SlideShare une entreprise Scribd logo
1  sur  18
Télécharger pour lire hors ligne
UP
UP
DN
DN UP
DN
D
C
B
A
5 6 7 8 9 10 11 12 13 14 18
49 m²
531.3 SF
Classroom One
1
39 m²
414.8 SF
Classroom Two
2
39 m²
414.8 SF
Classroom Three
3
66 m²
713.5 SF
Classroom Four
4
42 m²
455.0 SF
Corridor
5
20 m²
216.7 SF
Stairs
6
1842 3350 3350 3350 3350 3350 3350 3350 3350 1842
312520756215
5
SSP1A103
6
SSP1A103
Existing terrazzo
finish to staircase
and corridor
Existing
external steel
fire escape
staircase
Existing external
steel fire escape
staircase
Existing Terrazzo
finish to corridor
Existing Terrazzo
finish to corridor
Existing Parquet flooring
to classroom
Existing Parquet
flooring to classroom
Existing Parquet flooring
to classroom
Existing Parquet
flooring to classroom
D
C
B
A
5 6 7 8 9 10 11 12 13 14 18
207 m²
2228.1 SF
Classroom Five
7
30 m²
323.3 SF
Corridor
8
20 m²
213.2 SF
Stairs
9
1842 3350 3350 3350 3350 3350 3350 3350 3350 1842
312520756215
5
SSP1A103
6
SSP1A103
Existing
external steel
fire escape
staircase
Existing external
steel fire escape
staircase
Existing terrazzo
finish to staircase
and corridor
Existing Parquet
flooring to corridor
Existing Parquet flooring to classroom
Existing Parquet flooring to classroom
D
C
B
A
5 6 7 8 9 10 11 12 13 14 18
8 m²
87.7 SF
Corridor
10
20 m²
213.2 SF
Stairs
11
120 m²
1296.2 SF
Music oom
12
111 m²
1194.7 SF
Games Room
13
1842 3350 3350 3350 3350 3350 3350 3350 3350 1842
312520756215
5
SSP1A103
6
SSP1A103
Existing terrazzo
finish to staircase
and corridor
Existing floor finish to date is
paint applied directly to the
existing concrete screed
No floor finish existing within
the corridor, currently the
existing concrete screed has
been left exposed
No floor finish existing
within the gamers room,
currently the existing
concrete screed has
been left exposed
Existing external
steel fire escape
staircase Existing external
steel fire escape
staircase
15
100300
400
300
270
18 102 50 102
70
1010
30150
30150
260
102 50 102 18
Scale
LECTURER
Drawn by
Date
Project number
Institute of Technology Carlow
BSc. (Hons) in Architectural Technology
Year 4 2013-2014
As indicated
Block L Survey Sheet
1
Restoration, extension and
upgradation to protected structures
13-January-2014
Edel Fox
Noel Dunne, Sujana Sudhir,
& Dan O' Sullivan
SSP1A102
1 : 100
GFL Existing
1
1 : 100
FFL Existing
2
1 : 100
SFL Existing
3
Room Schedule Existing
Number Name Level Area Count
7 Classroom
Five
FFL 207 m² 1
8 Corridor FFL 30 m² 1
10 Corridor SFL 8 m² 1
11 Stairs SFL 20 m² 1
12 Music oom SFL 120 m² 1
13 Games
Room
SFL 111 m² 1
9 Stairs FFL 20 m² 1
Room Schedule Existing
Number Name Level Area Count
1 Classroom
One
GFL 49 m² 1
2 Classroom
Two
GFL 39 m² 1
3 Classroom
Three
GFL 39 m² 1
4 Classroom
Four
GFL 66 m² 1
5 Corridor GFL 42 m² 1
6 Stairs GFL 20 m² 1
General Specification
1 : 10
Existing Column
4
1 : 10
Existing Wall
5
1 : 10
Existing Roof
6
1 : 10
Existing Floor
7
1 : 10
Existing Iternal Wall
8
1 : 10
Existing Window
9
Current Condition Proposed Alterations
Assumed existing
external leaf 102mm
concrete bricks, then a
50mm cavity, then an
internal leaf of 102mm
concrete blocks,
finished with a layer of
18mm plaster.
Existing external
brickwork is stained
from water damage due
to poor drainage on the
east face, but other than
this the walls are in
relatively good
condition.
Proposed - additional dry-lining
board to the internal face of the
existing wall, consisting of 85mm
kingspan kooltherm K17
insulated dry-linig board in
between steel U channels, with
12.5mm plasterboard, finished
with a layer of 2.5mm skim.
Assumed existing
solid 260mm
blockwork internal
partition wall. These
walls have not been
finished with a layer of
plaster they blockwork
has just been painted.
Existing solid
blockwork internal walls
are unfinished ie. the
blockwork has just
been painted. They are
in relatively good
condition as they have
not been exposed to
the elements.
Proposed - additional dry-
linig board to both faces of
the partition wall, consisting
of 50mm kingspan kolltherm
K17 insulated dry-lining
board in between steel U
channels, with 12.5mm
plasterboard, finished with a
layer of 2.5mm skim. This
to be done to both sides of
the wall.
Assumed existing
150mm concrete slab
with 30mm concrete
screed, with 10mm
torch on felt, then a
rubber membrane,
finished with a layer of
150mm pebbles.
Existing roof is in
relatively bad condition
as can be seen from the
underside of the roof
there is alot of water
damage and the roof is
not insulated so there is
major condensation
issues that need to be
addressed.
Proposed - additional dry-
lining board at internal ceiling
level consisting of 85mm
kingspan kooltherm K17
insulated dry-lining board in
between timber battens,
12.5mm plasterboard
finished with a 2.5mm skim.
The existing rubber
membrane needs to be
stripped and the torch on felt
repaired and the pebbles
replaces, and the drainage
issues addressed.
Assumed existing
150mm concrete
floor slab, with 30mm
concrete screed,
topped with either
22mm Parquet
flooring or terazzo
flooring.
Existing floor in relatively
good condition
structurally but in terms
of thermal performance
there is room for
sufficient improvement.
The parquet and
terrazzo flooring is quiet
sufficiently dammaged
and will need to be
repaired where possible
and if not replaced.
Proposed - remove existing
harwood flooring to be repaired
where possible and if not
replaced, additional 80mm
kingspan Therma TF70 in
between timber battens to be
added on top of existing
screed. Repaired hardwood
flooring to be put back down
on top of the new insulation.
Assumed existing
timber framed,
single glazed pivot
windows currently
achieveing a u-
value of 4.8w/m²k
Existing windows are
old, in relatively bad
condition and rotting in
places. Window cills are
recessed allowing water
to sit and not drain
correctly. This poor
water drainage is
causing water damage
and the timber frames to
rot. Glass in some of the
windows is cracked or
damaged.
Proposed - Upgrading to
double glazed argon filled
timber framed windows which
will achieve a u-value of
1.8w/m²k. Install draught
proofing strips around all
windows to lower heat loss
even more. Address detailing
at cill to fix the water drainage
problem from occuring.
Conservation Principles to be followed:
Keeping a building in use – Is generally seen as the best
way to keep the building up to a good standard. If a
change of use must occur, minimum damage must be
made to the original character of the building.
Researching and analysing – Much research must be
done on the history, the fabric and the current condition of
the building before any proposals for works can be made.
Using expert conservation advice – expert advice should
be sought throughout the planning process and the
construction process to ensure that the works are
completed correctly.
Protecting the special interest – Inappropriate works
can damage the character and special interest of a
building, so special care must be taken to ensure this
does not happen.
Promoting minimum intervention – “do as much as
necessary and as little as possible”.
Respecting earlier alterations of interest – Earlier
alterations can be an insight into past construction
techniques and must be respected. They are
irreplaceable.
Repairing rather than replacing – the main aim should
be to repair rather than replace because to get the same
quality of materials now is next to impossible and most of
the materials were made by hand.
Promoting honesty of repairs and alterations –
materials used in replacement should not be artificially
aged; this will add confusion in the future as to when the
alterations were made.
Using appropriate materials and methods – appropriate
materials must be used during restoration as in past
examples certain materials accelerated the decay.
Ensuring reversibility of alterations – by ensuring
reversibility of alterations in the future this can allow a
quick fix to unforeseen problems caused by earlier
restorations.
Avoid incremental damage – major thought must be
given by the planning authority to the impact of minor
works to the character of protected structures.
Discouraging the use of architectural salvage from
other buildings – the re-use of architectural features can
confuse the understanding and appreciation of a
building, and promoting architectural salvage can cause
a market for these materials and promotes dismantling
of other old buildings.
Assumed existing
reinforced concrete
column with a 300mm
external face that steps
back 100mm and has
15mm insets on both
sides. The internal face
is 270mm in width. The
column has an overall
depth of 400mm.
Existing reinforced
concrete columns and
beams are in relatively
good condition but there
are cracks in certain
places throughout the
building. There is also
evidence of water
staining damage on the
face of the concrete
beams and columns.
Proposed - Fix all the cracks in
the structural columns and
beams. Additional insulation to
the inner face of the column in
line with the additional
insulation to the wall. 25mm
kingspan kooltherm K17
insulated dry-lining board in
between steel U channels, with
12.5mm plasterboard, finished
with a layer of 2.5mm skim.
GFL
0
FFL
3530
SFL
7030
Parapet
10530
56789101112131418
Existing reinforced concrete beams
Existing reinforced concrete columns
Existing steel fire escape staircase
Existing brick wall infill
between reinforced
concrete columns
Existing concrete parapet capping topped
with possibly an aluminium flashing
Existing timber framed single glazed windows
Existing steel fire
escape staircase
GFL
0
FFL
3530
SFL
7030
Parapet
10530
5 6 7 8 9 10 11 12 13 14 18
Existing reinforced concrete beams
Existing reinforced concrete columns
Existing steel fire escape staircase
Existing brick wall infill
between reinforced
concrete columns
Existing concrete parapet capping topped
with possibly an aluminium flashing
Existing timber framed single glazed windows
Existing steel fire
escape staircase
GFL
0
FFL
3530
SFL
7030
Parapet
10530
D C B A
Existing concrete parapet capping topped
with possibly an aluminium flashing
Existing reinforced concrete columns
Existing reinforced concrete beams
Existing fire escape doors that
lead out onto the fire escape
Existing steel fire escape staircase
Existing timber framed single glazed windows
Existing front entrance doorway,
timber framed single glazed door
GFL
0
FFL
3530
SFL
7030
Parapet
10530
DCBA
Existing concrete parapet capping topped
with possibly an aluminium flashing
Existing reinforced concrete columns
Existing reinforced concrete beams
Existing fire escape doors that
lead out onto the fire escape
Existing steel fire escape staircase
Existing timber framed single glazed windows
GFL
0
FFL
3530
SFL
7030
Parapet
10530
5 6 7 8 9 10 11 12 13 14 18
Existing steel fire
escape staircase
Existing steel fire
escape staircase
Existing reinforced concrete beams
Existing reinforced concrete column
Existing timber framed
single glazed window
Existing concrete parapet capping topped with possibly an aluminium flashing
GFL
0
FFL
3530
SFL
7030
Parapet
10530
DCBA
Existing concrete parapet capping topped
with possibly an aluminium flashing
Existing reinforced concrete beams
Existing internal partition wall
Existing concrete staircase
with a terrazzo finish
Existing reinforced concrete column
Existing timber framed
single glazed window
Scale
LECTURER
Drawn by
Date
Project number
Institute of Technology Carlow
BSc. (Hons) in Architectural Technology
Year 4 2013-2014
As indicated
Block L Survey Sheet
1
Restoration, extension and
upgradation to protected structures
13-January-2014
Edel Fox
Noel Dunne, Sujana Sudhir,
& Dan O' Sullivan
SSP1A103
1 : 100
North Elevation as Existing
1
1 : 100
South Elevation as Existing
2
1 : 100
East Elevation as Existing
3
1 : 100
West Elevation as Existing
4
1 : 100
Long Section A-A
5
1 : 100
Short Section A-A
6
1 : 1
Key Plan
7
Conservation Principles to be followed:
Keeping a building in use – Is generally seen as the best
way to keep the building up to a good standard. If a
change of use must occur, minimum damage must be
made to the original character of the building.
Researching and analysing – Much research must be
done on the history, the fabric and the current condition of
the building before any proposals for works can be made.
Using expert conservation advice – expert advice should
be sought throughout the planning process and the
construction process to ensure that the works are
completed correctly.
Protecting the special interest – Inappropriate works
can damage the character and special interest of a
building, so special care must be taken to ensure this
does not happen.
Promoting minimum intervention – “do as much as
necessary and as little as possible”.
Respecting earlier alterations of interest – Earlier
alterations can be an insight into past construction
techniques and must be respected. They are
irreplaceable.
Repairing rather than replacing – the main aim should
be to repair rather than replace because to get the same
quality of materials now is next to impossible and most of
the materials were made by hand.
Promoting honesty of repairs and alterations –
materials used in replacement should not be artificially
aged; this will add confusion in the future as to when the
alterations were made.
Using appropriate materials and methods – appropriate
materials must be used during restoration as in past
examples certain materials accelerated the decay.
Ensuring reversibility of alterations – by ensuring
reversibility of alterations in the future this can allow a
quick fix to unforeseen problems caused by earlier
restorations.
Avoid incremental damage – major thought must be
given by the planning authority to the impact of minor
works to the character of protected structures.
Discouraging the use of architectural salvage from
other buildings – the re-use of architectural features can
confuse the understanding and appreciation of a
building, and promoting architectural salvage can cause
a market for these materials and promotes dismantling
of other old buildings.
UP
UP
DN
DN UP
DN
D
C
B
A
5 6 7 8 9 10 11 12 13 14 18
Proposed ramp to accomodate level change
between corridor and classroom after
insulation has been added to the floor in
accordance with the conservation principles
ensuring reversability of alterations.
Proposed ramp to accomodate level change
between corridor and classroom after insulation
has been added to the floor in accordance with
the conservation principle ensuring reversability of
alterations.
Proposed timber stud partition wall 130mm thick,
consisting of 2.5mm skim a double laye of gypsum
plasterboard with a 60minute fire rating, 75mm timber
studs with insulation in between, double layer of
12.5mm gypsum plasterboard with a 60minute fire
rating in accordance with BS 476, finished with a
layer of 2.5mm skim in accordance with the
conservation principle ensuring reversability of
alterations.
Proposed new
external fire exit to
accomodate a safe
exit from the building
in case of fire in
accordance with
conservation
principle promoting
minimum intervention
Proposed new
alternative steel fire
escape staircase to
replace the existing
staircase in accordance
with the conservation
principle ensuring
reversability of
alterations
Proposed new alternative
steel fire escape staircase
to replace to existing
staircase in accordance
with the conservation
principle ensuring
reversability of alterations
Proposed 2000mm clear width corridor to allow access to all classrooms for
disableds users, after the isulation has been added to the existing floor and the
floor level within the classrooms has been raised. the corridor must be a
minimum of 2000mm to accomodate the amount of traffic that will pass through
the area on a daily basis in accordance with conservation principle promoting
minimum intervention
Proposed all windows to be upgraded to double glazed argon filled timber
framed windows. Proposed draught proofing strips to be added around all
windows and the detailing at cill level is to be addressed. Materials must not
be artificially aged in terms of the conservation principle promoting honesty of
repairs and in terms of not changing the apperance of the building
Existing section of this wall is proposed to be demolisehed to
allow access for the new corridor in accordance with
conservation principle promoting minimum intervention
Proposed upgrading of existing doors throughout the
ground floor with smoke seals all around and covered in a
layer of intumescent paint to provide a fire resistance of
30mins in accordance with conservation principle promoting
minimum intervention
Proposed access ramp to main entrance at a
gradient of 1:12 in accordance with TGD M and
the conservation principles in terms of ensuring
reversability of alterations.
D
C
B
A
5 6 7 8 9 10 11 12 13 14 18
Proposed new alternative
steel fire escape staircase
to replace to existing
staircase in accordance
with the conservation
principle ensuring
reversability of alterations
Proposed new alternative
steel fire escape staircase to
replace to existing staircase
in accordance with the
conservation principle
ensuring reversability of
alterations
Proposed all windows to be upgraded to double glazed argon filled timber
framed windows. Proposed draught proofing strips to be added around all
windows and the detailing at cill level is to be addressed. Materials must
not be artificially aged in terms of the conservation principle promoting
honesty of repairs and in terms of not changing the apperance of the
building
Existing terrazzo covered staircase is in
accordance with current TGD M Building
Regulations
Proposed new 30minute fire rated folding partition alternative walls
to replace existing folding partition walls, to be in compliance with
TGD B in accordance with the conservation principle ensuring
reversability of alterations
Proposed ramp to accomodate level change
between corridor and classroom after insulation
has been added to the floor in accordance with the
conservation principle ensuring reversability of
alterations
Proposed ramp to accomodate
level change between corridor and
classroom after insulation has
been added to the floor in
accordance with the conservation
principle ensuring reversability of
alterations
Proposed parquet flooring to be repaired were possible and relaid
and if not possible to be replaced after the insulation has been
added to the floor in accordance with conservation principle
repairing rather than replacing
D
C
B
A
5 6 7 8 9 10 11 12 13 14 18
Proposed new alternative
steel fire escape staircase
to replace to existing
staircase in accordance
with conservation principle
reversability of alterations
Proposed new alternative steel
fire escape staircase to
replace to existing staircase in
accordance with conservation
principle reversability of
alterations
Proposed all windows to be upgraded to double glazed argon filled
timber framed windows. Proposed draught proofing strips to be
added around all windows and the detailing at cill level is to be
addressed.
Existing terrazzo covered staircase is in
accordance with current TGD M Building
Regulations
Assumed position of existing shower rooms
Proposed demolishment of existing corridor
walls as adequate space was no provided
for wheelchair users in accordance with
TGD M in accordance with the conservation
principle promoting minimum intervention
Proposed demolishment of existing internal doors for wider more sufficient
alternatives in accordance with TGD M
Proposed upgrade of existing
fire escape doors to 60minute
fire escape doors in
accordane with TGD B
Proposed upgrade of existing fire
escape doors to 60minute fire escape
doors in accordane with TGD B
Proposed upgrade of existing doors to 30minute fire
resistant doors with smoke seals all around the edges and a
leayer of intumescent paint to be added in accordance with
the conservation principle promoting minimum intervention
Proposed new corridor a minimum width of 2000mm to allow sufficient access for
disabled access and to allow sufficient room for the foot traffic that will pass through
the building in accordance with TGD M
Proposed upgrade to existing walls with an additional dry-lining board to both faces of the partition
wall, consisting of 50mm kingspan kolltherm K17 insulated dry-lining board in between steel U
channels, with 12.5mm gypsum plasterboard with a 60minute fire rating in accordance with BS 476,
finished with a layer of 2.5mm skim. This to be done to both sides of the wall, in accordance with the
conservation principle ensuring reversability of alterations
Proposed ramp to accomodate level change between corridor and classroom after
insulation has been added to the floor in accordance with the conservation principle
ensuring reversability of alterations
Proposed ramp to accomodate level change between corridor and
classroom after insulation has been added to the floor in accordance with
the conservation principle ensuring reversability of alterations
Proposed addition of Parquet flooring to be added after
insulation has been added to the floor to keep in character
with the rest of the building in accordance with the
conservation principle protecting the special interest
Proposed addition of Parquet
flooring to be added after
insulation has been added to the
floor to keep in character with the
rest of the building in accordance
with the conservation principle
protecting the special interest
Proposed addition of Parquet flooring to be added after
insulation has been added to the floor to keep in character
with the rest of the building in accordance with the
conservation principle protecting the special interest
GFL
0
FFL
3530
SFL
7030
Parapet
10530
DCBA
Existing concrete parapet capping topped with
lead, proposed to be repaired if neccesary and
resealed in accordance with the conservation
principle repairing rather than replacing
Existing terrazzo covered staircase is in
accordance with current TGD M Building
Regulations
Proposed upgrading of existing doors throughout the ground floor
with smoke seals all around and covered in a layer of intumescent
paint to provide a fire resistance of 30mins in accordance with the
conservation principle promoting minimum intervention
Proposed - Upgrading to double glazed argon filled timber
framed windows which will achieve a u-value of 1.8w/m²k.
Install draught proofing strips around all windows to lower
heat loss even more. Materials must not be artificially aged in
terms of the conservation principle promoting honesty of
repairs and in terms of not changing the apperance of the
building
Proposed - remove existing harwood flooring to be repaired where possible and if not replaced, additional
80mm kingspan Therma TF70 in between timber battens to be added on top of existing screed. Repaired
hardwood flooring to be put back down on top of the new insulation in accordance with the conservtion
principle ensuring reversability of alterations
Proposed - timber stud partition wall 130mm thick, consisting of 2.5mm skim a double laye of
gypsum plasterboard with a 60minute fire rating, 75mm timber studs with insulation in between,
double layer of 12.5mm gypsum plasterboard with a 60minute fire rating in accordance with BS
476, finished with a layer of 2.5mm skim in accordance with the conservtion principle ensuring
reversability of alterations
Proposed - additional dry-lining board at internal ceiling level consisting of 85mm
kingspan kooltherm K17 insulated dry-lining board in between timber battens,
12.5mm plasterboard finished with a 2.5mm skim. The existing rubber membrane
needs to be stripped and the torch on felt repaired and the pebbles replaces, and
the drainage issues addressed in accordance with the conservtion principle
ensuring reversability of alterations
Proposed new bathroom layout
with accessible disabled WC in
accordance with TGD M and in
accordance with the conservation
principle promoting minimum
intervention
Proposed 2000mm clear width
corridor in accordance with the
conservation principle promoting
minimum intervention
312540530954053005
Assumed existing floor build up of block l
80mm x 40mm timber battens fixed to the existing floor @ 60mm c/c creating a frame that can be
easily removed in accordance with the conservation principle ensuring reversability of alterations
80mm Kingspan Therma TF70 in between timber battens
18mm Plywood sheeting put in place to fix the flooring to
Repaired paraquet flooring replaced after installation of additional insulation
in accordance with the conservation principle repair rather than replace
85mm x 40mm Vertical steel U channels fixed to the existing wall @
600mm c/c creating a frame that can be easily removed in accordance with
the conservation principle ensuring reversability of alterations
Existing external wall of block l
85mm Kingspan kooltherm K17 insulated dry-lining board in
between steel U channels
12.5mm Gyproc board finished with a layer of 2.5mm plaster skim
Walling alterations
Proposed - additional dry-lining board to the internal
face of the existing wall, consisting of 85mm
kingspan kooltherm K17 insulated dry-linig board in
between steel U channels, with 12.5mm gypsum
plasterboard with a 60minute fir rating in
accordance with BS 476, finished with a layer of
2.5mm skim. Steel U channels to be used as a base
frame for the proposed alterations, with limited
fixings along the horizontal steel U channels to limit
the amount of damage to the original structure as
possible in accordance with the conservation
principle ensuring reversibility of alterations.
Flooring alterations
Proposed - remove existing harwood flooring to
be repaired where possible and if not replaced,
additional 80mm kingspan Therma TF70 in
between timber battens to be added on top of
existing screed. Repaired hardwood flooring to
be put back down on top of the new insulation.
Timber battens to be used as a base frame for
the proposed alterations, with limited fixings so
to create the least amount of damage to the
original structure as possible in accordance with
the conservtion principle ensuring reversability
of alterations.
Scale
LECTURER
Drawn by
Date
Project number
Institute of Technology Carlow
BSc. (Hons) in Architectural Technology
Year 4 2013-2014
As indicated
Conservation Sheet
1
Restoration, extension and
upgradation to protected structures
13-January-2014
Edel Fox
Noel Dunne, Sujana Sudhir
& Dan O' Sulivan
CSP1A104
1 : 100
Ground Floor Level Proposed Conservation
1
1 : 100
First Floor Level Proposed Conservation
2
1 : 100
Second Floor Level Proposed Conservation
3
Conservation Principles to be followed:
Keeping a building in use – Is generally seen as the best
way to keep the building up to a good standard. If a
change of use must occur, minimum damage must be
made to the original character of the building.
Researching and analysing – Much research must be
done on the history, the fabric and the current condition of
the building before any proposals for works can be made.
Using expert conservation advice – expert advice should
be sought throughout the planning process and the
construction process to ensure that the works are
completed correctly.
Protecting the special interest – Inappropriate works
can damage the character and special interest of a
building, so special care must be taken to ensure this
does not happen.
Promoting minimum intervention – “do as much as
necessary and as little as possible”.
Respecting earlier alterations of interest – Earlier
alterations can be an insight into past construction
techniques and must be respected. They are
irreplaceable.
Repairing rather than replacing – the main aim should
be to repair rather than replace because to get the same
quality of materials now is next to impossible and most of
the materials were made by hand.
Promoting honesty of repairs and alterations –
materials used in replacement should not be artificially
aged; this will add confusion in the future as to when the
alterations were made.
Using appropriate materials and methods – appropriate
materials must be used during restoration as in past
examples certain materials accelerated the decay.
Ensuring reversibility of alterations – by ensuring
reversibility of alterations in the future this can allow a
quick fix to unforeseen problems caused by earlier
restorations.
Avoid incremental damage – major thought must be
given by the planning authority to the impact of minor
works to the character of protected structures.
Discouraging the use of architectural salvage from
other buildings – the re-use of architectural features can
confuse the understanding and appreciation of a
building, and promoting architectural salvage can cause
a market for these materials and promotes dismantling
of other old buildings.
1 : 100
Proposed Short Section A-A Conservation
4
3D Proposed Additional Isulation
5
1 : 1
Section A-A Key Plan
6
3D Walling Alterations
7
3D Flooring Alterations
8
Existing U-Value
Existing Ground Floor 0.645W/m²K
Existing External Wall 1.84W/m²K
Existing Column 3.03W/m²K
Existing Roof 2.43W/m²K
Existing Windows 4.8W/m²K
Achieved U-Value
0.24W/m²K
0.21W/m²K
0.23W/m²K
0.23W/m²K
1.8W/m²K
1 : 1
3D Key Plan
9
16 17 18 19 21 22 23 24 25
