SlideShare une entreprise Scribd logo
1  sur  6
Télécharger pour lire hors ligne
Within the Context of Seveso II, Importance of Risk-Based Inspection in
Oil, Gas and Petrochemical Industry
(XIX World Congress on Safety and Health at Work)
Özlem ÖZKILIÇ
M.Sc., Chemical Engineer
Ministry of Labor and Social Security -Labor Inspector
ASQ- Reliability Expert
Senior Non-Key Expert - EuropeAid Turkey Project -Technical Assistance on Increasing
the Implementation Capacity of the Seveso II Directive Tranning (EuropeAid130724/D
/SER/TR)
After the serious industrial accident happened in Seveso, Italy in 1976, a Directive (82/501/EEC)
has been agreed regarding the accident prevention in industrial installations. Afterwards, two
accidents which happened in Bhopal, India in 1984 and Basel, Switzerland in 1986 have resulted
in the amendment of this directive.
A revised and reviewed Directive on the control of major-accident hazards involving hazardous
substances - 96/82/EC was accepted in 1996 and replaced the Directive 82/501/EEC. Finally,
Directive 2003/105/EC dated 16 December 2003 amending Council Directive 96/82/EC on the
control of major-accident hazards involving hazardous substances has been published. The
Seveso Directive has brought about various control obligations concerning the prevention of
major industrial accidents involving hazardous substances. The plants within scope of the Seveso
Directive are obliged to prepare safety reports and emergency action plans.
As it is known, on the issues of prevention of the large industrial accidents arising from industrial
activities, preparedness against the accidents, intervention in case of the accidents occurring and
integrating European Union Council Directive 96/82/EC (Seveso II Directive) with regard to
control of the major accident risk comprising hazardous chemical substance into the legislation in
Turkey, Harmonization Project of the Seveso II Directive was realized by Ministry of
Environment and Forestry of Republic of Turkey. The Regulation on the Control of Major
Industrial Accidents was completed and published in the Official Gazette dated August 18, 2010
and No. 27676
Seveso Directive requires the preparation of a Major Accident Prevention Policy. This policy
should demonstrate that all the necessary measures have been taken to prevent major accidents
and limit their consequences to persons and the environment. It recognizes that risk cannot
always be completely eliminated, but there is a inversely proportional relationship between the
risk and the measures taken to control the risk.
Preventing the loss of containment system of hazardous substances is often key to avoid major
accidents. It is therefore necessary to take appropriate measures to achieve adequately continuous
integrity of containment equipment (vessels, tanks, pipework etc.). A suitable scheme of in-
service examination can therefore be an important part of the necessary measures to avoid major
accidents, but is not an explicit requirement of the Seveso regulations.
The Oil, Gas and Petrochemical Industry is facing tough challenges regarding risk mitigation to
improve safety and reliability on the one hand cost pressure about the risk mitigation measures on
the other hand. However, in most cases the highest risk is mostly associated with a small
percentage of plant items. These potential high-risk components require a greater degree of
attention than others. Knowing which areas to prioritize becomes paramount. Therefore it is
essential to balance inspection costs and risk through the use of an appropriate technology for
inspection and maintenance planning. One of the best methodologies for providing an effective
inspection and maintenance program is Risk Based Inspection (RBI).
Effective implementation of a Risk Based Inspection program extends the operating life of
equipment and piping, safely and cost effectively. RBI is accepted as good engineering
practice for the implementation of inspection and maintenance programs and has its roots in
Process Safety Management and Mechanical Integrity programs. The objective, principals
and practices of Risk Based Inspection are demonstrated and explained.
What is Risk-Based Inspection Why It is Necessary?
The Control of Major Accident Hazards Regulations (COMAH or Seveso II) cover the control of
major accident hazards at installations as a whole. Such installations may include atmospheric
storage tanks, process pipework and other equipment containing flammable or toxic and other
hazardous materials.
Risk-based inspection refers to the application of risk analysis principles to manage inspection
programs for plant equipment. RBI has been used in the nuclear power generation industry for
some time and is also employed in refineries and petrochemical plant. The ultimate goal of RBI is
to develop a cost-effective inspection and maintenance program that provides assurance of
acceptable mechanical integrity and reliability.
Causes Of Failure
Any unintentional release of stored energy and/or hazardous contents from a pressure system or
containment constitutes a failure. Failure usually involves a breach in the containment boundary
and a release of contents into the environment. In extreme cases, stored energy may be released
as a high pressure jet, missiles, structural collapse or pipe whip and contents may be flammable
and/or toxic.
Root causes of failure of pressure systems, tanks and other containers include:
• Inadequate design and/or material for the loading and operating environment.
• Incorrect and/or defective manufacture.
• Unanticipated in-service deterioration such as corrosion or fatigue cracking.
• System errors in operation or maintenance or over-pressure protection.
• Malfunction of instrumentation, control systems or feed and utility supplies.
• Human factors including deliberate damage.
• External events such as fire, impacts or storms.
Risk Assessment
There are many techniques available for Duty Holders to use to identify accident scenarios. They
