Plant Layout and Facility Design
Course code: Greg 4181
Target group: 4th year GED
Chapter two
Plant location
By: Endashaw Yohannes
Kombolcha/Ethiopia
Nov, 2019
1/29/2020 1
CHAPTER TWO OUTTLINE
o Concept of plant location
o Factors governing plant location
o Theories of industrial location
o Economic survey of the site selection
1. Concept of Plant Location
o Plant location meaning: is the establishment
of an industry at a particular place.
oThe fundamental objective of location
analysis is to maximize the profits by
minimizing the total cost of production
associated with the production process.
1. Concept of Plant Location cont...
oThe principle of plant location
 is that the sum of manufacturing and distributing cost
should be at minimum for best location.
oThe necessary factors in selection of plant location
vary among industries and with changing technical and
economical conditions.
2. Circumstances for plant location decision
Four situations require an answer to the question of
plant locations:
1. New facility establishment
2. Expansion of existing facility
3. Additional facility in new territory due to growth
4. Change of existing facility location outweighed due
to new developments, economic, social, legal or
political factors
3. Mistakes in location decision Cause
o Higher investment
o Higher cost of production,
o Difficult marketing and transportation
o Dissatisfied and frustrated employees
and consumer
o Frequent interruption production
o Abnormal wastages
o Delays and substandard quality etc
4. Location Planning
o Before a location for a plant is sought, long-range forecasts
should be made anticipating the future needs of the company.
o These should be based on the
 Company’s expansion policy,
 The anticipated diversification of products,
 The changing market,
 The changing source of raw materials, and any other
foreseeable influences.
o Careful attention should be given to all the economic factors
that influence the need for the new plant and the size and
location of the plant.
o Seven basic steps in locating and building every new plant:
1. Establish the need for a new plant.
2. Determine the best geographical area for the plant on the
basis of the company’s business needs.
3. Establish the requirements
o Product to be made,
o Equipment and Buildings needed,
o Utilities necessary
oTransportation necessary,
o Number of employees, and etc.
4. Location Planning cont...
o Seven basic steps in locating and building every new plant
cont..
4. Screen many communities within the general area
decided on
5. Pinpoint a few communities for detained studies.
6. Select the best location.
7. Build the plant.
4. Location Planning cont...
Location decision has two stages
1. General location of the plant
 Factors must be considered for selecting a
region where a factory is to be located
2. The selection of a particular site
 Factors must be considered for selecting a
suitable site in that region.
5. Factors governing plant location
5.1. Factors governing General location of the plant
1) Availability of raw materials
o The site should be near to the source of raw material
o Transportation cost should be minimum
2) Proximity to markets
o The cost of transporting finished goods, advertising
and distribution cost reduced if it is near to markets
o Quick service to customer and their needs
3) Transport facilities
o Availability of road ,rail, air and ship transport
4) Availability of productive labor
o Low wages often over-emphasized
o Labor productivity important
o Labor cost per unit should be criterion: (Labor cost/day/
Units made/day)
Eg. Hourly Compensation ($)Mfg. Workers (1994)
Germany 27.37
Japan 21.38
U.S. 17.10
Hong Kong 4.79
Mexico 2.57
5) Availability and rate of power
o Electricity, coal mines, solar, wind, etc
6) Climatic and atmospheric condition
o It is a governing factor for several industries to
reduce the cost of air conditioning
E.g.. Cotton textile industries require moist climate
7) Availability of water
o All factories need soft and pure water
8) Availability of capital
o Amount of capital available determines size of a plant
and its future
9) Social and recreational facilities
o During off hours employees need amenities like parks,
retail stores, cinemas ,education centers for worker
health and work interest.
10) Business and Commercial Facilities
o Availability of financial and banking facilities for
factories constant feeding of working capital
11) Existence of related industries
• Especially for small scale industries to have common
facilities like maintenance and repairing service.
12) Other factors
o Taxes
o Government incentives
o Fire protection facilities
o Postal service
o Internet and telecommunication services
5.1. Factors governing selection of a particular
site
1) Community attitude
o The attitude of the people and the state
government
o Most communities usually welcome setting up of
industries as it provide direct and indirect job
opportunities to the local community
o However in case of polluting and adverse working
condition the local community provide resistance
2) Community facilities
o Facilities which affect quality of life like schools,
