CHAPTER 19: PRODUCTIVITY
Responses to Questions
1. Productivity improvement is a continuous activity. It can be achieved
through improvements in technology, in management systems and
procedures, in skills and knowledge improvement – all of these backed by
effective leadership motivating the people working with the firm and
aligning their capabilities and motivations with the goals of the firm.
Productivity improvement as a ‘one shot’ project will be temporary and
unsustainable.
2. A productivity measure is situation-dependent. There could be different
inputs and outputs giving rise to various measures of productivity.
Different measures offer different perspectives of productivity.
Management has to take an integrated view.
3. Total Factor Productivity (TFP) has been defined in the chapter and it is
not the sum of all partial productivities.
4. Partial Productivities
With respect to the inputs:
Human: Sales 140 + 250 + 90 = 480
Input 14 + 23 + 12 49
≡ Rs. million per Rupee of human effort
____ 480___ = 480 ≡ Sales to Capital
Capital: 28 + 81 + 14 123 Input Ratio
Materials: _ 480___ = 480 ≡ Sales to Material
72 +108 + 24 204 Input Ratio
Total Productivities of Products
AC Motors: ____ 140___ = 140 ≡ Sales to Total
14+28+72 +9 123 Inputs
DC Motors: 250
123 ≡ Sales to Total Inputs
Transformers: 90
123 ≡ Sales to Total Inputs
2
Total Factor Productivity (TFP) of the Firm:
140 + 250 + 90 = 480
(14+23+12+28+81+14 376
+72+108 +24+ 9+20+10)
5. Partial productivity measures are useful but insufficient in telling a
complete story.
6. Managerial productivity could be measured by the short term and long
term results produced by a manager. While the long term results would
depend highly upon a manager’s ability to provide vision, to lead, to
motivate and to give direction, he could also be measured based upon the
performance in the Key Result Areas.
7. Sur/petition is about ‘surprising’ the competition by taking action through a
fundamental rethinking about the business, systems and organization.
‘Com’petition involves generally going along with the other players and
playing their game; while ‘sur’petition would surprise them through a total
reengineering of the business and its processes and thus playing a
different game. The delightful surprise is also for the customers.
8. Problem-solving approach is reactive (after the problem has arisen) and is
not proactive. While solving problems – when they arise – is an essential
action, it is better to ensure that problems do not arise at all or,
alternatively, kept to a minimum. Problem-solving approach, due to its
reactive nature, tends to be a piece-meal approach. What is needed is an
integrated approach.
9. Productivity happens only when the products/services get sold, which can
happen only when the customers (or prospective ones) are happy to buy
and use the product/service. Since productivity is not a one-shot affair,
customer-orientation is a must.
10.Being ‘proactive’ means taking action in anticipation of or prior to a certain
event/circumstance occurring.
A company can be proactive in the market by anticipating about the
customers’ needs or expectations. In such a company, the
production/operations capacity and the product/service would be ready the
moment the customers want it. Similarly, a maintenance action can also
be done prior to an actual breakdown occurring. Thus, there could be a
proactive preventive maintenance action which enhances productivity of
the machines and that of the operations system.
11.Generic Benchmarking could be a proactive action.
3
Processes/procedures of dissimilar industries could be used or emulated
to improve productivities. Even internal benchmarking or competitive or
functional benchmarking could suggest several proactive actions.
Examples have been given in the text book.
12.TQM, Benchmarking and BPR are organisation-wide exercises to improve
productivity. So, they are connected. However, while TQM approach is
more organic and evolving, the BPR approach is more surgical or radical
