SlideShare une entreprise Scribd logo
1  sur  8
Project Management Case Study
Boeing's Virtual Fence(Barriers)
Presenter
Mr.Nagarajan G
Chairperson
Dr LRS Mani
Professor-Project Management
Brief profile of case
• The Boeing’s Virtual Fence Project was initiated by the Department of
Homeland Security (DHS) to stem the continual flow of illegal border
crossing along the Mexican Border which had reached epidemic
proportions. The main driving force behind the construction of
project was the threat of illegal aliens, terrorists, and drug smugglers,
which had sparked national security concerns. The Department of
Homeland Security had been charged with the sole responsibility of
monitoring illegal crossings in the wake of the September 11 attacks.
Giving the size and complexity of the project, Boeing was contracted
to successfully complete the project at an initial estimate of $1.1
billion which was later revised to $8.0 billion. However, a
congressional watchdog group argued that the project cost estimate
could rise as much as $30.0 billion.
Problem Statement
The Virtual Fence project lacked a comprehensive and a robust
integration management systems that ensured that all the 100
subcontractors that had been contracted by Boeing, the main
contractor on the project, would work in a unified and team-oriented
fashion to complete the multi-billion security project ahead of both
schedule and cost.
The original cause of the problem could be credited to the DHS
formulating the entire project as a turnkey where all the work and
oversight will be conducted by the contractor Boeing. There was a clear
conflict of interest at the initiation of the project.
Scope Management
• Project scope management is a process that helps in determining and
documenting the list of all the project goals, tasks, deliverables,
deadlines, and budgets as a part of the planning process. In project
management, it is common for a big project to have modifications
along the way.
• With the scope in the project management defined right in the
beginning, it becomes much easier for project teams to manage and
make the required changes.
A well-defined project scope management helps avoid common issues like:
• Constantly changing requirements
• Turning the project direction when you are already mid-way
• Realizing that the final outcome isn’t what was expected
• Going over the discussed budget
• Falling behind the project deadlines
• The scope is defined by understanding the project requirements and the
client’s expectations. The scope statement usually contains,
• project objectives
• project deliverables
• exclusions
• project constraints and
• project assumptions.
SCOPE MANAGEMENT-5.1
BOEING’S VIRTUAL FENCE
SWOT Analysis:
Strengths: Not afraid to scrap projects that cost too much, Boeing is very
determined, very influential and credible.
Weaknesses: Terrible project management skills, constant ballooning costs,
terrible timeline, Boeing had never attempted anything like this before.
Opportunity: Chance to create an amazing technology, attempting
something Boeing has never done before could really put them ahead of
competition.
Threats: Ballooning costs could get the project shut-down, unexpected 7
year delay, 2,000 mile border could be too much work for something never
attempted by this company before.
Questions: 1) What problems do you see emerging from a project such as
SBInet where the government allows the contractor to determine scope,
manage all contractor relations, and decide how to share project status
information with oversight bodies?
• Oversight, particularly early in the project’s development, is critical.
• It is during the early phases of the project that most technical decisions are made, that
overall project scope is frozen, and that project capabilities and standards for
evaluation are determined.
• Thus, when the government gave this power to the contractor without sufficient
checks and balances, they opened the way for overruns, poor technical quality, and
loss of accountability.
• In retrospect, it is actually surprising that the project was cancelled as early as it was.
Under similar circumstances, federally funded projects have been much bigger black
holes for budget and schedule overruns.
2) Consider the following two arguments: “The failure of SBInet was due to
poor scope management,” versus “SBInet failed because of poor oversight
and project controls.” Take one side or the other in this argument, and justify
your response. A case can be made for either position in this example.
The project was poorly scoped, mainly due to an inadequate understanding of
the technical requirements for developing and maintaining a virtual fence
across a long border.
Even the pilot project on the 28-miletest section of the border was not
technically sound and demonstrated a number of flaws within the system.
On the other hand, there was a continued lack of oversight of the project
through much of the early qualification phases, when Boeing was scrutinizing
suppliers, trying to determine the project’s scope, and creating a management
structure that seemed designed to promote overruns and poor quality.

