Refurbishing Heathrow Airport Terminal 1
2
PROJECT BRIEF
• London Heathrow Airport is the busiest
international airport in the world
• Terminal 1 had been out of date and
badly in need of refurbishment, with the
40-year old building not seeing any
significant updates since it was built in
the 60s.
• as well as the upcoming opening of
Terminal 5 and the introduction of
international passengers to Terminal 1
3
STAKEHOLDERS
BRITISH AIRPORT
AUTHORITY
STAR ALLIANCE David Buisson Contractors
PMP
4
STAKEHOLDERS
BMI AIRLINES 11 TOP TIER SUPPLIERS
5
CHALLENGES
Structural challenge
Scope challenge
Communication and time management
Planning and scheduling
Cost and procurement
Environmental challenges
6
RISKS INVOLVED
Health and safety risk
Electrical risk
Financial risk
Asbestos risk
7
SOLUTIONS
ENVIRONMENTAL CHALLENGES
 Focus on renovation versus new construction
 Installation of energy-saving and sustainable
measures
TECHNOLOGICAL CHALLENGES
Replacing existing systems with the new ones like office
network system, flight info screens, regulatory systems for
passenger processing & closed-circuit TV
RISK MANAGEMENT
 Develop and maintain two primary risk management
schedules
 Risk management schedules were reviewed, updated
and published through a formal review meeting
Health & safety challenge
Adopt safety department to find out risks involved for
every contractor
8
CONCLUSION
• Heathrow airport terminal 1 has completed on time and with in budget
• It has good health and safety records without reported incidents
• Effective teamwork between numerous contractors, suppliers, stakeholders and
various support functions.
• All challenges were successfully met by the project team.
• The project was completed on time in September 2008
9

Contenu connexe

Tendances

Design and creative ideas for no frills airports in tier-ii & tier-iii cities
Design and creative ideas for no frills airports in tier-ii & tier-iii citiesDesign and creative ideas for no frills airports in tier-ii & tier-iii cities
Design and creative ideas for no frills airports in tier-ii & tier-iii cities
Rajiv Babu Chintala
 
Design Of An Electric Cart For Airport Terminal
Design Of An Electric Cart For Airport TerminalDesign Of An Electric Cart For Airport Terminal
Design Of An Electric Cart For Airport Terminal
Jithesh Ramesh
 

Tendances (20)

Airport terminal design (lecture note)
Airport terminal design (lecture note)Airport terminal design (lecture note)
Airport terminal design (lecture note)
 
Orlando international airport
Orlando international airportOrlando international airport
Orlando international airport
 
MAGCARGO_Brochure
MAGCARGO_BrochureMAGCARGO_Brochure
MAGCARGO_Brochure
 
Heathrow Terminal 5
Heathrow Terminal 5Heathrow Terminal 5
Heathrow Terminal 5
 
Incheon international airport
Incheon international airportIncheon international airport
Incheon international airport
 
Presentation on Airport Engineering
Presentation on Airport EngineeringPresentation on Airport Engineering
Presentation on Airport Engineering
 
Airport facilities
Airport facilitiesAirport facilities
Airport facilities
 
Sam Linke - Session 3: Airport City Design
Sam Linke - Session 3: Airport City DesignSam Linke - Session 3: Airport City Design
Sam Linke - Session 3: Airport City Design
 
Jeddah airport case study
Jeddah airport case studyJeddah airport case study
Jeddah airport case study
 
Design and creative ideas for no frills airports in tier-ii & tier-iii cities
Design and creative ideas for no frills airports in tier-ii & tier-iii citiesDesign and creative ideas for no frills airports in tier-ii & tier-iii cities
Design and creative ideas for no frills airports in tier-ii & tier-iii cities
 
Mr. Rami Semaan Senior Transport Expert, TMS Consult, Lebanon
Mr. Rami Semaan Senior Transport Expert, TMS Consult, Lebanon   Mr. Rami Semaan Senior Transport Expert, TMS Consult, Lebanon
Mr. Rami Semaan Senior Transport Expert, TMS Consult, Lebanon
 
riyadh airport
riyadh airportriyadh airport
riyadh airport
 
Marculesti International Airport
Marculesti International AirportMarculesti International Airport
Marculesti International Airport
 
