1. Route 606 Loudoun County Parkway /
Old Ox Road Reconstruction and
Widening Project
Lunsford Middle School
October 17, 2016
2. 2
Objectives
Provide an Overview of the Project
Discuss the Project Schedule
Describe Construction Sequence
Answer Your Questions
3. 3
Major Design Features
Typical Section
Four lane divided roadway
Raised 28’ Wide Grass Median
8’ wide full Depth Shoulders
10’ Wide Shared Use Path on West Side
6. 6
Project Metrics
Total Project Cost: $107.7 Million
Construction Contract Value: $89.9 Million
Project Length: 5 Miles
Right-of-Way Acquisition: 55 Parcels
(Including up to 40 Acres from MWAA)
Adjustments to 9 Utilities
Project Duration: 50 months
7. 7
June 2014 Notice To Proceed
June 2014 - Spring 2015 Complete Design / Permitting
Spring - Fall 2016 Right of Way Acquisition
Fall 2015 – Spring 2017 Utility Relocations
Fall 2015 – Spring 2017 Stage 1 Construction
Early 2017- Spring 2018 Stage 2 Construction
Summer 2018 Stage 3 / Complete Project
Project Schedule