Linear Programming:
Two Phase Method
By
Er. ASHISH BANSODE
M.E. Civil-Water Res. Engg.
DEPARTMENT OF CIVIL ENGINEERING.
GOVERNMENT COLLEGE OF ENGINEERING
AURANGABAD-431 005
10/3/2013 Two-Phase Method 1
Two Phase Method
 In the Big M Method, we observed that it
was frequently necessary to add artificial
variables to the constraints to obtain an
initial basic feasible solution to an LPP. If
problem is to be solved, the artificial variable
must be driven to zero.
 The two phase method is another method to
handle these artificial variable. Here the LP
problem is solved in two phase.
10/3/2013 2Two-Phase Method
Phase I
1. In this phase, we find an ibfs to the original problem,
for this all artificial variable are to be driven to zero.
To do this an artificial objective function (w) is
created which is the sum of all artificial variables.
The new objective function is then minimized,
subjected to the constraints of the given original
problem using the simplex method. At the end of
Phase I, three cases arises
A. If the minimum value of w=0, and no artificial
variable appears in the basis at a positive level then
the given problem has no feasible solution and
procedure terminates.
10/3/2013 3Two-Phase Method
B. If the minimum value of w=0, and no artificial
variable appears in the basis, then a basic feasible
solution to the given problem is obtained.
C. If the minimum value of the w=0 and one or
more artificial variable appears in the basis at
zero level, then a feasible solution to the original
problem is obtained. However, we must take care
of this artificial variable and see that it never
become positive during Phase II computations.
10/3/2013 4Two-Phase Method
Phase II
 When Phase I results in (B) or (C), we go on for Phase
II to find optimum solution to the given LP problem.
The basic feasible solution found at the end of Phase I
now used as a starting solution for the original LP
problem. Mean that find table of Phase I becomes
initial table for Phase II in which artificial (auxiliary)
objective function is replaced by the original objective
function. Simplex method is then applied to arrive at
optimum solution.
 Note that the new objective function is always of
minimization type regardless of whether the original
problem of maximization or minimization type.
10/3/2013 5Two-Phase Method
Example 1
 Solve given LPP by Two-Phase Method
1 2 3
1 2 3
1 2 3
1 2 3
5 4 3
Subject to 2 6 20
6 5 10 76
8 3 6 50
Max Z x x x
x x x
x x x
x x x
10/3/2013 6Two-Phase Method
 Add artificial variable to the first constraint and slack
variable to second and third constraints.
 Phase I
 Assigning a cost 1 to artificial variable and cost o to
other variables, the objective function of the auxiliary
LPP is
1 2 3 1
1 2 3 1
1 2 3 1
1 2 3 1
1 2 3 2
* 0 0 0
* 0 0 0 0
Subject to 2 6 20
6 5 10 76
8 3 6 50
Min Z x x x A
Min Z x x x A
x x x A
x x x S
x x x S
10/3/2013 7Two-Phase Method
Basis
Variable
Coefficients of RHS Ratio
X1 X2 X3 S1 S2 A1
A1 2 1 -6 0 0 1 20
S1 6 5 10 1 0 0 76
S2 8 -3 6 0 1 0 50
Z* 0 0 0 0 0 -1 0
10/3/2013 8Two-Phase Method
 Row Calculations
 New Z=Old Z+R1
 X1 is entering variable and S2 is leaving variable
Basis
Variable
Coefficients of RHS Ratio
X1 X2 X3 S1 S2 A1
A1 2 1 -6 0 0 1 20 10
S1 6 5 10 1 0 0 76 76/6
S2 8 -3 6 0 1 0 50 50/8
Z* 2 1 -6 0 0 0 20
10/3/2013 9Two-Phase Method
 Row Calculations
 New R3=Old R3/8
 New R1=New R3*2-Old R1
 New R2=NewR3*6-Old R2
 New Z*=New R3*2-Old Z*
 X2 is entering variable and A1 is leaving variable
Basis
Variable
Coefficients of RHS Ratio
X1 X2 X3 S1 S2 A1
A1 0 1.75 -7.5 0 -1/4 1 7.5 4.28
S1 0 29/4 11/2 1 -0.75 0 77/2 5.31
X1 1 -3/8 6/8 0 1/8 0 50/8 ---
Z* 0 1.75 -7.5 0 -1/4 0 7.5
10/3/2013 10Two-Phase Method
 Row Calculations
 New R1=Old R1/1.75
 New R2=New R1*29/4-Old R2
 New R3=NewR1*(3/8)+Old R3
 New Z*=New R1-Old Z*
 As there is no artificial variable in the basis go to Phase
II
Basis
Variable
Coefficients of RHS Ratio
X1 X2 X3 S1 S2 A1
X2 0 1 -4.28 0 -0.14 0.57 4.28
S1 0 0 36.53 0 0.765 -4.13 7.47
X1 1 0 -8.86 0 0.073 0.041 7.85
Z* 0 0 0 0 0 0.08 0.01
10/3/2013 11Two-Phase Method
Phase II
 Consider the final Simplex table of Phase I, consider