in nature. That does not suggest that the aspect of customer-orientation
which is emphatic in BPR cannot be used in TQM. Also, TQM can always
use inputs from benchmarking; so can BPR. Similarly the TQM thinking on
leadership, human resource management and on organization goals can
be used in BPR.
13.With the advances in technology and use of automation, there is a danger
of a reduction in human interactions within in an organisation. In such a
case, the organizational climate might get affected. Also, organizational
learning might get affected. Moreover, technology may make certain jobs
redundant and the staff in those jobs may need to be re-trained for other
jobs. All this requires much Human Resource Development action. This is
true of both manufacturing and service industries.
14. Yes. In fact, many Japanese management techniques / philosophies
seem to exhibit the ‘family’ culture. Family involves a committed team
work. This concept could be transferred to the work place. But, for
anything to work a committed top management is essential.
15.Western and Japanese management are now coming closer and such
distinctions will soon vanish with increased globalization. However if
‘traditional’ means ‘earlier’ styles, then the human dimension has been
more emphasized in the Japanese style of management with its Quality
circles, Productivity teams, Life long employment and such other
practices.
Traditional Western and Japanese styles could be used in such a way as
to complement each other. Only when a firm does not evolve and utilize
what is good elsewhere does the firm start getting slowly out-dated.
16.Social values do have a large impact on the attitudes of managers and
other staff of the Company. Management styles cannot be divorced from
society and its ways of functioning. Therefore, work culture does depend
upon the social values and hence productivity also gets affected. For
instance, in India the family culture would have its repercussions in the
management of an enterprise. Similarly, the concept of time in India had
been different from that in the occident. However, with rapid globalization
4
the social values are merging with each other and management styles are
getting increasingly integrated.
5
Chapter 19: Productivity
Objective Questions
1. Total Factor productivity is:
a. the summation of partial productivities
b. the summation of indirect productivities
c. the ratio of Net sales to Fixed assets
√d. none of the above.
2. Inventory turnover is:
√a. Sales/Inventory
b. Inventory / Production costs
c. Inventory / sales
d. Production costs / Inventory
3. Efficiency is to Effectiveness as:
a. Ordinary is to Extraordinary
b. Accuracy is to Precision
√c. Precision is to Accuracy
d. Business result is to Strategic planning.
4. Benchmarking and BPR are related in the following way:
a. BPR is a must for a good Benchmarking exercise
b. Benchmarking looks at industry averages, while BPR looks at
radical improvements.
c. Benchmarking depends heavily on the human element, just as in
BPR.
√d. Benchmarking is a must for BPR.
5. Tata Business Excellence Model is based upon internationally acclaimed
a. Deming award
√b. Baldridge award
c. Juran award
d. Drucker award.
6. Generic Benchmarking can be used when:
a. dissimilar processes are compared in dissimilar industries.
b. dissimilar processes are compared in similar industries
√c. some processes are same in dissimilar industries
d. some industries are common to dissimilar processes
6
7. The difference between ‘processes’ in BPR parlance and ‘operations’ is:
a. Operations are organizational objective oriented unlike the
processes
b. Operations concern with results unlike the processes.
√c. Processes flow horizontally and across various functions unlike
operations
d. Processes flow vertically and across various functions unlike
operations.
8. If 180 pieces are produced at a standard price of 1000 each, with a labour
cost of Rs. 8000, material cost of Rs. 12000 and overhead of Rs.16000,
the multifactor productivity would be
a. 2.5 √b. 5.0 c. 7.5 c. 10.0

