Question 1- The new president of Miskatonic University has decided on building a pool. She sat down with the contractor and together they determined what activities would have to occur, their precedence relationships, and the estimated durations (in weeks). The data are listed below. Draw the network diagram for this project. 1- What is the latest finish time for Activity D? 2- What is the earliest finish time for Activity G? 3- What is the slack time for Activity B? 4- What is the duration of the project on the critical path? 5- What is the critical path?.