1  sur  39
1
Introduction
Need for the study
Objectives
Works done
Methodology
Table of
contents
2
• In developing countries like India the nature of the traffic conditions
are heterogeneous - no lane discipline is followed and no
segregation of different classes of vehicles.
• In order to study the traffic characteristics, the different vehicular
categories should be converted to one common standard vehicular
unit.
• It is the common practice to consider the passenger car as the
standard vehicle unit to convert the other vehicle classes and this
unit is called the Passenger Car Unit or PCU.
• The PCU value varies based on the traffic characteristics, hence
dynamic PCU values have to be adopted.
INTRODUCTION
3
NEED FOR THE STUDY
• The Highway Capacity Manual (HCM) has stated PCU values for the different vehicle
categories and for the different road sections.
• The stated values are static in nature but many researches has found out that the PCU values
are dynamic in nature – it varies depends upon the nature of the vehicular dimensions and
the traffic characteristics.
• Many researches has found out many methods for the estimation of the dynamic PCU’s for
different kind of vehicle categories but the PCU values found out using those methods varies
from one another.
• A slight variation in the PCU values may lead to the inappropriate effects in calculating the
capacity of the roads.
4
• The present study is an attempt to discuss the suitability of the different methods for
different circumstances so that one can make the right choice while adopting a PCU
estimation method.
• This study considers all the factors which may lead to the variations in the PCU values
and comes up with a new methodology for the estimation of the PCU, so that the
variations may be less when compared to the other estimation methods.
Contd…..
5
OBJECTIVES
Following are objective of this study,
 To Identify the various factors which affects the PCU values in the urban arterial roads.
 To study the suitability of different PCU estimation methods for the urban arterial roads.
 To come up with a new methodology for estimating the PCU based on heterogeneous traffic
conditions.
6
LITERATURE REVIEW
• The study of Literature Review is carried in relation to the objective of this study and identified
the different methodologies and concepts adopted in estimating the PCU of a selected section of
the road.
• The following are the different methods adopted to find out the PCU values
 PCU based on speed and area ratio
 PCU based on Homogeneous Co-efficient Method
 PCU based on Lagging headway Method
 PCU based on Platoon Formation Method
7
INFERENCE FROM LITERATURE REVIEW
 The lane width and the number of the lanes have the significant effect on the speed of the vehicles.
 The provision of a service lane has higher benefit cost ratio as compared to adding an extra lane on the main
carriageway without a service lane.
 The physical size of a vehicle is an indicator of the pavement occupancy, which is crucial in operational
characteristics of traffic stream.
 The PCU for a vehicle type increases linearly with the carriageway width.
 The influence of the roadway and traffic characteristics on vehicular movement could be easily studied from
the model which simulates the traffic flow characteristics
8
 When volume of the traffic increases, the physical dimensions and low maneuverability of heavy vehicles
become dominating and therefore heavy vehicles become more detrimental to the traffic stream as
compared to all other vehicle types.
 The PCE of the vehicle type varies with the traffic volume and its composition. It increases with an increase
in compositional share of respective vehicle types in the traffic stream.
 The parameters used in the estimation of PCU for homogeneous and mixed traffic are different for almost
all the facility types.
 Dynamic PCU values might better define the influence of a vehicle type in a traffic stream over different
traffic flow conditions.
Contd…..
9
Problem Identification
Formulation of objective
Review of literature
Selection of study stretch
Data collection
Geometric data:
Carriageway width
Roadway type
Presence of shoulders
IR method:
Classified volume count
Speed
Headway
Data extraction
PCU Estimation by the selected methods
Result and Conclusion
Methodology
10
Study location
For this study, a 4-lane divided urban road and a 6- lane divided urban road are selected as study locations in
Chennai.
6 lane divided roads
Rajiv Gandhi Road or IT Corridor is a major road in suburban Chennai, India, beginning at
the Madhya Kailash temple in Adyar in South Chennai and continuing south till Mahabalipuram, ultimately
merging with the East Coast Road. This road is State highway-49A
4 lane divided roads
Sardar Patel road which connects Guindy and Adyar. It is a Four Lane Divided Carriageway.
11
Study Stretch – IT corridor, Madhya
Kailash
12
Study Stretch – Sardar Patel Road
13
PARAMETERS INFLUENCING PCU VALUES
Speed
Headway
Delay
Density
Travel time
Queue Discharge
flow
For homogeneous traffic conditions several factors
are considered, some of them are listed below
Besides these for mixed traffic some other parameters
are also considered which are as follows
Area
occupancy
Platoon
Formation
Time
occupancy
Vehicle
hours
Influence area
V/C ratio
Note : Road width, Presence of shoulders, roughness of road, traffic composition, Land use and type of facility
are also some of the factors which influences the PCU values
14
Sardar patel
road
Characteristics of study area
SH – 49 A
Towards Perungudi
Six lane divided
3.1 m
No Shoulder
Location
Direction
Type
Lane width
Shoulder type
Study area
IT-Corridor
SH – 49
Towards Guindy
Four lane divided
3.5 m
Paved Shoulder
15
Vehicle Composition – IT Corridor
2 - Wheeler
57 %
Auto
12 %
Car
23 %
LCV
4 %
MCV
3%
16
Vehicle Composition – Sardar Patel Road
2 - Wheeler
53 %
Auto
10 %
MCV
3 %
Car
30 %
LCV
4 % 17
Lane usage – IT Corridor
L1 L2 L1 – L2 L2 – L3
• Lane usage are detected by the instrument used for
data collection known as TIRTL.
• Based on the time interval between the infrared
beams from transmitter to the receiver, the lane
usage are detected.
• The collected data shows that the 28% of the total
vehicle used L1, 40% of the total vehicle used the
lane L2, 22% of the total vehicle used L3, 6% of the
total vehicle doesn’t follows the lane discipline and
travels in between lane 1 and lane 2 and 9% of the
total vehicle doesn’t follows the lane discipline and
travels in between lane 2 and lane 3
L3
18
Lane usage – Sardar Patel road
L1 L2 L1 – L2 SL
• Lane usage are detected by the instrument used for data
collection known as TIRTL.
• Based on the time interval between the infrared beams from
transmitter to the receiver, the lane usage are detected.
• The collected data shows that the 56% of the total vehicle
used L1, 33% of the total vehicle used the lane L2, 11% of
the total vehicle travelled in the intermediate distance, 0% of
the total vehicle used shoulder for maneuvering
19
Speed and area
ratio
01
02
Platoon Formation
03
Based on
Homogeneous
Co-efficient method
Lagging headway
04
PCU estimation methods
20
Speed and area ratio method
• The PCU of different categories of vehicles are estimated based on the
speed of the individual vehicles and the area occupied by them. PCU could
be estimated from the relation shown below
PCUi = (Vc /Vi ) / (Ac/Ai )
PCUi = Passenger Car Unit of vehicle type i.
Vc, Vi = Average speed of small car and vehicle type i, respectively
Ac, Ai = Projected area of small car and vehicle type i, respectively.
21
Speed and area ratio method
Vehicle Category Minimum Value PCU Maximum Value
2-Wheeler 0.2 0.25 0.36
Auto 0.87 1.1 1.61
Car - 1 -
LCV 1.65 2.2 3.79
MCV 5.11 6.51 10.29
Vehicle Category Minimum Value PCU Maximum Value
2-Wheeler 0.14 0.24 0.44
Auto 0.64 1.02 2.66
Car - 1 -
LCV 1.17 2.04 4.16
MCV 4.23 6.11 9.74
Sardar Patel Road
IT Corridor
22
PCU based on Homogeneous Co-efficient Method
Permanent International Association of Road Congress (PIARC) proposed a model to
determine Homogeneous Coefficient (or PCU) of a vehicle category present in a mixed
traffic stream. The speed, as well as the length of a vehicle, were considered to
formulate the Homogeneous Coefficient (HCi) as given below.
PCUi = (Li/ Vi) / (Lc / Vc )
Where Li is the length of the subject vehicle (m)
Lc is the length of the standard car
Vi is the speed of the subject vehicle (Km/hr)
