Information Technology Project
Management, Seventh Edition
Note: See the text itself for full citations.
Copyright 2014
 Describe an overall framework for project
integration management as it relates to the other
project management knowledge areas and the
project life cycle
 Discuss the strategic planning process and apply
different project selection methods
 Explain the importance of creating a project charter
to formally initiate projects
 Describe project management plan development,
understand the content of these plans, and review
approaches for creating them
Information Technology Project
Management, Seventh Edition 2
Copyright 2014
 Explain project execution, its relationship to project
planning, the factors related to successful results, and
tools and techniques to assist in directing and
managing project work
 Describe the process of monitoring and controlling a
project
 Understand the integrated change control process,
planning for and managing changes on information
technology (IT) projects, and developing and using a
change control system
 Explain the importance of developing and following
good procedures for closing projects
 Describe how software can assist in project integration
management
Information Technology Project
Management, Seventh Edition 3
Copyright 2014
 Project managers must coordinate all of the other
knowledge areas throughout a project’s life cycle
 Many new project managers have trouble looking
at the “big picture” and want to focus on too many
details (See opening case for a real example)
 Project integration management is not the same
thing as software integration
Information Technology Project
Management, Seventh Edition 4
Copyright 2014
 1. Developing the project charter involves working
with stakeholders to create the document that
formally authorizes a project—the charter.
 2. Developing the project management plan
involves coordinating all planning efforts to create a
consistent, coherent document—the project
management plan.
 3. Directing and managing project work involves
carrying out the project management plan by
performing the activities included in it.
Information Technology Project
Management, Seventh Edition 5
Copyright 2014
 Monitoring and controlling project work involves
overseeing activities to meet the performance
objectives of the project
 Performing integrated change control involves
identifying, evaluating, and managing changes
throughout the project life cycle.
 Closing the project or phase involves finalizing all
activities to formally close the project or phase.
Information Technology Project
Management, Seventh Edition 6
Copyright 2014
Information Technology Project
Management, Seventh Edition 7
Copyright 2014
 The Airbus A380 megajet project was two years behind
schedule in Oct. 2006, causing Airbus’ parent company to
face an expected loss of $6.1 billion over the next four years
 The project suffered from severe integration management
problems, or “integration disintegration...Early this year,
when pre-assembled bundles containing hundreds of miles
of cabin wiring were delivered from a German factory to the
assembly line in France, workers discovered that the
bundles, called harnesses, didn't fit properly into the plane.
Assembly slowed to a near-standstill, as workers tried to
pull the bundles apart and re-thread them through the
fuselage. Now Airbus will have to go back to the drawing
board and redesign the wiring system.”*
Information Technology Project
Management, Seventh Edition 8
*Matlack, Carol. “First, Blame the Software,” BusinessWeek Online (October 5, 2006).
Copyright 2014
 Strategic planning involves determining long-term
objectives, predicting future trends, and projecting
the need for new products and services
 Organizations often perform a SWOT analysis
◦ analyzing Strengths, Weaknesses, Opportunities, and
Threats
 As part of strategic planning, organizations
◦ identify potential projects
◦ use realistic methods to select which projects to work on
◦ formalize project initiation by issuing a project charter
Information Technology Project
Management, Seventh Edition 9
Copyright 2014
Information Technology Project
Management, Seventh Edition 10
Copyright 2014
Information Technology Project
Management, Seventh Edition 11
Copyright 2014
 Only one in seven product concepts comes to fruition. Why is
it that some companies, like Proctor & Gamble, Johnson and
Johnson, Hewlett Packard, and Sony are consistently
successful in NPD? Because they use a disciplined,
systematic approach to NPD projects based on best practices
 Four important forces behind NPD success include the
following:
1. A product innovation and technology strategy for the business
2. Resource commitment and focusing on the right projects, or solid
portfolio management
3. An effective, flexible and streamlined idea-to-launch process
4. The right climate and culture for innovation, true cross-functional
teams, and senior management commitment to NPD
Information Technology Project
Management, Seventh Edition 12
Copyright 2014
 There are usually more projects than available
time and resources to implement them
 Methods for selecting projects include:
◦ focusing on broad organizational needs
◦ categorizing information technology projects
◦ performing net present value or other financial
analyses
◦ using a weighted scoring model
◦ implementing a balanced scorecard
Information Technology Project
Management, Seventh Edition 13
Copyright 2014
 It is often difficult to provide strong justification for
many IT projects, but everyone agrees they have
a high value
 “It is better to measure gold roughly than to count
pennies precisely”
 Three important criteria for projects:
◦ There is a need for the project
◦ There are funds available
◦ There’s a strong will to make the project succeed
Information Technology Project
Management, Seventh Edition 14
Copyright 2014
 One categorization is whether the project
addresses
◦ a problem
◦ an opportunity, or
◦ a directive
 Another categorization is how long it will take to do
and when it is needed
 Another is the overall priority of the project
Information Technology Project
Management, Seventh Edition 15
Copyright 2014
 Financial considerations are often an important
consideration in selecting projects
 Three primary methods for determining the projected
financial value of projects:
◦ Net present value (NPV) analysis
◦ Return on investment (ROI)
◦ Payback analysis
Information Technology Project
Management, Seventh Edition 16
Copyright 2014
 Net present value (NPV) analysis is a method of
calculating the expected net monetary gain or loss
from a project by discounting all expected future
cash inflows and outflows to the present point in
time
 Projects with a positive NPV should be considered if
financial value is a key criterion
 The higher the NPV, the better
Information Technology Project