O
N
M
L
K
13
8
7
6
5
4
2
9
10
I
H
G
E
D
C
B
1
15
A
P
J
3
F
14
Proposed ramp to accomodate level change
between corridor and classroom after insulation
has been added to the floor
Proposed ramp to
accomodate level
change between
corridor and classroom
after insulation has
been added to the floor
Proposed timber stud partition wall 130mm thick,
consisting of 2.5mm skim a double laye of gypsum
plasterboard with a 60minute fire rating, 75mm timber
studs with insulation in between, double layer of
12.5mm gypsum plasterboard with a 60minute fire
rating in accordance with BS 476, finished with a layer
of 2.5mm skim.
Proposed
new
external
fire exit to
accomodat
e a safe
exit from
the building
in case of
fire
Proposed
new
alternative
steel fire
escape
staircase
to replace
to existing
staircase
Proposed 2000mm clear width corridor to allow access to
all classrooms for disableds users, after the isulation has
been added to the existing floor and the floor level within
the classrooms has been raised. the corridor must be a
minimum of 2000mm to accomodate the amount of
traffic that will pass through the area on a daily basis.
Proposed all windows to be upgraded to double glazed argon filled timber
framed windows. Proposed draught proofing strips to be added around all
windows and the detailing at cill level is to be addressed.
Existing terrazzo covered staircase is in
accordance with current TGD M Building
Regulations
Existing section of this wall is proposed to be
demolisehed to allow access for the new corridor
Proposed upgrading of existing doors throughout the ground floor with smoke
seals all around and covered in a layer of intumescent paint to provide a fire
resistance of 30mins
2880
1500
1200
1380
Proposed access ramp to main entrance at a
gradient of 1:12 in accordance with TGD M
1988
47 m²
Classroom
1
34 m²
Corridor 1
2
15 m²
WC's
3
23 m²
Classroom
4
64 m²
Cassroom
5
23 m²
Main Corridor GF
6
20 m²
Stairwell GF
714 m²
Stairwell GF
8
9 m²
Stairs Lobby
9
138 m²
Science Lab
10
43 m²
Lab Storage
11
94 m²
Staff Room
12
43 m²
Classroom
13
44 m²
Classroom
14
12 m²
Protective Corridor
15
24 m²
WC's
16
17 m²
Stairwell GF
17
66 m²
Kitchen
18
175 m²
Canteen
19
Room Legend
Canteen
Cassroom
Classroom
Corridor
Corridor 1
Kitchen
Lab Storage
Main Corridor GF
Protective Corridor
Science Lab
Staff Room
Stairs Lobby
Stairwell GF
WC's
1211 19132
18762
11069
10500
21090
7000
14540
7060
3168
573 2000 1350 2000 1350 2000 675 840 2000 600 2000 600 2000 400
6598 3350 3350 3350 1740
342335003578342335002500
290300032030006403040320300050030003873245
342335003230
2903000320300011961810536
3224 1842 1508 1842 3350 3350 3453
1791 2000 1275 675 2000 1350 2000 675 675 2000 1350 2000 778839
3500
3500
3230
1514
2000
1350
2000
1350
2000
1228
3423
3230
705
2000
1350
2000
598
373
1271
2126
3500
3500
3398
373
373
723
2000
1500
2000
1500
2000
675
825
2000
573 373
4414
3577
3423
348
348598
2000
1350
2000
1052
548
2000
1866
125
11886
100 3150 100320 1010 398840 1340 890532 1010 2582043 1010 4001940 1010 400480 1002 360
360
1010
2233
1194
1010
1194
1324
1010
1166
175
1340
735406
1810
427
208
1810
133
1770
1010 258
1199167662543316761121
2834
9024
1000
2151
2858
3015
15
FD30
12
FD30
13
FD30
9
FD60
8
FD60
2
FD60
1
FD60
3
FD60
4
FD30
5
FD30
7
FD30
6
FD30
10
FD30
11
FD30
16
FD60
17
FD60
28
FD30
25
FD30
24
FD30
20
FD30
19
FD30
21
FD60
26
FD60
23
FD30
22
FD60
27
FD60
14
FD60
15 m²
Stairwell GF
20
5 m²
Stairs Lobby
21
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
120min Fire
Rated Straw
Bale Panel
External Wall
120min Fire
Rated Straw
Bale Panel
External Wall
120min Fire
Rated Straw
Bale Panel
External Wall
120min Fire
Rated Straw
Bale Panel
External Wall
120min Fire
Rated Straw
Bale Panel
External Wall
120min Fire
Rated Straw
Bale Panel
External Wall
120min Fire
Rated Straw
Bale Panel
External Wall
120min Fire
Rated Straw
Bale Panel
External Wall
120min Fire
Rated Straw
Bale Panel
External Wall
120min Fire
Rated Straw
Bale Panel
External Wall
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
3400
3398
262
400
2698
3700
262
8650
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
Existing Block L
1
2
3
4
5
6
7
8
9
10
11
22
21
20
19
18
17
16
15
14
13
12
UP 1 2 3 4 5 6 7 8 9 10
11 12 13 14 15 16 17 18 19 20
UP
UP
1
2
3
4
5
6
7
8
9
1011
12
13
14
15
16
17
18
19
20
348
193
146.00°
146.00°
1550
409 1810 409
2355
2634
10010006481000100
1000 628 1000
1000
1660
1
2
3
4
5
6
789101112
13
14
1516171819
20
21
22
23
24
25
26
27
28
29
30
31
Atrium Opening Above
155
1016
300
679 1707 700
General Notes:
-All works to comply with current building
regulations and code of practice.
-All works must be done to the satisfaction of
the buildign control officer.
-All dimensions in mm unless otherwise
noted.
-Drawings must not be scaled, written
dimensions must be followed.
-Expert advice must be sought from a
conservation architect and the heritage group
before construction can start on site.
-Glulaminated columns to be placed on the
intersection of grid lines as shown.
-Glulaminated beams to span along gridlines
from column to column.
-Walls not placed along gridlines.
-Primary structure glumainated columns and
beams to be in accordance with EN 14080.
-Cross laminated timber panels to be in
accordance with BS EN 1995-2, BS EN
12354-1 and BS EN 12354 -2 in terms of fire
and acoustic performance.
-Precast concrete for lift shaft and stair shaft
to comply with BS EN 1992-1-2:2004.
-Lift and stair shaft to be 60min fire proof
including access doors.
-All escape fire doors to be 60min fire rated
and fitted with automatic closers.
-Floor finish to be non-slip ceramic tiles and
timber floors where indicated on plan.
-Entrance area to have a minimum level
landing within 1800mm of entrance door.
29
FD60
32 33 35 36 37 38 39 40
4142434445
46
4748
49
505152
Wall dimensions either
side of gridline
Proposed demolishment of existing window and installation of
new fire rated door to allow for link access to new extension block
126
64
FD60
65
FD60
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
69
FD30
18
FD60
30
FD30
30667
19 m²
Corridor
22
120min Fire
Rated Straw
Bale Panel
External Wall
Reynaers Eco
System 50
insulated and
ventilated
windows
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
120min Fire
Rated Straw
Bale Panel
External Wall
Reynaers Eco
System 50
insulated and
ventilated
windows
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
Scale
LECTURER
Drawn by
Date
Project number
Institute of Technology Carlow
BSc. (Hons) in Architectural Technology
Year 4 2013-2014
1 : 100
Combined Ground Floor Plan
1
Restoration, extension and
upgradation to protected structures
13-January-2014
Edel Fox
Noel Dunne, Sujana Sudhir
& Dan O' Sullivan
GAP1A105
1 : 100
Ground Floor Level
1
Door Schedule Ground Floor Level
Level Mark Fire Rating Width Height
GFL 1 FD60 1810 2110
GFL 2 FD60 1810 2110
GFL 3 FD60 1810 2110
GFL 4 FD30 1010 2110
GFL 5 FD30 1010 2110
GFL 6 FD30 1010 2110
GFL 7 FD30 1010 2110
GFL 8 FD60 1810 2110
GFL 9 FD60 1810 2110
GFL 10 FD30 1010 2110
GFL 11 FD30 1010 2110
GFL 12 FD30 1010 2110
GFL 13 FD30 1010 2110
GFL 14 FD60 1810 2110
GFL 15 FD30 1010 2110
GFL 16 FD60 813 2184
GFL 17 FD60 813 2184
GFL 18 FD60 1810 2110
GFL 19 FD30 910 2110
GFL 20 FD30 910 2110
GFL 21 FD60 1810 2110
GFL 22 FD60 1010 2110
GFL 23 FD30 1010 2110
GFL 24 FD30 910 2110
GFL 25 FD30 910 2110
GFL 26 FD60 1810 2110
GFL 27 FD60 1010 2110
GFL 28 FD30 835 2595
GFL 29 FD60 1810 2110
GFL 30 FD30 1950 2325
GFL 64 FD60 1810 2110
GFL 65 FD60 1810 2110
GFL 69 FD30 1950 2025
GFL 74 FD60 1810 2110
Room Schedule Ground Floor Level
Number Name Level Area
1 Classroom GFL 47 m²
2 Corridor 1 GFL 34 m²
3 WC's GFL 15 m²
4 Classroom GFL 23 m²
5 Cassroom GFL 64 m²
6 Main Corridor GF GFL 23 m²
7 Stairwell GF GFL 20 m²
8 Stairwell GF GFL 14 m²
9 Stairs Lobby GFL 9 m²
10 Science Lab GFL 138 m²
11 Lab Storage GFL 43 m²
12 Staff Room GFL 94 m²
13 Classroom GFL 43 m²
14 Classroom GFL 44 m²
15 Protective Corridor GFL 12 m²
16 WC's GFL 24 m²
17 Stairwell GF GFL 17 m²
18 Kitchen GFL 66 m²
19 Canteen GFL 175 m²
20 Stairwell GF GFL 15 m²
21 Stairs Lobby GFL 5 m²
22 Corridor GFL 19 m²
General Specification
Block L
Proposed upgrade to existing external walls
Proposed - additional dry-lining board to the internal face of the existing wall,
consisting of 85mm kingspan kooltherm K17 insulated dry-linig board in between
steel U channels, with 12.5mm gypsum plasterboard with a 60minute fir rating in
accordance with BS 476, finished with a layer of 2.5mm skim.
Proposed upgrade to existing internal walls
Proposed - additional dry-linig board to both faces of the partition wall, consisting
of 50mm kingspan kolltherm K17 insulated dry-lining board in between steel U
channels, with 12.5mm gypsum plasterboard with a 60minute fire rating in
accordance with BS 476, finished with a layer of 2.5mm skim. This to be done to
both sides of the wall.
Proposed upgrade to existing floor
Proposed - remove existing harwood flooring to be repaired where possible and
if not replaced, additional 80mm kingspan Therma TF70 in between timber
battens to be added on top of existing screed. Repaired hardwood flooring to be
put back down on top of the new insulation.
Proposed upgrade to existing roof
Proposed - additional dry-lining board at internal ceiling level consisting of 85mm
kingspan kooltherm K17 insulated dry-lining board in between timber battens,
12.5mm plasterboard finished with a 2.5mm skim. The existing rubber membrane
needs to be stripped and the torch on felt repaired and the pebbles replaces, and
the drainage issues addressed.
Proposed timber stud partition
Proposed - timber stud partition wall 130mm thick, consisting of 2.5mm skim a
double laye of gypsum plasterboard with a 60minute fire rating, 75mm timber
studs with insulation in between, double layer of 12.5mm gypsum plasterboard
with a 60minute fire rating in accordance with BS 476, finished with a layer of
2.5mm skim.
Proposed upgrade to existing windows
Proposed - Upgrading to double glazed argon filled timber framed windows which
will achieve a u-value of 1.8w/m²k. Install draught proofing strips around all
windows to lower heat loss even more. Address detailing at cill to fix the water
drainage problem from occuring.
Proposed upgrade to existing internal doors
Proposed upgrading of existing doors throughout the ground floor with smoke
seals all around and covered in a layer of intumescent paint to provide a fire
resistance of 30mins.
New Extension
Structural Foundations – 540mm X 400mm reinforced concrete ring beams to
carry the load of the external and internal walls, while also allocating a space for
the hollowcore flooring to sit into. The hollowcore flooring will bear half way on to
each beam and be securely strapped back using T12 tie bars bedded in with the
screed. Each structural glulam column will be connected back to a 360mm x
360mm square reinforced concrete column. Each concrete column will vary in
depth as the ground is gradually sloped. The reinforced concrete column will be
structurally supported below by a pad foundation. Each column is to have its own
individual pad foundation where possible.
Ground Floor Build Up – DPM to be placed between hollowcore floor slabs and
ground, 200mm precast concrete hollowcore flooring slabs to be connected back
to the reinforced concrete ring beams, both in accordance with BS EN 1992-1-
2:2004. 75mm structural concrete screed to be placed on top of the hollowcore
flooring slabs. 80mm Kingspan Kooltherm K3 Floorboard to be placed on top of
the structural screed, with 80mm x 40mm thimber battens @ 600mm c/c to be
placed in between. 18mm plywood sheeting to be placed over the insulation and
fixed back to the timber battens @ 600mm c/c. Finally the floor is to be finished
in accordance with the use of each specific room, with 22mm oak flooring to be
placed in most areas and a tile finish to be placed in the kitchen and WC areas.
Intermediate Floor Build Up – On the underside, the floor is to be finished with a
2.5mm plaster skim, which is applied directly to 12.5mm gyproc board. This is
followed by a 25mm services gap and then 50mm rockwool insulation, in between
25mm x 75mm timber battens @ 600mm c/c fixed back to the cross laminated
timber panels. These battens are used to support and fix the gyproc board in
place. The main structure of the floor is made up of a 200mm (5 x 40mm layers)
cross laminated timber panels, which spans from one glulam beam to another.
Above this there is another layer of 50mm rockwool insulation in between 25mm
x 50mm timber battens @ 600mm c/c. Then sheets of 18mm plywood finally
finished off with a 22mm oak flooring or a tile finish depending on the use of the
room.
Roof Build Up - On the underside, the roof is to be finished with a 2.5mm plaster
skim, which is applied directly to 12.5mm gyproc board. This is followed by a
25mm services gap and then 50mm rockwool insulation, in between 25mm x
75mm timber battens @ 600mm c/c fixed back to the cross laminated timber
panels. These battens are used to support and fix the gyproc board in place.
The main structure of the floor is made up of a 200mm (5 x 40mm layers) cross
laminated timber panels, which spans from one glulam beam to another. Above
this a vapour barrier layer is to be added. Followed by 120mm Kingspan
Thermaroof TR31, then a 3G base layer, finished with a triple layer of built up felt
waterproofing.
External Wall Build Up – From Exterior: 8mm external lime render finish, 40mm
wood fibre combined breather membrane board, 12mm timbervent, 400mm
wheat straw bale insulation in between 400mm ‘I’ studs spaced @ 600mm c/c,
15mm OSB, 25mm services cavity in between 25mm x 50mm vertical timber
battens fixed back to the 15mm OSB, finished on the interior side with a layer of
12.5mm gyproc board and 2.5mm plaster skim finish. Each end of the straw bale
panel is closed with a 43mm x 400mm glulaminated column. This system is from
the manufacturer Modcell, it is the Modcell Core + panel. This wall panel
achieves a u-value of 0.11 W/(m2K), a fire rating of 120mins, and an acoustic
performance rating of 52db.
Internal Wall Build Up – 2.5mm plaster finish, 12.5mm gyproc board, 25mm
rockwool insulation in between 25mm x 25mm vertical timber battens spaced @
600mm c/c fixed back to the cross laminated timber panel, put in place to support
and fix the gyproc board to. Followed by 120mm (40mm x 3 layers) cross
laminated timber wall panel in accordance with BS EN 1995-2, BS EN 12354-1
and BS EN 12354-2 in terms of fire and acoustic performance, 25mm rockwool
insulation in between 25mm x 25mm vertical timber battens spaced @ 600mm
c/c fixed back to the cross laminated timber panel, put in place to support and fix
the gyproc board to. Finished with 12.5mm gyproc board and 2.5mm plaster
skim finish.
Concrete Wall Panels – 200mm reinforced precast concrete solid wall panels to
be used in the stairs, stair lobby, lift shaft and protected corridor to provide
structural strength and achieve the required fire rating in accordance with TGD B.
the panels are also relatively soundproof so this will eliminate sound transmission
throughout the building. The internal panels will have a 25mm service cavity in
between 25mm x 50mm vertical timber battens, finished with 12.5mm gyproc
board and a 2.5mm plaster skim finish, with the side inside the lift or stairs shaft
having the concrete left exposed. The panels that are exposed to the outside will
have no internal finish (concrete to be left exposed), and an 8mm lime render
finish to the external face.
3D GL
2
16 17 18 19 21 22 23 24 25
O
N
M
L
K
13
8
7
6
5
4
2
9
10
I
H
G
E
D
C
B
1
15
A
P
J
3
F
14
Proposed new alternative steel
fire escape staircase to replace
to existing staircase
Proposed all windows to be upgraded to double glazed argon filled timber
framed windows. Proposed draught proofing strips to be added around all
windows and the detailing at cill level is to be addressed.
Existing terrazzo covered staircase is in
accordance with current TGD M Building
Regulations
Proposed ramp to accomodate level change
between corridor and classroom after insulation
has been added to the floor
Proposed ramp to accomodate level change between
corridor and classroom after insulation has been
added to the floor
Proposed parquet flooring to be repaired were possible
and relaid and if not possible to be replaced after the
insulation has been added to the floor
201 m²
Classroom
29
30 m²
Corridor
30
20 m²
Stairwell FFL
3114 m²
Stairwell FFL
32
9 m²
Stairwell Lobby
33
138 m²
Science Lab
34
43 m²
Lab Storage
35
67 m²
Classroom
36
25 m²
Storage
37
43 m²
Classroom
38
44 m²
Classroom
39
12 m²
Protective Corridor
40
24 m²
WC's
41
17 m²
Stairwell FFL
42
64 m²
Kitchen Storage
43
176 m²
Canteen
44
15 m²
Room
45
5 m²
Room
46
1211
21090
820250035003423357835003423348
638300032030003133283040320300050030003133320
10500
7000
14540
6598 3350 3350 3350 1740
342335003230
29030003203000
3500
3500
3230
2000
1350
2000
1350
2000
1228
3423
3230
705
2000
1350
2000
598
4414
3577
3423
348
348598
2000
1350
2000
1052
548
2000
1866
125
11886
9020
1000
2151
2858
3011
19132
573 2000 1350 2000 1350 2000 675 840 2000 600 2000 600 2000 400
313
18746
3304 1842 1508 1842 3350 3350 3777
1871 2000 1275 675 2000 1350 2000 675 675 2000 1350 2000 1102
11149
373
3398
3500
3500
2126
1271
373
373
573
2000
825
675
2000
1500
2000
1500
2000
723
373
Room Legend
Canteen
Classroom
Corridor
Kitchen Storage
Lab Storage
Protective Corridor
Room
Science Lab
Stairwell FFL
Stairwell Lobby
Storage
WC's
45
FD60
44
FD60
39
FD30
41
FD30
40
FD30
31
FD60 32
FD60
33
FD30
34
FD30
36
FD30
35
FD30
37
FD30
38
FD30
42
FD60
43
FD60
49
FD30
48
FD30
47
FD30 50
FD6046
FD60
429
1794
437
1296
1794
308
155
22511340
735
175
4784
1000
1200
1200
Ramp @
gradient of 1:20
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
Atrium Opening Above
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
120min Fire
Rated Straw
Bale Panel
External Wall
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
120min Fire
Rated Straw
Bale Panel
External Wall
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
120min Fire
Rated Straw
Bale Panel
External Wall
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
120min Fire
Rated Straw
Bale Panel
External Wall
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
120min Fire
Rated Straw
Bale Panel
External Wall
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
120min Fire
Rated Straw
Bale Panel
External Wall
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
120min Fire
Rated Straw
Bale Panel
External Wall
120min Fire
Rated Straw
Bale Panel
External Wall
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
120min Fire
Rated Straw
Bale Panel
External Wall
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
1324
1010
1166
1194
1010
1194
300
1010
2293
532 1010 300 2140 1010 200 2243 1010 200 565 1010 1010 398 3350
409 1810 409
2355
1851
64172464
461 1010 1383
2854
10006481000
1000 628 1000
1660
1000
General Notes:
-All works to comply with current building
regulations and code of practice.
-All works must be done to the satisfaction of
the buildign control officer.
-All dimensions in mm unless otherwise
noted.
-Drawings must not be scaled, written
dimensions must be followed.
-Expert advice must be sought from a
conservation architect and the heritage group
before construction can start on site.
-Glulaminated columns to be placed on the
intersection of grid lines as shown.
-Glulaminated beams to span along gridlines
from column to column.
-Walls not placed along gridlines.
-Primary structure glumainated columns and
beams to be in accordance with EN 14080.
-Cross laminated timber panels to be in
accordance with BS EN 1995-2, BS EN
12354-1 and BS EN 12354 -2 in terms of fire
and acoustic performance.
-Precast concrete for lift shaft and stair shaft
to comply with BS EN 1992-1-2:2004.
-Lift and stair shaft to be 60min fire proof
including access doors.
-All escape fire doors to be 60min fire rated
and fitted with automatic closers.
-Floor finish to be non-slip ceramic tiles and
timber floors where indicated on plan.
-Entrance area to have a minimum level
landing within 1800mm of entrance door.
1
2
3
4
5
6
7
8
9
10
11
23
22
21
20
19
18
17
16
15
14
13
1
2
3
4
5
6
7
8
9
1011
12
13
14
15
16
17
18
19
20
1 2 3 4 5 6 7 8 9 10
11 12 13 14 15 16 17 18 19 20
53
54
55
56
57
58
596061626364
65
66
6768697071
72
73
74
75
76
77
78
79
80
81
82
83
84 85 86 87 88 89 90 91 92
9394959697
9899
100101102
12
24
Proposed demolishment of existing window and installation of new
fire rated door to allow for link access to new extension block
348
193
Wall dimensions either
side of gridline
146.00°
146.00°
63
FD60
66
FD60
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
127
128
8650
400
2698
403
2700
598
262
3400
3398
262
7060
1842 1366
3208
30763
Existing Block L
120min Fire
Rated Straw
Bale Panel
External Wall
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
Reynaers Eco
System 50
insulated and
ventilated
windows
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
120min Fire
Rated Straw
Bale Panel
External Wall
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
Scale
LECTURER
Drawn by
Date
Project number
Institute of Technology Carlow
BSc. (Hons) in Architectural Technology
Year 4 2013-2014
1 : 100
Combined First Floor Plan
1
Restoration, extension and
upgradation to protected structures
13-January-2014
Edel Fox
Noel Dunne, Sujana Sudhir
& Dan O' Sullivan
GAP1A106
1 : 100
First Floor Level
1
General Specification
Block L
Proposed upgrade to existing external walls
Proposed - additional dry-lining board to the internal face of the existing wall,
consisting of 85mm kingspan kooltherm K17 insulated dry-linig board in between
steel U channels, with 12.5mm gypsum plasterboard with a 60minute fir rating in
accordance with BS 476, finished with a layer of 2.5mm skim.
Proposed upgrade to existing internal walls
Proposed - additional dry-linig board to both faces of the partition wall,
consisting of 50mm kingspan kolltherm K17 insulated dry-lining board in between
steel U channels, with 12.5mm gypsum plasterboard with a 60minute fire rating
in accordance with BS 476, finished with a layer of 2.5mm skim. This to be done
to both sides of the wall.
Proposed upgrade to existing floor
Proposed - remove existing harwood flooring to be repaired where possible and
if not replaced, additional 80mm kingspan Therma TF70 in between timber
battens to be added on top of existing screed. Repaired hardwood flooring to
be put back down on top of the new insulation.
Proposed upgrade to existing roof
Proposed - additional dry-lining board at internal ceiling level consisting of 85mm
kingspan kooltherm K17 insulated dry-lining board in between timber battens,
12.5mm plasterboard finished with a 2.5mm skim. The existing rubber
membrane needs to be stripped and the torch on felt repaired and the pebbles
replaces, and the drainage issues addressed.
Proposed timber stud partition
Proposed - timber stud partition wall 130mm thick, consisting of 2.5mm skim a
double laye of gypsum plasterboard with a 60minute fire rating, 75mm timber
studs with insulation in between, double layer of 12.5mm gypsum plasterboard
with a 60minute fire rating in accordance with BS 476, finished with a layer of
2.5mm skim.
Proposed upgrade to existing windows
Proposed - Upgrading to double glazed argon filled timber framed windows
which will achieve a u-value of 1.8w/m²k. Install draught proofing strips around all
windows to lower heat loss even more. Address detailing at cill to fix the water
drainage problem from occuring.
Proposed upgrade to existing internal doors
Proposed upgrading of existing doors throughout the ground floor with smoke
seals all around and covered in a layer of intumescent paint to provide a fire
resistance of 30mins.
New Extension
Structural Foundations – 540mm X 400mm reinforced concrete ring beams to
carry the load of the external and internal walls, while also allocating a space for
the hollowcore flooring to sit into. The hollowcore flooring will bear half way on
to each beam and be securely strapped back using T12 tie bars bedded in with
the screed. Each structural glulam column will be connected back to a 360mm x
360mm square reinforced concrete column. Each concrete column will vary in
depth as the ground is gradually sloped. The reinforced concrete column will be
structurally supported below by a pad foundation. Each column is to have its
own individual pad foundation where possible.
Ground Floor Build Up – DPM to be placed between hollowcore floor slabs
and ground, 200mm precast concrete hollowcore flooring slabs to be connected
back to the reinforced concrete ring beams, both in accordance with BS EN
1992-1-2:2004. 75mm structural concrete screed to be placed on top of the
hollowcore flooring slabs. 80mm Kingspan Kooltherm K3 Floorboard to be
placed on top of the structural screed, with 80mm x 40mm thimber battens @
600mm c/c to be placed in between. 18mm plywood sheeting to be placed over
the insulation and fixed back to the timber battens @ 600mm c/c. Finally the
floor is to be finished in accordance with the use of each specific room, with
22mm oak flooring to be placed in most areas and a tile finish to be placed in
the kitchen and WC areas.
Intermediate Floor Build Up – On the underside, the floor is to be finished with
a 2.5mm plaster skim, which is applied directly to 12.5mm gyproc board. This is
followed by a 25mm services gap and then 50mm rockwool insulation, in
between 25mm x 75mm timber battens @ 600mm c/c fixed back to the cross
laminated timber panels. These battens are used to support and fix the gyproc
board in place. The main structure of the floor is made up of a 200mm (5 x
40mm layers) cross laminated timber panels, which spans from one glulam
beam to another. Above this there is another layer of 50mm rockwool insulation
in between 25mm x 50mm timber battens @ 600mm c/c. Then sheets of 18mm
plywood finally finished off with a 22mm oak flooring or a tile finish depending
on the use of the room.
Roof Build Up - On the underside, the roof is to be finished with a 2.5mm
plaster skim, which is applied directly to 12.5mm gyproc board. This is followed
by a 25mm services gap and then 50mm rockwool insulation, in between 25mm
x 75mm timber battens @ 600mm c/c fixed back to the cross laminated timber
panels. These battens are used to support and fix the gyproc board in place.
The main structure of the floor is made up of a 200mm (5 x 40mm layers) cross
laminated timber panels, which spans from one glulam beam to another. Above
this a vapour barrier layer is to be added. Followed by 120mm Kingspan
Thermaroof TR31, then a 3G base layer, finished with a triple layer of built up
felt waterproofing.
External Wall Build Up – From Exterior: 8mm external lime render finish, 40mm
wood fibre combined breather membrane board, 12mm timbervent, 400mm
wheat straw bale insulation in between 400mm ‘I’ studs spaced @ 600mm c/c,
15mm OSB, 25mm services cavity in between 25mm x 50mm vertical timber
battens fixed back to the 15mm OSB, finished on the interior side with a layer of
12.5mm gyproc board and 2.5mm plaster skim finish. Each end of the straw
bale panel is closed with a 43mm x 400mm glulaminated column. This system is
from the manufacturer Modcell, it is the Modcell Core + panel. This wall panel
achieves a u-value of 0.11 W/(m2K), a fire rating of 120mins, and an acoustic
performance rating of 52db.
Internal Wall Build Up – 2.5mm plaster finish, 12.5mm gyproc board, 25mm
rockwool insulation in between 25mm x 25mm vertical timber battens spaced @
600mm c/c fixed back to the cross laminated timber panel, put in place to
support and fix the gyproc board to. Followed by 120mm (40mm x 3 layers)
cross laminated timber wall panel in accordance with BS EN 1995-2, BS EN
12354-1 and BS EN 12354-2 in terms of fire and acoustic performance, 25mm
rockwool insulation in between 25mm x 25mm vertical timber battens spaced @
600mm c/c fixed back to the cross laminated timber panel, put in place to
support and fix the gyproc board to. Finished with 12.5mm gyproc board and
2.5mm plaster skim finish.
Concrete Wall Panels – 200mm reinforced precast concrete solid wall panels
to be used in the stairs, stair lobby, lift shaft and protected corridor to provide
structural strength and achieve the required fire rating in accordance with TGD
B. the panels are also relatively soundproof so this will eliminate sound
transmission throughout the building. The internal panels will have a 25mm
service cavity in between 25mm x 50mm vertical timber battens, finished with
12.5mm gyproc board and a 2.5mm plaster skim finish, with the side inside the
lift or stairs shaft having the concrete left exposed. The panels that are exposed
to the outside will have no internal finish (concrete to be left exposed), and an
8mm lime render finish to the external face.
Door Schedule First Floor Level
Level Mark Fire Rating Width Height
FFL 15 FD60 184 1245
FFL 16 FD60 184 190
FFL 31 FD60 1810 2110
FFL 32 FD60 1810 2110
FFL 33 FD30 1010 2110
FFL 34 FD30 1010 2110
FFL 35 FD30 1010 2110
FFL 36 FD30 1010 2110
FFL 37 FD30 1010 2110
FFL 38 FD30 1010 2110
