SlideShare une entreprise Scribd logo
1  sur  46
Presentation TitlePaul Eastwood HarrisEastwood Harris Pty Ltd24 July 2010 The most comprehensive Oracle applications & technology content under one roof
Purpose of the Presentation To demonstrate the P6 Version 7 bars functions, To suggest some solutions for bar formatting issues and Demonstrate some other tricks and traps.
Topics TRICKY P6 FUNCTIONS Remove Float on a Completed Activities Remove Relationships on a Baseline Bar How to Create a Summary Bar Remove Negative Float on a Complete Activity Why is Negative Float showing when it should not Summary Duration Calculations Baseline Bar showing when no baseline is set TECHNIQUES Bars without Successors are critical Multiple Project Float Calculation Start or End Float Activity Durations with Resources Cash Flow with Expenses
HOW TO REMOVE FLOAT FROM A COMPLETED ACTIVITY By default a Total Float bar is displayed on a completed task, but the Float value is set to “Null”, this is not logical:
HOW TO REMOVE FLOAT FROM A COMPLETED ACTIVITY To remove this set the filter on the Float Bar in the in the Bars form to be Not Started or In Progress:
HOW TO REMOVE FLOAT FROM A COMPLETED ACTIVITY
REMOVE RELATIONSHIPS FROM A BASELINE BAR  To remove relationships on the Baseline bar, move in to the Baseline bars to the bottom of the Bars form:
HOW TO CREATE A SUMMARY BAR To create a new summary bar you will see that you can not select Summary from the filter drop down box:
HOW TO CREATE A SUMMARY BAR Open to the Bars form, Bar Settings tab and select Show bar for grouping bands:
NEGATIVE FLOAT SHOULD NOT BE SHOWING Why do I have one day Negative Float:
NEGATIVE FLOAT SHOULD NOT BE SHOWING Always show the time when scheduling as P6 does not have a default start or finish time and often selects 00:00, at the start of the day, as the time when setting actuals or constraints:
A GAP BETWEEN THE DATA DATE AND ACTIVITY BAR When an activity is complete the Early Start and Early Finish are set to the Data Date, 12 Oct at midnight, NOT to the Actual Start as in many other products,  When an activity is in progress the Early Start is set to the Activity calendar Start Date and Time NOT to the Actual Start as in many other products. To prevent this set the Data Date to the Activity Calendar Start Date:
HOW DO SUMMARY DURATIONS CALCULATE What Bars are these?
Database Default Calendar, WBS and Project Durations– Version 6.2 & Earlier  The durations of all bands such as Project, WBS, and Resources are calculated from: The Database Default Calendar and  The Hours/Day setting in the Edit, User Preferences…, Time Units tab.  The following picture show the duration of the workshop used in this publication set at firstly 5 days per week, 8 hours per day and a duration of 35 days with an Hours/Day setting of 8 hours.
Database Default Calendar, WBS and Project Durations – Version 6.2 & Earlier ,[object Object]
The duration of the Project Summary WBS Nodes are also clearly misleading, the Research Node is not 31 days long.,[object Object]
Calculation of Activity Duration in Days – Version 7 In earlier version of P6 the calculation of the durations in hours for all calendars was set either by the Administrator in  Admin, Admin Preferences…, Time Periods tab or by the User in the Edit, User Preferences…, Time Units tab.  Primavera  Version 7 has removed these two options above and has created of a new calendar function for each titled Hours per Time Period:
Calculation of Activity Duration in Days – Version 7 The picture below has the Project Default calendar set as the 8hr/d & 5d/w and the picture shows that when the calendars are different then the Project Default calendar is used to calculate the summary duration for WBS Nodes, Projects etc:
WHY IS A BASELINE BAR DISPLAYED WHEN NO BASELINE SET This issue is due to the planned dates, Bar Owl!
Planned Dates The Planned Dates are very complex and their calculation method is outlined in the book, in summary: When an activity is Complete or In-progress they match the status of the schedule before the last update,  When an activity has Not Started they match the Early Start and Early Finish.
Planned Dates Issues The Planned Dates are dates that most schedulers would not want displayed, These dates are displayed as the Project Baseline bars and Primary User Baseline bars when no baseline has been assigned, You must be sure that all users set their Primary User Baseline baselines before they display the bars.
Bar Refaeli Scheduling OptionsMake Open Ends Critical
Make Open-ended Activities Critical Activities without a successor as displayed as critical when they have float, this option makes the Late Dates equal the Early Dates when an activity has no successor. Open-ends Not Critical: ,[object Object],[object Object],[object Object]
Opened projects,[object Object]
Finish Float = Late Finish – Early Finish
Smallest of Start Float and Finish Float
Note: It can be seen from the pictures above that the Total Float bar only displays the Finish Float. ,[object Object]
When it is switched ON the resource durations are linked to the activity duration:,[object Object]
Resource Lag A Resource may be assigned a Lag, the duration from the start of the activity to the point at which the Resource commences work,  In the following example the Activity Duration is 12 days, which is calculated from Angela Lowe’s Resource Original Lag of 7 days and Resource Original Duration of 5 days:
COST MANAGEMENT USING WBS ACTIVITIES AND EXPENSES P6 was developed without the ability to catch and collect costs at WBS Node, Many software packages do collect costs at WBS Node which includes SAP, This section will outline how one can use WBS Activities and Expenses to manage costs collected by another system and imported into P6.
Set Up the User Definable Fields In order to import cost at WBS Node I suggest: ,[object Object]
Assign Costs to Expenses, then you will not run into issues such as the Cost zeroing out when the Remaining Duration equals Zero as may happen with resources.
P6 Expenses only have Budget, Actual, Remaining and At Completion cost fields.
Costs have a number of elements, including Budget, Committed, Received, Quality Checked, Invoices, Outstanding Commitment against contracts and orders, Unallocated WBS funds (Remaining Contingency).  These may all not be recorded in the Expense Costs Fields,[object Object]
Costs in the Expense User Definable Fields may then be Global Changed into the appropriate Expense field for reporting and comparing to the Baseline.
Set up Activity User Definable Fields to import the costs into to display the costs in columns as Expense User Definable Fields may not be displayed in Gant chart columns.
Both the Expense User Definable Fields and the Activity User Definable Fields are identical and the costs end up in three places, Expense Costs, Expense User Definable Fields and Activity User Definable Fields.,[object Object]
Expense Costs fields which are populated by a Global Change from the Expense User Definable Fields
Activity User Definable Fields allowing costs to be show in Gantt Chart Columns.,[object Object]
The Activity and Expense are identical,
The “PO” prefix keeps the order in the database and keeps the fields together.,[object Object]
Expense Costs fields which are populated by a Global Change from the Expense User Definable Fields
Activity User Definable Fields allowing costs to be show in Gantt Chart Columns.,[object Object]
Export the UDS Fields to Excel Export the Activity and Expense UDF Fields to Excel to be populated and import, create a template as per below, Filter just on WBS Activities:
Update the Spread Sheet & Import The Activity and Expenses Spread Sheet will both have exactly the same fields, Populate one TASK sheet and Copy & Paste to the PROJCOST sheet, Import the data:
Review Data Review the data, the costs should be assigned against the Activity UDFs and the Expense UDFs:

