LEAN CONSTRUCTIONLEAN CONSTRUCTION
SUPPLY CHAINSUPPLY CHAIN
MANAGEMENT (SCM)MANAGEMENT (SCM)
&&
LAST PLANNER SYSTEMLAST PLANNER SYSTEM
(LPS)(LPS)
LEAN CONSTRUCTION
 Lean construction main objective is
to maximizes value and reduces
waste.
 It applies specific techniques in an
innovative project delivery
approach.
 It including:
1. supply chain management,
2. Just-In-Time techniques.
LEAN CONSTRUCTION
 As well as the open sharing of
information between all the parties
involved in the production process.
 Lean manufacturing is an outgrowth of
the Toyota Production system.
 Developed by Taichii Ohno in Toyota
in the 1950s.
SUPPLY CHAIN MANAGEMENT
The term supply chain, includes,
all the activities that lead a high
quality product.
Customer satisfaction comes
from a good service or high
quality product such as:
materials
information
SUPPLY CHAIN MANAGEMENT
 funds
 People
 etc.
 Some researchers argue that the cost of a
product or service will increase of up to
10% percent because of poor supply
chain design.
SUPPLY CHAIN MANAGEMENT
 Supply Chain Management (SCM)
analyzes the impact of design work on
the construction process.
 It enables much better project
planning and management.
 Through SCM, all parties are kept
aware of important determinants such
as:
SUPPLY CHAIN MANAGEMENT
 commitments
 schedules
 A high level of team work and corporation
that can:
 Source, produce and deliver products with
minimal lead-time and expense.
SUPPLY CHAIN MANAGEMENT
 Construction industry does not emphasize
enough on construction productivity and it’s
determinants.
 The industry measures performance in
terms of the following:
 completion on time
 completion within budget
 meeting construction codes
SUPPLY CHAIN MANAGEMENT
 Contractors often hire subcontractors
 Sub contractors do not have contracts
with the owner
 Poor supply chain
 Sometimes client pays a high price to
contractor, however, the subcontractor
may still have to work with inadequate
budgets.
 Often compromising quality as a result.
SUPPLY CHAIN MANAGEMENT
 Communication tends to be via the
contract, and is limited.
 Innovation moves slowly in
construction.
 Sometimes there is a complete lack
on innovation.
 Few large companies, and almost no
small companies have implemented
the concept of a high quality product
or service.
SUPPLY CHAIN MANAGEMENT
 There is no desire to have a productivity
manager.
 The traditional approach is to depend on
the experienced staff to run projects
efficiently.
 Such staff are rarely if ever trained in
optimization techniques.
LAST PLANNER SYSTEM
 The Last Planner System (LPS)-for
small firms, improves both design
and construction schedule/
programme predictability.
 Work completed always on time.
 It is a system of inter-related
elements.
LAST PLANNER SYSTEM
 Full benefits come when all are
implemented together.
 Based on simple paper forms, it can be
administered using Post-it notes, paper,
pencil, eraser and photocopier.
 A spreadsheet can help.
LAST PLANNER SYSTEM
 LPS begins with collaborative
scheduling/programming engaging the
main project suppliers from the start.
 Risk analysis ensures that float is built in
where it will best protect programme
integrity and predictability.
 Where appropriate the process can be
used for programme compression too.
LAST PLANNER SYSTEM
LAST PLANNER SYSTEM
 A key part of the continual improvement
process is a study of the reasons why
tasks promised in the WWP are delivered
late.
 The following chart shows typical
reasons:

Figure 4: example of a reasons Pareto
chart
LAST PLANNER SYSTEM
LAST PLANNER SYSTEM
 Differences between Lean
Construction approach and PMI
approach
 Lean Construction Exam questions.
LAST PLANNER SYSTEM

Contenu connexe

Tendances

Lean Construction_PMI_Nov 19, 2016
Lean Construction_PMI_Nov 19, 2016Lean Construction_PMI_Nov 19, 2016
Lean Construction_PMI_Nov 19, 2016Murali Naidu
 