Contenu connexe

Tendances

Chapter 1 An Overview Of Project Management
Chapter 1  An Overview Of Project ManagementChapter 1  An Overview Of Project Management
Chapter 1 An Overview Of Project Management
Mahesh Bendigeri
 
8.project management chapter 8
8.project management chapter 88.project management chapter 8
8.project management chapter 8
Warui Maina
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
haroldtaylor1113
 
Proposal writing resource the logframe approach
Proposal writing  resource   the logframe approachProposal writing  resource   the logframe approach
Proposal writing resource the logframe approach
tccafrica
 
Chapter 1 Introduction to Project Management.ppt
Chapter 1 Introduction to Project Management.pptChapter 1 Introduction to Project Management.ppt
Chapter 1 Introduction to Project Management.ppt
AhmadTawfigAlRadaide
 

Tendances (20)

Project charter
Project charterProject charter
Project charter
 
Chapter 1 An Overview Of Project Management
Chapter 1  An Overview Of Project ManagementChapter 1  An Overview Of Project Management
Chapter 1 An Overview Of Project Management
 
8.project management chapter 8
8.project management chapter 88.project management chapter 8
8.project management chapter 8
 
Is project failure
Is project failureIs project failure
Is project failure
 
Sustainability in Project Management
Sustainability in Project ManagementSustainability in Project Management
Sustainability in Project Management
 
Final Project Closing
Final Project ClosingFinal Project Closing
Final Project Closing
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
project goals and objectives
 project goals and objectives project goals and objectives
project goals and objectives
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
 
Project management chapter 2
Project management chapter 2Project management chapter 2
Project management chapter 2
 
Practical Guide to Programme/Project Cycle Management
Practical Guide to Programme/Project Cycle ManagementPractical Guide to Programme/Project Cycle Management
Practical Guide to Programme/Project Cycle Management
 
Proposal writing resource the logframe approach
Proposal writing  resource   the logframe approachProposal writing  resource   the logframe approach
Proposal writing resource the logframe approach
 
Project Management PowerPoint Presentation Slides
Project Management PowerPoint Presentation SlidesProject Management PowerPoint Presentation Slides
Project Management PowerPoint Presentation Slides
 
Chapter 1 Introduction to Project Management.ppt
Chapter 1 Introduction to Project Management.pptChapter 1 Introduction to Project Management.ppt
Chapter 1 Introduction to Project Management.ppt
 
Lecture 1. general introduction to project management
Lecture 1. general introduction to project management Lecture 1. general introduction to project management
Lecture 1. general introduction to project management
 
Smart Goal Setting and Project Planning
Smart Goal Setting and Project PlanningSmart Goal Setting and Project Planning
Smart Goal Setting and Project Planning
 
Pm study project risk management test
Pm study project  risk management testPm study project  risk management test
Pm study project risk management test
 
Ch 2-The Role of the Project Manager-1.pptx
Ch 2-The Role of the Project Manager-1.pptxCh 2-The Role of the Project Manager-1.pptx
Ch 2-The Role of the Project Manager-1.pptx
 
Chunnel Project_Development Phase
Chunnel Project_Development PhaseChunnel Project_Development Phase
Chunnel Project_Development Phase
 
HM 418 2e hcpm05 (1)
HM 418 2e hcpm05 (1)HM 418 2e hcpm05 (1)
HM 418 2e hcpm05 (1)
 

Similaire à Project management case study.pptx

Project failure reason 1
Project failure reason 1Project failure reason 1
Project failure reason 1
Arash Moto
 
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
Project XYC  Project PlanEric Malone, Jennifer Napier, .docxProject XYC  Project PlanEric Malone, Jennifer Napier, .docx
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
wkyra78
 

Similaire à Project management case study.pptx (20)

Boeing's Virtual Fence(Barriers) Nagarajan.pptx
Boeing's Virtual Fence(Barriers)  Nagarajan.pptxBoeing's Virtual Fence(Barriers)  Nagarajan.pptx
Boeing's Virtual Fence(Barriers) Nagarajan.pptx
 
Chunnel Project
Chunnel ProjectChunnel Project
Chunnel Project
 
Chunnel ppt
Chunnel pptChunnel ppt
Chunnel ppt
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
Cost and time overruns in indian construction industry
Cost and time overruns in indian construction industryCost and time overruns in indian construction industry
Cost and time overruns in indian construction industry
 
Project failure reason 1
Project failure reason 1Project failure reason 1
Project failure reason 1
 
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
Project XYC  Project PlanEric Malone, Jennifer Napier, .docxProject XYC  Project PlanEric Malone, Jennifer Napier, .docx
Project XYC Project PlanEric Malone, Jennifer Napier, .docx
 
Major Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperMajor Projects - Faster Better Cheaper
Major Projects - Faster Better Cheaper
 
megaprojects, SPUR 2022.pdf
megaprojects, SPUR 2022.pdfmegaprojects, SPUR 2022.pdf
megaprojects, SPUR 2022.pdf
 
The Channel Tunnel
The Channel TunnelThe Channel Tunnel
The Channel Tunnel
 
Chapter 1
Chapter 1Chapter 1
Chapter 1
 
CHAPTER 1 - Project Management.pdf
CHAPTER 1 - Project Management.pdfCHAPTER 1 - Project Management.pdf
CHAPTER 1 - Project Management.pdf
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
Warrington Western Link, Robert Holloway
Warrington Western Link, Robert HollowayWarrington Western Link, Robert Holloway
Warrington Western Link, Robert Holloway
 
