SlideShare une entreprise Scribd logo
1  sur  18
Transportable
  Treatment
    Units
WHAT IS A TTU?



IT IS A FULLY FUNCTIONING WATER TREATMENT WORKS THAT CAN BE TRANSPORTED TO
                        SITE ON THE BACK OF A LOW LOADER.
WHAT IS A TTU?


A TTU contains a Water Treatment Works which is primarily used for removing Colour, Turbidity and
                    Cryptosporidium from the water, making it safe to drink.

            A TTU can produce anything from 2m³ to 220m³ of drinkable water each day.

 For greater requirements we can supply a ‘modular build plant’ which is capable of producing up to
1320m³ of water per day. While this plant is not a TTU it is a purpose made building utilising the same
              technology and containing skids that carry all of the working components.
A TTU is the complete package for a Nano Filtration plant and offers huge environmental advantages
                       and cost savings over a conventional ‘on site’ building.

 A complete transportable WTW offering a turn key solution that has been designed and developed
                     through ongoing innovations at Ross-Shire Engineering.
PROCESS


PROCESS AND INSTRUMENTATION DIAGRAM – 100m³ Per Day plant
PROCESS


                         A variety of options available for a TTU Design.

there are currently 18 options available depending on the requirements of the site. These options
     include, Feed Pumps, Duty/Stand By Strainers, Permeate Tanks, Re-Lift Pumps, etc...
DESIGN AND FABRICATION




                                                  The TTU’s are designed and fabricated ‘in
                                                 house’ and leave our fabrication facility as a
                                                          fully commissioned plant.




The TTU Building, Pipework, Cabling, Civil and
   Software Design are all carried out and
 completed at our Head office in Muir of Ord.
DESIGN AND FABRICATION


The TTU Building is designed to withstand the highest wind speeds ever recorded in the British Isles.
attention to this design detail ensures suitability for placement from the Shetland Islands to lands End.



  Each building is enclosed in a thermal cladding
  which helps maintain the inside temperature at a
                  steady constant.
    The TTU also has high security doors and a
      motorised roller door on the Gable End.




                                                     The building is designed to allow a crane to lift it
                                                       from the lorry bed onto the concrete slab that
                                                     the TTU ultimately sits on, whilst fully laden with
                                                                     all the equipment.
DESIGN AND FABRICATION


All of the pipework within the TTU is Stainless Steel and fully welded which negates any risk of leakage
 through the joints. It is fully designed within our 3D Design package, Autodesk Inventor, which allows
                   for full ‘walk through’ design including instrumentation and cabling.

 The pipework is routed to allow for clear walkways
      throughout the building allowing ease of
   maintenance if required. All pipework is fixed
  500mm from the floor to allow for cable tray and
 cables to be run underneath, without any conflicts.




                                                            All pipework is compiled and put onto
                                                         drawings for review by the design team and
                                                       the pipefitters / welders. This ensures that the
                                                        pipework is designed correctly practically and
                                                                           efficiently.
DESIGN AND FABRICATION


The plants are designed with an intelligent MCC that utilises a Siemens PLC with a Profibus network to
    communicate with all the pumps, valves and instruments, including pressure, flow and quality
                                             instruments.

     Using a ProfiBUS network for control and
     automation reduces the amount of cabling
    required by 25% and allows the MCC, cable
 containment and building to be smaller than with a
            conventional control system.




                                                      The use of a Intelligent MCC allows the option
                                                      of remote control and monitoring, should it be
                                                                          required.
DESIGN AND FABRICATION


 All pipework spools are initially put into the 3d Model and arranged to suit each specific site. they are
then put onto separate drawings and sized to allow the pipe fitters and welders to fabricate the spools.
 Once produced the spools are pre fitted, cleaned and flushed before final installation within the TTU.
DESIGN AND FABRICATION


 Once the TTU design, fabrication, pre-Installation is complete the final Install can begin. This work is
carried out by a fully trained team of multi skilled time served men and women working closely together
                                       efficiently and constructively.