differ in the degree of detail to which events leading up to and after the failure are identified and
quantified within a logical structure. The following lists the main specialist techniques that may
be used:
 Hazards and Operability Study (HAZOP)
 Failure Modes and Effects Analysis (FMEA)
 Fault Tree Analysis (FTA)
 Event Tree Analysis (ETA)
 Human Reliability Analysis (HRA)
API Publication 581, a base resource document for Risk Based Inspection is an industry specific
document designed to be applied to the petroleum and chemical process areas. According to the
API 581, it recognizes that a RBI program aims to:
 Define and measure the level of risk associated with an item.
 Evaluate safety, environmental and business interruption risks.
 Reduce risk of failure by the effective use of inspection resources.
According to the API 581,the probability of failure is the mean frequency or rate with which the
specified failure event would be expected to occur in a given period of time, normally one year.
The qualitative approach assesses each plant item with a position in a 5 x 5 risk matrix. The
likelihood of failure is determined from the sum of six weighted factors:
1. Amount of equipment within item.
2. Damage mechanism.
3. Usefulness of inspection.
4. Current equipment condition.
5. Nature of process.
6. Safety design and mechanisms.
The consequence of failure is divided into only two factors:
a) Fire/Explosion.
b) Toxicity.
The general approach of the quantitative analysis is to first establish details on the process, the
equipment and other pertinent information. Risk is then calculated as the product of each
consequence and likelihood for each damage scenario, the total risk for an item being the sum of
all the scenario risks:
According to the API 581, the risk of failure combines the probability of failure with a measure
of the consequences of that failure. If these are evaluated numerically, then the risk is defined as
the product of the probability of failure rate and the measured consequence.
RiskITEM = Σ RiskS
Process of Risk Based Inspection
Many refining and petrochemical plants struggle with a mountain of process safety and
engineering information. This critical information is often scattered in file rooms, drawers or
legacy applications. Compounding the problem are multiple versions of the same information
housed in maintenance, engineering, safety, operations and other functional areas. What’s more,
the information is often recreated and revalidated over and over again by different disciplines
with different needs.
During the RBI process, engineers design inspection strategies (what, when, how to inspect) that
most efficiently match forecasted or observed degradation mechanisms.
Risk Based Inspection (RBI) schemes are a planning tool used to develop the optimum plan for
the execution of inspection activities. RBI uses the findings from a formal risk analysis, such as a
Corrosion Risk Assessment, to guide the direction and emphasis of the inspection planning and
the physical inspection procedures. A risk based approach to inspection planning is used to:
• Ensure risk is reduced to as low as reasonably practicable
• Optimize the inspection schedule
• Focus inspection effort onto the most critical areas
• Identify and use the most appropriate methods of inspection
RBI provides a logical, documented, repeatable methodology for determining the optimum
combination of inspection frequencies and inspection scopes. RBI objective is to ensure focus of
inspection to areas with high risk, while inspection in areas with low risk will be reduced or
excluded from the normal inspection program and therefore result in significant inspection and
maintenance cost reduction.
CONCLUSION
The concept of risk analysis has been around for a long time and Risk Based Inspection (RBI)
programs have generated considerable interest in industry. Risk-Based Inspection is a process
that identifies, assesses and maps industrial risks (due to corrosion and stress cracking), which
can compromise equipment integrity in both pressurized equipment and structural elements. RBI
addresses risks that can be controlled through proper inspections and analysis.
The consequence of failure through the unintentional release of stored energy and hazardous
material is the potential for harm. Duty Holders have a responsibility to assess the potential harm
to the Health and Safety of employees and/or the public, and to the environment from pollution
and other damage. They may also legitimately consider the consequences of failure on their
business, such as the costs of lost production, repair and replacement of equipment and the
damage to of the company reputation.
The inspection program is being developed to reduce that risk. To do this we need to know the
following issues;
 What type of damage to look for?
 Where to look for damage.
 How to look for damage.
 When to look for damage.
An integrated integrity management strategy will contain measures that address and mitigate the
possibility of root causes of failure. Design reviews, manufacturing quality assurance, operating
training, and systems analyses are examples of such measures. In-service inspection is a backstop
to prevent failure when a root cause has led to deterioration from the design intent or the as
manufactured condition.
Although RBI is quite a new concept and not known very well in our country, for the
reasons outlined previously, it should be paid attention and its widely acceptance should be
promoted.
REFERENCES
1. API Publication 581 – Risk Based inspection, Base Resource Document – 1st edition
2000.
2. API Publication 580 – Recommended Practice for Risk Based inspection– 1st edition
2002.
3. HSE, Best Practice for Risk Based Inspection as a part of Plant Integrity
Management, Contract Research Report 363/2001
4. Ramesh J. P., Risk Based Inspection, Middle East Nondestructive Testing Conference
& Exhibition - 27-30 Nov 2005 Bahrain, Manama
öZlem özkiliç  makale - en