Another Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham ZeinounAnother Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham Zeinoun
 
Chap 5.pdf
Chap 5.pdfChap 5.pdf
Chap 5.pdf
 
Chap 5.pdf
Chap 5.pdfChap 5.pdf
Chap 5.pdf
 
Chap 5.pdf
Chap 5.pdfChap 5.pdf
Chap 5.pdf
 
Project Financing in Public Projects
Project Financing in Public ProjectsProject Financing in Public Projects
Project Financing in Public Projects
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 

Dernier

Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
AnaAcapella
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
QucHHunhnh
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 

Dernier (20)

Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptx
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 

Project management case study.pptx

  • 1. Project Management Case Study Boeing's Virtual Fence(Barriers) Presenter Mr.Nagarajan G Chairperson Dr LRS Mani Professor-Project Management
  • 2. Brief profile of case • The Boeing’s Virtual Fence Project was initiated by the Department of Homeland Security (DHS) to stem the continual flow of illegal border crossing along the Mexican Border which had reached epidemic proportions. The main driving force behind the construction of project was the threat of illegal aliens, terrorists, and drug smugglers, which had sparked national security concerns. The Department of Homeland Security had been charged with the sole responsibility of monitoring illegal crossings in the wake of the September 11 attacks. Giving the size and complexity of the project, Boeing was contracted to successfully complete the project at an initial estimate of $1.1 billion which was later revised to $8.0 billion. However, a congressional watchdog group argued that the project cost estimate could rise as much as $30.0 billion.
  • 3. Problem Statement The Virtual Fence project lacked a comprehensive and a robust integration management systems that ensured that all the 100 subcontractors that had been contracted by Boeing, the main contractor on the project, would work in a unified and team-oriented fashion to complete the multi-billion security project ahead of both schedule and cost. The original cause of the problem could be credited to the DHS formulating the entire project as a turnkey where all the work and oversight will be conducted by the contractor Boeing. There was a clear conflict of interest at the initiation of the project.
  • 4. Scope Management • Project scope management is a process that helps in determining and documenting the list of all the project goals, tasks, deliverables, deadlines, and budgets as a part of the planning process. In project management, it is common for a big project to have modifications along the way. • With the scope in the project management defined right in the beginning, it becomes much easier for project teams to manage and make the required changes.
  • 5. A well-defined project scope management helps avoid common issues like: • Constantly changing requirements • Turning the project direction when you are already mid-way • Realizing that the final outcome isn’t what was expected • Going over the discussed budget • Falling behind the project deadlines • The scope is defined by understanding the project requirements and the client’s expectations. The scope statement usually contains, • project objectives • project deliverables • exclusions • project constraints and • project assumptions.
  • 6. SCOPE MANAGEMENT-5.1 BOEING’S VIRTUAL FENCE SWOT Analysis: Strengths: Not afraid to scrap projects that cost too much, Boeing is very determined, very influential and credible. Weaknesses: Terrible project management skills, constant ballooning costs, terrible timeline, Boeing had never attempted anything like this before. Opportunity: Chance to create an amazing technology, attempting something Boeing has never done before could really put them ahead of competition. Threats: Ballooning costs could get the project shut-down, unexpected 7 year delay, 2,000 mile border could be too much work for something never attempted by this company before.
  • 7. Questions: 1) What problems do you see emerging from a project such as SBInet where the government allows the contractor to determine scope, manage all contractor relations, and decide how to share project status information with oversight bodies? • Oversight, particularly early in the project’s development, is critical. • It is during the early phases of the project that most technical decisions are made, that overall project scope is frozen, and that project capabilities and standards for evaluation are determined. • Thus, when the government gave this power to the contractor without sufficient checks and balances, they opened the way for overruns, poor technical quality, and loss of accountability. • In retrospect, it is actually surprising that the project was cancelled as early as it was. Under similar circumstances, federally funded projects have been much bigger black holes for budget and schedule overruns.
  • 8. 2) Consider the following two arguments: “The failure of SBInet was due to poor scope management,” versus “SBInet failed because of poor oversight and project controls.” Take one side or the other in this argument, and justify your response. A case can be made for either position in this example. The project was poorly scoped, mainly due to an inadequate understanding of the technical requirements for developing and maintaining a virtual fence across a long border. Even the pilot project on the 28-miletest section of the border was not technically sound and demonstrated a number of flaws within the system. On the other hand, there was a continued lack of oversight of the project through much of the early qualification phases, when Boeing was scrutinizing suppliers, trying to determine the project’s scope, and creating a management structure that seemed designed to promote overruns and poor quality.