the actual cost associated with the original variables.
Delete the artificial variable A1 column from the table
as it is eliminated in Phase II.
1 3 1 2
1 3 1 2
5 4 3 0 0
5 4 3 0 0 0
M ax Z x x x S S
M ax Z x x x S S
10/3/2013 12Two-Phase Method
 Row calculation: New Z=Old z+5(R3)-4(R1)
Basis
Variable
Coefficients of RHS Ratio
X1 X2 X3 S1 S2
X2 0 1 -4.28 0 -0.14 4.28 0
S1 0 0 36.53 0 0.765 7.47 0
X1 1 0 -0.86 0 0.073 7.85 7.85
Z* -5 4 -3 0 0
Basis
Variable
Coefficients of RHS Ratio
X1 X2 X3 S1 S2
X2 0 1 -4.28 0 -0.14 4.28
S1 0 0 36.53 0 0.765 7.47
X1 1 0 -0.86 0 0.073 7.855
Z* 0 0 9.82 0 0.925 22.14810/3/2013 13Two-Phase Method
 As the given problem is of maximization and all the
values in Z row are either zero or positive, an optimal
solution is reached and is given by
 X1=7.855
 X2=4.28 and
 Z=5X1-4X2+3X3
 Z=5(7.855)-4(4.28)+3(0)
 = 22.15
10/3/2013 14Two-Phase Method
Example 2
 Solve by Two-Phase Simplex Method
1 2 3
1 2 3
1 2 3
1 2 3
4 3 9
Subject to 2 4 6 15
6 6 12
, , 0
Max Z x x x
x x x
x x x
x x x
10/3/2013 15Two-Phase Method
 Add artificial variable to the first constraint and slack
variable to second and third constraints.
 Phase I
 Assigning a cost 1 to artificial variable and cost o to
other variables, the objective function of the auxiliary
LPP is
A new auxiliary linear programming problem
10/3/2013 Two-Phase Method 16
1 2 3 1 2
1 2
1 2 3 1 1
1 2 3 2 2
* 0 0 0
* 0
2 4 6 15
6 6 12
M in Z x x x A A
M in Z A A
x x x S A
x x x S A
Phase I
Basis
Variable
Coefficients of RHS
X1 X2 X3 S1 S2 A1 A1
A1 2 4 6 -1 0 1 O 15
A2 6 1 6 0 -1 0 1 12
Z* 0 0 0 0 0 -1 -1 0
10/3/2013 17Two-Phase Method
 Row Calculations
 New Z*=R3+R1+R2
 X3 is entering variable and A2 is leaving variable
Basis
Variabl
e
Coefficients of RHS Ratio
X1 X2 X3 S1 S2 A1 A1
A1 2 4 6 -1 0 1 O 15 15/6
A2 6 1 6 0 -1 0 1 12 12/6
Z* 8 5 12 -1 -1 0 0 27
10/3/2013 18Two-Phase Method
 Row Calculations
 New R2=Old R2/6
 New R1= New R2*6-Old R1
 New Z*=New R2*12-Old Z*
 X2 is entering variable and A1 is leaving variable
Basis
Variabl
e
Coefficients of RHS Ratio
X1 X2 X3 S1 S2 A1 A2
A1 -4 3 0 -1 1 1 -1 3 1
X3 1 1/6 1 0 -1/6 0 1/6 2 12
Z* -4 3 0 -1 1 0 -2 3
10/3/2013 19Two-Phase Method
 Row Calculations
 New R1=Old R1/3
 New R2= New R1*(1/6)-Old R2
 New Z*=New R1*3-Old Z*
 Optimality condition is satisfied as Z* is having zero
value
Basis
Variable
Coefficients of RHS
X1 X2 X3 S1 S2 A1 A2
X2 -4/3 1 0 -1/3 1/3 1/3 -1/3 1
X3 11/9 0 1 1/18 -2/9 -2/27 2/9 11/6
Z* 0 0 0 0 0 -1 -1 0
10/3/2013 20Two-Phase Method
Phase II
 Original objective function is given as
 Consider the final Simplex table of Phase I, consider
the actual cost associated with the original variables.
Delete the artificial variable A1 column from the table
as it is eliminated in Phase II.
1 2 3 1 2
1 2 3 1 2
1 2 3 1
1 2 3 2
1 2 3
4 3 9 0 0
4 3 9 0 0
Subject to 2 4 6 0 15
6 6 0 12
, , 0
M ax Z x x x S S
M ax Z x x x S S
x x x S
x x x S
x x x
10/3/2013 21Two-Phase Method
Initial Basic Feasible Solution
 Row calculations New Z=OldZ-3R1-9R2
Basis
Variable
Coefficients of RHS
X1 X2 X3 S1 S2
X2 -4/3 1 0 -1/3 1/3
X3 11/9 0 1 1/18 -2/9
Z 4 3 9 0 0 0
10/3/2013 22Two-Phase Method
 X1 is entering variable and X3 is leaving variable
Basis
Variable
Coefficients of RHS Ratio
X1 X2 X3 S1 S2
X2 -4/3 1 0 -1/3 1/3 1 ---
X3 11/9 0 1 1/18 -2/9 11/6 1.5
Z -3 0 0 1/2 1 -19/5
10/3/2013 23Two-Phase Method
 Row Calculations
 New R2=Old R2/(11/9)
 New R1=New R2+Old R1
 New Z= New R2*3+Old Z
 As all the values in Z row are zero or positive, the
condition of optimality is reached.
Basis
Variable
Coefficients of RH
S
Ratio
X1 X2 X3 S1 S2
X2 0 1 12/11 -3/11 13/33 3
X1 1 0 9/11 1/22 -2/11 3/2
Z 0 0 27/11 7/11 3/11 -15
10/3/2013 24Two-Phase Method
 X1=3/2
 X3=3
 Hence Z=-4x1-3x2-9x3
Z=-4(1.5)-3(3)-9(0)
Z=-15
10/3/2013 25Two-Phase Method
Exercise
1.
2.
1 2 3
1 2 3
1 2 3
1 2 3
1 2 3
2
Subject to 4 6 3 8
3 6 4 1
2 3 5 4
, , 0
M ax Z x x x
x x x
x x x
x x x
x x x
1 2
1 2
1 2
1 2
2
Subject to 2
4
, 0
Min Z x x
x x
x x
x x
10/3/2013 26Two-Phase Method
3.
1 2 3
1 2 3
1 2
2 3
1 2 3
5 2 3
Subject to 2 2 2
3 4 3
3 5
, , 0
M ax Z x x x
x x x
x x
x x
x x x
10/3/2013 27Two-Phase Method