Vc is the speed of the standard car (Km/hr) 23
PCU based on Homogeneous Coefficient Method
Vehicle Category Minimum Value PCU Maximum Value
2-Wheeler 0.38 0.46 0.65
Auto 0.75 0.96 1.42
Car - 1 -
LCV 0.82 1.18 2.43
MCV 1.66 2.4 3.67
Vehicle Category Minimum Value PCU Maximum Value
2-Wheeler 0.29 0.44 1.05
Auto 0.56 0.9 2.72
Car - 1 -
LCV 0.65 1.15 2.25
MCV 1.13 5.25 9.37
Sardar Patel Road
IT Corridor
24
PCU based on lagging headway
Here, PCEs is defined as the ratio of the mean lagging headway of a subject vehicle
divided by the mean lagging headway of the basic passenger car. Lagging headway
is defined as the time or space from the rear of the leading vehicle to the rear of the
vehicle of interest; it is composed of the length of the subject vehicle and the
intravehicular gap.
PCUi = (Hij) / (Hpcj )
Lagging headway of various categories of vehicles was calculated from the
aggregated data and the PCUs of various categories of vehicles are calculated.
25
PCU based on lagging headway
Vehicle Category Minimum Value PCU Maximum Value
2-Wheeler 0.23 0.78 3.27
Auto 0.10 0.87 4.36
Car - 1 -
LCV 0.14 1.04 3.91
MCV 0.13 1.2 4.6
Vehicle Category Minimum Value PCU Maximum Value
2-Wheeler 0.23 0.89 3.27
Auto 0.10 0.85 4.36
Car - 1 -
LCV 0.14 1.31 3.91
MCV 0.13 1.15 4.6
Sardar Patel Road
IT Corridor
26
Platoon Formation Method
The proper value of critical headway is used to decide whether vehicles included in platoons or not.
The value of critical headway can be determined based on the mean relative speed method.
RSPi = Si – Si-1
RSPi is the relative speed between vehicles i and i-1 in km/h
Si is the speed of vehicles i in km/h.
In the present study, to estimate the PCU values of car, two-wheeler, LCV, MCV and trucks, the
Huber’s concept was used. In Huber method two streams, one containing only Passenger car (base
stream) and the other containing Passenger cars and vehicle type for which PCU values is going to
be estimated
.
27
Sardar Patel Road
IT Corridor
Platoon Formation Method
Vehicle Category Minimum Value PCU Maximum Value
2-Wheeler 0.53 0.55 0.55
Auto 0.55 0.71 0.75
Car - 1 -
LCV 1.07 1.15 1.22
MCV 2.47 2.66 3.35
Vehicle Category Minimum Value PCU Maximum Value
2-Wheeler 0.44 0.52 0.55
Auto 0.52 0.7 0.78
Car - 1 -
LCV 1.16 1.18 1.23
MCV 2.37 2.47 2.52 28
CAPACITY ESTIMATION - Greenshield model
0
10
20
30
40
50
60
70
0 1000 2000 3000 4000 5000
Speed
Flow
0
10
20
30
40
50
60
70
0 5000 10000 15000
Speed
Flow
0
10
20
30
40
50
60
70
0 5000 10000 15000
Speed
Flow
y = -0.1033x + 51.737
R² = 0.4764
0
10
20
30
40
50
60
70
0 100 200 300 400
Speed
Density
y = -0.1598x + 53.733
R² = 0.6351
0
10
20
30
40
50
60
70
0 50 100 150
Speed
Density
y = -0.1622x + 53.845
R² = 0.6449
0
10
20
30
40
50
60
70
0 50 100 150
Speed
Density
Speed and area ratio method Homogeneous Coefficient method Lagging Headway method Platoon formation method
Sardar Patel Road
29
CAPACITY ESTIMATION - Greenshield model
PCU estimation
Methods
Capacity (PCU/hr) R2 value Equation
Speed and area ratio
method.
4469 0.6449 Y= -0.1622x + 53.845
Homogeneous
coefficient method
4517 0.6351 Y= -0.1598x + 53.733
Lagging headway
method
6478 0.4764 Y= -0.1033x+ 51.737
Platoon formation
method
3008 0.1948 Y= -0.3261x +53.866
Sardar Patel Road
30
CAPACITY ESTIMATION - Greenshield model
Speed and area ratio method Homogeneous Coefficient method Lagging Headway method Platoon formation method
IT Corridor
y = -0.1455x + 52.824
R² = 0.3219
0
10
20
30
40
50
60
0 20 40 60 80
Speed
Density
0
10
20
30
40
50
60
0 2000 4000 6000
Speed
Flow
y = -0.1372x + 52.905
R² = 0.3595
0
10
20
30
40
50
60
0 20 40 60 80 100
Speed
Density
0
10
20
30
40
50
60
0 2000 4000 6000
Speed
Flow
y = -0.0778x + 50.778
R² = 0.3335
0
10
20
30
40
50
60
0 50 100 150
Speed
Density
0
10
20
30
40
50
60
0 5000 10000
Speed
Flow
31
CAPACITY ESTIMATION - Greenshield model
IT Corridor
PCU estimation
Methods
Capacity (PCU/hr) R2 value Equation
Speed and area ratio
method.
4295 0.3219 Y= -0.1455x + 52.824
Homogeneous
coefficient method
5100 0.3595 Y= -0.1372x + 52.905
Lagging headway
method
8285 0.3335 Y= -0.0778x + 50.778
Platoon formation
method
7140 0.1462 Y= -0.0467x + 49.145
32
PCU Comparison
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
2 Wheeler Auto Bicycle Car HCV
0.25
1.10 1.00
2.20
6.51
0.46
0.96 1
1.18
2.4
0.78 0.87
1 1.04
1.2
0.52
0.7
1
1.18
2.47
IT Corridor
Speed area ratio
method
Homogeneous
Coefficient Method
Lagging headway
method
Platoon PCU
33
PCU Comparison
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
2 Wheeler Auto Bicycle Car HCV
0.24
1.02 1.00
2.04
6.11
0.44
0.9 1
1.15
2.15
0.89 0.85
1
1.31
1.15
0.55
0.71
1
1.15
2.66
PCU
Vehicle class
Sardar Patel Road
speed and area
ratio
Homogeneous
coefficient method
Lagging Headway
Platoon PCU
34
CONCLUSION
 Based on the analysis of the observed data it was found out that the Speed and area ratio method is
the best suited for estimating the PCUs of the different vehicle categories in the Urban roads in which
there is no lane discipline is being followed.
 The platoon formation methods could also be used to identify the PCU values in a situation in
which the Speed and area ratio method is found to be unreliable.
Capacity (PCUs/hr)
Sathish Chandra
method
Homogeneous
Coefficient method
Lagging headway
method
Platoon formation
method
Sardar Patel Road 4469 4517 6479 3008
IT Corridor 4795 5100 8285 7140
35
LIMITATIONS OF THIS STUDY
 Because the data was collected on urban roads, large vehicles such as HCVs, MAVs, and tractors
have a very minor role in the traffic flow. As a result, the PCU values for these vehicles could not be
calculated in this study.
 If the nature of the traffic flow changes, the PCU values found out during this study may alter.
 Since the PCU values found out using the Platoon formation method are based on the vehicular
combinations, if there are more combinations available then the PCU values may alter.
36
REFERENCE
1. Anand. S., Sekhar. S. V. C., & Karim. M. R. (1999). Development of passenger car unit values for Malaysia.
Journal of the Eastern Asia Society for Transportation Studies, Vol.3, No.3, September, 73-80.
2. Ashish Dhamaniya and Satish Chandra (2013), Concept of Stream Equivalency Factor for Heterogeneous Traffic
on Urban Arterial Roads, Journal of Transportation Engineering, Vol. 139, No. 11, November 1, 2013.
3. Chandra, S., and Sikdar, P. K. (2000). “Factors affecting PCE in mixed traffic situations on urban roads.” Road
Transp. Res., 9(3), 40–50.
4. Debasis Basu, Swati Roy Maitra and Bhargab Maitra (2006), Modelling Passenger Car Equivalency at an urban
midblock using stream speed as the measure of equivalence, European Transport  Trasporti Europei n. 34 (2006):
75-87.
5. Geetam Tiwari, Joseph Fazio, Sri Pavitravas (2007), ‘Passenger car units for heterogenous traffic using modified
density method’, National transportation library, US department of Transportation, Document 8612, pp. 246.
6. Pooja Raj, Kalaanidhi Sivagnanasundaram, Gowri Asaithambi and Ayyalasomayajula Udaya Ravi Shankar
(2019), Review of Methods for Estimation of Passenger Car Unit Values of Vehicles, Journal of Transportation
Engineering, Part A: Systems.
37
7. Rahman and Nakamura (2005), Measuring Passenger Car Equivalents for nonmotorized vehicle
(rickshaws) at mid-block sections, Journal of the Eastern Asia Society for Transportation Studies, Vol. 6,
pp. 119 - 126, 2005.
8. Sabayasachi Biswas, Ms. Somya Singh, Mr. Nihal Malik, Mr. Atul V.Bisen (2018), Estimation of Passenger Car
Unit by Multi-objective optimization technique.
9. Satish Chandra and U. Kumar (2003), “Effect of Lane Width on Capacity under Mixed Traffic Conditions in
India.” Journal of Transportation Engineering, ASCE 129 (2): 155–160. doi:10.1061/(ASCE)0733-
947X(2003)129:2(155).
10. Subhadip Biswas, Satish Chandra & Indrajit Ghosh (2018): An advanced approach for estimation of PCU values
on undivided urban roads under heterogeneous traffic conditions, Transportation Letters, DOI:
10.1080/19427867.2018.1563268
11. V. Thamizh Arasan and Reebu Zachariah Koshy (2005), Methodology for Modeling Highly Heterogeneous
Traffic Flow, the Journal of Transportation Engineering, Vol. 131, No. 7, July 1, 2005.
12. V. Thamizh Arasan and Shriniwas S. Arkatkar (2010), Microsimulation Study of Effect of Volume and Road
Width on PCU of Vehicles under Heterogeneous Traffic, the Journal of Transportation Engineering, Vol. 136, No.
12, December 1, 2010 38
39

