SlideShare une entreprise Scribd logo
1  sur  2
HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 Lifting Operations with mobile crane
Issued: Rev. Date:
Revision: 0
Page 1 of 2 HSEQ -Rev-01(Aug-2018)
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
P S RR
1
Crane checks on
arrival to site
PRIOR TO USE
 Use of mobile crane
 Unauthorized operation ofthe mobile
crane resulting in incident;
 Failure due to use of un-certificated
crane;
3 4
12
HIGH
i. All cranes to be Third Party Certificated by a DM approved inspector,
documentation available on arrival to site;
ii. Operators to have in-date Third Party certificate by approved body,
available for review on arrival to site;
iii. Crane load indicator to be installed and functioning correctly;
iv. Visual inspection ofcrane undertaken by competentperson;
Documentation
unavailable for
review
Crane quarantined until
evidence provided
Low
2
Access of crane to
work areas
 Plant and workers in
same working area;
 Collision with plantor vehicles and
live traffic;
 Workers struck by plant, very high
risk of fatality;
 Uncontrolled crane reversing;
i. Worker pedestrian routes to be designed and implemented with clear
signage to provide segregation;
ii. Instruction to workers at induction on use of access routes around the
project;
iii. Flagmen to be used to control crane movements;
iv. The Logistics plan shall clearlyillustrate crane access and egress points;
Workers not
complying with
flagmen
Regular topic in TBT’s Low
3 Siting and setting up of
crane
 Working in proximity
to existing structures
and services;
 Overturning due to incorrectsiting or
incorrectoutrigger extension;
 Collision with overhead services;
 Blocking access routes;
 Load striking moving and/or
stationarystructures;
3 4
12
High
i. Ensure crane is setup/rigged out correctly, is on firm level ground as per
crane plan with outriggers fullyextended;
ii. Solid barriers should be situated,where practicable,to protect crane from
traffic routes around working radius ofcab;
iii. Consideration given to overhead services and existing structures when
siting crane;
Unable to fully
extend outriggers
due to restrictions
in area
Lift revised, crane moved to
new area;
Crane never used withoutfull
outrigger extension
Low
4
Lifting of equipment
and material
(Mobile crane
Operator)
 Operator competency;
 Lift planning;
 Incidentdue to use of defective
lifting gear / equipment;
 Crane collapse due to lifting loads
beyond SWL;
 No crane documentation in place;
4 5
20
HIGH
i. ATC Minimum Acceptable Standard ATC/OHS/MAS/00941 to be adhered
to at all times;
ii. Lift Plan to be completed prior to any lift taking place by crane supervisor
and engineer;
iii. Ensure all lifting tackle and equipmenthave valid test certificate before
use (6 monthly3rd
party inspections);
iv. Method statements and risk assessments to be submitted and adhered to
for technical and/or non-routine lifts;
v. Crane load indicator to be functioning correctly, and not to be overridden
under any circumstances;
Machine
breakdown
Hydraulic fluid spill
Machine isolated and
quarantined until repaired.
Spoil removed and treated as
hazardous waste
Low
Project Name: xxx
RA Ref No.: xxx
RA compilation
Date:
Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Lifting operations using mobile crane within site boundary
Relevant Applicable MAS:
 01412 – Lifting Operations;
