BUEN GUIDO, BSME, ASQ-CQE
QA MANAGER
CASE STUDY – 0 Defect/100% OTD SUPPLIER QUALIFICATION
NewGen Construction
Case Study
• New Supplier “X” has been in the Construction
Industry, known for their sophistication for
automation has new sophisticated CNC Capability.
However the machine is currently being debugged.
• Able to take raw Revit files and feed directly to their
CNC machine eliminating the need for “Shop
Drawings”.
CASE #2 – ZERO/100 SUPPLIER QUALIFICATION
What?
Objective
• Qualify Supplier “X” as an approved NewGen
Construction supplier.
• Products produced to obtain Zero defects and
100% On-Time Delivery at the Construction Site.
CASE #2 – ZERO/100 SUPPLIER QUALIFICATION
Why?
Supplier Qualification:
I. Supplier “X” System and Process Audit.
II. CNC Manufacturer & Supplier “X” sign-off
• CNC Machine calibrated
• Operating per the manufacturers
specifications, limits and tolerances
III. Prototype Sample by Supplier using CNC
Obtain ZERO Defects & 100% OTD:
I. Process Development
II. Process (Six Sigma) Capability
III. Value Stream Mapping
CASE #2 – ZERO/100 SUPPLIER QUALIFICATION
How?
SupplierQualification
I – System & Process Audit
System Audit:
• Quality Program or Manual?
• Non-Conforming Material Management?
• Supply Quality Management?
• Corrective Action Preventive Action Process?
• KPI monitoring?
• ISO or other Certification?
Process Audit:
• How are incoming parts processed? Incoming QC
inspection present?
• PFMEA, Control Plan, PFD?
• Measurement Systems Capability?
• Metrology Lab?
• SPC?
• Ability to measure Rolled Throughput Yield?
SupplierQualification
II – CNC Manufacturer & Supplier Signoff
Final signoff to bring CNC Machine fully functional
and online for Production Use.
• Files from customers (Revit, Solidworks, Pro-E,
etc.) being translated with Zero degradation in
details?
• Perform several trial runs to make a part with
known dimensions and tolerances.
• Are the parts being produced within limits?
• Is the cycle time producing the part as per CNC
manufacturers Spec?
SupplierQualification
III – Prototype Sample by Supplier using CNC
Submission & Approval.
NewGen request for
RFQ and submits
completed design to
Supplier
Supplier Response –
Files accepted into
CNC
NewGen Approval to
Prototype. QA
monitors prototype
process
Supplier Prototype
Dimensional Report.
NewGen QA audits
report and Supplier’s
Measurement
Systems – Gage R&R
NewGen QA
Approves Prototype
Sample
ZERODefect&100%OTD
IV – Process Development
• Inputs from “lessons learned from Prototype”
• Equipment calibrated for first production run
• Volume ramp up – machine limitations
identified
• In-process and final QC inspections planned
• Control Plan – reaction plans for unplanned
production disruptions
• Measurement Systems – Gage R&R
ZERODefect&100%OTD
V – Process (Six Sigma) Capability
Run Process
Capability Study
Drive to a Six
Sigma Capability
Measure Rolled
Throughput Yield
ZERODefect&100%OTD
VI - Value Stream Mapping
 NewGen Contstruction to work with
Supplier LSS Black Belt in monitoring
performance (KPI) on a periodic basis.
 Develop a learning organization (NewGen
– Supplier) that will continue to find ways
to eliminate waste by running through
“Value Stream Mapping” over again.
Continuous
Improvement

Contenu connexe

Tendances

Ash Abel End of Semester Presentation
Ash Abel End of Semester PresentationAsh Abel End of Semester Presentation
Ash Abel End of Semester Presentation
Ash Abel
 
Resume +Tahir 2016
Resume +Tahir 2016Resume +Tahir 2016
Resume +Tahir 2016
Tahir Khan
 
D_David_ Thompson_resume_15_1
D_David_ Thompson_resume_15_1D_David_ Thompson_resume_15_1
D_David_ Thompson_resume_15_1
Dave Thompson
 
GP LIighting company presentation from Kenny
GP LIighting company presentation from KennyGP LIighting company presentation from Kenny
GP LIighting company presentation from Kenny
Kenny Deng
 
Tin To Professional Resume
Tin To Professional ResumeTin To Professional Resume
Tin To Professional Resume
Tin To
 
Qm ps for large db dbb projects
Qm ps for large db  dbb projectsQm ps for large db  dbb projects
Qm ps for large db dbb projects
Abayneh Mekonnen
 
Cbgl company overview 003
Cbgl company overview 003Cbgl company overview 003
Cbgl company overview 003
MyQlique
 

Tendances (18)

Ash Abel End of Semester Presentation
Ash Abel End of Semester PresentationAsh Abel End of Semester Presentation
Ash Abel End of Semester Presentation
 
