1910.180
TRUCK CRANE OPERATION
REVIEW. PART 1
TRAINER: BILL BROWN
INSPECTION MANAGER
inspections4me@gmail.com
Wheel mounted crane
(wagon crane) consists of a rotating
superstructure with power plant, operating
machinery and boom, mounted on a base
or platform equipped with axles and
rubber tired wheels for travel. Its function
is to hoist and swing loads at various radii.
Truck Crane
A truck Crane consists of a rotating
superstructure with power plant, operating
machinery and boom, mounted on a
automotive truck equipped with a power
plant for travel. Its function is to hoist and
swing loads at various radii.
. DEFINITIONS
AUTHORIZED: IS ONE APPOINTED OR
CREDENTIALLED BY A DULY CONSTITUTED
ADMINISTRATIVE OR REGULATORY
AUTHORITY
Competent Person
A competent person is one who by knowledge, training and
experience has demonstrated the ability to solve problems
and preform functions relating to the subject matter and
work
Truck Crane
Semi Truck Crane
Large Boom Truck
Carry Deck Crane
O S H A
Occupational Safety & Health
Administration
Federal Law (Required action)
A N S I
American National Standards Institute

.Reaction Time
Measure how quickly the person reacts to a set of signals, or
to an emergency
Distance Judgement
Measurement of depth perception is important for Crane
Operators.
Hearing
Several devices are available to test hearing ability. The
person should be able to meet standard requirements.
ANGLE INDICATOR
MEASURES ANGLE OF BOOM TO HORIZON
Angle Chart
SAFETY RULES
There are many safety rules that have been set up to be
observed by Crane Operators. However, if you follow these
rules you will observe most of the necessary precautions
while operating your crane.
.
1. No one but a regularly authorized operator is
allowed to use any crane.
2. Load Rating Chart with clearly legible letters and
figures shall be provided and fixed to the crane. Must
be clearly visible to operator at there controls
3. Before moving crane, be sure that the hook is high
enough to Clear all obstacles.
4. The operator SHALL NOT leave their position at the
controls while a load is suspended.
5. The Cranes Wire Rope SHALL NOT be wrapped
around. the load. Slings must be utilized
6. Do Not carry load over people on floor; sound warning
devices if crane is equipped to warn persons nearby.
7. Do not allow anyone to ride on a load carried by the
crane, or on the crane hook.
8. Do not drag slings chains or lifting devices out from
under loads that have been landed
9. If you are asked to do something that you DO NOT
believe is safe,
you should refuse to do it, and call your foreman/supervisor
in charge for advice
10.DO NOT exceed the rated capacity of your Hoist/Crane
11. An Operator MUST NOT operate a crane if he/she is not
physically
fit to do so.
12. In case of a problem always STOP operation and open
the power switch.
If your crane fails to respond correctly call your
foreman/supervisor.
Attempting to get out of difficulty by repeating the operation
may make the condition worse instead of better
15. Crane operators must follow the signals given to them only
by authorized persons (THE ASSIGNED RIGGER) and should
ignore directions given by others during operation of their
equipment.
The only EXCEPTION to this rule is if ANYONE commands
them to EMERGENCY STOP.
Crane Hand Signals
BOOM UP Hoist Up Slow Hoist Down
Boom Down Hoist Up Walk Crane
Crane Hand Signals #2
Swing Crane ------------------/ Retract Boom-------/ Everything Slow
EXTEND BOOM
Crane Hand Signals # 3
Emergency Stop------------------------------------- Routine Stop------------
Who can give the hand signals? or
Who can be a signaler?
a person qualified to give crane signals to
the operator, there should be only one
designated signaler at a time, if signalers
are changing between each other, the one
in charge should wear a clearly visible
badge of authority, a crane operator
should move loads only on signals from
one signaler, a crane operator must
obey STOP signals no matter who
gives it.  
DON’T BE A HEADLINE
SUMMARY
Every worker should know crane hand signals. Knowing
the signals may allow you to help out when needed If
you are asked to be a signal person, make sure you are
using the same signals as other workers and operators
on the project When tower cranes or situations where
hand signals are not safe enough, ensure that a two-way
radio is used for voice communication. This will give you
direct contact with the operator. Whatever system you
use - hands or radio - make sure the equipment and
workers are able to do the job right.  
Don't Be a Headline
Cranes
Cranes are designed to make “Vertical lifts of loads ONLY,
DO NOT angle/side load unless it has been determined by a qualified
person not to pose a hazard to equipment or personnel.
Limit Devices
A limiting device shall be installed and
maintainted to prevent the hook or other