hospitals, housing, banking ,communication and other
facilities.
3) Geographical topography
o This includes subsoil conditions for building
foundation, the cost of leveling and developing the
area, laying water supply, electricity, and sewage
system.
4) Transportation facility
o Transport infrastructure for quick access and
movement.
5) Waste disposal
o Including solid, liquid and gaseous wastes disposal
Eg. The plant should be positioned so that winds
carry out fumes away from populated areas .
6) Ecology and pollution
o Check if there is any restrictions on local
administration regarding ecology and pollution
7) Size of land
o Size of land should meet current facility
needs and future expansion plans.
8) Supporting industries
o Availability of supporting industries and other
services.
6. THEORY OF INDUSTRIAL LOCATION
o The location of an industry is based on a unique set of
circumstances – these factors will enable to business to
operate at a lower cost giving them an advantage over
competitors.
o The factor that offers the most significant cost saving
will be the most important one to determine final
location
o In most plant location models, the objective is to
minimize the sum of all costs affected by location.
o Some items of cost may be higher at location A but
others may be higher at location B.
o The main aim is to seek the location that minimizes
the total cost.
o In attempting to minimize costs we should not only
consider today costs but also long run costs.
6.1. Techniques used for best plant location
1) Subjective techniques
a) Industrial precedence
o New facility is located in an area previously
selected by similar industry.
 assumption “if the location was best for similar industry
in the past it must be best for us now”.
b) Preferential Factor:
o Usually involves personal preferences
o It is not professional approach and is not good business
decision making.
C) Dominant Factor
o This occurs when one factor dominates any other
factors and could influence location decision .
Eg. Mining and petroleum drilling operations must be
located in the areas where the mineral resources are
available.
2) Qualitative techniques
o Also known as “factor ranking system”
o No comparative relationships for values with in the
factor other than position in the list is established
o Ranking is therefore unsatisfactory
3) Semi- Quantitative techniques
o Also known as “factor weighting system”
o Rating scales are used to compare locations to
locations using factors
o Variable weights are assigned to each of the factors
1. Intangible (qualitative) factors
Example: Education quality, labor skills
2. Tangible (quantitative) factors
Example: Short-run & long-run costs
4) Quantitative techniques
Important quantitative techniques
1) Break-Even Analysis
• Helps to relate costs and revenues to facility location
• It shows relation ship among volume of output, costs
and revenues.
• Costs can be generally divided as fixed and variable
cost
a. Fixed costs are the same regardless of volume of out
put.
Eg. Heating ,lighting administrative cost
b. Variable costs fluctuate directly with volume of out
put.
Eg. Direct labor and material
o Break even point indicates the level of volume for
which the total costs equals total revenues.
o BEP analysis identifies the level of out put that must
be reached in order to recover all costs of operation
through revenues.
The break even chart
To understand the role & purpose of break
even analysis
2) Economic/Cost Analysis
o It shows relation ship among volume of
output, costs and revenues among different
location .
3) Transportation Model
o This and other quantitative techniques can
be dealt more on Operation research
subjects
Examples
Criterion Weighting
Possible Factory Location
A B C D E
PROXIMITYTO:
Skilled labour 7 2 14 3 21 0 0 1 7 4 28
A pool of unskilled labour 8 5 40 2 16 0 0 4 32 2 16
A motorway 7 3 21 2 14 1 7 3 21 4 28
An airport 4 1 4 3 12 4 16 2 8 2 8
The sea / a river 0 2 0 5 0 5 0 2 0 1 0
Housing 5 4 20 3 15 0 0 3 15 4 20
Amenities 5 3 15 2 10 0 0 2 10 3 15
Potential for expansion 7 2 14 1 7 5 35 3 21 2 14
Availability of grants/incentives 8 1 8 2 16 5 40 1 8 3 24
Safety 2 3 6 2 4 5 10 2 4 2 4
Planning constraints 5 2 10 3 15 5 25 4 20 2 10
Environmental impact 4 3 12 2 8 4 16 1 4 2 8
TOTAL 164 138 149 150 175
Example Factor Weight Rating System
8-32
Example 1: Cost-Volume Analysis
Fixed and variable costs for four potential
locations
L o c a t i o n F i x e d
C o s t
V a r i a b l e
C o s t
A
B
C
D
$ 2 5 0 , 0 0 0
1 0 0 , 0 0 0
1 5 0 , 0 0 0
2 0 0 , 0 0 0
$ 1 1
3 0
2 0
3 5
8-33
Example 1: Solution
Fixed
Costs
Variable
Costs
Total
Costs
A
B
C
D
$250,000
100,000
150,000
200,000
$11(10,000)
30(10,000)
20(10,000)
35(10,000)
$360,000
400,000
350,000
550,000
8-34
Example 1: Solution
800
700
600
500
400
300
200
100
0
Annual Output (000)
$(000)
8 10 12 14 166420
A
B
C
B Superior
C Superior
A Superior
D
Plant lay out and material handling
(R.B Choudary)
1) Determination of total cost/unit Page #11
2) Example 1.2 Page #12
3) Fig 1.2 page #16
4) Table 1.2 & table 1.3 page#20,21
5) Example 1.3 # page 21
1/29/2020 36