Contenu connexe

Tendances

MS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for YouMS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for YouCA Technologies
 
Configuring Primavera Team Member for Project Updates
Configuring Primavera Team Member for Project UpdatesConfiguring Primavera Team Member for Project Updates
Configuring Primavera Team Member for Project Updatesp6academy
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricksp6academy
 
Importance of Microsoft Project and Primavera
Importance of Microsoft Project and Primavera Importance of Microsoft Project and Primavera
Importance of Microsoft Project and Primavera Sagar Tilwani
 
100632 p6 v7 tricks and traps
100632 p6 v7 tricks and traps100632 p6 v7 tricks and traps
100632 p6 v7 tricks and trapsInSync Conference
 
Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorialKetut Swandana
 
Primavera Project Management P6 Course session 2
Primavera Project Management P6 Course session 2Primavera Project Management P6 Course session 2
Primavera Project Management P6 Course session 2Mohamed Adel
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project WorkshopEder Alves
 
204460 create s curve reports
204460 create s curve reports204460 create s curve reports
204460 create s curve reportsp6academy
 
Building Formulas And Dashboard In Ms Project
Building Formulas And Dashboard In Ms ProjectBuilding Formulas And Dashboard In Ms Project
Building Formulas And Dashboard In Ms ProjectRelu Rosenberg
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013Ong-Art Sanpinit
 
Project management by MS Project 2010
Project management by MS Project 2010Project management by MS Project 2010
Project management by MS Project 2010Wadhwani Foundation
 