end fitting from contacting the upper
sheaves.
Booms
When sections of booms are added or
removed, full number of bolts or pins of
the material and size recommended by the
manfacture
Fire Extinguishers
(i) A carbon dioxide, dry chemical, or
equivalent fire extinguisher shall be kept in
cab or vicinity of the crane
(ii) Operating and maintenance personal
shall be made familiar with the use and
care of the fire extinguishers provided.
Power Lines
For operating near electric power lines:
See 1910.333 (c) (3)
Load Rating
Load ratings - where stability governs lifting
performance."
1910.180(c)(1)(i)
The margin of stability for determination of load ratings,
with booms of stipulated lengths at stipulated working
radii for the various types of crane mountings, is
established by taking a percentage of the loads which
will produce a condition of tipping or balance with the
boom in the least stable direction, relative to the
mounting. The load ratings shall not exceed the following
percentages for cranes, with the indicated types of
mounting under conditions stipulated in paragraphs (c)
(1)(ii) and (iii) of this section. Truck cranes 85%
1910.180(c)(2)
"Load rating chart." A substantial and durable
rating chart with clearly legible letters and figures
shall be provided with each crane and securely
fixed to the crane cab in a location easily visible to
the operator while seated at his control station.
Load Rating Chart
Inspection classification" -
1910.180(d)(1)
"Initial inspection." Prior to initial use all new and altered
cranes shall be inspected to insure compliance with
provisions of this section.
..1910.180(d)(2)
1910.180(d)(2)
"Regular inspection." Inspection procedure for cranes in
regular service is divided into two general classifications
based upon the intervals at which inspection should be
performed. The intervals in turn are dependent upon the
nature of the critical components of the crane and the
degree of their exposure to wear, deterioration, or
malfunction. The two general classifications are herein
designated as "frequent" and "periodic", with respective
intervals between inspections as defined below:
Inspection of your Truck Crane
Frequent inspection: Daily to monthly intervals.
1910.180(d)(2)(ii)
Periodic inspection: 1- to 12- month intervals, or as
specifically recommended by the manufacturer.
1910.180(d)(3)
"Frequent inspection." Items such as the following shall
be inspected for defects at intervals as defined in
paragraph (d)(2)(i) of this section or as specifically
indicated including observation during operation for any
defects which might appear between regular inspections.
Any deficiencies such as listed shall be carefully
examined and determination made as to whether they
constitute a safety hazard:
Daily Inspections to monthly
1910.180(d)(3)(i)
All control mechanisms for maladjustment
interfering with proper operation: Daily.
1910.180(d)(3)(ii)
All control mechanisms for excessive wear of
components and contamination by lubricants or
other foreign matter.
1910.180(d)(3)(iii)
All safety devices for malfunction.
1910.180(d)(3)(iv)
Deterioration or leakage in air or hydraulic
systems: Daily.
Page 2 of inspections procedours
..1910.180(d)(3)(v)
1910.180(d)(3)(v)
Crane hooks with deformations or cracks. For hooks with
cracks or having more than 15 percent in excess of
normal throat opening or more than 10 deg. twist from
the plane of the unbent hook.
1910.180(d)(3)(vi)
Rope reeving for noncompliance with manufacturer's
recommendations.
1910.180(d)(3)(vii)
Electrical apparatus for malfunctioning, signs of
excessive deterioration, dirt, and moisture accumulation.
Periodic Inspection
Periodic inspection." Complete inspections of
the crane shall be performed at intervals as
generally defined in paragraph (d)(2)(ii) of this
section depending upon its activity, severity of
service, and environment, or as specifically
indicated below. These inspections shall include
the requirements of paragraph (d)(3) of this
section and in addition, items such as the
following. Any deficiencies such as listed shall
be carefully examined and determination made
as to whether they constitute a safety hazard:
Inspection Steps Page 1
 Deformed, cracked, or corroded members in the crane structure and
boom.
 1910.180(d)(4)(ii)
 Loose bolts or rivets.
 1910.180(d)(4)(iii)
 Cracked or worn sheaves and drums.
 ..1910.180(d)(4)(iv)
 1910.180(d)(4)(iv)
 Worn, cracked, or distorted parts such as pins, bearings, shafts,
gears, rollers and locking devices.
 1910.180(d)(4)(v)
 Excessive wear on brake and clutch system parts, linings, pawls,
and ratchets.
Inspection Steps Page 2
1910.180(d)(4)(vi)
Load, boom angle, and other indicators over their full
range, for any significant inaccuracies.
1910.180(d)(4)(vii)
Gasoline, diesel, electric, or other power plants for
