SlideShare une entreprise Scribd logo
1  sur  8
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
0
Project Management
Resource Allocation and Smoothing
Dr. Mahmoud Abbas Mahmoud
Assistant Professor
2017
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
1
Resource Allocation and Smoothing
1. Resource Planning
A resource may be defined as the machine or person who will perform the scope
of work. Resource planning is forecasting the resources required to perform the
scope of work within the time plan.
The resource constraint should be considered after the network diagram, schedule
bar chart and procurement schedule have been developed. But before the crash-
flow statement.
2. Resource Estimating
The resource estimates is linked directly to the scope of work and bill of materials
(BOM). The scope of work may be expressed as so many tons of steel, or so many
square meters of wall paint etc. From this description estimator can convert the
scope of work into manhours per unit ‘X’.
Consider the following, if the scope of work is to erect (assemble) 12 tons of steel
and the estimator knows from past experience that the work can be done in 150
manhours per ton and the men work 10 hour shifts, then the equation is:
( 12 tons × 150 manhours per ton )
10 hrs per day
= 180 mandays
Resource / Duration Trade-Off
3. Resource Forecasting
Resource forecasting is to forecast the total resource requirement by discipline or
interchangeable resource. An interchangeable resource is when you have a pool
(group) of workers and any one of them could perform the work. This is done by
compiling all the resource estimates and presenting them in a structured resource
table.
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
2
Resource Table
Resource Forecast - Bar Chart
Resource Forecast – Histogram
Note: The bar chart shows the number of resources per activity per day, and the
histogram shows the total recourse required per day.
4. Resource Availability
In establishing the resource availability, the following points should be
considered:
a- Other resource commitments - if your company is involved in a number of
projects which all draw from a common labor pool, the other projects'
requirements must also be considered (also called multi-project resource
scheduling).
b- The anticipated sickness and absenteeism rate. For example: allow for a
25% absentee rate based on experience.
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
3
Planning for a 25% Absenteeism
Keeping the above points in mind, the resource availability table will be
developed. Consider the following example:
5. Resource Histogram
The resource histogram is a popular planning tool because it gives a good visual
presentation which is easy to assimilate and understand. The prerequisites for
drawing the resource histogram are:
a- Early start bar chart (after considering the procurement requirements which
ensure the materials and equipment are available)
b- Resource forecast per activity.
Consider the following example:
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
4
Resource Table
Resource Bar chart and Histogram
6. Resource Loading
The resource forecast is now compared with the resources available. The ideal
situation is achieved when the resource requirement equals the resources
available. Unfortunately, in project management this seldom happens, because it
is not always possible to adjust supply with demand, so some form of compromise
is essential.
A resource overload is when the resource forecast exceeds the available
resources, while a resource under-load is when resource forecast is lower than the
available resource.
A resource overload will lead to some activities being delayed which could delay
the completion of the project.
A resource under-load will under-utilize the company's resources which could
have a detrimental effect on the company's profitability.
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
5
Resource Loading (overloading and under-loading)
The overloads and under-loads can now be identified and addressed as follows:
a- Resource Smoothing: assign resources to critical activities first, then try
moving the other activities to ease any overload and under-utilization.
b- Time-Limited Resource Scheduling: the end date of the project is fixed,
so resources must be increased to address any overloads.
c- Resource-Limited Resource Scheduling: the maximum number of
resources is fixed, so the end date may need to be extended to address any
overload.
d- Increase Resources: to address an overload.
e- Reduce Resources: to address an under-load (under-utilized).
7. Resource Smoothing
Resource smoothing is the process of moving activities to improve the resource
loading profile.
The first step is to select the resource to be smoothed. To decide which resource
to smooth consider:
a- The resource that is most overloaded.
b- The resource that is most used on the project.
c- The least flexible resource - this could be the resource that comes from
overseas, is difficult to get hold of or is least available.
d- The most expensive resource to hire.
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
6
Example:
Resource Bar chart and Histogram
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
7
Smoothed Bar chart and Histogram