Management, Seventh Edition 17
Copyright 2014
Information Technology Project
Management, Seventh Edition 18
Copyright 2014
Information Technology Project
Management, Seventh Edition 19
Note: See the template called business_case_financials.xls
Copyright 2014
 Determine estimated costs and benefits for the life
of the project and the products it produces
 Determine the discount rate (check with your
organization on what to use)
 Calculate the NPV (see text for details)
 Notes: Some organizations consider the
investment year as year 0, while others start in year
1. Some people entered costs as negative
numbers, while others do not. Check with your
organization for their preferences
Information Technology Project
Management, Seventh Edition 20
Copyright 2014
 Return on investment (ROI) is calculated by
subtracting the project costs from the benefits and
then dividing by the costs
ROI = (total discounted benefits - total discounted costs) /
discounted costs
 The higher the ROI, the better
 Many organizations have a required rate of return
or minimum acceptable rate of return on investment
for projects
 Internal rate of return (IRR) can by calculated by
finding the discount rate that makes the NPV equal
to zero
Information Technology Project
Management, Seventh Edition 21
Copyright 2014
 Another important financial consideration is
payback analysis
 The payback period is the amount of time it will
take to recoup, in the form of net cash inflows,
the total dollars invested in a project
 Payback occurs when the net cumulative
discounted benefits equals the costs
 Many organizations want IT projects to have a
fairly short payback period
Information Technology Project
Management, Seventh Edition 22
Copyright 2014
Information Technology Project
Management, Seventh Edition 23
Copyright 2014
 A weighted scoring model is a tool that provides a
systematic process for selecting projects based on
many criteria
 Identify criteria important to the project selection process
 Assign weights (percentages) to each criterion so they add
up to 100%
 Assign scores to each criterion for each project
 Multiply the scores by the weights and get the total
weighted scores
 The higher the weighted score, the better
Information Technology Project
Management, Seventh Edition 24
Copyright 2014
Information Technology Project
Management, Seventh Edition 25
Copyright 2014
 Drs. Robert Kaplan and David Norton developed
this approach to help select and manage projects
that align with business strategy
 A balanced scorecard
◦ is a methodology that converts an organization’s value
drivers, such as customer service, innovation, operational
efficiency, and financial performance, to a series of defined
metrics
 See www.balancedscorecard.org for more
information
Information Technology Project
Management, Seventh Edition 26
Copyright 2014
Information Technology Project
Management, Seventh Edition 27
Copyright 2014
 After deciding what project to work on, it is
important to let the rest of the organization know
 A project charter is a document that formally
recognizes the existence of a project and
provides direction on the project’s objectives and
management
 Key project stakeholders should sign a project
charter to acknowledge agreement on the need
and intent of the project; a signed charter is a key
output of project integration management
Information Technology Project
Management, Seventh Edition 28
Copyright 2014
 A project statement of work
 A business case
 Agreements
 Enterprise environmental factors
 Organizational process assets, which include
formal and informal plans, policies, procedures,
guidelines, information systems, financial systems,
management systems, lessons learned, and
historical information
Information Technology Project
Management, Seventh Edition 29
Copyright 2014
Information Technology Project
Management, Seventh Edition 30
Copyright 2014
Information Technology Project
Management, Seventh Edition 31
Copyright 2014
 A project management plan is a document used
to coordinate all project planning documents and
help guide a project’s execution and control
 Plans created in the other knowledge areas are
subsidiary parts of the overall project
management plan
Information Technology Project
Management, Seventh Edition 32
Copyright 2014
 Introduction or overview of the project
 Description of how the project is organized
 Management and technical processes used on
the project
 Work to be done, schedule, and budget
information
Information Technology Project
Management, Seventh Edition 33
Copyright 2014
Information Technology Project
Management, Seventh Edition 34
Copyright 2014
"The winners clearly spell out what needs to be done in a
project, by whom, when, and how. For this they use an
integrated toolbox, including PM tools, methods, and
techniques…If a scheduling template is developed and used
over and over, it becomes a repeatable action that leads to
higher productivity and lower uncertainty. Sure, using
scheduling templates is neither a breakthrough nor a feat.
But laggards exhibited almost no use of the templates.
Rather, in constructing schedules their project managers
started with a clean sheet, a clear waste of time.“*
Information Technology Project
Management, Seventh Edition 35
*Milosevic, Dragan and And Ozbay. “Delivering Projects: What the Winners Do.”
Proceedings of the Project Management Institute Annual Seminars & Symposium
(November 2001).
Copyright 2014
 Involves managing and performing the work
described in the project management plan
 The majority of time and money is usually spent
on execution
 The application area of the project directly affects
project execution because the products of the
project are produced during execution
Information Technology Project
Management, Seventh Edition 36
Copyright 2014
 Project planning and execution are intertwined
and inseparable activities
 Those who will do the work should help to plan the
work
 Project managers must solicit input from the team
to develop realistic plans
Information Technology Project
Management, Seventh Edition 37
Copyright 2014
 Project managers must lead by example to
demonstrate the importance of creating and then
following good project plans
 Organizational culture can help project execution by
◦ providing guidelines and templates
◦ tracking performance based on plans
 Project managers may still need to break the rules
to meet project goals, and senior managers must
support those actions
Information Technology Project
Management, Seventh Edition 38
Copyright 2014
 It is often helpful for IT project managers to have
prior technical experience
 On small projects, the project manager may be
required to perform some of the technical work or
mentor team members to complete the projects
 On large projects, the project manager must
understand the business and application area of
the project