Contenu connexe

Tendances

Om0017 advanced production planning and control
Om0017   advanced production planning and controlOm0017   advanced production planning and control
Om0017 advanced production planning and controlsmumbahelp
 
Om0017 advanced production planning and control
Om0017   advanced production planning and controlOm0017   advanced production planning and control
Om0017 advanced production planning and controlsmumbahelp
 
Msc Graduating project : The agile method of management
Msc Graduating project : The agile method of managementMsc Graduating project : The agile method of management
Msc Graduating project : The agile method of managementLoïc Deguilhem
 
Total quality management
Total quality managementTotal quality management
Total quality managementSatyendra Patel
 
Forum total quality manangemen
Forum total quality manangemenForum total quality manangemen
Forum total quality manangemenJudith Machisaca
 
Business Process Reengineering
Business Process ReengineeringBusiness Process Reengineering
Business Process ReengineeringMr. Murali
 
Cv april 2016
Cv april 2016Cv april 2016
Cv april 2016kumar S.B
 
Managing Operations Generic
Managing Operations GenericManaging Operations Generic
Managing Operations Genericstevepollard
 
Tqm indian auto component questionnaire
Tqm indian auto component questionnaireTqm indian auto component questionnaire
Tqm indian auto component questionnaireSatyendra Patel
 
Operation and Production Management
Operation and Production ManagementOperation and Production Management
Operation and Production ManagementSeetal Daas
 
Importance of Knowledge management for sustaining competitive advantage
Importance of Knowledge management for sustaining competitive advantageImportance of Knowledge management for sustaining competitive advantage
Importance of Knowledge management for sustaining competitive advantageSindhu Dasu
 
Organization planning, design and development
Organization planning, design and developmentOrganization planning, design and development
Organization planning, design and developmentKishor Tayade
 
Resistance to Change (Nokia Case Study)
Resistance to Change (Nokia Case Study)Resistance to Change (Nokia Case Study)
Resistance to Change (Nokia Case Study)Yashaswini Agarwal
 
BUS 51 - Mosley7e ch14
BUS 51 - Mosley7e ch14BUS 51 - Mosley7e ch14
BUS 51 - Mosley7e ch14kgordonb
 
Sample Report on Logistic Operation management by Global Assignment Help
Sample Report on Logistic Operation management by Global Assignment HelpSample Report on Logistic Operation management by Global Assignment Help
Sample Report on Logistic Operation management by Global Assignment HelpAmelia Jones
 
VTU MBA-TQM 12MBA42 Module 2
VTU MBA-TQM 12MBA42 Module 2VTU MBA-TQM 12MBA42 Module 2
VTU MBA-TQM 12MBA42 Module 2Adani University
 
The Role of Strategic Management and Modern Agricultural Technology in Develo...
The Role of Strategic Management and Modern Agricultural Technology in Develo...The Role of Strategic Management and Modern Agricultural Technology in Develo...
The Role of Strategic Management and Modern Agricultural Technology in Develo...Dr. Amarjeet Singh
 
Management of operational efficiency
Management of operational efficiencyManagement of operational efficiency
Management of operational efficiencyAlexander Decker
 

Tendances (19)

Om0017 advanced production planning and control
Om0017   advanced production planning and controlOm0017   advanced production planning and control
Om0017 advanced production planning and control
 
Om0017 advanced production planning and control
Om0017   advanced production planning and controlOm0017   advanced production planning and control
Om0017 advanced production planning and control
 
Msc Graduating project : The agile method of management
Msc Graduating project : The agile method of managementMsc Graduating project : The agile method of management
Msc Graduating project : The agile method of management
 
Total quality management
Total quality managementTotal quality management
Total quality management
 
Forum total quality manangemen
Forum total quality manangemenForum total quality manangemen
Forum total quality manangemen
 
Business Process Reengineering
Business Process ReengineeringBusiness Process Reengineering
Business Process Reengineering
 
Cv april 2016
Cv april 2016Cv april 2016
Cv april 2016
 
Managing Operations Generic
Managing Operations GenericManaging Operations Generic
Managing Operations Generic
 
Tqm indian auto component questionnaire
Tqm indian auto component questionnaireTqm indian auto component questionnaire
Tqm indian auto component questionnaire
 
Operation and Production Management
Operation and Production ManagementOperation and Production Management
Operation and Production Management
 
TQM, VTU, Unit 5
TQM, VTU, Unit 5TQM, VTU, Unit 5
TQM, VTU, Unit 5
 
Importance of Knowledge management for sustaining competitive advantage
Importance of Knowledge management for sustaining competitive advantageImportance of Knowledge management for sustaining competitive advantage
Importance of Knowledge management for sustaining competitive advantage
 
Organization planning, design and development
Organization planning, design and developmentOrganization planning, design and development
Organization planning, design and development
 
