SlideShare une entreprise Scribd logo
1  sur  9
Télécharger pour lire hors ligne
ISSN: 2278 – 1323
International Journal of Advanced Research in Computer Engineering & Technology (IJARCET)
Volume 2, Issue 6, June 2013
www.ijarcet.org 2177
Integrating Assembly Lines based on Lean Line Design
Concept
Ms. Surekha. S1
, Dr. R. V Praveena Gowda2
, Mr. Manoj Kulkarni3
Abstract
In today‟s competitive business scenario
manufacturing industries are under the
pressure to reduce cost and cycle time. It is a
lean manufacturing concept with a systematic
approach to identify and eliminate waste
through continuous and sustained
improvements by manufacturing the product
at the pull of the customer in pursuit of
perfection. This paper is to Design and
Integrate Assembly Lines „A‟ and „B‟ based
on „Lean Concept‟ using MTM/UAS analysis
for determine the time and to identify the
improvement. The study was carried out in 2
assembly lines in a reputed manufacturing
industry. The paper concentrates only on
assembly line and where assembly line „B‟ is
to be accommodated into assembly line „A‟.
The main focus of the paper is to study the
existing system and designing the new
solution based on Lean Line Design concept
which would follow the standards of the
manufacturing industry
Keywords: Integration, manual work system, line
balancing, manual time.
Abbreviations:
LLD- Lean line design
CTT– Customer takt time
OEE- Overall equipment effectiveness
PC/T- Planned cycle time
OBC- Operator balance chart
SW- Standardized work
CIP- Continuous improvement process
I. Introduction
The aim of the paper to integrate 2 assembly
lines by reducing space and operator which
results in effectively utilization of space and
the manpower. Different tools like takt time,
line balancing, and MTM/UAS analysis are
used to achieve the purpose. The integration
of the 2 lines is based on the LLD technique.
[4] The expected benefit is to effectively
utilize the space and manpower by 50% and
30%.
A. Method time measurement (MTM) and
universal analysis system (UAS) - is a
“Predetermined Time Systems” used
primarily in industrial settings to analyze
the methods used to perform any manual
operations or task & as a product of that
analysis, let the standard time in which a
worker should complete the task.
B. Lean Line Design- Lean Line Design is a
method for implementing manufacturing
industries principles like process
orientation, perfect quality,
standardization, flexibility, waste
elimination, transparent process, associate
involvement etc. LLD technique is as
shown in fig 1 while planning the new
design of manual and semi-automated
work systems this LLD technique is
required to result in the better line. The
qualitative aim is to redesign production
and logistics according to manufacturing
industries criteria. The quantitative aim is
to increase productivity and flexibility, as
well as lowering the investment ratio,
space requirements and through-put times.
Fig 1: LLD Technique
C. Approaches to LLD- Designing the lean
line means to rearrange the stations in the
existing line which would be meeting the
manufacturing industries standards. [3]
LLD which is used for rearranging is a
step by step approach, the approaches flow
is shown in fig 2.
Fig 2: Flow chart of LLD approaches
ISSN: 2278 – 1323
International Journal of Advanced Research in Computer Engineering & Technology (IJARCET)
Volume 2, Issue 6, June 2013
www.ijarcet.org 2178
II. Problem Statement
In recent days „A‟ elements has encountered
with a fluctuation in demand i.e., from high
demand to moderate demand, and there is a
moderate demand for „B‟ elements, therefore
there is no effective utilization of the line and
the man power in both the Pumps.
III. Initial Calculation
A. Customer Takt Time (CTT) - It is the rate
at which products or parts must be
produced to fulfill customer orders.
Equation to calculate CTT is as below in
e.q. 1.
E.q. 1: CTT
B. Planned Cycle Time (PC/T) - It is the
Customer Takt Time taking into accounts
C. all influencing parameters and losses
(included in OEE) at maximum capacity
of the line. Equation to calculate CTT is
as below in e.q. 2.
E.q. 2: PC/T
Note: Planned cycle time need to be at least
10% less than CTT, so that the product
could be delivered on time
The CTT and the PC/T for the A and
B line is calculated as shown in the table 1.
Which shows us how the CTT and PC/T for
A and B line is done.
Planned Operating
Time / day
Volume
A
Working
days B
Demand per
day = A/B
CTT PC/T
A
25200 seconds 9812
units
24 days 409 units 62
Seconds
52
Seconds
B
25200 seconds 840
units
24 days 35 units 720
Seconds
612
Seconds
Table 1: CTT and PC/T calculation for A and B line
IV. Asses Current Condition
A. Current Layout
Current layout of „A‟ and „B‟ elements can be
referred to the fig 3 and 4 shows the current
layout, where B line need to be
accommodated into A line
Fig 3: Existing layout of ‘A’ assembly line
Fig 4: Existing layout of ‘B’ assembly line
B. Process Flow
Process flow would help us to know the flow
carried out in the assembly line. [1] The
below fig 5 and fig 6 shows us the process
flow currently carried out in „A‟ and „B‟ lines
respectively.
ISSN: 2278 – 1323
International Journal of Advanced Research in Computer Engineering & Technology (IJARCET)
Volume 2, Issue 6, June 2013
www.ijarcet.org 2179
C. Work Distribution Diagram
Time studies of manual times and process
times for each station/operator will be copied
into the operator balance chart. The time
studies can be obtained by time study method
or method time measurement/ universal
analysis system (MTM/UAS) methods.
