SlideShare une entreprise Scribd logo
1  sur  53
INTRODUCTION TO
CONSTRUCTION
MANAGEMENT
1
PREPARED BY : ASST. PROF. VATSAL D. PATEL
MAHATMA GANDHI INSTITUTE OF
TECHNICAL EDUCATION &
RESEARCH CENTRE, NAVSARI.
Content
▪ Importance of machineries in construction
▪ Classification ofConstruction Equipment
▪ Plants & Equipment usedin construction
▪ Factors affecting selection of construction equipment
▪ Financial aspectsrelated to construction equipments
▪ Discounted present worthanalysis
▪ Depreciation
▪ Costof owning andoperating construction equipment
▪ Economiclife of construction equipment
▪ Equipment replacementpolicy
The importance of machineries for
construction
▪ Work can be completedfast.
▪ Costof project is reduced.
▪ Lessnumber oflaborers required.
▪ Excavation work canbe carried out rapidly by using Power
shovel, Draglineetc.
▪ Output ishigher
▪ Transportation of construction materials canbe done easily by using
Trucks, Wagons, Dumpersetc.
▪ Heavyloads canbe lifted with the help ofTower crane, Elevator etc.
The importance of machineries for
construction
▪ Better quality in construction is obtained by using construction
equipments.
▪ E.g.: canal lining, concrete spreading, compaction & finishing are
carried out by lining machine.
▪ Finishing & rolling of bituminous roadsis not possible without
Rollers.
PowerShovel
Dragline
Dumper
Tower
Crane
Lining
Machine
Concrete
Mixer
Bulldozer
Scrapper
Air
compressor
Belt
Conveyor
Classification of Construction
Equipment(according to work cycle)
1. IntermittentType: a.Bulldozers
b. Scrappers
c. PowerShovels
d. Concrete Mixers
e.Dragline
2. Continuous FlowType: a.Air Compressors
b. BeltConveyors
3. MixedType: a. MotorGraders
Classification of Construction
Equipment(according to nature of Automation)
1. Manually OperatedEquipment
2. Semi-Automatic Equipment
3. Fully AutomaticEquipment
Classification of Construction
Equipment(according to Standardization of machine)
1. Standard Equipment
2. SpecialEquipment
Difference B/w Standard and Special
Equipments
Standard Equipment
▪ Commonlyusedin all projects
▪ Manufacturedcommonly& easily availablefrom
dealer
▪ Initialinvestmentis low
▪ Resalepriceis high
▪ Deliveryis easy & fast
▪ Repairsand spare parts areeasilyfound
▪ Disposal iseasy
▪ Unit costof productionis less
▪ Rentis low and reasonable
▪ E.g.CanalTrimmer
Special Equipment
▪ Usedonly in specialcases
▪ Manufacturedas perrequirements,specialorder
has to beplaced
▪ Initialinvestmentis high
▪ Resalepriceislow
▪ Delivery is difficult & delayed
▪ Repairsand spare parts are difficultto find
▪ Disposal isdifficult
▪ Unit costof productionis high
▪ Rentishigh and unreasonable
▪ E.g. BeltConveyor
Plants & Equipments used in Construction
▪ Equipment forExcavation
▪ Earthmoving equipment
▪ Hauling equipment
▪ Hoisting equipment
▪ Conveying equipment
▪ Pile drivingequipment
▪ Drilling equipment
▪ Equipment for productionof
aggregate
▪ Plant for grouting and guniting
▪ Machineries for bituminousroad
▪ Machineries for concreteworks
▪ Dredging equipment
Equipment
for
Excavation
Earthmoving
Equipment
Hauling
Equipment
Hoisting
Equipment
Conveying
Equipment
Pumping
Equipment
Compacting
equipment
Pile Driving
Equipment
Drilling
Equipment
Equipmentfor
production of
Aggregate
Grouting
Guniting
Machinery for
Bituminous Road
Dredging
Equipment
Factors affecting the selection of
Construction Equipment
1. Use of standard equipments
2. Size ofequipment
3. Uniformity oftype
4. Country oforigin
5. Initial cost ofequipment
6. Availability of spareparts
7. Unitcost of production
8. Operating facility
9. Suitability forfuture
Financial aspects related to
construction equipments
▪ How to arrange finance
▪ Whether to buy or hire
Sourcesof
equipment
Longterm
Buy
Down
payment
On loans
mobilized
Payment in
installments
Lease
Timelease
Leasing with
option tobuy
later
Shortterm
Direct purchase
Advantages
▪ Equipment is always
economically operated
▪ Itreceives better care &
maintenance
▪ It canbe available and usedat
any time
Disadvantages
▪ If equipment becomesobsolete, it is
useless
▪ Large sums involved remainblocked
▪ Tendency to perform work asper
available equipment
▪ Disposal isdifficult
▪ Equipment may be usedbeyond its
economic life
▪ Equipment may remain in idle
condition forsome time
Hiring (advantages)
▪ Little care is required for maintenance and storage