Information Technology Project
Management, Seventh Edition 39
Copyright 2014
 Expert judgment: Experts can help project managers and
their teams make many decisions related to project
execution
 Meetings: Meetings allow people to develop relationships,
pick up on important body language or tone of voice, and
have a dialogue to help resolve problems.
 Project management information systems: There are
hundreds of project management software products
available on the market today, and many organizations are
moving toward powerful enterprise project management
systems that are accessible via the Internet
 See the What Went Right? example of Kuala Lumpur’s
Integrated Transport Information System on p. 169
Information Technology Project
Management, Seventh Edition 40
Copyright 2014
 Changes are inevitable on most projects, so it’s
important to develop and follow a process to
monitor and control changes
 Monitoring project work includes collecting,
measuring, and disseminating performance
information
 A baseline is the approved project management
plan plus approved changes
Information Technology Project
Management, Seventh Edition 41
Copyright 2014
 The 2002 Olympic Winter Games and Paralympics took five
years to plan and cost more than $1.9 billion. PMI awarded the
Salt Lake Organizing Committee (SLOC) the Project of the Year
award for delivering world-class games.
 Four years before the Games began, the SLOC used a
Primavera software-based system with a cascading color-
coded WBS to integrate planning…The SLOC also used an
Executive Roadmap, a one-page list of the top 100 Games-
wide activities, to keep executives apprised of progress.
Activities were tied to detailed project information within each
department’s schedule. A 90-day highlighter showed which
managers were accountable for each integrated activity.
 Fraser Bullock, SLOC Chief Operating Officer and Chief,
said, “We knew when we were on and off schedule and where
we had to apply additional resources. The interrelation of the
functions meant they could not run in isolation—it was a
smoothly running machine.”*
Information Technology Project
Management, Seventh Edition 42
*Foti, Ross, “The Best Winter Olympics, Period,” PM Network (January 2004) 23.
Copyright 2014
 Three main objectives are:
◦ Influencing the factors that create changes to
ensure that changes are beneficial
◦ Determining that a change has occurred
◦ Managing actual changes as they occur
Information Technology Project
Management, Seventh Edition 43
Copyright 2014
 Former view: The project team should strive to do
exactly what was planned on time and within
budget
 Problem: Stakeholders rarely agreed up-front on
the project scope, and time and cost estimates
were inaccurate
 Modern view: Project management is a process of
constant communication and negotiation
 Solution: Changes are often beneficial, and the
project team should plan for them
Information Technology Project
Management, Seventh Edition 44
Copyright 2014
 A change control system is a formal, documented
process that describes when and how official
project documents and work may be changed
 Describes who is authorized to make changes and
how to make them
Information Technology Project
Management, Seventh Edition 45
Copyright 2014
 A change control board is a formal group of
people responsible for approving or rejecting
changes on a project
 CCBs provide guidelines for preparing change
requests, evaluate change requests, and manage
the implementation of approved changes
 Includes stakeholders from the entire organization
Information Technology Project
Management, Seventh Edition 46
Copyright 2014
 Some CCBs only meet occasionally, so it may
take too long for changes to occur
 Some organizations have policies in place for
time-sensitive changes
◦ “48-hour policy” allows project team members to make
decisions, then they have 48 hours to reverse the
decision pending senior management approval
◦ Delegate changes to the lowest level possible, but keep
everyone informed of changes
Information Technology Project
Management, Seventh Edition 47
Copyright 2014
 Rapid changes in technology, such as the increased
use of mobile roaming for communications, often
cause governments around the world to take action.
 Incompatible hardware, software, and networks can
make communications difficult in some regions, and a
lack of competition can cause prices to soar.
 Fortunately, a group called the Organisation for
Economic Co-operation and Development (OECD)
promotes policies that will improve the economic and
social well-being of people around the world.
 In February 2012, the OECD called upon its members’
governments to boost competition in international
mobile roaming markets.
Information Technology Project
Management, Seventh Edition 48
Copyright 2014
 Configuration management ensures that the
descriptions of the project’s products are correct
and complete
 Involves identifying and controlling the functional
and physical design characteristics of products
and their support documentation
 Configuration management specialists identify
and document configuration requirements, control
changes, record and report changes, and audit
the products to verify conformance to
requirements
 See www.icmhq.com for more information
Information Technology Project
Management, Seventh Edition 49
Copyright 2014
Information Technology Project
Management, Seventh Edition 50
Copyright 2014
 To close a project or phase, you must finalize all
activities and transfer the completed or cancelled
work to the appropriate people
 Main outputs include
◦ Final product, service, or result transition
◦ Organizational process asset updates
Information Technology Project
Management, Seventh Edition 51
Copyright 2014
 Several types of software can be used to assist in
project integration management
◦ Documents can be created with word processing software
◦ Presentations are created with presentation software
◦ Tracking can be done with spreadsheets or databases
◦ Communication software like e-mail and Web authoring
tools facilitate communications
◦ Project management software can pull everything together
and show detailed and summarized information
◦ Business Service Management (BSM) tools track the
execution of business process flows
Information Technology Project
Management, Seventh Edition 52
Copyright 2014
Information Technology Project
Management, Seventh Edition 53
Source: www.projectmanager.com
Copyright 2014
 Project integration management involves
coordinating all of the other knowledge areas
throughout a project’s life cycle
 Main processes include
◦ Develop the project charter
◦ Develop the project management plan
◦ Direct and manage project execution
◦ Monitor and control project work
◦ Perform integrated change control
◦ Close the project or phase
Information Technology Project
Management, Seventh Edition 54