Create bar chart report for p6 r8.3 using bi publisher 11g - Oracle Primavera...
Create bar chart report for p6 r8.3 using bi publisher 11g - Oracle Primavera...Create bar chart report for p6 r8.3 using bi publisher 11g - Oracle Primavera...
Create bar chart report for p6 r8.3 using bi publisher 11g - Oracle Primavera...p6academy
 
Ms project management
Ms  project managementMs  project management
Ms project managementchinunki4
 

Tendances (20)

MS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for YouMS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for You
 
Configuring Primavera Team Member for Project Updates
Configuring Primavera Team Member for Project UpdatesConfiguring Primavera Team Member for Project Updates
Configuring Primavera Team Member for Project Updates
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
 
Importance of Microsoft Project and Primavera
Importance of Microsoft Project and Primavera Importance of Microsoft Project and Primavera
Importance of Microsoft Project and Primavera
 
100632 p6 v7 tricks and traps
100632 p6 v7 tricks and traps100632 p6 v7 tricks and traps
100632 p6 v7 tricks and traps
 
Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorial
 
Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners
 
Oracle Primavera Team member 8.3
Oracle Primavera Team member 8.3Oracle Primavera Team member 8.3
Oracle Primavera Team member 8.3
 
Primavera Project Management P6 Course session 2
Primavera Project Management P6 Course session 2Primavera Project Management P6 Course session 2
Primavera Project Management P6 Course session 2
 
MS Project
MS Project MS Project
MS Project
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
204460 create s curve reports
204460 create s curve reports204460 create s curve reports
204460 create s curve reports
 
Building Formulas And Dashboard In Ms Project
Building Formulas And Dashboard In Ms ProjectBuilding Formulas And Dashboard In Ms Project
Building Formulas And Dashboard In Ms Project
 
Dashboard reporting
Dashboard reporting Dashboard reporting
Dashboard reporting
 
Primavera P6 Online Training
Primavera  P6 Online TrainingPrimavera  P6 Online Training
Primavera P6 Online Training
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013
 
Project management by MS Project 2010
Project management by MS Project 2010Project management by MS Project 2010
Project management by MS Project 2010
 
Create bar chart report for p6 r8.3 using bi publisher 11g - Oracle Primavera...
Create bar chart report for p6 r8.3 using bi publisher 11g - Oracle Primavera...Create bar chart report for p6 r8.3 using bi publisher 11g - Oracle Primavera...
Create bar chart report for p6 r8.3 using bi publisher 11g - Oracle Primavera...
 
Ms project management
Ms  project managementMs  project management
Ms project management
 
SAP PS overview
SAP PS overviewSAP PS overview
SAP PS overview
 

En vedette

Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dateskrunalplanning
 
Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2danieljohn810
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Charlie Jackson
 
Building the perfect schedule (v5)(notes)
Building the perfect schedule (v5)(notes)Building the perfect schedule (v5)(notes)
Building the perfect schedule (v5)(notes)Glen Alleman
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleGlen Alleman
 
Integrated Master Schedule
Integrated Master ScheduleIntegrated Master Schedule
Integrated Master Scheduleellefsonj
 
Primavera project planner
Primavera project plannerPrimavera project planner
Primavera project plannerRahul
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2Abdelhay Ghanem
 
Primavera P6 Reports Tab Samples
Primavera P6 Reports Tab SamplesPrimavera P6 Reports Tab Samples
Primavera P6 Reports Tab SamplesTen Six Consulting
 
Primavera Project Management
Primavera Project ManagementPrimavera Project Management
Primavera Project ManagementTotalSoft
 

En vedette (14)

Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dates
 
P6 tips tricks-client
P6 tips tricks-clientP6 tips tricks-client
P6 tips tricks-client
 
Activity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in PrimaveraActivity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in Primavera
 
Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Building the perfect schedule (v5)(notes)
Building the perfect schedule (v5)(notes)Building the perfect schedule (v5)(notes)
Building the perfect schedule (v5)(notes)
 
Integrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master ScheduleIntegrated Master Plan and Integrated Master Schedule
Integrated Master Plan and Integrated Master Schedule
 
Integrated Master Schedule
Integrated Master ScheduleIntegrated Master Schedule
Integrated Master Schedule
 
Primavera project planner
Primavera project plannerPrimavera project planner
Primavera project planner
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
Primavera P6 Reports Tab Samples
Primavera P6 Reports Tab SamplesPrimavera P6 Reports Tab Samples
Primavera P6 Reports Tab Samples
 
Introduction, development and analysis of banana curve in project management....
Introduction, development and analysis of banana curve in project management....Introduction, development and analysis of banana curve in project management....
Introduction, development and analysis of banana curve in project management....
 