FFL 39 FD30 1010 2110
FFL 40 FD30 1010 2110
FFL 41 FD30 1010 2110
FFL 42 FD60 813 2184
FFL 43 FD60 813 2184
FFL 44 FD60 1810 2110
FFL 45 FD60 1810 2110
FFL 46 FD60 184 665
FFL 47 FD30 910 2110
FFL 48 FD30 1010 2110
FFL 49 FD30 910 2110
FFL 50 FD60 910 2110
FFL 63 FD60 1810 2110
FFL 66 FD60 1810 2110
FFL 73 FD30 910 2110
Room Schedule First Floor Leel
Number Name Level Area
29 Classroom FFL 201 m²
30 Corridor FFL 30 m²
31 Stairwell FFL FFL 20 m²
32 Stairwell FFL FFL 14 m²
33 Stairwell Lobby FFL 9 m²
34 Science Lab FFL 138 m²
35 Lab Storage FFL 43 m²
36 Classroom FFL 67 m²
37 Storage FFL 25 m²
38 Classroom FFL 43 m²
39 Classroom FFL 44 m²
40 Protective Corridor FFL 12 m²
41 WC's FFL 24 m²
42 Stairwell FFL FFL 17 m²
43 Kitchen Storage FFL 64 m²
44 Canteen FFL 176 m²
45 Room FFL 15 m²
46 Room FFL 5 m²
3D FFL
2
16 17 18 19 21 22 23 24 25
O
N
M
L
K
13
8
7
6
5
4
2
9
10
I
H
G
E
D
C
B
1
15
A
P
J
3
F
14
Proposed new alternative steel
fire escape staircase to replace
to existing staircase
Proposed all windows to be upgraded to double glazed argon filled timber framed windows.
Proposed draught proofing strips to be added around all windows and the detailing at cill level is to
be addressed.
Existing terrazzo covered staircase is in
accordance with current TGD M Building
Regulations
Proposed demolishment of existing
corridor walls as adequate space was no
provided for wheelchair users in
accordance with TGD M
Proposed new corridor a minimum width of 2000mm to allow sufficient access for
disabled access and to allow sufficient room for the foot traffic that will pass through
the building in accordance with TGD M
Proposed upgrade to existing walls with an additional dry-lining board to both faces of the
partition wall, consisting of 50mm kingspan kolltherm K17 insulated dry-lining board in between
steel U channels, with 12.5mm gypsum plasterboard with a 60minute fire rating in accordance
with BS 476, finished with a layer of 2.5mm skim. This to be done to both sides of the wall.
Proposed ramp to accomodate level change between corridor and
classroom after insulation has been added to the floor
Proposed ramp to accomodate level change between corridor and
classroom after insulation has been added to the floor
Proposed addition of Parquet
flooring to be added after
insulation has been added to the
floor to keep in character with the
rest of the building
Proposed addition of Parquet flooring to
be added after insulation has been added
to the floor to keep in character with
the rest of the building
Proposed addition of Parquet flooring to be added after
insulation has been added to the floor to keep in character
with the rest of the building
11 m²
Showers
47
99 m²
Games Room
48
116 m²
Music Room
49
6 m²
Corridor
50
20 m²
Stairwell SFL
51
14 m²
Stairwell SFL
52
9 m²
Stairwell Lobby
53
10 m²
Protected Corridor
54
24 m²
WC's
55
17 m²
Stairwell SFL
56
15 m²
Stairwell SFL
57
5 m²
Stairwell Lobby
58
Room Legend
Corridor
Games Room
Music Room
Protected Corridor
Showers
Stairwell Lobby
Stairwell SFL
WC's
1211
Atrium Opening Above
General Notes:
-All works to comply with current building
regulations and code of practice.
-All works must be done to the
satisfaction of the buildign control
officer.
-All dimensions in mm unless otherwise
noted.
-Drawings must not be scaled, written
dimensions must be followed.
-Expert advice must be sought from a
conservation architect and the heritage
group before construction can start on
site.
-Glulaminated columns to be placed on
the intersection of grid lines as shown.
-Glulaminated beams to span along
gridlines from column to column.
-Walls not placed along gridlines.
-Primary structure glumainated columns
and beams to be in accordance with EN
14080.
-Cross laminated timber panels to be in
accordance with BS EN 1995-2, BS EN
12354-1 and BS EN 12354 -2 in terms of
fire and acoustic performance.
-Precast concrete for lift shaft and stair
shaft to comply with BS EN 1992-1-
2:2004.
-Lift and stair shaft to be 60min fire proof
including access doors.
-All escape fire doors to be 60min fire
rated and fitted with automatic closers.
-Floor finish to be non-slip ceramic tiles
and timber floors where indicated on
plan.
-Entrance area to have a minimum level
landing within 1800mm of entrance door.
1
2
3
4
5
6
7
8
9
1011
12
13
14
15
16
17
18
19
20
1 2 3 4 5 6 7 8 9 10
11 12 13 14 15 16 17 18 19 20
Proposed demolishment of existing window and installation of
new fire rated door to allow for link access to new extension block
1
2
3
4
5
6
7
8
9
10
11
23
22
21
20
19
18
17
16
15
14
13
12
24
425
1810
425
1296
175
1340
735155
2251
155
9024
3015
2858
2151
1000
11874
335
3423
3577
4414
125
360
1271
2126
3500
3500
3398
360
14515
335
3423
3235
6993
903
3500
3500
3243
11146
3314 1842 1508 1842 3350 3350 3569
18775
348342335003243
360 6598 3350 3350 3350 1740
348342335003578342335002500
10010006481000100
2634
241 1010 1383
565 1010 3615 1010 398
56
FD60
53
FD30
55
FD30
54
FD30
62
FD6057
FD60
61
FD30
59
FD30
60
FD30
58
FD30
51
FD60 52
FD60
1851
859876116
409 1810 409
2355
1000 628 1000
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
60min Fire rated
Cross Laminated
Timber Panel
Parapet wall
covered in
roofing felt
Membrane
coated insulated
gutter
60min Fire rated
Cross Laminated
Timber Panel
Roof with a
Kingspan
Thermaroof
TR31 covering
60min Fire rated
200mm Cross
laminated timber
panel floor
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
120min Fire
Rated Straw
Bale Panel
External Wall
120min Fire
Rated Straw
Bale Panel
External Wall
60min Fire rated
Glulaminated
beam 140mm x
675mm EN
14080
60min Fire rated
Cross Laminated
Timber Panel
Parapet wall
covered in
roofing felt
60min Fire rated
Cross Laminated
Timber Panel
Roof with a
Kingspan
Thermaroof
TR31 covering
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
60min Fire rated
Cross Laminated
Timber Panel
Roof with a
Kingspan
Thermaroof
TR31 covering
120min Fire
Rated Straw
Bale Panel
External Wall
Glass handrail at
a height of
900mm
Glass handrail at
a height of
900mm
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
60min Fire rated
Cross Laminated
Timber Panel
Roof with a
Kingspan
Thermaroof
TR31 covering
60min Fire rated
Cross Laminated
Timber Panel
Roof with a
Kingspan
Thermaroof
TR31 covering
Membrane
coated insulated
gutter
Membrane
coated insulated
gutter
60min Fire rated
Cross Laminated
Timber Panel
Parapet wall
covered in
roofing felt
60min Fire rated
Cross Laminated
Timber Panel
Parapet wall
covered in
roofing felt60min Fire rated
Cross Laminated
Timber Panel
Parapet wall
covered in
roofing felt
8650
30763
400
2698
403
2700
598
262
3400
3398
262
7060
1842 1366
3208
21090
Existing Block L
Existing Block B
&
Block C
103
104
105
106 107 108 109 110 111 112 113 114
120121
Direction of rain water flow
Proposed to be demolished
Legend
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
67
FD60
68
FD60
8650
30763
400
2698
403
2700
598
262
3400
3398
262
7060
1842 1366
3208
22mm Accoya
timber cladding
finish to the
exterior
60min Fire rated
Cross Laminated
Timber Panel
Roof with a
Kingspan
Thermaroof
TR31 covering
Membrane
coated insulated
gutter
Reynaers Eco
System 50
insulated and
ventilated
windows
60min Fire rated
Cross Laminated
Timber Panel
Roof with a
Kingspan
Thermaroof
TR31 covering
Membrane
coated insulated
gutter
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
Reynaers Eco
System 50
insulated and
ventilated
windows
Scale
LECTURER
Drawn by
Date
Project number
Institute of Technology Carlow
BSc. (Hons) in Architectural Technology
Year 4 2013-2014
1 : 100
Combined Second Floor Plan
1
Restoration, extension and
upgradation to protected structures
13-January-2014
Edel Fox
Noel Dunne, Sujana Sudhir
& Dan O' Sullivan
GAP1A107
1 : 100
Second Floor Level
1
General Specification
Block L
Proposed upgrade to existing external walls
Proposed - additional dry-lining board to the internal face of the existing wall,
consisting of 85mm kingspan kooltherm K17 insulated dry-linig board in between
steel U channels, with 12.5mm gypsum plasterboard with a 60minute fir rating in
accordance with BS 476, finished with a layer of 2.5mm skim.
Proposed upgrade to existing internal walls
Proposed - additional dry-linig board to both faces of the partition wall,
consisting of 50mm kingspan kolltherm K17 insulated dry-lining board in between
steel U channels, with 12.5mm gypsum plasterboard with a 60minute fire rating
in accordance with BS 476, finished with a layer of 2.5mm skim. This to be done
to both sides of the wall.
Proposed upgrade to existing floor
Proposed - remove existing harwood flooring to be repaired where possible and
if not replaced, additional 80mm kingspan Therma TF70 in between timber
battens to be added on top of existing screed. Repaired hardwood flooring to
be put back down on top of the new insulation.
Proposed upgrade to existing roof
Proposed - additional dry-lining board at internal ceiling level consisting of 85mm
kingspan kooltherm K17 insulated dry-lining board in between timber battens,
12.5mm plasterboard finished with a 2.5mm skim. The existing rubber
membrane needs to be stripped and the torch on felt repaired and the pebbles
replaces, and the drainage issues addressed.
Proposed timber stud partition
Proposed - timber stud partition wall 130mm thick, consisting of 2.5mm skim a
double laye of gypsum plasterboard with a 60minute fire rating, 75mm timber
studs with insulation in between, double layer of 12.5mm gypsum plasterboard
with a 60minute fire rating in accordance with BS 476, finished with a layer of
2.5mm skim.
Proposed upgrade to existing windows
Proposed - Upgrading to double glazed argon filled timber framed windows
which will achieve a u-value of 1.8w/m²k. Install draught proofing strips around all
windows to lower heat loss even more. Address detailing at cill to fix the water
drainage problem from occuring.
Proposed upgrade to existing internal doors
Proposed upgrading of existing doors throughout the ground floor with smoke
seals all around and covered in a layer of intumescent paint to provide a fire
resistance of 30mins.
New Extension
Structural Foundations – 540mm X 400mm reinforced concrete ring beams to
carry the load of the external and internal walls, while also allocating a space for
the hollowcore flooring to sit into. The hollowcore flooring will bear half way on
to each beam and be securely strapped back using T12 tie bars bedded in with
the screed. Each structural glulam column will be connected back to a 360mm x
360mm square reinforced concrete column. Each concrete column will vary in
depth as the ground is gradually sloped. The reinforced concrete column will be
structurally supported below by a pad foundation. Each column is to have its
own individual pad foundation where possible.
Ground Floor Build Up – DPM to be placed between hollowcore floor slabs
and ground, 200mm precast concrete hollowcore flooring slabs to be connected
back to the reinforced concrete ring beams, both in accordance with BS EN
1992-1-2:2004. 75mm structural concrete screed to be placed on top of the
hollowcore flooring slabs. 80mm Kingspan Kooltherm K3 Floorboard to be
placed on top of the structural screed, with 80mm x 40mm thimber battens @
600mm c/c to be placed in between. 18mm plywood sheeting to be placed over
the insulation and fixed back to the timber battens @ 600mm c/c. Finally the
floor is to be finished in accordance with the use of each specific room, with
22mm oak flooring to be placed in most areas and a tile finish to be placed in
the kitchen and WC areas.
Intermediate Floor Build Up – On the underside, the floor is to be finished with
a 2.5mm plaster skim, which is applied directly to 12.5mm gyproc board. This is
followed by a 25mm services gap and then 50mm rockwool insulation, in
between 25mm x 75mm timber battens @ 600mm c/c fixed back to the cross
laminated timber panels. These battens are used to support and fix the gyproc
board in place. The main structure of the floor is made up of a 200mm (5 x
40mm layers) cross laminated timber panels, which spans from one glulam
beam to another. Above this there is another layer of 50mm rockwool insulation
in between 25mm x 50mm timber battens @ 600mm c/c. Then sheets of 18mm
plywood finally finished off with a 22mm oak flooring or a tile finish depending
on the use of the room.
Roof Build Up - On the underside, the roof is to be finished with a 2.5mm
plaster skim, which is applied directly to 12.5mm gyproc board. This is followed
by a 25mm services gap and then 50mm rockwool insulation, in between 25mm
x 75mm timber battens @ 600mm c/c fixed back to the cross laminated timber
panels. These battens are used to support and fix the gyproc board in place.
The main structure of the floor is made up of a 200mm (5 x 40mm layers) cross
laminated timber panels, which spans from one glulam beam to another. Above
this a vapour barrier layer is to be added. Followed by 120mm Kingspan
Thermaroof TR31, then a 3G base layer, finished with a triple layer of built up
felt waterproofing.
External Wall Build Up – From Exterior: 8mm external lime render finish, 40mm
wood fibre combined breather membrane board, 12mm timbervent, 400mm
wheat straw bale insulation in between 400mm ‘I’ studs spaced @ 600mm c/c,
15mm OSB, 25mm services cavity in between 25mm x 50mm vertical timber
battens fixed back to the 15mm OSB, finished on the interior side with a layer of
12.5mm gyproc board and 2.5mm plaster skim finish. Each end of the straw
bale panel is closed with a 43mm x 400mm glulaminated column. This system is
from the manufacturer Modcell, it is the Modcell Core + panel. This wall panel
achieves a u-value of 0.11 W/(m2K), a fire rating of 120mins, and an acoustic
performance rating of 52db.
Internal Wall Build Up – 2.5mm plaster finish, 12.5mm gyproc board, 25mm
rockwool insulation in between 25mm x 25mm vertical timber battens spaced @
600mm c/c fixed back to the cross laminated timber panel, put in place to
support and fix the gyproc board to. Followed by 120mm (40mm x 3 layers)
cross laminated timber wall panel in accordance with BS EN 1995-2, BS EN
12354-1 and BS EN 12354-2 in terms of fire and acoustic performance, 25mm
rockwool insulation in between 25mm x 25mm vertical timber battens spaced @
600mm c/c fixed back to the cross laminated timber panel, put in place to
support and fix the gyproc board to. Finished with 12.5mm gyproc board and
2.5mm plaster skim finish.
Concrete Wall Panels – 200mm reinforced precast concrete solid wall panels
to be used in the stairs, stair lobby, lift shaft and protected corridor to provide
structural strength and achieve the required fire rating in accordance with TGD
B. the panels are also relatively soundproof so this will eliminate sound
transmission throughout the building. The internal panels will have a 25mm
service cavity in between 25mm x 50mm vertical timber battens, finished with
12.5mm gyproc board and a 2.5mm plaster skim finish, with the side inside the
lift or stairs shaft having the concrete left exposed. The panels that are exposed
to the outside will have no internal finish (concrete to be left exposed), and an
8mm lime render finish to the external face.
Door Schedule Second Floor Level
Level Mark Fire Rating Width Height
SFL 51 FD60 1810 2110
SFL 53 FD30 1010 2110
SFL 54 FD30 1010 2110
SFL 55 FD30 1010 2110
SFL 56 FD60 1810 2110
SFL 57 FD60 825 2025
SFL 58 FD30 910 2110
SFL 59 FD30 1010 2110
SFL 60 FD30 1010 2110
SFL 61 FD30 1010 2110
SFL 62 FD60 910 2110
SFL 67 FD60 1810 2110
SFL 68 FD60 1810 2110
Room Schedule Second Floor Leel
Number Name Level Area
47 Showers SFL 11 m²
48 Games Room SFL 99 m²
49 Music Room SFL 116 m²
50 Corridor SFL 6 m²
51 Stairwell SFL SFL 20 m²
52 Stairwell SFL SFL 14 m²
53 Stairwell Lobby SFL 9 m²
54 Protected Corridor SFL 10 m²
55 WC's SFL 24 m²
56 Stairwell SFL SFL 17 m²
57 Stairwell SFL SFL 15 m²
58 Stairwell Lobby SFL 5 m²
3D SFL
2
161718192122232425 13
GFL
0
FFL
3530
SFL
7030
Parapet 1
10530
15 14
Parapet 2
11000
Parapet 3
12500
Parapet
7830
Parapet 4
13000
10987 11 12
646362616059
15
67 68 69
1716 18
70 71
19 20
72 73
21 22
74 75 76
23 24 25
77
26
78 79 80
2827
60min Fire rated
Cross Laminated
Timber Panel
Roof with a
Kingspan
Thermaroof
TR31 covering
60min Fire rated
Cross Laminated
Timber Panel
Parapet wall
covered in
roofing felt
22mm Accoya
timber cladding
finish to the
exterior
60min Fire rated
Cross Laminated
Timber Panel
Roof with a
Kingspan
Thermaroof
TR31 coveringSolid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
120min Fire
Rated Straw
Bale Panel
External Wall
60min Fire rated
Cross Laminated
Timber Panel
Roof with a
Kingspan
Thermaroof
TR31 covering
22mm Accoya
timber cladding
finish to the
exterior
120min Fire
Rated Straw
Bale Panel
External Wall
Reynaers Eco
System 50
insulated and
ventilated
windows
Reynaers Eco
System 50
insulated and
ventilated
windows
Reynaers Eco
System 50
insulated and
ventilated
windows
O N M L K
GFL
0
FFL
3530
SFL
7030
Parapet 1
10530
P J
Parapet 2
11000
Parapet 3
12500
Parapet
7830
Parapet 4
13000
120
98
46
28
FD30
50
FD60
62
FD60
103
53
1
27
FD60
2
54 55 56 57 58
6543
120min Fire
Rated Straw
Bale Panel
External Wall
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
60min Fire rated
Cross Laminated
Timber Panel
Roof with a
Kingspan
Thermaroof
TR31 covering
Structural
Glulaminated
Columns 200mm
x 250mm to EN
14080
60min Fire
Rated CLT
Internal Partition
to BS EN 1995-2
120min Fire
Rated Straw
Bale Panel
External Wall
60min Fire rated
Cross Laminated
Timber Panel
Roof with a
Kingspan
Thermaroof
TR31 covering
Solid Wall
Precast
Concrete Panels
to BS EN
1992-1-2:2004
Reynaers Eco
System 50
insulated and
ventilated
windows
Reynaers Eco
System 50
insulated and
ventilated
windows
Reynaers Eco
System 50
insulated and
ventilated
windows
22mm Accoya
timber cladding
finish to the
exterior
Scale
LECTURER
Drawn by
Date
Project number
Institute of Technology Carlow
BSc. (Hons) in Architectural Technology
Year 4 2013-2014
1 : 100
Combined North & East Elevations
1
Restoration, extension and
upgradation to protected structures
13-January-2014
Edel Fox
Noel Dunne, Sujana Sudhir
& Dan O' Sullivan
NEEP1A108
General Specification
Block L
Proposed upgrade to existing external walls
Proposed - additional dry-lining board to the internal face of the existing wall,
consisting of 85mm kingspan kooltherm K17 insulated dry-linig board in between
steel U channels, with 12.5mm gypsum plasterboard with a 60minute fir rating in
accordance with BS 476, finished with a layer of 2.5mm skim.
Proposed upgrade to existing internal walls
Proposed - additional dry-linig board to both faces of the partition wall, consisting
of 50mm kingspan kolltherm K17 insulated dry-lining board in between steel U
channels, with 12.5mm gypsum plasterboard with a 60minute fire rating in
accordance with BS 476, finished with a layer of 2.5mm skim. This to be done to
both sides of the wall.
Proposed upgrade to existing floor
Proposed - remove existing harwood flooring to be repaired where possible and
if not replaced, additional 80mm kingspan Therma TF70 in between timber
battens to be added on top of existing screed. Repaired hardwood flooring to be
put back down on top of the new insulation.
Proposed upgrade to existing roof
Proposed - additional dry-lining board at internal ceiling level consisting of 85mm
kingspan kooltherm K17 insulated dry-lining board in between timber battens,
12.5mm plasterboard finished with a 2.5mm skim. The existing rubber membrane
needs to be stripped and the torch on felt repaired and the pebbles replaces, and
the drainage issues addressed.
Proposed timber stud partition
Proposed - timber stud partition wall 130mm thick, consisting of 2.5mm skim a
double laye of gypsum plasterboard with a 60minute fire rating, 75mm timber
studs with insulation in between, double layer of 12.5mm gypsum plasterboard
with a 60minute fire rating in accordance with BS 476, finished with a layer of
2.5mm skim.
Proposed upgrade to existing windows
Proposed - Upgrading to double glazed argon filled timber framed windows which
will achieve a u-value of 1.8w/m²k. Install draught proofing strips around all
windows to lower heat loss even more. Address detailing at cill to fix the water
drainage problem from occuring.
Proposed upgrade to existing internal doors
Proposed upgrading of existing doors throughout the ground floor with smoke
seals all around and covered in a layer of intumescent paint to provide a fire
resistance of 30mins.
New Extension
Structural Foundations – 540mm X 400mm reinforced concrete ring beams to
carry the load of the external and internal walls, while also allocating a space for
the hollowcore flooring to sit into. The hollowcore flooring will bear half way on to
each beam and be securely strapped back using T12 tie bars bedded in with the
screed. Each structural glulam column will be connected back to a 360mm x
360mm square reinforced concrete column. Each concrete column will vary in
depth as the ground is gradually sloped. The reinforced concrete column will be
structurally supported below by a pad foundation. Each column is to have its own
individual pad foundation where possible.
Ground Floor Build Up – DPM to be placed between hollowcore floor slabs and
ground, 200mm precast concrete hollowcore flooring slabs to be connected back
to the reinforced concrete ring beams, both in accordance with BS EN 1992-1-
2:2004. 75mm structural concrete screed to be placed on top of the hollowcore
flooring slabs. 80mm Kingspan Kooltherm K3 Floorboard to be placed on top of
the structural screed, with 80mm x 40mm thimber battens @ 600mm c/c to be
placed in between. 18mm plywood sheeting to be placed over the insulation and
fixed back to the timber battens @ 600mm c/c. Finally the floor is to be finished
in accordance with the use of each specific room, with 22mm oak flooring to be
placed in most areas and a tile finish to be placed in the kitchen and WC areas.
Intermediate Floor Build Up – On the underside, the floor is to be finished with a
2.5mm plaster skim, which is applied directly to 12.5mm gyproc board. This is
followed by a 25mm services gap and then 50mm rockwool insulation, in between
25mm x 75mm timber battens @ 600mm c/c fixed back to the cross laminated
timber panels. These battens are used to support and fix the gyproc board in
place. The main structure of the floor is made up of a 200mm (5 x 40mm layers)
cross laminated timber panels, which spans from one glulam beam to another.
Above this there is another layer of 50mm rockwool insulation in between 25mm
x 50mm timber battens @ 600mm c/c. Then sheets of 18mm plywood finally
finished off with a 22mm oak flooring or a tile finish depending on the use of the
room.
Roof Build Up - On the underside, the roof is to be finished with a 2.5mm plaster
skim, which is applied directly to 12.5mm gyproc board. This is followed by a
25mm services gap and then 50mm rockwool insulation, in between 25mm x
75mm timber battens @ 600mm c/c fixed back to the cross laminated timber
panels. These battens are used to support and fix the gyproc board in place.
The main structure of the floor is made up of a 200mm (5 x 40mm layers) cross
laminated timber panels, which spans from one glulam beam to another. Above
this a vapour barrier layer is to be added. Followed by 120mm Kingspan
Thermaroof TR31, then a 3G base layer, finished with a triple layer of built up felt
waterproofing.
External Wall Build Up – From Exterior: 8mm external lime render finish, 40mm
wood fibre combined breather membrane board, 12mm timbervent, 400mm
wheat straw bale insulation in between 400mm ‘I’ studs spaced @ 600mm c/c,
15mm OSB, 25mm services cavity in between 25mm x 50mm vertical timber
battens fixed back to the 15mm OSB, finished on the interior side with a layer of
12.5mm gyproc board and 2.5mm plaster skim finish. Each end of the straw bale
panel is closed with a 43mm x 400mm glulaminated column. This system is from
the manufacturer Modcell, it is the Modcell Core + panel. This wall panel
achieves a u-value of 0.11 W/(m2K), a fire rating of 120mins, and an acoustic
performance rating of 52db.
Internal Wall Build Up – 2.5mm plaster finish, 12.5mm gyproc board, 25mm
rockwool insulation in between 25mm x 25mm vertical timber battens spaced @
600mm c/c fixed back to the cross laminated timber panel, put in place to support
and fix the gyproc board to. Followed by 120mm (40mm x 3 layers) cross
laminated timber wall panel in accordance with BS EN 1995-2, BS EN 12354-1
and BS EN 12354-2 in terms of fire and acoustic performance, 25mm rockwool
insulation in between 25mm x 25mm vertical timber battens spaced @ 600mm
c/c fixed back to the cross laminated timber panel, put in place to support and fix
the gyproc board to. Finished with 12.5mm gyproc board and 2.5mm plaster
skim finish.
Concrete Wall Panels – 200mm reinforced precast concrete solid wall panels to
be used in the stairs, stair lobby, lift shaft and protected corridor to provide
structural strength and achieve the required fire rating in accordance with TGD B.
the panels are also relatively soundproof so this will eliminate sound transmission
throughout the building. The internal panels will have a 25mm service cavity in
between 25mm x 50mm vertical timber battens, finished with 12.5mm gyproc
board and a 2.5mm plaster skim finish, with the side inside the lift or stairs shaft
having the concrete left exposed. The panels that are exposed to the outside will
have no internal finish (concrete to be left exposed), and an 8mm lime render
finish to the external face.
Windows and door Specifications
Reynaers ecosystem CS 86-HI
CS 86-HI is a multi-chamber system for windows and doors that combines aesthetic
design, optimal stability and high thermal comfort. Due to the insulating skeleton
strips, CS 86-HI achieves Uf-values down to 1.2 W/m²K, making this a highly energy
efficient system. Flexible expansion strips in the door vents ensure stability in all
conditions.
Minimum visable width inward opening window:
Frame 51mm / Vent 35mm
Minimum visable width outward opening flush door:
Frame 42mm / Vent 102mm
Thermal insulation in accordance with EN 10077-2: Achieves U-value of 1.2 W/m²K
Burglar resistance: WK 2 in accordance with EnV 1627 – ENV 1630
Curtain Walling Specifications
Curtain Wall CW 50
• Manufacturer: Reynaers Ltd
• Product reference: Curtain Wall CW 50 Standard
/Curtain Wall CW 50-FP EW 30
/Curtain Wall CW 50-FP EW 60 /Curtain Wall CW
50- HL /Curtain Wall CW 50-RA
• Internal framing member: Extruded aluminium
- Finish: Anodized /Polyester powder coated
- Colour:
- Minimum film thickness:
• External cover cap: Extruded aluminium
- Finish: Anodized /Polyester powder coated
- Colour:
- Minimum film thickness:
• Doors:
• Windows: Fixed light (CW50-FP) /Glazed in windows
/Structural glazing
- Configuration: Horizontal pivot /Parallel opener
/Side hung /Tilt and turn /Top hung
• Glazing: Insulating glass units /Single glazed panes
• Glazing system: Dry glazed gasket
• Panel/ Facing type:
External Render
Lime Render
Render mix - 3.5 NHL : Moderate to eminently hydraulic
Binder sand ratio
1: 1.5 to 1:3 depending on the support and backround conditions
and the fineness of the sand.
Sand grading: Sharp and Gritty 3-4mm down to 75 mirons
Scratch coat - 3-5 mm, Ratio: 1 volume of NHL 4.5 to 1.5
volumes of sand
Undercoat - 15-20mm, Ratio: 1 volume of NHL 3.5 to 2 volumes
of sand (at this dosage consumption 0.35kg of NHL 3.5m2 per
each mm of thickness)
Finish coat 5-10mm, Ratio 1 volume of NHL 3.5 to 2.5 volumes
of sand
Caution: No water barriers should be added to the wall as lime
render works in conjunction with the breathability of the wall
Timber Cladding
Accoya by Accys Technologies
Accoya wood is made from softwood but has the qualities of
hardwood, produced via a process called acetylation. Acetylation
transforms the free hydroxyls in the wood into acetyl groups,
reducing the wood’s ability to absorb water, making it more
dimensionally stable and more durable.
Manufacturer Accys Technologies
Type of cladding Horizontal and vertical
Wood species Softwood, for example Radiata pine
Treatment Acetylation
Life expectancy 50 years
Maintenance Low frequency due to increased dimensional
stability as coatings do not stretch and shrink
Certification FSC, PEFC certified and cradle-tocradle gold
standard
Recyclability Can be reused or used as a biofuel to produce
heat and power
1 : 100
North Elevation
1
1 : 100
East Elevation
2
Restoration, extension and upgradation of protected structures
Restoration, extension and upgradation of protected structures
Restoration, extension and upgradation of protected structures
Restoration, extension and upgradation of protected structures
Restoration, extension and upgradation of protected structures
Restoration, extension and upgradation of protected structures
Restoration, extension and upgradation of protected structures
Restoration, extension and upgradation of protected structures
Restoration, extension and upgradation of protected structures
Restoration, extension and upgradation of protected structures
Restoration, extension and upgradation of protected structures

