This document provides summaries of projects and work packages for a construction project. It includes sections on health and safety, organization structure, manpower forecasting, and the program of works. Under the program of works there are subsections detailing planning for civil works on typical levels, structural works, secondary trades, guest rooms, and lifts. It also notes the status of architectural, interior, and MEP designs as well as pending variations to approved work packages.
2. I. HEALTH & SAFETY
II. ORGANIZATION CHART
III.FORECAST CURVE OF MANPOWER
IV. PROGRAM OF WORKS
a) General Planning
b) Planning Civil Works Typical Level
c) Rotation Structural Works Typical Floor
d) Planning Secondary Trades
e) Rotation Guest Room
f) Planning Civil Works Typical Level
2
3. g) Lifts
h) Optional & Excluded Works
i) Design Status
V. FAÇADE: OKYANUS INTRODUCTION
VI. MEP: PROGRESS STATUS BY LEM
3
73. 2014 2015
Today
Aug Sep Oct Nov Dec 2015
1
20 Aug
2
12 Sep
3
23 Sep
4
21 Nov
5
1 Dec
6
23 Dec
7
1 Jan
Groupe Package
Dates acc.
Workshop
09.2014
Milestones
acc.Program
of Works
Remark
1
Access Card Control System & Intruder System
20/08/2014
15/10/2014
BMS 15/10/2014
Car Park Vehicle Counting System 15/10/2014
CCTV System 15/10/2014
Centralized Emergency Exit Management System 15/10/2014
Digital Lighting Control System 15/10/2014
Fire Alarm system 15/10/2014
Intercommunication System -PABX 15/10/2014
Public Address and Sound Sysytems 11/11/2014
15/10/2014Telecommunication System
2
UPS
12/09/2014
15/10/2014
Additional Cubicle on MV SWITCHGEARS 15/10/2014
3
Analogic Clock System
23/09/2014
15/10/2014
ANSUL Suppression System 11/11/2014
FM200 Suppression System 11/11/2014
Kitchen Equipments 15/10/2014
Nurse Call System 15/10/2014
4 UPS Panel Boards 21/11/2014 15/10/2014
5 MV connection 01/12/2014 03/11/2014
6
Generators
23/12/2014
11/11/2014
IP Television 11/11/2014
Totalizing Panel 11/11/2014
7 Scanners & metal Detectors 12/01/2015 12/01/2015
1. Status of Optional Works
Access Card Control System & Intruder System
h) Optional & Excluded Works
Intercommunication System -PABX
Telecommunication System
NOT YET
AWARDED
Analogic Clock System
73
74. 2. Excluded Works (EKO)
f) UPS (for lifts) 2 proposals submitted
g) Bore Hole & Water treatment plant
i) Swimming pool already contracted by EKO
Dates according Program of the Works
h) Sewage treatment plant
b) All services related to medical zones (white partitions, plumbed
partitions,equipments, specific lighting,..)
