 55 microns 12 microns 60 microns Area of substrate 13766 𝑚2 25297 𝑚2 1522 𝑚2 6584 𝑚2 7037 𝑚2 Time taken 65 min 640 min 40 min 100 min 140 min Weight inserted Print + Lamination 250+255 kg 459+597 kg 35+83 kg 130+114 kg 125+410 kg Machine output 325m/min 77m/min 63m/min 82m/min 74m/min 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 17
  • 18. Data Sheet for Solvent less Lamination: Observation no. 1 2 3 4 5 Printing film material used BOPP BOPP PET PET BOPP Thickness of the film (In microns) 20 20 12 12 15 Lamination Film Material M.BOPP M.BOPP M.CPP PE.WHITE BOPP Length of substrate 26890 25250 34367 21275 51559 Thickness of Lamination film 20 microns 20 microns 25 microns 40 microns 30 microns Area of substrate 24739 𝑚2 23230 𝑚2 25260 𝑚2 17020 𝑚2 37895 𝑚2 Time taken 180 min 170 min 180 min 90 min 300 min Weight inserted Print + Lamination 500+500 kg 500+500kg 461+592kg 300+663kg 549+839kg Machine output 150m/min 148m/min 190m/min 236m/min 171m/min 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 18
  • 19. RESULTS OF DATA TABLES Following conclusions were drawn from the data tables of different departments.  Processes are highly unstable  Results are unpredictable  Work is not standardized 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 19
  • 20. 1ST CURRENT STATE MAP 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 20
  • 21. FINDINGS OF 1ST CURRENT STATE MAP 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 21  PRODUCTION LEAD TIME: 3.5 DAYS  VALUE ADDED TIME: 28 HOURS Non Value Added Time 67% Value added time 33% Time Non Value Added Time Value added time
  • 22. 2ND CURRENT STATE MAP 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 22
  • 23. FINDINGS OF 2ND CURRENT STATE MAP  PRODUCTION LEAD TIME: 7 DAYS  VALUE ADDED TIME: 48 HOURS 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 23 Non Value Added Time 71% Value added time 29% Time Non Value Added Time Value added time
  • 24. 3RD CURRENT STATE MAP 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 24
  • 25. FINDINGS OF 3RD CURRENT STATE MAP 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 25  PRODUCTION LEAD TIME: 8.5 DAYS  VALUE ADDED TIME: 52 HOURS Non Value Added Time 75% Value added time 25% Time Non Value Added Time Value added time
  • 26. MAJOR SOURCES OF MUDA I.E. WASTES AND NON VALUE ADDED ACTIVITIES The major wastes which team found with the help of current state map are as follows;  Defects were not found on the production floor.  Overproduction was not an issue either, on the contrary, underproduction was an issue at the printech packages, the team witnessed many situations when production was done less than the required quantity due to various factors such as shortage of substrate, inks or other materials, or due to gas load shedding.  Transportation, the 3rd waste identified in Lean philosophy was also present at the printech packages, persons pulling, loading and unloading is a common sight at printech packages, the company consists of 8 floors and it results into a very inefficient system of material handling. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 26
  • 27. MUDA IN CURRENT STATE MAPS(CONTD.)  Waiting, the 4th waste identified in lean methodology was also present at printech packages, but this waiting was in form of starvation i.e. machines were waiting for feeds from previous in-line machines and as a result accumulating wastes.  Inventory waste was also accumulated in printech packages as finished products were kept for longer periods of time without any reason and there were also cases of under inventory when the company ran out of stocks and production had to be stopped.  Motion waste was also present at the printech, it is ironic to suggest it as a waste because there was such lack of standardization that motion elimination could not be done immediately. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 27
  • 28. FUTURE STATE MAP The team addressed all the problems discussed in the previous sections. A future state map was drawn after some brainstorming sessions. Note: only one future state map was drawn, unlike current state maps, where there were separate current state maps for each product. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 28
  • 29. FUTURE STATE MAP 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 29
  • 30. CHANGES PROPOSED IN FUTURE STATE MAPS The kaizen bursts on a future state map represent kaizen opportunities which ,if implemented, will result into an overall improvement of the system. The team placed 6 kaizen bursts on the future state map. Following will be a description of all those kaizen bursts. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 30