Resistance to Change (Nokia Case Study)
Resistance to Change (Nokia Case Study)Resistance to Change (Nokia Case Study)
Resistance to Change (Nokia Case Study)
 
BUS 51 - Mosley7e ch14
BUS 51 - Mosley7e ch14BUS 51 - Mosley7e ch14
BUS 51 - Mosley7e ch14
 
Sample Report on Logistic Operation management by Global Assignment Help
Sample Report on Logistic Operation management by Global Assignment HelpSample Report on Logistic Operation management by Global Assignment Help
Sample Report on Logistic Operation management by Global Assignment Help
 
VTU MBA-TQM 12MBA42 Module 2
VTU MBA-TQM 12MBA42 Module 2VTU MBA-TQM 12MBA42 Module 2
VTU MBA-TQM 12MBA42 Module 2
 
The Role of Strategic Management and Modern Agricultural Technology in Develo...
The Role of Strategic Management and Modern Agricultural Technology in Develo...The Role of Strategic Management and Modern Agricultural Technology in Develo...
The Role of Strategic Management and Modern Agricultural Technology in Develo...
 
Management of operational efficiency
Management of operational efficiencyManagement of operational efficiency
Management of operational efficiency
 

En vedette (12)

Ch3 verbal
Ch3 verbalCh3 verbal
Ch3 verbal
 
Chapter 19
Chapter 19 Chapter 19
Chapter 19
 
Spare Parts Management
Spare Parts ManagementSpare Parts Management
Spare Parts Management
 
SPARE PARTS
SPARE PARTSSPARE PARTS
SPARE PARTS
 
3..maintenance management
3..maintenance management3..maintenance management
3..maintenance management
 
Maintenance management
Maintenance managementMaintenance management
Maintenance management
 
Maintenance management
Maintenance managementMaintenance management
Maintenance management
 
Maintenance
MaintenanceMaintenance
Maintenance
 
Maintenence management
Maintenence managementMaintenence management
Maintenence management
 
Types of maintenance
Types of maintenanceTypes of maintenance
Types of maintenance
 
Maintenance Management
Maintenance ManagementMaintenance Management
Maintenance Management
 
Effective Spare Parts Management - 8 rules
Effective Spare Parts Management - 8 rulesEffective Spare Parts Management - 8 rules
Effective Spare Parts Management - 8 rules
 

Similaire à Production & Operation Management Chapter19[1]

Drucker Master Class Day Breakout Exercises
Drucker Master Class Day Breakout ExercisesDrucker Master Class Day Breakout Exercises
Drucker Master Class Day Breakout ExercisesMason Stevenson
 
Production & Operation ManagementChapter2[1]
Production & Operation ManagementChapter2[1]Production & Operation ManagementChapter2[1]
Production & Operation ManagementChapter2[1]Hariharan Ponnusamy
 
How to Introduce Operational Excellence in your Organisation?
How to Introduce Operational Excellence in your Organisation?How to Introduce Operational Excellence in your Organisation?
How to Introduce Operational Excellence in your Organisation?Tina Arora
 
The change.asia - results not reports
The change.asia  - results not reportsThe change.asia  - results not reports
The change.asia - results not reportspck100
 
Creating the Performance Culture
Creating the Performance CultureCreating the Performance Culture
Creating the Performance CultureScott Staunton
 
1502 (V2) Managerial Training PPT.pptx
1502 (V2) Managerial Training PPT.pptx1502 (V2) Managerial Training PPT.pptx
1502 (V2) Managerial Training PPT.pptxNeha Kajulkar
 
Om0017 advanced production planning and control
Om0017   advanced production planning and controlOm0017   advanced production planning and control
Om0017 advanced production planning and controlStudy Stuff
 
Uhy Lean Core
Uhy Lean CoreUhy Lean Core
Uhy Lean Corealanlund
 
Str 581 week 2 discussion questions
Str 581 week 2 discussion questionsStr 581 week 2 discussion questions
Str 581 week 2 discussion questionsfranrijfriqi1988
 