▪ Desiredequipment is available in working order at short
notice
▪ Investment costscan be diverted to other better purposes
▪ No fear of obsolescence of equipment, full advantage is
taken by contractor of the improved technical aspects of
equipment
▪ If found useful, equipment canbe bought later
Discounted Present Worth Analysis
▪ It involves calculatingthe present valueof all
amounts involved in all the alternatives to
determine the present worth of the proposed
alternatives.
▪ Decisionproblems may beof two types:
a. Revenue dominated cashflowdiagram
b. Cost dominated cash flowdiagram
What is Inflow and Outflow:
(a) Revenue P r o f i t dominated cash flow
diagram:
▪ In this type of cashflow diagram, the revenue, profit, salvage
value, etc. (inflows) will be assigned a(+ve) sign while costs
(outflows) will beassigned.
▪ Finally, the alternative having the maximum present worth amount
should be selected asthe best alternative.
(b) Cost dominated cash flow diagram:
▪ In this type of diagram, the cost(outflows) will be assigned with (+ve)
sign and revenue, profit, salvage value(all inflows) etc. will be
assigned with (-ve)sign.
▪ Finally, the alternative having the minimum present worth amount
should be selected asthe best alternative.
Depreciation
▪ It is the gradual loss in the value of the property due to its
use,life, wear, tear and decay.
▪ It is dependent on its original condition, quality of
maintenance & mode of use.
▪ Usually a%of depreciation per annum is allowed, which
gradually increases withtime
▪ Present value ofproperty
= Initial cost -Total amount of depreciation
Types of depreciation
a) Physical depreciation
1.wear and tear fromoperation
2. action of time and other elements
b) Functional depreciation
1.inadequacy orsuppression
2. obsolescence
Methods of Calculating Depreciation:
1. Straight Linemethod
2. Constant Percentagemethod
3. Sinking Fundmethod
4. Sum of Digitsmethod
5. Service Outputmethod
Straight Line method
Assumption: Property loses its value by the same amount every year.
Therefore,Annual Depreciation=Annual Decreasein property value
where, D=AnnualDepreciation
C=OriginalCost
Depreciation of property after m years: S=ScrapValue
n , m=life in years
Therefore,Book value after m years:
Constant Percentage method
▪ Assumption: Property will lose its value by aconstant percentage of its
value at the beginning of every year.
Where, p=%rate of annual Depreciation
S=Scrap value
C=Originalcost
n= life inyears
▪ If any ageof property is m years, the value of property after m years:
Sinking Fund method
▪ Assumption: depreciation of the property =the annual sinking fund
+ interest on the sinking fund for that year
▪ If I is the rate of interest, the annual sinking fund installment(p) to
accumulate 1Rsin m years:
▪ If I is the rate of interest, and 1Rsis deposited every year, total
sinking fund accumulated at the end of n years:
▪ Rateof depreciation in n years:
Factors affecting Cost of Owning
& operating Equipment:
▪ Costof the equipment to the owner
▪ Demand of the equipment at the end of its useful life
▪ Number of hours it is usedper year
▪ Number of years it isused
▪ Severity of conditions under which it is used
▪ State of maintenance and repairs
Costs to be considered for owning and
operating equipment:
▪ DepreciationCost
▪ InvestmentCost (Average investment= )
▪ Maintenance and repairCost
▪ OperationCost(Repaircharges, Depreciation on tyres and
tubes, Labour Charges, Fuel Charges, Operators and
maintenance crew charges, MiscellaneousSupplies)
▪ Down timeCost
▪ ObsolescenceCost
▪ ReplacementCosts
Economic l i f e of Construction
Equipments:
Equipment should be replacedunder following circumstances:
1. Depreciation
2. Downtime
3. Inadequacy
4. Normal Deterioration
Equipment Replacement Policy:
A firm has to face three type of decisions:
1.The replacementof equipment as it wears out
2.The equipment required forexpansion
3.The replacement of old technology by new
Equipment is replaced before its estimated lifeto:
▪ Reduce production cost
▪ Reducefatigue
▪ Raise quality
▪ Increaseoutput
▪ Securegreater convenience, safety and reliability
What not to consider while selecting an
equipment:
For Equipment inUse
▪OriginalCost
▪Money already spent on repairs and maintenance
▪Unrealistic bookvalue
For NewEquipment
▪Any savings notclearly assessable
▪Overheadcharges
53