c) All material and installations related to kitchen zones and restaurant
d) Fixed furnitures (ex. Placards, desks, …hall equipment and sport court)
e) Mobile furnitures (ex.: beds, tables,…)COBEL declined for this Trade
a) Roads, lanscaping and other external works
01.10.2014
01.08.2014
04.07.2014
74
75. Received 26 Aug
Received 04 Sep
Received 07 Nov
2014 2015Aug Sep Oct Nov Dec 2015
Coordinated PRO
2014 as per POW
11 Aug
Today
21 Jan
22 Aug
Layouts
Basement to L08
22 Aug
Layouts L09
to L25
12 Sep
Elevations &
Sections
19
Sep
Stairs and
swimming Pool
26 Sep
External ceilings
and Fences
26 Sep
Other
architectural
drawings
26 SepFire Zoning
Received
Rev.D
23.10.2014
Rev.E still
to be
received
(Status
20.01.15 11:00)
1. Architectural Design PRO 2014
Planned to be received 11.08.2014 acc. POW
f. Design Status
75
76. Received
31.10.2014
Received
07.11.2014
Receive
27.11.2014
2014 2015Aug Sep Oct Nov Dec 2015
Milestone PRO 2014 as per POW
11 Aug
Today
21 Jan
22 Sep - 1 Oct
Serie 200
Flooring
2 Oct - 10 Oct
Serie 300 Flase
Ceilings
22 Sep - 1 Oct
Serie 500 Wall
covering
14 Oct - 24 OctSerie 400 & 600 Part 1
27 Oct - 14 NovSerie 400 & 600 Part 2
17 Nov - 28 NovSerie 400 & 600 Part 3
1 Dec - 12 DecSerie 400 & 600 Part 4
12 DecSerie 700, 800 & 900
1 Oct
Serie
100
2. Interior Design
Planned to be received 30.08.2014 acc. POW
Received
revision
16.01.2015
Except Plumbing
and Sanitary
Fixtures
700: Zoning
800: Access Control
900: Floor Boxes
76
79. 4. Variations Status
1 CEILINGS Verbal Approval
3 WALL COVERING Rejected
11 INTERIOR PAINTS Verbal Approval (No Floor & Wall painting in
Parking)
• QTY & LOCATION OF CEILING TILES 99%HR
a) PRICING TRANSMITTED FOR INTERIOR DESIGN
TO BE CONFIRMED BY EKO:
REVISION ACCORDING TO REVISED ID PACKAGES RECEIVED
22.08.2014 - SUBMITTED 28.10.2014 Rejected
NEW REVISION – SUBMITTED 19.12.2014
(1)VARIATION 4 PACKAGES/14 SUB-PACKAGES SUBMITTED 12.05.2014
2 FLOORINGS & SKIRTINGS Rejected (except alternative rubber
flooring for sport room)
• COLOR OF FLOOR TILES & WALL CERAMICS
• COLOR OF PAINT
• UPDATED ID CONSIDERING THESE CHANGES
• ACCEPTANCE OF VARIATION
16.01.2015
16.01.2015
16.01.2015
79
80. (2)VARIATION 2 PACKAGES SUBMITTED 08.08.2014
RESUBMISSION 27.10.2014 Rejected 16.12.2014
NEW REVISION ( ALTERNATIVE ROCA )SUBMITTED 05.12.2014
13 PLUMBING & SANITARY FIXTURES
14 SANITARY&HOSPITALITY ACCESSORIES
ACCEPTANCE OF VARIATION TO BE CONFIRMED BY EKO
80
81. b) OTHER VARIATIONS SUBMITTED
(1)FACADE NEW WINDOW AT SPORT ROOM
(2)FACADE BULLET PROOF GLASS
(3)FACADE MAINTENANCE PLATFORMS
(4)SWIMMING POOL (STRUCTURAL WORKS ONLY)
81
82. c) PENDING VARIATIONS
5. STONE & SOLID SURFACES Stone Thresholds cancelled
6. PARTITIONS
9. METAL WORKS
10. GLAZING WORKS Waiting updated Work Package
(2)SHAFT ACCESS HATCHES (New Schedule Received 28.08.2014)
(1)ID FINISHES (5, 6, 9 & 10) ACC. UPDATED ID PRO 2014 TO BE RECEIVED
(3)DOORS (Last Revised Schedule Received 17.12.2014) still to be coordinated
with ELV Packages/ waiting for selection of colours
(4)NEW SECURITY ROOM (IN PLACE OF 2 PARKING) Received 20.08.2014 –
waiting design
(5)NEW LAYOUT OF THE BATHROOMS OF THE GUEST ROOMS FROM LEVEL
G+15 TO LEVEL G+24 Received 09.09.2014
(6)FACADES WATERPROOFING SYSTEM
(7)ROOF PAVEMENT According To New Concept Pro 2014 Received
23.10.2014
82
83. (8)DRAINING SCREED AND SLOPES IN BASEMENT According Concept Received
15.10.2014
(10)EXTERNAL WORKS
(9)LIFTS EMERGENCY DOORS According To Arch. File Received 28.10.2014
83