Total Quality Management Project Charter for HP India
Total Quality Management Project Charter for HP IndiaTotal Quality Management Project Charter for HP India
Total Quality Management Project Charter for HP IndiaKaustav Lahiri
 

Similaire à Production & Operation Management Chapter19[1] (20)

Drucker Master Class Day Breakout Exercises
Drucker Master Class Day Breakout ExercisesDrucker Master Class Day Breakout Exercises
Drucker Master Class Day Breakout Exercises
 
Chapter2[1]
Chapter2[1]Chapter2[1]
Chapter2[1]
 
Production & Operation ManagementChapter2[1]
Production & Operation ManagementChapter2[1]Production & Operation ManagementChapter2[1]
Production & Operation ManagementChapter2[1]
 
Notes c1
Notes c1Notes c1
Notes c1
 
Tqm points
Tqm pointsTqm points
Tqm points
 
How to Introduce Operational Excellence in your Organisation?
How to Introduce Operational Excellence in your Organisation?How to Introduce Operational Excellence in your Organisation?
How to Introduce Operational Excellence in your Organisation?
 
OE -2013.ppt
OE -2013.pptOE -2013.ppt
OE -2013.ppt
 
The change.asia - results not reports
The change.asia  - results not reportsThe change.asia  - results not reports
The change.asia - results not reports
 
ISS_5
ISS_5ISS_5
ISS_5
 
Operations strategy
Operations strategyOperations strategy
Operations strategy
 
Creating the Performance Culture
Creating the Performance CultureCreating the Performance Culture
Creating the Performance Culture
 
1502 (V2) Managerial Training PPT.pptx
1502 (V2) Managerial Training PPT.pptx1502 (V2) Managerial Training PPT.pptx
1502 (V2) Managerial Training PPT.pptx
 
Om0017 advanced production planning and control
Om0017   advanced production planning and controlOm0017   advanced production planning and control
Om0017 advanced production planning and control
 
Uhy Lean Core
Uhy Lean CoreUhy Lean Core
Uhy Lean Core
 
Business policy & strategy pp
Business policy & strategy ppBusiness policy & strategy pp
Business policy & strategy pp
 
Str 581 week 2 discussion questions
Str 581 week 2 discussion questionsStr 581 week 2 discussion questions
Str 581 week 2 discussion questions
 
Organizational effectiveness goes digital
Organizational effectiveness goes digital  Organizational effectiveness goes digital
Organizational effectiveness goes digital
 
Lean management
Lean managementLean management
Lean management
 
7 M's of Management
7 M's of Management7 M's of Management
7 M's of Management
 
Total Quality Management Project Charter for HP India
Total Quality Management Project Charter for HP IndiaTotal Quality Management Project Charter for HP India
Total Quality Management Project Charter for HP India
 

Plus de Hariharan Ponnusamy

Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter36[1]
Production & Operation Management Chapter36[1]Production & Operation Management Chapter36[1]
Production & Operation Management Chapter36[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter32[1]
Production & Operation Management Chapter32[1]Production & Operation Management Chapter32[1]
Production & Operation Management Chapter32[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter30[1]
Production & Operation Management Chapter30[1]Production & Operation Management Chapter30[1]
Production & Operation Management Chapter30[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter29[1]
Production & Operation Management Chapter29[1]Production & Operation Management Chapter29[1]
Production & Operation Management Chapter29[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter28[1]
Production & Operation Management Chapter28[1]Production & Operation Management Chapter28[1]
Production & Operation Management Chapter28[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter27[1]
Production & Operation Management Chapter27[1]Production & Operation Management Chapter27[1]
Production & Operation Management Chapter27[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter26[1]
Production & Operation Management Chapter26[1]Production & Operation Management Chapter26[1]
Production & Operation Management Chapter26[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter25[1]
Production & Operation Management Chapter25[1]Production & Operation Management Chapter25[1]
Production & Operation Management Chapter25[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter24[1]
Production & Operation Management Chapter24[1]Production & Operation Management Chapter24[1]
Production & Operation Management Chapter24[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter22[1]
Production & Operation Management Chapter22[1]Production & Operation Management Chapter22[1]
Production & Operation Management Chapter22[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter21[1]
Production & Operation Management Chapter21[1]Production & Operation Management Chapter21[1]
Production & Operation Management Chapter21[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter20[1]
Production & Operation Management Chapter20[1]Production & Operation Management Chapter20[1]
Production & Operation Management Chapter20[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter16[1]
Production & Operation Management Chapter16[1]Production & Operation Management Chapter16[1]
Production & Operation Management Chapter16[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter14[1]
Production & Operation Management Chapter14[1]Production & Operation Management Chapter14[1]
Production & Operation Management Chapter14[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter13[1]
Production & Operation Management Chapter13[1]Production & Operation Management Chapter13[1]
Production & Operation Management Chapter13[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter12[1]
Production & Operation Management Chapter12[1]Production & Operation Management Chapter12[1]
Production & Operation Management Chapter12[1]Hariharan Ponnusamy
 