Lean Construction: From Theory to Implementation
Lean Construction: From Theory to ImplementationLean Construction: From Theory to Implementation
Lean Construction: From Theory to ImplementationAntonius Pompi Bramono
 
LCI Ireland COP March 2015 Event ( Sponsored by Project Management )
LCI Ireland COP   March 2015 Event ( Sponsored by Project Management )LCI Ireland COP   March 2015 Event ( Sponsored by Project Management )
LCI Ireland COP March 2015 Event ( Sponsored by Project Management )John French
 
Lean Construction Webinar
Lean Construction WebinarLean Construction Webinar
Lean Construction WebinarBMGI India
 
Chapter 3. CON CURRENT ENGINEERING
Chapter 3. CON CURRENT ENGINEERINGChapter 3. CON CURRENT ENGINEERING
Chapter 3. CON CURRENT ENGINEERINGProf.Mayur Modi
 
Concurrent Engineering
Concurrent EngineeringConcurrent Engineering
Concurrent Engineeringajithsrc
 
Last planner system
Last planner systemLast planner system
Last planner systemAnshi Verma
 
Dfma as the tool for concurrent engineering
Dfma as the tool for concurrent engineeringDfma as the tool for concurrent engineering
Dfma as the tool for concurrent engineeringGowsick Subramaniam
 
Minimising waste in construction by using lean six sigma principle
Minimising waste in construction by using lean six sigma principleMinimising waste in construction by using lean six sigma principle
Minimising waste in construction by using lean six sigma principleIAEME Publication
 
Concurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & SustainabilityConcurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & SustainabilityIRJET Journal
 
Five ways to improve productivity at the construction site
Five ways to improve productivity at the construction siteFive ways to improve productivity at the construction site
Five ways to improve productivity at the construction siteVikaslal2006
 
Concurrent Engineering in Industry
Concurrent Engineering in IndustryConcurrent Engineering in Industry
Concurrent Engineering in IndustryPrashanth Selvam
 
Tuning the planning and control system to product and process design: G1
Tuning the planning and control system to product and process design: G1Tuning the planning and control system to product and process design: G1
Tuning the planning and control system to product and process design: G1i4VC
 
Lean and agile manufacturing system
Lean and agile manufacturing systemLean and agile manufacturing system
Lean and agile manufacturing systemAnas CK
 

Tendances (20)

Lean Construction_PMI_Nov 19, 2016
Lean Construction_PMI_Nov 19, 2016Lean Construction_PMI_Nov 19, 2016
Lean Construction_PMI_Nov 19, 2016
 
Lean Construction: From Theory to Implementation
Lean Construction: From Theory to ImplementationLean Construction: From Theory to Implementation
Lean Construction: From Theory to Implementation
 
LCI Ireland COP March 2015 Event ( Sponsored by Project Management )
LCI Ireland COP   March 2015 Event ( Sponsored by Project Management )LCI Ireland COP   March 2015 Event ( Sponsored by Project Management )
LCI Ireland COP March 2015 Event ( Sponsored by Project Management )
 
Lean construction
Lean constructionLean construction
Lean construction
 
Lean Construction Webinar
Lean Construction WebinarLean Construction Webinar
Lean Construction Webinar
 
Lean Construction Management
Lean Construction Management Lean Construction Management
Lean Construction Management
 
Chapter 3. CON CURRENT ENGINEERING
Chapter 3. CON CURRENT ENGINEERINGChapter 3. CON CURRENT ENGINEERING
Chapter 3. CON CURRENT ENGINEERING
 
Concurrent Engineering
Concurrent EngineeringConcurrent Engineering
Concurrent Engineering
 
Last planner system
Last planner systemLast planner system
Last planner system
 
Dfma as the tool for concurrent engineering
Dfma as the tool for concurrent engineeringDfma as the tool for concurrent engineering
Dfma as the tool for concurrent engineering
 