improper performance or noncompliance with safety
requirements.
1910.180(d)(4)(viii)
Excessive wear of chain-drive sprockets and excessive
chain stretch.
1910.180(d)(4)(ix)
Travel steering, braking, and locking devices, for
malfunction.
1910.180(d)(4)(x)
Excessively worn or damaged tires.
Rope Inspection
Rope inspection." -
1910.180(g)(1)
"Running ropes." A thorough inspection of all ropes in
use shall be made at least once a month and a
certification record which includes the date of inspection,
the signature of the person who performed the
inspection and an identifier for the ropes shall be
prepared and kept on file where readily available. All
inspections shall be performed by an appointed or
authorized person. Any deterioration, resulting in
appreciable loss of original strength shall be carefully
observed and determination made as to whether further
use of the rope would constitute a safety hazard. Some
of the conditions that could result in an appreciable loss
of strength are the following:
..1910.180(g)(1)(i)
Rope inspection #2
1910.180(g)(1)(i)
Reduction of rope diameter below nominal diameter due
to loss of core support, internal or external corrosion, or
wear of outside wires.
1910.180(g)(1)(ii)
A number of broken outside wires and the degree of
distribution of concentration of such broken wires.
1910.180(g)(1)(iii)
Worn outside wires.
1910.180(g)(1)(iv)
Corroded or broken wires at end connections.
1910.180(g)(1)(v)
Corroded, cracked, bent, worn, or improperly applied
end connections.
Rope inspection # 3
1910.180(g)(1)(vi)
Severe kinking, crushing, cutting, or
unstranding.
1910.180(g)(2)
"Other ropes."
1910.180(g)(2)(i)
Heavy wear and/or broken wires may occur in
sections in contact with equalizer sheaves or
other sheaves where rope travel is limited, or
with saddles. Particular care shall be taken to
inspect ropes at these locations.
..1910.180(g)(2)(ii)
NEVER USE A BAD ROPE!
KNOW THE LOAD
THE OPERATOR IS NEVER TO
EXCEED THE CAPACITY OF THE
CRANE.
Look on shippers tag for the weight or
weigh the item on shipping scale.
 If unsure always ask !
Testing
Testing" -
1910.180(e)(1)
"Operational tests."
1910.180(e)(1)(i)
In addition to prototype tests and quality-control
measures, each new production crane shall be
tested by the manufacturer to the extent
necessary to insure compliance with the
operational requirements of this paragraph
including functions such as the following:
Maintenance Procedure
"Maintenance procedure" - "General."
After adjustments and repairs have been
made the crane shall not be operated until
all guards have been reinstalled, safety
devices reactivated, and maintenance
equipment removed
Idle Ropes
All rope which has been idle for a period of a month or
more due to shutdown or storage of a crane on which it
is installed shall be given a thorough inspection before it
is used. This inspection shall be for all types of
deterioration and shall be performed by an appointed or
authorized person whose approval shall be required for
further use of the rope. A certification record which
includes the date of inspection, the signature of the
person who performed the inspection, and an identifier
for the rope which was inspected shall be prepared and
kept readily available.
1910.180(g)(2)(iii)
Particular care shall be taken in the inspection of
nonrotating rope.
1910.180(h)
Records
"Inspection records." Certification records
which include the date of inspection, the
signature of the person who performed the
inspection and the serial number, or other
identifier, of the crane which was
inspected shall be made monthly on
critical items in use such as brakes, crane
hooks, and ropes. This certification record
shall be kept readily available.
PATH OF OPERATOR
DAILY INSPECTION
1910.179
B30.2 OPERATION
1. PROPER OPERATION, ALL MOTIONS,PROPER MARKING ON CONROLER
2. CHECK ALL BRAKES (NO EXCESSIVE DRIFT) (REVERSE PLUGGING OK)
3.CHECK LOWER HOOK FOR DAMAGE (NICKS,WELDS,SADDLE WEAR, HOOK
BEARING)
4. CHECK HOOK BEARING (FREE MOVEMENT) & HOOK LATCH FOR
PROPER FIT, 15% HOOK STRECH, 10% TWIST
5. CHECK WIRE ROPE FOR BROKEN WIRES,LOSE OF DIAM,KINKS, CRUSHED,OR
ANY DAMAGE.
6. CHECK ROPE REEVING FOR PROPER INSTALLATION AND FIT ON DRUM.
7. CHECK LIMIT DEVICE, CHECK BY INCHING, & FULL SPEED, REVERSE PHASE.
8.OIL LEAKAGE ( NO LEAKS ALLOWED)
19. UNUSUAL NOISE AND VIBRATION ( REPORT ANY IF FOUND)
10. WARNING AND SAFETY LABLES, CHECK TO SEE IF INSTALLED, PENDENT,
DISCONNECT.
PATH OF THE OPERATOR
INSPECTION DAILY CHECK
Lower block
Check Sheaves and Lower Hook in block
assy. Check the hook bearing for free
movement.
The lower hook must have a safety latch.
Note: Unless it causes operator more
harm than good. (must be written down
why)
Load testing to 100% to 110% max.
OPERATING CONTROLS
ALL LABLES MUST BE LEGABLE
MUST HAVE STRAIN RELIEF ATTACHED
PENDENT MUST NOT HAVE ANY CRACKS

