I N T R O D U C T I O N
Doubling of railway line means construction of an additional line. It is
normally done when single line is not in a position to carry the number of
trains required to pass on the section.
The doubling of Utraitia - Sultanpur-Zafrabad project is for diverting
freight traffic from Mughalsarai - Allahabad - New Delhi route so as to
provide room for additional coaching traffic to be introduced in near
future .
The patch doubling from Zafrabad to Shri Krishna Nagar (34 kms),
Sultanpur to Bandhuakalan (09 kms) & Utraitia to Chandraulli (37
kms) has been completed. The balance 148 km stretch is with single
railway track that need to be double.
Specific section of 10 kms length between Shivnagar and Bandhuakalan has
been selected for the project.
OBJECTIVE
To eradicate
mounting pressure
of rail traffic.
To get the
optimum benefit
from the modern
maintenance
machines.
To cope up with
the additional
requirement to
traffic. The need to divert
rail traffic from
one route to
another due to
accident /mishap,
or any other
unforeseen reason.
To reduce initial
costs of a line that
is certain to see
heavy traffic in the
future, a line may
be built as single-
track .
M E T H O D O L O G Y
SITE &
TRAFFIC
SURVEY
COLLECTION
OF SAMPLES
SPECIFICATION
& DATA
COLLECTION
FROM
RAILWAY
OFFICE
ANALYSING
DATA &
SAMPLES
ESTIMATION
OF
EARTHWORK
L O C A T I O N
Bandhuakalan -
Shivnagar Section (12.5
km)
LUCKNOW
UTRAITIA
BAKKAS
ANUPGANJ
RAHMATNAGAR
CHANDRAULLI
TRIVEDIGANJ
HAIDERGARGH
CHAUBISI
AKBARGANJ
SINDHURWA
NIHALGARH
ADHINPUR
MUSAFIRKHANA
SHIVNAGAR
BANDHUAKALAN
SULTANPUR
HARPALGANJ
JAUNPUR
ZAFRABAD
P R O C E S S O F D O U B L I N G
Engineering
cum Traffic
Survey
Specification
of work
Land
acquisition
EarthworkBridgesPlate laying
Opening for
goods traffic
&ballasting
Opening line
for passenger
traffic
ENGI NEERI NG CUM TRAFFI C SURVEY
T RAF F I C SURV EY DETAI L S
Timings of the train (Hourly
basis)
No. of trains passing
SHIVNAGAR
No. of trains passing
BANDHUAKALAN
BEFORE AFTER BEFORE AFTER
03:00-04:00 0 0 0 0
05:00-06:00 0 2 0 2
06:00-07:00 1 1 2 2
07:00-08:00 1 1 0 0
08:00-09:00 1 4 1 5
10:00-11:00 0 0 0 0
11:00-12:00 0 0 0 2
12:00-13:00 1 1 0 0
13:00-14:00 0 2 0 3
14:00-15:00 0 2 0 1
15:00-16:00 0 2 0 1
16:00-17:00 0 2 0 1
17:00-18:00 0 0 0 2
18:00-19:00 0 3 0 0
19:00-20:00 2 2 2 2
20:00-21:00 0 0 0 0
21:00-22:00 1 1 1 1
23:00-00:00 0 0 0 0
TOTAL 7 23 6 22
SPECIFICATION OF WORK
Rail and fastenings
• The permanent way consists of 60 kg (UIC), 90 UTS rails welded into LWR (By
FB(Flush butt welding)/AT(Alumino-Thermit welding) welding with SKV
process) over main line. Loop lines, consist 60 Kg 90 UTS SH rails welded into
LWR (By AT welding with SKV process).
Fish Plates
• 1 M Long new fish plates with six holes of standard type to suit 60
kg rails have been used.
Sleepers and fastenings
• MAIN LINE: PRC sleepers complete with elastic fastenings to M+ 8 (1660 no.
per Km) densities have been used.
• LOOP LINE: PRC sleepers complete with elastic fastenings to M+ 7 (1540 no.
per Km) densities have been used.
Guard Rails
Guard rails of 52 Kg rails resting on PSC sleepers have been provided on all major
bridges.
Points and Crossings
All turn out to be negotiated by passenger trains are of 1 in 12 with curved
switches except turn outs laid for sand humps which are of 1 in 8-1/2 laid on
symmetrical split.
60 kg trap points on PSC sleepers have been provided wherever required for the
purpose of isolation in new line.
Ballast
65mm gauge hard stone Machine Crushed ballast with cushion of 350mm on main