Design Of An Electric Cart For Airport Terminal
Design Of An Electric Cart For Airport TerminalDesign Of An Electric Cart For Airport Terminal
Design Of An Electric Cart For Airport Terminal
 
Airport Engineering
Airport EngineeringAirport Engineering
Airport Engineering
 
Airlines and airports
Airlines and airportsAirlines and airports
Airlines and airports
 
The port of alexandria
The port of alexandriaThe port of alexandria
The port of alexandria
 
SPEDAP AIRPORT DESIGN
SPEDAP AIRPORT DESIGNSPEDAP AIRPORT DESIGN
SPEDAP AIRPORT DESIGN
 
Airport engineering
Airport engineeringAirport engineering
Airport engineering
 
Hamad international airport
Hamad international airportHamad international airport
Hamad international airport
 

Similaire à Heathrow airport

Changing the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docxChanging the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docx
cravennichole326
 
Changing the Face at the Busiest Airport in the World th.docx
Changing the Face  at the Busiest Airport  in the World th.docxChanging the Face  at the Busiest Airport  in the World th.docx
Changing the Face at the Busiest Airport in the World th.docx
cravennichole326
 
pipleling hazard SN PERFOEMANCE OPTIMAZITION
pipleling hazard SN PERFOEMANCE OPTIMAZITIONpipleling hazard SN PERFOEMANCE OPTIMAZITION
pipleling hazard SN PERFOEMANCE OPTIMAZITION
nathsibun9
 
commissioning-federal-facilities.pdf
commissioning-federal-facilities.pdfcommissioning-federal-facilities.pdf
commissioning-federal-facilities.pdf
Vincent Bui
 
Girish-Kabra-Centrica-Energy1
Girish-Kabra-Centrica-Energy1Girish-Kabra-Centrica-Energy1
Girish-Kabra-Centrica-Energy1
Girish Kabra
 
Phil Davies and Tim Surgenor
Phil Davies and Tim SurgenorPhil Davies and Tim Surgenor
Phil Davies and Tim Surgenor
Informa Australia
 
Demonstration case studies
Demonstration case studiesDemonstration case studies
Demonstration case studies
parkerjce
 

Similaire à Heathrow airport (20)

Changing the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docxChanging the Face at the Busiest Airport in the World thro.docx
Changing the Face at the Busiest Airport in the World thro.docx
 
Changing the Face at the Busiest Airport in the World th.docx
Changing the Face  at the Busiest Airport  in the World th.docxChanging the Face  at the Busiest Airport  in the World th.docx
Changing the Face at the Busiest Airport in the World th.docx
 
NigelCalverleyCV
NigelCalverleyCVNigelCalverleyCV
NigelCalverleyCV
 
Heathrow Airport - Refurbishment of Terminal 1
Heathrow Airport - Refurbishment of Terminal 1Heathrow Airport - Refurbishment of Terminal 1
Heathrow Airport - Refurbishment of Terminal 1
 
Heathrow Terminal 5 - Success or Failure?
Heathrow Terminal 5 - Success or Failure?Heathrow Terminal 5 - Success or Failure?
Heathrow Terminal 5 - Success or Failure?
 
M25 Media Pack
M25 Media PackM25 Media Pack
M25 Media Pack
 
pipleling hazard SN PERFOEMANCE OPTIMAZITION
pipleling hazard SN PERFOEMANCE OPTIMAZITIONpipleling hazard SN PERFOEMANCE OPTIMAZITION
pipleling hazard SN PERFOEMANCE OPTIMAZITION
 
German perez lifes50+ design summary - deep wind 2018
German perez   lifes50+ design summary - deep wind 2018German perez   lifes50+ design summary - deep wind 2018
German perez lifes50+ design summary - deep wind 2018
 
Implementing Business Continuity in Crossrail: Europe's Largest Construction ...
Implementing Business Continuity in Crossrail: Europe's Largest Construction ...Implementing Business Continuity in Crossrail: Europe's Largest Construction ...
Implementing Business Continuity in Crossrail: Europe's Largest Construction ...
 