Contenu connexe

Tendances

Tendances (20)

high rise case study
high rise case studyhigh rise case study
high rise case study
 
Building Services | Waste management and disposal - 2020
Building Services | Waste management and disposal - 2020Building Services | Waste management and disposal - 2020
Building Services | Waste management and disposal - 2020
 
Gfrc
GfrcGfrc
Gfrc
 
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHEREPREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
PREFABRICATED CONSTRUCTION CASE STUDY: THE HEMISPHERE
 
Acp and glazing
Acp and glazingAcp and glazing
Acp and glazing
 
M3 EG BQ metal frame door
M3 EG BQ metal frame doorM3 EG BQ metal frame door
M3 EG BQ metal frame door
 
Steel & Construction
Steel & ConstructionSteel & Construction
Steel & Construction
 
Auditorium Design (Case Study)
Auditorium Design (Case Study)Auditorium Design (Case Study)
Auditorium Design (Case Study)
 
Curtain wall system
Curtain wall systemCurtain wall system
Curtain wall system
 
M3 EG BQ for timber roof covering
M3 EG BQ for timber roof  coveringM3 EG BQ for timber roof  covering
M3 EG BQ for timber roof covering
 
Stick framing system with glazing
Stick framing system with glazingStick framing system with glazing
Stick framing system with glazing
 
Glass Murals
Glass MuralsGlass Murals
Glass Murals
 
Bechtler Museum Construction
Bechtler Museum ConstructionBechtler Museum Construction
Bechtler Museum Construction
 
Presentation Design Drawing for Architectural Drawing
Presentation Design Drawing for Architectural DrawingPresentation Design Drawing for Architectural Drawing
Presentation Design Drawing for Architectural Drawing
 
ceiling note
ceiling noteceiling note
ceiling note
 
Structural glazing details
Structural glazing detailsStructural glazing details
Structural glazing details
 
CASE STUDY F/o FINE ARTS JAMIA DELHI
CASE STUDY F/o FINE ARTS JAMIA DELHICASE STUDY F/o FINE ARTS JAMIA DELHI
CASE STUDY F/o FINE ARTS JAMIA DELHI
 
Compiled report
Compiled reportCompiled report
Compiled report
 
Smart High Performanc Facades
Smart High Performanc FacadesSmart High Performanc Facades
Smart High Performanc Facades
 
One world trade centre
One world trade centreOne world trade centre
One world trade centre
 

En vedette

School Buildings of the Future
School Buildings of the FutureSchool Buildings of the Future
School Buildings of the FutureEdel Fox
 
Novel medical therapy
Novel medical therapyNovel medical therapy
Novel medical therapydrucsamal
 
Leading the Transformation: Changing the Dialogue
Leading the Transformation: Changing the DialogueLeading the Transformation: Changing the Dialogue
Leading the Transformation: Changing the DialogueBen Ponne
 
Team Building in Sydney's Wonderland with Beyond the Boardroom
Team Building in Sydney's Wonderland with Beyond the BoardroomTeam Building in Sydney's Wonderland with Beyond the Boardroom
Team Building in Sydney's Wonderland with Beyond the Boardroomsteve dalton
 
I P L Business Model
I P L  Business  ModelI P L  Business  Model
I P L Business Modelanuragswain
 
Drc semana06 medios de transmisión no guiados
Drc semana06 medios de transmisión no guiadosDrc semana06 medios de transmisión no guiados
Drc semana06 medios de transmisión no guiadosJorge Pariasca
 
Competitive Strategy - A Study About Electric Guitar Pedals Market
Competitive Strategy - A Study About Electric Guitar Pedals MarketCompetitive Strategy - A Study About Electric Guitar Pedals Market
Competitive Strategy - A Study About Electric Guitar Pedals MarketSteven Truffley
 
Tema 04 seleccion multiple
Tema 04 seleccion multipleTema 04 seleccion multiple
Tema 04 seleccion multipleJorge Pariasca
 
SFO15-200: Linux kernel generic TEE driver
SFO15-200: Linux kernel generic TEE driverSFO15-200: Linux kernel generic TEE driver
SFO15-200: Linux kernel generic TEE driverLinaro
 

En vedette (16)

School Buildings of the Future
School Buildings of the FutureSchool Buildings of the Future
School Buildings of the Future
 
iqiic.pdf
iqiic.pdfiqiic.pdf
iqiic.pdf
 
Drc semana08 osi
Drc semana08 osiDrc semana08 osi
Drc semana08 osi
 
Novel medical therapy
Novel medical therapyNovel medical therapy
Novel medical therapy
 
Leading the Transformation: Changing the Dialogue
Leading the Transformation: Changing the DialogueLeading the Transformation: Changing the Dialogue
Leading the Transformation: Changing the Dialogue
 
resume 2015
resume 2015resume 2015
resume 2015
 
Expo materia virtual
Expo materia virtualExpo materia virtual
Expo materia virtual
 