Contenu connexe

Tendances

grouting and guniting
grouting and gunitinggrouting and guniting
grouting and guniting
Vipul Kerni
 

Tendances (20)

Special concrete
Special concreteSpecial concrete
Special concrete
 
Critical State Model (Advance Soil Mechanics)
Critical State Model (Advance Soil Mechanics)Critical State Model (Advance Soil Mechanics)
Critical State Model (Advance Soil Mechanics)
 
Dynamic Pile Formulae
Dynamic Pile FormulaeDynamic Pile Formulae
Dynamic Pile Formulae
 
Bonding Agents
Bonding AgentsBonding Agents
Bonding Agents
 
BUILDING ESTIMATION (Details Estimate For G+2 Storied Building presentation ...
BUILDING ESTIMATION (Details Estimate For G+2  Storied Building presentation ...BUILDING ESTIMATION (Details Estimate For G+2  Storied Building presentation ...
BUILDING ESTIMATION (Details Estimate For G+2 Storied Building presentation ...
 
Design of industrial roof truss
Design of industrial roof truss Design of industrial roof truss
Design of industrial roof truss
 
Seismic Retrofitting Techniques
Seismic Retrofitting TechniquesSeismic Retrofitting Techniques
Seismic Retrofitting Techniques
 
Foundation Engineering
Foundation EngineeringFoundation Engineering
Foundation Engineering
 
Chapter 3 compaction and consolidation
Chapter 3 compaction and consolidationChapter 3 compaction and consolidation
Chapter 3 compaction and consolidation
 
WORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-IWORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-I
 
Valuation
ValuationValuation
Valuation
 
Strength evaluation of existing structures
Strength evaluation of existing structuresStrength evaluation of existing structures
Strength evaluation of existing structures
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & Equipments
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPTCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
 
grouting and guniting
grouting and gunitinggrouting and guniting
grouting and guniting
 
Valuation
ValuationValuation
Valuation
 
Earthwork
EarthworkEarthwork
Earthwork
 
staad pro
staad prostaad pro
staad pro
 
CONSTRUCTION METHODS BASICS BTCE-503-18
CONSTRUCTION METHODS BASICSBTCE-503-18CONSTRUCTION METHODS BASICSBTCE-503-18
CONSTRUCTION METHODS BASICS BTCE-503-18
 
High performance concrete; types and uses
High performance concrete; types and usesHigh performance concrete; types and uses
High performance concrete; types and uses
 

Similaire à 9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTU

Ali Khidr CV
Ali Khidr CVAli Khidr CV
Ali Khidr CV
Ali Khidr
 
Analyis of Rate MODULE VI October 2022.pptx
Analyis of Rate  MODULE VI October 2022.pptxAnalyis of Rate  MODULE VI October 2022.pptx
Analyis of Rate MODULE VI October 2022.pptx
rekhat26
 
Ali Khidr CV
Ali Khidr CVAli Khidr CV
Ali Khidr CV
Ali Khidr
 

Similaire à 9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTU (20)

Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Equipment management
Equipment managementEquipment management
Equipment management
 
Construction machinery - Associated costs and basic concepts
Construction machinery - Associated costs and basic conceptsConstruction machinery - Associated costs and basic concepts
Construction machinery - Associated costs and basic concepts
 
Chapter 9 introduction to construction equipments
Chapter  9 introduction to construction equipmentsChapter  9 introduction to construction equipments
Chapter 9 introduction to construction equipments
 
Ali Khidr CV
Ali Khidr CVAli Khidr CV
Ali Khidr CV
 
Analyis of Rate MODULE VI October 2022.pptx
Analyis of Rate  MODULE VI October 2022.pptxAnalyis of Rate  MODULE VI October 2022.pptx
Analyis of Rate MODULE VI October 2022.pptx
 
EAR and CAR Insurance in Construction
EAR and CAR Insurance in ConstructionEAR and CAR Insurance in Construction
EAR and CAR Insurance in Construction
 