Contenu connexe

Tendances

Geometric design of highway
Geometric design of  highwayGeometric design of  highway
Geometric design of highwayPratikShinde113
 
Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Civil Zone
 
Accidents studies by ravindra c
Accidents studies by ravindra cAccidents studies by ravindra c
Accidents studies by ravindra cŔąvî Bøňđ
 
Traffic Engineering And Drainage
Traffic Engineering And DrainageTraffic Engineering And Drainage
Traffic Engineering And DrainagePrashant Ranjan
 
O and d study
O and d studyO and d study
O and d studymeetmksvs
 
Traffic Engineering
Traffic Engineering Traffic Engineering
Traffic Engineering PadduS
 
Traffic Volume Studies
Traffic Volume StudiesTraffic Volume Studies
Traffic Volume StudiesMd Tanvir Alam
 
Cordon line survey
Cordon line surveyCordon line survey
Cordon line surveyNilgabs1
 
Highway & road geomatric and its component
Highway & road geomatric and its component Highway & road geomatric and its component
Highway & road geomatric and its component Sumit Kumar
 
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTUVATSAL PATEL
 
Measurement of spot speed
Measurement of spot speedMeasurement of spot speed
Measurement of spot speedSagar Vekariya
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )mohit kumar panchal
 

Tendances (20)

Geometric design of highway
Geometric design of  highwayGeometric design of  highway
Geometric design of highway
 
Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)
 
Traffic studies
Traffic studiesTraffic studies
Traffic studies
 
Parking study
Parking studyParking study
Parking study
 
Highway planning and alignment
Highway planning and alignmentHighway planning and alignment
Highway planning and alignment
 
Accidents studies by ravindra c
Accidents studies by ravindra cAccidents studies by ravindra c
Accidents studies by ravindra c
 
Traffic Engineering And Drainage
Traffic Engineering And DrainageTraffic Engineering And Drainage
Traffic Engineering And Drainage
 
O and d study
O and d studyO and d study
O and d study
 
Traffic Engineering
Traffic Engineering Traffic Engineering
Traffic Engineering
 
O & d survey
O & d survey O & d survey
O & d survey
 
ROAD SAFETY AUDIT
ROAD SAFETY AUDITROAD SAFETY AUDIT
ROAD SAFETY AUDIT
 
Traffic engineering
Traffic engineeringTraffic engineering
Traffic engineering
 
Traffic Volume Studies
Traffic Volume StudiesTraffic Volume Studies
Traffic Volume Studies
 
Cordon line survey
Cordon line surveyCordon line survey
Cordon line survey
 
Highway & road geomatric and its component
Highway & road geomatric and its component Highway & road geomatric and its component
Highway & road geomatric and its component
 
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
 
Measurement of spot speed
Measurement of spot speedMeasurement of spot speed
Measurement of spot speed
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
 
Traffic speed study
Traffic speed studyTraffic speed study
Traffic speed study
 
Traffic Volume Study
Traffic Volume StudyTraffic Volume Study
Traffic Volume Study
 

Similaire à PCU Estimation.pptx

Modeling to Traffic Flow on Indian Expressway and Urban Mid-Block Section usi...
Modeling to Traffic Flow on Indian Expressway and Urban Mid-Block Section usi...Modeling to Traffic Flow on Indian Expressway and Urban Mid-Block Section usi...
Modeling to Traffic Flow on Indian Expressway and Urban Mid-Block Section usi...IRJET Journal
 
Evaluation of Traffic Characteristics: a Case Study on NH-12, Near Barkatulla...
Evaluation of Traffic Characteristics: a Case Study on NH-12, Near Barkatulla...Evaluation of Traffic Characteristics: a Case Study on NH-12, Near Barkatulla...
Evaluation of Traffic Characteristics: a Case Study on NH-12, Near Barkatulla...IRJET Journal
 
CAPACITY ESTIMATION OF TWO LANE UNDIVIDED HIGHWAY
CAPACITY ESTIMATION OF TWO LANE UNDIVIDED HIGHWAYCAPACITY ESTIMATION OF TWO LANE UNDIVIDED HIGHWAY
CAPACITY ESTIMATION OF TWO LANE UNDIVIDED HIGHWAYMANJUNATH BORAKANAVAR
 