Contenu connexe

Tendances

Plant layout design for safety aspect
Plant layout design for  safety aspectPlant layout design for  safety aspect
Plant layout design for safety aspect
Anurag Singh
 
5 need for selecting a suitable location
5 need for selecting a suitable location5 need for selecting a suitable location
5 need for selecting a suitable location
Salamat Ali
 
Facilities Planning and Design 01
Facilities Planning and Design 01Facilities Planning and Design 01
Facilities Planning and Design 01
Victor Molina
 
Process selection
Process selectionProcess selection
Process selection
Hammaduddin
 
location planning and analysis
location planning and analysislocation planning and analysis
location planning and analysis
janyne aguilar
 
Facility location and techniques
Facility location and techniquesFacility location and techniques
Facility location and techniques
Piyush Sharma
 

Tendances (20)

Process design layout
Process design layoutProcess design layout
Process design layout
 
Plant layout design for safety aspect
Plant layout design for  safety aspectPlant layout design for  safety aspect
Plant layout design for safety aspect
 
Selection Criteria of a Plant
Selection Criteria of a PlantSelection Criteria of a Plant
Selection Criteria of a Plant
 
5 need for selecting a suitable location
5 need for selecting a suitable location5 need for selecting a suitable location
5 need for selecting a suitable location
 
Plant Location Selection Decision
Plant Location Selection DecisionPlant Location Selection Decision
Plant Location Selection Decision
 
Plant location and layout
Plant location and layoutPlant location and layout
Plant location and layout
 
Cost of quality
Cost of qualityCost of quality
Cost of quality
 
Production management
Production managementProduction management
Production management
 
Facility Location Planning
Facility Location Planning Facility Location Planning
Facility Location Planning
 
Facilities Planning and Design 01
Facilities Planning and Design 01Facilities Planning and Design 01
Facilities Planning and Design 01
 
Facility Design.pptx
Facility Design.pptxFacility Design.pptx
Facility Design.pptx
 
Plant location & layout design
Plant location & layout designPlant location & layout design
Plant location & layout design
 
Process selection
Process selectionProcess selection
Process selection
 
Facility layout
Facility  layoutFacility  layout
Facility layout
 
FACILITY PLANNING
FACILITY PLANNINGFACILITY PLANNING
FACILITY PLANNING
 
Production planning, routing, scheduling, Activating, Monitoring
Production planning, routing, scheduling, Activating, MonitoringProduction planning, routing, scheduling, Activating, Monitoring
Production planning, routing, scheduling, Activating, Monitoring
 
Plant Location - Influencing factors and Location Decision Process
Plant Location - Influencing factors and Location Decision ProcessPlant Location - Influencing factors and Location Decision Process
Plant Location - Influencing factors and Location Decision Process
 
location planning and analysis
location planning and analysislocation planning and analysis
location planning and analysis
 
Facility location and techniques
Facility location and techniquesFacility location and techniques
Facility location and techniques
 
Plant location and Layout
Plant location and LayoutPlant location and Layout
Plant location and Layout
 

Similaire à PLANT LOCATION

Plant site selection and layout
Plant site selection and layoutPlant site selection and layout
Plant site selection and layout
Robin Gulati
 
1347 notes ii_ppe_304
1347 notes ii_ppe_3041347 notes ii_ppe_304
1347 notes ii_ppe_304
kriti201
 

Similaire à PLANT LOCATION (20)

Site selection and plant layout
Site selection and plant layoutSite selection and plant layout
Site selection and plant layout
 
Ch_2_105026.pdf
Ch_2_105026.pdfCh_2_105026.pdf
Ch_2_105026.pdf
 
plantlocation-160518065808.pdf
plantlocation-160518065808.pdfplantlocation-160518065808.pdf
plantlocation-160518065808.pdf
 
unit-2.pdf
unit-2.pdfunit-2.pdf
unit-2.pdf
 
Textile plant location.pptx
Textile plant location.pptxTextile plant location.pptx
Textile plant location.pptx
 