line and 250 mm on loop line below the sleeper has been provided under the track
and turn outs with boxing. The newly laid track and turn outs have been thoroughly
packed manually and machine packing will be done before commissioning
SPECIFICATION OF WORK
EARTHWORK AND FORMATION
CROSS SECTION PROFILE
QUANTITY ESTIMATE
BLANKETING MATERIAL
SOIL1.4 m
0.6 m
5.3 m
Existing track
Proposed
double line
Subgrade = 74200 Cubic Meter
Blanketing Material = 10600 Cubic Meter
Ballast = 2800 Cubic Meter
Sleeper =16600 Nos.
BRIDGES
48 No. of Bridges
Provided for 25 T loading
1 major bridge & 47 minor
bridges.
Provided as extension of
bridges on existing track
LEVEL CROSSINGS
Total 15 level
Crossings
8 Manned Level
Crossings
7 Unmanned Level
Crossings
L I S T O F L E V E L C R O S S I N G S
SN Level X-ing No. Manned / Unmanned Interlocked/
Non interlocked
Remark
1 82/C Manned Interlocked Traffic
2 83/C Manned Interlocked Traffic
3 84/C Manned Non-interlocked Engineering
4 85/C Manned Non-interlocked Engineering
5 86/C Manned Non-interlocked Engineering
6 87/C Un- Manned Non-interlocked Engineering
7 88/C Un- Manned Non-interlocked Engineering
8 89/C Un- Manned Non-interlocked Engineering
9 90/C Manned Non-interlocked Engineering
11 91/C Un- Manned Non-interlocked Engineering
12 92/C Un- Manned Non-interlocked Engineering
13 93/C Un- Manned Non-interlocked Engineering
14 94/B Manned Interlocked Traffic
15 95/B Manned Interlocked Traffic
TEST ON AGGREGATE
STONE AGGREGATE TEST
SN Sample No. Abrasion value Impact value Water
absorption
1 1 16.68% 13.75% 0.296%
2 2 15.90% 13.79% 0.347%
3. AVERAGE 16.29% 13.77% 0.321%
4. MAXIMUM
PERMISSIBLE
VALUE
30% 20% 1%
5. WITHIN
PERMISSIBLE
LIMITSOR NOT?
YES YES YES
TEST ON SOI L
TEST ON BURROW SOIL
SN Location of Subgrade
sample
LL PL Dispersive
nature
1 SHIVNAGAR 22.10 6.55 NO
2 BANDHUAKALAN 22.29 6.70 NO
PLATE LAYI NG OR TRACK LI NKI NG
Rails, sleepers and other fittings are taken to the
base depot and unloaded
Tracks materials are taken to the rail head and
track linked and packed
Rail head is advanced up to the extent the track
is laid
Dip lorry is used to take rack material to rail head
Rail head goes on advancing till full track is linked
T E L E S C O P I C M E T H O D
Unloading
of materials
Linking of
track
Packing of
track
Ballasting
of track
O P E N I N G F O R G O O D S T R A F F I C A N D B A L L A S T I N G
C O N C L U S I O N
Simplified
signaling
system.
Bi-
directional
running .
Enhancement
of line capacity
utilization
Section
capacity
showed
significant
increase
Train delay
reduced.
F U T U R E S C O P E
Soil report may be used as a reference for
other civil project near the site of project.
Topographical
survey data
can be used
for similar
projects near
the site for
design of any
other
structure.
The traffic survey cab help in
proper maintenance and future
developments in the concerned
area.
The continuation of this project
will help in understanding the
use of new technologies
employed for this purpose.
A D V A N T A G E
It can
manage a
larger
amount of
traffic with
usually twice
the capacity
of single
track.
Faster trains
can overtake
slower ones,
and doubling
can
contribute to
faster
operation of
trains.
It is easy to
maintenance
and
engineering
work
Provision of
alternate
routes would
reduce
Pressure on
existing
network .
Doubling would
help it earn
more revenue
from the
additional
traffic.
“Railway is a unique integrator of India.
We must restore the strength of
Indian railways as the back bone of India.”
- Mr. Suresh Prabhu
Railway Minister of India
Thanks