SHASHANK Intern PPT
SHASHANK Intern PPTSHASHANK Intern PPT
SHASHANK Intern PPT
 
Managing The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy ProjectsManaging The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy Projects
 
Red Meat Processing Advanced Manufacturing - Waterless Frenching
Red Meat Processing Advanced Manufacturing - Waterless FrenchingRed Meat Processing Advanced Manufacturing - Waterless Frenching
Red Meat Processing Advanced Manufacturing - Waterless Frenching
 
vijay cv
vijay cvvijay cv
vijay cv
 
Michael Olinski Resume
Michael Olinski ResumeMichael Olinski Resume
Michael Olinski Resume
 
Samaa CV
Samaa CVSamaa CV
Samaa CV
 
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction Costs
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction CostsWhy 3D Laser Scanning Technology Lowers Brownfield Capital Construction Costs
Why 3D Laser Scanning Technology Lowers Brownfield Capital Construction Costs
 
Resume +Tahir 2016
Resume +Tahir 2016Resume +Tahir 2016
Resume +Tahir 2016
 
GenMach_Insert
GenMach_InsertGenMach_Insert
GenMach_Insert
 
Corporate Aviation Motion Products / VIP Market
Corporate Aviation Motion Products / VIP MarketCorporate Aviation Motion Products / VIP Market
Corporate Aviation Motion Products / VIP Market
 
D_David_ Thompson_resume_15_1
D_David_ Thompson_resume_15_1D_David_ Thompson_resume_15_1
D_David_ Thompson_resume_15_1
 
GP LIighting company presentation from Kenny
GP LIighting company presentation from KennyGP LIighting company presentation from Kenny
GP LIighting company presentation from Kenny
 
Tin To Professional Resume
Tin To Professional ResumeTin To Professional Resume
Tin To Professional Resume
 
RESUME
RESUMERESUME
RESUME
 
Qm ps for large db dbb projects
Qm ps for large db  dbb projectsQm ps for large db  dbb projects
Qm ps for large db dbb projects
 
Cbgl Company Overview(1)
Cbgl Company Overview(1)Cbgl Company Overview(1)
Cbgl Company Overview(1)
 
Cbgl company overview 003
Cbgl company overview 003Cbgl company overview 003
Cbgl company overview 003
 

Similaire à SUPPLIER QUALIFICATION CASE STUDY

Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006
Chris Baichoo
 
BQ-Engg Design Services 2012
BQ-Engg Design Services 2012BQ-Engg Design Services 2012
BQ-Engg Design Services 2012
NEERAJ SRIVASTAVA
 
BIM modeling for Carmel Valley Inn Hotel
BIM modeling for Carmel Valley Inn HotelBIM modeling for Carmel Valley Inn Hotel
BIM modeling for Carmel Valley Inn Hotel
Gaurav Kumar
 
GenerationRFID_Corp_2015_02
GenerationRFID_Corp_2015_02GenerationRFID_Corp_2015_02
GenerationRFID_Corp_2015_02
Albert Escala
 
MAKE IN INDIA @ KONZERT_ATD_PTD_04_AUG_2015
MAKE IN INDIA @ KONZERT_ATD_PTD_04_AUG_2015MAKE IN INDIA @ KONZERT_ATD_PTD_04_AUG_2015
MAKE IN INDIA @ KONZERT_ATD_PTD_04_AUG_2015
RAJIV SESHADRI
 

Similaire à SUPPLIER QUALIFICATION CASE STUDY (20)

OmexEngBrochure
OmexEngBrochureOmexEngBrochure
OmexEngBrochure
 
Preeti Sharma tech
Preeti Sharma techPreeti Sharma tech
Preeti Sharma tech
 
Manish engg ppt 26.04.16
Manish engg ppt 26.04.16Manish engg ppt 26.04.16
Manish engg ppt 26.04.16
 
SMT Sales 2011
SMT Sales 2011SMT Sales 2011
SMT Sales 2011
 
SMT 2011
SMT 2011SMT 2011
SMT 2011
 
Control Panels USA - custom industiral control solutions
Control Panels USA - custom industiral control solutionsControl Panels USA - custom industiral control solutions
Control Panels USA - custom industiral control solutions
 
Functional verification techniques EW16 session
Functional verification techniques  EW16 sessionFunctional verification techniques  EW16 session
Functional verification techniques EW16 session
 
Sdlc
Sdlc Sdlc
Sdlc
 
Vinay Resume
Vinay ResumeVinay Resume
Vinay Resume
 
atm-facilities-and-equipment.pptx
atm-facilities-and-equipment.pptxatm-facilities-and-equipment.pptx
atm-facilities-and-equipment.pptx
 
atm-facilitie.pptx
atm-facilitie.pptxatm-facilitie.pptx
atm-facilitie.pptx
 
atm-faci.pptx
atm-faci.pptxatm-faci.pptx
atm-faci.pptx
 
atm-facilities-and-equipment.pptx
atm-facilities-and-equipment.pptxatm-facilities-and-equipment.pptx
atm-facilities-and-equipment.pptx
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006
 