Guia de inicio
Guia de inicioGuia de inicio
Guia de inicio
 
Team Building in Sydney's Wonderland with Beyond the Boardroom
Team Building in Sydney's Wonderland with Beyond the BoardroomTeam Building in Sydney's Wonderland with Beyond the Boardroom
Team Building in Sydney's Wonderland with Beyond the Boardroom
 
I P L Business Model
I P L  Business  ModelI P L  Business  Model
I P L Business Model
 
Obra de teatro daniel
Obra de teatro danielObra de teatro daniel
Obra de teatro daniel
 
Drc semana06 medios de transmisión no guiados
Drc semana06 medios de transmisión no guiadosDrc semana06 medios de transmisión no guiados
Drc semana06 medios de transmisión no guiados
 
Competitive Strategy - A Study About Electric Guitar Pedals Market
Competitive Strategy - A Study About Electric Guitar Pedals MarketCompetitive Strategy - A Study About Electric Guitar Pedals Market
Competitive Strategy - A Study About Electric Guitar Pedals Market
 
Tema 04 seleccion multiple
Tema 04 seleccion multipleTema 04 seleccion multiple
Tema 04 seleccion multiple
 
SFO15-200: Linux kernel generic TEE driver
SFO15-200: Linux kernel generic TEE driverSFO15-200: Linux kernel generic TEE driver
SFO15-200: Linux kernel generic TEE driver
 
Itc fortune brand
Itc fortune brandItc fortune brand
Itc fortune brand
 

Similaire à Restoration, extension and upgradation of protected structures

Mill 14-1-15 - Sheet - A101 - GROUND FLOOR PLANS
Mill 14-1-15 - Sheet - A101 - GROUND FLOOR PLANSMill 14-1-15 - Sheet - A101 - GROUND FLOOR PLANS
Mill 14-1-15 - Sheet - A101 - GROUND FLOOR PLANSSin Byrne
 
Mill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONS
Mill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONSMill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONS
Mill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONSSin Byrne
 
Mill 14-1-15 - Sheet - A118 - 3D SECTIONS
Mill 14-1-15 - Sheet - A118 - 3D SECTIONSMill 14-1-15 - Sheet - A118 - 3D SECTIONS
Mill 14-1-15 - Sheet - A118 - 3D SECTIONSSin Byrne
 
Mill 14-1-15 - Sheet - A111 - PROPOSED PLAN DETAILS
Mill 14-1-15 - Sheet - A111 - PROPOSED PLAN DETAILSMill 14-1-15 - Sheet - A111 - PROPOSED PLAN DETAILS
Mill 14-1-15 - Sheet - A111 - PROPOSED PLAN DETAILSSin Byrne
 
Tutor l1 the house
Tutor l1 the houseTutor l1 the house
Tutor l1 the houseLuke D'Arcy
 
Der bindley 200 dpi_03-01-10
Der bindley 200 dpi_03-01-10Der bindley 200 dpi_03-01-10
Der bindley 200 dpi_03-01-10SmarterHomeGuide
 
Everhaus catalogue
Everhaus catalogueEverhaus catalogue
Everhaus catalogueMatis Velt
 
House Messinger Proposal 2-Sections & Elevations
House Messinger Proposal 2-Sections & ElevationsHouse Messinger Proposal 2-Sections & Elevations
House Messinger Proposal 2-Sections & ElevationsAyla Damon
 
Visual Dictionary Revised 2
Visual Dictionary Revised 2Visual Dictionary Revised 2
Visual Dictionary Revised 2siding
 
false ceiling ppt.pptx
false ceiling ppt.pptxfalse ceiling ppt.pptx
false ceiling ppt.pptxSAKSHIVASWANI3
 
Visual Dictionary- Sp10Crawlspace
Visual Dictionary- Sp10CrawlspaceVisual Dictionary- Sp10Crawlspace
Visual Dictionary- Sp10CrawlspaceSp10Crawlspace
 
Visual Dictionary 1 of 2
Visual Dictionary 1 of 2Visual Dictionary 1 of 2
Visual Dictionary 1 of 2spandrel
 
Lesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxLesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxsydneyaugust1
 
Joist Visual Dictionary 3
Joist Visual Dictionary 3Joist Visual Dictionary 3
Joist Visual Dictionary 3joist
 

Similaire à Restoration, extension and upgradation of protected structures (20)

Mill 14-1-15 - Sheet - A101 - GROUND FLOOR PLANS
Mill 14-1-15 - Sheet - A101 - GROUND FLOOR PLANSMill 14-1-15 - Sheet - A101 - GROUND FLOOR PLANS
Mill 14-1-15 - Sheet - A101 - GROUND FLOOR PLANS
 
Mill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONS
Mill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONSMill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONS
Mill 14-1-15 - Sheet - A107 - PROPOSED EAST & SOUTH ELEVATIONS
 
Mill 14-1-15 - Sheet - A118 - 3D SECTIONS
Mill 14-1-15 - Sheet - A118 - 3D SECTIONSMill 14-1-15 - Sheet - A118 - 3D SECTIONS
Mill 14-1-15 - Sheet - A118 - 3D SECTIONS
 
Mill 14-1-15 - Sheet - A111 - PROPOSED PLAN DETAILS
Mill 14-1-15 - Sheet - A111 - PROPOSED PLAN DETAILSMill 14-1-15 - Sheet - A111 - PROPOSED PLAN DETAILS
Mill 14-1-15 - Sheet - A111 - PROPOSED PLAN DETAILS
 
final dcc
final dccfinal dcc
final dcc
 
Tutor l1 the house
Tutor l1 the houseTutor l1 the house
Tutor l1 the house
 
the house
 the house the house
the house
 
all sheets
all sheetsall sheets
all sheets
 
Der bindley 200 dpi_03-01-10
Der bindley 200 dpi_03-01-10Der bindley 200 dpi_03-01-10
Der bindley 200 dpi_03-01-10
 
Everhaus catalogue
Everhaus catalogueEverhaus catalogue
Everhaus catalogue
 
House Messinger Proposal 2-Sections & Elevations
House Messinger Proposal 2-Sections & ElevationsHouse Messinger Proposal 2-Sections & Elevations
House Messinger Proposal 2-Sections & Elevations
 
Air bricks
Air bricksAir bricks
Air bricks
 
Visual Dictionary Revised 2
Visual Dictionary Revised 2Visual Dictionary Revised 2
Visual Dictionary Revised 2
 
false ceiling ppt.pptx
false ceiling ppt.pptxfalse ceiling ppt.pptx
false ceiling ppt.pptx
 
Visual Dictionary- Sp10Crawlspace
Visual Dictionary- Sp10CrawlspaceVisual Dictionary- Sp10Crawlspace
Visual Dictionary- Sp10Crawlspace
 
Visual Dictionary 1 of 2
Visual Dictionary 1 of 2Visual Dictionary 1 of 2
Visual Dictionary 1 of 2
 
Lesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxLesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptx
 
Sp10Crawlspace
Sp10CrawlspaceSp10Crawlspace
Sp10Crawlspace
 
Full PORTFOLIO 5
Full PORTFOLIO 5Full PORTFOLIO 5
Full PORTFOLIO 5
 
Joist Visual Dictionary 3
Joist Visual Dictionary 3Joist Visual Dictionary 3
Joist Visual Dictionary 3
 