Contenu connexe

Tendances

Information Technology Project Management
Information Technology Project ManagementInformation Technology Project Management
Information Technology Project Management
Goutama Bachtiar
 
Information Technology Project Management - part 09
Information Technology Project Management - part 09Information Technology Project Management - part 09
Information Technology Project Management - part 09
Rizwan Khurram
 

Tendances (20)

Information Technology Project Management
Information Technology Project ManagementInformation Technology Project Management
Information Technology Project Management
 
Information Technology Project Management - part 09
Information Technology Project Management - part 09Information Technology Project Management - part 09
Information Technology Project Management - part 09
 
Information Technology Project Management - part 07
Information Technology Project Management - part 07Information Technology Project Management - part 07
Information Technology Project Management - part 07
 
Chap03 the project management process groups
Chap03 the project management process groupsChap03 the project management process groups
Chap03 the project management process groups
 
Chapter 3: The Project Management Process Groups: A Case Study
Chapter 3:The Project Management Process Groups: A Case StudyChapter 3:The Project Management Process Groups: A Case Study
Chapter 3: The Project Management Process Groups: A Case Study
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
 
Project management IT Project Management
Project management IT Project Management Project management IT Project Management
Project management IT Project Management
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
The project management process groups a case study
The project management process groups a case studyThe project management process groups a case study
The project management process groups a case study
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project Communications Management - PMBOK6
Project Communications Management - PMBOK6Project Communications Management - PMBOK6
Project Communications Management - PMBOK6
 
PMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource managementPMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource management
 
Chapter 2
Chapter 2Chapter 2
Chapter 2
 
Project management process groups case study
Project management process groups case studyProject management process groups case study
Project management process groups case study
 
Project communication management
Project communication  managementProject communication  management
Project communication management
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
 
Project governance
Project governanceProject governance
Project governance
 
10 project management knowledge areas
10 project management knowledge areas10 project management knowledge areas
10 project management knowledge areas
 

Similaire à Information Technology Project Management - part 04

Chapter 2 The Project Management and Information Technology Context.ppt
Chapter 2 The Project Management and Information Technology Context.pptChapter 2 The Project Management and Information Technology Context.ppt
Chapter 2 The Project Management and Information Technology Context.ppt
AhmadTawfigAlRadaide
 
Project management chapter 4 - project integration management-1
Project management   chapter 4 - project integration management-1Project management   chapter 4 - project integration management-1
Project management chapter 4 - project integration management-1
Eduardo Antero
 
Chapter 1 Introduction to Project Management.ppt
Chapter 1 Introduction to Project Management.pptChapter 1 Introduction to Project Management.ppt
Chapter 1 Introduction to Project Management.ppt
AhmadTawfigAlRadaide
 
Project Planning, Execution And Closure Essay
Project Planning, Execution And Closure EssayProject Planning, Execution And Closure Essay
Project Planning, Execution And Closure Essay
Jennifer Letterman
 
Chapter 07 project cost management
Chapter 07 project cost managementChapter 07 project cost management
Chapter 07 project cost management
Sara Kharono
 

Similaire à Information Technology Project Management - part 04 (20)

ch04.ppt
ch04.pptch04.ppt
ch04.ppt
 
Project integration management
Project integration managementProject integration management
Project integration management
 
Ch04
Ch04Ch04
Ch04
 
المحاضرة الرابعة والخامسة
المحاضرة الرابعة والخامسةالمحاضرة الرابعة والخامسة
المحاضرة الرابعة والخامسة
 
project management process groups
project management process groupsproject management process groups
project management process groups
 