BQ-Engg Design Services 2012
BQ-Engg Design Services 2012BQ-Engg Design Services 2012
BQ-Engg Design Services 2012
 
RADIX Presentation
RADIX PresentationRADIX Presentation
RADIX Presentation
 
Mecosoft Product Development Lifecycle
Mecosoft Product Development LifecycleMecosoft Product Development Lifecycle
Mecosoft Product Development Lifecycle
 
BIM modeling for Carmel Valley Inn Hotel
BIM modeling for Carmel Valley Inn HotelBIM modeling for Carmel Valley Inn Hotel
BIM modeling for Carmel Valley Inn Hotel
 
GenerationRFID_Corp_2015_02
GenerationRFID_Corp_2015_02GenerationRFID_Corp_2015_02
GenerationRFID_Corp_2015_02
 
MAKE IN INDIA @ KONZERT_ATD_PTD_04_AUG_2015
MAKE IN INDIA @ KONZERT_ATD_PTD_04_AUG_2015MAKE IN INDIA @ KONZERT_ATD_PTD_04_AUG_2015
MAKE IN INDIA @ KONZERT_ATD_PTD_04_AUG_2015
 

SUPPLIER QUALIFICATION CASE STUDY

  • 1. BUEN GUIDO, BSME, ASQ-CQE QA MANAGER CASE STUDY – 0 Defect/100% OTD SUPPLIER QUALIFICATION NewGen Construction
  • 2. Case Study • New Supplier “X” has been in the Construction Industry, known for their sophistication for automation has new sophisticated CNC Capability. However the machine is currently being debugged. • Able to take raw Revit files and feed directly to their CNC machine eliminating the need for “Shop Drawings”. CASE #2 – ZERO/100 SUPPLIER QUALIFICATION What?
  • 3. Objective • Qualify Supplier “X” as an approved NewGen Construction supplier. • Products produced to obtain Zero defects and 100% On-Time Delivery at the Construction Site. CASE #2 – ZERO/100 SUPPLIER QUALIFICATION Why?
  • 4. Supplier Qualification: I. Supplier “X” System and Process Audit. II. CNC Manufacturer & Supplier “X” sign-off • CNC Machine calibrated • Operating per the manufacturers specifications, limits and tolerances III. Prototype Sample by Supplier using CNC Obtain ZERO Defects & 100% OTD: I. Process Development II. Process (Six Sigma) Capability III. Value Stream Mapping CASE #2 – ZERO/100 SUPPLIER QUALIFICATION How?
  • 5. SupplierQualification I – System & Process Audit System Audit: • Quality Program or Manual? • Non-Conforming Material Management? • Supply Quality Management? • Corrective Action Preventive Action Process? • KPI monitoring? • ISO or other Certification? Process Audit: • How are incoming parts processed? Incoming QC inspection present? • PFMEA, Control Plan, PFD? • Measurement Systems Capability? • Metrology Lab? • SPC? • Ability to measure Rolled Throughput Yield?
  • 6. SupplierQualification II – CNC Manufacturer & Supplier Signoff Final signoff to bring CNC Machine fully functional and online for Production Use. • Files from customers (Revit, Solidworks, Pro-E, etc.) being translated with Zero degradation in details? • Perform several trial runs to make a part with known dimensions and tolerances. • Are the parts being produced within limits? • Is the cycle time producing the part as per CNC manufacturers Spec?
  • 7. SupplierQualification III – Prototype Sample by Supplier using CNC Submission & Approval. NewGen request for RFQ and submits completed design to Supplier Supplier Response – Files accepted into CNC NewGen Approval to Prototype. QA monitors prototype process Supplier Prototype Dimensional Report. NewGen QA audits report and Supplier’s Measurement Systems – Gage R&R NewGen QA Approves Prototype Sample
  • 8. ZERODefect&100%OTD IV – Process Development • Inputs from “lessons learned from Prototype” • Equipment calibrated for first production run • Volume ramp up – machine limitations identified • In-process and final QC inspections planned • Control Plan – reaction plans for unplanned production disruptions • Measurement Systems – Gage R&R
  • 9. ZERODefect&100%OTD V – Process (Six Sigma) Capability Run Process Capability Study Drive to a Six Sigma Capability Measure Rolled Throughput Yield
  • 11.  NewGen Contstruction to work with Supplier LSS Black Belt in monitoring performance (KPI) on a periodic basis.  Develop a learning organization (NewGen – Supplier) that will continue to find ways to eliminate waste by running through “Value Stream Mapping” over again. Continuous Improvement