Production & Operation Management Chapter11[1]
Production & Operation Management Chapter11[1]Production & Operation Management Chapter11[1]
Production & Operation Management Chapter11[1]Hariharan Ponnusamy
 

Plus de Hariharan Ponnusamy (20)

Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]Production & Operation Management Chapter 34, 35[1]
Production & Operation Management Chapter 34, 35[1]
 
Production & Operation Management Chapter36[1]
Production & Operation Management Chapter36[1]Production & Operation Management Chapter36[1]
Production & Operation Management Chapter36[1]
 
Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]
 
Production & Operation Management Chapter32[1]
Production & Operation Management Chapter32[1]Production & Operation Management Chapter32[1]
Production & Operation Management Chapter32[1]
 
Production & Operation Management Chapter30[1]
Production & Operation Management Chapter30[1]Production & Operation Management Chapter30[1]
Production & Operation Management Chapter30[1]
 
Production & Operation Management Chapter29[1]
Production & Operation Management Chapter29[1]Production & Operation Management Chapter29[1]
Production & Operation Management Chapter29[1]
 
Production & Operation Management Chapter28[1]
Production & Operation Management Chapter28[1]Production & Operation Management Chapter28[1]
Production & Operation Management Chapter28[1]
 
Production & Operation Management Chapter27[1]
Production & Operation Management Chapter27[1]Production & Operation Management Chapter27[1]
Production & Operation Management Chapter27[1]
 
Production & Operation Management Chapter26[1]
Production & Operation Management Chapter26[1]Production & Operation Management Chapter26[1]
Production & Operation Management Chapter26[1]
 
Production & Operation Management Chapter25[1]
Production & Operation Management Chapter25[1]Production & Operation Management Chapter25[1]
Production & Operation Management Chapter25[1]
 
Production & Operation Management Chapter24[1]
Production & Operation Management Chapter24[1]Production & Operation Management Chapter24[1]
Production & Operation Management Chapter24[1]
 
Production & Operation Management Chapter22[1]
Production & Operation Management Chapter22[1]Production & Operation Management Chapter22[1]
Production & Operation Management Chapter22[1]
 
Production & Operation Management Chapter21[1]
Production & Operation Management Chapter21[1]Production & Operation Management Chapter21[1]
Production & Operation Management Chapter21[1]
 
Production & Operation Management Chapter20[1]
Production & Operation Management Chapter20[1]Production & Operation Management Chapter20[1]
Production & Operation Management Chapter20[1]
 
Production & Operation Management Chapter16[1]
Production & Operation Management Chapter16[1]Production & Operation Management Chapter16[1]
Production & Operation Management Chapter16[1]
 
Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]Production & Operation Management Chapter15[1]
Production & Operation Management Chapter15[1]
 
Production & Operation Management Chapter14[1]
Production & Operation Management Chapter14[1]Production & Operation Management Chapter14[1]
Production & Operation Management Chapter14[1]
 