Restoration, extension and upgradation of protected structures

  • 1. UP UP DN DN UP DN D C B A 5 6 7 8 9 10 11 12 13 14 18 49 m² 531.3 SF Classroom One 1 39 m² 414.8 SF Classroom Two 2 39 m² 414.8 SF Classroom Three 3 66 m² 713.5 SF Classroom Four 4 42 m² 455.0 SF Corridor 5 20 m² 216.7 SF Stairs 6 1842 3350 3350 3350 3350 3350 3350 3350 3350 1842 312520756215 5 SSP1A103 6 SSP1A103 Existing terrazzo finish to staircase and corridor Existing external steel fire escape staircase Existing external steel fire escape staircase Existing Terrazzo finish to corridor Existing Terrazzo finish to corridor Existing Parquet flooring to classroom Existing Parquet flooring to classroom Existing Parquet flooring to classroom Existing Parquet flooring to classroom D C B A 5 6 7 8 9 10 11 12 13 14 18 207 m² 2228.1 SF Classroom Five 7 30 m² 323.3 SF Corridor 8 20 m² 213.2 SF Stairs 9 1842 3350 3350 3350 3350 3350 3350 3350 3350 1842 312520756215 5 SSP1A103 6 SSP1A103 Existing external steel fire escape staircase Existing external steel fire escape staircase Existing terrazzo finish to staircase and corridor Existing Parquet flooring to corridor Existing Parquet flooring to classroom Existing Parquet flooring to classroom D C B A 5 6 7 8 9 10 11 12 13 14 18 8 m² 87.7 SF Corridor 10 20 m² 213.2 SF Stairs 11 120 m² 1296.2 SF Music oom 12 111 m² 1194.7 SF Games Room 13 1842 3350 3350 3350 3350 3350 3350 3350 3350 1842 312520756215 5 SSP1A103 6 SSP1A103 Existing terrazzo finish to staircase and corridor Existing floor finish to date is paint applied directly to the existing concrete screed No floor finish existing within the corridor, currently the existing concrete screed has been left exposed No floor finish existing within the gamers room, currently the existing concrete screed has been left exposed Existing external steel fire escape staircase Existing external steel fire escape staircase 15 100300 400 300 270 18 102 50 102 70 1010 30150 30150 260 102 50 102 18 Scale LECTURER Drawn by Date Project number Institute of Technology Carlow BSc. (Hons) in Architectural Technology Year 4 2013-2014 As indicated Block L Survey Sheet 1 Restoration, extension and upgradation to protected structures 13-January-2014 Edel Fox Noel Dunne, Sujana Sudhir, & Dan O' Sullivan SSP1A102 1 : 100 GFL Existing 1 1 : 100 FFL Existing 2 1 : 100 SFL Existing 3 Room Schedule Existing Number Name Level Area Count 7 Classroom Five FFL 207 m² 1 8 Corridor FFL 30 m² 1 10 Corridor SFL 8 m² 1 11 Stairs SFL 20 m² 1 12 Music oom SFL 120 m² 1 13 Games Room SFL 111 m² 1 9 Stairs FFL 20 m² 1 Room Schedule Existing Number Name Level Area Count 1 Classroom One GFL 49 m² 1 2 Classroom Two GFL 39 m² 1 3 Classroom Three GFL 39 m² 1 4 Classroom Four GFL 66 m² 1 5 Corridor GFL 42 m² 1 6 Stairs GFL 20 m² 1 General Specification 1 : 10 Existing Column 4 1 : 10 Existing Wall 5 1 : 10 Existing Roof 6 1 : 10 Existing Floor 7 1 : 10 Existing Iternal Wall 8 1 : 10 Existing Window 9 Current Condition Proposed Alterations Assumed existing external leaf 102mm concrete bricks, then a 50mm cavity, then an internal leaf of 102mm concrete blocks, finished with a layer of 18mm plaster. Existing external brickwork is stained from water damage due to poor drainage on the east face, but other than this the walls are in relatively good condition. Proposed - additional dry-lining board to the internal face of the existing wall, consisting of 85mm kingspan kooltherm K17 insulated dry-linig board in between steel U channels, with 12.5mm plasterboard, finished with a layer of 2.5mm skim. Assumed existing solid 260mm blockwork internal partition wall. These walls have not been finished with a layer of plaster they blockwork has just been painted. Existing solid blockwork internal walls are unfinished ie. the blockwork has just been painted. They are in relatively good condition as they have not been exposed to the elements. Proposed - additional dry- linig board to both faces of the partition wall, consisting of 50mm kingspan kolltherm K17 insulated dry-lining board in between steel U channels, with 12.5mm plasterboard, finished with a layer of 2.5mm skim. This to be done to both sides of the wall. Assumed existing 150mm concrete slab with 30mm concrete screed, with 10mm torch on felt, then a rubber membrane, finished with a layer of 150mm pebbles. Existing roof is in relatively bad condition as can be seen from the underside of the roof there is alot of water damage and the roof is not insulated so there is major condensation issues that need to be addressed. Proposed - additional dry- lining board at internal ceiling level consisting of 85mm kingspan kooltherm K17 insulated dry-lining board in between timber battens, 12.5mm plasterboard finished with a 2.5mm skim. The existing rubber membrane needs to be stripped and the torch on felt repaired and the pebbles replaces, and the drainage issues addressed. Assumed existing 150mm concrete floor slab, with 30mm concrete screed, topped with either 22mm Parquet flooring or terazzo flooring. Existing floor in relatively good condition structurally but in terms of thermal performance there is room for sufficient improvement. The parquet and terrazzo flooring is quiet sufficiently dammaged and will need to be repaired where possible and if not replaced. Proposed - remove existing harwood flooring to be repaired where possible and if not replaced, additional 80mm kingspan Therma TF70 in between timber battens to be added on top of existing screed. Repaired hardwood flooring to be put back down on top of the new insulation. Assumed existing timber framed, single glazed pivot windows currently achieveing a u- value of 4.8w/m²k Existing windows are old, in relatively bad condition and rotting in places. Window cills are recessed allowing water to sit and not drain correctly. This poor water drainage is causing water damage and the timber frames to rot. Glass in some of the windows is cracked or damaged. Proposed - Upgrading to double glazed argon filled timber framed windows which will achieve a u-value of 1.8w/m²k. Install draught proofing strips around all windows to lower heat loss even more. Address detailing at cill to fix the water drainage problem from occuring. Conservation Principles to be followed: Keeping a building in use – Is generally seen as the best way to keep the building up to a good standard. If a change of use must occur, minimum damage must be made to the original character of the building. Researching and analysing – Much research must be done on the history, the fabric and the current condition of the building before any proposals for works can be made. Using expert conservation advice – expert advice should be sought throughout the planning process and the construction process to ensure that the works are completed correctly. Protecting the special interest – Inappropriate works can damage the character and special interest of a building, so special care must be taken to ensure this does not happen. Promoting minimum intervention – “do as much as necessary and as little as possible”. Respecting earlier alterations of interest – Earlier alterations can be an insight into past construction techniques and must be respected. They are irreplaceable. Repairing rather than replacing – the main aim should be to repair rather than replace because to get the same quality of materials now is next to impossible and most of the materials were made by hand. Promoting honesty of repairs and alterations – materials used in replacement should not be artificially aged; this will add confusion in the future as to when the alterations were made. Using appropriate materials and methods – appropriate materials must be used during restoration as in past examples certain materials accelerated the decay. Ensuring reversibility of alterations – by ensuring reversibility of alterations in the future this can allow a quick fix to unforeseen problems caused by earlier restorations. Avoid incremental damage – major thought must be given by the planning authority to the impact of minor works to the character of protected structures. Discouraging the use of architectural salvage from other buildings – the re-use of architectural features can confuse the understanding and appreciation of a building, and promoting architectural salvage can cause a market for these materials and promotes dismantling of other old buildings. Assumed existing reinforced concrete column with a 300mm external face that steps back 100mm and has 15mm insets on both sides. The internal face is 270mm in width. The column has an overall depth of 400mm. Existing reinforced concrete columns and beams are in relatively good condition but there are cracks in certain places throughout the building. There is also evidence of water staining damage on the face of the concrete beams and columns. Proposed - Fix all the cracks in the structural columns and beams. Additional insulation to the inner face of the column in line with the additional insulation to the wall. 25mm kingspan kooltherm K17 insulated dry-lining board in between steel U channels, with 12.5mm plasterboard, finished with a layer of 2.5mm skim.
  • 2. GFL 0 FFL 3530 SFL 7030 Parapet 10530 56789101112131418 Existing reinforced concrete beams Existing reinforced concrete columns Existing steel fire escape staircase Existing brick wall infill between reinforced concrete columns Existing concrete parapet capping topped with possibly an aluminium flashing Existing timber framed single glazed windows Existing steel fire escape staircase GFL 0 FFL 3530 SFL 7030 Parapet 10530 5 6 7 8 9 10 11 12 13 14 18 Existing reinforced concrete beams Existing reinforced concrete columns Existing steel fire escape staircase Existing brick wall infill between reinforced concrete columns Existing concrete parapet capping topped with possibly an aluminium flashing Existing timber framed single glazed windows Existing steel fire escape staircase GFL 0 FFL 3530 SFL 7030 Parapet 10530 D C B A Existing concrete parapet capping topped with possibly an aluminium flashing Existing reinforced concrete columns Existing reinforced concrete beams Existing fire escape doors that lead out onto the fire escape Existing steel fire escape staircase Existing timber framed single glazed windows Existing front entrance doorway, timber framed single glazed door GFL 0 FFL 3530 SFL 7030 Parapet 10530 DCBA Existing concrete parapet capping topped with possibly an aluminium flashing Existing reinforced concrete columns Existing reinforced concrete beams Existing fire escape doors that lead out onto the fire escape Existing steel fire escape staircase Existing timber framed single glazed windows GFL 0 FFL 3530 SFL 7030 Parapet 10530 5 6 7 8 9 10 11 12 13 14 18 Existing steel fire escape staircase Existing steel fire escape staircase Existing reinforced concrete beams Existing reinforced concrete column Existing timber framed single glazed window Existing concrete parapet capping topped with possibly an aluminium flashing GFL 0 FFL 3530 SFL 7030 Parapet 10530 DCBA Existing concrete parapet capping topped with possibly an aluminium flashing Existing reinforced concrete beams Existing internal partition wall Existing concrete staircase with a terrazzo finish Existing reinforced concrete column Existing timber framed single glazed window Scale LECTURER Drawn by Date Project number Institute of Technology Carlow BSc. (Hons) in Architectural Technology Year 4 2013-2014 As indicated Block L Survey Sheet 1 Restoration, extension and upgradation to protected structures 13-January-2014 Edel Fox Noel Dunne, Sujana Sudhir, & Dan O' Sullivan SSP1A103 1 : 100 North Elevation as Existing 1 1 : 100 South Elevation as Existing 2 1 : 100 East Elevation as Existing 3 1 : 100 West Elevation as Existing 4 1 : 100 Long Section A-A 5 1 : 100 Short Section A-A 6 1 : 1 Key Plan 7 Conservation Principles to be followed: Keeping a building in use – Is generally seen as the best way to keep the building up to a good standard. If a change of use must occur, minimum damage must be made to the original character of the building. Researching and analysing – Much research must be done on the history, the fabric and the current condition of the building before any proposals for works can be made. Using expert conservation advice – expert advice should be sought throughout the planning process and the construction process to ensure that the works are completed correctly. Protecting the special interest – Inappropriate works can damage the character and special interest of a building, so special care must be taken to ensure this does not happen. Promoting minimum intervention – “do as much as necessary and as little as possible”. Respecting earlier alterations of interest – Earlier alterations can be an insight into past construction techniques and must be respected. They are irreplaceable. Repairing rather than replacing – the main aim should be to repair rather than replace because to get the same quality of materials now is next to impossible and most of the materials were made by hand. Promoting honesty of repairs and alterations – materials used in replacement should not be artificially aged; this will add confusion in the future as to when the alterations were made. Using appropriate materials and methods – appropriate materials must be used during restoration as in past examples certain materials accelerated the decay. Ensuring reversibility of alterations – by ensuring reversibility of alterations in the future this can allow a quick fix to unforeseen problems caused by earlier restorations. Avoid incremental damage – major thought must be given by the planning authority to the impact of minor works to the character of protected structures. Discouraging the use of architectural salvage from other buildings – the re-use of architectural features can confuse the understanding and appreciation of a building, and promoting architectural salvage can cause a market for these materials and promotes dismantling of other old buildings.
  • 3. UP UP DN DN UP DN D C B A 5 6 7 8 9 10 11 12 13 14 18 Proposed ramp to accomodate level change between corridor and classroom after insulation has been added to the floor in accordance with the conservation principles ensuring reversability of alterations. Proposed ramp to accomodate level change between corridor and classroom after insulation has been added to the floor in accordance with the conservation principle ensuring reversability of alterations. Proposed timber stud partition wall 130mm thick, consisting of 2.5mm skim a double laye of gypsum plasterboard with a 60minute fire rating, 75mm timber studs with insulation in between, double layer of 12.5mm gypsum plasterboard with a 60minute fire rating in accordance with BS 476, finished with a layer of 2.5mm skim in accordance with the conservation principle ensuring reversability of alterations. Proposed new external fire exit to accomodate a safe exit from the building in case of fire in accordance with conservation principle promoting minimum intervention Proposed new alternative steel fire escape staircase to replace the existing staircase in accordance with the conservation principle ensuring reversability of alterations Proposed new alternative steel fire escape staircase to replace to existing staircase in accordance with the conservation principle ensuring reversability of alterations Proposed 2000mm clear width corridor to allow access to all classrooms for disableds users, after the isulation has been added to the existing floor and the floor level within the classrooms has been raised. the corridor must be a minimum of 2000mm to accomodate the amount of traffic that will pass through the area on a daily basis in accordance with conservation principle promoting minimum intervention Proposed all windows to be upgraded to double glazed argon filled timber framed windows. Proposed draught proofing strips to be added around all windows and the detailing at cill level is to be addressed. Materials must not be artificially aged in terms of the conservation principle promoting honesty of repairs and in terms of not changing the apperance of the building Existing section of this wall is proposed to be demolisehed to allow access for the new corridor in accordance with conservation principle promoting minimum intervention Proposed upgrading of existing doors throughout the ground floor with smoke seals all around and covered in a layer of intumescent paint to provide a fire resistance of 30mins in accordance with conservation principle promoting minimum intervention Proposed access ramp to main entrance at a gradient of 1:12 in accordance with TGD M and the conservation principles in terms of ensuring reversability of alterations. D C B A 5 6 7 8 9 10 11 12 13 14 18 Proposed new alternative steel fire escape staircase to replace to existing staircase in accordance with the conservation principle ensuring reversability of alterations Proposed new alternative steel fire escape staircase to replace to existing staircase in accordance with the conservation principle ensuring reversability of alterations Proposed all windows to be upgraded to double glazed argon filled timber framed windows. Proposed draught proofing strips to be added around all windows and the detailing at cill level is to be addressed. Materials must not be artificially aged in terms of the conservation principle promoting honesty of repairs and in terms of not changing the apperance of the building Existing terrazzo covered staircase is in accordance with current TGD M Building Regulations Proposed new 30minute fire rated folding partition alternative walls to replace existing folding partition walls, to be in compliance with TGD B in accordance with the conservation principle ensuring reversability of alterations Proposed ramp to accomodate level change between corridor and classroom after insulation has been added to the floor in accordance with the conservation principle ensuring reversability of alterations Proposed ramp to accomodate level change between corridor and classroom after insulation has been added to the floor in accordance with the conservation principle ensuring reversability of alterations Proposed parquet flooring to be repaired were possible and relaid and if not possible to be replaced after the insulation has been added to the floor in accordance with conservation principle repairing rather than replacing D C B A 5 6 7 8 9 10 11 12 13 14 18 Proposed new alternative steel fire escape staircase to replace to existing staircase in accordance with conservation principle reversability of alterations Proposed new alternative steel fire escape staircase to replace to existing staircase in accordance with conservation principle reversability of alterations Proposed all windows to be upgraded to double glazed argon filled timber framed windows. Proposed draught proofing strips to be added around all windows and the detailing at cill level is to be addressed. Existing terrazzo covered staircase is in accordance with current TGD M Building Regulations Assumed position of existing shower rooms Proposed demolishment of existing corridor walls as adequate space was no provided for wheelchair users in accordance with TGD M in accordance with the conservation principle promoting minimum intervention Proposed demolishment of existing internal doors for wider more sufficient alternatives in accordance with TGD M Proposed upgrade of existing fire escape doors to 60minute fire escape doors in accordane with TGD B Proposed upgrade of existing fire escape doors to 60minute fire escape doors in accordane with TGD B Proposed upgrade of existing doors to 30minute fire resistant doors with smoke seals all around the edges and a leayer of intumescent paint to be added in accordance with the conservation principle promoting minimum intervention Proposed new corridor a minimum width of 2000mm to allow sufficient access for disabled access and to allow sufficient room for the foot traffic that will pass through the building in accordance with TGD M Proposed upgrade to existing walls with an additional dry-lining board to both faces of the partition wall, consisting of 50mm kingspan kolltherm K17 insulated dry-lining board in between steel U channels, with 12.5mm gypsum plasterboard with a 60minute fire rating in accordance with BS 476, finished with a layer of 2.5mm skim. This to be done to both sides of the wall, in accordance with the conservation principle ensuring reversability of alterations Proposed ramp to accomodate level change between corridor and classroom after insulation has been added to the floor in accordance with the conservation principle ensuring reversability of alterations Proposed ramp to accomodate level change between corridor and classroom after insulation has been added to the floor in accordance with the conservation principle ensuring reversability of alterations Proposed addition of Parquet flooring to be added after insulation has been added to the floor to keep in character with the rest of the building in accordance with the conservation principle protecting the special interest Proposed addition of Parquet flooring to be added after insulation has been added to the floor to keep in character with the rest of the building in accordance with the conservation principle protecting the special interest Proposed addition of Parquet flooring to be added after insulation has been added to the floor to keep in character with the rest of the building in accordance with the conservation principle protecting the special interest GFL 0 FFL 3530 SFL 7030 Parapet 10530 DCBA Existing concrete parapet capping topped with lead, proposed to be repaired if neccesary and resealed in accordance with the conservation principle repairing rather than replacing Existing terrazzo covered staircase is in accordance with current TGD M Building Regulations Proposed upgrading of existing doors throughout the ground floor with smoke seals all around and covered in a layer of intumescent paint to provide a fire resistance of 30mins in accordance with the conservation principle promoting minimum intervention Proposed - Upgrading to double glazed argon filled timber framed windows which will achieve a u-value of 1.8w/m²k. Install draught proofing strips around all windows to lower heat loss even more. Materials must not be artificially aged in terms of the conservation principle promoting honesty of repairs and in terms of not changing the apperance of the building Proposed - remove existing harwood flooring to be repaired where possible and if not replaced, additional 80mm kingspan Therma TF70 in between timber battens to be added on top of existing screed. Repaired hardwood flooring to be put back down on top of the new insulation in accordance with the conservtion principle ensuring reversability of alterations Proposed - timber stud partition wall 130mm thick, consisting of 2.5mm skim a double laye of gypsum plasterboard with a 60minute fire rating, 75mm timber studs with insulation in between, double layer of 12.5mm gypsum plasterboard with a 60minute fire rating in accordance with BS 476, finished with a layer of 2.5mm skim in accordance with the conservtion principle ensuring reversability of alterations Proposed - additional dry-lining board at internal ceiling level consisting of 85mm kingspan kooltherm K17 insulated dry-lining board in between timber battens, 12.5mm plasterboard finished with a 2.5mm skim. The existing rubber membrane needs to be stripped and the torch on felt repaired and the pebbles replaces, and the drainage issues addressed in accordance with the conservtion principle ensuring reversability of alterations Proposed new bathroom layout with accessible disabled WC in accordance with TGD M and in accordance with the conservation principle promoting minimum intervention Proposed 2000mm clear width corridor in accordance with the conservation principle promoting minimum intervention 312540530954053005 Assumed existing floor build up of block l 80mm x 40mm timber battens fixed to the existing floor @ 60mm c/c creating a frame that can be easily removed in accordance with the conservation principle ensuring reversability of alterations 80mm Kingspan Therma TF70 in between timber battens 18mm Plywood sheeting put in place to fix the flooring to Repaired paraquet flooring replaced after installation of additional insulation in accordance with the conservation principle repair rather than replace 85mm x 40mm Vertical steel U channels fixed to the existing wall @ 600mm c/c creating a frame that can be easily removed in accordance with the conservation principle ensuring reversability of alterations Existing external wall of block l 85mm Kingspan kooltherm K17 insulated dry-lining board in between steel U channels 12.5mm Gyproc board finished with a layer of 2.5mm plaster skim Walling alterations Proposed - additional dry-lining board to the internal face of the existing wall, consisting of 85mm kingspan kooltherm K17 insulated dry-linig board in between steel U channels, with 12.5mm gypsum plasterboard with a 60minute fir rating in accordance with BS 476, finished with a layer of 2.5mm skim. Steel U channels to be used as a base frame for the proposed alterations, with limited fixings along the horizontal steel U channels to limit the amount of damage to the original structure as possible in accordance with the conservation principle ensuring reversibility of alterations. Flooring alterations Proposed - remove existing harwood flooring to be repaired where possible and if not replaced, additional 80mm kingspan Therma TF70 in between timber battens to be added on top of existing screed. Repaired hardwood flooring to be put back down on top of the new insulation. Timber battens to be used as a base frame for the proposed alterations, with limited fixings so to create the least amount of damage to the original structure as possible in accordance with the conservtion principle ensuring reversability of alterations. Scale LECTURER Drawn by Date Project number Institute of Technology Carlow BSc. (Hons) in Architectural Technology Year 4 2013-2014 As indicated Conservation Sheet 1 Restoration, extension and upgradation to protected structures 13-January-2014 Edel Fox Noel Dunne, Sujana Sudhir & Dan O' Sulivan CSP1A104 1 : 100 Ground Floor Level Proposed Conservation 1 1 : 100 First Floor Level Proposed Conservation 2 1 : 100 Second Floor Level Proposed Conservation 3 Conservation Principles to be followed: Keeping a building in use – Is generally seen as the best way to keep the building up to a good standard. If a change of use must occur, minimum damage must be made to the original character of the building. Researching and analysing – Much research must be done on the history, the fabric and the current condition of the building before any proposals for works can be made. Using expert conservation advice – expert advice should be sought throughout the planning process and the construction process to ensure that the works are completed correctly. Protecting the special interest – Inappropriate works can damage the character and special interest of a building, so special care must be taken to ensure this does not happen. Promoting minimum intervention – “do as much as necessary and as little as possible”. Respecting earlier alterations of interest – Earlier alterations can be an insight into past construction techniques and must be respected. They are irreplaceable. Repairing rather than replacing – the main aim should be to repair rather than replace because to get the same quality of materials now is next to impossible and most of the materials were made by hand. Promoting honesty of repairs and alterations – materials used in replacement should not be artificially aged; this will add confusion in the future as to when the alterations were made. Using appropriate materials and methods – appropriate materials must be used during restoration as in past examples certain materials accelerated the decay. Ensuring reversibility of alterations – by ensuring reversibility of alterations in the future this can allow a quick fix to unforeseen problems caused by earlier restorations. Avoid incremental damage – major thought must be given by the planning authority to the impact of minor works to the character of protected structures. Discouraging the use of architectural salvage from other buildings – the re-use of architectural features can confuse the understanding and appreciation of a building, and promoting architectural salvage can cause a market for these materials and promotes dismantling of other old buildings. 1 : 100 Proposed Short Section A-A Conservation 4 3D Proposed Additional Isulation 5 1 : 1 Section A-A Key Plan 6 3D Walling Alterations 7 3D Flooring Alterations 8 Existing U-Value Existing Ground Floor 0.645W/m²K Existing External Wall 1.84W/m²K Existing Column 3.03W/m²K Existing Roof 2.43W/m²K Existing Windows 4.8W/m²K Achieved U-Value 0.24W/m²K 0.21W/m²K 0.23W/m²K 0.23W/m²K 1.8W/m²K 1 : 1 3D Key Plan 9