Traffic Forecasting
Traffic Forecasting Traffic Forecasting
Traffic Forecasting icanearn555
 
TRAFFIC ANALYSIS AND DESIGN OF FLYOVER AT PERUMBAVOOR SIGNAL
TRAFFIC ANALYSIS AND DESIGN OF FLYOVER AT PERUMBAVOOR SIGNALTRAFFIC ANALYSIS AND DESIGN OF FLYOVER AT PERUMBAVOOR SIGNAL
TRAFFIC ANALYSIS AND DESIGN OF FLYOVER AT PERUMBAVOOR SIGNALIRJET Journal
 
Mode choice between roadway and waterway
Mode choice between roadway and waterwayMode choice between roadway and waterway
Mode choice between roadway and waterwayAglaia Connect
 
A Review on Intrusion Detection System Based Data Mining Techniques
A Review on Intrusion Detection System Based Data Mining TechniquesA Review on Intrusion Detection System Based Data Mining Techniques
A Review on Intrusion Detection System Based Data Mining TechniquesIRJET Journal
 
Analysis of Traffic Behavior at the Toll Plazas Around Bangalore
Analysis of Traffic Behavior at the Toll Plazas Around BangaloreAnalysis of Traffic Behavior at the Toll Plazas Around Bangalore
Analysis of Traffic Behavior at the Toll Plazas Around BangaloreIRJET Journal
 
ATE - U-I.pptx
ATE - U-I.pptxATE - U-I.pptx
ATE - U-I.pptxCivilhod15
 
Design of traffic signal on NH-12 near Barkatullah University, Bhopal Distric...
Design of traffic signal on NH-12 near Barkatullah University, Bhopal Distric...Design of traffic signal on NH-12 near Barkatullah University, Bhopal Distric...
Design of traffic signal on NH-12 near Barkatullah University, Bhopal Distric...IRJET Journal
 
Fixation of Toll charge for Six Lane Highway
 Fixation of Toll charge for Six Lane Highway Fixation of Toll charge for Six Lane Highway
Fixation of Toll charge for Six Lane Highwayijsrd.com
 
Exit Presentation 2.pptx
Exit Presentation 2.pptxExit Presentation 2.pptx
Exit Presentation 2.pptxYitbarekSisay
 
Evaluation of operational efficiency of urban road
Evaluation of operational efficiency of urban roadEvaluation of operational efficiency of urban road
Evaluation of operational efficiency of urban roadeSAT Publishing House
 
Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...eSAT Journals
 
Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...eSAT Journals
 
Paper id 71201923
Paper id 71201923Paper id 71201923
Paper id 71201923IJRAT
 
Travel speed report by pronob ghosh buet 1204011
Travel speed report by pronob ghosh buet 1204011Travel speed report by pronob ghosh buet 1204011
Travel speed report by pronob ghosh buet 1204011Pronob Ghosh
 
TRAFFIC SIMULATION AT TOLL ROAD SECTION USING VISSIM SOFTWARE
TRAFFIC SIMULATION AT TOLL ROAD SECTION USING VISSIM SOFTWARETRAFFIC SIMULATION AT TOLL ROAD SECTION USING VISSIM SOFTWARE
TRAFFIC SIMULATION AT TOLL ROAD SECTION USING VISSIM SOFTWAREshrikrishna kesharwani
 

Similaire à PCU Estimation.pptx (20)

Modeling to Traffic Flow on Indian Expressway and Urban Mid-Block Section usi...
Modeling to Traffic Flow on Indian Expressway and Urban Mid-Block Section usi...Modeling to Traffic Flow on Indian Expressway and Urban Mid-Block Section usi...
Modeling to Traffic Flow on Indian Expressway and Urban Mid-Block Section usi...
 
Evaluation of Traffic Characteristics: a Case Study on NH-12, Near Barkatulla...
Evaluation of Traffic Characteristics: a Case Study on NH-12, Near Barkatulla...Evaluation of Traffic Characteristics: a Case Study on NH-12, Near Barkatulla...
Evaluation of Traffic Characteristics: a Case Study on NH-12, Near Barkatulla...
 
CAPACITY ESTIMATION OF TWO LANE UNDIVIDED HIGHWAY
CAPACITY ESTIMATION OF TWO LANE UNDIVIDED HIGHWAYCAPACITY ESTIMATION OF TWO LANE UNDIVIDED HIGHWAY
CAPACITY ESTIMATION OF TWO LANE UNDIVIDED HIGHWAY
 
Traffic Forecasting
Traffic Forecasting Traffic Forecasting
Traffic Forecasting
 
TRAFFIC ANALYSIS AND DESIGN OF FLYOVER AT PERUMBAVOOR SIGNAL
TRAFFIC ANALYSIS AND DESIGN OF FLYOVER AT PERUMBAVOOR SIGNALTRAFFIC ANALYSIS AND DESIGN OF FLYOVER AT PERUMBAVOOR SIGNAL
TRAFFIC ANALYSIS AND DESIGN OF FLYOVER AT PERUMBAVOOR SIGNAL
 
F04514151
F04514151F04514151
F04514151
 
Mode choice between roadway and waterway
Mode choice between roadway and waterwayMode choice between roadway and waterway
Mode choice between roadway and waterway
 
A Review on Intrusion Detection System Based Data Mining Techniques
A Review on Intrusion Detection System Based Data Mining TechniquesA Review on Intrusion Detection System Based Data Mining Techniques
A Review on Intrusion Detection System Based Data Mining Techniques
 
Analysis of Traffic Behavior at the Toll Plazas Around Bangalore
Analysis of Traffic Behavior at the Toll Plazas Around BangaloreAnalysis of Traffic Behavior at the Toll Plazas Around Bangalore
Analysis of Traffic Behavior at the Toll Plazas Around Bangalore
 
ATE - U-I.pptx
ATE - U-I.pptxATE - U-I.pptx
ATE - U-I.pptx
 
Design of traffic signal on NH-12 near Barkatullah University, Bhopal Distric...
Design of traffic signal on NH-12 near Barkatullah University, Bhopal Distric...Design of traffic signal on NH-12 near Barkatullah University, Bhopal Distric...
Design of traffic signal on NH-12 near Barkatullah University, Bhopal Distric...
 
Fixation of Toll charge for Six Lane Highway
 Fixation of Toll charge for Six Lane Highway Fixation of Toll charge for Six Lane Highway
Fixation of Toll charge for Six Lane Highway
 
Exit Presentation 2.pptx
Exit Presentation 2.pptxExit Presentation 2.pptx
Exit Presentation 2.pptx
 
Evaluation of operational efficiency of urban road
Evaluation of operational efficiency of urban roadEvaluation of operational efficiency of urban road
Evaluation of operational efficiency of urban road
 
Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...
 
Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...
 