Ch04
Ch04Ch04
Ch04
 
Lecture 2
Lecture 2Lecture 2
Lecture 2
 
Chapter 2 The Project Management and Information Technology Context.ppt
Chapter 2 The Project Management and Information Technology Context.pptChapter 2 The Project Management and Information Technology Context.ppt
Chapter 2 The Project Management and Information Technology Context.ppt
 
chapter-4 cost mngt.pptx
chapter-4 cost mngt.pptxchapter-4 cost mngt.pptx
chapter-4 cost mngt.pptx
 
Project management chapter 4 - project integration management-1
Project management   chapter 4 - project integration management-1Project management   chapter 4 - project integration management-1
Project management chapter 4 - project integration management-1
 
5 - Project Scope Management.pptx
5 - Project Scope Management.pptx5 - Project Scope Management.pptx
5 - Project Scope Management.pptx
 
Chapter 1 Introduction to Project Management.ppt
Chapter 1 Introduction to Project Management.pptChapter 1 Introduction to Project Management.ppt
Chapter 1 Introduction to Project Management.ppt
 
Schwalbe-07ProjectCost.ppt
Schwalbe-07ProjectCost.pptSchwalbe-07ProjectCost.ppt
Schwalbe-07ProjectCost.ppt
 
Introduction.ppt
Introduction.pptIntroduction.ppt
Introduction.ppt
 
Schwalbe 07 projectcost
Schwalbe 07 projectcostSchwalbe 07 projectcost
Schwalbe 07 projectcost
 
Project Planning, Execution And Closure Essay
Project Planning, Execution And Closure EssayProject Planning, Execution And Closure Essay
Project Planning, Execution And Closure Essay
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
01 itpm6
01 itpm601 itpm6
01 itpm6
 
Project Time Managment.pptx
Project Time Managment.pptxProject Time Managment.pptx
Project Time Managment.pptx
 
Chapter 07 project cost management
Chapter 07 project cost managementChapter 07 project cost management
Chapter 07 project cost management
 

Plus de Rizwan Khurram

Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
Rizwan Khurram
 
Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
Rizwan Khurram
 
Total employee involvement
Total employee involvementTotal employee involvement
Total employee involvement
Rizwan Khurram
 
Objectives., mission and vision
Objectives., mission and visionObjectives., mission and vision
Objectives., mission and vision
Rizwan Khurram
 
New microsoft word document
New microsoft word documentNew microsoft word document
New microsoft word document
Rizwan Khurram
 
Jinnah hospital,lahore (1)
Jinnah hospital,lahore (1)Jinnah hospital,lahore (1)
Jinnah hospital,lahore (1)
Rizwan Khurram
 

Plus de Rizwan Khurram (20)

Exploring the risk factors associated with peb projects in lahore.
Exploring the risk factors associated with peb projects in lahore.Exploring the risk factors associated with peb projects in lahore.
Exploring the risk factors associated with peb projects in lahore.
 
Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
 
Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
 
Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
 
Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
 
Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
 
Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
 
Strategic Delivery of Change Management
Strategic Delivery of Change Management Strategic Delivery of Change Management
Strategic Delivery of Change Management
 
Vision and mission
Vision and missionVision and mission
Vision and mission
 
Total employee involvement
Total employee involvementTotal employee involvement
Total employee involvement
 
Performance measures
Performance measuresPerformance measures
Performance measures
 
Objectives., mission and vision
Objectives., mission and visionObjectives., mission and vision
Objectives., mission and vision
 
New microsoft word document
New microsoft word documentNew microsoft word document
New microsoft word document
 
Jinnah hospital,lahore (1)
Jinnah hospital,lahore (1)Jinnah hospital,lahore (1)
Jinnah hospital,lahore (1)
 
Introduction to tqm
Introduction to tqmIntroduction to tqm
Introduction to tqm
 
Customer satisfaction
Customer satisfactionCustomer satisfaction
Customer satisfaction
 
Cost of quality
Cost of qualityCost of quality
Cost of quality
 
Mission and vission
Mission and vissionMission and vission
Mission and vission
 
Heizer supp 11
Heizer supp 11Heizer supp 11
Heizer supp 11
 
Heizer supp 07
Heizer supp 07Heizer supp 07
Heizer supp 07
 

Dernier

Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
negromaestrong
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
QucHHunhnh
 

Dernier (20)

Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptx
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 