  • 31. KAIZEN BURSTS  1ST KAIZEN BURST(FORECASTING) The first kaizen burst placed on the FSM was forecasting. There is no forecasting done in printech, as a result there are incidents where order is not met. A proper forecasting method should be adopted.  2ND KAIZEN BURST(RELOCATION OF THE ELEVATOR) The 2nd kaizen burst suggests relocation of the elevator, which is currently outside the production hall, it should ne relocated into production hall, it will not only save the time but will also eliminate the need of a human operator.  3RD KAIZEN BURST(SMED) Quick changeover techniques should be practiced in all the departments of printech i.e. printing, lamination, rewinding etc. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 31
  • 32. KAIZEN BURSTS(CONTD.)  4TH KAIZEN BURST(Operator Sharing) There is a huge difference between cycle times of printing and rewinding and also lamination and slitting, which can result into inventory piling up at those station. To avoid this situation, the team recommends a sharing of workers between printing and rewinding and slitting and packing. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 32
  • 33. OTHER IMPROVEMENTS IN FUTURE STATE MAP SUPERMARKET System at the Stores Department: A supermarket symbol is inserted beside the store department it suggests a setup in which the relevant departments can draw whatever they need and in whichever quantity. The kanban signaling system shows that production department will be alerted when supermarket runs low on stocks. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 33
  • 34. OTHER IMPROVEMENTS IN FUTURE STATE MAP FIFO lane between the departments: The team recommends use of a FIFO lane between all the departments The usage of these FIFO lanes will also mean that there will be very little waiting time and very little bottlenecking as well. Material handling will also be improved. It should be kept in mind that production scheduling will only be done at the printing department and it will get its daily schedule from production department and all the other departments will process on the jobs they get from their previous in line departments, this will result into the overall smoothness of the operations. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 34
  • 35. OTHER IMPROVEMENTS IN FUTURE STATE MAP  Supermarket system after Packing: The team proposes a supermarket system at the packing end as well. All the finished and packed substrate would go to the supermarket where they will be retrieved and shipped accordingly. This system will ensure a smooth dispatching of finished goods materials. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 35
  • 36. RESULTS OF FUTURE STATE MAP  The data for the designing of future state map was taken from the 3rd current state map, here is a comparison of the two maps i.e. current state and future state maps. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 36 210 52 158 115 49 66 PRODUCTION LEAD TIME VALUE ADDED TIME NON VALUE ADDED TIME COMPARISON OF CSM & FSM CURRENT STATE MAP FUTURE STATE MAP
  • 37. TIME REDUCTION TABLE ACTIVITY PREVIOUS TIME NEW TIME REASON CHANGEOVER IN PRINT DEPARTMENT 1-3 HOURS 30 MIN SMED WAITING BEFORE REWINDING 2 HOURS 10 MIN PROPER SCHEDULING WAITING BEFORE LAMINATION 4 DAYS 2 DAYS PROPER SCHEDULING LAMINATION CHANGEOVER 1 HOUR 30 MIN SMED WAITING BEFORE PACKING 2 DAYS 1 HOUR PROPER SCHEDULING 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 37
  • 38. DOWNTIME REPORT OF PRINTING MACHINES  THE TEAM ALSO COLLECTED SOME DATA REGARDING DOWNTIMES OF PRINTING MACHINES. THE RESULT IS AS UNDER. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 38 Changeover, 2145, 58% Power failure, 750, 20% No Production Plan, 615, 17% Technical Issues, 180, 5% Downtimes Changeover Power failure No Production Plan Technical Issues
  • 39. DOWNTIMES  It is evident from the previous cart that major cause of downtime of printing machines is “long changeover process”. 55% of the total down time in 15 days, was due to changeover, followed by power crisis and no production plan with 20% and 17% respectively.  These long changeovers made printech a strong candidate for adoption of SMED. The team gave detailed recommendation regarding SMED in printing department. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 39
  • 40. SINGLE MINUTE EXCHANGE OF DIES  Step 1: Creating the SMED Team:  Step 2: Select the Equipment:  Step 3: Document Every Step of the Changeover:  Step 4: Define the Target Time for the Changeover  Step 5: Differentiate between Internal and External Steps:  Step 6: Convert Internal Elements to External  Step 7: Streamline Remaining Elements:  Step 8: Implement the new method and check for results: 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 40
  • 41. CHANGEOVER PROCESS AT PRINTING DEPARTMENT OF PRINTECH PACKAGES Steps involved in Changeover  Winding of the substrate. Mounting rubber rollers.  Emptying color tray. Mounting dr. blade.  Washing color tray. Running the test run  Dismounting the rubber rollers  Cleaning the rubber rollers.  Removing dr. blade.  Bringing rubber roller, cylinder and inks on the site.  Pouring the inks  Mounting the substrate roll.  Mixing different inks and solvents. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 41