 00941 – Lifting equipment
Additional Training required:
Riggers /Slingers
NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be?
What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen
frequently
Often (4)
6 to 12 times a year
Likely (3)
1 to 5 times a year
Possible (2)
Once every 5 years
Rarely (1)
Less than once every 5
years
Can the hazard be Eliminated or removed
from the w ork place?
Catastrophic (5)
Multiple Fatalities
High 25 High 20 High 15 Medium 10 Medium 5
Can the product or process be substitutedfor
a less hazardous alternative?
Serious (4)
Class 1 single fatality
High 20 High 16 High 12 Medium 8 Low 4
Can the hazard be engineered aw ay w ith
guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1
Permanently disabling effects
High 15 High 12 Medium 9 Medium 6 Low 3
Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work
restrictions. MTI
Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment &
Clothing be w orn to safe guard against
hazards?Insignificant (1)
FAI
Medium10 Medium 4 Low 3 Low 2 Low 1
HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 Lifting Operations with mobile crane
Issued: Rev. Date:
Revision: 0
Page 2 of 2 HSEQ -Rev-01(Aug-2018)
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
P S RR
vi. Operator to adhere to crane safe working load limits,weightofload and
COG established before lifting;
5 Crane supervision
 Lifting operations
around workers;
 Workers in crane
operating radius;
 Persons underneath load struck by
materials;
 Load swinging /spinning
uncontrolled;
 Falling materials;
 Damage to lifting slings from sharp
edges;
 Over-sailing of material over live
traffic routes;
 High winds – adverse weather;
4 5
20
High
i. Lift controlled by designated trained rigger/banks man using approved
hand signals only;
ii. No personnel situated or walking under elevated loads,avoid over-
sailing ofpersonnel ifpracticable;
iii. No over-sailing ofloads over live traffic routes withoutroad closure;
iv. No lifts undertaken when wind speed exceeds 40kph;
v. No blind lifts withoutvisual and communication aids,radios etc.;
vi. Tag lines shall be used to guide materials while lifting,2 lines minimum
10m in length;
vii. Slings protected from sharp edges with rubber etc.;
viii. Riggers to undertake visual inspection ofall lifting equipmentdaily;
Incident– falling
materials
Work stopped,area cleared
and full investigation
undertaken
Low
6
Crane Maintenance
(revised 06-06-2018)  Injury to operatives;
 Untrained staffattempting repairs;
 Inadequate and unsafe repairs,
resulting in failure of equipment;
 Injury to mechanics undertaking
repairs;
3 4 12
i. Only trained and competentmechanics to attemptany repairs on mobile
cranes,including engine,hydraulics,lifting mechanism,rams etc.;
ii. If any breakdowns occur,regardless ofmanagementpressure,the crane
shall be isolated,locked and plantdepartmentinformed ofthe breakdown;
iii.Machine barriered off if in risk areas such as access routes,traffic routes
etc. If on live traffic routes advanced warning vehicle to be mobilized;
iv. Mechanics shall be advised of time,activity and nature of breakdown;
v. Under no circumstances shall temporaryrepairs be undertaken on any
mobile crane;
vi. During repairs under no circumstances shall workers be placed atrisk by
pinch points,crush area,high pressure release or moving parts;
Low