         Before the final fitment, pipe, pipe
 supports, brackets and cable tray is all installed to
 ensure fit and quality. Once the pre fit is complete
  the job is checked against the design criteria for
   each site, once checked it is sent for finishing.




                                                              Upon completion of the painting and
                                                         galvanizing of the fabricated components they
                                                         are placed into the building for final fitment. the
                                                           cabling is then completed ready for testing.
COMMISIONING


   THE COMMISSIONING IS CARRIED OUT IN THREE STAGES, FIRST AN INSTALLATION
INSPECTION IS CARRIED OUT TO ENSURE THE PLANT HAS BEEN CONSTRUCTED AS THE
                                  DESIGN.

Next comes the dry testing, the plant is powered
 up and the required settings for pumps, valves
and drives are entered. The profibus network is
       also commissioned at this stage.




                                                    Once the dry test is complete the wet testing
                                                    can begin. This is carried out in our workshop
                                                   and the plant is tested with full flows through it.
CIVILS


  Infrastructure in any contract within the water
industry is essential, it provides the services and
   structures for the M & E install process. The
  bespoke reinforced concrete base provides a
robust platform which encapsulates the services
 penetrations to allow mechanical and electrical
  install to take place directly after the TTU has
                    been placed.
TRANSPORTATION


Upon completion of the construction and testing, the TTU embarks on the final stage of its journey, to
site. It is placed onto ‘skates’ and rolled out of the workshop, it is then lifted onto the back of a 40ft Lo-
                                              loader by crane.



 Once the TTU has been fully secured it leaves for
 site. This part of its journey has involved a great
        deal of in-depth logistical planning.




                                                            Due to the variety of site locations within
                                                            Scotland tending to be served by B Class
                                                             roads the logistics route planning and
                                                              surveying can in itself be extremely
                                                                          challenging.
TRANSPORTATION


Many sites are on islands or only accessible via ferry, this has to all be planned and programmed into
the journey of the TTU. The Units are designed to conform to the maximum width and height allowed
                                on UK roads, without a Police escort.



On arrival at site the crane then lifts the TTU onto
  a concrete slab that has been constructed to
        mirror the detail of the 3d Model.




                                                       Once placed onto the slab it is anchored by
                                                       Eight M30 holding down bolts pre-cast into
                                                                       the slab.
COMPLETED TTU


After all of the tie-ins have been completed and the remainder of the site work complete the TTU is
                   then ready to be Fully commissioned and be put into its Test Stage.
CURRENT RSE SITES


Ross-Shire Engineering are currently carrying out work
on various sites throughout Scotland. These sites vary
            in location, size and build type.



                   TTU BUILDS
          Sheildaig WTW - 150m³ per day
        Kinlochewe WTW – 150m³ per day
        Loch katrine WTW – 35m³ per day
       Stronachlachar WTW – 35m³ per day
          Kilchoan WTW – 160m³ per day
              Raasay - 200m³ per day



           PURPOSE MADE BUILDS
        Lochcarron WTW – 520m³ per day
           Unst WTW – 520m³ per day
         Broadford WTW - 520m³ per day
RSE INNOVATIVE DEVELOPMENTS


    After winning the ‘SCDI Highlands and Islands Business Excellence Award for Excellence in
 Research and Innovation’. Ross-Shire Engineering has not rested on its laurels, and are currently
looking into further developing the design of the TTU to incorporate clear water tanks and chemical
 waste tanks. This will remove a vast amount of the civil scope of works and will greatly benefit the
   environment, as well as being even more cost effective. incorporating these two tanks into the
building will ensure there is far less disruption to the area within the immediate vicinity of the WTW.
   These designs are still in their early stages, but are looking extremely positive and will have a
           massive impact on the amount of site work required at WTW sites in the future.