Lean construction
Lean constructionLean construction
Lean construction
 
Fms seminar
Fms seminarFms seminar
Fms seminar
 
Minimising waste in construction by using lean six sigma principle
Minimising waste in construction by using lean six sigma principleMinimising waste in construction by using lean six sigma principle
Minimising waste in construction by using lean six sigma principle
 
Lean vs agile manufacturing
Lean vs agile manufacturingLean vs agile manufacturing
Lean vs agile manufacturing
 
Concurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & SustainabilityConcurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & Sustainability
 
120 tqm-constructability-bar chart
120 tqm-constructability-bar chart120 tqm-constructability-bar chart
120 tqm-constructability-bar chart
 
Five ways to improve productivity at the construction site
Five ways to improve productivity at the construction siteFive ways to improve productivity at the construction site
Five ways to improve productivity at the construction site
 
Concurrent Engineering in Industry
Concurrent Engineering in IndustryConcurrent Engineering in Industry
Concurrent Engineering in Industry
 
Tuning the planning and control system to product and process design: G1
Tuning the planning and control system to product and process design: G1Tuning the planning and control system to product and process design: G1
Tuning the planning and control system to product and process design: G1
 
Lean and agile manufacturing system
Lean and agile manufacturing systemLean and agile manufacturing system
Lean and agile manufacturing system
 

En vedette

Lean practices for effective project management
Lean practices for effective project managementLean practices for effective project management
Lean practices for effective project managementvimal raj
 
Project delivery, what good looks like
Project delivery, what good looks likeProject delivery, what good looks like
Project delivery, what good looks likeMatthew Rees
 
Mise en place d’une démarche lean construction dans le pilotage des corps d’é...
Mise en place d’une démarche lean construction dans le pilotage des corps d’é...Mise en place d’une démarche lean construction dans le pilotage des corps d’é...
Mise en place d’une démarche lean construction dans le pilotage des corps d’é...Stéphane Cazin
 
6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery Methods6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery MethodsMcCarthy Holdings, Inc.
 
Integrated Project Delivery
Integrated Project DeliveryIntegrated Project Delivery
Integrated Project DeliveryMike Purdy
 
Design thinking & lean startup
Design thinking & lean startupDesign thinking & lean startup
Design thinking & lean startupRemko Vermeulen
 
Design Thinking vs Lean Startup - which to use, and when
Design Thinking vs Lean Startup - which to use, and whenDesign Thinking vs Lean Startup - which to use, and when
Design Thinking vs Lean Startup - which to use, and whenOXC Design + Strategy
 
Lean product development implementation
Lean product development implementationLean product development implementation
Lean product development implementationITZHAK123
 
Lean Product Development 101
Lean Product Development 101Lean Product Development 101
Lean Product Development 101Cloud Elements
 
Lean Product Development
Lean Product DevelopmentLean Product Development
Lean Product DevelopmentTim McMahon
 
Lean Design Thinking Crash Course
Lean Design Thinking Crash CourseLean Design Thinking Crash Course
Lean Design Thinking Crash CourseReuven Cohen
 
Design thinking and agile development
Design thinking and agile developmentDesign thinking and agile development
Design thinking and agile developmentW. Alex Jansen
 
Design Thinking & Agile Innovation Workshop
Design Thinking & Agile Innovation WorkshopDesign Thinking & Agile Innovation Workshop
Design Thinking & Agile Innovation WorkshopJosef Scherer
 
Journée Agilité avec EI.CESI du 4 mai 2012
Journée Agilité avec EI.CESI du 4 mai 2012Journée Agilité avec EI.CESI du 4 mai 2012
Journée Agilité avec EI.CESI du 4 mai 2012Fabrice Aimetti
 

En vedette (18)

Lean practices for effective project management
Lean practices for effective project managementLean practices for effective project management
Lean practices for effective project management
 
Project delivery, what good looks like
Project delivery, what good looks likeProject delivery, what good looks like
Project delivery, what good looks like
 
Last planner s
Last planner sLast planner s
Last planner s
 
Mise en place d’une démarche lean construction dans le pilotage des corps d’é...
Mise en place d’une démarche lean construction dans le pilotage des corps d’é...Mise en place d’une démarche lean construction dans le pilotage des corps d’é...
Mise en place d’une démarche lean construction dans le pilotage des corps d’é...
 