Contenu connexe

Tendances

Simplex method concept,
Simplex method concept,Simplex method concept,
Simplex method concept,Dronak Sahu
 
Operation research unit 1: LPP Big M and Two Phase method
Operation research unit 1: LPP Big M and Two Phase methodOperation research unit 1: LPP Big M and Two Phase method
Operation research unit 1: LPP Big M and Two Phase methodDr. L K Bhagi
 
Chapter 4 Simplex Method ppt
Chapter 4  Simplex Method pptChapter 4  Simplex Method ppt
Chapter 4 Simplex Method pptDereje Tigabu
 
Simplex Method
Simplex MethodSimplex Method
Simplex MethodSachin MK
 
Operation Research (Simplex Method)
Operation Research (Simplex Method)Operation Research (Simplex Method)
Operation Research (Simplex Method)Shivani Gautam
 
Linear Programming Problems : Dr. Purnima Pandit
Linear Programming Problems : Dr. Purnima PanditLinear Programming Problems : Dr. Purnima Pandit
Linear Programming Problems : Dr. Purnima PanditPurnima Pandit
 
Artificial Variable Technique –
Artificial Variable Technique –Artificial Variable Technique –
Artificial Variable Technique –itsvineeth209
 
Sensitivity analysis linear programming copy
Sensitivity analysis linear programming   copySensitivity analysis linear programming   copy
Sensitivity analysis linear programming copyKiran Jadhav
 
Special Cases in Simplex Method
Special Cases in Simplex MethodSpecial Cases in Simplex Method
Special Cases in Simplex MethodDivyansh Verma
 
Linear Programming Feasible Region
Linear Programming Feasible RegionLinear Programming Feasible Region
Linear Programming Feasible RegionVARUN MODI
 

Tendances (20)

Simplex method concept,
Simplex method concept,Simplex method concept,
Simplex method concept,
 
Simplex algorithm
Simplex algorithmSimplex algorithm
Simplex algorithm
 
Operations Research - The Two Phase Method
Operations Research - The Two Phase MethodOperations Research - The Two Phase Method
Operations Research - The Two Phase Method
 
Dual simplexmethod
Dual simplexmethodDual simplexmethod
Dual simplexmethod
 
Operation research unit 1: LPP Big M and Two Phase method
Operation research unit 1: LPP Big M and Two Phase methodOperation research unit 1: LPP Big M and Two Phase method
Operation research unit 1: LPP Big M and Two Phase method
 