Contenu connexe

Similaire à Rosshire engineering

AGE TECHNOLOGIES_2014 project briefs
AGE TECHNOLOGIES_2014 project briefsAGE TECHNOLOGIES_2014 project briefs
AGE TECHNOLOGIES_2014 project briefsAGE Technologies
 
Development Strategic Solutions
Development Strategic SolutionsDevelopment Strategic Solutions
Development Strategic Solutionsguest11c3c80a
 
Roxtec industry oem
Roxtec industry oemRoxtec industry oem
Roxtec industry oemRADOME-IT
 
CT3 1c aluminium formwork+
CT3 1c aluminium formwork+ CT3 1c aluminium formwork+
CT3 1c aluminium formwork+ Est
 
INDUSTRIAL TRAINING SLIDE AFIF.pptx
INDUSTRIAL TRAINING SLIDE AFIF.pptxINDUSTRIAL TRAINING SLIDE AFIF.pptx
INDUSTRIAL TRAINING SLIDE AFIF.pptxeiyshab5428
 
VSL_techniques_and_services
VSL_techniques_and_servicesVSL_techniques_and_services
VSL_techniques_and_servicesBrian Lim
 
Mmmp Mep Experience Sheet
Mmmp   Mep Experience SheetMmmp   Mep Experience Sheet
Mmmp Mep Experience Sheetfuadhabayeb
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridgesCivil Engineers
 
130702_Interview Portfolio_reduced
130702_Interview Portfolio_reduced130702_Interview Portfolio_reduced
130702_Interview Portfolio_reducedMihir Benodekar
 
ASCO Numatics Fluid Power & Pneumatic Solutions for Automotive & Tyre Manufac...
ASCO Numatics Fluid Power & Pneumatic Solutions for Automotive & Tyre Manufac...ASCO Numatics Fluid Power & Pneumatic Solutions for Automotive & Tyre Manufac...
ASCO Numatics Fluid Power & Pneumatic Solutions for Automotive & Tyre Manufac...Thorne & Derrick UK
 
dark_territory_switch_monitoring_ptc_system
dark_territory_switch_monitoring_ptc_systemdark_territory_switch_monitoring_ptc_system
dark_territory_switch_monitoring_ptc_systemDeepak Dangi
 
Larsen & toubro constructions
Larsen & toubro constructionsLarsen & toubro constructions
Larsen & toubro constructionsengineeringwatch
 
EDUARDO H. PARE 10 METHODS TO AVOID WATER LEAKAGES ON BUILDING CONSTRUCTION
EDUARDO H. PARE 10 METHODS TO AVOID WATER LEAKAGES ON BUILDING CONSTRUCTIONEDUARDO H. PARE 10 METHODS TO AVOID WATER LEAKAGES ON BUILDING CONSTRUCTION
EDUARDO H. PARE 10 METHODS TO AVOID WATER LEAKAGES ON BUILDING CONSTRUCTIONEduardo H. Pare
 
Cofely Fabricom Brochure OilGas 2015
Cofely Fabricom Brochure OilGas 2015Cofely Fabricom Brochure OilGas 2015
Cofely Fabricom Brochure OilGas 2015Jailton Rodrigues
 
WaterProof Lift Pit Brochure - Web
WaterProof Lift Pit Brochure - WebWaterProof Lift Pit Brochure - Web
WaterProof Lift Pit Brochure - WebJeff Heath
 
PVH_CorpPresentation_Nov_v1
PVH_CorpPresentation_Nov_v1PVH_CorpPresentation_Nov_v1
PVH_CorpPresentation_Nov_v1Gregory Lukens
 

Similaire à Rosshire engineering (20)

AGE TECHNOLOGIES_2014 project briefs
AGE TECHNOLOGIES_2014 project briefsAGE TECHNOLOGIES_2014 project briefs
AGE TECHNOLOGIES_2014 project briefs
 
Development Strategic Solutions
Development Strategic SolutionsDevelopment Strategic Solutions
Development Strategic Solutions
 
Roxtec industry oem
Roxtec industry oemRoxtec industry oem
Roxtec industry oem
 
cv2016
cv2016cv2016
cv2016
 
CT3 1c aluminium formwork+
CT3 1c aluminium formwork+ CT3 1c aluminium formwork+
CT3 1c aluminium formwork+
 