Contenu connexe

Tendances

Indian railway final report
Indian railway  final reportIndian railway  final report
Indian railway final reportashwani kumar
 
Aayush_loco report-PNEUMATIC SYSTEMS IN WAG-7
Aayush_loco report-PNEUMATIC SYSTEMS IN WAG-7Aayush_loco report-PNEUMATIC SYSTEMS IN WAG-7
Aayush_loco report-PNEUMATIC SYSTEMS IN WAG-7Aayush Singhal
 
Railway Industrial Training Report
Railway Industrial Training ReportRailway Industrial Training Report
Railway Industrial Training ReportLokesh Parihar
 
Railway carriage workshop Ajmer
Railway carriage workshop AjmerRailway carriage workshop Ajmer
Railway carriage workshop AjmerBhupesh Jangid
 
DIESEL LOCOMOTIVE WORKS VARANASI, Summer Training Report
DIESEL LOCOMOTIVE WORKS VARANASI, Summer Training ReportDIESEL LOCOMOTIVE WORKS VARANASI, Summer Training Report
DIESEL LOCOMOTIVE WORKS VARANASI, Summer Training ReportRahul Kumar
 
Summer Training at Electrical LOCO shed, Ghaziabad
Summer Training at Electrical LOCO shed, GhaziabadSummer Training at Electrical LOCO shed, Ghaziabad
Summer Training at Electrical LOCO shed, GhaziabadVishal Dubey
 
Dlw summer training presentation
Dlw summer training presentationDlw summer training presentation
Dlw summer training presentationVarun Mishra
 
Summer Training Presentation, DLW Varanasi
Summer Training Presentation, DLW VaranasiSummer Training Presentation, DLW Varanasi
Summer Training Presentation, DLW VaranasiSHAILESH SHUKLA
 
Electric Loco Shed, Tughlakabad, New Delhi
Electric Loco Shed, Tughlakabad, New DelhiElectric Loco Shed, Tughlakabad, New Delhi
Electric Loco Shed, Tughlakabad, New DelhiPrabjeet Singh
 
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)Vivek Yadav
 
DLW varanasi summer training report
DLW varanasi summer training reportDLW varanasi summer training report
DLW varanasi summer training reportshubham chaurasiya
 
Promotion aspects in Indian railways along with its organisational set up
Promotion aspects in Indian railways along with its organisational set upPromotion aspects in Indian railways along with its organisational set up
Promotion aspects in Indian railways along with its organisational set upRajesh KUMAR Gupta
 
DLW Varanasi Training report
DLW Varanasi Training reportDLW Varanasi Training report
DLW Varanasi Training reportGyanendra Prakash
 
Dlw trainig report by Sumit Tiwari
Dlw trainig report by Sumit TiwariDlw trainig report by Sumit Tiwari
Dlw trainig report by Sumit TiwariSumitTiwari76
 
CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)
CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)
CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)Vipin Kumar
 
Diesel locomotive works, varanasi
Diesel locomotive works, varanasiDiesel locomotive works, varanasi
Diesel locomotive works, varanasiShubham​ Yadav
 

Tendances (20)

Indian railway final report
Indian railway  final reportIndian railway  final report
Indian railway final report
 
Indian railway turnaround story
Indian railway turnaround storyIndian railway turnaround story
Indian railway turnaround story
 