Contenu connexe

Tendances

Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation TafseerKishan Solankimbaccepmp
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineeringrathodjaydeep2
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Managementsrinivas2036
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & ScheduleVîñõđ Kůmåř
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)Nur Azwin
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
time cost trade off
 time cost trade off time cost trade off
time cost trade offbriankirui9
 
Role and Responsibilities of Project Manager
Role and Responsibilities of Project ManagerRole and Responsibilities of Project Manager
Role and Responsibilities of Project Managerkanti choudhary
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Schedulingakashpadole
 

Tendances (20)

Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
time cost trade off
 time cost trade off time cost trade off
time cost trade off
 
Role and Responsibilities of Project Manager
Role and Responsibilities of Project ManagerRole and Responsibilities of Project Manager
Role and Responsibilities of Project Manager
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
 

En vedette

Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsMaria Erland, PMP
 
Project Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisProject Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisBPUG Congress
 
How To Build A PMO
How To Build A PMOHow To Build A PMO
How To Build A PMOTURKI , PMP
 
Resource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tipsResource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tipsian jones
 
Resource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingResource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingMashilo Kabedi
 
PMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_ManagementPMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_ManagementBob Zoller
 
Planning, scheduling and resource allocation
Planning, scheduling and resource allocationPlanning, scheduling and resource allocation
Planning, scheduling and resource allocationJatin Mandhyan
 
Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Hussain Bandukwala
 
Strategy and Resource Allocation
Strategy and Resource Allocation Strategy and Resource Allocation
Strategy and Resource Allocation Riadh Mohammed Arif
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)Anand Subramaniam
 
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017Carol Smith
 

En vedette (13)

Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And Benefits
 
Resource management
Resource managementResource management
Resource management
 
PMO Frameworks
PMO FrameworksPMO Frameworks
PMO Frameworks
 
Project Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisProject Resource Management 3 Jon Lewis
Project Resource Management 3 Jon Lewis
 
How To Build A PMO
How To Build A PMOHow To Build A PMO
How To Build A PMO
 
Resource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tipsResource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tips
 
Resource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingResource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder Meeting
 
PMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_ManagementPMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_Management
 
Planning, scheduling and resource allocation
Planning, scheduling and resource allocationPlanning, scheduling and resource allocation
Planning, scheduling and resource allocation
 
Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)
 
Strategy and Resource Allocation
Strategy and Resource Allocation Strategy and Resource Allocation
Strategy and Resource Allocation
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
 

Similaire à Resource allocation and smoothing

Resource planning and resource allocation
Resource planning and resource allocationResource planning and resource allocation
Resource planning and resource allocationVenu Yemul
 
Resource Planning
Resource PlanningResource Planning
Resource PlanningWajahat Ali
 
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...HIMADRI BANERJI
 
SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)Peter Mello
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project ResourcesToyin Osunlaja
 
The Ultimate Guide To Project Resources Management
The Ultimate Guide To Project Resources ManagementThe Ultimate Guide To Project Resources Management
The Ultimate Guide To Project Resources ManagementOrangescrum
 
Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)danieljohn810
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 MBA 6951, Managing Complex Projects 1 Course Learning.docx MBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docxaryan532920
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6IOSRJMCE
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: BudgetMinhas Kamal
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
Resource Scheduling
Resource Scheduling  Resource Scheduling
Resource Scheduling Nicola2903
 
pinto_pm5_inppt_12.pptx
pinto_pm5_inppt_12.pptxpinto_pm5_inppt_12.pptx
pinto_pm5_inppt_12.pptxIftikhar1985
 

Similaire à Resource allocation and smoothing (20)

Resource planning and resource allocation
Resource planning and resource allocationResource planning and resource allocation
Resource planning and resource allocation
 
Resource Planning
Resource PlanningResource Planning
Resource Planning
 
Ch6 resources
Ch6 resourcesCh6 resources
Ch6 resources
 
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
 
SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project Resources
 
B012440511
B012440511B012440511
B012440511
 
The Ultimate Guide To Project Resources Management
The Ultimate Guide To Project Resources ManagementThe Ultimate Guide To Project Resources Management
The Ultimate Guide To Project Resources Management
 
Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
Resource allocation
Resource allocationResource allocation
Resource allocation
 
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 MBA 6951, Managing Complex Projects 1 Course Learning.docx MBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: Budget
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Resource Scheduling
Resource Scheduling  Resource Scheduling
Resource Scheduling
 
Managing Project Success
Managing Project SuccessManaging Project Success
Managing Project Success
 
pinto_pm5_inppt_12.pptx
pinto_pm5_inppt_12.pptxpinto_pm5_inppt_12.pptx
pinto_pm5_inppt_12.pptx
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
CE427-Chp6-Resource-Allocation-24Apr2019.pptx
CE427-Chp6-Resource-Allocation-24Apr2019.pptxCE427-Chp6-Resource-Allocation-24Apr2019.pptx
CE427-Chp6-Resource-Allocation-24Apr2019.pptx
 

Plus de Dr. Mahmoud Al-Naimi

أسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfأسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfDr. Mahmoud Al-Naimi
 
Certificate - Dr. Mahmoud AL-Naimi
Certificate  - Dr. Mahmoud AL-NaimiCertificate  - Dr. Mahmoud AL-Naimi
Certificate - Dr. Mahmoud AL-NaimiDr. Mahmoud Al-Naimi
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعDr. Mahmoud Al-Naimi
 
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةكيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةDr. Mahmoud Al-Naimi
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...Dr. Mahmoud Al-Naimi
 
أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)Dr. Mahmoud Al-Naimi
 
Product design and manufacture lecture 1
Product design and manufacture lecture  1Product design and manufacture lecture  1
Product design and manufacture lecture 1Dr. Mahmoud Al-Naimi
 
Easy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projectsEasy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projectsDr. Mahmoud Al-Naimi
 
Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Dr. Mahmoud Al-Naimi
 
Easy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationEasy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationDr. Mahmoud Al-Naimi
 
ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق Dr. Mahmoud Al-Naimi
 
Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Dr. Mahmoud Al-Naimi
 
Computer in Design and Manufacturing
Computer in Design and Manufacturing Computer in Design and Manufacturing
Computer in Design and Manufacturing Dr. Mahmoud Al-Naimi
 
إنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةإنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةDr. Mahmoud Al-Naimi
 

Plus de Dr. Mahmoud Al-Naimi (20)

أسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfأسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdf
 
Certificate - Dr. Mahmoud AL-Naimi
Certificate  - Dr. Mahmoud AL-NaimiCertificate  - Dr. Mahmoud AL-Naimi
Certificate - Dr. Mahmoud AL-Naimi
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريع
 
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةكيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...
 
أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)
 
(Aoa) and (aon) networks
(Aoa) and (aon) networks(Aoa) and (aon) networks
(Aoa) and (aon) networks
 
Applications dr. mahmoud al-naimi
Applications   dr. mahmoud al-naimiApplications   dr. mahmoud al-naimi
Applications dr. mahmoud al-naimi
 
Product design and manufacture lecture 1
Product design and manufacture lecture  1Product design and manufacture lecture  1
Product design and manufacture lecture 1
 
Easy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projectsEasy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projects
 
Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations
 
Easy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationEasy steps to network construction and critical path determination
Easy steps to network construction and critical path determination
 
ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق
 
Control charts for variables
Control charts for variables Control charts for variables
Control charts for variables
 
Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)
 
Evolution of mrp type systems
Evolution of mrp type systemsEvolution of mrp type systems
Evolution of mrp type systems
 
Computer in Design and Manufacturing
Computer in Design and Manufacturing Computer in Design and Manufacturing
Computer in Design and Manufacturing
 
إنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةإنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكية
 
Network construction
Network construction  Network construction
Network construction
 
Production planning hierarchy
Production planning hierarchyProduction planning hierarchy
Production planning hierarchy
 