Chapter 4 Simplex Method ppt
Chapter 4  Simplex Method pptChapter 4  Simplex Method ppt
Chapter 4 Simplex Method ppt
 
Simplex Method
Simplex MethodSimplex Method
Simplex Method
 
Operation Research (Simplex Method)
Operation Research (Simplex Method)Operation Research (Simplex Method)
Operation Research (Simplex Method)
 
Linear Programming Problems : Dr. Purnima Pandit
Linear Programming Problems : Dr. Purnima PanditLinear Programming Problems : Dr. Purnima Pandit
Linear Programming Problems : Dr. Purnima Pandit
 
4-The Simplex Method.ppt
4-The Simplex Method.ppt4-The Simplex Method.ppt
4-The Simplex Method.ppt
 
Artificial Variable Technique –
Artificial Variable Technique –Artificial Variable Technique –
Artificial Variable Technique –
 
Big-M Method Presentation
Big-M Method PresentationBig-M Method Presentation
Big-M Method Presentation
 
Simplex two phase
Simplex two phaseSimplex two phase
Simplex two phase
 
Operations Research - The Big M Method
Operations Research - The Big M MethodOperations Research - The Big M Method
Operations Research - The Big M Method
 
Sensitivity analysis linear programming copy
Sensitivity analysis linear programming   copySensitivity analysis linear programming   copy
Sensitivity analysis linear programming copy
 
Special Cases in Simplex Method
Special Cases in Simplex MethodSpecial Cases in Simplex Method
Special Cases in Simplex Method
 
Linear Programming Feasible Region
Linear Programming Feasible RegionLinear Programming Feasible Region
Linear Programming Feasible Region
 
Simplex method
Simplex methodSimplex method
Simplex method
 
Linear programing
Linear programingLinear programing
Linear programing
 
Lp simplex 3_
Lp simplex 3_Lp simplex 3_
Lp simplex 3_
 

En vedette

Simplex method Big M infeasible
Simplex method Big M infeasibleSimplex method Big M infeasible
Simplex method Big M infeasibleIzzati Hamid
 
optimization simplex method introduction
optimization simplex method introductionoptimization simplex method introduction
optimization simplex method introductionKunal Shinde
 
Dual y simplex dual
Dual y simplex dualDual y simplex dual
Dual y simplex dualpuracastillo
 
Graphical Method Of LPP
Graphical Method Of LPPGraphical Method Of LPP
Graphical Method Of LPPKJ Savaliya
 
Mean field Green function solution of the two-band Hubbard model in cuprates
Mean field Green function solution of the two-band Hubbard model in cupratesMean field Green function solution of the two-band Hubbard model in cuprates
Mean field Green function solution of the two-band Hubbard model in cupratesABDERRAHMANE REGGAD
 
Abel - A great mathematician
Abel - A great mathematicianAbel - A great mathematician
Abel - A great mathematicianNandiniNandus
 
Simplex method
Simplex methodSimplex method
Simplex methodAbu Bashar
 
Solving linear programming model by simplex method
Solving linear programming model by simplex methodSolving linear programming model by simplex method
Solving linear programming model by simplex methodRoshan Kumar Patel
 
Linear programming - Model formulation, Graphical Method
Linear programming  - Model formulation, Graphical MethodLinear programming  - Model formulation, Graphical Method
Linear programming - Model formulation, Graphical MethodJoseph Konnully
 

En vedette (18)

Operations research 1_the_two-phase_simp
Operations research 1_the_two-phase_simpOperations research 1_the_two-phase_simp
Operations research 1_the_two-phase_simp
 
Simplex method Big M infeasible
Simplex method Big M infeasibleSimplex method Big M infeasible
Simplex method Big M infeasible
 
Big m method
Big m methodBig m method
Big m method
 
optimization simplex method introduction
optimization simplex method introductionoptimization simplex method introduction
optimization simplex method introduction
 
Dual y simplex dual
Dual y simplex dualDual y simplex dual
Dual y simplex dual
 
S1 Dualsimplex
S1 DualsimplexS1 Dualsimplex
S1 Dualsimplex
 
Graphical Method Of LPP
Graphical Method Of LPPGraphical Method Of LPP
Graphical Method Of LPP
 
Mean field Green function solution of the two-band Hubbard model in cuprates
Mean field Green function solution of the two-band Hubbard model in cupratesMean field Green function solution of the two-band Hubbard model in cuprates
Mean field Green function solution of the two-band Hubbard model in cuprates
 
Abel - A great mathematician
Abel - A great mathematicianAbel - A great mathematician
Abel - A great mathematician
 
Number theory lecture (part 1)
Number theory lecture (part 1)Number theory lecture (part 1)
Number theory lecture (part 1)
 