Information Technology Project Management - part 04

  • 1. Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
  • 2. Copyright 2014  Describe an overall framework for project integration management as it relates to the other project management knowledge areas and the project life cycle  Discuss the strategic planning process and apply different project selection methods  Explain the importance of creating a project charter to formally initiate projects  Describe project management plan development, understand the content of these plans, and review approaches for creating them Information Technology Project Management, Seventh Edition 2
  • 3. Copyright 2014  Explain project execution, its relationship to project planning, the factors related to successful results, and tools and techniques to assist in directing and managing project work  Describe the process of monitoring and controlling a project  Understand the integrated change control process, planning for and managing changes on information technology (IT) projects, and developing and using a change control system  Explain the importance of developing and following good procedures for closing projects  Describe how software can assist in project integration management Information Technology Project Management, Seventh Edition 3
  • 4. Copyright 2014  Project managers must coordinate all of the other knowledge areas throughout a project’s life cycle  Many new project managers have trouble looking at the “big picture” and want to focus on too many details (See opening case for a real example)  Project integration management is not the same thing as software integration Information Technology Project Management, Seventh Edition 4
  • 5. Copyright 2014  1. Developing the project charter involves working with stakeholders to create the document that formally authorizes a project—the charter.  2. Developing the project management plan involves coordinating all planning efforts to create a consistent, coherent document—the project management plan.  3. Directing and managing project work involves carrying out the project management plan by performing the activities included in it. Information Technology Project Management, Seventh Edition 5
  • 6. Copyright 2014  Monitoring and controlling project work involves overseeing activities to meet the performance objectives of the project  Performing integrated change control involves identifying, evaluating, and managing changes throughout the project life cycle.  Closing the project or phase involves finalizing all activities to formally close the project or phase. Information Technology Project Management, Seventh Edition 6
  • 7. Copyright 2014 Information Technology Project Management, Seventh Edition 7
  • 8. Copyright 2014  The Airbus A380 megajet project was two years behind schedule in Oct. 2006, causing Airbus’ parent company to face an expected loss of $6.1 billion over the next four years  The project suffered from severe integration management problems, or “integration disintegration...Early this year, when pre-assembled bundles containing hundreds of miles of cabin wiring were delivered from a German factory to the assembly line in France, workers discovered that the bundles, called harnesses, didn't fit properly into the plane. Assembly slowed to a near-standstill, as workers tried to pull the bundles apart and re-thread them through the fuselage. Now Airbus will have to go back to the drawing board and redesign the wiring system.”* Information Technology Project Management, Seventh Edition 8 *Matlack, Carol. “First, Blame the Software,” BusinessWeek Online (October 5, 2006).
  • 9. Copyright 2014  Strategic planning involves determining long-term objectives, predicting future trends, and projecting the need for new products and services  Organizations often perform a SWOT analysis ◦ analyzing Strengths, Weaknesses, Opportunities, and Threats  As part of strategic planning, organizations ◦ identify potential projects ◦ use realistic methods to select which projects to work on ◦ formalize project initiation by issuing a project charter Information Technology Project Management, Seventh Edition 9
  • 10. Copyright 2014 Information Technology Project Management, Seventh Edition 10
  • 11. Copyright 2014 Information Technology Project Management, Seventh Edition 11
  • 12. Copyright 2014  Only one in seven product concepts comes to fruition. Why is it that some companies, like Proctor & Gamble, Johnson and Johnson, Hewlett Packard, and Sony are consistently successful in NPD? Because they use a disciplined, systematic approach to NPD projects based on best practices  Four important forces behind NPD success include the following: 1. A product innovation and technology strategy for the business 2. Resource commitment and focusing on the right projects, or solid portfolio management 3. An effective, flexible and streamlined idea-to-launch process 4. The right climate and culture for innovation, true cross-functional teams, and senior management commitment to NPD Information Technology Project Management, Seventh Edition 12
  • 13. Copyright 2014  There are usually more projects than available time and resources to implement them  Methods for selecting projects include: ◦ focusing on broad organizational needs ◦ categorizing information technology projects ◦ performing net present value or other financial analyses ◦ using a weighted scoring model ◦ implementing a balanced scorecard Information Technology Project Management, Seventh Edition 13
  • 14. Copyright 2014  It is often difficult to provide strong justification for many IT projects, but everyone agrees they have a high value  “It is better to measure gold roughly than to count pennies precisely”  Three important criteria for projects: ◦ There is a need for the project ◦ There are funds available ◦ There’s a strong will to make the project succeed Information Technology Project Management, Seventh Edition 14
  • 15. Copyright 2014  One categorization is whether the project addresses ◦ a problem ◦ an opportunity, or ◦ a directive  Another categorization is how long it will take to do and when it is needed  Another is the overall priority of the project Information Technology Project Management, Seventh Edition 15
  • 16. Copyright 2014  Financial considerations are often an important consideration in selecting projects  Three primary methods for determining the projected financial value of projects: ◦ Net present value (NPV) analysis ◦ Return on investment (ROI) ◦ Payback analysis Information Technology Project Management, Seventh Edition 16
  • 17. Copyright 2014  Net present value (NPV) analysis is a method of calculating the expected net monetary gain or loss from a project by discounting all expected future cash inflows and outflows to the present point in time  Projects with a positive NPV should be considered if financial value is a key criterion  The higher the NPV, the better Information Technology Project Management, Seventh Edition 17