Contenu connexe

Tendances

Kp bloch psm preparedness final rev
Kp bloch psm preparedness final revKp bloch psm preparedness final rev
Kp bloch psm preparedness final revAnn-Marie Roche
 
_Process_Safety_Management
_Process_Safety_Management_Process_Safety_Management
_Process_Safety_ManagementEssam Osmaan
 
IRJET- Assessing the Workplace Risk in Food Industry
IRJET-  	  Assessing the Workplace Risk in Food IndustryIRJET-  	  Assessing the Workplace Risk in Food Industry
IRJET- Assessing the Workplace Risk in Food IndustryIRJET Journal
 
Safety management plan by DGMS
Safety management plan by DGMSSafety management plan by DGMS
Safety management plan by DGMSKrishna Deo Prasad
 
The business case for process safety final ppt
The business case for process safety final pptThe business case for process safety final ppt
The business case for process safety final pptorosghe
 
Ep seminar presentation version 2 morgan mar 2013
Ep seminar presentation version 2 morgan mar 2013Ep seminar presentation version 2 morgan mar 2013
Ep seminar presentation version 2 morgan mar 2013Andrew Morgan
 
Hazard assessment and risk management techniques
Hazard assessment and risk management techniquesHazard assessment and risk management techniques
Hazard assessment and risk management techniquesPRANJAY PATIL
 
A real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 ElementsA real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 Elements360factors
 
Health, Safety and Environmental Management Plan
Health, Safety and Environmental Management PlanHealth, Safety and Environmental Management Plan
Health, Safety and Environmental Management PlanFlevy.com Best Practices
 
Process Safety
Process SafetyProcess Safety
Process SafetyConsultivo
 
Elements of Process Safety Management
Elements of Process Safety ManagementElements of Process Safety Management
Elements of Process Safety ManagementShirazeh arghami
 
Application of Combustion Analyzers in Safety Instrumented Systems
Application of Combustion Analyzers in Safety Instrumented SystemsApplication of Combustion Analyzers in Safety Instrumented Systems
Application of Combustion Analyzers in Safety Instrumented SystemsBelilove Company-Engineers
 
PSM RM - Process Safety Management implementation guidance 1
PSM RM - Process Safety Management implementation guidance 1PSM RM - Process Safety Management implementation guidance 1
PSM RM - Process Safety Management implementation guidance 1Process Safety Culture
 
Method for accident and incident analysis
Method for accident and incident analysisMethod for accident and incident analysis
Method for accident and incident analysisDoytchin Doytchev
 
TSA 2011 Pipeline Security Guidelines
TSA 2011 Pipeline Security GuidelinesTSA 2011 Pipeline Security Guidelines
TSA 2011 Pipeline Security GuidelinesJennifer Taylor
 

Tendances (20)

Kp bloch psm preparedness final rev
Kp bloch psm preparedness final revKp bloch psm preparedness final rev
Kp bloch psm preparedness final rev
 
Process safety managment
Process safety managmentProcess safety managment
Process safety managment
 
_Process_Safety_Management
_Process_Safety_Management_Process_Safety_Management
_Process_Safety_Management
 
IRJET- Assessing the Workplace Risk in Food Industry
IRJET-  	  Assessing the Workplace Risk in Food IndustryIRJET-  	  Assessing the Workplace Risk in Food Industry
IRJET- Assessing the Workplace Risk in Food Industry
 
Safety management plan by DGMS
Safety management plan by DGMSSafety management plan by DGMS
Safety management plan by DGMS
 
The business case for process safety final ppt
The business case for process safety final pptThe business case for process safety final ppt
The business case for process safety final ppt
 
Safety (1)
Safety (1)Safety (1)
Safety (1)
 
Ep seminar presentation version 2 morgan mar 2013
Ep seminar presentation version 2 morgan mar 2013Ep seminar presentation version 2 morgan mar 2013
Ep seminar presentation version 2 morgan mar 2013
 
Hazard assessment and risk management techniques
Hazard assessment and risk management techniquesHazard assessment and risk management techniques
Hazard assessment and risk management techniques
 
A real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 ElementsA real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 Elements
 
Health, Safety and Environmental Management Plan
Health, Safety and Environmental Management PlanHealth, Safety and Environmental Management Plan
Health, Safety and Environmental Management Plan
 
Control focused inspection tools (Mark Smith)
Control focused inspection tools (Mark Smith)Control focused inspection tools (Mark Smith)
Control focused inspection tools (Mark Smith)
 