INDUSTRIAL TRAINING SLIDE AFIF.pptx
INDUSTRIAL TRAINING SLIDE AFIF.pptxINDUSTRIAL TRAINING SLIDE AFIF.pptx
INDUSTRIAL TRAINING SLIDE AFIF.pptx
 
VSL_techniques_and_services
VSL_techniques_and_servicesVSL_techniques_and_services
VSL_techniques_and_services
 
Mmmp Mep Experience Sheet
Mmmp   Mep Experience SheetMmmp   Mep Experience Sheet
Mmmp Mep Experience Sheet
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
Segmnetal construction of bridges
Segmnetal construction of bridgesSegmnetal construction of bridges
Segmnetal construction of bridges
 
130702_Interview Portfolio_reduced
130702_Interview Portfolio_reduced130702_Interview Portfolio_reduced
130702_Interview Portfolio_reduced
 
ASCO Numatics Fluid Power & Pneumatic Solutions for Automotive & Tyre Manufac...
ASCO Numatics Fluid Power & Pneumatic Solutions for Automotive & Tyre Manufac...ASCO Numatics Fluid Power & Pneumatic Solutions for Automotive & Tyre Manufac...
ASCO Numatics Fluid Power & Pneumatic Solutions for Automotive & Tyre Manufac...
 
dark_territory_switch_monitoring_ptc_system
dark_territory_switch_monitoring_ptc_systemdark_territory_switch_monitoring_ptc_system
dark_territory_switch_monitoring_ptc_system
 
Larsen & toubro constructions
Larsen & toubro constructionsLarsen & toubro constructions
Larsen & toubro constructions
 
EDUARDO H. PARE 10 METHODS TO AVOID WATER LEAKAGES ON BUILDING CONSTRUCTION
EDUARDO H. PARE 10 METHODS TO AVOID WATER LEAKAGES ON BUILDING CONSTRUCTIONEDUARDO H. PARE 10 METHODS TO AVOID WATER LEAKAGES ON BUILDING CONSTRUCTION
EDUARDO H. PARE 10 METHODS TO AVOID WATER LEAKAGES ON BUILDING CONSTRUCTION
 
QKS flyer Rev 2
QKS flyer Rev 2QKS flyer Rev 2
QKS flyer Rev 2
 
Ccs mithushibushi
Ccs mithushibushiCcs mithushibushi
Ccs mithushibushi
 
Cofely Fabricom Brochure OilGas 2015
Cofely Fabricom Brochure OilGas 2015Cofely Fabricom Brochure OilGas 2015
Cofely Fabricom Brochure OilGas 2015
 
WaterProof Lift Pit Brochure - Web
WaterProof Lift Pit Brochure - WebWaterProof Lift Pit Brochure - Web
WaterProof Lift Pit Brochure - Web
 
PVH_CorpPresentation_Nov_v1
PVH_CorpPresentation_Nov_v1PVH_CorpPresentation_Nov_v1
PVH_CorpPresentation_Nov_v1
 

Plus de victorialambert (20)

BCSD-UK Decentralised Energy Guide
BCSD-UK Decentralised Energy GuideBCSD-UK Decentralised Energy Guide
BCSD-UK Decentralised Energy Guide
 
Skanska school ppp dm to put on web
Skanska school ppp dm to put on webSkanska school ppp dm to put on web
Skanska school ppp dm to put on web
 
Nick grayson slides
Nick grayson slidesNick grayson slides
Nick grayson slides
 
Sharon freedman slides
Sharon freedman slidesSharon freedman slides
Sharon freedman slides
 
D maxwell slides
D maxwell slidesD maxwell slides
D maxwell slides
 
Russell codling slides
Russell codling slidesRussell codling slides
Russell codling slides
 
Wsp presentation
Wsp presentationWsp presentation
Wsp presentation
 
Skanska presentation
Skanska presentationSkanska presentation
Skanska presentation
 
Converteam presentation
Converteam presentationConverteam presentation
Converteam presentation
 