  • 42. PROPOSED CHANGEOVER METHOD  Washing color tray.  Cleaning the rubber rollers.  Bringing rubber roller, cylinder and inks on the site.  Mixing different Inks and solvents (these are external steps which should be performed before stopping the machine for changeover)  Winding of the substrate.  Emptying color tray.  dismounting the rubber rollers 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 42
  • 43. PROPOSED CHANGEOVER(CONTD.)  Removing dr. blade  Pouring the inks  Mounting the substrate roll  Mounting rubber rollers.  Mounting dr. blade. (Internal setup activities that should be performed as quickly as possible, during this the machine is stopped)  Running the test run 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 43
  • 44. BENEFITS EXPECTED OF THE NEW CHANGEOVER If the above stated sequence is followed and the continuous efforts are made to reduce the changeover times, the ultimate goal of changing over in single minute i.e. less than ten minutes can be achieved. Regular drills and workshops regarding quick changeover should be arranged and every worker should be made aware about how important it is to have a short changeover time. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 44
  • 45. CONCLUSION  This was the presentation about the project under the title Lead Time reduction Value Stream Mapping, the team drew current state maps and identified the sources of wastes and gave means to eliminate the wastes in the form of Future State Map. It should be noted that Printech Packages needs to bring basic stability in their processes before they can run on the road to Lean. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 45
  • 46. RECOMMENDATIONS The detailed recommendations have been given in future state map and now they are being listed again below.  Standardized Working: every job must be documented and all the work elements be defined and documented. Standard operating procedures be developed and followed.  A Proper Forecasting Method: A proper forecasting method is recommended for printech packages. On numerous occasions it was observed that the production had to be stopped because of unavailability of one or two materials. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 46
  • 47. RECOMMENDATIONS(CONTD.)  A feasibility of Cellular Manufacturing: There is a feasibility of a cellular type manufacturing layout in the printech facility, with every job passing through almost the same machines and steps , the condition is ideally suited for a cellular manufacturing system, they have space, they have machines and they are willing to bring the change. A try should be given to cellular manufacturing system as well.  Measuring in the right unit: All the measurements of outputs of all machines should be taken in meters or in meter2 because this is how the true output of the machine may be found out. Also right type of equipment should be used to measure the quantity of inks being poured into the trays, this measurement should be in litres and not in kilograms (which is operating practice at printech). This right measurement and accurate record will help making decisions in future and a better understanding of profitability will be developed among the personnel concerned 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 47
  • 48. RECOMMENDATIONS(CONTD.)  Adoption of SAP ERP application. This adoption can help overcome scheduling problems and will eliminate situations where no production is run or the inventory is out of stock. This type of application can also act as a database management application which is very necessary at Printech packages. An accurate record is what acts as information in a decision making process.  Health, Safety &Environment: Due care should be given to consideration of a proper HSE method to ensure the maintenance of health of operators. All the chemicals and all the fumes produces during the printing should be dealt accordingly. Masks and gloves should be used when working in the print department. Fire safety system were observed but the exhaustion of fumes was not satisfactory. A better system of exhausting fumes is recommended. 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 48
  • 49. RECOMMENDATIONS(CONTD.)  Future State Map: In addition with these guidelines, recommendations given in the Future State Map should also be followed. If implemented properly, these steps will result into a better, adaptive, agile, productive and profitable company 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 49
  • 50. THANKS A LOT FOR YOUR KIND PRESENCE 2/16/2015DAWOOD UNIVERSITY OF ENGINEERING AND TECHNOLOGY, KARACHI 50