Simplex method
Simplex methodSimplex method
Simplex method
 
Number theory Grade 7, 8 and 9
Number theory Grade 7, 8 and 9Number theory Grade 7, 8 and 9
Number theory Grade 7, 8 and 9
 
Number theory
Number theoryNumber theory
Number theory
 
OR 14 15-unit_1
OR 14 15-unit_1OR 14 15-unit_1
OR 14 15-unit_1
 
Types of coagulants
Types of coagulantsTypes of coagulants
Types of coagulants
 
Solving linear programming model by simplex method
Solving linear programming model by simplex methodSolving linear programming model by simplex method
Solving linear programming model by simplex method
 
Linear programming ppt
Linear programming pptLinear programming ppt
Linear programming ppt
 
Linear programming - Model formulation, Graphical Method
Linear programming  - Model formulation, Graphical MethodLinear programming  - Model formulation, Graphical Method
Linear programming - Model formulation, Graphical Method
 

Similaire à LINEAR PROGRAMMING

Twophasemethod 131003081339-phpapp01
Twophasemethod 131003081339-phpapp01Twophasemethod 131003081339-phpapp01
Twophasemethod 131003081339-phpapp01kongara
 
Simplex Algorithm
Simplex AlgorithmSimplex Algorithm
Simplex AlgorithmAizaz Ahmad
 
Optimum Solution of Quadratic Programming Problem: By Wolfe’s Modified Simple...
Optimum Solution of Quadratic Programming Problem: By Wolfe’s Modified Simple...Optimum Solution of Quadratic Programming Problem: By Wolfe’s Modified Simple...
Optimum Solution of Quadratic Programming Problem: By Wolfe’s Modified Simple...IJLT EMAS
 
Simplex part 2 of 4
Simplex part 2 of 4Simplex part 2 of 4
Simplex part 2 of 4Ed Dansereau
 
CHAPTER 7.pdfdjdjdjdjdjdjdjsjsjddhhdudsko
CHAPTER 7.pdfdjdjdjdjdjdjdjsjsjddhhdudskoCHAPTER 7.pdfdjdjdjdjdjdjdjsjsjddhhdudsko
CHAPTER 7.pdfdjdjdjdjdjdjdjsjsjddhhdudskoSydneyJaydeanKhanyil
 
OR Linear Programming
OR Linear ProgrammingOR Linear Programming
OR Linear Programmingchaitu87
 
Linear programming
Linear programmingLinear programming
Linear programmingsabin kafle
 
simplex method-maths 4 mumbai university
simplex method-maths 4 mumbai universitysimplex method-maths 4 mumbai university
simplex method-maths 4 mumbai universityshobhakedari59
 
performance management and Resource optimization part-2.pptx
performance management and Resource optimization part-2.pptxperformance management and Resource optimization part-2.pptx
performance management and Resource optimization part-2.pptxtefera21
 
Applied numerical methods lec6
Applied numerical methods lec6Applied numerical methods lec6
Applied numerical methods lec6Yasser Ahmed
 
Numerical integration
Numerical integration Numerical integration
Numerical integration Dhyey Shukla
 
Integer Linear Programming
Integer Linear ProgrammingInteger Linear Programming
Integer Linear ProgrammingSukhpalRamanand
 
18-21 Principles of Least Squares.ppt
18-21 Principles of Least Squares.ppt18-21 Principles of Least Squares.ppt
18-21 Principles of Least Squares.pptBAGARAGAZAROMUALD2
 
Chapter 12 Dynamic programming.pptx
Chapter 12 Dynamic programming.pptxChapter 12 Dynamic programming.pptx
Chapter 12 Dynamic programming.pptxMdSazolAhmmed
 
3rd-edition-linear-algebra-and-its-applications-solutions-manual.pdf
3rd-edition-linear-algebra-and-its-applications-solutions-manual.pdf3rd-edition-linear-algebra-and-its-applications-solutions-manual.pdf
3rd-edition-linear-algebra-and-its-applications-solutions-manual.pdfJennifer Strong
 

Similaire à LINEAR PROGRAMMING (20)

Twophasemethod 131003081339-phpapp01
Twophasemethod 131003081339-phpapp01Twophasemethod 131003081339-phpapp01
Twophasemethod 131003081339-phpapp01
 
Simplex Algorithm
Simplex AlgorithmSimplex Algorithm
Simplex Algorithm
 
aaoczc2252
aaoczc2252aaoczc2252
aaoczc2252
 
Optimum Solution of Quadratic Programming Problem: By Wolfe’s Modified Simple...
Optimum Solution of Quadratic Programming Problem: By Wolfe’s Modified Simple...Optimum Solution of Quadratic Programming Problem: By Wolfe’s Modified Simple...
Optimum Solution of Quadratic Programming Problem: By Wolfe’s Modified Simple...
 