Lecture -4.pptxTender & Tender Notice bfh
Lecture -4.pptxTender & Tender Notice bfhLecture -4.pptxTender & Tender Notice bfh
Lecture -4.pptxTender & Tender Notice bfh
 
STUDY ON CONSTRUCTION EQUIPMENT MANAGEMENT IN PAVEMENT CONSTRUCTION By Shabaz...
STUDY ON CONSTRUCTION EQUIPMENT MANAGEMENT IN PAVEMENT CONSTRUCTION By Shabaz...STUDY ON CONSTRUCTION EQUIPMENT MANAGEMENT IN PAVEMENT CONSTRUCTION By Shabaz...
STUDY ON CONSTRUCTION EQUIPMENT MANAGEMENT IN PAVEMENT CONSTRUCTION By Shabaz...
 
Mechanised construction
Mechanised constructionMechanised construction
Mechanised construction
 
Ali Khidr CV
Ali Khidr CVAli Khidr CV
Ali Khidr CV
 
GROUP-2-COMMON-REPORT.pptx
GROUP-2-COMMON-REPORT.pptxGROUP-2-COMMON-REPORT.pptx
GROUP-2-COMMON-REPORT.pptx
 
UNIT 2.pptx
UNIT 2.pptxUNIT 2.pptx
UNIT 2.pptx
 
Rate analysis brief
Rate analysis briefRate analysis brief
Rate analysis brief
 
Unit 6 A Construction Equipments for civil engineering.pdf
Unit 6 A Construction Equipments for civil engineering.pdfUnit 6 A Construction Equipments for civil engineering.pdf
Unit 6 A Construction Equipments for civil engineering.pdf
 
Estimating & costing of civil engineering structures
Estimating & costing of civil engineering structuresEstimating & costing of civil engineering structures
Estimating & costing of civil engineering structures
 
CL 380_Unit-1.pptx
CL 380_Unit-1.pptxCL 380_Unit-1.pptx
CL 380_Unit-1.pptx
 
CL 380_Unit-1 (1).pptx
CL 380_Unit-1 (1).pptxCL 380_Unit-1 (1).pptx
CL 380_Unit-1 (1).pptx
 
Construction Equipment used in construction projects
Construction Equipment used in construction projectsConstruction Equipment used in construction projects
Construction Equipment used in construction projects
 
Resources of Construction Industry
Resources of Construction IndustryResources of Construction Industry
Resources of Construction Industry
 

Plus de VATSAL PATEL

Plus de VATSAL PATEL (20)

5. AIR TRANSPORTATION (TRE) GTU 3150611
5. AIR TRANSPORTATION (TRE) GTU 31506115. AIR TRANSPORTATION (TRE) GTU 3150611
5. AIR TRANSPORTATION (TRE) GTU 3150611
 
3. RAIL TRANSPORTATION (TRE) GTU 3150611
3. RAIL TRANSPORTATION (TRE) GTU 31506113. RAIL TRANSPORTATION (TRE) GTU 3150611
3. RAIL TRANSPORTATION (TRE) GTU 3150611
 
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
 
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
 
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
 
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
 
2. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 31706232. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 3170623
 
4. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 31506114. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 3150611
 
8. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 31706238. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 3170623
 
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
 
7. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 31706237. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 3170623
 
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 31706236. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
 
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 31706235. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
 
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 31706234. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
 
3. NATURAL PHENOMENA (PHE) GTU 3170623
3. NATURAL PHENOMENA (PHE) GTU 31706233. NATURAL PHENOMENA (PHE) GTU 3170623
3. NATURAL PHENOMENA (PHE) GTU 3170623
 
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
 
1. INTRODUCTION TO WATER TRANSPORTATION (PHE) GTU 3170623
1. INTRODUCTION  TO WATER TRANSPORTATION (PHE) GTU 31706231. INTRODUCTION  TO WATER TRANSPORTATION (PHE) GTU 3170623
1. INTRODUCTION TO WATER TRANSPORTATION (PHE) GTU 3170623
 
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
 
1. INTRODUCTION (TRE) 3150611 GTU
1. INTRODUCTION (TRE) 3150611 GTU1. INTRODUCTION (TRE) 3150611 GTU
1. INTRODUCTION (TRE) 3150611 GTU
 
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
 

Dernier

Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
chumtiyababu
 

Dernier (20)

DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 

9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTU

  • 1. INTRODUCTION TO CONSTRUCTION MANAGEMENT 1 PREPARED BY : ASST. PROF. VATSAL D. PATEL MAHATMA GANDHI INSTITUTE OF TECHNICAL EDUCATION & RESEARCH CENTRE, NAVSARI.
  • 2. Content ▪ Importance of machineries in construction ▪ Classification ofConstruction Equipment ▪ Plants & Equipment usedin construction ▪ Factors affecting selection of construction equipment ▪ Financial aspectsrelated to construction equipments ▪ Discounted present worthanalysis ▪ Depreciation ▪ Costof owning andoperating construction equipment ▪ Economiclife of construction equipment ▪ Equipment replacementpolicy
  • 3. The importance of machineries for construction ▪ Work can be completedfast. ▪ Costof project is reduced. ▪ Lessnumber oflaborers required. ▪ Excavation work canbe carried out rapidly by using Power shovel, Draglineetc. ▪ Output ishigher ▪ Transportation of construction materials canbe done easily by using Trucks, Wagons, Dumpersetc. ▪ Heavyloads canbe lifted with the help ofTower crane, Elevator etc.
  • 4. The importance of machineries for construction ▪ Better quality in construction is obtained by using construction equipments. ▪ E.g.: canal lining, concrete spreading, compaction & finishing are carried out by lining machine. ▪ Finishing & rolling of bituminous roadsis not possible without Rollers.
  • 15. Classification of Construction Equipment(according to work cycle) 1. IntermittentType: a.Bulldozers b. Scrappers c. PowerShovels d. Concrete Mixers e.Dragline 2. Continuous FlowType: a.Air Compressors b. BeltConveyors 3. MixedType: a. MotorGraders
  • 16. Classification of Construction Equipment(according to nature of Automation) 1. Manually OperatedEquipment 2. Semi-Automatic Equipment 3. Fully AutomaticEquipment
  • 17. Classification of Construction Equipment(according to Standardization of machine) 1. Standard Equipment 2. SpecialEquipment
  • 18. Difference B/w Standard and Special Equipments Standard Equipment ▪ Commonlyusedin all projects ▪ Manufacturedcommonly& easily availablefrom dealer ▪ Initialinvestmentis low ▪ Resalepriceis high ▪ Deliveryis easy & fast ▪ Repairsand spare parts areeasilyfound ▪ Disposal iseasy ▪ Unit costof productionis less ▪ Rentis low and reasonable ▪ E.g.CanalTrimmer Special Equipment ▪ Usedonly in specialcases ▪ Manufacturedas perrequirements,specialorder has to beplaced ▪ Initialinvestmentis high ▪ Resalepriceislow ▪ Delivery is difficult & delayed ▪ Repairsand spare parts are difficultto find ▪ Disposal isdifficult ▪ Unit costof productionis high ▪ Rentishigh and unreasonable ▪ E.g. BeltConveyor
  • 19. Plants & Equipments used in Construction ▪ Equipment forExcavation ▪ Earthmoving equipment ▪ Hauling equipment ▪ Hoisting equipment ▪ Conveying equipment ▪ Pile drivingequipment ▪ Drilling equipment ▪ Equipment for productionof aggregate ▪ Plant for grouting and guniting ▪ Machineries for bituminousroad ▪ Machineries for concreteworks ▪ Dredging equipment
  • 34. Factors affecting the selection of Construction Equipment 1. Use of standard equipments 2. Size ofequipment 3. Uniformity oftype 4. Country oforigin 5. Initial cost ofequipment 6. Availability of spareparts 7. Unitcost of production 8. Operating facility 9. Suitability forfuture
  • 35. Financial aspects related to construction equipments ▪ How to arrange finance ▪ Whether to buy or hire Sourcesof equipment Longterm Buy Down payment On loans mobilized Payment in installments Lease Timelease Leasing with option tobuy later Shortterm
  • 36. Direct purchase Advantages ▪ Equipment is always economically operated ▪ Itreceives better care & maintenance ▪ It canbe available and usedat any time Disadvantages ▪ If equipment becomesobsolete, it is useless ▪ Large sums involved remainblocked ▪ Tendency to perform work asper available equipment ▪ Disposal isdifficult ▪ Equipment may be usedbeyond its economic life ▪ Equipment may remain in idle condition forsome time
  • 37. Hiring (advantages) ▪ Little care is required for maintenance and storage ▪ Desiredequipment is available in working order at short notice ▪ Investment costscan be diverted to other better purposes ▪ No fear of obsolescence of equipment, full advantage is taken by contractor of the improved technical aspects of equipment ▪ If found useful, equipment canbe bought later