Paper id 71201923
Paper id 71201923Paper id 71201923
Paper id 71201923
 
Travel speed report by pronob ghosh buet 1204011
Travel speed report by pronob ghosh buet 1204011Travel speed report by pronob ghosh buet 1204011
Travel speed report by pronob ghosh buet 1204011
 
Ab4502180184
Ab4502180184Ab4502180184
Ab4502180184
 
TRAFFIC SIMULATION AT TOLL ROAD SECTION USING VISSIM SOFTWARE
TRAFFIC SIMULATION AT TOLL ROAD SECTION USING VISSIM SOFTWARETRAFFIC SIMULATION AT TOLL ROAD SECTION USING VISSIM SOFTWARE
TRAFFIC SIMULATION AT TOLL ROAD SECTION USING VISSIM SOFTWARE
 

Dernier

Anupama Kundoo Cost Effective detailed ppt with plans and elevations with det...
Anupama Kundoo Cost Effective detailed ppt with plans and elevations with det...Anupama Kundoo Cost Effective detailed ppt with plans and elevations with det...
Anupama Kundoo Cost Effective detailed ppt with plans and elevations with det...sriharipichandi
 
一比一定(购)卡尔顿大学毕业证(CU毕业证)成绩单学位证
一比一定(购)卡尔顿大学毕业证(CU毕业证)成绩单学位证一比一定(购)卡尔顿大学毕业证(CU毕业证)成绩单学位证
一比一定(购)卡尔顿大学毕业证(CU毕业证)成绩单学位证wpkuukw
 
TRose UXPA Experience Design Concord .pptx
TRose UXPA Experience Design Concord .pptxTRose UXPA Experience Design Concord .pptx
TRose UXPA Experience Design Concord .pptxtrose8
 
Just Call Vip call girls Fatehpur Escorts ☎️8617370543 Two shot with one girl...
Just Call Vip call girls Fatehpur Escorts ☎️8617370543 Two shot with one girl...Just Call Vip call girls Fatehpur Escorts ☎️8617370543 Two shot with one girl...
Just Call Vip call girls Fatehpur Escorts ☎️8617370543 Two shot with one girl...Nitya salvi
 
Pondicherry Escorts Service Girl ^ 9332606886, WhatsApp Anytime Pondicherry
Pondicherry Escorts Service Girl ^ 9332606886, WhatsApp Anytime PondicherryPondicherry Escorts Service Girl ^ 9332606886, WhatsApp Anytime Pondicherry
Pondicherry Escorts Service Girl ^ 9332606886, WhatsApp Anytime Pondicherrymeghakumariji156
 
Gamestore case study UI UX by Amgad Ibrahim
Gamestore case study UI UX by Amgad IbrahimGamestore case study UI UX by Amgad Ibrahim
Gamestore case study UI UX by Amgad Ibrahimamgadibrahim92
 
Minimalist Orange Portfolio by Slidesgo.pptx
Minimalist Orange Portfolio by Slidesgo.pptxMinimalist Orange Portfolio by Slidesgo.pptx
Minimalist Orange Portfolio by Slidesgo.pptxbalqisyamutia
 
怎样办理伯明翰城市大学毕业证(BCU毕业证书)成绩单留信认证
怎样办理伯明翰城市大学毕业证(BCU毕业证书)成绩单留信认证怎样办理伯明翰城市大学毕业证(BCU毕业证书)成绩单留信认证
怎样办理伯明翰城市大学毕业证(BCU毕业证书)成绩单留信认证eeanqy
 
怎样办理莫纳什大学毕业证(Monash毕业证书)成绩单留信认证
怎样办理莫纳什大学毕业证(Monash毕业证书)成绩单留信认证怎样办理莫纳什大学毕业证(Monash毕业证书)成绩单留信认证
怎样办理莫纳什大学毕业证(Monash毕业证书)成绩单留信认证ehyxf
 
How to Turn a Picture Into a Line Drawing in Photoshop
How to Turn a Picture Into a Line Drawing in PhotoshopHow to Turn a Picture Into a Line Drawing in Photoshop
How to Turn a Picture Into a Line Drawing in PhotoshopZenith Clipping
 
Madhyamgram \ (Genuine) Escort Service Kolkata | Service-oriented sexy call g...
Madhyamgram \ (Genuine) Escort Service Kolkata | Service-oriented sexy call g...Madhyamgram \ (Genuine) Escort Service Kolkata | Service-oriented sexy call g...
Madhyamgram \ (Genuine) Escort Service Kolkata | Service-oriented sexy call g...HyderabadDolls
 
怎样办理巴斯大学毕业证(Bath毕业证书)成绩单留信认证
怎样办理巴斯大学毕业证(Bath毕业证书)成绩单留信认证怎样办理巴斯大学毕业证(Bath毕业证书)成绩单留信认证
怎样办理巴斯大学毕业证(Bath毕业证书)成绩单留信认证eeanqy
 
Call Girls In Ratnagiri Escorts ☎️8617370543 🔝 💃 Enjoy 24/7 Escort Service En...
Call Girls In Ratnagiri Escorts ☎️8617370543 🔝 💃 Enjoy 24/7 Escort Service En...Call Girls In Ratnagiri Escorts ☎️8617370543 🔝 💃 Enjoy 24/7 Escort Service En...
Call Girls In Ratnagiri Escorts ☎️8617370543 🔝 💃 Enjoy 24/7 Escort Service En...Nitya salvi
 
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样yhavx
 
poliovirus-190801072449. pptx
poliovirus-190801072449.            pptxpoliovirus-190801072449.            pptx
poliovirus-190801072449. pptxssuser0ad194
 
Lecture 01 Introduction To Multimedia.pptx
Lecture 01 Introduction To Multimedia.pptxLecture 01 Introduction To Multimedia.pptx
Lecture 01 Introduction To Multimedia.pptxShoaibRajper1
 
Top profile Call Girls In Mysore [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Mysore [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Mysore [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Mysore [ 7014168258 ] Call Me For Genuine Models We...gajnagarg
 
Call Girls Jalaun Just Call 8617370543 Top Class Call Girl Service Available
Call Girls Jalaun Just Call 8617370543 Top Class Call Girl Service AvailableCall Girls Jalaun Just Call 8617370543 Top Class Call Girl Service Available
Call Girls Jalaun Just Call 8617370543 Top Class Call Girl Service AvailableNitya salvi
 
Sweety Planet Packaging Design Process Book.pptx
Sweety Planet Packaging Design Process Book.pptxSweety Planet Packaging Design Process Book.pptx
Sweety Planet Packaging Design Process Book.pptxbingyichin04
 
How to Build a Simple Shopify Website
How to Build a Simple Shopify WebsiteHow to Build a Simple Shopify Website
How to Build a Simple Shopify Websitemark11275
 

Dernier (20)

Anupama Kundoo Cost Effective detailed ppt with plans and elevations with det...
Anupama Kundoo Cost Effective detailed ppt with plans and elevations with det...Anupama Kundoo Cost Effective detailed ppt with plans and elevations with det...
Anupama Kundoo Cost Effective detailed ppt with plans and elevations with det...
 
一比一定(购)卡尔顿大学毕业证(CU毕业证)成绩单学位证
一比一定(购)卡尔顿大学毕业证(CU毕业证)成绩单学位证一比一定(购)卡尔顿大学毕业证(CU毕业证)成绩单学位证
一比一定(购)卡尔顿大学毕业证(CU毕业证)成绩单学位证
 
TRose UXPA Experience Design Concord .pptx
TRose UXPA Experience Design Concord .pptxTRose UXPA Experience Design Concord .pptx
TRose UXPA Experience Design Concord .pptx
 
Just Call Vip call girls Fatehpur Escorts ☎️8617370543 Two shot with one girl...
Just Call Vip call girls Fatehpur Escorts ☎️8617370543 Two shot with one girl...Just Call Vip call girls Fatehpur Escorts ☎️8617370543 Two shot with one girl...
Just Call Vip call girls Fatehpur Escorts ☎️8617370543 Two shot with one girl...
 