Contenu connexe

Tendances

selection operation and maintainance of mobile cranes ( for education purpose...
selection operation and maintainance of mobile cranes ( for education purpose...selection operation and maintainance of mobile cranes ( for education purpose...
selection operation and maintainance of mobile cranes ( for education purpose...swaroop k s
 
Crane Safety Awareness by University of Texas Arlington
Crane Safety Awareness by University of Texas ArlingtonCrane Safety Awareness by University of Texas Arlington
Crane Safety Awareness by University of Texas ArlingtonAtlantic Training, LLC.
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training PresentationFAIZ FAREED
 
Crawler crane introduction
Crawler crane   introductionCrawler crane   introduction
Crawler crane introductionBhushan Goyal
 
1910.179 osha class
1910.179 osha class1910.179 osha class
1910.179 osha classBill Brown
 
Basic load out methodologies introduction
Basic load out methodologies introductionBasic load out methodologies introduction
Basic load out methodologies introductionBruce nguyen
 
Crane Accidents and Emergencies Causes, Repairs and Prevention
Crane Accidents and Emergencies Causes, Repairs and PreventionCrane Accidents and Emergencies Causes, Repairs and Prevention
Crane Accidents and Emergencies Causes, Repairs and PreventionPortek International Pte Ltd
 
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...PowerLift Events
 
Crane Safety & Rigging
Crane Safety & RiggingCrane Safety & Rigging
Crane Safety & Riggingfcarlson
 
Rigging | Rigging Safety | Gaurav Singh Rajput
Rigging | Rigging Safety | Gaurav Singh RajputRigging | Rigging Safety | Gaurav Singh Rajput
Rigging | Rigging Safety | Gaurav Singh RajputGaurav Singh Rajput
 
Lifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sitesLifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sitesSimon Faulkner-Duke
 

Tendances (20)

selection operation and maintainance of mobile cranes ( for education purpose...
selection operation and maintainance of mobile cranes ( for education purpose...selection operation and maintainance of mobile cranes ( for education purpose...
selection operation and maintainance of mobile cranes ( for education purpose...
 
Cranes ppt
Cranes pptCranes ppt
Cranes ppt
 
Crane Incident Handbook
Crane Incident Handbook Crane Incident Handbook
Crane Incident Handbook
 
Mobile crane
Mobile craneMobile crane
Mobile crane
 
CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK CRANE SAFETY HANDBOOK
CRANE SAFETY HANDBOOK
 
Crane Safety Awareness by University of Texas Arlington
Crane Safety Awareness by University of Texas ArlingtonCrane Safety Awareness by University of Texas Arlington
Crane Safety Awareness by University of Texas Arlington
 
Lifting tools
Lifting toolsLifting tools
Lifting tools
 
Mobile crane
Mobile craneMobile crane
Mobile crane
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training Presentation
 
Crawler crane introduction
Crawler crane   introductionCrawler crane   introduction
Crawler crane introduction
 
Rigging
RiggingRigging
Rigging
 
1910.179 osha class
1910.179 osha class1910.179 osha class
1910.179 osha class
 
Basic load out methodologies introduction
Basic load out methodologies introductionBasic load out methodologies introduction
Basic load out methodologies introduction
 
Crane Accidents and Emergencies Causes, Repairs and Prevention
Crane Accidents and Emergencies Causes, Repairs and PreventionCrane Accidents and Emergencies Causes, Repairs and Prevention
Crane Accidents and Emergencies Causes, Repairs and Prevention
 
2015 CRW - Setting Up for Success
2015 CRW - Setting Up for Success2015 CRW - Setting Up for Success
2015 CRW - Setting Up for Success
 
2014 CRW - Operating Cranes around Power Lines
2014 CRW - Operating Cranes around Power Lines2014 CRW - Operating Cranes around Power Lines
2014 CRW - Operating Cranes around Power Lines
 
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
 
Crane Safety & Rigging
Crane Safety & RiggingCrane Safety & Rigging
Crane Safety & Rigging
 
Rigging | Rigging Safety | Gaurav Singh Rajput
Rigging | Rigging Safety | Gaurav Singh RajputRigging | Rigging Safety | Gaurav Singh Rajput
Rigging | Rigging Safety | Gaurav Singh Rajput
 
Lifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sitesLifting plans for non-crane lifts on small construction sites
Lifting plans for non-crane lifts on small construction sites
 

En vedette

Endeavour wharf centre whitby 29.04.15
Endeavour wharf centre whitby 29.04.15Endeavour wharf centre whitby 29.04.15
Endeavour wharf centre whitby 29.04.15Edison Mugoya
 
EOT CRANES-TECHNICAL RBS Cranes & Engineering 9466626496
EOT CRANES-TECHNICAL RBS Cranes & Engineering 9466626496EOT CRANES-TECHNICAL RBS Cranes & Engineering 9466626496
EOT CRANES-TECHNICAL RBS Cranes & Engineering 9466626496AJIT HOODA
 
Sop overhead crane
Sop overhead craneSop overhead crane
Sop overhead craneWina Indah
 
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANES
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANESB30 5 ASME-MOBILE AND LOCOMOTIVE CRANES
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANESANA ISABEL R.R.
 
Team rockets oms.
Team rockets oms.Team rockets oms.
Team rockets oms.c_liberty
 
Team Orange Lucid Chart
Team Orange Lucid ChartTeam Orange Lucid Chart
Team Orange Lucid ChartTeamOrange
 
Smart pointer
Smart pointerSmart pointer
Smart pointerNewHeart
 
Web framework security
Web framework securityWeb framework security
Web framework securityNewHeart
 
Sql server 2014 what's new-
Sql server 2014  what's new-Sql server 2014  what's new-
Sql server 2014 what's new-Stuart Ainsworth
 
Tugas V Mektan I Redha RM
Tugas V Mektan I Redha RMTugas V Mektan I Redha RM
Tugas V Mektan I Redha RMRedha RM
 
Presentació física química.
Presentació física química.Presentació física química.
Presentació física química.clarart
 

En vedette (17)