Primavera Project Management
Primavera Project ManagementPrimavera Project Management
Primavera Project Management
 
Primavera p6 v8.2 session 1
Primavera p6 v8.2 session 1Primavera p6 v8.2 session 1
Primavera p6 v8.2 session 1
 

Similaire à P6 Version 7 Tricks and Traps

Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingSHAZEBALIKHAN1
 
Project management
Project managementProject management
Project managementervinod
 
110918_P6_Cost Management_with_Expenses.pdf
110918_P6_Cost Management_with_Expenses.pdf110918_P6_Cost Management_with_Expenses.pdf
110918_P6_Cost Management_with_Expenses.pdfAbdulfeta7
 
Odoo project management_casestudy
Odoo project management_casestudyOdoo project management_casestudy
Odoo project management_casestudyRishi Pujara
 
Ms project presentation
Ms project presentationMs project presentation
Ms project presentationKhem Singh
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentationFarrukh Raja
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project PresentationKhem Singh
 
dokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptxdokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptxSunilHotkar2
 
ms-project-presentation.pptx
ms-project-presentation.pptxms-project-presentation.pptx
ms-project-presentation.pptxSunilHotkar2
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxcarolinef5
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxdonaldp2
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguideJason Koo
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide성철 박
 
Project Share Feature List - MS Project Services
Project Share Feature List - MS Project ServicesProject Share Feature List - MS Project Services
Project Share Feature List - MS Project Servicesmahyars
 
Odoo 13 project management
Odoo 13 project managementOdoo 13 project management
Odoo 13 project managementPlanetOdoo
 

Similaire à P6 Version 7 Tricks and Traps (20)

Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01
 
MS Project 2010 Training
MS Project 2010 TrainingMS Project 2010 Training
MS Project 2010 Training
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
 
Project management
Project managementProject management
Project management
 
110918_P6_Cost Management_with_Expenses.pdf
110918_P6_Cost Management_with_Expenses.pdf110918_P6_Cost Management_with_Expenses.pdf
110918_P6_Cost Management_with_Expenses.pdf
 
Odoo project management_casestudy
Odoo project management_casestudyOdoo project management_casestudy
Odoo project management_casestudy
 
Ms project presentation
Ms project presentationMs project presentation
Ms project presentation
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentation
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
 
MS Project Guide.pdf
MS Project Guide.pdfMS Project Guide.pdf
MS Project Guide.pdf
 
ASANA ppt
ASANA pptASANA ppt
ASANA ppt
 
dokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptxdokumen.tips_ms-project-presentation.pptx
dokumen.tips_ms-project-presentation.pptx
 
ms-project-presentation.pptx
ms-project-presentation.pptxms-project-presentation.pptx
ms-project-presentation.pptx
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
 
Oracle Primavera P6 PRO R8 Tips & tricks
Oracle Primavera P6 PRO R8 Tips & tricksOracle Primavera P6 PRO R8 Tips & tricks
Oracle Primavera P6 PRO R8 Tips & tricks
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide
 
Project Share Feature List - MS Project Services
Project Share Feature List - MS Project ServicesProject Share Feature List - MS Project Services
Project Share Feature List - MS Project Services
 
Odoo 13 project management
Odoo 13 project managementOdoo 13 project management
Odoo 13 project management
 

Plus de InSync Conference

Frank munz oracle fusion middleware and aws cloud services in sync11
Frank munz oracle fusion middleware and aws cloud services in sync11Frank munz oracle fusion middleware and aws cloud services in sync11
Frank munz oracle fusion middleware and aws cloud services in sync11InSync Conference
 
Pythian MySQL - database for the web based economy
Pythian   MySQL - database for the web based economyPythian   MySQL - database for the web based economy
Pythian MySQL - database for the web based economyInSync Conference
 
IBM and Oracle Joint Solution Centre
IBM and Oracle Joint Solution CentreIBM and Oracle Joint Solution Centre
IBM and Oracle Joint Solution CentreInSync Conference
 