Contenu connexe

Tendances

FORKLIFT SAFETY
FORKLIFT SAFETYFORKLIFT SAFETY
FORKLIFT SAFETY
Dwarika Bhushan Sharma
 
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 

Tendances (20)

Lifting plan template
Lifting plan templateLifting plan template
Lifting plan template
 
22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessment
 
32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templates32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templates
 
6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates
 
Crane Operation - Lifting
Crane Operation -  LiftingCrane Operation -  Lifting
Crane Operation - Lifting
 
Lifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptxLifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptx
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates
 
Work at height safety
Work at height safetyWork at height safety
Work at height safety
 
FORKLIFT SAFETY
FORKLIFT SAFETYFORKLIFT SAFETY
FORKLIFT SAFETY
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
 
23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates
 
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx
 
Fire Risk Assessment.pdf
Fire Risk Assessment.pdfFire Risk Assessment.pdf
Fire Risk Assessment.pdf
 
3 emergency management risk assessment templates
3 emergency management risk assessment templates3 emergency management risk assessment templates
3 emergency management risk assessment templates
 
Work at Height | Safety during work at hight
Work at Height | Safety during work at hightWork at Height | Safety during work at hight
Work at Height | Safety during work at hight
 
19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templates19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templates
 
TOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsTOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operations
 

Similaire à 8 lifting operations with mobile crane risk assessment templates

8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
24 Casting of Bridge Decks Risk Assessment Templates.docx
24 Casting of Bridge Decks Risk Assessment Templates.docx24 Casting of Bridge Decks Risk Assessment Templates.docx
24 Casting of Bridge Decks Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
Dwarika Bhushan Sharma
 
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 

Similaire à 8 lifting operations with mobile crane risk assessment templates (20)

8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
 
15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx
 
22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx
 
7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx
 
24 Casting of Bridge Decks Risk Assessment Templates.docx
24 Casting of Bridge Decks Risk Assessment Templates.docx24 Casting of Bridge Decks Risk Assessment Templates.docx
24 Casting of Bridge Decks Risk Assessment Templates.docx
 
23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx
 
14 use of plant graders and road rollers risk assessment templates
14 use of plant  graders and road rollers risk assessment templates14 use of plant  graders and road rollers risk assessment templates
14 use of plant graders and road rollers risk assessment templates
 
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
 
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
 
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
 
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
 
24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templates24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templates
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates
 

Plus de Dwarika Bhushan Sharma

PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
Dwarika Bhushan Sharma
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
Dwarika Bhushan Sharma
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
Dwarika Bhushan Sharma
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
Dwarika Bhushan Sharma
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
Dwarika Bhushan Sharma
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
Dwarika Bhushan Sharma
 

Plus de Dwarika Bhushan Sharma (20)

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
 
1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
 
WITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docxWITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docx
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
 

Dernier

Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
KarakKing
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 

Dernier (20)

Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Wellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxWellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptx
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 