Dernier

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 

Dernier (20)

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 

Resource allocation and smoothing

  • 1. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 0 Project Management Resource Allocation and Smoothing Dr. Mahmoud Abbas Mahmoud Assistant Professor 2017
  • 2. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 1 Resource Allocation and Smoothing 1. Resource Planning A resource may be defined as the machine or person who will perform the scope of work. Resource planning is forecasting the resources required to perform the scope of work within the time plan. The resource constraint should be considered after the network diagram, schedule bar chart and procurement schedule have been developed. But before the crash- flow statement. 2. Resource Estimating The resource estimates is linked directly to the scope of work and bill of materials (BOM). The scope of work may be expressed as so many tons of steel, or so many square meters of wall paint etc. From this description estimator can convert the scope of work into manhours per unit ‘X’. Consider the following, if the scope of work is to erect (assemble) 12 tons of steel and the estimator knows from past experience that the work can be done in 150 manhours per ton and the men work 10 hour shifts, then the equation is: ( 12 tons × 150 manhours per ton ) 10 hrs per day = 180 mandays Resource / Duration Trade-Off 3. Resource Forecasting Resource forecasting is to forecast the total resource requirement by discipline or interchangeable resource. An interchangeable resource is when you have a pool (group) of workers and any one of them could perform the work. This is done by compiling all the resource estimates and presenting them in a structured resource table.
  • 3. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 2 Resource Table Resource Forecast - Bar Chart Resource Forecast – Histogram Note: The bar chart shows the number of resources per activity per day, and the histogram shows the total recourse required per day. 4. Resource Availability In establishing the resource availability, the following points should be considered: a- Other resource commitments - if your company is involved in a number of projects which all draw from a common labor pool, the other projects' requirements must also be considered (also called multi-project resource scheduling). b- The anticipated sickness and absenteeism rate. For example: allow for a 25% absentee rate based on experience.
  • 4. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 3 Planning for a 25% Absenteeism Keeping the above points in mind, the resource availability table will be developed. Consider the following example: 5. Resource Histogram The resource histogram is a popular planning tool because it gives a good visual presentation which is easy to assimilate and understand. The prerequisites for drawing the resource histogram are: a- Early start bar chart (after considering the procurement requirements which ensure the materials and equipment are available) b- Resource forecast per activity. Consider the following example:
  • 5. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 4 Resource Table Resource Bar chart and Histogram 6. Resource Loading The resource forecast is now compared with the resources available. The ideal situation is achieved when the resource requirement equals the resources available. Unfortunately, in project management this seldom happens, because it is not always possible to adjust supply with demand, so some form of compromise is essential. A resource overload is when the resource forecast exceeds the available resources, while a resource under-load is when resource forecast is lower than the available resource. A resource overload will lead to some activities being delayed which could delay the completion of the project. A resource under-load will under-utilize the company's resources which could have a detrimental effect on the company's profitability.
  • 6. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 5 Resource Loading (overloading and under-loading) The overloads and under-loads can now be identified and addressed as follows: a- Resource Smoothing: assign resources to critical activities first, then try moving the other activities to ease any overload and under-utilization. b- Time-Limited Resource Scheduling: the end date of the project is fixed, so resources must be increased to address any overloads. c- Resource-Limited Resource Scheduling: the maximum number of resources is fixed, so the end date may need to be extended to address any overload. d- Increase Resources: to address an overload. e- Reduce Resources: to address an under-load (under-utilized). 7. Resource Smoothing Resource smoothing is the process of moving activities to improve the resource loading profile. The first step is to select the resource to be smoothed. To decide which resource to smooth consider: a- The resource that is most overloaded. b- The resource that is most used on the project. c- The least flexible resource - this could be the resource that comes from overseas, is difficult to get hold of or is least available. d- The most expensive resource to hire.
  • 7. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 6 Example: Resource Bar chart and Histogram
  • 8. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 7 Smoothed Bar chart and Histogram