In Sync Running Apps On Oracle
In Sync  Running Apps On OracleIn Sync  Running Apps On Oracle
In Sync Running Apps On OracleInSync Conference
 
Oracle Fusion Middleware for JD Edwards
Oracle Fusion Middleware for JD EdwardsOracle Fusion Middleware for JD Edwards
Oracle Fusion Middleware for JD EdwardsInSync Conference
 
In sync10 cliffgodwin-ebs-final
In sync10 cliffgodwin-ebs-finalIn sync10 cliffgodwin-ebs-final
In sync10 cliffgodwin-ebs-finalInSync Conference
 
In sync10 cliffgodwin-appskeynote-final
In sync10 cliffgodwin-appskeynote-finalIn sync10 cliffgodwin-appskeynote-final
In sync10 cliffgodwin-appskeynote-finalInSync Conference
 
Optim Insync10 Paul Griffin presentation
Optim Insync10 Paul Griffin presentationOptim Insync10 Paul Griffin presentation
Optim Insync10 Paul Griffin presentationInSync Conference
 
Nswh Insync 2010 Ammar Customer Presentation
Nswh Insync 2010 Ammar Customer PresentationNswh Insync 2010 Ammar Customer Presentation
Nswh Insync 2010 Ammar Customer PresentationInSync Conference
 
Insync10 IBM JDE Sol Ed Announcement
Insync10 IBM JDE Sol Ed AnnouncementInsync10 IBM JDE Sol Ed Announcement
Insync10 IBM JDE Sol Ed AnnouncementInSync Conference
 
InSync10 Implement JDE Financial Analytics and Make Better Decisions
InSync10  Implement JDE Financial Analytics and Make Better DecisionsInSync10  Implement JDE Financial Analytics and Make Better Decisions
InSync10 Implement JDE Financial Analytics and Make Better DecisionsInSync Conference
 
Ebs operational reporting at santos evaluation, selection & implementation
Ebs operational reporting at santos evaluation, selection & implementationEbs operational reporting at santos evaluation, selection & implementation
Ebs operational reporting at santos evaluation, selection & implementationInSync Conference
 
Santos change management utility, our alternative to application change manag...
Santos change management utility, our alternative to application change manag...Santos change management utility, our alternative to application change manag...
Santos change management utility, our alternative to application change manag...InSync Conference
 

Plus de InSync Conference (20)

Frank munz oracle fusion middleware and aws cloud services in sync11
Frank munz oracle fusion middleware and aws cloud services in sync11Frank munz oracle fusion middleware and aws cloud services in sync11
Frank munz oracle fusion middleware and aws cloud services in sync11
 
Pythian MySQL - database for the web based economy
Pythian   MySQL - database for the web based economyPythian   MySQL - database for the web based economy
Pythian MySQL - database for the web based economy
 
IBM and Oracle Joint Solution Centre
IBM and Oracle Joint Solution CentreIBM and Oracle Joint Solution Centre
IBM and Oracle Joint Solution Centre
 
In Sync Running Apps On Oracle
In Sync  Running Apps On OracleIn Sync  Running Apps On Oracle
In Sync Running Apps On Oracle
 
P6 analytics
P6 analyticsP6 analytics
P6 analytics
 
Upk presentation insync
Upk presentation insync Upk presentation insync
Upk presentation insync
 
Oracle Fusion Middleware for JD Edwards
Oracle Fusion Middleware for JD EdwardsOracle Fusion Middleware for JD Edwards
Oracle Fusion Middleware for JD Edwards
 
In sync10 grc_suite
In sync10 grc_suiteIn sync10 grc_suite
In sync10 grc_suite
 
In sync10 cliffgodwin-ebs-final
In sync10 cliffgodwin-ebs-finalIn sync10 cliffgodwin-ebs-final
In sync10 cliffgodwin-ebs-final
 
In sync10 cliffgodwin-appskeynote-final
In sync10 cliffgodwin-appskeynote-finalIn sync10 cliffgodwin-appskeynote-final
In sync10 cliffgodwin-appskeynote-final
 
Mnod linsync10 oba
Mnod linsync10 obaMnod linsync10 oba
Mnod linsync10 oba
 
D linsync10 ofa5yrs
D linsync10 ofa5yrsD linsync10 ofa5yrs
D linsync10 ofa5yrs
 
D linsync10 fusaapps
D linsync10 fusaappsD linsync10 fusaapps
D linsync10 fusaapps
 