DLW training PPT
DLW   training  PPTDLW   training  PPT
DLW training PPT
 
Aayush_loco report-PNEUMATIC SYSTEMS IN WAG-7
Aayush_loco report-PNEUMATIC SYSTEMS IN WAG-7Aayush_loco report-PNEUMATIC SYSTEMS IN WAG-7
Aayush_loco report-PNEUMATIC SYSTEMS IN WAG-7
 
Railway Industrial Training Report
Railway Industrial Training ReportRailway Industrial Training Report
Railway Industrial Training Report
 
Railway carriage workshop Ajmer
Railway carriage workshop AjmerRailway carriage workshop Ajmer
Railway carriage workshop Ajmer
 
DIESEL LOCOMOTIVE WORKS VARANASI, Summer Training Report
DIESEL LOCOMOTIVE WORKS VARANASI, Summer Training ReportDIESEL LOCOMOTIVE WORKS VARANASI, Summer Training Report
DIESEL LOCOMOTIVE WORKS VARANASI, Summer Training Report
 
Summer Training at Electrical LOCO shed, Ghaziabad
Summer Training at Electrical LOCO shed, GhaziabadSummer Training at Electrical LOCO shed, Ghaziabad
Summer Training at Electrical LOCO shed, Ghaziabad
 
RDSO Training
RDSO TrainingRDSO Training
RDSO Training
 
Dlw summer training presentation
Dlw summer training presentationDlw summer training presentation
Dlw summer training presentation
 
Summer Training Presentation, DLW Varanasi
Summer Training Presentation, DLW VaranasiSummer Training Presentation, DLW Varanasi
Summer Training Presentation, DLW Varanasi
 
Electric Loco Shed, Tughlakabad, New Delhi
Electric Loco Shed, Tughlakabad, New DelhiElectric Loco Shed, Tughlakabad, New Delhi
Electric Loco Shed, Tughlakabad, New Delhi
 
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)
Summer Training Report,DIESEL LOCOMOTIVE WORKS,VARANASI(DLW)
 
DLW varanasi summer training report
DLW varanasi summer training reportDLW varanasi summer training report
DLW varanasi summer training report
 
Promotion aspects in Indian railways along with its organisational set up
Promotion aspects in Indian railways along with its organisational set upPromotion aspects in Indian railways along with its organisational set up
Promotion aspects in Indian railways along with its organisational set up
 
Railway training ppt
Railway training pptRailway training ppt
Railway training ppt
 
DLW Varanasi Training report
DLW Varanasi Training reportDLW Varanasi Training report
DLW Varanasi Training report
 
Dlw trainig report by Sumit Tiwari
Dlw trainig report by Sumit TiwariDlw trainig report by Sumit Tiwari
Dlw trainig report by Sumit Tiwari
 
CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)
CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)
CONCEPT AND WORKING OF WILD (Wheel Impact Load Detector)
 
Diesel locomotive works, varanasi
Diesel locomotive works, varanasiDiesel locomotive works, varanasi
Diesel locomotive works, varanasi
 

Similaire à Doubling presentation

Doubling progress report
Doubling progress reportDoubling progress report
Doubling progress reportNeha Singh
 
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptxRAKESHPANDEY754083
 
Lahore orange line train project
Lahore orange line train projectLahore orange line train project
Lahore orange line train projectQurat1255
 
Grievance redressal of Hubli railway station : A multistorey approach
Grievance redressal of Hubli railway station : A multistorey approach Grievance redressal of Hubli railway station : A multistorey approach
Grievance redressal of Hubli railway station : A multistorey approach Nishanth Patil
 
Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)Saksham Bhutani
 
Project brief updated_aug081
Project brief updated_aug081Project brief updated_aug081
Project brief updated_aug081Anush verma
 
Innovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yardInnovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yardRajesh Prasad
 
Tunnels infographic
Tunnels infographicTunnels infographic
Tunnels infographicIQPC Asia
 
Civil engineering in indian railways spce
Civil engineering in indian railways spceCivil engineering in indian railways spce
Civil engineering in indian railways spceirkportal
 