6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery Methods6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery Methods
 
Integrated Project Delivery
Integrated Project DeliveryIntegrated Project Delivery
Integrated Project Delivery
 
Design thinking & lean startup
Design thinking & lean startupDesign thinking & lean startup
Design thinking & lean startup
 
Design Thinking vs Lean Startup - which to use, and when
Design Thinking vs Lean Startup - which to use, and whenDesign Thinking vs Lean Startup - which to use, and when
Design Thinking vs Lean Startup - which to use, and when
 
Last planner system
Last planner systemLast planner system
Last planner system
 
Lean product development implementation
Lean product development implementationLean product development implementation
Lean product development implementation
 
Lean Product Development by Ron Mascitelli
Lean Product Development by Ron Mascitelli Lean Product Development by Ron Mascitelli
Lean Product Development by Ron Mascitelli
 
Lean Product Development 101
Lean Product Development 101Lean Product Development 101
Lean Product Development 101
 
Last planner workshop
Last planner workshopLast planner workshop
Last planner workshop
 
Lean Product Development
Lean Product DevelopmentLean Product Development
Lean Product Development
 
Lean Design Thinking Crash Course
Lean Design Thinking Crash CourseLean Design Thinking Crash Course
Lean Design Thinking Crash Course
 
Design thinking and agile development
Design thinking and agile developmentDesign thinking and agile development
Design thinking and agile development
 
Design Thinking & Agile Innovation Workshop
Design Thinking & Agile Innovation WorkshopDesign Thinking & Agile Innovation Workshop
Design Thinking & Agile Innovation Workshop
 
Journée Agilité avec EI.CESI du 4 mai 2012
Journée Agilité avec EI.CESI du 4 mai 2012Journée Agilité avec EI.CESI du 4 mai 2012
Journée Agilité avec EI.CESI du 4 mai 2012
 

Similaire à 059 LEAN CONSTRUCTION SUPPLY CHAIN-SCM &LPS

058 lean construction (2)
058 lean construction (2)058 lean construction (2)
058 lean construction (2)drdej19
 
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSSTUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSIRJET Journal
 
044 integrating scm with fem and tqm
044 integrating scm with fem and tqm044 integrating scm with fem and tqm
044 integrating scm with fem and tqmdrdej19
 
044 INTERGRATING SCN WITH FEM AND TQM
044 INTERGRATING SCN WITH FEM AND TQM 044 INTERGRATING SCN WITH FEM AND TQM
044 INTERGRATING SCN WITH FEM AND TQM Dr Fereidoun Dejahang
 
Agile Project Management Methods of ERP
Agile Project Management Methods of ERPAgile Project Management Methods of ERP
Agile Project Management Methods of ERPlisa_yogi
 
The Product Life Management ; A challenge for Aerospace
The Product Life Management ; A challenge for AerospaceThe Product Life Management ; A challenge for Aerospace
The Product Life Management ; A challenge for AerospaceJérémy LECOINTRE
 
Product Life Management ; A challenge for Aerospace
Product Life Management ; A challenge for AerospaceProduct Life Management ; A challenge for Aerospace
Product Life Management ; A challenge for AerospaceJérémy LECOINTRE
 
The ‘Product Life Management’, a challenge for Aerospace
The ‘Product Life Management’, a challenge for AerospaceThe ‘Product Life Management’, a challenge for Aerospace
The ‘Product Life Management’, a challenge for AerospaceJérémy LECOINTRE
 