Process Safety
Process SafetyProcess Safety
Process Safety
 
Elements of Process Safety Management
Elements of Process Safety ManagementElements of Process Safety Management
Elements of Process Safety Management
 
Safety Management System SMS
Safety Management System SMSSafety Management System SMS
Safety Management System SMS
 
Application of Combustion Analyzers in Safety Instrumented Systems
Application of Combustion Analyzers in Safety Instrumented SystemsApplication of Combustion Analyzers in Safety Instrumented Systems
Application of Combustion Analyzers in Safety Instrumented Systems
 
PSM RM - Learn from experience
PSM RM - Learn from experiencePSM RM - Learn from experience
PSM RM - Learn from experience
 
PSM RM - Process Safety Management implementation guidance 1
PSM RM - Process Safety Management implementation guidance 1PSM RM - Process Safety Management implementation guidance 1
PSM RM - Process Safety Management implementation guidance 1
 
Method for accident and incident analysis
Method for accident and incident analysisMethod for accident and incident analysis
Method for accident and incident analysis
 
TSA 2011 Pipeline Security Guidelines
TSA 2011 Pipeline Security GuidelinesTSA 2011 Pipeline Security Guidelines
TSA 2011 Pipeline Security Guidelines
 

En vedette

039 Chemnitzer Pilotprojekt für Gehörlose auf Jobsuche.pdf
039 Chemnitzer Pilotprojekt für Gehörlose auf Jobsuche.pdf039 Chemnitzer Pilotprojekt für Gehörlose auf Jobsuche.pdf
039 Chemnitzer Pilotprojekt für Gehörlose auf Jobsuche.pdfunn | UNITED NEWS NETWORK GmbH
 
6th math c1 -l35--dec18
6th math c1 -l35--dec186th math c1 -l35--dec18
6th math c1 -l35--dec18jdurst65
 
F junioren endr_gruppe_1_2
F junioren endr_gruppe_1_2F junioren endr_gruppe_1_2
F junioren endr_gruppe_1_2cillitbang
 
6th math c1 -l38--jan4
6th math c1 -l38--jan46th math c1 -l38--jan4
6th math c1 -l38--jan4jdurst65
 
รูปทรงกลม
รูปทรงกลมรูปทรงกลม
รูปทรงกลมSarun Chaikaew
 
Wall Street Industry Forum - Yeshiva University
Wall Street Industry Forum - Yeshiva UniversityWall Street Industry Forum - Yeshiva University
Wall Street Industry Forum - Yeshiva Universityytwersky
 
7th pre alg -L13--sept14
7th pre alg -L13--sept147th pre alg -L13--sept14
7th pre alg -L13--sept14jdurst65
 
6th math c1 -l33--dec11
6th math c1 -l33--dec116th math c1 -l33--dec11
6th math c1 -l33--dec11jdurst65
 
8th pre alg - L3--aug23
8th pre alg - L3--aug238th pre alg - L3--aug23
8th pre alg - L3--aug23jdurst65
 
6th math c2 -inv5--feb7
6th math c2 -inv5--feb76th math c2 -inv5--feb7
6th math c2 -inv5--feb7jdurst65
 
Bridging work
Bridging workBridging work
Bridging worktori98
 
7th pre alg -L16--sept18
7th pre alg -L16--sept187th pre alg -L16--sept18
7th pre alg -L16--sept18jdurst65
 
background check
background checkbackground check
background checkxilvar
 
งานนำเสนอไม่มีชื่อ
งานนำเสนอไม่มีชื่องานนำเสนอไม่มีชื่อ
งานนำเสนอไม่มีชื่อSupaporn Kanthachan
 
Deutsche Bank Charity Work
Deutsche Bank Charity WorkDeutsche Bank Charity Work
Deutsche Bank Charity Workytwersky
 
Internet Governance in Transition_ The ITU as a Battleground for Rival Visions
Internet Governance in Transition_ The ITU as a Battleground for Rival VisionsInternet Governance in Transition_ The ITU as a Battleground for Rival Visions
Internet Governance in Transition_ The ITU as a Battleground for Rival VisionsCarl Frank
 

En vedette (20)

039 Chemnitzer Pilotprojekt für Gehörlose auf Jobsuche.pdf
039 Chemnitzer Pilotprojekt für Gehörlose auf Jobsuche.pdf039 Chemnitzer Pilotprojekt für Gehörlose auf Jobsuche.pdf
039 Chemnitzer Pilotprojekt für Gehörlose auf Jobsuche.pdf
 
6th math c1 -l35--dec18
6th math c1 -l35--dec186th math c1 -l35--dec18
6th math c1 -l35--dec18
 