7 Most Significant Underground Projects in Asia Today [Infograph]
7 Most Significant Underground Projects in Asia Today [Infograph]7 Most Significant Underground Projects in Asia Today [Infograph]
7 Most Significant Underground Projects in Asia Today [Infograph]Darwin Jayson Mariano
 
TRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gaugeTRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gaugeJangid Devendra
 
Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Hitesh Khanna
 
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...
IRJET-  	  Comparative Study of Effect of Varying Span Length on Major Elemen...IRJET-  	  Comparative Study of Effect of Varying Span Length on Major Elemen...
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...IRJET Journal
 
10 infrastructure projects in india(Chenab bridge)
10 infrastructure  projects in india(Chenab bridge)10 infrastructure  projects in india(Chenab bridge)
10 infrastructure projects in india(Chenab bridge)Kartik Modi
 

Similaire à Doubling presentation (20)

The poster
The posterThe poster
The poster
 
Doubling progress report
Doubling progress reportDoubling progress report
Doubling progress report
 
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
 
Lahore orange line train project
Lahore orange line train projectLahore orange line train project
Lahore orange line train project
 
Grievance redressal of Hubli railway station : A multistorey approach
Grievance redressal of Hubli railway station : A multistorey approach Grievance redressal of Hubli railway station : A multistorey approach
Grievance redressal of Hubli railway station : A multistorey approach
 
Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)Indian Railways Surveying (RECT, PECT and FLS)
Indian Railways Surveying (RECT, PECT and FLS)
 
Bridge report
Bridge reportBridge report
Bridge report
 
Project brief updated_aug081
Project brief updated_aug081Project brief updated_aug081
Project brief updated_aug081
 
Design of expressway
Design of expresswayDesign of expressway
Design of expressway
 
Railway engineering part2
Railway engineering part2Railway engineering part2
Railway engineering part2
 
Innovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yardInnovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yard
 
Tunnels infographic
Tunnels infographicTunnels infographic
Tunnels infographic
 
Civil engineering in indian railways spce
Civil engineering in indian railways spceCivil engineering in indian railways spce
Civil engineering in indian railways spce
 
INDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTINDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORT
 
R.R.A.C.L-WB1.pdf
R.R.A.C.L-WB1.pdfR.R.A.C.L-WB1.pdf
R.R.A.C.L-WB1.pdf
 
7 Most Significant Underground Projects in Asia Today [Infograph]
7 Most Significant Underground Projects in Asia Today [Infograph]7 Most Significant Underground Projects in Asia Today [Infograph]
7 Most Significant Underground Projects in Asia Today [Infograph]
 
TRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gaugeTRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gauge
 
Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.
 
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...
IRJET-  	  Comparative Study of Effect of Varying Span Length on Major Elemen...IRJET-  	  Comparative Study of Effect of Varying Span Length on Major Elemen...
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...
 
10 infrastructure projects in india(Chenab bridge)
10 infrastructure  projects in india(Chenab bridge)10 infrastructure  projects in india(Chenab bridge)
10 infrastructure projects in india(Chenab bridge)
 

Dernier

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 

Dernier (20)

Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 

Doubling presentation

  • 1. PROJECT REPORT Project Guide Miss Deepti Gupta Senior Lecturer Submitted By Neha Singh 1212200073 Rakesh Kumar Gupta 1212200083 Zeeshan Ahmed 1212200126 PLANNING OF DOUBLING OF BROAD GAUGE RAILWAY LINE AT SHIVNAGAR- BANDHUAKALAN (10 KM) S H R I R A M S WA R O O P M E M O R I A L C O L L E G E O F E N G I N E E R I N G & M A N A G E M E N T
  • 2. I N T R O D U C T I O N Doubling of railway line means construction of an additional line. It is normally done when single line is not in a position to carry the number of trains required to pass on the section. The doubling of Utraitia - Sultanpur-Zafrabad project is for diverting freight traffic from Mughalsarai - Allahabad - New Delhi route so as to provide room for additional coaching traffic to be introduced in near future . The patch doubling from Zafrabad to Shri Krishna Nagar (34 kms), Sultanpur to Bandhuakalan (09 kms) & Utraitia to Chandraulli (37 kms) has been completed. The balance 148 km stretch is with single railway track that need to be double. Specific section of 10 kms length between Shivnagar and Bandhuakalan has been selected for the project.
  • 3. OBJECTIVE To eradicate mounting pressure of rail traffic. To get the optimum benefit from the modern maintenance machines. To cope up with the additional requirement to traffic. The need to divert rail traffic from one route to another due to accident /mishap, or any other unforeseen reason. To reduce initial costs of a line that is certain to see heavy traffic in the future, a line may be built as single- track .
  • 4. M E T H O D O L O G Y SITE & TRAFFIC SURVEY COLLECTION OF SAMPLES SPECIFICATION & DATA COLLECTION FROM RAILWAY OFFICE ANALYSING DATA & SAMPLES ESTIMATION OF EARTHWORK
  • 5. L O C A T I O N Bandhuakalan - Shivnagar Section (12.5 km) LUCKNOW UTRAITIA BAKKAS ANUPGANJ RAHMATNAGAR CHANDRAULLI TRIVEDIGANJ HAIDERGARGH CHAUBISI AKBARGANJ SINDHURWA NIHALGARH ADHINPUR MUSAFIRKHANA SHIVNAGAR BANDHUAKALAN SULTANPUR HARPALGANJ JAUNPUR ZAFRABAD
  • 6. P R O C E S S O F D O U B L I N G Engineering cum Traffic Survey Specification of work Land acquisition EarthworkBridgesPlate laying Opening for goods traffic &ballasting Opening line for passenger traffic
  • 7. ENGI NEERI NG CUM TRAFFI C SURVEY T RAF F I C SURV EY DETAI L S Timings of the train (Hourly basis) No. of trains passing SHIVNAGAR No. of trains passing BANDHUAKALAN BEFORE AFTER BEFORE AFTER 03:00-04:00 0 0 0 0 05:00-06:00 0 2 0 2 06:00-07:00 1 1 2 2 07:00-08:00 1 1 0 0 08:00-09:00 1 4 1 5 10:00-11:00 0 0 0 0 11:00-12:00 0 0 0 2 12:00-13:00 1 1 0 0 13:00-14:00 0 2 0 3 14:00-15:00 0 2 0 1 15:00-16:00 0 2 0 1 16:00-17:00 0 2 0 1 17:00-18:00 0 0 0 2 18:00-19:00 0 3 0 0 19:00-20:00 2 2 2 2 20:00-21:00 0 0 0 0 21:00-22:00 1 1 1 1 23:00-00:00 0 0 0 0 TOTAL 7 23 6 22
  • 8. SPECIFICATION OF WORK Rail and fastenings • The permanent way consists of 60 kg (UIC), 90 UTS rails welded into LWR (By FB(Flush butt welding)/AT(Alumino-Thermit welding) welding with SKV process) over main line. Loop lines, consist 60 Kg 90 UTS SH rails welded into LWR (By AT welding with SKV process). Fish Plates • 1 M Long new fish plates with six holes of standard type to suit 60 kg rails have been used. Sleepers and fastenings • MAIN LINE: PRC sleepers complete with elastic fastenings to M+ 8 (1660 no. per Km) densities have been used. • LOOP LINE: PRC sleepers complete with elastic fastenings to M+ 7 (1540 no. per Km) densities have been used.