  • 4. 16 17 18 19 21 22 23 24 25 O N M L K 13 8 7 6 5 4 2 9 10 I H G E D C B 1 15 A P J 3 F 14 Proposed ramp to accomodate level change between corridor and classroom after insulation has been added to the floor Proposed ramp to accomodate level change between corridor and classroom after insulation has been added to the floor Proposed timber stud partition wall 130mm thick, consisting of 2.5mm skim a double laye of gypsum plasterboard with a 60minute fire rating, 75mm timber studs with insulation in between, double layer of 12.5mm gypsum plasterboard with a 60minute fire rating in accordance with BS 476, finished with a layer of 2.5mm skim. Proposed new external fire exit to accomodat e a safe exit from the building in case of fire Proposed new alternative steel fire escape staircase to replace to existing staircase Proposed 2000mm clear width corridor to allow access to all classrooms for disableds users, after the isulation has been added to the existing floor and the floor level within the classrooms has been raised. the corridor must be a minimum of 2000mm to accomodate the amount of traffic that will pass through the area on a daily basis. Proposed all windows to be upgraded to double glazed argon filled timber framed windows. Proposed draught proofing strips to be added around all windows and the detailing at cill level is to be addressed. Existing terrazzo covered staircase is in accordance with current TGD M Building Regulations Existing section of this wall is proposed to be demolisehed to allow access for the new corridor Proposed upgrading of existing doors throughout the ground floor with smoke seals all around and covered in a layer of intumescent paint to provide a fire resistance of 30mins 2880 1500 1200 1380 Proposed access ramp to main entrance at a gradient of 1:12 in accordance with TGD M 1988 47 m² Classroom 1 34 m² Corridor 1 2 15 m² WC's 3 23 m² Classroom 4 64 m² Cassroom 5 23 m² Main Corridor GF 6 20 m² Stairwell GF 714 m² Stairwell GF 8 9 m² Stairs Lobby 9 138 m² Science Lab 10 43 m² Lab Storage 11 94 m² Staff Room 12 43 m² Classroom 13 44 m² Classroom 14 12 m² Protective Corridor 15 24 m² WC's 16 17 m² Stairwell GF 17 66 m² Kitchen 18 175 m² Canteen 19 Room Legend Canteen Cassroom Classroom Corridor Corridor 1 Kitchen Lab Storage Main Corridor GF Protective Corridor Science Lab Staff Room Stairs Lobby Stairwell GF WC's 1211 19132 18762 11069 10500 21090 7000 14540 7060 3168 573 2000 1350 2000 1350 2000 675 840 2000 600 2000 600 2000 400 6598 3350 3350 3350 1740 342335003578342335002500 290300032030006403040320300050030003873245 342335003230 2903000320300011961810536 3224 1842 1508 1842 3350 3350 3453 1791 2000 1275 675 2000 1350 2000 675 675 2000 1350 2000 778839 3500 3500 3230 1514 2000 1350 2000 1350 2000 1228 3423 3230 705 2000 1350 2000 598 373 1271 2126 3500 3500 3398 373 373 723 2000 1500 2000 1500 2000 675 825 2000 573 373 4414 3577 3423 348 348598 2000 1350 2000 1052 548 2000 1866 125 11886 100 3150 100320 1010 398840 1340 890532 1010 2582043 1010 4001940 1010 400480 1002 360 360 1010 2233 1194 1010 1194 1324 1010 1166 175 1340 735406 1810 427 208 1810 133 1770 1010 258 1199167662543316761121 2834 9024 1000 2151 2858 3015 15 FD30 12 FD30 13 FD30 9 FD60 8 FD60 2 FD60 1 FD60 3 FD60 4 FD30 5 FD30 7 FD30 6 FD30 10 FD30 11 FD30 16 FD60 17 FD60 28 FD30 25 FD30 24 FD30 20 FD30 19 FD30 21 FD60 26 FD60 23 FD30 22 FD60 27 FD60 14 FD60 15 m² Stairwell GF 20 5 m² Stairs Lobby 21 60min Fire Rated CLT Internal Partition to BS EN 1995-2 60min Fire Rated CLT Internal Partition to BS EN 1995-2 60min Fire Rated CLT Internal Partition to BS EN 1995-2 60min Fire Rated CLT Internal Partition to BS EN 1995-2 60min Fire Rated CLT Internal Partition to BS EN 1995-2 60min Fire Rated CLT Internal Partition to BS EN 1995-2 60min Fire Rated CLT Internal Partition to BS EN 1995-2 60min Fire Rated CLT Internal Partition to BS EN 1995-2 60min Fire Rated CLT Internal Partition to BS EN 1995-2 60min Fire Rated CLT Internal Partition to BS EN 1995-2 120min Fire Rated Straw Bale Panel External Wall 120min Fire Rated Straw Bale Panel External Wall 120min Fire Rated Straw Bale Panel External Wall 120min Fire Rated Straw Bale Panel External Wall 120min Fire Rated Straw Bale Panel External Wall 120min Fire Rated Straw Bale Panel External Wall 120min Fire Rated Straw Bale Panel External Wall 120min Fire Rated Straw Bale Panel External Wall 120min Fire Rated Straw Bale Panel External Wall 120min Fire Rated Straw Bale Panel External Wall Structural Glulaminated Columns 200mm x 250mm to EN 14080 Structural Glulaminated Columns 200mm x 250mm to EN 14080 Structural Glulaminated Columns 200mm x 250mm to EN 14080 3400 3398 262 400 2698 3700 262 8650 Structural Glulaminated Columns 200mm x 250mm to EN 14080 Structural Glulaminated Columns 200mm x 250mm to EN 14080 Structural Glulaminated Columns 200mm x 250mm to EN 14080 Structural Glulaminated Columns 200mm x 250mm to EN 14080 Structural Glulaminated Columns 200mm x 250mm to EN 14080 Structural Glulaminated Columns 200mm x 250mm to EN 14080 Structural Glulaminated Columns 200mm x 250mm to EN 14080 Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 Existing Block L 1 2 3 4 5 6 7 8 9 10 11 22 21 20 19 18 17 16 15 14 13 12 UP 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 UP UP 1 2 3 4 5 6 7 8 9 1011 12 13 14 15 16 17 18 19 20 348 193 146.00° 146.00° 1550 409 1810 409 2355 2634 10010006481000100 1000 628 1000 1000 1660 1 2 3 4 5 6 789101112 13 14 1516171819 20 21 22 23 24 25 26 27 28 29 30 31 Atrium Opening Above 155 1016 300 679 1707 700 General Notes: -All works to comply with current building regulations and code of practice. -All works must be done to the satisfaction of the buildign control officer. -All dimensions in mm unless otherwise noted. -Drawings must not be scaled, written dimensions must be followed. -Expert advice must be sought from a conservation architect and the heritage group before construction can start on site. -Glulaminated columns to be placed on the intersection of grid lines as shown. -Glulaminated beams to span along gridlines from column to column. -Walls not placed along gridlines. -Primary structure glumainated columns and beams to be in accordance with EN 14080. -Cross laminated timber panels to be in accordance with BS EN 1995-2, BS EN 12354-1 and BS EN 12354 -2 in terms of fire and acoustic performance. -Precast concrete for lift shaft and stair shaft to comply with BS EN 1992-1-2:2004. -Lift and stair shaft to be 60min fire proof including access doors. -All escape fire doors to be 60min fire rated and fitted with automatic closers. -Floor finish to be non-slip ceramic tiles and timber floors where indicated on plan. -Entrance area to have a minimum level landing within 1800mm of entrance door. 29 FD60 32 33 35 36 37 38 39 40 4142434445 46 4748 49 505152 Wall dimensions either side of gridline Proposed demolishment of existing window and installation of new fire rated door to allow for link access to new extension block 126 64 FD60 65 FD60 Structural Glulaminated Columns 200mm x 250mm to EN 14080 69 FD30 18 FD60 30 FD30 30667 19 m² Corridor 22 120min Fire Rated Straw Bale Panel External Wall Reynaers Eco System 50 insulated and ventilated windows Structural Glulaminated Columns 200mm x 250mm to EN 14080 Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 60min Fire Rated CLT Internal Partition to BS EN 1995-2 120min Fire Rated Straw Bale Panel External Wall Reynaers Eco System 50 insulated and ventilated windows Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 Scale LECTURER Drawn by Date Project number Institute of Technology Carlow BSc. (Hons) in Architectural Technology Year 4 2013-2014 1 : 100 Combined Ground Floor Plan 1 Restoration, extension and upgradation to protected structures 13-January-2014 Edel Fox Noel Dunne, Sujana Sudhir & Dan O' Sullivan GAP1A105 1 : 100 Ground Floor Level 1 Door Schedule Ground Floor Level Level Mark Fire Rating Width Height GFL 1 FD60 1810 2110 GFL 2 FD60 1810 2110 GFL 3 FD60 1810 2110 GFL 4 FD30 1010 2110 GFL 5 FD30 1010 2110 GFL 6 FD30 1010 2110 GFL 7 FD30 1010 2110 GFL 8 FD60 1810 2110 GFL 9 FD60 1810 2110 GFL 10 FD30 1010 2110 GFL 11 FD30 1010 2110 GFL 12 FD30 1010 2110 GFL 13 FD30 1010 2110 GFL 14 FD60 1810 2110 GFL 15 FD30 1010 2110 GFL 16 FD60 813 2184 GFL 17 FD60 813 2184 GFL 18 FD60 1810 2110 GFL 19 FD30 910 2110 GFL 20 FD30 910 2110 GFL 21 FD60 1810 2110 GFL 22 FD60 1010 2110 GFL 23 FD30 1010 2110 GFL 24 FD30 910 2110 GFL 25 FD30 910 2110 GFL 26 FD60 1810 2110 GFL 27 FD60 1010 2110 GFL 28 FD30 835 2595 GFL 29 FD60 1810 2110 GFL 30 FD30 1950 2325 GFL 64 FD60 1810 2110 GFL 65 FD60 1810 2110 GFL 69 FD30 1950 2025 GFL 74 FD60 1810 2110 Room Schedule Ground Floor Level Number Name Level Area 1 Classroom GFL 47 m² 2 Corridor 1 GFL 34 m² 3 WC's GFL 15 m² 4 Classroom GFL 23 m² 5 Cassroom GFL 64 m² 6 Main Corridor GF GFL 23 m² 7 Stairwell GF GFL 20 m² 8 Stairwell GF GFL 14 m² 9 Stairs Lobby GFL 9 m² 10 Science Lab GFL 138 m² 11 Lab Storage GFL 43 m² 12 Staff Room GFL 94 m² 13 Classroom GFL 43 m² 14 Classroom GFL 44 m² 15 Protective Corridor GFL 12 m² 16 WC's GFL 24 m² 17 Stairwell GF GFL 17 m² 18 Kitchen GFL 66 m² 19 Canteen GFL 175 m² 20 Stairwell GF GFL 15 m² 21 Stairs Lobby GFL 5 m² 22 Corridor GFL 19 m² General Specification Block L Proposed upgrade to existing external walls Proposed - additional dry-lining board to the internal face of the existing wall, consisting of 85mm kingspan kooltherm K17 insulated dry-linig board in between steel U channels, with 12.5mm gypsum plasterboard with a 60minute fir rating in accordance with BS 476, finished with a layer of 2.5mm skim. Proposed upgrade to existing internal walls Proposed - additional dry-linig board to both faces of the partition wall, consisting of 50mm kingspan kolltherm K17 insulated dry-lining board in between steel U channels, with 12.5mm gypsum plasterboard with a 60minute fire rating in accordance with BS 476, finished with a layer of 2.5mm skim. This to be done to both sides of the wall. Proposed upgrade to existing floor Proposed - remove existing harwood flooring to be repaired where possible and if not replaced, additional 80mm kingspan Therma TF70 in between timber battens to be added on top of existing screed. Repaired hardwood flooring to be put back down on top of the new insulation. Proposed upgrade to existing roof Proposed - additional dry-lining board at internal ceiling level consisting of 85mm kingspan kooltherm K17 insulated dry-lining board in between timber battens, 12.5mm plasterboard finished with a 2.5mm skim. The existing rubber membrane needs to be stripped and the torch on felt repaired and the pebbles replaces, and the drainage issues addressed. Proposed timber stud partition Proposed - timber stud partition wall 130mm thick, consisting of 2.5mm skim a double laye of gypsum plasterboard with a 60minute fire rating, 75mm timber studs with insulation in between, double layer of 12.5mm gypsum plasterboard with a 60minute fire rating in accordance with BS 476, finished with a layer of 2.5mm skim. Proposed upgrade to existing windows Proposed - Upgrading to double glazed argon filled timber framed windows which will achieve a u-value of 1.8w/m²k. Install draught proofing strips around all windows to lower heat loss even more. Address detailing at cill to fix the water drainage problem from occuring. Proposed upgrade to existing internal doors Proposed upgrading of existing doors throughout the ground floor with smoke seals all around and covered in a layer of intumescent paint to provide a fire resistance of 30mins. New Extension Structural Foundations – 540mm X 400mm reinforced concrete ring beams to carry the load of the external and internal walls, while also allocating a space for the hollowcore flooring to sit into. The hollowcore flooring will bear half way on to each beam and be securely strapped back using T12 tie bars bedded in with the screed. Each structural glulam column will be connected back to a 360mm x 360mm square reinforced concrete column. Each concrete column will vary in depth as the ground is gradually sloped. The reinforced concrete column will be structurally supported below by a pad foundation. Each column is to have its own individual pad foundation where possible. Ground Floor Build Up – DPM to be placed between hollowcore floor slabs and ground, 200mm precast concrete hollowcore flooring slabs to be connected back to the reinforced concrete ring beams, both in accordance with BS EN 1992-1- 2:2004. 75mm structural concrete screed to be placed on top of the hollowcore flooring slabs. 80mm Kingspan Kooltherm K3 Floorboard to be placed on top of the structural screed, with 80mm x 40mm thimber battens @ 600mm c/c to be placed in between. 18mm plywood sheeting to be placed over the insulation and fixed back to the timber battens @ 600mm c/c. Finally the floor is to be finished in accordance with the use of each specific room, with 22mm oak flooring to be placed in most areas and a tile finish to be placed in the kitchen and WC areas. Intermediate Floor Build Up – On the underside, the floor is to be finished with a 2.5mm plaster skim, which is applied directly to 12.5mm gyproc board. This is followed by a 25mm services gap and then 50mm rockwool insulation, in between 25mm x 75mm timber battens @ 600mm c/c fixed back to the cross laminated timber panels. These battens are used to support and fix the gyproc board in place. The main structure of the floor is made up of a 200mm (5 x 40mm layers) cross laminated timber panels, which spans from one glulam beam to another. Above this there is another layer of 50mm rockwool insulation in between 25mm x 50mm timber battens @ 600mm c/c. Then sheets of 18mm plywood finally finished off with a 22mm oak flooring or a tile finish depending on the use of the room. Roof Build Up - On the underside, the roof is to be finished with a 2.5mm plaster skim, which is applied directly to 12.5mm gyproc board. This is followed by a 25mm services gap and then 50mm rockwool insulation, in between 25mm x 75mm timber battens @ 600mm c/c fixed back to the cross laminated timber panels. These battens are used to support and fix the gyproc board in place. The main structure of the floor is made up of a 200mm (5 x 40mm layers) cross laminated timber panels, which spans from one glulam beam to another. Above this a vapour barrier layer is to be added. Followed by 120mm Kingspan Thermaroof TR31, then a 3G base layer, finished with a triple layer of built up felt waterproofing. External Wall Build Up – From Exterior: 8mm external lime render finish, 40mm wood fibre combined breather membrane board, 12mm timbervent, 400mm wheat straw bale insulation in between 400mm ‘I’ studs spaced @ 600mm c/c, 15mm OSB, 25mm services cavity in between 25mm x 50mm vertical timber battens fixed back to the 15mm OSB, finished on the interior side with a layer of 12.5mm gyproc board and 2.5mm plaster skim finish. Each end of the straw bale panel is closed with a 43mm x 400mm glulaminated column. This system is from the manufacturer Modcell, it is the Modcell Core + panel. This wall panel achieves a u-value of 0.11 W/(m2K), a fire rating of 120mins, and an acoustic performance rating of 52db. Internal Wall Build Up – 2.5mm plaster finish, 12.5mm gyproc board, 25mm rockwool insulation in between 25mm x 25mm vertical timber battens spaced @ 600mm c/c fixed back to the cross laminated timber panel, put in place to support and fix the gyproc board to. Followed by 120mm (40mm x 3 layers) cross laminated timber wall panel in accordance with BS EN 1995-2, BS EN 12354-1 and BS EN 12354-2 in terms of fire and acoustic performance, 25mm rockwool insulation in between 25mm x 25mm vertical timber battens spaced @ 600mm c/c fixed back to the cross laminated timber panel, put in place to support and fix the gyproc board to. Finished with 12.5mm gyproc board and 2.5mm plaster skim finish. Concrete Wall Panels – 200mm reinforced precast concrete solid wall panels to be used in the stairs, stair lobby, lift shaft and protected corridor to provide structural strength and achieve the required fire rating in accordance with TGD B. the panels are also relatively soundproof so this will eliminate sound transmission throughout the building. The internal panels will have a 25mm service cavity in between 25mm x 50mm vertical timber battens, finished with 12.5mm gyproc board and a 2.5mm plaster skim finish, with the side inside the lift or stairs shaft having the concrete left exposed. The panels that are exposed to the outside will have no internal finish (concrete to be left exposed), and an 8mm lime render finish to the external face. 3D GL 2
  • 5. 16 17 18 19 21 22 23 24 25 O N M L K 13 8 7 6 5 4 2 9 10 I H G E D C B 1 15 A P J 3 F 14 Proposed new alternative steel fire escape staircase to replace to existing staircase Proposed all windows to be upgraded to double glazed argon filled timber framed windows. Proposed draught proofing strips to be added around all windows and the detailing at cill level is to be addressed. Existing terrazzo covered staircase is in accordance with current TGD M Building Regulations Proposed ramp to accomodate level change between corridor and classroom after insulation has been added to the floor Proposed ramp to accomodate level change between corridor and classroom after insulation has been added to the floor Proposed parquet flooring to be repaired were possible and relaid and if not possible to be replaced after the insulation has been added to the floor 201 m² Classroom 29 30 m² Corridor 30 20 m² Stairwell FFL 3114 m² Stairwell FFL 32 9 m² Stairwell Lobby 33 138 m² Science Lab 34 43 m² Lab Storage 35 67 m² Classroom 36 25 m² Storage 37 43 m² Classroom 38 44 m² Classroom 39 12 m² Protective Corridor 40 24 m² WC's 41 17 m² Stairwell FFL 42 64 m² Kitchen Storage 43 176 m² Canteen 44 15 m² Room 45 5 m² Room 46 1211 21090 820250035003423357835003423348 638300032030003133283040320300050030003133320 10500 7000 14540 6598 3350 3350 3350 1740 342335003230 29030003203000 3500 3500 3230 2000 1350 2000 1350 2000 1228 3423 3230 705 2000 1350 2000 598 4414 3577 3423 348 348598 2000 1350 2000 1052 548 2000 1866 125 11886 9020 1000 2151 2858 3011 19132 573 2000 1350 2000 1350 2000 675 840 2000 600 2000 600 2000 400 313 18746 3304 1842 1508 1842 3350 3350 3777 1871 2000 1275 675 2000 1350 2000 675 675 2000 1350 2000 1102 11149 373 3398 3500 3500 2126 1271 373 373 573 2000 825 675 2000 1500 2000 1500 2000 723 373 Room Legend Canteen Classroom Corridor Kitchen Storage Lab Storage Protective Corridor Room Science Lab Stairwell FFL Stairwell Lobby Storage WC's 45 FD60 44 FD60 39 FD30 41 FD30 40 FD30 31 FD60 32 FD60 33 FD30 34 FD30 36 FD30 35 FD30 37 FD30 38 FD30 42 FD60 43 FD60 49 FD30 48 FD30 47 FD30 50 FD6046 FD60 429 1794 437 1296 1794 308 155 22511340 735 175 4784 1000 1200 1200 Ramp @ gradient of 1:20 Structural Glulaminated Columns 200mm x 250mm to EN 14080 Atrium Opening Above Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 120min Fire Rated Straw Bale Panel External Wall Structural Glulaminated Columns 200mm x 250mm to EN 14080 120min Fire Rated Straw Bale Panel External Wall 60min Fire Rated CLT Internal Partition to BS EN 1995-2 60min Fire Rated CLT Internal Partition to BS EN 1995-2 Structural Glulaminated Columns 200mm x 250mm to EN 14080 120min Fire Rated Straw Bale Panel External Wall 60min Fire Rated CLT Internal Partition to BS EN 1995-2 Structural Glulaminated Columns 200mm x 250mm to EN 14080 120min Fire Rated Straw Bale Panel External Wall Structural Glulaminated Columns 200mm x 250mm to EN 14080 Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 60min Fire Rated CLT Internal Partition to BS EN 1995-2 120min Fire Rated Straw Bale Panel External Wall 60min Fire Rated CLT Internal Partition to BS EN 1995-2 120min Fire Rated Straw Bale Panel External Wall Structural Glulaminated Columns 200mm x 250mm to EN 14080 60min Fire Rated CLT Internal Partition to BS EN 1995-2 Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 60min Fire Rated CLT Internal Partition to BS EN 1995-2 Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 Structural Glulaminated Columns 200mm x 250mm to EN 14080 120min Fire Rated Straw Bale Panel External Wall 120min Fire Rated Straw Bale Panel External Wall 60min Fire Rated CLT Internal Partition to BS EN 1995-2 120min Fire Rated Straw Bale Panel External Wall Structural Glulaminated Columns 200mm x 250mm to EN 14080 60min Fire Rated CLT Internal Partition to BS EN 1995-2 1324 1010 1166 1194 1010 1194 300 1010 2293 532 1010 300 2140 1010 200 2243 1010 200 565 1010 1010 398 3350 409 1810 409 2355 1851 64172464 461 1010 1383 2854 10006481000 1000 628 1000 1660 1000 General Notes: -All works to comply with current building regulations and code of practice. -All works must be done to the satisfaction of the buildign control officer. -All dimensions in mm unless otherwise noted. -Drawings must not be scaled, written dimensions must be followed. -Expert advice must be sought from a conservation architect and the heritage group before construction can start on site. -Glulaminated columns to be placed on the intersection of grid lines as shown. -Glulaminated beams to span along gridlines from column to column. -Walls not placed along gridlines. -Primary structure glumainated columns and beams to be in accordance with EN 14080. -Cross laminated timber panels to be in accordance with BS EN 1995-2, BS EN 12354-1 and BS EN 12354 -2 in terms of fire and acoustic performance. -Precast concrete for lift shaft and stair shaft to comply with BS EN 1992-1-2:2004. -Lift and stair shaft to be 60min fire proof including access doors. -All escape fire doors to be 60min fire rated and fitted with automatic closers. -Floor finish to be non-slip ceramic tiles and timber floors where indicated on plan. -Entrance area to have a minimum level landing within 1800mm of entrance door. 1 2 3 4 5 6 7 8 9 10 11 23 22 21 20 19 18 17 16 15 14 13 1 2 3 4 5 6 7 8 9 1011 12 13 14 15 16 17 18 19 20 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 53 54 55 56 57 58 596061626364 65 66 6768697071 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 9394959697 9899 100101102 12 24 Proposed demolishment of existing window and installation of new fire rated door to allow for link access to new extension block 348 193 Wall dimensions either side of gridline 146.00° 146.00° 63 FD60 66 FD60 Structural Glulaminated Columns 200mm x 250mm to EN 14080 127 128 8650 400 2698 403 2700 598 262 3400 3398 262 7060 1842 1366 3208 30763 Existing Block L 120min Fire Rated Straw Bale Panel External Wall Structural Glulaminated Columns 200mm x 250mm to EN 14080 Reynaers Eco System 50 insulated and ventilated windows 60min Fire Rated CLT Internal Partition to BS EN 1995-2 120min Fire Rated Straw Bale Panel External Wall Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 Scale LECTURER Drawn by Date Project number Institute of Technology Carlow BSc. (Hons) in Architectural Technology Year 4 2013-2014 1 : 100 Combined First Floor Plan 1 Restoration, extension and upgradation to protected structures 13-January-2014 Edel Fox Noel Dunne, Sujana Sudhir & Dan O' Sullivan GAP1A106 1 : 100 First Floor Level 1 General Specification Block L Proposed upgrade to existing external walls Proposed - additional dry-lining board to the internal face of the existing wall, consisting of 85mm kingspan kooltherm K17 insulated dry-linig board in between steel U channels, with 12.5mm gypsum plasterboard with a 60minute fir rating in accordance with BS 476, finished with a layer of 2.5mm skim. Proposed upgrade to existing internal walls Proposed - additional dry-linig board to both faces of the partition wall, consisting of 50mm kingspan kolltherm K17 insulated dry-lining board in between steel U channels, with 12.5mm gypsum plasterboard with a 60minute fire rating in accordance with BS 476, finished with a layer of 2.5mm skim. This to be done to both sides of the wall. Proposed upgrade to existing floor Proposed - remove existing harwood flooring to be repaired where possible and if not replaced, additional 80mm kingspan Therma TF70 in between timber battens to be added on top of existing screed. Repaired hardwood flooring to be put back down on top of the new insulation. Proposed upgrade to existing roof Proposed - additional dry-lining board at internal ceiling level consisting of 85mm kingspan kooltherm K17 insulated dry-lining board in between timber battens, 12.5mm plasterboard finished with a 2.5mm skim. The existing rubber membrane needs to be stripped and the torch on felt repaired and the pebbles replaces, and the drainage issues addressed. Proposed timber stud partition Proposed - timber stud partition wall 130mm thick, consisting of 2.5mm skim a double laye of gypsum plasterboard with a 60minute fire rating, 75mm timber studs with insulation in between, double layer of 12.5mm gypsum plasterboard with a 60minute fire rating in accordance with BS 476, finished with a layer of 2.5mm skim. Proposed upgrade to existing windows Proposed - Upgrading to double glazed argon filled timber framed windows which will achieve a u-value of 1.8w/m²k. Install draught proofing strips around all windows to lower heat loss even more. Address detailing at cill to fix the water drainage problem from occuring. Proposed upgrade to existing internal doors Proposed upgrading of existing doors throughout the ground floor with smoke seals all around and covered in a layer of intumescent paint to provide a fire resistance of 30mins. New Extension Structural Foundations – 540mm X 400mm reinforced concrete ring beams to carry the load of the external and internal walls, while also allocating a space for the hollowcore flooring to sit into. The hollowcore flooring will bear half way on to each beam and be securely strapped back using T12 tie bars bedded in with the screed. Each structural glulam column will be connected back to a 360mm x 360mm square reinforced concrete column. Each concrete column will vary in depth as the ground is gradually sloped. The reinforced concrete column will be structurally supported below by a pad foundation. Each column is to have its own individual pad foundation where possible. Ground Floor Build Up – DPM to be placed between hollowcore floor slabs and ground, 200mm precast concrete hollowcore flooring slabs to be connected back to the reinforced concrete ring beams, both in accordance with BS EN 1992-1-2:2004. 75mm structural concrete screed to be placed on top of the hollowcore flooring slabs. 80mm Kingspan Kooltherm K3 Floorboard to be placed on top of the structural screed, with 80mm x 40mm thimber battens @ 600mm c/c to be placed in between. 18mm plywood sheeting to be placed over the insulation and fixed back to the timber battens @ 600mm c/c. Finally the floor is to be finished in accordance with the use of each specific room, with 22mm oak flooring to be placed in most areas and a tile finish to be placed in the kitchen and WC areas. Intermediate Floor Build Up – On the underside, the floor is to be finished with a 2.5mm plaster skim, which is applied directly to 12.5mm gyproc board. This is followed by a 25mm services gap and then 50mm rockwool insulation, in between 25mm x 75mm timber battens @ 600mm c/c fixed back to the cross laminated timber panels. These battens are used to support and fix the gyproc board in place. The main structure of the floor is made up of a 200mm (5 x 40mm layers) cross laminated timber panels, which spans from one glulam beam to another. Above this there is another layer of 50mm rockwool insulation in between 25mm x 50mm timber battens @ 600mm c/c. Then sheets of 18mm plywood finally finished off with a 22mm oak flooring or a tile finish depending on the use of the room. Roof Build Up - On the underside, the roof is to be finished with a 2.5mm plaster skim, which is applied directly to 12.5mm gyproc board. This is followed by a 25mm services gap and then 50mm rockwool insulation, in between 25mm x 75mm timber battens @ 600mm c/c fixed back to the cross laminated timber panels. These battens are used to support and fix the gyproc board in place. The main structure of the floor is made up of a 200mm (5 x 40mm layers) cross laminated timber panels, which spans from one glulam beam to another. Above this a vapour barrier layer is to be added. Followed by 120mm Kingspan Thermaroof TR31, then a 3G base layer, finished with a triple layer of built up felt waterproofing. External Wall Build Up – From Exterior: 8mm external lime render finish, 40mm wood fibre combined breather membrane board, 12mm timbervent, 400mm wheat straw bale insulation in between 400mm ‘I’ studs spaced @ 600mm c/c, 15mm OSB, 25mm services cavity in between 25mm x 50mm vertical timber battens fixed back to the 15mm OSB, finished on the interior side with a layer of 12.5mm gyproc board and 2.5mm plaster skim finish. Each end of the straw bale panel is closed with a 43mm x 400mm glulaminated column. This system is from the manufacturer Modcell, it is the Modcell Core + panel. This wall panel achieves a u-value of 0.11 W/(m2K), a fire rating of 120mins, and an acoustic performance rating of 52db. Internal Wall Build Up – 2.5mm plaster finish, 12.5mm gyproc board, 25mm rockwool insulation in between 25mm x 25mm vertical timber battens spaced @ 600mm c/c fixed back to the cross laminated timber panel, put in place to support and fix the gyproc board to. Followed by 120mm (40mm x 3 layers) cross laminated timber wall panel in accordance with BS EN 1995-2, BS EN 12354-1 and BS EN 12354-2 in terms of fire and acoustic performance, 25mm rockwool insulation in between 25mm x 25mm vertical timber battens spaced @ 600mm c/c fixed back to the cross laminated timber panel, put in place to support and fix the gyproc board to. Finished with 12.5mm gyproc board and 2.5mm plaster skim finish. Concrete Wall Panels – 200mm reinforced precast concrete solid wall panels to be used in the stairs, stair lobby, lift shaft and protected corridor to provide structural strength and achieve the required fire rating in accordance with TGD B. the panels are also relatively soundproof so this will eliminate sound transmission throughout the building. The internal panels will have a 25mm service cavity in between 25mm x 50mm vertical timber battens, finished with 12.5mm gyproc board and a 2.5mm plaster skim finish, with the side inside the lift or stairs shaft having the concrete left exposed. The panels that are exposed to the outside will have no internal finish (concrete to be left exposed), and an 8mm lime render finish to the external face. Door Schedule First Floor Level Level Mark Fire Rating Width Height FFL 15 FD60 184 1245 FFL 16 FD60 184 190 FFL 31 FD60 1810 2110 FFL 32 FD60 1810 2110 FFL 33 FD30 1010 2110 FFL 34 FD30 1010 2110 FFL 35 FD30 1010 2110 FFL 36 FD30 1010 2110 FFL 37 FD30 1010 2110 FFL 38 FD30 1010 2110 FFL 39 FD30 1010 2110 FFL 40 FD30 1010 2110 FFL 41 FD30 1010 2110 FFL 42 FD60 813 2184 FFL 43 FD60 813 2184 FFL 44 FD60 1810 2110 FFL 45 FD60 1810 2110 FFL 46 FD60 184 665 FFL 47 FD30 910 2110 FFL 48 FD30 1010 2110 FFL 49 FD30 910 2110 FFL 50 FD60 910 2110 FFL 63 FD60 1810 2110 FFL 66 FD60 1810 2110 FFL 73 FD30 910 2110 Room Schedule First Floor Leel Number Name Level Area 29 Classroom FFL 201 m² 30 Corridor FFL 30 m² 31 Stairwell FFL FFL 20 m² 32 Stairwell FFL FFL 14 m² 33 Stairwell Lobby FFL 9 m² 34 Science Lab FFL 138 m² 35 Lab Storage FFL 43 m² 36 Classroom FFL 67 m² 37 Storage FFL 25 m² 38 Classroom FFL 43 m² 39 Classroom FFL 44 m² 40 Protective Corridor FFL 12 m² 41 WC's FFL 24 m² 42 Stairwell FFL FFL 17 m² 43 Kitchen Storage FFL 64 m² 44 Canteen FFL 176 m² 45 Room FFL 15 m² 46 Room FFL 5 m² 3D FFL 2