8 lifting operations with mobile crane risk assessment templates

  • 1. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 Lifting Operations with mobile crane Issued: Rev. Date: Revision: 0 Page 1 of 2 HSEQ -Rev-01(Aug-2018) No Specific Task Step (In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR P S RR 1 Crane checks on arrival to site PRIOR TO USE  Use of mobile crane  Unauthorized operation ofthe mobile crane resulting in incident;  Failure due to use of un-certificated crane; 3 4 12 HIGH i. All cranes to be Third Party Certificated by a DM approved inspector, documentation available on arrival to site; ii. Operators to have in-date Third Party certificate by approved body, available for review on arrival to site; iii. Crane load indicator to be installed and functioning correctly; iv. Visual inspection ofcrane undertaken by competentperson; Documentation unavailable for review Crane quarantined until evidence provided Low 2 Access of crane to work areas  Plant and workers in same working area;  Collision with plantor vehicles and live traffic;  Workers struck by plant, very high risk of fatality;  Uncontrolled crane reversing; i. Worker pedestrian routes to be designed and implemented with clear signage to provide segregation; ii. Instruction to workers at induction on use of access routes around the project; iii. Flagmen to be used to control crane movements; iv. The Logistics plan shall clearlyillustrate crane access and egress points; Workers not complying with flagmen Regular topic in TBT’s Low 3 Siting and setting up of crane  Working in proximity to existing structures and services;  Overturning due to incorrectsiting or incorrectoutrigger extension;  Collision with overhead services;  Blocking access routes;  Load striking moving and/or stationarystructures; 3 4 12 High i. Ensure crane is setup/rigged out correctly, is on firm level ground as per crane plan with outriggers fullyextended; ii. Solid barriers should be situated,where practicable,to protect crane from traffic routes around working radius ofcab; iii. Consideration given to overhead services and existing structures when siting crane; Unable to fully extend outriggers due to restrictions in area Lift revised, crane moved to new area; Crane never used withoutfull outrigger extension Low 4 Lifting of equipment and material (Mobile crane Operator)  Operator competency;  Lift planning;  Incidentdue to use of defective lifting gear / equipment;  Crane collapse due to lifting loads beyond SWL;  No crane documentation in place; 4 5 20 HIGH i. ATC Minimum Acceptable Standard ATC/OHS/MAS/00941 to be adhered to at all times; ii. Lift Plan to be completed prior to any lift taking place by crane supervisor and engineer; iii. Ensure all lifting tackle and equipmenthave valid test certificate before use (6 monthly3rd party inspections); iv. Method statements and risk assessments to be submitted and adhered to for technical and/or non-routine lifts; v. Crane load indicator to be functioning correctly, and not to be overridden under any circumstances; Machine breakdown Hydraulic fluid spill Machine isolated and quarantined until repaired. Spoil removed and treated as hazardous waste Low Project Name: xxx RA Ref No.: xxx RA compilation Date: Review date: Date: Compiled by: Reviewed by: Approved by: Overall Task Details Lifting operations using mobile crane within site boundary Relevant Applicable MAS:  01412 – Lifting Operations;  00941 – Lifting equipment Additional Training required: Riggers /Slingers NOC’s Required for task: RISK SCORE CALCULATOR Use the Risk Score Calculator to Determine the Level of Risk of each Hazard What would be the CONSEQUENCE of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls Frequent/Almost certain (5) Continuous or will happen frequently Often (4) 6 to 12 times a year Likely (3) 1 to 5 times a year Possible (2) Once every 5 years Rarely (1) Less than once every 5 years Can the hazard be Eliminated or removed from the w ork place? Catastrophic (5) Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substitutedfor a less hazardous alternative? Serious (4) Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered aw ay w ith guards or barriers? Moderate (3) Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted I.e. procedures, job rotation etc. Minor (2) Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be w orn to safe guard against hazards?Insignificant (1) FAI Medium10 Medium 4 Low 3 Low 2 Low 1
  • 2. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 Lifting Operations with mobile crane Issued: Rev. Date: Revision: 0 Page 2 of 2 HSEQ -Rev-01(Aug-2018) No Specific Task Step (In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR P S RR vi. Operator to adhere to crane safe working load limits,weightofload and COG established before lifting; 5 Crane supervision  Lifting operations around workers;  Workers in crane operating radius;  Persons underneath load struck by materials;  Load swinging /spinning uncontrolled;  Falling materials;  Damage to lifting slings from sharp edges;  Over-sailing of material over live traffic routes;  High winds – adverse weather; 4 5 20 High i. Lift controlled by designated trained rigger/banks man using approved hand signals only; ii. No personnel situated or walking under elevated loads,avoid over- sailing ofpersonnel ifpracticable; iii. No over-sailing ofloads over live traffic routes withoutroad closure; iv. No lifts undertaken when wind speed exceeds 40kph; v. No blind lifts withoutvisual and communication aids,radios etc.; vi. Tag lines shall be used to guide materials while lifting,2 lines minimum 10m in length; vii. Slings protected from sharp edges with rubber etc.; viii. Riggers to undertake visual inspection ofall lifting equipmentdaily; Incident– falling materials Work stopped,area cleared and full investigation undertaken Low 6 Crane Maintenance (revised 06-06-2018)  Injury to operatives;  Untrained staffattempting repairs;  Inadequate and unsafe repairs, resulting in failure of equipment;  Injury to mechanics undertaking repairs; 3 4 12 i. Only trained and competentmechanics to attemptany repairs on mobile cranes,including engine,hydraulics,lifting mechanism,rams etc.; ii. If any breakdowns occur,regardless ofmanagementpressure,the crane shall be isolated,locked and plantdepartmentinformed ofthe breakdown; iii.Machine barriered off if in risk areas such as access routes,traffic routes etc. If on live traffic routes advanced warning vehicle to be mobilized; iv. Mechanics shall be advised of time,activity and nature of breakdown; v. Under no circumstances shall temporaryrepairs be undertaken on any mobile crane; vi. During repairs under no circumstances shall workers be placed atrisk by pinch points,crush area,high pressure release or moving parts; Low