Truck mounted crane
Truck mounted craneTruck mounted crane
Truck mounted crane
 
Endeavour wharf centre whitby 29.04.15
Endeavour wharf centre whitby 29.04.15Endeavour wharf centre whitby 29.04.15
Endeavour wharf centre whitby 29.04.15
 
EOT CRANES-TECHNICAL RBS Cranes & Engineering 9466626496
EOT CRANES-TECHNICAL RBS Cranes & Engineering 9466626496EOT CRANES-TECHNICAL RBS Cranes & Engineering 9466626496
EOT CRANES-TECHNICAL RBS Cranes & Engineering 9466626496
 
Sop overhead crane
Sop overhead craneSop overhead crane
Sop overhead crane
 
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANES
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANESB30 5 ASME-MOBILE AND LOCOMOTIVE CRANES
B30 5 ASME-MOBILE AND LOCOMOTIVE CRANES
 
Keselamatan crane
Keselamatan crane Keselamatan crane
Keselamatan crane
 
Team rockets oms.
Team rockets oms.Team rockets oms.
Team rockets oms.
 
Team Orange Lucid Chart
Team Orange Lucid ChartTeam Orange Lucid Chart
Team Orange Lucid Chart
 
Pdhpe slideshow
Pdhpe slideshowPdhpe slideshow
Pdhpe slideshow
 
Smart pointer
Smart pointerSmart pointer
Smart pointer
 
Web framework security
Web framework securityWeb framework security
Web framework security
 
Assignmen1
Assignmen1Assignmen1
Assignmen1
 
Sql server 2014 what's new-
Sql server 2014  what's new-Sql server 2014  what's new-
Sql server 2014 what's new-
 
заохочення і покарання
заохочення  і покараннязаохочення  і покарання
заохочення і покарання
 
Tugas V Mektan I Redha RM
Tugas V Mektan I Redha RMTugas V Mektan I Redha RM
Tugas V Mektan I Redha RM
 
мова Html
мова Htmlмова Html
мова Html
 
Presentació física química.
Presentació física química.Presentació física química.
Presentació física química.
 

Similaire à Truck crane training bill brown

2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sitesPrastowo Priyatmoko
 
Crane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptxCrane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptxVikasMore37
 
Crane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdfCrane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdfManoj Kumar
 
Rig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.docRig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.docYasserAbdulkareem1
 
Safety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationSafety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationComplianceSigns, LLC
 
Quality Control Operator Training &.pptx
Quality Control Operator Training &.pptxQuality Control Operator Training &.pptx
Quality Control Operator Training &.pptxAizazFarhat3
 
Mechanical Handling updated.ppt
Mechanical Handling updated.pptMechanical Handling updated.ppt
Mechanical Handling updated.pptCheDillon1
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdfdinesh622857
 
Crane operator safety procedure
Crane operator safety procedureCrane operator safety procedure
Crane operator safety procedureAbdul Shukur
 
Cranes and Derricks-2.PPT
Cranes and Derricks-2.PPTCranes and Derricks-2.PPT
Cranes and Derricks-2.PPTHesamEsfandi
 
Safety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekSafety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekRoseGaming1
 
Overhead-Cranes safety training.ppt
Overhead-Cranes safety training.pptOverhead-Cranes safety training.ppt
Overhead-Cranes safety training.pptRazFazwan
 
NGI-Cranes-Part 01
NGI-Cranes-Part 01NGI-Cranes-Part 01
NGI-Cranes-Part 01lifecombo
 

Similaire à Truck crane training bill brown (20)

2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites
 
Crane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptxCrane-Safety-PowerPoint-Presentation.pptx
Crane-Safety-PowerPoint-Presentation.pptx
 
Crane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdfCrane Safety Tips for Construction Project..pdf
Crane Safety Tips for Construction Project..pdf
 
Rig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.docRig Move Management and Logistics Plan.doc
Rig Move Management and Logistics Plan.doc
 
Safety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane OperationSafety Tip: 10 Steps to Safer Crane Operation
Safety Tip: 10 Steps to Safer Crane Operation
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
 
Quality Control Operator Training &.pptx
Quality Control Operator Training &.pptxQuality Control Operator Training &.pptx
Quality Control Operator Training &.pptx
 
Rigger safety .pdf
Rigger safety                        .pdfRigger safety                        .pdf
Rigger safety .pdf
 
Rigging Course .pdf
Rigging Course                       .pdfRigging Course                       .pdf
Rigging Course .pdf
 
Mechanical Handling updated.ppt
Mechanical Handling updated.pptMechanical Handling updated.ppt
Mechanical Handling updated.ppt
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdf
 
Failure analysis mtn526
Failure analysis mtn526Failure analysis mtn526
Failure analysis mtn526
 
Crane operator safety procedure
Crane operator safety procedureCrane operator safety procedure
Crane operator safety procedure
 
safe lift EMERSON EDUARDO RODRIGUES
safe lift EMERSON EDUARDO RODRIGUESsafe lift EMERSON EDUARDO RODRIGUES
safe lift EMERSON EDUARDO RODRIGUES
 