Production & Operation Management Chapter13[1]
Production & Operation Management Chapter13[1]Production & Operation Management Chapter13[1]
Production & Operation Management Chapter13[1]
 
Production & Operation Management Chapter12[1]
Production & Operation Management Chapter12[1]Production & Operation Management Chapter12[1]
Production & Operation Management Chapter12[1]
 
Production & Operation Management Chapter11[1]
Production & Operation Management Chapter11[1]Production & Operation Management Chapter11[1]
Production & Operation Management Chapter11[1]
 

Dernier

Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field ArtilleryKennethSwanberg
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelNitya salvi
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdfArtiSrivastava23
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownSandaliGurusinghe2
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxssuserf63bd7
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentNimot Muili
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxAaron Stannard
 
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siligurimeghakumariji156
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Ram V Chary
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdfAlejandromexEspino
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalWilliam (Bill) H. Bender, FCSI
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamraAllTops
 

Dernier (16)

Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdf
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
 

Production & Operation Management Chapter19[1]

  • 1. CHAPTER 19: PRODUCTIVITY Responses to Questions 1. Productivity improvement is a continuous activity. It can be achieved through improvements in technology, in management systems and procedures, in skills and knowledge improvement – all of these backed by effective leadership motivating the people working with the firm and aligning their capabilities and motivations with the goals of the firm. Productivity improvement as a ‘one shot’ project will be temporary and unsustainable. 2. A productivity measure is situation-dependent. There could be different inputs and outputs giving rise to various measures of productivity. Different measures offer different perspectives of productivity. Management has to take an integrated view. 3. Total Factor Productivity (TFP) has been defined in the chapter and it is not the sum of all partial productivities. 4. Partial Productivities With respect to the inputs: Human: Sales 140 + 250 + 90 = 480 Input 14 + 23 + 12 49 ≡ Rs. million per Rupee of human effort ____ 480___ = 480 ≡ Sales to Capital Capital: 28 + 81 + 14 123 Input Ratio Materials: _ 480___ = 480 ≡ Sales to Material 72 +108 + 24 204 Input Ratio Total Productivities of Products AC Motors: ____ 140___ = 140 ≡ Sales to Total 14+28+72 +9 123 Inputs DC Motors: 250 123 ≡ Sales to Total Inputs Transformers: 90 123 ≡ Sales to Total Inputs
  • 2. 2 Total Factor Productivity (TFP) of the Firm: 140 + 250 + 90 = 480 (14+23+12+28+81+14 376 +72+108 +24+ 9+20+10) 5. Partial productivity measures are useful but insufficient in telling a complete story. 6. Managerial productivity could be measured by the short term and long term results produced by a manager. While the long term results would depend highly upon a manager’s ability to provide vision, to lead, to motivate and to give direction, he could also be measured based upon the performance in the Key Result Areas. 7. Sur/petition is about ‘surprising’ the competition by taking action through a fundamental rethinking about the business, systems and organization. ‘Com’petition involves generally going along with the other players and playing their game; while ‘sur’petition would surprise them through a total reengineering of the business and its processes and thus playing a different game. The delightful surprise is also for the customers. 8. Problem-solving approach is reactive (after the problem has arisen) and is not proactive. While solving problems – when they arise – is an essential action, it is better to ensure that problems do not arise at all or, alternatively, kept to a minimum. Problem-solving approach, due to its reactive nature, tends to be a piece-meal approach. What is needed is an integrated approach. 9. Productivity happens only when the products/services get sold, which can happen only when the customers (or prospective ones) are happy to buy and use the product/service. Since productivity is not a one-shot affair, customer-orientation is a must. 10.Being ‘proactive’ means taking action in anticipation of or prior to a certain event/circumstance occurring. A company can be proactive in the market by anticipating about the customers’ needs or expectations. In such a company, the production/operations capacity and the product/service would be ready the moment the customers want it. Similarly, a maintenance action can also be done prior to an actual breakdown occurring. Thus, there could be a proactive preventive maintenance action which enhances productivity of the machines and that of the operations system. 11.Generic Benchmarking could be a proactive action.