Arbeitszeugnis_Budersand
Arbeitszeugnis_BudersandArbeitszeugnis_Budersand
Arbeitszeugnis_Budersand
 
F junioren endr_gruppe_1_2
F junioren endr_gruppe_1_2F junioren endr_gruppe_1_2
F junioren endr_gruppe_1_2
 
6th math c1 -l38--jan4
6th math c1 -l38--jan46th math c1 -l38--jan4
6th math c1 -l38--jan4
 
รูปทรงกลม
รูปทรงกลมรูปทรงกลม
รูปทรงกลม
 
Wall Street Industry Forum - Yeshiva University
Wall Street Industry Forum - Yeshiva UniversityWall Street Industry Forum - Yeshiva University
Wall Street Industry Forum - Yeshiva University
 
world_fuqua
world_fuquaworld_fuqua
world_fuqua
 
7th pre alg -L13--sept14
7th pre alg -L13--sept147th pre alg -L13--sept14
7th pre alg -L13--sept14
 
6th math c1 -l33--dec11
6th math c1 -l33--dec116th math c1 -l33--dec11
6th math c1 -l33--dec11
 
8th pre alg - L3--aug23
8th pre alg - L3--aug238th pre alg - L3--aug23
8th pre alg - L3--aug23
 
Programmheft_OYE_21.01.10.pdf
Programmheft_OYE_21.01.10.pdfProgrammheft_OYE_21.01.10.pdf
Programmheft_OYE_21.01.10.pdf
 
6th math c2 -inv5--feb7
6th math c2 -inv5--feb76th math c2 -inv5--feb7
6th math c2 -inv5--feb7
 
Bridging work
Bridging workBridging work
Bridging work
 
7th pre alg -L16--sept18
7th pre alg -L16--sept187th pre alg -L16--sept18
7th pre alg -L16--sept18
 
background check
background checkbackground check
background check
 
Manifesto 02
Manifesto 02Manifesto 02
Manifesto 02
 
งานนำเสนอไม่มีชื่อ
งานนำเสนอไม่มีชื่องานนำเสนอไม่มีชื่อ
งานนำเสนอไม่มีชื่อ
 
Deutsche Bank Charity Work
Deutsche Bank Charity WorkDeutsche Bank Charity Work
Deutsche Bank Charity Work
 
Internet Governance in Transition_ The ITU as a Battleground for Rival Visions
Internet Governance in Transition_ The ITU as a Battleground for Rival VisionsInternet Governance in Transition_ The ITU as a Battleground for Rival Visions
Internet Governance in Transition_ The ITU as a Battleground for Rival Visions
 

Similaire à öZlem özkiliç makale - en

Risk analysis and environmental hazard management
Risk analysis and environmental hazard managementRisk analysis and environmental hazard management
Risk analysis and environmental hazard managementeSAT Publishing House
 
IRJET - Gap Analysis for Safety Improvements in Chemical Handling
IRJET -  	  Gap Analysis for Safety Improvements in Chemical HandlingIRJET -  	  Gap Analysis for Safety Improvements in Chemical Handling
IRJET - Gap Analysis for Safety Improvements in Chemical HandlingIRJET Journal
 
Safety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxSafety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxalutarep1
 
Safety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxSafety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxalutarep1
 
Environment presentation
Environment presentationEnvironment presentation
Environment presentationJarnail Singh
 
WASHEQ PPT Afternoon session 2011
WASHEQ PPT Afternoon session 2011WASHEQ PPT Afternoon session 2011
WASHEQ PPT Afternoon session 2011Ella Agbettor
 
SGS API580 Risk based Inspection (RBI).pdf
SGS API580 Risk based Inspection (RBI).pdfSGS API580 Risk based Inspection (RBI).pdf
SGS API580 Risk based Inspection (RBI).pdfMuhammadNasirAbbas4
 
Hazard Identification, Risk Assessment And Risk Control In a 250 MW Solar Pow...
Hazard Identification, Risk Assessment And Risk Control In a 250 MW Solar Pow...Hazard Identification, Risk Assessment And Risk Control In a 250 MW Solar Pow...
Hazard Identification, Risk Assessment And Risk Control In a 250 MW Solar Pow...IRJET Journal
 
PROJECT REPORT ACHIEVEMENTS HITESH
PROJECT REPORT ACHIEVEMENTS HITESHPROJECT REPORT ACHIEVEMENTS HITESH
PROJECT REPORT ACHIEVEMENTS HITESHHITESH RATHOD
 
Rel maint-final
Rel maint-finalRel maint-final
Rel maint-finalamar sadi
 
Australian-Offshore-Drilling-Fleet-Transformed-from-OutofCompliance-to-World-...
Australian-Offshore-Drilling-Fleet-Transformed-from-OutofCompliance-to-World-...Australian-Offshore-Drilling-Fleet-Transformed-from-OutofCompliance-to-World-...
Australian-Offshore-Drilling-Fleet-Transformed-from-OutofCompliance-to-World-...Mike Poland, CMRP
 