  • 38. Discounted Present Worth Analysis ▪ It involves calculatingthe present valueof all amounts involved in all the alternatives to determine the present worth of the proposed alternatives. ▪ Decisionproblems may beof two types: a. Revenue dominated cashflowdiagram b. Cost dominated cash flowdiagram
  • 39. What is Inflow and Outflow:
  • 40. (a) Revenue P r o f i t dominated cash flow diagram: ▪ In this type of cashflow diagram, the revenue, profit, salvage value, etc. (inflows) will be assigned a(+ve) sign while costs (outflows) will beassigned. ▪ Finally, the alternative having the maximum present worth amount should be selected asthe best alternative.
  • 41. (b) Cost dominated cash flow diagram: ▪ In this type of diagram, the cost(outflows) will be assigned with (+ve) sign and revenue, profit, salvage value(all inflows) etc. will be assigned with (-ve)sign. ▪ Finally, the alternative having the minimum present worth amount should be selected asthe best alternative.
  • 42. Depreciation ▪ It is the gradual loss in the value of the property due to its use,life, wear, tear and decay. ▪ It is dependent on its original condition, quality of maintenance & mode of use. ▪ Usually a%of depreciation per annum is allowed, which gradually increases withtime ▪ Present value ofproperty = Initial cost -Total amount of depreciation
  • 43. Types of depreciation a) Physical depreciation 1.wear and tear fromoperation 2. action of time and other elements b) Functional depreciation 1.inadequacy orsuppression 2. obsolescence
  • 44. Methods of Calculating Depreciation: 1. Straight Linemethod 2. Constant Percentagemethod 3. Sinking Fundmethod 4. Sum of Digitsmethod 5. Service Outputmethod
  • 45. Straight Line method Assumption: Property loses its value by the same amount every year. Therefore,Annual Depreciation=Annual Decreasein property value where, D=AnnualDepreciation C=OriginalCost Depreciation of property after m years: S=ScrapValue n , m=life in years Therefore,Book value after m years:
  • 46. Constant Percentage method ▪ Assumption: Property will lose its value by aconstant percentage of its value at the beginning of every year. Where, p=%rate of annual Depreciation S=Scrap value C=Originalcost n= life inyears ▪ If any ageof property is m years, the value of property after m years:
  • 47. Sinking Fund method ▪ Assumption: depreciation of the property =the annual sinking fund + interest on the sinking fund for that year ▪ If I is the rate of interest, the annual sinking fund installment(p) to accumulate 1Rsin m years: ▪ If I is the rate of interest, and 1Rsis deposited every year, total sinking fund accumulated at the end of n years: ▪ Rateof depreciation in n years:
  • 48. Factors affecting Cost of Owning & operating Equipment: ▪ Costof the equipment to the owner ▪ Demand of the equipment at the end of its useful life ▪ Number of hours it is usedper year ▪ Number of years it isused ▪ Severity of conditions under which it is used ▪ State of maintenance and repairs
  • 49. Costs to be considered for owning and operating equipment: ▪ DepreciationCost ▪ InvestmentCost (Average investment= ) ▪ Maintenance and repairCost ▪ OperationCost(Repaircharges, Depreciation on tyres and tubes, Labour Charges, Fuel Charges, Operators and maintenance crew charges, MiscellaneousSupplies) ▪ Down timeCost ▪ ObsolescenceCost ▪ ReplacementCosts
  • 50. Economic l i f e of Construction Equipments: Equipment should be replacedunder following circumstances: 1. Depreciation 2. Downtime 3. Inadequacy 4. Normal Deterioration
  • 51. Equipment Replacement Policy: A firm has to face three type of decisions: 1.The replacementof equipment as it wears out 2.The equipment required forexpansion 3.The replacement of old technology by new Equipment is replaced before its estimated lifeto: ▪ Reduce production cost ▪ Reducefatigue ▪ Raise quality ▪ Increaseoutput ▪ Securegreater convenience, safety and reliability
  • 52. What not to consider while selecting an equipment: For Equipment inUse ▪OriginalCost ▪Money already spent on repairs and maintenance ▪Unrealistic bookvalue For NewEquipment ▪Any savings notclearly assessable ▪Overheadcharges
  • 53. 53