  • 6. 16 17 18 19 21 22 23 24 25 O N M L K 13 8 7 6 5 4 2 9 10 I H G E D C B 1 15 A P J 3 F 14 Proposed new alternative steel fire escape staircase to replace to existing staircase Proposed all windows to be upgraded to double glazed argon filled timber framed windows. Proposed draught proofing strips to be added around all windows and the detailing at cill level is to be addressed. Existing terrazzo covered staircase is in accordance with current TGD M Building Regulations Proposed demolishment of existing corridor walls as adequate space was no provided for wheelchair users in accordance with TGD M Proposed new corridor a minimum width of 2000mm to allow sufficient access for disabled access and to allow sufficient room for the foot traffic that will pass through the building in accordance with TGD M Proposed upgrade to existing walls with an additional dry-lining board to both faces of the partition wall, consisting of 50mm kingspan kolltherm K17 insulated dry-lining board in between steel U channels, with 12.5mm gypsum plasterboard with a 60minute fire rating in accordance with BS 476, finished with a layer of 2.5mm skim. This to be done to both sides of the wall. Proposed ramp to accomodate level change between corridor and classroom after insulation has been added to the floor Proposed ramp to accomodate level change between corridor and classroom after insulation has been added to the floor Proposed addition of Parquet flooring to be added after insulation has been added to the floor to keep in character with the rest of the building Proposed addition of Parquet flooring to be added after insulation has been added to the floor to keep in character with the rest of the building Proposed addition of Parquet flooring to be added after insulation has been added to the floor to keep in character with the rest of the building 11 m² Showers 47 99 m² Games Room 48 116 m² Music Room 49 6 m² Corridor 50 20 m² Stairwell SFL 51 14 m² Stairwell SFL 52 9 m² Stairwell Lobby 53 10 m² Protected Corridor 54 24 m² WC's 55 17 m² Stairwell SFL 56 15 m² Stairwell SFL 57 5 m² Stairwell Lobby 58 Room Legend Corridor Games Room Music Room Protected Corridor Showers Stairwell Lobby Stairwell SFL WC's 1211 Atrium Opening Above General Notes: -All works to comply with current building regulations and code of practice. -All works must be done to the satisfaction of the buildign control officer. -All dimensions in mm unless otherwise noted. -Drawings must not be scaled, written dimensions must be followed. -Expert advice must be sought from a conservation architect and the heritage group before construction can start on site. -Glulaminated columns to be placed on the intersection of grid lines as shown. -Glulaminated beams to span along gridlines from column to column. -Walls not placed along gridlines. -Primary structure glumainated columns and beams to be in accordance with EN 14080. -Cross laminated timber panels to be in accordance with BS EN 1995-2, BS EN 12354-1 and BS EN 12354 -2 in terms of fire and acoustic performance. -Precast concrete for lift shaft and stair shaft to comply with BS EN 1992-1- 2:2004. -Lift and stair shaft to be 60min fire proof including access doors. -All escape fire doors to be 60min fire rated and fitted with automatic closers. -Floor finish to be non-slip ceramic tiles and timber floors where indicated on plan. -Entrance area to have a minimum level landing within 1800mm of entrance door. 1 2 3 4 5 6 7 8 9 1011 12 13 14 15 16 17 18 19 20 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Proposed demolishment of existing window and installation of new fire rated door to allow for link access to new extension block 1 2 3 4 5 6 7 8 9 10 11 23 22 21 20 19 18 17 16 15 14 13 12 24 425 1810 425 1296 175 1340 735155 2251 155 9024 3015 2858 2151 1000 11874 335 3423 3577 4414 125 360 1271 2126 3500 3500 3398 360 14515 335 3423 3235 6993 903 3500 3500 3243 11146 3314 1842 1508 1842 3350 3350 3569 18775 348342335003243 360 6598 3350 3350 3350 1740 348342335003578342335002500 10010006481000100 2634 241 1010 1383 565 1010 3615 1010 398 56 FD60 53 FD30 55 FD30 54 FD30 62 FD6057 FD60 61 FD30 59 FD30 60 FD30 58 FD30 51 FD60 52 FD60 1851 859876116 409 1810 409 2355 1000 628 1000 Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 60min Fire rated Cross Laminated Timber Panel Parapet wall covered in roofing felt Membrane coated insulated gutter 60min Fire rated Cross Laminated Timber Panel Roof with a Kingspan Thermaroof TR31 covering 60min Fire rated 200mm Cross laminated timber panel floor Structural Glulaminated Columns 200mm x 250mm to EN 14080 120min Fire Rated Straw Bale Panel External Wall 120min Fire Rated Straw Bale Panel External Wall 60min Fire rated Glulaminated beam 140mm x 675mm EN 14080 60min Fire rated Cross Laminated Timber Panel Parapet wall covered in roofing felt 60min Fire rated Cross Laminated Timber Panel Roof with a Kingspan Thermaroof TR31 covering Structural Glulaminated Columns 200mm x 250mm to EN 14080 60min Fire rated Cross Laminated Timber Panel Roof with a Kingspan Thermaroof TR31 covering 120min Fire Rated Straw Bale Panel External Wall Glass handrail at a height of 900mm Glass handrail at a height of 900mm Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 60min Fire Rated CLT Internal Partition to BS EN 1995-2 60min Fire rated Cross Laminated Timber Panel Roof with a Kingspan Thermaroof TR31 covering 60min Fire rated Cross Laminated Timber Panel Roof with a Kingspan Thermaroof TR31 covering Membrane coated insulated gutter Membrane coated insulated gutter 60min Fire rated Cross Laminated Timber Panel Parapet wall covered in roofing felt 60min Fire rated Cross Laminated Timber Panel Parapet wall covered in roofing felt60min Fire rated Cross Laminated Timber Panel Parapet wall covered in roofing felt 8650 30763 400 2698 403 2700 598 262 3400 3398 262 7060 1842 1366 3208 21090 Existing Block L Existing Block B & Block C 103 104 105 106 107 108 109 110 111 112 113 114 120121 Direction of rain water flow Proposed to be demolished Legend Structural Glulaminated Columns 200mm x 250mm to EN 14080 67 FD60 68 FD60 8650 30763 400 2698 403 2700 598 262 3400 3398 262 7060 1842 1366 3208 22mm Accoya timber cladding finish to the exterior 60min Fire rated Cross Laminated Timber Panel Roof with a Kingspan Thermaroof TR31 covering Membrane coated insulated gutter Reynaers Eco System 50 insulated and ventilated windows 60min Fire rated Cross Laminated Timber Panel Roof with a Kingspan Thermaroof TR31 covering Membrane coated insulated gutter Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 Reynaers Eco System 50 insulated and ventilated windows Scale LECTURER Drawn by Date Project number Institute of Technology Carlow BSc. (Hons) in Architectural Technology Year 4 2013-2014 1 : 100 Combined Second Floor Plan 1 Restoration, extension and upgradation to protected structures 13-January-2014 Edel Fox Noel Dunne, Sujana Sudhir & Dan O' Sullivan GAP1A107 1 : 100 Second Floor Level 1 General Specification Block L Proposed upgrade to existing external walls Proposed - additional dry-lining board to the internal face of the existing wall, consisting of 85mm kingspan kooltherm K17 insulated dry-linig board in between steel U channels, with 12.5mm gypsum plasterboard with a 60minute fir rating in accordance with BS 476, finished with a layer of 2.5mm skim. Proposed upgrade to existing internal walls Proposed - additional dry-linig board to both faces of the partition wall, consisting of 50mm kingspan kolltherm K17 insulated dry-lining board in between steel U channels, with 12.5mm gypsum plasterboard with a 60minute fire rating in accordance with BS 476, finished with a layer of 2.5mm skim. This to be done to both sides of the wall. Proposed upgrade to existing floor Proposed - remove existing harwood flooring to be repaired where possible and if not replaced, additional 80mm kingspan Therma TF70 in between timber battens to be added on top of existing screed. Repaired hardwood flooring to be put back down on top of the new insulation. Proposed upgrade to existing roof Proposed - additional dry-lining board at internal ceiling level consisting of 85mm kingspan kooltherm K17 insulated dry-lining board in between timber battens, 12.5mm plasterboard finished with a 2.5mm skim. The existing rubber membrane needs to be stripped and the torch on felt repaired and the pebbles replaces, and the drainage issues addressed. Proposed timber stud partition Proposed - timber stud partition wall 130mm thick, consisting of 2.5mm skim a double laye of gypsum plasterboard with a 60minute fire rating, 75mm timber studs with insulation in between, double layer of 12.5mm gypsum plasterboard with a 60minute fire rating in accordance with BS 476, finished with a layer of 2.5mm skim. Proposed upgrade to existing windows Proposed - Upgrading to double glazed argon filled timber framed windows which will achieve a u-value of 1.8w/m²k. Install draught proofing strips around all windows to lower heat loss even more. Address detailing at cill to fix the water drainage problem from occuring. Proposed upgrade to existing internal doors Proposed upgrading of existing doors throughout the ground floor with smoke seals all around and covered in a layer of intumescent paint to provide a fire resistance of 30mins. New Extension Structural Foundations – 540mm X 400mm reinforced concrete ring beams to carry the load of the external and internal walls, while also allocating a space for the hollowcore flooring to sit into. The hollowcore flooring will bear half way on to each beam and be securely strapped back using T12 tie bars bedded in with the screed. Each structural glulam column will be connected back to a 360mm x 360mm square reinforced concrete column. Each concrete column will vary in depth as the ground is gradually sloped. The reinforced concrete column will be structurally supported below by a pad foundation. Each column is to have its own individual pad foundation where possible. Ground Floor Build Up – DPM to be placed between hollowcore floor slabs and ground, 200mm precast concrete hollowcore flooring slabs to be connected back to the reinforced concrete ring beams, both in accordance with BS EN 1992-1-2:2004. 75mm structural concrete screed to be placed on top of the hollowcore flooring slabs. 80mm Kingspan Kooltherm K3 Floorboard to be placed on top of the structural screed, with 80mm x 40mm thimber battens @ 600mm c/c to be placed in between. 18mm plywood sheeting to be placed over the insulation and fixed back to the timber battens @ 600mm c/c. Finally the floor is to be finished in accordance with the use of each specific room, with 22mm oak flooring to be placed in most areas and a tile finish to be placed in the kitchen and WC areas. Intermediate Floor Build Up – On the underside, the floor is to be finished with a 2.5mm plaster skim, which is applied directly to 12.5mm gyproc board. This is followed by a 25mm services gap and then 50mm rockwool insulation, in between 25mm x 75mm timber battens @ 600mm c/c fixed back to the cross laminated timber panels. These battens are used to support and fix the gyproc board in place. The main structure of the floor is made up of a 200mm (5 x 40mm layers) cross laminated timber panels, which spans from one glulam beam to another. Above this there is another layer of 50mm rockwool insulation in between 25mm x 50mm timber battens @ 600mm c/c. Then sheets of 18mm plywood finally finished off with a 22mm oak flooring or a tile finish depending on the use of the room. Roof Build Up - On the underside, the roof is to be finished with a 2.5mm plaster skim, which is applied directly to 12.5mm gyproc board. This is followed by a 25mm services gap and then 50mm rockwool insulation, in between 25mm x 75mm timber battens @ 600mm c/c fixed back to the cross laminated timber panels. These battens are used to support and fix the gyproc board in place. The main structure of the floor is made up of a 200mm (5 x 40mm layers) cross laminated timber panels, which spans from one glulam beam to another. Above this a vapour barrier layer is to be added. Followed by 120mm Kingspan Thermaroof TR31, then a 3G base layer, finished with a triple layer of built up felt waterproofing. External Wall Build Up – From Exterior: 8mm external lime render finish, 40mm wood fibre combined breather membrane board, 12mm timbervent, 400mm wheat straw bale insulation in between 400mm ‘I’ studs spaced @ 600mm c/c, 15mm OSB, 25mm services cavity in between 25mm x 50mm vertical timber battens fixed back to the 15mm OSB, finished on the interior side with a layer of 12.5mm gyproc board and 2.5mm plaster skim finish. Each end of the straw bale panel is closed with a 43mm x 400mm glulaminated column. This system is from the manufacturer Modcell, it is the Modcell Core + panel. This wall panel achieves a u-value of 0.11 W/(m2K), a fire rating of 120mins, and an acoustic performance rating of 52db. Internal Wall Build Up – 2.5mm plaster finish, 12.5mm gyproc board, 25mm rockwool insulation in between 25mm x 25mm vertical timber battens spaced @ 600mm c/c fixed back to the cross laminated timber panel, put in place to support and fix the gyproc board to. Followed by 120mm (40mm x 3 layers) cross laminated timber wall panel in accordance with BS EN 1995-2, BS EN 12354-1 and BS EN 12354-2 in terms of fire and acoustic performance, 25mm rockwool insulation in between 25mm x 25mm vertical timber battens spaced @ 600mm c/c fixed back to the cross laminated timber panel, put in place to support and fix the gyproc board to. Finished with 12.5mm gyproc board and 2.5mm plaster skim finish. Concrete Wall Panels – 200mm reinforced precast concrete solid wall panels to be used in the stairs, stair lobby, lift shaft and protected corridor to provide structural strength and achieve the required fire rating in accordance with TGD B. the panels are also relatively soundproof so this will eliminate sound transmission throughout the building. The internal panels will have a 25mm service cavity in between 25mm x 50mm vertical timber battens, finished with 12.5mm gyproc board and a 2.5mm plaster skim finish, with the side inside the lift or stairs shaft having the concrete left exposed. The panels that are exposed to the outside will have no internal finish (concrete to be left exposed), and an 8mm lime render finish to the external face. Door Schedule Second Floor Level Level Mark Fire Rating Width Height SFL 51 FD60 1810 2110 SFL 53 FD30 1010 2110 SFL 54 FD30 1010 2110 SFL 55 FD30 1010 2110 SFL 56 FD60 1810 2110 SFL 57 FD60 825 2025 SFL 58 FD30 910 2110 SFL 59 FD30 1010 2110 SFL 60 FD30 1010 2110 SFL 61 FD30 1010 2110 SFL 62 FD60 910 2110 SFL 67 FD60 1810 2110 SFL 68 FD60 1810 2110 Room Schedule Second Floor Leel Number Name Level Area 47 Showers SFL 11 m² 48 Games Room SFL 99 m² 49 Music Room SFL 116 m² 50 Corridor SFL 6 m² 51 Stairwell SFL SFL 20 m² 52 Stairwell SFL SFL 14 m² 53 Stairwell Lobby SFL 9 m² 54 Protected Corridor SFL 10 m² 55 WC's SFL 24 m² 56 Stairwell SFL SFL 17 m² 57 Stairwell SFL SFL 15 m² 58 Stairwell Lobby SFL 5 m² 3D SFL 2
  • 7. 161718192122232425 13 GFL 0 FFL 3530 SFL 7030 Parapet 1 10530 15 14 Parapet 2 11000 Parapet 3 12500 Parapet 7830 Parapet 4 13000 10987 11 12 646362616059 15 67 68 69 1716 18 70 71 19 20 72 73 21 22 74 75 76 23 24 25 77 26 78 79 80 2827 60min Fire rated Cross Laminated Timber Panel Roof with a Kingspan Thermaroof TR31 covering 60min Fire rated Cross Laminated Timber Panel Parapet wall covered in roofing felt 22mm Accoya timber cladding finish to the exterior 60min Fire rated Cross Laminated Timber Panel Roof with a Kingspan Thermaroof TR31 coveringSolid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 120min Fire Rated Straw Bale Panel External Wall 60min Fire rated Cross Laminated Timber Panel Roof with a Kingspan Thermaroof TR31 covering 22mm Accoya timber cladding finish to the exterior 120min Fire Rated Straw Bale Panel External Wall Reynaers Eco System 50 insulated and ventilated windows Reynaers Eco System 50 insulated and ventilated windows Reynaers Eco System 50 insulated and ventilated windows O N M L K GFL 0 FFL 3530 SFL 7030 Parapet 1 10530 P J Parapet 2 11000 Parapet 3 12500 Parapet 7830 Parapet 4 13000 120 98 46 28 FD30 50 FD60 62 FD60 103 53 1 27 FD60 2 54 55 56 57 58 6543 120min Fire Rated Straw Bale Panel External Wall Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 60min Fire rated Cross Laminated Timber Panel Roof with a Kingspan Thermaroof TR31 covering Structural Glulaminated Columns 200mm x 250mm to EN 14080 60min Fire Rated CLT Internal Partition to BS EN 1995-2 120min Fire Rated Straw Bale Panel External Wall 60min Fire rated Cross Laminated Timber Panel Roof with a Kingspan Thermaroof TR31 covering Solid Wall Precast Concrete Panels to BS EN 1992-1-2:2004 Reynaers Eco System 50 insulated and ventilated windows Reynaers Eco System 50 insulated and ventilated windows Reynaers Eco System 50 insulated and ventilated windows 22mm Accoya timber cladding finish to the exterior Scale LECTURER Drawn by Date Project number Institute of Technology Carlow BSc. (Hons) in Architectural Technology Year 4 2013-2014 1 : 100 Combined North & East Elevations 1 Restoration, extension and upgradation to protected structures 13-January-2014 Edel Fox Noel Dunne, Sujana Sudhir & Dan O' Sullivan NEEP1A108 General Specification Block L Proposed upgrade to existing external walls Proposed - additional dry-lining board to the internal face of the existing wall, consisting of 85mm kingspan kooltherm K17 insulated dry-linig board in between steel U channels, with 12.5mm gypsum plasterboard with a 60minute fir rating in accordance with BS 476, finished with a layer of 2.5mm skim. Proposed upgrade to existing internal walls Proposed - additional dry-linig board to both faces of the partition wall, consisting of 50mm kingspan kolltherm K17 insulated dry-lining board in between steel U channels, with 12.5mm gypsum plasterboard with a 60minute fire rating in accordance with BS 476, finished with a layer of 2.5mm skim. This to be done to both sides of the wall. Proposed upgrade to existing floor Proposed - remove existing harwood flooring to be repaired where possible and if not replaced, additional 80mm kingspan Therma TF70 in between timber battens to be added on top of existing screed. Repaired hardwood flooring to be put back down on top of the new insulation. Proposed upgrade to existing roof Proposed - additional dry-lining board at internal ceiling level consisting of 85mm kingspan kooltherm K17 insulated dry-lining board in between timber battens, 12.5mm plasterboard finished with a 2.5mm skim. The existing rubber membrane needs to be stripped and the torch on felt repaired and the pebbles replaces, and the drainage issues addressed. Proposed timber stud partition Proposed - timber stud partition wall 130mm thick, consisting of 2.5mm skim a double laye of gypsum plasterboard with a 60minute fire rating, 75mm timber studs with insulation in between, double layer of 12.5mm gypsum plasterboard with a 60minute fire rating in accordance with BS 476, finished with a layer of 2.5mm skim. Proposed upgrade to existing windows Proposed - Upgrading to double glazed argon filled timber framed windows which will achieve a u-value of 1.8w/m²k. Install draught proofing strips around all windows to lower heat loss even more. Address detailing at cill to fix the water drainage problem from occuring. Proposed upgrade to existing internal doors Proposed upgrading of existing doors throughout the ground floor with smoke seals all around and covered in a layer of intumescent paint to provide a fire resistance of 30mins. New Extension Structural Foundations – 540mm X 400mm reinforced concrete ring beams to carry the load of the external and internal walls, while also allocating a space for the hollowcore flooring to sit into. The hollowcore flooring will bear half way on to each beam and be securely strapped back using T12 tie bars bedded in with the screed. Each structural glulam column will be connected back to a 360mm x 360mm square reinforced concrete column. Each concrete column will vary in depth as the ground is gradually sloped. The reinforced concrete column will be structurally supported below by a pad foundation. Each column is to have its own individual pad foundation where possible. Ground Floor Build Up – DPM to be placed between hollowcore floor slabs and ground, 200mm precast concrete hollowcore flooring slabs to be connected back to the reinforced concrete ring beams, both in accordance with BS EN 1992-1- 2:2004. 75mm structural concrete screed to be placed on top of the hollowcore flooring slabs. 80mm Kingspan Kooltherm K3 Floorboard to be placed on top of the structural screed, with 80mm x 40mm thimber battens @ 600mm c/c to be placed in between. 18mm plywood sheeting to be placed over the insulation and fixed back to the timber battens @ 600mm c/c. Finally the floor is to be finished in accordance with the use of each specific room, with 22mm oak flooring to be placed in most areas and a tile finish to be placed in the kitchen and WC areas. Intermediate Floor Build Up – On the underside, the floor is to be finished with a 2.5mm plaster skim, which is applied directly to 12.5mm gyproc board. This is followed by a 25mm services gap and then 50mm rockwool insulation, in between 25mm x 75mm timber battens @ 600mm c/c fixed back to the cross laminated timber panels. These battens are used to support and fix the gyproc board in place. The main structure of the floor is made up of a 200mm (5 x 40mm layers) cross laminated timber panels, which spans from one glulam beam to another. Above this there is another layer of 50mm rockwool insulation in between 25mm x 50mm timber battens @ 600mm c/c. Then sheets of 18mm plywood finally finished off with a 22mm oak flooring or a tile finish depending on the use of the room. Roof Build Up - On the underside, the roof is to be finished with a 2.5mm plaster skim, which is applied directly to 12.5mm gyproc board. This is followed by a 25mm services gap and then 50mm rockwool insulation, in between 25mm x 75mm timber battens @ 600mm c/c fixed back to the cross laminated timber panels. These battens are used to support and fix the gyproc board in place. The main structure of the floor is made up of a 200mm (5 x 40mm layers) cross laminated timber panels, which spans from one glulam beam to another. Above this a vapour barrier layer is to be added. Followed by 120mm Kingspan Thermaroof TR31, then a 3G base layer, finished with a triple layer of built up felt waterproofing. External Wall Build Up – From Exterior: 8mm external lime render finish, 40mm wood fibre combined breather membrane board, 12mm timbervent, 400mm wheat straw bale insulation in between 400mm ‘I’ studs spaced @ 600mm c/c, 15mm OSB, 25mm services cavity in between 25mm x 50mm vertical timber battens fixed back to the 15mm OSB, finished on the interior side with a layer of 12.5mm gyproc board and 2.5mm plaster skim finish. Each end of the straw bale panel is closed with a 43mm x 400mm glulaminated column. This system is from the manufacturer Modcell, it is the Modcell Core + panel. This wall panel achieves a u-value of 0.11 W/(m2K), a fire rating of 120mins, and an acoustic performance rating of 52db. Internal Wall Build Up – 2.5mm plaster finish, 12.5mm gyproc board, 25mm rockwool insulation in between 25mm x 25mm vertical timber battens spaced @ 600mm c/c fixed back to the cross laminated timber panel, put in place to support and fix the gyproc board to. Followed by 120mm (40mm x 3 layers) cross laminated timber wall panel in accordance with BS EN 1995-2, BS EN 12354-1 and BS EN 12354-2 in terms of fire and acoustic performance, 25mm rockwool insulation in between 25mm x 25mm vertical timber battens spaced @ 600mm c/c fixed back to the cross laminated timber panel, put in place to support and fix the gyproc board to. Finished with 12.5mm gyproc board and 2.5mm plaster skim finish. Concrete Wall Panels – 200mm reinforced precast concrete solid wall panels to be used in the stairs, stair lobby, lift shaft and protected corridor to provide structural strength and achieve the required fire rating in accordance with TGD B. the panels are also relatively soundproof so this will eliminate sound transmission throughout the building. The internal panels will have a 25mm service cavity in between 25mm x 50mm vertical timber battens, finished with 12.5mm gyproc board and a 2.5mm plaster skim finish, with the side inside the lift or stairs shaft having the concrete left exposed. The panels that are exposed to the outside will have no internal finish (concrete to be left exposed), and an 8mm lime render finish to the external face. Windows and door Specifications Reynaers ecosystem CS 86-HI CS 86-HI is a multi-chamber system for windows and doors that combines aesthetic design, optimal stability and high thermal comfort. Due to the insulating skeleton strips, CS 86-HI achieves Uf-values down to 1.2 W/m²K, making this a highly energy efficient system. Flexible expansion strips in the door vents ensure stability in all conditions. Minimum visable width inward opening window: Frame 51mm / Vent 35mm Minimum visable width outward opening flush door: Frame 42mm / Vent 102mm Thermal insulation in accordance with EN 10077-2: Achieves U-value of 1.2 W/m²K Burglar resistance: WK 2 in accordance with EnV 1627 – ENV 1630 Curtain Walling Specifications Curtain Wall CW 50 • Manufacturer: Reynaers Ltd • Product reference: Curtain Wall CW 50 Standard /Curtain Wall CW 50-FP EW 30 /Curtain Wall CW 50-FP EW 60 /Curtain Wall CW 50- HL /Curtain Wall CW 50-RA • Internal framing member: Extruded aluminium - Finish: Anodized /Polyester powder coated - Colour: - Minimum film thickness: • External cover cap: Extruded aluminium - Finish: Anodized /Polyester powder coated - Colour: - Minimum film thickness: • Doors: • Windows: Fixed light (CW50-FP) /Glazed in windows /Structural glazing - Configuration: Horizontal pivot /Parallel opener /Side hung /Tilt and turn /Top hung • Glazing: Insulating glass units /Single glazed panes • Glazing system: Dry glazed gasket • Panel/ Facing type: External Render Lime Render Render mix - 3.5 NHL : Moderate to eminently hydraulic Binder sand ratio 1: 1.5 to 1:3 depending on the support and backround conditions and the fineness of the sand. Sand grading: Sharp and Gritty 3-4mm down to 75 mirons Scratch coat - 3-5 mm, Ratio: 1 volume of NHL 4.5 to 1.5 volumes of sand Undercoat - 15-20mm, Ratio: 1 volume of NHL 3.5 to 2 volumes of sand (at this dosage consumption 0.35kg of NHL 3.5m2 per each mm of thickness) Finish coat 5-10mm, Ratio 1 volume of NHL 3.5 to 2.5 volumes of sand Caution: No water barriers should be added to the wall as lime render works in conjunction with the breathability of the wall Timber Cladding Accoya by Accys Technologies Accoya wood is made from softwood but has the qualities of hardwood, produced via a process called acetylation. Acetylation transforms the free hydroxyls in the wood into acetyl groups, reducing the wood’s ability to absorb water, making it more dimensionally stable and more durable. Manufacturer Accys Technologies Type of cladding Horizontal and vertical Wood species Softwood, for example Radiata pine Treatment Acetylation Life expectancy 50 years Maintenance Low frequency due to increased dimensional stability as coatings do not stretch and shrink Certification FSC, PEFC certified and cradle-tocradle gold standard Recyclability Can be reused or used as a biofuel to produce heat and power 1 : 100 North Elevation 1 1 : 100 East Elevation 2