MFCS2-Module1.pptx
MFCS2-Module1.pptxMFCS2-Module1.pptx
MFCS2-Module1.pptx
 
Big m method
Big   m methodBig   m method
Big m method
 
Simplex part 2 of 4
Simplex part 2 of 4Simplex part 2 of 4
Simplex part 2 of 4
 
CHAPTER 7.pdfdjdjdjdjdjdjdjsjsjddhhdudsko
CHAPTER 7.pdfdjdjdjdjdjdjdjsjsjddhhdudskoCHAPTER 7.pdfdjdjdjdjdjdjdjsjsjddhhdudsko
CHAPTER 7.pdfdjdjdjdjdjdjdjsjsjddhhdudsko
 
OR Linear Programming
OR Linear ProgrammingOR Linear Programming
OR Linear Programming
 
Linear programming
Linear programmingLinear programming
Linear programming
 
simplex method-maths 4 mumbai university
simplex method-maths 4 mumbai universitysimplex method-maths 4 mumbai university
simplex method-maths 4 mumbai university
 
performance management and Resource optimization part-2.pptx
performance management and Resource optimization part-2.pptxperformance management and Resource optimization part-2.pptx
performance management and Resource optimization part-2.pptx
 
Applied numerical methods lec6
Applied numerical methods lec6Applied numerical methods lec6
Applied numerical methods lec6
 
Simplex Algorithm
Simplex AlgorithmSimplex Algorithm
Simplex Algorithm
 
Numerical integration
Numerical integration Numerical integration
Numerical integration
 
Integer Linear Programming
Integer Linear ProgrammingInteger Linear Programming
Integer Linear Programming
 
18-21 Principles of Least Squares.ppt
18-21 Principles of Least Squares.ppt18-21 Principles of Least Squares.ppt
18-21 Principles of Least Squares.ppt
 
Xx
XxXx
Xx
 
Chapter 12 Dynamic programming.pptx
Chapter 12 Dynamic programming.pptxChapter 12 Dynamic programming.pptx
Chapter 12 Dynamic programming.pptx
 
3rd-edition-linear-algebra-and-its-applications-solutions-manual.pdf
3rd-edition-linear-algebra-and-its-applications-solutions-manual.pdf3rd-edition-linear-algebra-and-its-applications-solutions-manual.pdf
3rd-edition-linear-algebra-and-its-applications-solutions-manual.pdf
 

Dernier

Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfChris Hunter
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Shubhangi Sonawane
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxnegromaestrong
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docxPoojaSen20
 

Dernier (20)

Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 

LINEAR PROGRAMMING

  • 1. Linear Programming: Two Phase Method By Er. ASHISH BANSODE M.E. Civil-Water Res. Engg. DEPARTMENT OF CIVIL ENGINEERING. GOVERNMENT COLLEGE OF ENGINEERING AURANGABAD-431 005 10/3/2013 Two-Phase Method 1
  • 2. Two Phase Method  In the Big M Method, we observed that it was frequently necessary to add artificial variables to the constraints to obtain an initial basic feasible solution to an LPP. If problem is to be solved, the artificial variable must be driven to zero.  The two phase method is another method to handle these artificial variable. Here the LP problem is solved in two phase. 10/3/2013 2Two-Phase Method
  • 3. Phase I 1. In this phase, we find an ibfs to the original problem, for this all artificial variable are to be driven to zero. To do this an artificial objective function (w) is created which is the sum of all artificial variables. The new objective function is then minimized, subjected to the constraints of the given original problem using the simplex method. At the end of Phase I, three cases arises A. If the minimum value of w=0, and no artificial variable appears in the basis at a positive level then the given problem has no feasible solution and procedure terminates. 10/3/2013 3Two-Phase Method
  • 4. B. If the minimum value of w=0, and no artificial variable appears in the basis, then a basic feasible solution to the given problem is obtained. C. If the minimum value of the w=0 and one or more artificial variable appears in the basis at zero level, then a feasible solution to the original problem is obtained. However, we must take care of this artificial variable and see that it never become positive during Phase II computations. 10/3/2013 4Two-Phase Method
  • 5. Phase II  When Phase I results in (B) or (C), we go on for Phase II to find optimum solution to the given LP problem. The basic feasible solution found at the end of Phase I now used as a starting solution for the original LP problem. Mean that find table of Phase I becomes initial table for Phase II in which artificial (auxiliary) objective function is replaced by the original objective function. Simplex method is then applied to arrive at optimum solution.  Note that the new objective function is always of minimization type regardless of whether the original problem of maximization or minimization type. 10/3/2013 5Two-Phase Method
  • 6. Example 1  Solve given LPP by Two-Phase Method 1 2 3 1 2 3 1 2 3 1 2 3 5 4 3 Subject to 2 6 20 6 5 10 76 8 3 6 50 Max Z x x x x x x x x x x x x 10/3/2013 6Two-Phase Method
  • 7.  Add artificial variable to the first constraint and slack variable to second and third constraints.  Phase I  Assigning a cost 1 to artificial variable and cost o to other variables, the objective function of the auxiliary LPP is 1 2 3 1 1 2 3 1 1 2 3 1 1 2 3 1 1 2 3 2 * 0 0 0 * 0 0 0 0 Subject to 2 6 20 6 5 10 76 8 3 6 50 Min Z x x x A Min Z x x x A x x x A x x x S x x x S 10/3/2013 7Two-Phase Method
  • 8. Basis Variable Coefficients of RHS Ratio X1 X2 X3 S1 S2 A1 A1 2 1 -6 0 0 1 20 S1 6 5 10 1 0 0 76 S2 8 -3 6 0 1 0 50 Z* 0 0 0 0 0 -1 0 10/3/2013 8Two-Phase Method
  • 9.  Row Calculations  New Z=Old Z+R1  X1 is entering variable and S2 is leaving variable Basis Variable Coefficients of RHS Ratio X1 X2 X3 S1 S2 A1 A1 2 1 -6 0 0 1 20 10 S1 6 5 10 1 0 0 76 76/6 S2 8 -3 6 0 1 0 50 50/8 Z* 2 1 -6 0 0 0 20 10/3/2013 9Two-Phase Method
  • 10.  Row Calculations  New R3=Old R3/8  New R1=New R3*2-Old R1  New R2=NewR3*6-Old R2  New Z*=New R3*2-Old Z*  X2 is entering variable and A1 is leaving variable Basis Variable Coefficients of RHS Ratio X1 X2 X3 S1 S2 A1 A1 0 1.75 -7.5 0 -1/4 1 7.5 4.28 S1 0 29/4 11/2 1 -0.75 0 77/2 5.31 X1 1 -3/8 6/8 0 1/8 0 50/8 --- Z* 0 1.75 -7.5 0 -1/4 0 7.5 10/3/2013 10Two-Phase Method
  • 11.  Row Calculations  New R1=Old R1/1.75  New R2=New R1*29/4-Old R2  New R3=NewR1*(3/8)+Old R3  New Z*=New R1-Old Z*  As there is no artificial variable in the basis go to Phase II Basis Variable Coefficients of RHS Ratio X1 X2 X3 S1 S2 A1 X2 0 1 -4.28 0 -0.14 0.57 4.28 S1 0 0 36.53 0 0.765 -4.13 7.47 X1 1 0 -8.86 0 0.073 0.041 7.85 Z* 0 0 0 0 0 0.08 0.01 10/3/2013 11Two-Phase Method