Application of Lean Tools in the Oil Field Safety Management
Application of Lean Tools in the Oil Field Safety ManagementApplication of Lean Tools in the Oil Field Safety Management
Application of Lean Tools in the Oil Field Safety ManagementIJERA Editor
 
Psm guide 4th edition
Psm guide 4th editionPsm guide 4th edition
Psm guide 4th editionArul Arasu K
 
HAZARD IDENTIFICATION AND RISK ASSESSMENT IN AUTO COMPONENTS MANUFACTURING IN...
HAZARD IDENTIFICATION AND RISK ASSESSMENT IN AUTO COMPONENTS MANUFACTURING IN...HAZARD IDENTIFICATION AND RISK ASSESSMENT IN AUTO COMPONENTS MANUFACTURING IN...
HAZARD IDENTIFICATION AND RISK ASSESSMENT IN AUTO COMPONENTS MANUFACTURING IN...IRJET Journal
 

Similaire à öZlem özkiliç makale - en (20)

risk analysis
 risk analysis risk analysis
risk analysis
 
risk analysis
risk analysisrisk analysis
risk analysis
 
Risk analysis and environmental hazard management
Risk analysis and environmental hazard managementRisk analysis and environmental hazard management
Risk analysis and environmental hazard management
 
IRJET - Gap Analysis for Safety Improvements in Chemical Handling
IRJET -  	  Gap Analysis for Safety Improvements in Chemical HandlingIRJET -  	  Gap Analysis for Safety Improvements in Chemical Handling
IRJET - Gap Analysis for Safety Improvements in Chemical Handling
 
Safety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxSafety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptx
 
Safety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptxSafety Engineering in Project Supervision.pptx
Safety Engineering in Project Supervision.pptx
 
Topic5
Topic5Topic5
Topic5
 
Psm by Ronak
Psm by RonakPsm by Ronak
Psm by Ronak
 
Environment presentation
Environment presentationEnvironment presentation
Environment presentation
 
WASHEQ PPT Afternoon session 2011
WASHEQ PPT Afternoon session 2011WASHEQ PPT Afternoon session 2011
WASHEQ PPT Afternoon session 2011
 
OTC 2015 LCE Paper
OTC 2015 LCE PaperOTC 2015 LCE Paper
OTC 2015 LCE Paper
 
SGS API580 Risk based Inspection (RBI).pdf
SGS API580 Risk based Inspection (RBI).pdfSGS API580 Risk based Inspection (RBI).pdf
SGS API580 Risk based Inspection (RBI).pdf
 
Hazard Identification, Risk Assessment And Risk Control In a 250 MW Solar Pow...
Hazard Identification, Risk Assessment And Risk Control In a 250 MW Solar Pow...Hazard Identification, Risk Assessment And Risk Control In a 250 MW Solar Pow...
Hazard Identification, Risk Assessment And Risk Control In a 250 MW Solar Pow...
 
PROJECT REPORT ACHIEVEMENTS HITESH
PROJECT REPORT ACHIEVEMENTS HITESHPROJECT REPORT ACHIEVEMENTS HITESH
PROJECT REPORT ACHIEVEMENTS HITESH
 
Rel maint-final
Rel maint-finalRel maint-final
Rel maint-final
 
HAZOP
HAZOPHAZOP
HAZOP
 
Australian-Offshore-Drilling-Fleet-Transformed-from-OutofCompliance-to-World-...
Australian-Offshore-Drilling-Fleet-Transformed-from-OutofCompliance-to-World-...Australian-Offshore-Drilling-Fleet-Transformed-from-OutofCompliance-to-World-...
Australian-Offshore-Drilling-Fleet-Transformed-from-OutofCompliance-to-World-...
 
Application of Lean Tools in the Oil Field Safety Management
Application of Lean Tools in the Oil Field Safety ManagementApplication of Lean Tools in the Oil Field Safety Management
Application of Lean Tools in the Oil Field Safety Management
 
Psm guide 4th edition
Psm guide 4th editionPsm guide 4th edition
Psm guide 4th edition
 
HAZARD IDENTIFICATION AND RISK ASSESSMENT IN AUTO COMPONENTS MANUFACTURING IN...
HAZARD IDENTIFICATION AND RISK ASSESSMENT IN AUTO COMPONENTS MANUFACTURING IN...HAZARD IDENTIFICATION AND RISK ASSESSMENT IN AUTO COMPONENTS MANUFACTURING IN...
HAZARD IDENTIFICATION AND RISK ASSESSMENT IN AUTO COMPONENTS MANUFACTURING IN...
 