Optim Insync10 Paul Griffin presentation
Optim Insync10 Paul Griffin presentationOptim Insync10 Paul Griffin presentation
Optim Insync10 Paul Griffin presentation
 
Nswh Insync 2010 Ammar Customer Presentation
Nswh Insync 2010 Ammar Customer PresentationNswh Insync 2010 Ammar Customer Presentation
Nswh Insync 2010 Ammar Customer Presentation
 
Insync10 IBM JDE Sol Ed Announcement
Insync10 IBM JDE Sol Ed AnnouncementInsync10 IBM JDE Sol Ed Announcement
Insync10 IBM JDE Sol Ed Announcement
 
InSync10 Implement JDE Financial Analytics and Make Better Decisions
InSync10  Implement JDE Financial Analytics and Make Better DecisionsInSync10  Implement JDE Financial Analytics and Make Better Decisions
InSync10 Implement JDE Financial Analytics and Make Better Decisions
 
Life after upgrading to r12
Life after upgrading to r12Life after upgrading to r12
Life after upgrading to r12
 
Ebs operational reporting at santos evaluation, selection & implementation
Ebs operational reporting at santos evaluation, selection & implementationEbs operational reporting at santos evaluation, selection & implementation
Ebs operational reporting at santos evaluation, selection & implementation
 
Santos change management utility, our alternative to application change manag...
Santos change management utility, our alternative to application change manag...Santos change management utility, our alternative to application change manag...
Santos change management utility, our alternative to application change manag...
 

Dernier

UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfNirmal Dwivedi
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docxPoojaSen20
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfPoh-Sun Goh
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseAnaAcapella
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfSherif Taha
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701bronxfugly43
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17Celine George
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 
Third Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxThird Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxAmita Gupta
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxheathfieldcps1
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSCeline George
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 

Dernier (20)

UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Third Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxThird Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptx
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 