Pondicherry Escorts Service Girl ^ 9332606886, WhatsApp Anytime Pondicherry
Pondicherry Escorts Service Girl ^ 9332606886, WhatsApp Anytime PondicherryPondicherry Escorts Service Girl ^ 9332606886, WhatsApp Anytime Pondicherry
Pondicherry Escorts Service Girl ^ 9332606886, WhatsApp Anytime Pondicherry
 
Gamestore case study UI UX by Amgad Ibrahim
Gamestore case study UI UX by Amgad IbrahimGamestore case study UI UX by Amgad Ibrahim
Gamestore case study UI UX by Amgad Ibrahim
 
Minimalist Orange Portfolio by Slidesgo.pptx
Minimalist Orange Portfolio by Slidesgo.pptxMinimalist Orange Portfolio by Slidesgo.pptx
Minimalist Orange Portfolio by Slidesgo.pptx
 
怎样办理伯明翰城市大学毕业证(BCU毕业证书)成绩单留信认证
怎样办理伯明翰城市大学毕业证(BCU毕业证书)成绩单留信认证怎样办理伯明翰城市大学毕业证(BCU毕业证书)成绩单留信认证
怎样办理伯明翰城市大学毕业证(BCU毕业证书)成绩单留信认证
 
怎样办理莫纳什大学毕业证(Monash毕业证书)成绩单留信认证
怎样办理莫纳什大学毕业证(Monash毕业证书)成绩单留信认证怎样办理莫纳什大学毕业证(Monash毕业证书)成绩单留信认证
怎样办理莫纳什大学毕业证(Monash毕业证书)成绩单留信认证
 
How to Turn a Picture Into a Line Drawing in Photoshop
How to Turn a Picture Into a Line Drawing in PhotoshopHow to Turn a Picture Into a Line Drawing in Photoshop
How to Turn a Picture Into a Line Drawing in Photoshop
 
Madhyamgram \ (Genuine) Escort Service Kolkata | Service-oriented sexy call g...
Madhyamgram \ (Genuine) Escort Service Kolkata | Service-oriented sexy call g...Madhyamgram \ (Genuine) Escort Service Kolkata | Service-oriented sexy call g...
Madhyamgram \ (Genuine) Escort Service Kolkata | Service-oriented sexy call g...
 
怎样办理巴斯大学毕业证(Bath毕业证书)成绩单留信认证
怎样办理巴斯大学毕业证(Bath毕业证书)成绩单留信认证怎样办理巴斯大学毕业证(Bath毕业证书)成绩单留信认证
怎样办理巴斯大学毕业证(Bath毕业证书)成绩单留信认证
 
Call Girls In Ratnagiri Escorts ☎️8617370543 🔝 💃 Enjoy 24/7 Escort Service En...
Call Girls In Ratnagiri Escorts ☎️8617370543 🔝 💃 Enjoy 24/7 Escort Service En...Call Girls In Ratnagiri Escorts ☎️8617370543 🔝 💃 Enjoy 24/7 Escort Service En...
Call Girls In Ratnagiri Escorts ☎️8617370543 🔝 💃 Enjoy 24/7 Escort Service En...
 
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
一比一原版(ANU毕业证书)澳大利亚国立大学毕业证原件一模一样
 
poliovirus-190801072449. pptx
poliovirus-190801072449.            pptxpoliovirus-190801072449.            pptx
poliovirus-190801072449. pptx
 
Lecture 01 Introduction To Multimedia.pptx
Lecture 01 Introduction To Multimedia.pptxLecture 01 Introduction To Multimedia.pptx
Lecture 01 Introduction To Multimedia.pptx
 
Top profile Call Girls In Mysore [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Mysore [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Mysore [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Mysore [ 7014168258 ] Call Me For Genuine Models We...
 
Call Girls Jalaun Just Call 8617370543 Top Class Call Girl Service Available
Call Girls Jalaun Just Call 8617370543 Top Class Call Girl Service AvailableCall Girls Jalaun Just Call 8617370543 Top Class Call Girl Service Available
Call Girls Jalaun Just Call 8617370543 Top Class Call Girl Service Available
 
Sweety Planet Packaging Design Process Book.pptx
Sweety Planet Packaging Design Process Book.pptxSweety Planet Packaging Design Process Book.pptx
Sweety Planet Packaging Design Process Book.pptx
 
How to Build a Simple Shopify Website
How to Build a Simple Shopify WebsiteHow to Build a Simple Shopify Website
How to Build a Simple Shopify Website
 