Dernier

University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projectssmsksolar
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 

Dernier (20)

University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 

öZlem özkiliç makale - en

  • 1. Within the Context of Seveso II, Importance of Risk-Based Inspection in Oil, Gas and Petrochemical Industry (XIX World Congress on Safety and Health at Work) Özlem ÖZKILIÇ M.Sc., Chemical Engineer Ministry of Labor and Social Security -Labor Inspector ASQ- Reliability Expert Senior Non-Key Expert - EuropeAid Turkey Project -Technical Assistance on Increasing the Implementation Capacity of the Seveso II Directive Tranning (EuropeAid130724/D /SER/TR) After the serious industrial accident happened in Seveso, Italy in 1976, a Directive (82/501/EEC) has been agreed regarding the accident prevention in industrial installations. Afterwards, two accidents which happened in Bhopal, India in 1984 and Basel, Switzerland in 1986 have resulted in the amendment of this directive. A revised and reviewed Directive on the control of major-accident hazards involving hazardous substances - 96/82/EC was accepted in 1996 and replaced the Directive 82/501/EEC. Finally, Directive 2003/105/EC dated 16 December 2003 amending Council Directive 96/82/EC on the control of major-accident hazards involving hazardous substances has been published. The Seveso Directive has brought about various control obligations concerning the prevention of major industrial accidents involving hazardous substances. The plants within scope of the Seveso Directive are obliged to prepare safety reports and emergency action plans. As it is known, on the issues of prevention of the large industrial accidents arising from industrial activities, preparedness against the accidents, intervention in case of the accidents occurring and integrating European Union Council Directive 96/82/EC (Seveso II Directive) with regard to control of the major accident risk comprising hazardous chemical substance into the legislation in Turkey, Harmonization Project of the Seveso II Directive was realized by Ministry of Environment and Forestry of Republic of Turkey. The Regulation on the Control of Major
  • 2. Industrial Accidents was completed and published in the Official Gazette dated August 18, 2010 and No. 27676 Seveso Directive requires the preparation of a Major Accident Prevention Policy. This policy should demonstrate that all the necessary measures have been taken to prevent major accidents and limit their consequences to persons and the environment. It recognizes that risk cannot always be completely eliminated, but there is a inversely proportional relationship between the risk and the measures taken to control the risk. Preventing the loss of containment system of hazardous substances is often key to avoid major accidents. It is therefore necessary to take appropriate measures to achieve adequately continuous integrity of containment equipment (vessels, tanks, pipework etc.). A suitable scheme of in- service examination can therefore be an important part of the necessary measures to avoid major accidents, but is not an explicit requirement of the Seveso regulations. The Oil, Gas and Petrochemical Industry is facing tough challenges regarding risk mitigation to improve safety and reliability on the one hand cost pressure about the risk mitigation measures on the other hand. However, in most cases the highest risk is mostly associated with a small percentage of plant items. These potential high-risk components require a greater degree of attention than others. Knowing which areas to prioritize becomes paramount. Therefore it is essential to balance inspection costs and risk through the use of an appropriate technology for inspection and maintenance planning. One of the best methodologies for providing an effective inspection and maintenance program is Risk Based Inspection (RBI). Effective implementation of a Risk Based Inspection program extends the operating life of equipment and piping, safely and cost effectively. RBI is accepted as good engineering practice for the implementation of inspection and maintenance programs and has its roots in Process Safety Management and Mechanical Integrity programs. The objective, principals and practices of Risk Based Inspection are demonstrated and explained. What is Risk-Based Inspection Why It is Necessary? The Control of Major Accident Hazards Regulations (COMAH or Seveso II) cover the control of major accident hazards at installations as a whole. Such installations may include atmospheric storage tanks, process pipework and other equipment containing flammable or toxic and other hazardous materials. Risk-based inspection refers to the application of risk analysis principles to manage inspection programs for plant equipment. RBI has been used in the nuclear power generation industry for some time and is also employed in refineries and petrochemical plant. The ultimate goal of RBI is to develop a cost-effective inspection and maintenance program that provides assurance of acceptable mechanical integrity and reliability. Causes Of Failure Any unintentional release of stored energy and/or hazardous contents from a pressure system or containment constitutes a failure. Failure usually involves a breach in the containment boundary and a release of contents into the environment. In extreme cases, stored energy may be released