Production management -BBA
Production management -BBAProduction management -BBA
Production management -BBA
 
Unit v operations mgt
Unit v operations mgtUnit v operations mgt
Unit v operations mgt
 
plant location
plant locationplant location
plant location
 
Facility location - A Topic from Production and Operation Management
Facility location - A Topic from Production and Operation ManagementFacility location - A Topic from Production and Operation Management
Facility location - A Topic from Production and Operation Management
 
Loc Plan Ch08
Loc  Plan  Ch08Loc  Plan  Ch08
Loc Plan Ch08
 
Sisay PPT.pdf
Sisay PPT.pdfSisay PPT.pdf
Sisay PPT.pdf
 
Chapter 3 ;Plant Design.ppt
Chapter 3 ;Plant Design.pptChapter 3 ;Plant Design.ppt
Chapter 3 ;Plant Design.ppt
 
Plant site selection and layout
Plant site selection and layoutPlant site selection and layout
Plant site selection and layout
 
PLANNING AND INSTALLATION OF LAYOUT
PLANNING AND INSTALLATION OF LAYOUTPLANNING AND INSTALLATION OF LAYOUT
PLANNING AND INSTALLATION OF LAYOUT
 
Industrial Economics Lecture 4.pptx
Industrial Economics Lecture 4.pptxIndustrial Economics Lecture 4.pptx
Industrial Economics Lecture 4.pptx
 
1347 notes ii_ppe_304
1347 notes ii_ppe_3041347 notes ii_ppe_304
1347 notes ii_ppe_304
 
Weathering the Environmental Storm in China's - Beyond Compliance
Weathering the Environmental Storm in China's - Beyond ComplianceWeathering the Environmental Storm in China's - Beyond Compliance
Weathering the Environmental Storm in China's - Beyond Compliance
 
Diethyl Ether (DEE): Site Selection and Plant Layout
Diethyl Ether (DEE): Site Selection and Plant LayoutDiethyl Ether (DEE): Site Selection and Plant Layout
Diethyl Ether (DEE): Site Selection and Plant Layout
 
Chapter One:Basic principle of engineering economics PPT(pdf)
Chapter One:Basic principle of engineering economics PPT(pdf)Chapter One:Basic principle of engineering economics PPT(pdf)
Chapter One:Basic principle of engineering economics PPT(pdf)
 
Feasibility report
Feasibility reportFeasibility report
Feasibility report
 

Plus de Endashaw Yohannes Hailu (8)

PLANT LAYOUT TECHNIQUES AND MODEL
PLANT LAYOUT TECHNIQUES AND MODELPLANT LAYOUT TECHNIQUES AND MODEL
PLANT LAYOUT TECHNIQUES AND MODEL
 
PLANT LAYOUT AND TYPES OF LAYOUTS
PLANT LAYOUT AND TYPES OF LAYOUTSPLANT LAYOUT AND TYPES OF LAYOUTS
PLANT LAYOUT AND TYPES OF LAYOUTS
 
LEAN SYSTEM JIDOKA
LEAN SYSTEM JIDOKALEAN SYSTEM JIDOKA
LEAN SYSTEM JIDOKA
 
LEAN STANDARDIZED WORK TOOL
LEAN STANDARDIZED WORK TOOLLEAN STANDARDIZED WORK TOOL
LEAN STANDARDIZED WORK TOOL
 
JUST IN TIME PRODUCTION SYSTEM
JUST IN TIME PRODUCTION SYSTEMJUST IN TIME PRODUCTION SYSTEM
JUST IN TIME PRODUCTION SYSTEM
 
LEAN SYSTEM ENGINEERING
LEAN SYSTEM ENGINEERINGLEAN SYSTEM ENGINEERING
LEAN SYSTEM ENGINEERING
 
LEAN STABILITY
LEAN STABILITYLEAN STABILITY
LEAN STABILITY
 
BIRTH OF LEAN SYSTEM
BIRTH OF LEAN SYSTEMBIRTH OF LEAN SYSTEM
BIRTH OF LEAN SYSTEM
 

Dernier

VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 

Dernier (20)

KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 

PLANT LOCATION

  • 1. KIOT Plant Layout and Facility Design Course code: Greg 4181 Target group: 4th year GED Chapter two Plant location By: Endashaw Yohannes Kombolcha/Ethiopia Nov, 2019 1/29/2020 1
  • 2. CHAPTER TWO OUTTLINE o Concept of plant location o Factors governing plant location o Theories of industrial location o Economic survey of the site selection
  • 3. 1. Concept of Plant Location o Plant location meaning: is the establishment of an industry at a particular place. oThe fundamental objective of location analysis is to maximize the profits by minimizing the total cost of production associated with the production process.
  • 4. 1. Concept of Plant Location cont... oThe principle of plant location  is that the sum of manufacturing and distributing cost should be at minimum for best location. oThe necessary factors in selection of plant location vary among industries and with changing technical and economical conditions.
  • 5. 2. Circumstances for plant location decision Four situations require an answer to the question of plant locations: 1. New facility establishment 2. Expansion of existing facility 3. Additional facility in new territory due to growth 4. Change of existing facility location outweighed due to new developments, economic, social, legal or political factors
  • 6. 3. Mistakes in location decision Cause o Higher investment o Higher cost of production, o Difficult marketing and transportation o Dissatisfied and frustrated employees and consumer o Frequent interruption production o Abnormal wastages o Delays and substandard quality etc
  • 7. 4. Location Planning o Before a location for a plant is sought, long-range forecasts should be made anticipating the future needs of the company. o These should be based on the  Company’s expansion policy,  The anticipated diversification of products,  The changing market,  The changing source of raw materials, and any other foreseeable influences. o Careful attention should be given to all the economic factors that influence the need for the new plant and the size and location of the plant.
  • 8. o Seven basic steps in locating and building every new plant: 1. Establish the need for a new plant. 2. Determine the best geographical area for the plant on the basis of the company’s business needs. 3. Establish the requirements o Product to be made, o Equipment and Buildings needed, o Utilities necessary oTransportation necessary, o Number of employees, and etc. 4. Location Planning cont...
  • 9. o Seven basic steps in locating and building every new plant cont.. 4. Screen many communities within the general area decided on 5. Pinpoint a few communities for detained studies. 6. Select the best location. 7. Build the plant. 4. Location Planning cont...
  • 10. Location decision has two stages 1. General location of the plant  Factors must be considered for selecting a region where a factory is to be located 2. The selection of a particular site  Factors must be considered for selecting a suitable site in that region. 5. Factors governing plant location
  • 11. 5.1. Factors governing General location of the plant 1) Availability of raw materials o The site should be near to the source of raw material o Transportation cost should be minimum 2) Proximity to markets o The cost of transporting finished goods, advertising and distribution cost reduced if it is near to markets o Quick service to customer and their needs
  • 12. 3) Transport facilities o Availability of road ,rail, air and ship transport 4) Availability of productive labor o Low wages often over-emphasized o Labor productivity important o Labor cost per unit should be criterion: (Labor cost/day/ Units made/day) Eg. Hourly Compensation ($)Mfg. Workers (1994) Germany 27.37 Japan 21.38 U.S. 17.10 Hong Kong 4.79 Mexico 2.57
  • 13. 5) Availability and rate of power o Electricity, coal mines, solar, wind, etc 6) Climatic and atmospheric condition o It is a governing factor for several industries to reduce the cost of air conditioning E.g.. Cotton textile industries require moist climate 7) Availability of water o All factories need soft and pure water
  • 14. 8) Availability of capital o Amount of capital available determines size of a plant and its future 9) Social and recreational facilities o During off hours employees need amenities like parks, retail stores, cinemas ,education centers for worker health and work interest. 10) Business and Commercial Facilities o Availability of financial and banking facilities for factories constant feeding of working capital
  • 15. 11) Existence of related industries • Especially for small scale industries to have common facilities like maintenance and repairing service. 12) Other factors o Taxes o Government incentives o Fire protection facilities o Postal service o Internet and telecommunication services
  • 16. 5.1. Factors governing selection of a particular site 1) Community attitude o The attitude of the people and the state government o Most communities usually welcome setting up of industries as it provide direct and indirect job opportunities to the local community o However in case of polluting and adverse working condition the local community provide resistance