The ‘Product Life Management’, a challenge for Aerospace
The ‘Product Life Management’, a challenge for AerospaceThe ‘Product Life Management’, a challenge for Aerospace
The ‘Product Life Management’, a challenge for AerospaceJérémy LECOINTRE
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"David Pedreno
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"David Pedreno
 
Northern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentNorthern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentSiwawong Wuttipongprasert
 
041 Integrating Lean Construction (PART 2)
041 Integrating Lean Construction (PART 2)041 Integrating Lean Construction (PART 2)
041 Integrating Lean Construction (PART 2)Dr Fereidoun Dejahang
 
041 integrating lean construction (2)
041 integrating lean construction (2)041 integrating lean construction (2)
041 integrating lean construction (2)drdej19
 
Major Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperMajor Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperIan Heptinstall
 
Keys to Succeed in Implementing Total Preventive Maintenance (TPM) and Lean S...
Keys to Succeed in Implementing Total Preventive Maintenance (TPM) and Lean S...Keys to Succeed in Implementing Total Preventive Maintenance (TPM) and Lean S...
Keys to Succeed in Implementing Total Preventive Maintenance (TPM) and Lean S...IJMTST Journal
 
Increasing Vehicle Outsourcing ( % Of Car Value ) Essay
Increasing Vehicle Outsourcing ( % Of Car Value ) EssayIncreasing Vehicle Outsourcing ( % Of Car Value ) Essay
Increasing Vehicle Outsourcing ( % Of Car Value ) EssayAlison Reed
 
6475- RAILWAY RESERVATION SYSTEM.pdf
6475- RAILWAY RESERVATION SYSTEM.pdf6475- RAILWAY RESERVATION SYSTEM.pdf
6475- RAILWAY RESERVATION SYSTEM.pdfRmsDagi
 
Engineering Construction 4.0 Revolution
Engineering Construction 4.0 RevolutionEngineering Construction 4.0 Revolution
Engineering Construction 4.0 RevolutionFrancesco Legname
 

Similaire à 059 LEAN CONSTRUCTION SUPPLY CHAIN-SCM &LPS (20)

058 lean construction (2)
058 lean construction (2)058 lean construction (2)
058 lean construction (2)
 
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSSTUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
 
044 integrating scm with fem and tqm
044 integrating scm with fem and tqm044 integrating scm with fem and tqm
044 integrating scm with fem and tqm
 
044 INTERGRATING SCN WITH FEM AND TQM
044 INTERGRATING SCN WITH FEM AND TQM 044 INTERGRATING SCN WITH FEM AND TQM
044 INTERGRATING SCN WITH FEM AND TQM
 
Agile Project Management Methods of ERP
Agile Project Management Methods of ERPAgile Project Management Methods of ERP
Agile Project Management Methods of ERP
 
The Product Life Management ; A challenge for Aerospace
The Product Life Management ; A challenge for AerospaceThe Product Life Management ; A challenge for Aerospace
The Product Life Management ; A challenge for Aerospace
 
Product Life Management ; A challenge for Aerospace
Product Life Management ; A challenge for AerospaceProduct Life Management ; A challenge for Aerospace
Product Life Management ; A challenge for Aerospace
 
The ‘Product Life Management’, a challenge for Aerospace
The ‘Product Life Management’, a challenge for AerospaceThe ‘Product Life Management’, a challenge for Aerospace
The ‘Product Life Management’, a challenge for Aerospace
 
The ‘Product Life Management’, a challenge for Aerospace
The ‘Product Life Management’, a challenge for AerospaceThe ‘Product Life Management’, a challenge for Aerospace
The ‘Product Life Management’, a challenge for Aerospace
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
 
Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"Asset Finance Systems: Project Initiation "101"
Asset Finance Systems: Project Initiation "101"
 
Northern Finishing School: IT Project Managment
Northern Finishing School: IT Project ManagmentNorthern Finishing School: IT Project Managment
Northern Finishing School: IT Project Managment
 