Webinar: CO2 pipeline infrastructure: Lessons learned
Webinar: CO2 pipeline infrastructure: Lessons learnedWebinar: CO2 pipeline infrastructure: Lessons learned
Webinar: CO2 pipeline infrastructure: Lessons learned
 
commissioning-federal-facilities.pdf
commissioning-federal-facilities.pdfcommissioning-federal-facilities.pdf
commissioning-federal-facilities.pdf
 
Girish-Kabra-Centrica-Energy1
Girish-Kabra-Centrica-Energy1Girish-Kabra-Centrica-Energy1
Girish-Kabra-Centrica-Energy1
 
Phil Davies and Tim Surgenor
Phil Davies and Tim SurgenorPhil Davies and Tim Surgenor
Phil Davies and Tim Surgenor
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
 
Demonstration case studies
Demonstration case studiesDemonstration case studies
Demonstration case studies
 
Sustainability OF AIR Transportation
Sustainability OF AIR Transportation Sustainability OF AIR Transportation
Sustainability OF AIR Transportation
 
Refit london Hadjidakis
Refit london HadjidakisRefit london Hadjidakis
Refit london Hadjidakis
 
Opira - Indoor Air Quality Risk Management Planning
Opira - Indoor Air Quality Risk Management PlanningOpira - Indoor Air Quality Risk Management Planning
Opira - Indoor Air Quality Risk Management Planning
 
Richard (Rik) Stuart Barnett Resume
Richard (Rik) Stuart Barnett ResumeRichard (Rik) Stuart Barnett Resume
Richard (Rik) Stuart Barnett Resume
 
LEANWIND-EUSEW-2017-06-20FDM 5.pptx
LEANWIND-EUSEW-2017-06-20FDM 5.pptxLEANWIND-EUSEW-2017-06-20FDM 5.pptx
LEANWIND-EUSEW-2017-06-20FDM 5.pptx
 

Plus de AKHIL GEORGE (11)

Cc 2
Cc 2Cc 2
Cc 2
 
Sub presentation (1)
Sub presentation (1)Sub presentation (1)
Sub presentation (1)
 
Cbd
CbdCbd
Cbd
 
Essentials of-communication
Essentials of-communicationEssentials of-communication
Essentials of-communication
 
Quality ppt copy
Quality ppt   copyQuality ppt   copy
Quality ppt copy
 
HRM ASPECTS OF A PROJECT
HRM ASPECTS OF A PROJECT HRM ASPECTS OF A PROJECT
HRM ASPECTS OF A PROJECT
 
Toxic leadership ppt
Toxic leadership pptToxic leadership ppt
Toxic leadership ppt
 
Wood barn India: Trying to break Concrete Mindset
 Wood barn India: Trying to break Concrete Mindset Wood barn India: Trying to break Concrete Mindset
Wood barn India: Trying to break Concrete Mindset
 
Jackma
JackmaJackma
Jackma
 
Law presentation
Law presentationLaw presentation
Law presentation
 
Waste Disposal and Recycling
Waste Disposal and RecyclingWaste Disposal and Recycling
Waste Disposal and Recycling
 

Dernier

Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 

Dernier (20)

Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Plant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxPlant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptx
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 

Heathrow airport

  • 2. 2 PROJECT BRIEF • London Heathrow Airport is the busiest international airport in the world • Terminal 1 had been out of date and badly in need of refurbishment, with the 40-year old building not seeing any significant updates since it was built in the 60s. • as well as the upcoming opening of Terminal 5 and the introduction of international passengers to Terminal 1
  • 4. 4 STAKEHOLDERS BMI AIRLINES 11 TOP TIER SUPPLIERS
  • 5. 5 CHALLENGES Structural challenge Scope challenge Communication and time management Planning and scheduling Cost and procurement Environmental challenges
  • 6. 6 RISKS INVOLVED Health and safety risk Electrical risk Financial risk Asbestos risk
  • 7. 7 SOLUTIONS ENVIRONMENTAL CHALLENGES  Focus on renovation versus new construction  Installation of energy-saving and sustainable measures TECHNOLOGICAL CHALLENGES Replacing existing systems with the new ones like office network system, flight info screens, regulatory systems for passenger processing & closed-circuit TV RISK MANAGEMENT  Develop and maintain two primary risk management schedules  Risk management schedules were reviewed, updated and published through a formal review meeting Health & safety challenge Adopt safety department to find out risks involved for every contractor
  • 8. 8 CONCLUSION • Heathrow airport terminal 1 has completed on time and with in budget • It has good health and safety records without reported incidents • Effective teamwork between numerous contractors, suppliers, stakeholders and various support functions. • All challenges were successfully met by the project team. • The project was completed on time in September 2008