The hydrogen office
The hydrogen officeThe hydrogen office
The hydrogen office
 
Sse water evolution
Sse water evolutionSse water evolution
Sse water evolution
 
Siemens
SiemensSiemens
Siemens
 
Pure
PurePure
Pure
 
E.on
E.onE.on
E.on
 
Carbon trust
Carbon trustCarbon trust
Carbon trust
 
Cev workshop jan 12 wbcsd slides
Cev workshop jan 12 wbcsd slidesCev workshop jan 12 wbcsd slides
Cev workshop jan 12 wbcsd slides
 
Cev workshop jan 12 heineken slides
Cev workshop jan 12 heineken slidesCev workshop jan 12 heineken slides
Cev workshop jan 12 heineken slides
 
Cev workshop jan 12 esktn slides
Cev workshop jan 12 esktn slidesCev workshop jan 12 esktn slides
Cev workshop jan 12 esktn slides
 
Annes slides WBCSD
Annes slides WBCSDAnnes slides WBCSD
Annes slides WBCSD
 
Anglian Water
Anglian WaterAnglian Water
Anglian Water
 

Rosshire engineering

  • 2. WHAT IS A TTU? IT IS A FULLY FUNCTIONING WATER TREATMENT WORKS THAT CAN BE TRANSPORTED TO SITE ON THE BACK OF A LOW LOADER.
  • 3. WHAT IS A TTU? A TTU contains a Water Treatment Works which is primarily used for removing Colour, Turbidity and Cryptosporidium from the water, making it safe to drink. A TTU can produce anything from 2m³ to 220m³ of drinkable water each day. For greater requirements we can supply a ‘modular build plant’ which is capable of producing up to 1320m³ of water per day. While this plant is not a TTU it is a purpose made building utilising the same technology and containing skids that carry all of the working components. A TTU is the complete package for a Nano Filtration plant and offers huge environmental advantages and cost savings over a conventional ‘on site’ building. A complete transportable WTW offering a turn key solution that has been designed and developed through ongoing innovations at Ross-Shire Engineering.
  • 4. PROCESS PROCESS AND INSTRUMENTATION DIAGRAM – 100m³ Per Day plant
  • 5. PROCESS A variety of options available for a TTU Design. there are currently 18 options available depending on the requirements of the site. These options include, Feed Pumps, Duty/Stand By Strainers, Permeate Tanks, Re-Lift Pumps, etc...
  • 6. DESIGN AND FABRICATION The TTU’s are designed and fabricated ‘in house’ and leave our fabrication facility as a fully commissioned plant. The TTU Building, Pipework, Cabling, Civil and Software Design are all carried out and completed at our Head office in Muir of Ord.
  • 7. DESIGN AND FABRICATION The TTU Building is designed to withstand the highest wind speeds ever recorded in the British Isles. attention to this design detail ensures suitability for placement from the Shetland Islands to lands End. Each building is enclosed in a thermal cladding which helps maintain the inside temperature at a steady constant. The TTU also has high security doors and a motorised roller door on the Gable End. The building is designed to allow a crane to lift it from the lorry bed onto the concrete slab that the TTU ultimately sits on, whilst fully laden with all the equipment.
  • 8. DESIGN AND FABRICATION All of the pipework within the TTU is Stainless Steel and fully welded which negates any risk of leakage through the joints. It is fully designed within our 3D Design package, Autodesk Inventor, which allows for full ‘walk through’ design including instrumentation and cabling. The pipework is routed to allow for clear walkways throughout the building allowing ease of maintenance if required. All pipework is fixed 500mm from the floor to allow for cable tray and cables to be run underneath, without any conflicts. All pipework is compiled and put onto drawings for review by the design team and the pipefitters / welders. This ensures that the pipework is designed correctly practically and efficiently.
  • 9. DESIGN AND FABRICATION The plants are designed with an intelligent MCC that utilises a Siemens PLC with a Profibus network to communicate with all the pumps, valves and instruments, including pressure, flow and quality instruments. Using a ProfiBUS network for control and automation reduces the amount of cabling required by 25% and allows the MCC, cable containment and building to be smaller than with a conventional control system. The use of a Intelligent MCC allows the option of remote control and monitoring, should it be required.