041 Integrating Lean Construction (PART 2)
041 Integrating Lean Construction (PART 2)041 Integrating Lean Construction (PART 2)
041 Integrating Lean Construction (PART 2)
 
041 integrating lean construction (2)
041 integrating lean construction (2)041 integrating lean construction (2)
041 integrating lean construction (2)
 
Major Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperMajor Projects - Faster Better Cheaper
Major Projects - Faster Better Cheaper
 
Keys to Succeed in Implementing Total Preventive Maintenance (TPM) and Lean S...
Keys to Succeed in Implementing Total Preventive Maintenance (TPM) and Lean S...Keys to Succeed in Implementing Total Preventive Maintenance (TPM) and Lean S...
Keys to Succeed in Implementing Total Preventive Maintenance (TPM) and Lean S...
 
Pia white paper
Pia white paperPia white paper
Pia white paper
 
Increasing Vehicle Outsourcing ( % Of Car Value ) Essay
Increasing Vehicle Outsourcing ( % Of Car Value ) EssayIncreasing Vehicle Outsourcing ( % Of Car Value ) Essay
Increasing Vehicle Outsourcing ( % Of Car Value ) Essay
 
6475- RAILWAY RESERVATION SYSTEM.pdf
6475- RAILWAY RESERVATION SYSTEM.pdf6475- RAILWAY RESERVATION SYSTEM.pdf
6475- RAILWAY RESERVATION SYSTEM.pdf
 
Engineering Construction 4.0 Revolution
Engineering Construction 4.0 RevolutionEngineering Construction 4.0 Revolution
Engineering Construction 4.0 Revolution
 

Plus de Dr Fereidoun Dejahang

27 j20 my news punch -dr f dejahang 27-01-2020
27 j20 my news punch -dr f dejahang  27-01-202027 j20 my news punch -dr f dejahang  27-01-2020
27 j20 my news punch -dr f dejahang 27-01-2020Dr Fereidoun Dejahang
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrunDr Fereidoun Dejahang
 
026 fast react-productivity improvement
026 fast react-productivity improvement026 fast react-productivity improvement
026 fast react-productivity improvementDr Fereidoun Dejahang
 
022 b construction productivity-write
022 b construction productivity-write022 b construction productivity-write
022 b construction productivity-writeDr Fereidoun Dejahang
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sectorDr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projectsDr Fereidoun Dejahang
 

Plus de Dr Fereidoun Dejahang (20)

27 j20 my news punch -dr f dejahang 27-01-2020
27 j20 my news punch -dr f dejahang  27-01-202027 j20 my news punch -dr f dejahang  27-01-2020
27 j20 my news punch -dr f dejahang 27-01-2020
 
28 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-201928 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-2019
 
16 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-201916 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-2019
 
029 fast-tracking projects
029 fast-tracking projects029 fast-tracking projects
029 fast-tracking projects
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun
 
027 fast-tracked projects-materials
027 fast-tracked projects-materials027 fast-tracked projects-materials
027 fast-tracked projects-materials
 
026 fast react-productivity improvement
026 fast react-productivity improvement026 fast react-productivity improvement
026 fast react-productivity improvement
 
025 enterprise resources management
025 enterprise resources management025 enterprise resources management
025 enterprise resources management
 
022 b construction productivity-write
022 b construction productivity-write022 b construction productivity-write
022 b construction productivity-write
 
022 a construction productivity (2)
022 a construction productivity (2)022 a construction productivity (2)
022 a construction productivity (2)
 
021 construction productivity (1)
021 construction productivity (1)021 construction productivity (1)
021 construction productivity (1)
 
019 competencies-managers
019 competencies-managers019 competencies-managers
019 competencies-managers
 
018 company productivity
018 company productivity018 company productivity
018 company productivity
 
017 communication
017 communication017 communication
017 communication
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sector
 
015 changes-process model
015 changes-process model015 changes-process model
015 changes-process model
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projects
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
 