  • 3. 3 Processes/procedures of dissimilar industries could be used or emulated to improve productivities. Even internal benchmarking or competitive or functional benchmarking could suggest several proactive actions. Examples have been given in the text book. 12.TQM, Benchmarking and BPR are organisation-wide exercises to improve productivity. So, they are connected. However, while TQM approach is more organic and evolving, the BPR approach is more surgical or radical in nature. That does not suggest that the aspect of customer-orientation which is emphatic in BPR cannot be used in TQM. Also, TQM can always use inputs from benchmarking; so can BPR. Similarly the TQM thinking on leadership, human resource management and on organization goals can be used in BPR. 13.With the advances in technology and use of automation, there is a danger of a reduction in human interactions within in an organisation. In such a case, the organizational climate might get affected. Also, organizational learning might get affected. Moreover, technology may make certain jobs redundant and the staff in those jobs may need to be re-trained for other jobs. All this requires much Human Resource Development action. This is true of both manufacturing and service industries. 14. Yes. In fact, many Japanese management techniques / philosophies seem to exhibit the ‘family’ culture. Family involves a committed team work. This concept could be transferred to the work place. But, for anything to work a committed top management is essential. 15.Western and Japanese management are now coming closer and such distinctions will soon vanish with increased globalization. However if ‘traditional’ means ‘earlier’ styles, then the human dimension has been more emphasized in the Japanese style of management with its Quality circles, Productivity teams, Life long employment and such other practices. Traditional Western and Japanese styles could be used in such a way as to complement each other. Only when a firm does not evolve and utilize what is good elsewhere does the firm start getting slowly out-dated. 16.Social values do have a large impact on the attitudes of managers and other staff of the Company. Management styles cannot be divorced from society and its ways of functioning. Therefore, work culture does depend upon the social values and hence productivity also gets affected. For instance, in India the family culture would have its repercussions in the management of an enterprise. Similarly, the concept of time in India had been different from that in the occident. However, with rapid globalization
  • 4. 4 the social values are merging with each other and management styles are getting increasingly integrated.
  • 5. 5 Chapter 19: Productivity Objective Questions 1. Total Factor productivity is: a. the summation of partial productivities b. the summation of indirect productivities c. the ratio of Net sales to Fixed assets √d. none of the above. 2. Inventory turnover is: √a. Sales/Inventory b. Inventory / Production costs c. Inventory / sales d. Production costs / Inventory 3. Efficiency is to Effectiveness as: a. Ordinary is to Extraordinary b. Accuracy is to Precision √c. Precision is to Accuracy d. Business result is to Strategic planning. 4. Benchmarking and BPR are related in the following way: a. BPR is a must for a good Benchmarking exercise b. Benchmarking looks at industry averages, while BPR looks at radical improvements. c. Benchmarking depends heavily on the human element, just as in BPR. √d. Benchmarking is a must for BPR. 5. Tata Business Excellence Model is based upon internationally acclaimed a. Deming award √b. Baldridge award c. Juran award d. Drucker award. 6. Generic Benchmarking can be used when: a. dissimilar processes are compared in dissimilar industries. b. dissimilar processes are compared in similar industries √c. some processes are same in dissimilar industries d. some industries are common to dissimilar processes
  • 6. 6 7. The difference between ‘processes’ in BPR parlance and ‘operations’ is: a. Operations are organizational objective oriented unlike the processes b. Operations concern with results unlike the processes. √c. Processes flow horizontally and across various functions unlike operations d. Processes flow vertically and across various functions unlike operations. 8. If 180 pieces are produced at a standard price of 1000 each, with a labour cost of Rs. 8000, material cost of Rs. 12000 and overhead of Rs.16000, the multifactor productivity would be a. 2.5 √b. 5.0 c. 7.5 c. 10.0