Cranes and Derricks-2.PPT
Cranes and Derricks-2.PPTCranes and Derricks-2.PPT
Cranes and Derricks-2.PPT
 
Safety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekSafety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhek
 
SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
Overhead-Cranes safety training.ppt
Overhead-Cranes safety training.pptOverhead-Cranes safety training.ppt
Overhead-Cranes safety training.ppt
 
NGI-Cranes-Part 01
NGI-Cranes-Part 01NGI-Cranes-Part 01
NGI-Cranes-Part 01
 

Dernier

Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseAnaAcapella
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxdhanalakshmis0310
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxAmanpreet Kaur
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docxPoojaSen20
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Association for Project Management
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Jisc
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...pradhanghanshyam7136
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxheathfieldcps1
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...Poonam Aher Patil
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Third Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxThird Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxAmita Gupta
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSCeline George
 

Dernier (20)

Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptx
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Third Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxThird Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptx
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 

Truck crane training bill brown

  • 1. 1910.180 TRUCK CRANE OPERATION REVIEW. PART 1 TRAINER: BILL BROWN INSPECTION MANAGER inspections4me@gmail.com
  • 2. Wheel mounted crane (wagon crane) consists of a rotating superstructure with power plant, operating machinery and boom, mounted on a base or platform equipped with axles and rubber tired wheels for travel. Its function is to hoist and swing loads at various radii.
  • 3. Truck Crane A truck Crane consists of a rotating superstructure with power plant, operating machinery and boom, mounted on a automotive truck equipped with a power plant for travel. Its function is to hoist and swing loads at various radii.
  • 4. . DEFINITIONS AUTHORIZED: IS ONE APPOINTED OR CREDENTIALLED BY A DULY CONSTITUTED ADMINISTRATIVE OR REGULATORY AUTHORITY
  • 5. Competent Person A competent person is one who by knowledge, training and experience has demonstrated the ability to solve problems and preform functions relating to the subject matter and work
  • 10. O S H A Occupational Safety & Health Administration Federal Law (Required action)
  • 11. A N S I American National Standards Institute 
  • 12. .Reaction Time Measure how quickly the person reacts to a set of signals, or to an emergency
  • 13. Distance Judgement Measurement of depth perception is important for Crane Operators. Hearing Several devices are available to test hearing ability. The person should be able to meet standard requirements.
  • 14. ANGLE INDICATOR MEASURES ANGLE OF BOOM TO HORIZON
  • 16. SAFETY RULES There are many safety rules that have been set up to be observed by Crane Operators. However, if you follow these rules you will observe most of the necessary precautions while operating your crane. .
  • 17. 1. No one but a regularly authorized operator is allowed to use any crane. 2. Load Rating Chart with clearly legible letters and figures shall be provided and fixed to the crane. Must be clearly visible to operator at there controls 3. Before moving crane, be sure that the hook is high enough to Clear all obstacles.
  • 18. 4. The operator SHALL NOT leave their position at the controls while a load is suspended. 5. The Cranes Wire Rope SHALL NOT be wrapped around. the load. Slings must be utilized 6. Do Not carry load over people on floor; sound warning devices if crane is equipped to warn persons nearby.
  • 19. 7. Do not allow anyone to ride on a load carried by the crane, or on the crane hook. 8. Do not drag slings chains or lifting devices out from under loads that have been landed
  • 20. 9. If you are asked to do something that you DO NOT believe is safe, you should refuse to do it, and call your foreman/supervisor in charge for advice 10.DO NOT exceed the rated capacity of your Hoist/Crane 11. An Operator MUST NOT operate a crane if he/she is not physically fit to do so.
  • 21. 12. In case of a problem always STOP operation and open the power switch. If your crane fails to respond correctly call your foreman/supervisor. Attempting to get out of difficulty by repeating the operation may make the condition worse instead of better
  • 22. 15. Crane operators must follow the signals given to them only by authorized persons (THE ASSIGNED RIGGER) and should ignore directions given by others during operation of their equipment. The only EXCEPTION to this rule is if ANYONE commands them to EMERGENCY STOP.
  • 23. Crane Hand Signals BOOM UP Hoist Up Slow Hoist Down Boom Down Hoist Up Walk Crane
  • 24. Crane Hand Signals #2 Swing Crane ------------------/ Retract Boom-------/ Everything Slow EXTEND BOOM
  • 25. Crane Hand Signals # 3 Emergency Stop------------------------------------- Routine Stop------------