011 business performance management
011 business performance management011 business performance management
011 business performance management
 

Dernier

Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesRAJNEESHKUMAR341697
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesMayuraD1
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 

Dernier (20)

Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 

059 LEAN CONSTRUCTION SUPPLY CHAIN-SCM &LPS

  • 1. helpdesk@construction-productivity.co.uk htt://www.construction-productivity.co.uk LEAN CONSTRUCTIONLEAN CONSTRUCTION SUPPLY CHAINSUPPLY CHAIN MANAGEMENT (SCM)MANAGEMENT (SCM) && LAST PLANNER SYSTEMLAST PLANNER SYSTEM (LPS)(LPS)
  • 2. LEAN CONSTRUCTION  Lean construction main objective is to maximizes value and reduces waste.  It applies specific techniques in an innovative project delivery approach.  It including: 1. supply chain management, 2. Just-In-Time techniques.
  • 3.
  • 4. LEAN CONSTRUCTION  As well as the open sharing of information between all the parties involved in the production process.  Lean manufacturing is an outgrowth of the Toyota Production system.  Developed by Taichii Ohno in Toyota in the 1950s.
  • 5. SUPPLY CHAIN MANAGEMENT The term supply chain, includes, all the activities that lead a high quality product. Customer satisfaction comes from a good service or high quality product such as: materials information
  • 6. SUPPLY CHAIN MANAGEMENT  funds  People  etc.  Some researchers argue that the cost of a product or service will increase of up to 10% percent because of poor supply chain design.
  • 7. SUPPLY CHAIN MANAGEMENT  Supply Chain Management (SCM) analyzes the impact of design work on the construction process.  It enables much better project planning and management.  Through SCM, all parties are kept aware of important determinants such as:
  • 8. SUPPLY CHAIN MANAGEMENT  commitments  schedules  A high level of team work and corporation that can:  Source, produce and deliver products with minimal lead-time and expense.
  • 9. SUPPLY CHAIN MANAGEMENT  Construction industry does not emphasize enough on construction productivity and it’s determinants.  The industry measures performance in terms of the following:  completion on time  completion within budget  meeting construction codes
  • 10. SUPPLY CHAIN MANAGEMENT  Contractors often hire subcontractors  Sub contractors do not have contracts with the owner  Poor supply chain  Sometimes client pays a high price to contractor, however, the subcontractor may still have to work with inadequate budgets.  Often compromising quality as a result.
  • 11. SUPPLY CHAIN MANAGEMENT  Communication tends to be via the contract, and is limited.  Innovation moves slowly in construction.  Sometimes there is a complete lack on innovation.  Few large companies, and almost no small companies have implemented the concept of a high quality product or service.
  • 12. SUPPLY CHAIN MANAGEMENT  There is no desire to have a productivity manager.  The traditional approach is to depend on the experienced staff to run projects efficiently.  Such staff are rarely if ever trained in optimization techniques.
  • 13. LAST PLANNER SYSTEM  The Last Planner System (LPS)-for small firms, improves both design and construction schedule/ programme predictability.  Work completed always on time.  It is a system of inter-related elements.
  • 14. LAST PLANNER SYSTEM  Full benefits come when all are implemented together.  Based on simple paper forms, it can be administered using Post-it notes, paper, pencil, eraser and photocopier.  A spreadsheet can help.
  • 15. LAST PLANNER SYSTEM  LPS begins with collaborative scheduling/programming engaging the main project suppliers from the start.  Risk analysis ensures that float is built in where it will best protect programme integrity and predictability.  Where appropriate the process can be used for programme compression too.
  • 16.
  • 18. LAST PLANNER SYSTEM  A key part of the continual improvement process is a study of the reasons why tasks promised in the WWP are delivered late.  The following chart shows typical reasons:  Figure 4: example of a reasons Pareto chart
  • 20. LAST PLANNER SYSTEM  Differences between Lean Construction approach and PMI approach  Lean Construction Exam questions.