  • 9. Guard Rails Guard rails of 52 Kg rails resting on PSC sleepers have been provided on all major bridges. Points and Crossings All turn out to be negotiated by passenger trains are of 1 in 12 with curved switches except turn outs laid for sand humps which are of 1 in 8-1/2 laid on symmetrical split. 60 kg trap points on PSC sleepers have been provided wherever required for the purpose of isolation in new line. Ballast 65mm gauge hard stone Machine Crushed ballast with cushion of 350mm on main line and 250 mm on loop line below the sleeper has been provided under the track and turn outs with boxing. The newly laid track and turn outs have been thoroughly packed manually and machine packing will be done before commissioning SPECIFICATION OF WORK
  • 11.
  • 12.
  • 13.
  • 14.
  • 15.
  • 16.
  • 17.
  • 19. QUANTITY ESTIMATE BLANKETING MATERIAL SOIL1.4 m 0.6 m 5.3 m Existing track Proposed double line Subgrade = 74200 Cubic Meter Blanketing Material = 10600 Cubic Meter Ballast = 2800 Cubic Meter Sleeper =16600 Nos.
  • 20. BRIDGES 48 No. of Bridges Provided for 25 T loading 1 major bridge & 47 minor bridges. Provided as extension of bridges on existing track
  • 21.
  • 22.
  • 23. LEVEL CROSSINGS Total 15 level Crossings 8 Manned Level Crossings 7 Unmanned Level Crossings
  • 24. L I S T O F L E V E L C R O S S I N G S SN Level X-ing No. Manned / Unmanned Interlocked/ Non interlocked Remark 1 82/C Manned Interlocked Traffic 2 83/C Manned Interlocked Traffic 3 84/C Manned Non-interlocked Engineering 4 85/C Manned Non-interlocked Engineering 5 86/C Manned Non-interlocked Engineering 6 87/C Un- Manned Non-interlocked Engineering 7 88/C Un- Manned Non-interlocked Engineering 8 89/C Un- Manned Non-interlocked Engineering 9 90/C Manned Non-interlocked Engineering 11 91/C Un- Manned Non-interlocked Engineering 12 92/C Un- Manned Non-interlocked Engineering 13 93/C Un- Manned Non-interlocked Engineering 14 94/B Manned Interlocked Traffic 15 95/B Manned Interlocked Traffic
  • 25. TEST ON AGGREGATE STONE AGGREGATE TEST SN Sample No. Abrasion value Impact value Water absorption 1 1 16.68% 13.75% 0.296% 2 2 15.90% 13.79% 0.347% 3. AVERAGE 16.29% 13.77% 0.321% 4. MAXIMUM PERMISSIBLE VALUE 30% 20% 1% 5. WITHIN PERMISSIBLE LIMITSOR NOT? YES YES YES
  • 26. TEST ON SOI L TEST ON BURROW SOIL SN Location of Subgrade sample LL PL Dispersive nature 1 SHIVNAGAR 22.10 6.55 NO 2 BANDHUAKALAN 22.29 6.70 NO
  • 27. PLATE LAYI NG OR TRACK LI NKI NG Rails, sleepers and other fittings are taken to the base depot and unloaded Tracks materials are taken to the rail head and track linked and packed Rail head is advanced up to the extent the track is laid Dip lorry is used to take rack material to rail head Rail head goes on advancing till full track is linked T E L E S C O P I C M E T H O D
  • 28. Unloading of materials Linking of track Packing of track Ballasting of track
  • 29. O P E N I N G F O R G O O D S T R A F F I C A N D B A L L A S T I N G
  • 30. C O N C L U S I O N Simplified signaling system. Bi- directional running . Enhancement of line capacity utilization Section capacity showed significant increase Train delay reduced.
  • 31. F U T U R E S C O P E Soil report may be used as a reference for other civil project near the site of project. Topographical survey data can be used for similar projects near the site for design of any other structure. The traffic survey cab help in proper maintenance and future developments in the concerned area. The continuation of this project will help in understanding the use of new technologies employed for this purpose.
  • 32. A D V A N T A G E It can manage a larger amount of traffic with usually twice the capacity of single track. Faster trains can overtake slower ones, and doubling can contribute to faster operation of trains. It is easy to maintenance and engineering work Provision of alternate routes would reduce Pressure on existing network . Doubling would help it earn more revenue from the additional traffic.
  • 33. “Railway is a unique integrator of India. We must restore the strength of Indian railways as the back bone of India.” - Mr. Suresh Prabhu Railway Minister of India Thanks