  • 17. 2) Community facilities o Facilities which affect quality of life like schools, hospitals, housing, banking ,communication and other facilities. 3) Geographical topography o This includes subsoil conditions for building foundation, the cost of leveling and developing the area, laying water supply, electricity, and sewage system.
  • 18. 4) Transportation facility o Transport infrastructure for quick access and movement. 5) Waste disposal o Including solid, liquid and gaseous wastes disposal Eg. The plant should be positioned so that winds carry out fumes away from populated areas .
  • 19. 6) Ecology and pollution o Check if there is any restrictions on local administration regarding ecology and pollution 7) Size of land o Size of land should meet current facility needs and future expansion plans. 8) Supporting industries o Availability of supporting industries and other services.
  • 20. 6. THEORY OF INDUSTRIAL LOCATION o The location of an industry is based on a unique set of circumstances – these factors will enable to business to operate at a lower cost giving them an advantage over competitors. o The factor that offers the most significant cost saving will be the most important one to determine final location
  • 21. o In most plant location models, the objective is to minimize the sum of all costs affected by location. o Some items of cost may be higher at location A but others may be higher at location B. o The main aim is to seek the location that minimizes the total cost. o In attempting to minimize costs we should not only consider today costs but also long run costs.
  • 22. 6.1. Techniques used for best plant location 1) Subjective techniques a) Industrial precedence o New facility is located in an area previously selected by similar industry.  assumption “if the location was best for similar industry in the past it must be best for us now”. b) Preferential Factor: o Usually involves personal preferences o It is not professional approach and is not good business decision making.
  • 23. C) Dominant Factor o This occurs when one factor dominates any other factors and could influence location decision . Eg. Mining and petroleum drilling operations must be located in the areas where the mineral resources are available.
  • 24. 2) Qualitative techniques o Also known as “factor ranking system” o No comparative relationships for values with in the factor other than position in the list is established o Ranking is therefore unsatisfactory
  • 25. 3) Semi- Quantitative techniques o Also known as “factor weighting system” o Rating scales are used to compare locations to locations using factors o Variable weights are assigned to each of the factors 1. Intangible (qualitative) factors Example: Education quality, labor skills 2. Tangible (quantitative) factors Example: Short-run & long-run costs
  • 26. 4) Quantitative techniques Important quantitative techniques 1) Break-Even Analysis • Helps to relate costs and revenues to facility location • It shows relation ship among volume of output, costs and revenues. • Costs can be generally divided as fixed and variable cost
  • 27. a. Fixed costs are the same regardless of volume of out put. Eg. Heating ,lighting administrative cost b. Variable costs fluctuate directly with volume of out put. Eg. Direct labor and material o Break even point indicates the level of volume for which the total costs equals total revenues. o BEP analysis identifies the level of out put that must be reached in order to recover all costs of operation through revenues.
  • 28. The break even chart To understand the role & purpose of break even analysis
  • 29. 2) Economic/Cost Analysis o It shows relation ship among volume of output, costs and revenues among different location . 3) Transportation Model o This and other quantitative techniques can be dealt more on Operation research subjects
  • 31. Criterion Weighting Possible Factory Location A B C D E PROXIMITYTO: Skilled labour 7 2 14 3 21 0 0 1 7 4 28 A pool of unskilled labour 8 5 40 2 16 0 0 4 32 2 16 A motorway 7 3 21 2 14 1 7 3 21 4 28 An airport 4 1 4 3 12 4 16 2 8 2 8 The sea / a river 0 2 0 5 0 5 0 2 0 1 0 Housing 5 4 20 3 15 0 0 3 15 4 20 Amenities 5 3 15 2 10 0 0 2 10 3 15 Potential for expansion 7 2 14 1 7 5 35 3 21 2 14 Availability of grants/incentives 8 1 8 2 16 5 40 1 8 3 24 Safety 2 3 6 2 4 5 10 2 4 2 4 Planning constraints 5 2 10 3 15 5 25 4 20 2 10 Environmental impact 4 3 12 2 8 4 16 1 4 2 8 TOTAL 164 138 149 150 175 Example Factor Weight Rating System
  • 32. 8-32 Example 1: Cost-Volume Analysis Fixed and variable costs for four potential locations L o c a t i o n F i x e d C o s t V a r i a b l e C o s t A B C D $ 2 5 0 , 0 0 0 1 0 0 , 0 0 0 1 5 0 , 0 0 0 2 0 0 , 0 0 0 $ 1 1 3 0 2 0 3 5
  • 34. 8-34 Example 1: Solution 800 700 600 500 400 300 200 100 0 Annual Output (000) $(000) 8 10 12 14 166420 A B C B Superior C Superior A Superior D
  • 35. Plant lay out and material handling (R.B Choudary) 1) Determination of total cost/unit Page #11 2) Example 1.2 Page #12 3) Fig 1.2 page #16 4) Table 1.2 & table 1.3 page#20,21 5) Example 1.3 # page 21