  • 10. DESIGN AND FABRICATION All pipework spools are initially put into the 3d Model and arranged to suit each specific site. they are then put onto separate drawings and sized to allow the pipe fitters and welders to fabricate the spools. Once produced the spools are pre fitted, cleaned and flushed before final installation within the TTU.
  • 11. DESIGN AND FABRICATION Once the TTU design, fabrication, pre-Installation is complete the final Install can begin. This work is carried out by a fully trained team of multi skilled time served men and women working closely together efficiently and constructively. Before the final fitment, pipe, pipe supports, brackets and cable tray is all installed to ensure fit and quality. Once the pre fit is complete the job is checked against the design criteria for each site, once checked it is sent for finishing. Upon completion of the painting and galvanizing of the fabricated components they are placed into the building for final fitment. the cabling is then completed ready for testing.
  • 12. COMMISIONING THE COMMISSIONING IS CARRIED OUT IN THREE STAGES, FIRST AN INSTALLATION INSPECTION IS CARRIED OUT TO ENSURE THE PLANT HAS BEEN CONSTRUCTED AS THE DESIGN. Next comes the dry testing, the plant is powered up and the required settings for pumps, valves and drives are entered. The profibus network is also commissioned at this stage. Once the dry test is complete the wet testing can begin. This is carried out in our workshop and the plant is tested with full flows through it.
  • 13. CIVILS Infrastructure in any contract within the water industry is essential, it provides the services and structures for the M & E install process. The bespoke reinforced concrete base provides a robust platform which encapsulates the services penetrations to allow mechanical and electrical install to take place directly after the TTU has been placed.
  • 14. TRANSPORTATION Upon completion of the construction and testing, the TTU embarks on the final stage of its journey, to site. It is placed onto ‘skates’ and rolled out of the workshop, it is then lifted onto the back of a 40ft Lo- loader by crane. Once the TTU has been fully secured it leaves for site. This part of its journey has involved a great deal of in-depth logistical planning. Due to the variety of site locations within Scotland tending to be served by B Class roads the logistics route planning and surveying can in itself be extremely challenging.
  • 15. TRANSPORTATION Many sites are on islands or only accessible via ferry, this has to all be planned and programmed into the journey of the TTU. The Units are designed to conform to the maximum width and height allowed on UK roads, without a Police escort. On arrival at site the crane then lifts the TTU onto a concrete slab that has been constructed to mirror the detail of the 3d Model. Once placed onto the slab it is anchored by Eight M30 holding down bolts pre-cast into the slab.
  • 16. COMPLETED TTU After all of the tie-ins have been completed and the remainder of the site work complete the TTU is then ready to be Fully commissioned and be put into its Test Stage.
  • 17. CURRENT RSE SITES Ross-Shire Engineering are currently carrying out work on various sites throughout Scotland. These sites vary in location, size and build type. TTU BUILDS Sheildaig WTW - 150m³ per day Kinlochewe WTW – 150m³ per day Loch katrine WTW – 35m³ per day Stronachlachar WTW – 35m³ per day Kilchoan WTW – 160m³ per day Raasay - 200m³ per day PURPOSE MADE BUILDS Lochcarron WTW – 520m³ per day Unst WTW – 520m³ per day Broadford WTW - 520m³ per day
  • 18. RSE INNOVATIVE DEVELOPMENTS After winning the ‘SCDI Highlands and Islands Business Excellence Award for Excellence in Research and Innovation’. Ross-Shire Engineering has not rested on its laurels, and are currently looking into further developing the design of the TTU to incorporate clear water tanks and chemical waste tanks. This will remove a vast amount of the civil scope of works and will greatly benefit the environment, as well as being even more cost effective. incorporating these two tanks into the building will ensure there is far less disruption to the area within the immediate vicinity of the WTW. These designs are still in their early stages, but are looking extremely positive and will have a massive impact on the amount of site work required at WTW sites in the future.