  • 3. as a high pressure jet, missiles, structural collapse or pipe whip and contents may be flammable and/or toxic. Root causes of failure of pressure systems, tanks and other containers include: • Inadequate design and/or material for the loading and operating environment. • Incorrect and/or defective manufacture. • Unanticipated in-service deterioration such as corrosion or fatigue cracking. • System errors in operation or maintenance or over-pressure protection. • Malfunction of instrumentation, control systems or feed and utility supplies. • Human factors including deliberate damage. • External events such as fire, impacts or storms. Risk Assessment There are many techniques available for Duty Holders to use to identify accident scenarios. They differ in the degree of detail to which events leading up to and after the failure are identified and quantified within a logical structure. The following lists the main specialist techniques that may be used:  Hazards and Operability Study (HAZOP)  Failure Modes and Effects Analysis (FMEA)  Fault Tree Analysis (FTA)  Event Tree Analysis (ETA)  Human Reliability Analysis (HRA) API Publication 581, a base resource document for Risk Based Inspection is an industry specific document designed to be applied to the petroleum and chemical process areas. According to the API 581, it recognizes that a RBI program aims to:  Define and measure the level of risk associated with an item.  Evaluate safety, environmental and business interruption risks.  Reduce risk of failure by the effective use of inspection resources. According to the API 581,the probability of failure is the mean frequency or rate with which the specified failure event would be expected to occur in a given period of time, normally one year. The qualitative approach assesses each plant item with a position in a 5 x 5 risk matrix. The likelihood of failure is determined from the sum of six weighted factors: 1. Amount of equipment within item. 2. Damage mechanism. 3. Usefulness of inspection. 4. Current equipment condition. 5. Nature of process. 6. Safety design and mechanisms. The consequence of failure is divided into only two factors:
  • 4. a) Fire/Explosion. b) Toxicity. The general approach of the quantitative analysis is to first establish details on the process, the equipment and other pertinent information. Risk is then calculated as the product of each consequence and likelihood for each damage scenario, the total risk for an item being the sum of all the scenario risks: According to the API 581, the risk of failure combines the probability of failure with a measure of the consequences of that failure. If these are evaluated numerically, then the risk is defined as the product of the probability of failure rate and the measured consequence. RiskITEM = Σ RiskS Process of Risk Based Inspection Many refining and petrochemical plants struggle with a mountain of process safety and engineering information. This critical information is often scattered in file rooms, drawers or legacy applications. Compounding the problem are multiple versions of the same information housed in maintenance, engineering, safety, operations and other functional areas. What’s more, the information is often recreated and revalidated over and over again by different disciplines with different needs. During the RBI process, engineers design inspection strategies (what, when, how to inspect) that most efficiently match forecasted or observed degradation mechanisms. Risk Based Inspection (RBI) schemes are a planning tool used to develop the optimum plan for the execution of inspection activities. RBI uses the findings from a formal risk analysis, such as a Corrosion Risk Assessment, to guide the direction and emphasis of the inspection planning and the physical inspection procedures. A risk based approach to inspection planning is used to: • Ensure risk is reduced to as low as reasonably practicable • Optimize the inspection schedule • Focus inspection effort onto the most critical areas • Identify and use the most appropriate methods of inspection RBI provides a logical, documented, repeatable methodology for determining the optimum combination of inspection frequencies and inspection scopes. RBI objective is to ensure focus of inspection to areas with high risk, while inspection in areas with low risk will be reduced or excluded from the normal inspection program and therefore result in significant inspection and maintenance cost reduction. CONCLUSION The concept of risk analysis has been around for a long time and Risk Based Inspection (RBI) programs have generated considerable interest in industry. Risk-Based Inspection is a process that identifies, assesses and maps industrial risks (due to corrosion and stress cracking), which
  • 5. can compromise equipment integrity in both pressurized equipment and structural elements. RBI addresses risks that can be controlled through proper inspections and analysis. The consequence of failure through the unintentional release of stored energy and hazardous material is the potential for harm. Duty Holders have a responsibility to assess the potential harm to the Health and Safety of employees and/or the public, and to the environment from pollution and other damage. They may also legitimately consider the consequences of failure on their business, such as the costs of lost production, repair and replacement of equipment and the damage to of the company reputation. The inspection program is being developed to reduce that risk. To do this we need to know the following issues;  What type of damage to look for?  Where to look for damage.  How to look for damage.  When to look for damage. An integrated integrity management strategy will contain measures that address and mitigate the possibility of root causes of failure. Design reviews, manufacturing quality assurance, operating training, and systems analyses are examples of such measures. In-service inspection is a backstop to prevent failure when a root cause has led to deterioration from the design intent or the as manufactured condition. Although RBI is quite a new concept and not known very well in our country, for the reasons outlined previously, it should be paid attention and its widely acceptance should be promoted. REFERENCES 1. API Publication 581 – Risk Based inspection, Base Resource Document – 1st edition 2000. 2. API Publication 580 – Recommended Practice for Risk Based inspection– 1st edition 2002. 3. HSE, Best Practice for Risk Based Inspection as a part of Plant Integrity Management, Contract Research Report 363/2001 4. Ramesh J. P., Risk Based Inspection, Middle East Nondestructive Testing Conference & Exhibition - 27-30 Nov 2005 Bahrain, Manama