P6 Version 7 Tricks and Traps

  • 1. Presentation TitlePaul Eastwood HarrisEastwood Harris Pty Ltd24 July 2010 The most comprehensive Oracle applications & technology content under one roof
  • 2. Purpose of the Presentation To demonstrate the P6 Version 7 bars functions, To suggest some solutions for bar formatting issues and Demonstrate some other tricks and traps.
  • 3. Topics TRICKY P6 FUNCTIONS Remove Float on a Completed Activities Remove Relationships on a Baseline Bar How to Create a Summary Bar Remove Negative Float on a Complete Activity Why is Negative Float showing when it should not Summary Duration Calculations Baseline Bar showing when no baseline is set TECHNIQUES Bars without Successors are critical Multiple Project Float Calculation Start or End Float Activity Durations with Resources Cash Flow with Expenses
  • 4. HOW TO REMOVE FLOAT FROM A COMPLETED ACTIVITY By default a Total Float bar is displayed on a completed task, but the Float value is set to “Null”, this is not logical:
  • 5. HOW TO REMOVE FLOAT FROM A COMPLETED ACTIVITY To remove this set the filter on the Float Bar in the in the Bars form to be Not Started or In Progress:
  • 6. HOW TO REMOVE FLOAT FROM A COMPLETED ACTIVITY
  • 7. REMOVE RELATIONSHIPS FROM A BASELINE BAR To remove relationships on the Baseline bar, move in to the Baseline bars to the bottom of the Bars form:
  • 8. HOW TO CREATE A SUMMARY BAR To create a new summary bar you will see that you can not select Summary from the filter drop down box:
  • 9. HOW TO CREATE A SUMMARY BAR Open to the Bars form, Bar Settings tab and select Show bar for grouping bands:
  • 10. NEGATIVE FLOAT SHOULD NOT BE SHOWING Why do I have one day Negative Float:
  • 11. NEGATIVE FLOAT SHOULD NOT BE SHOWING Always show the time when scheduling as P6 does not have a default start or finish time and often selects 00:00, at the start of the day, as the time when setting actuals or constraints:
  • 12. A GAP BETWEEN THE DATA DATE AND ACTIVITY BAR When an activity is complete the Early Start and Early Finish are set to the Data Date, 12 Oct at midnight, NOT to the Actual Start as in many other products, When an activity is in progress the Early Start is set to the Activity calendar Start Date and Time NOT to the Actual Start as in many other products. To prevent this set the Data Date to the Activity Calendar Start Date:
  • 13. HOW DO SUMMARY DURATIONS CALCULATE What Bars are these?
  • 14. Database Default Calendar, WBS and Project Durations– Version 6.2 & Earlier The durations of all bands such as Project, WBS, and Resources are calculated from: The Database Default Calendar and The Hours/Day setting in the Edit, User Preferences…, Time Units tab. The following picture show the duration of the workshop used in this publication set at firstly 5 days per week, 8 hours per day and a duration of 35 days with an Hours/Day setting of 8 hours.
  • 15.
  • 16.
  • 17. Calculation of Activity Duration in Days – Version 7 In earlier version of P6 the calculation of the durations in hours for all calendars was set either by the Administrator in Admin, Admin Preferences…, Time Periods tab or by the User in the Edit, User Preferences…, Time Units tab. Primavera Version 7 has removed these two options above and has created of a new calendar function for each titled Hours per Time Period:
  • 18. Calculation of Activity Duration in Days – Version 7 The picture below has the Project Default calendar set as the 8hr/d & 5d/w and the picture shows that when the calendars are different then the Project Default calendar is used to calculate the summary duration for WBS Nodes, Projects etc:
  • 19. WHY IS A BASELINE BAR DISPLAYED WHEN NO BASELINE SET This issue is due to the planned dates, Bar Owl!
  • 20. Planned Dates The Planned Dates are very complex and their calculation method is outlined in the book, in summary: When an activity is Complete or In-progress they match the status of the schedule before the last update, When an activity has Not Started they match the Early Start and Early Finish.
  • 21. Planned Dates Issues The Planned Dates are dates that most schedulers would not want displayed, These dates are displayed as the Project Baseline bars and Primary User Baseline bars when no baseline has been assigned, You must be sure that all users set their Primary User Baseline baselines before they display the bars.
  • 22. Bar Refaeli Scheduling OptionsMake Open Ends Critical
  • 23.
  • 24.
  • 25. Finish Float = Late Finish – Early Finish
  • 26. Smallest of Start Float and Finish Float
  • 27.
  • 28.
  • 29. Resource Lag A Resource may be assigned a Lag, the duration from the start of the activity to the point at which the Resource commences work, In the following example the Activity Duration is 12 days, which is calculated from Angela Lowe’s Resource Original Lag of 7 days and Resource Original Duration of 5 days:
  • 30. COST MANAGEMENT USING WBS ACTIVITIES AND EXPENSES P6 was developed without the ability to catch and collect costs at WBS Node, Many software packages do collect costs at WBS Node which includes SAP, This section will outline how one can use WBS Activities and Expenses to manage costs collected by another system and imported into P6.
  • 31.
  • 32. Assign Costs to Expenses, then you will not run into issues such as the Cost zeroing out when the Remaining Duration equals Zero as may happen with resources.
  • 33. P6 Expenses only have Budget, Actual, Remaining and At Completion cost fields.
  • 34.
  • 35. Costs in the Expense User Definable Fields may then be Global Changed into the appropriate Expense field for reporting and comparing to the Baseline.
  • 36. Set up Activity User Definable Fields to import the costs into to display the costs in columns as Expense User Definable Fields may not be displayed in Gant chart columns.
  • 37.
  • 38. Expense Costs fields which are populated by a Global Change from the Expense User Definable Fields
  • 39.
  • 40. The Activity and Expense are identical,
  • 41.
  • 42. Expense Costs fields which are populated by a Global Change from the Expense User Definable Fields
  • 43.
  • 44. Export the UDS Fields to Excel Export the Activity and Expense UDF Fields to Excel to be populated and import, create a template as per below, Filter just on WBS Activities:
  • 45. Update the Spread Sheet & Import The Activity and Expenses Spread Sheet will both have exactly the same fields, Populate one TASK sheet and Copy & Paste to the PROJCOST sheet, Import the data:
  • 46. Review Data Review the data, the costs should be assigned against the Activity UDFs and the Expense UDFs:
  • 47. Global Change UDF into Expense Columns Depending on what cost you want put where run a Global Change like the one below:
  • 48. Review Data The UDF Values for Activities and Expenses should be the same:
  • 49.
  • 50. Questions Any Bar questions.
  • 51. Thank you for attending theEastwood Harris Pty LtdPrimavera P6Version 7TRICKS AND TRAPS PRESENTATIONCopyright of Eastwood Harris Pty Ltd
  • 52. Tell us what you think… http://feedback.insync10.com.au