  • 18. Copyright 2014 Information Technology Project Management, Seventh Edition 18
  • 19. Copyright 2014 Information Technology Project Management, Seventh Edition 19 Note: See the template called business_case_financials.xls
  • 20. Copyright 2014  Determine estimated costs and benefits for the life of the project and the products it produces  Determine the discount rate (check with your organization on what to use)  Calculate the NPV (see text for details)  Notes: Some organizations consider the investment year as year 0, while others start in year 1. Some people entered costs as negative numbers, while others do not. Check with your organization for their preferences Information Technology Project Management, Seventh Edition 20
  • 21. Copyright 2014  Return on investment (ROI) is calculated by subtracting the project costs from the benefits and then dividing by the costs ROI = (total discounted benefits - total discounted costs) / discounted costs  The higher the ROI, the better  Many organizations have a required rate of return or minimum acceptable rate of return on investment for projects  Internal rate of return (IRR) can by calculated by finding the discount rate that makes the NPV equal to zero Information Technology Project Management, Seventh Edition 21
  • 22. Copyright 2014  Another important financial consideration is payback analysis  The payback period is the amount of time it will take to recoup, in the form of net cash inflows, the total dollars invested in a project  Payback occurs when the net cumulative discounted benefits equals the costs  Many organizations want IT projects to have a fairly short payback period Information Technology Project Management, Seventh Edition 22
  • 23. Copyright 2014 Information Technology Project Management, Seventh Edition 23
  • 24. Copyright 2014  A weighted scoring model is a tool that provides a systematic process for selecting projects based on many criteria  Identify criteria important to the project selection process  Assign weights (percentages) to each criterion so they add up to 100%  Assign scores to each criterion for each project  Multiply the scores by the weights and get the total weighted scores  The higher the weighted score, the better Information Technology Project Management, Seventh Edition 24
  • 25. Copyright 2014 Information Technology Project Management, Seventh Edition 25
  • 26. Copyright 2014  Drs. Robert Kaplan and David Norton developed this approach to help select and manage projects that align with business strategy  A balanced scorecard ◦ is a methodology that converts an organization’s value drivers, such as customer service, innovation, operational efficiency, and financial performance, to a series of defined metrics  See www.balancedscorecard.org for more information Information Technology Project Management, Seventh Edition 26
  • 27. Copyright 2014 Information Technology Project Management, Seventh Edition 27
  • 28. Copyright 2014  After deciding what project to work on, it is important to let the rest of the organization know  A project charter is a document that formally recognizes the existence of a project and provides direction on the project’s objectives and management  Key project stakeholders should sign a project charter to acknowledge agreement on the need and intent of the project; a signed charter is a key output of project integration management Information Technology Project Management, Seventh Edition 28
  • 29. Copyright 2014  A project statement of work  A business case  Agreements  Enterprise environmental factors  Organizational process assets, which include formal and informal plans, policies, procedures, guidelines, information systems, financial systems, management systems, lessons learned, and historical information Information Technology Project Management, Seventh Edition 29
  • 30. Copyright 2014 Information Technology Project Management, Seventh Edition 30
  • 31. Copyright 2014 Information Technology Project Management, Seventh Edition 31
  • 32. Copyright 2014  A project management plan is a document used to coordinate all project planning documents and help guide a project’s execution and control  Plans created in the other knowledge areas are subsidiary parts of the overall project management plan Information Technology Project Management, Seventh Edition 32
  • 33. Copyright 2014  Introduction or overview of the project  Description of how the project is organized  Management and technical processes used on the project  Work to be done, schedule, and budget information Information Technology Project Management, Seventh Edition 33
  • 34. Copyright 2014 Information Technology Project Management, Seventh Edition 34
  • 35. Copyright 2014 "The winners clearly spell out what needs to be done in a project, by whom, when, and how. For this they use an integrated toolbox, including PM tools, methods, and techniques…If a scheduling template is developed and used over and over, it becomes a repeatable action that leads to higher productivity and lower uncertainty. Sure, using scheduling templates is neither a breakthrough nor a feat. But laggards exhibited almost no use of the templates. Rather, in constructing schedules their project managers started with a clean sheet, a clear waste of time.“* Information Technology Project Management, Seventh Edition 35 *Milosevic, Dragan and And Ozbay. “Delivering Projects: What the Winners Do.” Proceedings of the Project Management Institute Annual Seminars & Symposium (November 2001).
  • 36. Copyright 2014  Involves managing and performing the work described in the project management plan  The majority of time and money is usually spent on execution  The application area of the project directly affects project execution because the products of the project are produced during execution Information Technology Project Management, Seventh Edition 36
  • 37. Copyright 2014  Project planning and execution are intertwined and inseparable activities  Those who will do the work should help to plan the work  Project managers must solicit input from the team to develop realistic plans Information Technology Project Management, Seventh Edition 37
  • 38. Copyright 2014  Project managers must lead by example to demonstrate the importance of creating and then following good project plans  Organizational culture can help project execution by ◦ providing guidelines and templates ◦ tracking performance based on plans  Project managers may still need to break the rules to meet project goals, and senior managers must support those actions Information Technology Project Management, Seventh Edition 38
  • 39. Copyright 2014  It is often helpful for IT project managers to have prior technical experience  On small projects, the project manager may be required to perform some of the technical work or mentor team members to complete the projects  On large projects, the project manager must understand the business and application area of the project Information Technology Project Management, Seventh Edition 39