PCU Estimation.pptx

  • 1. 1
  • 2. Introduction Need for the study Objectives Works done Methodology Table of contents 2
  • 3. • In developing countries like India the nature of the traffic conditions are heterogeneous - no lane discipline is followed and no segregation of different classes of vehicles. • In order to study the traffic characteristics, the different vehicular categories should be converted to one common standard vehicular unit. • It is the common practice to consider the passenger car as the standard vehicle unit to convert the other vehicle classes and this unit is called the Passenger Car Unit or PCU. • The PCU value varies based on the traffic characteristics, hence dynamic PCU values have to be adopted. INTRODUCTION 3
  • 4. NEED FOR THE STUDY • The Highway Capacity Manual (HCM) has stated PCU values for the different vehicle categories and for the different road sections. • The stated values are static in nature but many researches has found out that the PCU values are dynamic in nature – it varies depends upon the nature of the vehicular dimensions and the traffic characteristics. • Many researches has found out many methods for the estimation of the dynamic PCU’s for different kind of vehicle categories but the PCU values found out using those methods varies from one another. • A slight variation in the PCU values may lead to the inappropriate effects in calculating the capacity of the roads. 4
  • 5. • The present study is an attempt to discuss the suitability of the different methods for different circumstances so that one can make the right choice while adopting a PCU estimation method. • This study considers all the factors which may lead to the variations in the PCU values and comes up with a new methodology for the estimation of the PCU, so that the variations may be less when compared to the other estimation methods. Contd….. 5
  • 6. OBJECTIVES Following are objective of this study,  To Identify the various factors which affects the PCU values in the urban arterial roads.  To study the suitability of different PCU estimation methods for the urban arterial roads.  To come up with a new methodology for estimating the PCU based on heterogeneous traffic conditions. 6
  • 7. LITERATURE REVIEW • The study of Literature Review is carried in relation to the objective of this study and identified the different methodologies and concepts adopted in estimating the PCU of a selected section of the road. • The following are the different methods adopted to find out the PCU values  PCU based on speed and area ratio  PCU based on Homogeneous Co-efficient Method  PCU based on Lagging headway Method  PCU based on Platoon Formation Method 7
  • 8. INFERENCE FROM LITERATURE REVIEW  The lane width and the number of the lanes have the significant effect on the speed of the vehicles.  The provision of a service lane has higher benefit cost ratio as compared to adding an extra lane on the main carriageway without a service lane.  The physical size of a vehicle is an indicator of the pavement occupancy, which is crucial in operational characteristics of traffic stream.  The PCU for a vehicle type increases linearly with the carriageway width.  The influence of the roadway and traffic characteristics on vehicular movement could be easily studied from the model which simulates the traffic flow characteristics 8
  • 9.  When volume of the traffic increases, the physical dimensions and low maneuverability of heavy vehicles become dominating and therefore heavy vehicles become more detrimental to the traffic stream as compared to all other vehicle types.  The PCE of the vehicle type varies with the traffic volume and its composition. It increases with an increase in compositional share of respective vehicle types in the traffic stream.  The parameters used in the estimation of PCU for homogeneous and mixed traffic are different for almost all the facility types.  Dynamic PCU values might better define the influence of a vehicle type in a traffic stream over different traffic flow conditions. Contd….. 9
  • 10. Problem Identification Formulation of objective Review of literature Selection of study stretch Data collection Geometric data: Carriageway width Roadway type Presence of shoulders IR method: Classified volume count Speed Headway Data extraction PCU Estimation by the selected methods Result and Conclusion Methodology 10
  • 11. Study location For this study, a 4-lane divided urban road and a 6- lane divided urban road are selected as study locations in Chennai. 6 lane divided roads Rajiv Gandhi Road or IT Corridor is a major road in suburban Chennai, India, beginning at the Madhya Kailash temple in Adyar in South Chennai and continuing south till Mahabalipuram, ultimately merging with the East Coast Road. This road is State highway-49A 4 lane divided roads Sardar Patel road which connects Guindy and Adyar. It is a Four Lane Divided Carriageway. 11
  • 12. Study Stretch – IT corridor, Madhya Kailash 12
  • 13. Study Stretch – Sardar Patel Road 13
  • 14. PARAMETERS INFLUENCING PCU VALUES Speed Headway Delay Density Travel time Queue Discharge flow For homogeneous traffic conditions several factors are considered, some of them are listed below Besides these for mixed traffic some other parameters are also considered which are as follows Area occupancy Platoon Formation Time occupancy Vehicle hours Influence area V/C ratio Note : Road width, Presence of shoulders, roughness of road, traffic composition, Land use and type of facility are also some of the factors which influences the PCU values 14
  • 15. Sardar patel road Characteristics of study area SH – 49 A Towards Perungudi Six lane divided 3.1 m No Shoulder Location Direction Type Lane width Shoulder type Study area IT-Corridor SH – 49 Towards Guindy Four lane divided 3.5 m Paved Shoulder 15
  • 16. Vehicle Composition – IT Corridor 2 - Wheeler 57 % Auto 12 % Car 23 % LCV 4 % MCV 3% 16
  • 17. Vehicle Composition – Sardar Patel Road 2 - Wheeler 53 % Auto 10 % MCV 3 % Car 30 % LCV 4 % 17
  • 18. Lane usage – IT Corridor L1 L2 L1 – L2 L2 – L3 • Lane usage are detected by the instrument used for data collection known as TIRTL. • Based on the time interval between the infrared beams from transmitter to the receiver, the lane usage are detected. • The collected data shows that the 28% of the total vehicle used L1, 40% of the total vehicle used the lane L2, 22% of the total vehicle used L3, 6% of the total vehicle doesn’t follows the lane discipline and travels in between lane 1 and lane 2 and 9% of the total vehicle doesn’t follows the lane discipline and travels in between lane 2 and lane 3 L3 18
  • 19. Lane usage – Sardar Patel road L1 L2 L1 – L2 SL • Lane usage are detected by the instrument used for data collection known as TIRTL. • Based on the time interval between the infrared beams from transmitter to the receiver, the lane usage are detected. • The collected data shows that the 56% of the total vehicle used L1, 33% of the total vehicle used the lane L2, 11% of the total vehicle travelled in the intermediate distance, 0% of the total vehicle used shoulder for maneuvering 19
  • 20. Speed and area ratio 01 02 Platoon Formation 03 Based on Homogeneous Co-efficient method Lagging headway 04 PCU estimation methods 20
  • 21. Speed and area ratio method • The PCU of different categories of vehicles are estimated based on the speed of the individual vehicles and the area occupied by them. PCU could be estimated from the relation shown below PCUi = (Vc /Vi ) / (Ac/Ai ) PCUi = Passenger Car Unit of vehicle type i. Vc, Vi = Average speed of small car and vehicle type i, respectively Ac, Ai = Projected area of small car and vehicle type i, respectively. 21
  • 22. Speed and area ratio method Vehicle Category Minimum Value PCU Maximum Value 2-Wheeler 0.2 0.25 0.36 Auto 0.87 1.1 1.61 Car - 1 - LCV 1.65 2.2 3.79 MCV 5.11 6.51 10.29 Vehicle Category Minimum Value PCU Maximum Value 2-Wheeler 0.14 0.24 0.44 Auto 0.64 1.02 2.66 Car - 1 - LCV 1.17 2.04 4.16 MCV 4.23 6.11 9.74 Sardar Patel Road IT Corridor 22
  • 23. PCU based on Homogeneous Co-efficient Method Permanent International Association of Road Congress (PIARC) proposed a model to determine Homogeneous Coefficient (or PCU) of a vehicle category present in a mixed traffic stream. The speed, as well as the length of a vehicle, were considered to formulate the Homogeneous Coefficient (HCi) as given below. PCUi = (Li/ Vi) / (Lc / Vc ) Where Li is the length of the subject vehicle (m) Lc is the length of the standard car Vi is the speed of the subject vehicle (Km/hr) Vc is the speed of the standard car (Km/hr) 23