  • 26. Who can give the hand signals? or Who can be a signaler? a person qualified to give crane signals to the operator, there should be only one designated signaler at a time, if signalers are changing between each other, the one in charge should wear a clearly visible badge of authority, a crane operator should move loads only on signals from one signaler, a crane operator must obey STOP signals no matter who gives it.  
  • 27. DON’T BE A HEADLINE SUMMARY Every worker should know crane hand signals. Knowing the signals may allow you to help out when needed If you are asked to be a signal person, make sure you are using the same signals as other workers and operators on the project When tower cranes or situations where hand signals are not safe enough, ensure that a two-way radio is used for voice communication. This will give you direct contact with the operator. Whatever system you use - hands or radio - make sure the equipment and workers are able to do the job right.   Don't Be a Headline
  • 28. Cranes Cranes are designed to make “Vertical lifts of loads ONLY, DO NOT angle/side load unless it has been determined by a qualified person not to pose a hazard to equipment or personnel.
  • 29. Limit Devices A limiting device shall be installed and maintainted to prevent the hook or other end fitting from contacting the upper sheaves.
  • 30. Booms When sections of booms are added or removed, full number of bolts or pins of the material and size recommended by the manfacture
  • 31. Fire Extinguishers (i) A carbon dioxide, dry chemical, or equivalent fire extinguisher shall be kept in cab or vicinity of the crane (ii) Operating and maintenance personal shall be made familiar with the use and care of the fire extinguishers provided.
  • 32. Power Lines For operating near electric power lines: See 1910.333 (c) (3)
  • 33. Load Rating Load ratings - where stability governs lifting performance." 1910.180(c)(1)(i) The margin of stability for determination of load ratings, with booms of stipulated lengths at stipulated working radii for the various types of crane mountings, is established by taking a percentage of the loads which will produce a condition of tipping or balance with the boom in the least stable direction, relative to the mounting. The load ratings shall not exceed the following percentages for cranes, with the indicated types of mounting under conditions stipulated in paragraphs (c) (1)(ii) and (iii) of this section. Truck cranes 85%
  • 34. 1910.180(c)(2) "Load rating chart." A substantial and durable rating chart with clearly legible letters and figures shall be provided with each crane and securely fixed to the crane cab in a location easily visible to the operator while seated at his control station. Load Rating Chart
  • 35. Inspection classification" - 1910.180(d)(1) "Initial inspection." Prior to initial use all new and altered cranes shall be inspected to insure compliance with provisions of this section. ..1910.180(d)(2) 1910.180(d)(2) "Regular inspection." Inspection procedure for cranes in regular service is divided into two general classifications based upon the intervals at which inspection should be performed. The intervals in turn are dependent upon the nature of the critical components of the crane and the degree of their exposure to wear, deterioration, or malfunction. The two general classifications are herein designated as "frequent" and "periodic", with respective intervals between inspections as defined below:
  • 36. Inspection of your Truck Crane Frequent inspection: Daily to monthly intervals. 1910.180(d)(2)(ii) Periodic inspection: 1- to 12- month intervals, or as specifically recommended by the manufacturer. 1910.180(d)(3) "Frequent inspection." Items such as the following shall be inspected for defects at intervals as defined in paragraph (d)(2)(i) of this section or as specifically indicated including observation during operation for any defects which might appear between regular inspections. Any deficiencies such as listed shall be carefully examined and determination made as to whether they constitute a safety hazard:
  • 37. Daily Inspections to monthly 1910.180(d)(3)(i) All control mechanisms for maladjustment interfering with proper operation: Daily. 1910.180(d)(3)(ii) All control mechanisms for excessive wear of components and contamination by lubricants or other foreign matter. 1910.180(d)(3)(iii) All safety devices for malfunction. 1910.180(d)(3)(iv) Deterioration or leakage in air or hydraulic systems: Daily.
  • 38. Page 2 of inspections procedours ..1910.180(d)(3)(v) 1910.180(d)(3)(v) Crane hooks with deformations or cracks. For hooks with cracks or having more than 15 percent in excess of normal throat opening or more than 10 deg. twist from the plane of the unbent hook. 1910.180(d)(3)(vi) Rope reeving for noncompliance with manufacturer's recommendations. 1910.180(d)(3)(vii) Electrical apparatus for malfunctioning, signs of excessive deterioration, dirt, and moisture accumulation.
  • 39. Periodic Inspection Periodic inspection." Complete inspections of the crane shall be performed at intervals as generally defined in paragraph (d)(2)(ii) of this section depending upon its activity, severity of service, and environment, or as specifically indicated below. These inspections shall include the requirements of paragraph (d)(3) of this section and in addition, items such as the following. Any deficiencies such as listed shall be carefully examined and determination made as to whether they constitute a safety hazard:
  • 40. Inspection Steps Page 1  Deformed, cracked, or corroded members in the crane structure and boom.  1910.180(d)(4)(ii)  Loose bolts or rivets.  1910.180(d)(4)(iii)  Cracked or worn sheaves and drums.  ..1910.180(d)(4)(iv)  1910.180(d)(4)(iv)  Worn, cracked, or distorted parts such as pins, bearings, shafts, gears, rollers and locking devices.  1910.180(d)(4)(v)  Excessive wear on brake and clutch system parts, linings, pawls, and ratchets.
  • 41. Inspection Steps Page 2 1910.180(d)(4)(vi) Load, boom angle, and other indicators over their full range, for any significant inaccuracies. 1910.180(d)(4)(vii) Gasoline, diesel, electric, or other power plants for improper performance or noncompliance with safety requirements. 1910.180(d)(4)(viii) Excessive wear of chain-drive sprockets and excessive chain stretch. 1910.180(d)(4)(ix) Travel steering, braking, and locking devices, for malfunction. 1910.180(d)(4)(x) Excessively worn or damaged tires.
  • 42. Rope Inspection Rope inspection." - 1910.180(g)(1) "Running ropes." A thorough inspection of all ropes in use shall be made at least once a month and a certification record which includes the date of inspection, the signature of the person who performed the inspection and an identifier for the ropes shall be prepared and kept on file where readily available. All inspections shall be performed by an appointed or authorized person. Any deterioration, resulting in appreciable loss of original strength shall be carefully observed and determination made as to whether further use of the rope would constitute a safety hazard. Some of the conditions that could result in an appreciable loss of strength are the following: ..1910.180(g)(1)(i)
  • 43. Rope inspection #2 1910.180(g)(1)(i) Reduction of rope diameter below nominal diameter due to loss of core support, internal or external corrosion, or wear of outside wires. 1910.180(g)(1)(ii) A number of broken outside wires and the degree of distribution of concentration of such broken wires. 1910.180(g)(1)(iii) Worn outside wires. 1910.180(g)(1)(iv) Corroded or broken wires at end connections. 1910.180(g)(1)(v) Corroded, cracked, bent, worn, or improperly applied end connections.
  • 44. Rope inspection # 3 1910.180(g)(1)(vi) Severe kinking, crushing, cutting, or unstranding. 1910.180(g)(2) "Other ropes." 1910.180(g)(2)(i) Heavy wear and/or broken wires may occur in sections in contact with equalizer sheaves or other sheaves where rope travel is limited, or with saddles. Particular care shall be taken to inspect ropes at these locations. ..1910.180(g)(2)(ii)
  • 45. NEVER USE A BAD ROPE!
  • 46. KNOW THE LOAD THE OPERATOR IS NEVER TO EXCEED THE CAPACITY OF THE CRANE. Look on shippers tag for the weight or weigh the item on shipping scale.  If unsure always ask !
  • 47. Testing Testing" - 1910.180(e)(1) "Operational tests." 1910.180(e)(1)(i) In addition to prototype tests and quality-control measures, each new production crane shall be tested by the manufacturer to the extent necessary to insure compliance with the operational requirements of this paragraph including functions such as the following:
  • 48. Maintenance Procedure "Maintenance procedure" - "General." After adjustments and repairs have been made the crane shall not be operated until all guards have been reinstalled, safety devices reactivated, and maintenance equipment removed
  • 49. Idle Ropes All rope which has been idle for a period of a month or more due to shutdown or storage of a crane on which it is installed shall be given a thorough inspection before it is used. This inspection shall be for all types of deterioration and shall be performed by an appointed or authorized person whose approval shall be required for further use of the rope. A certification record which includes the date of inspection, the signature of the person who performed the inspection, and an identifier for the rope which was inspected shall be prepared and kept readily available. 1910.180(g)(2)(iii) Particular care shall be taken in the inspection of nonrotating rope. 1910.180(h)
  • 50. Records "Inspection records." Certification records which include the date of inspection, the signature of the person who performed the inspection and the serial number, or other identifier, of the crane which was inspected shall be made monthly on critical items in use such as brakes, crane hooks, and ropes. This certification record shall be kept readily available.
  • 51.
  • 52. PATH OF OPERATOR DAILY INSPECTION 1910.179 B30.2 OPERATION
  • 53. 1. PROPER OPERATION, ALL MOTIONS,PROPER MARKING ON CONROLER 2. CHECK ALL BRAKES (NO EXCESSIVE DRIFT) (REVERSE PLUGGING OK) 3.CHECK LOWER HOOK FOR DAMAGE (NICKS,WELDS,SADDLE WEAR, HOOK BEARING) 4. CHECK HOOK BEARING (FREE MOVEMENT) & HOOK LATCH FOR PROPER FIT, 15% HOOK STRECH, 10% TWIST 5. CHECK WIRE ROPE FOR BROKEN WIRES,LOSE OF DIAM,KINKS, CRUSHED,OR ANY DAMAGE. 6. CHECK ROPE REEVING FOR PROPER INSTALLATION AND FIT ON DRUM. 7. CHECK LIMIT DEVICE, CHECK BY INCHING, & FULL SPEED, REVERSE PHASE. 8.OIL LEAKAGE ( NO LEAKS ALLOWED) 19. UNUSUAL NOISE AND VIBRATION ( REPORT ANY IF FOUND) 10. WARNING AND SAFETY LABLES, CHECK TO SEE IF INSTALLED, PENDENT, DISCONNECT. PATH OF THE OPERATOR INSPECTION DAILY CHECK
  • 54.
  • 55. Lower block Check Sheaves and Lower Hook in block assy. Check the hook bearing for free movement. The lower hook must have a safety latch. Note: Unless it causes operator more harm than good. (must be written down why) Load testing to 100% to 110% max.
  • 56. OPERATING CONTROLS ALL LABLES MUST BE LEGABLE MUST HAVE STRAIN RELIEF ATTACHED PENDENT MUST NOT HAVE ANY CRACKS

Notes de l'éditeur

  1. DALILY INSPECTIONS PER 1910.179 --------- 29 CFR-------------
  2. PENDENT STATION CHECKED DAILY