  • 12. Phase II  Consider the final Simplex table of Phase I, consider the actual cost associated with the original variables. Delete the artificial variable A1 column from the table as it is eliminated in Phase II. 1 3 1 2 1 3 1 2 5 4 3 0 0 5 4 3 0 0 0 M ax Z x x x S S M ax Z x x x S S 10/3/2013 12Two-Phase Method
  • 13.  Row calculation: New Z=Old z+5(R3)-4(R1) Basis Variable Coefficients of RHS Ratio X1 X2 X3 S1 S2 X2 0 1 -4.28 0 -0.14 4.28 0 S1 0 0 36.53 0 0.765 7.47 0 X1 1 0 -0.86 0 0.073 7.85 7.85 Z* -5 4 -3 0 0 Basis Variable Coefficients of RHS Ratio X1 X2 X3 S1 S2 X2 0 1 -4.28 0 -0.14 4.28 S1 0 0 36.53 0 0.765 7.47 X1 1 0 -0.86 0 0.073 7.855 Z* 0 0 9.82 0 0.925 22.14810/3/2013 13Two-Phase Method
  • 14.  As the given problem is of maximization and all the values in Z row are either zero or positive, an optimal solution is reached and is given by  X1=7.855  X2=4.28 and  Z=5X1-4X2+3X3  Z=5(7.855)-4(4.28)+3(0)  = 22.15 10/3/2013 14Two-Phase Method
  • 15. Example 2  Solve by Two-Phase Simplex Method 1 2 3 1 2 3 1 2 3 1 2 3 4 3 9 Subject to 2 4 6 15 6 6 12 , , 0 Max Z x x x x x x x x x x x x 10/3/2013 15Two-Phase Method
  • 16.  Add artificial variable to the first constraint and slack variable to second and third constraints.  Phase I  Assigning a cost 1 to artificial variable and cost o to other variables, the objective function of the auxiliary LPP is A new auxiliary linear programming problem 10/3/2013 Two-Phase Method 16 1 2 3 1 2 1 2 1 2 3 1 1 1 2 3 2 2 * 0 0 0 * 0 2 4 6 15 6 6 12 M in Z x x x A A M in Z A A x x x S A x x x S A
  • 17. Phase I Basis Variable Coefficients of RHS X1 X2 X3 S1 S2 A1 A1 A1 2 4 6 -1 0 1 O 15 A2 6 1 6 0 -1 0 1 12 Z* 0 0 0 0 0 -1 -1 0 10/3/2013 17Two-Phase Method
  • 18.  Row Calculations  New Z*=R3+R1+R2  X3 is entering variable and A2 is leaving variable Basis Variabl e Coefficients of RHS Ratio X1 X2 X3 S1 S2 A1 A1 A1 2 4 6 -1 0 1 O 15 15/6 A2 6 1 6 0 -1 0 1 12 12/6 Z* 8 5 12 -1 -1 0 0 27 10/3/2013 18Two-Phase Method
  • 19.  Row Calculations  New R2=Old R2/6  New R1= New R2*6-Old R1  New Z*=New R2*12-Old Z*  X2 is entering variable and A1 is leaving variable Basis Variabl e Coefficients of RHS Ratio X1 X2 X3 S1 S2 A1 A2 A1 -4 3 0 -1 1 1 -1 3 1 X3 1 1/6 1 0 -1/6 0 1/6 2 12 Z* -4 3 0 -1 1 0 -2 3 10/3/2013 19Two-Phase Method
  • 20.  Row Calculations  New R1=Old R1/3  New R2= New R1*(1/6)-Old R2  New Z*=New R1*3-Old Z*  Optimality condition is satisfied as Z* is having zero value Basis Variable Coefficients of RHS X1 X2 X3 S1 S2 A1 A2 X2 -4/3 1 0 -1/3 1/3 1/3 -1/3 1 X3 11/9 0 1 1/18 -2/9 -2/27 2/9 11/6 Z* 0 0 0 0 0 -1 -1 0 10/3/2013 20Two-Phase Method
  • 21. Phase II  Original objective function is given as  Consider the final Simplex table of Phase I, consider the actual cost associated with the original variables. Delete the artificial variable A1 column from the table as it is eliminated in Phase II. 1 2 3 1 2 1 2 3 1 2 1 2 3 1 1 2 3 2 1 2 3 4 3 9 0 0 4 3 9 0 0 Subject to 2 4 6 0 15 6 6 0 12 , , 0 M ax Z x x x S S M ax Z x x x S S x x x S x x x S x x x 10/3/2013 21Two-Phase Method
  • 22. Initial Basic Feasible Solution  Row calculations New Z=OldZ-3R1-9R2 Basis Variable Coefficients of RHS X1 X2 X3 S1 S2 X2 -4/3 1 0 -1/3 1/3 X3 11/9 0 1 1/18 -2/9 Z 4 3 9 0 0 0 10/3/2013 22Two-Phase Method
  • 23.  X1 is entering variable and X3 is leaving variable Basis Variable Coefficients of RHS Ratio X1 X2 X3 S1 S2 X2 -4/3 1 0 -1/3 1/3 1 --- X3 11/9 0 1 1/18 -2/9 11/6 1.5 Z -3 0 0 1/2 1 -19/5 10/3/2013 23Two-Phase Method
  • 24.  Row Calculations  New R2=Old R2/(11/9)  New R1=New R2+Old R1  New Z= New R2*3+Old Z  As all the values in Z row are zero or positive, the condition of optimality is reached. Basis Variable Coefficients of RH S Ratio X1 X2 X3 S1 S2 X2 0 1 12/11 -3/11 13/33 3 X1 1 0 9/11 1/22 -2/11 3/2 Z 0 0 27/11 7/11 3/11 -15 10/3/2013 24Two-Phase Method
  • 25.  X1=3/2  X3=3  Hence Z=-4x1-3x2-9x3 Z=-4(1.5)-3(3)-9(0) Z=-15 10/3/2013 25Two-Phase Method
  • 26. Exercise 1. 2. 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 2 Subject to 4 6 3 8 3 6 4 1 2 3 5 4 , , 0 M ax Z x x x x x x x x x x x x x x x 1 2 1 2 1 2 1 2 2 Subject to 2 4 , 0 Min Z x x x x x x x x 10/3/2013 26Two-Phase Method
  • 27. 3. 1 2 3 1 2 3 1 2 2 3 1 2 3 5 2 3 Subject to 2 2 2 3 4 3 3 5 , , 0 M ax Z x x x x x x x x x x x x x 10/3/2013 27Two-Phase Method