  • 24. PCU based on Homogeneous Coefficient Method Vehicle Category Minimum Value PCU Maximum Value 2-Wheeler 0.38 0.46 0.65 Auto 0.75 0.96 1.42 Car - 1 - LCV 0.82 1.18 2.43 MCV 1.66 2.4 3.67 Vehicle Category Minimum Value PCU Maximum Value 2-Wheeler 0.29 0.44 1.05 Auto 0.56 0.9 2.72 Car - 1 - LCV 0.65 1.15 2.25 MCV 1.13 5.25 9.37 Sardar Patel Road IT Corridor 24
  • 25. PCU based on lagging headway Here, PCEs is defined as the ratio of the mean lagging headway of a subject vehicle divided by the mean lagging headway of the basic passenger car. Lagging headway is defined as the time or space from the rear of the leading vehicle to the rear of the vehicle of interest; it is composed of the length of the subject vehicle and the intravehicular gap. PCUi = (Hij) / (Hpcj ) Lagging headway of various categories of vehicles was calculated from the aggregated data and the PCUs of various categories of vehicles are calculated. 25
  • 26. PCU based on lagging headway Vehicle Category Minimum Value PCU Maximum Value 2-Wheeler 0.23 0.78 3.27 Auto 0.10 0.87 4.36 Car - 1 - LCV 0.14 1.04 3.91 MCV 0.13 1.2 4.6 Vehicle Category Minimum Value PCU Maximum Value 2-Wheeler 0.23 0.89 3.27 Auto 0.10 0.85 4.36 Car - 1 - LCV 0.14 1.31 3.91 MCV 0.13 1.15 4.6 Sardar Patel Road IT Corridor 26
  • 27. Platoon Formation Method The proper value of critical headway is used to decide whether vehicles included in platoons or not. The value of critical headway can be determined based on the mean relative speed method. RSPi = Si – Si-1 RSPi is the relative speed between vehicles i and i-1 in km/h Si is the speed of vehicles i in km/h. In the present study, to estimate the PCU values of car, two-wheeler, LCV, MCV and trucks, the Huber’s concept was used. In Huber method two streams, one containing only Passenger car (base stream) and the other containing Passenger cars and vehicle type for which PCU values is going to be estimated . 27
  • 28. Sardar Patel Road IT Corridor Platoon Formation Method Vehicle Category Minimum Value PCU Maximum Value 2-Wheeler 0.53 0.55 0.55 Auto 0.55 0.71 0.75 Car - 1 - LCV 1.07 1.15 1.22 MCV 2.47 2.66 3.35 Vehicle Category Minimum Value PCU Maximum Value 2-Wheeler 0.44 0.52 0.55 Auto 0.52 0.7 0.78 Car - 1 - LCV 1.16 1.18 1.23 MCV 2.37 2.47 2.52 28
  • 29. CAPACITY ESTIMATION - Greenshield model 0 10 20 30 40 50 60 70 0 1000 2000 3000 4000 5000 Speed Flow 0 10 20 30 40 50 60 70 0 5000 10000 15000 Speed Flow 0 10 20 30 40 50 60 70 0 5000 10000 15000 Speed Flow y = -0.1033x + 51.737 R² = 0.4764 0 10 20 30 40 50 60 70 0 100 200 300 400 Speed Density y = -0.1598x + 53.733 R² = 0.6351 0 10 20 30 40 50 60 70 0 50 100 150 Speed Density y = -0.1622x + 53.845 R² = 0.6449 0 10 20 30 40 50 60 70 0 50 100 150 Speed Density Speed and area ratio method Homogeneous Coefficient method Lagging Headway method Platoon formation method Sardar Patel Road 29
  • 30. CAPACITY ESTIMATION - Greenshield model PCU estimation Methods Capacity (PCU/hr) R2 value Equation Speed and area ratio method. 4469 0.6449 Y= -0.1622x + 53.845 Homogeneous coefficient method 4517 0.6351 Y= -0.1598x + 53.733 Lagging headway method 6478 0.4764 Y= -0.1033x+ 51.737 Platoon formation method 3008 0.1948 Y= -0.3261x +53.866 Sardar Patel Road 30
  • 31. CAPACITY ESTIMATION - Greenshield model Speed and area ratio method Homogeneous Coefficient method Lagging Headway method Platoon formation method IT Corridor y = -0.1455x + 52.824 R² = 0.3219 0 10 20 30 40 50 60 0 20 40 60 80 Speed Density 0 10 20 30 40 50 60 0 2000 4000 6000 Speed Flow y = -0.1372x + 52.905 R² = 0.3595 0 10 20 30 40 50 60 0 20 40 60 80 100 Speed Density 0 10 20 30 40 50 60 0 2000 4000 6000 Speed Flow y = -0.0778x + 50.778 R² = 0.3335 0 10 20 30 40 50 60 0 50 100 150 Speed Density 0 10 20 30 40 50 60 0 5000 10000 Speed Flow 31
  • 32. CAPACITY ESTIMATION - Greenshield model IT Corridor PCU estimation Methods Capacity (PCU/hr) R2 value Equation Speed and area ratio method. 4295 0.3219 Y= -0.1455x + 52.824 Homogeneous coefficient method 5100 0.3595 Y= -0.1372x + 52.905 Lagging headway method 8285 0.3335 Y= -0.0778x + 50.778 Platoon formation method 7140 0.1462 Y= -0.0467x + 49.145 32
  • 33. PCU Comparison 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 2 Wheeler Auto Bicycle Car HCV 0.25 1.10 1.00 2.20 6.51 0.46 0.96 1 1.18 2.4 0.78 0.87 1 1.04 1.2 0.52 0.7 1 1.18 2.47 IT Corridor Speed area ratio method Homogeneous Coefficient Method Lagging headway method Platoon PCU 33
  • 34. PCU Comparison 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 2 Wheeler Auto Bicycle Car HCV 0.24 1.02 1.00 2.04 6.11 0.44 0.9 1 1.15 2.15 0.89 0.85 1 1.31 1.15 0.55 0.71 1 1.15 2.66 PCU Vehicle class Sardar Patel Road speed and area ratio Homogeneous coefficient method Lagging Headway Platoon PCU 34
  • 35. CONCLUSION  Based on the analysis of the observed data it was found out that the Speed and area ratio method is the best suited for estimating the PCUs of the different vehicle categories in the Urban roads in which there is no lane discipline is being followed.  The platoon formation methods could also be used to identify the PCU values in a situation in which the Speed and area ratio method is found to be unreliable. Capacity (PCUs/hr) Sathish Chandra method Homogeneous Coefficient method Lagging headway method Platoon formation method Sardar Patel Road 4469 4517 6479 3008 IT Corridor 4795 5100 8285 7140 35
  • 36. LIMITATIONS OF THIS STUDY  Because the data was collected on urban roads, large vehicles such as HCVs, MAVs, and tractors have a very minor role in the traffic flow. As a result, the PCU values for these vehicles could not be calculated in this study.  If the nature of the traffic flow changes, the PCU values found out during this study may alter.  Since the PCU values found out using the Platoon formation method are based on the vehicular combinations, if there are more combinations available then the PCU values may alter. 36
  • 37. REFERENCE 1. Anand. S., Sekhar. S. V. C., & Karim. M. R. (1999). Development of passenger car unit values for Malaysia. Journal of the Eastern Asia Society for Transportation Studies, Vol.3, No.3, September, 73-80. 2. Ashish Dhamaniya and Satish Chandra (2013), Concept of Stream Equivalency Factor for Heterogeneous Traffic on Urban Arterial Roads, Journal of Transportation Engineering, Vol. 139, No. 11, November 1, 2013. 3. Chandra, S., and Sikdar, P. K. (2000). “Factors affecting PCE in mixed traffic situations on urban roads.” Road Transp. Res., 9(3), 40–50. 4. Debasis Basu, Swati Roy Maitra and Bhargab Maitra (2006), Modelling Passenger Car Equivalency at an urban midblock using stream speed as the measure of equivalence, European Transport Trasporti Europei n. 34 (2006): 75-87. 5. Geetam Tiwari, Joseph Fazio, Sri Pavitravas (2007), ‘Passenger car units for heterogenous traffic using modified density method’, National transportation library, US department of Transportation, Document 8612, pp. 246. 6. Pooja Raj, Kalaanidhi Sivagnanasundaram, Gowri Asaithambi and Ayyalasomayajula Udaya Ravi Shankar (2019), Review of Methods for Estimation of Passenger Car Unit Values of Vehicles, Journal of Transportation Engineering, Part A: Systems. 37
  • 38. 7. Rahman and Nakamura (2005), Measuring Passenger Car Equivalents for nonmotorized vehicle (rickshaws) at mid-block sections, Journal of the Eastern Asia Society for Transportation Studies, Vol. 6, pp. 119 - 126, 2005. 8. Sabayasachi Biswas, Ms. Somya Singh, Mr. Nihal Malik, Mr. Atul V.Bisen (2018), Estimation of Passenger Car Unit by Multi-objective optimization technique. 9. Satish Chandra and U. Kumar (2003), “Effect of Lane Width on Capacity under Mixed Traffic Conditions in India.” Journal of Transportation Engineering, ASCE 129 (2): 155–160. doi:10.1061/(ASCE)0733- 947X(2003)129:2(155). 10. Subhadip Biswas, Satish Chandra & Indrajit Ghosh (2018): An advanced approach for estimation of PCU values on undivided urban roads under heterogeneous traffic conditions, Transportation Letters, DOI: 10.1080/19427867.2018.1563268 11. V. Thamizh Arasan and Reebu Zachariah Koshy (2005), Methodology for Modeling Highly Heterogeneous Traffic Flow, the Journal of Transportation Engineering, Vol. 131, No. 7, July 1, 2005. 12. V. Thamizh Arasan and Shriniwas S. Arkatkar (2010), Microsimulation Study of Effect of Volume and Road Width on PCU of Vehicles under Heterogeneous Traffic, the Journal of Transportation Engineering, Vol. 136, No. 12, December 1, 2010 38