  • 40. Copyright 2014  Expert judgment: Experts can help project managers and their teams make many decisions related to project execution  Meetings: Meetings allow people to develop relationships, pick up on important body language or tone of voice, and have a dialogue to help resolve problems.  Project management information systems: There are hundreds of project management software products available on the market today, and many organizations are moving toward powerful enterprise project management systems that are accessible via the Internet  See the What Went Right? example of Kuala Lumpur’s Integrated Transport Information System on p. 169 Information Technology Project Management, Seventh Edition 40
  • 41. Copyright 2014  Changes are inevitable on most projects, so it’s important to develop and follow a process to monitor and control changes  Monitoring project work includes collecting, measuring, and disseminating performance information  A baseline is the approved project management plan plus approved changes Information Technology Project Management, Seventh Edition 41
  • 42. Copyright 2014  The 2002 Olympic Winter Games and Paralympics took five years to plan and cost more than $1.9 billion. PMI awarded the Salt Lake Organizing Committee (SLOC) the Project of the Year award for delivering world-class games.  Four years before the Games began, the SLOC used a Primavera software-based system with a cascading color- coded WBS to integrate planning…The SLOC also used an Executive Roadmap, a one-page list of the top 100 Games- wide activities, to keep executives apprised of progress. Activities were tied to detailed project information within each department’s schedule. A 90-day highlighter showed which managers were accountable for each integrated activity.  Fraser Bullock, SLOC Chief Operating Officer and Chief, said, “We knew when we were on and off schedule and where we had to apply additional resources. The interrelation of the functions meant they could not run in isolation—it was a smoothly running machine.”* Information Technology Project Management, Seventh Edition 42 *Foti, Ross, “The Best Winter Olympics, Period,” PM Network (January 2004) 23.
  • 43. Copyright 2014  Three main objectives are: ◦ Influencing the factors that create changes to ensure that changes are beneficial ◦ Determining that a change has occurred ◦ Managing actual changes as they occur Information Technology Project Management, Seventh Edition 43
  • 44. Copyright 2014  Former view: The project team should strive to do exactly what was planned on time and within budget  Problem: Stakeholders rarely agreed up-front on the project scope, and time and cost estimates were inaccurate  Modern view: Project management is a process of constant communication and negotiation  Solution: Changes are often beneficial, and the project team should plan for them Information Technology Project Management, Seventh Edition 44
  • 45. Copyright 2014  A change control system is a formal, documented process that describes when and how official project documents and work may be changed  Describes who is authorized to make changes and how to make them Information Technology Project Management, Seventh Edition 45
  • 46. Copyright 2014  A change control board is a formal group of people responsible for approving or rejecting changes on a project  CCBs provide guidelines for preparing change requests, evaluate change requests, and manage the implementation of approved changes  Includes stakeholders from the entire organization Information Technology Project Management, Seventh Edition 46
  • 47. Copyright 2014  Some CCBs only meet occasionally, so it may take too long for changes to occur  Some organizations have policies in place for time-sensitive changes ◦ “48-hour policy” allows project team members to make decisions, then they have 48 hours to reverse the decision pending senior management approval ◦ Delegate changes to the lowest level possible, but keep everyone informed of changes Information Technology Project Management, Seventh Edition 47
  • 48. Copyright 2014  Rapid changes in technology, such as the increased use of mobile roaming for communications, often cause governments around the world to take action.  Incompatible hardware, software, and networks can make communications difficult in some regions, and a lack of competition can cause prices to soar.  Fortunately, a group called the Organisation for Economic Co-operation and Development (OECD) promotes policies that will improve the economic and social well-being of people around the world.  In February 2012, the OECD called upon its members’ governments to boost competition in international mobile roaming markets. Information Technology Project Management, Seventh Edition 48
  • 49. Copyright 2014  Configuration management ensures that the descriptions of the project’s products are correct and complete  Involves identifying and controlling the functional and physical design characteristics of products and their support documentation  Configuration management specialists identify and document configuration requirements, control changes, record and report changes, and audit the products to verify conformance to requirements  See www.icmhq.com for more information Information Technology Project Management, Seventh Edition 49
  • 50. Copyright 2014 Information Technology Project Management, Seventh Edition 50
  • 51. Copyright 2014  To close a project or phase, you must finalize all activities and transfer the completed or cancelled work to the appropriate people  Main outputs include ◦ Final product, service, or result transition ◦ Organizational process asset updates Information Technology Project Management, Seventh Edition 51
  • 52. Copyright 2014  Several types of software can be used to assist in project integration management ◦ Documents can be created with word processing software ◦ Presentations are created with presentation software ◦ Tracking can be done with spreadsheets or databases ◦ Communication software like e-mail and Web authoring tools facilitate communications ◦ Project management software can pull everything together and show detailed and summarized information ◦ Business Service Management (BSM) tools track the execution of business process flows Information Technology Project Management, Seventh Edition 52
  • 53. Copyright 2014 Information Technology Project Management, Seventh Edition 53 Source: www.projectmanager.com
  • 54. Copyright 2014  Project integration management involves coordinating all of the other knowledge areas throughout a project’s life cycle  Main processes include ◦ Develop the project charter ◦ Develop the project management plan ◦ Direct and manage project execution ◦ Monitor and control project work ◦ Perform integrated change control ◦ Close the project or phase Information Technology Project Management, Seventh Edition 54