MTM Method (Method Time
Measurement) - Time determination MTM
basic method is a “Predetermined Time
Systems” that is used primarily in industrial
settings to analyze the methods used to
perform any manual operations or task & as a
product of that analysis, let the standard time
in which a worker should complete the task
UAS (Universal Analysis System) -
UAS is a procedure for dividing a manual
task into so called basic procedures, which
consists of a combination of frequently
recurring basic sequences of motion. The
basic procedures are assigned standards time
values, the amount of which is equal to the
mean value to the mean value of the MTM
basic sequences of motion included.
The time measurement unit for the
MTM and UAS is in TMU (Time
measurement unit) it‟s converted to seconds
using the following table 2
Time Units- TMU (Time Measurement Unit)
→ TMU Sec Min Hrs
TMU 1 0.036 0.0006 0.00001
Sec 27.8 1 0.0167 0.000278
Min 1666.7 60 1 0.0167
Hrs 100000 3600 60 1
Table 2: Conversion of TMU to Seconds
a. Stack Diagram
A stack diagram is prepared for all manual
operations in „A‟ and „B‟ elements assembly
line, which are put in a stack in a scaled
manner completely independent from the
physical work station, the MTM study of each
station is carried out an example of some
station using MTM and UAS is shown in the
table 2A (not covering all the station) and
arranged in stack diagram as shown in table
3A and 3B. Each loop is identified in
different color.
Manual Time
Line Station Type
In
TMU
In
Sec
A Station A2 MTM 135.1 4.9
A Station A7 UAS 117.7 4.2
B Station B2 MTM 510.1 18.3
B Station B3 UAS 1005 36.2
Table 2A: Example of MTM and UAS
analysis
A In Seconds
Station Manual Auto
Station A1 2.2 0
Station A2 4.9 0
Station A3 30 0.6
Station A4 8.7 0
Station A5 4.3 2
Station A6 17.1 0.5
Station A9 4.2 0.1
Station A7 2.6 3.5
Station A8 12.3 0
Total 86.5 6.7
Table 3A: A line operator time
B In Seconds
Station Manual Auto
Station B1 20.5 0
Station B2 36.2 0
Station B3 4.2 0.1
Station B4 35 3.5
Total 96 3.6
Table 3B: B line operator time
b. OBC
Operator Balance Chart, time studies of
manual times and process times for each
station/operators result will be copied into the
operator balance chart as shown in the fig 7
and 8.
Note: target cycle time is 15%less than the
CTT so that the product could be delivered
within the time
ISSN: 2278 – 1323
International Journal of Advanced Research in Computer Engineering & Technology (IJARCET)
Volume 2, Issue 6, June 2013
www.ijarcet.org 2180
Fig 7: OBC of ‘A’ line
Fig 8: OBC of ‘B’ line
Interpretation form fig 7, it‟s clearly visible
from the line balancing that the operator 1 and
2 are not utilized completely and operator 3
can be utilized for other task completion.
From fig 8 the operator can be utilized for
other task completion
V. Developing Operator flow vision
A. Paper Kaizen and Timing the work
Element
Improvements were identified to
eliminate the waste in the manual operations;
improvements were identified based on the
MTM/UAS analysis and observation.
Improvements are classified into 4 types they
are.
Ergonomic improvement
Workplace arrangement
Method
Out sourcing
The improvements identified are
summarized in the table 4 and 5
SLNO Types for A line No
1 Methods improvement 8
2 Workplace arrangement 4
3 Ergonomic improvement 2
4 Outsourcing of operation 5
Table 4: A line improvements
SLNO Types for B line No
1 Methods improvement 11
2 Workplace arrangement 2
3 Ergonomic improvement 2
4 Outsourcing of operation 0
Table 5: B line improvements
The improvements identified are considered
and the work elements are timed as shown in
the table 6 and 7. In the table below we are
comparing the before and after Kaizen value
where „before‟ refer to initial manual time and
„after‟ refers to the manual time after the
elimination of waste i.e. after paper Kaizen.
A In Seconds
Station Before After
Station A1 2.2 2.2
Station A2 4.9 4.9
Station A3 30 24.6
Station A4 8.7 8.7
Station A5 4.3 4.1
Station A6 17.1 15.2
Station A9 4.2
Station A7 2.6 2.6
Station A8 12.3 12.3
Total 86.5 74.6
Table 6: Timed work element for A line
B In Seconds
Station Before After
Station B1 20.5
50.2
Station B2 36.2
Station B3 4.2 3.5
Station B4 35 35
Total 96 88.6
Table 7: Timed work element for B line
B. Creating Single Operator Stack
Description of sequence for 1 operator like
recording of work contents at each station,
listing them to scale (regarding time) in
sequence of building one part (one-operator
flow), the single operator is created as in the
table 8 and 9.
No proper
utilization of
the operator
Operator
utilized to
other task
ISSN: 2278 – 1323
International Journal of Advanced Research in Computer Engineering & Technology (IJARCET)
Volume 2, Issue 6, June 2013
www.ijarcet.org 2181
1A In Seconds
Station Manual Auto
Station A1 2.2 0
Station A2 4.9 0
Station A3 24.6 0.6
Station A4 8.7 0
Station A5 4.1 2
Station A6 15.2 0.5
Station A7 2.6 3.5
Station A8 12.3 0
Total 74.6 6.7
Table 8: Single operator stack for A line
2B In Seconds
Station Manual Auto
Station B1 &
B2 50.2 0
Station B3 3.5 0
Station B4 35 3.5
Total 88.6 3.6
Table 9: Single operator stack for B line
VI. Line Design
A. Rough Line Concept
Rough line concepts helps us to plan and
design the new line according to the
manufacturing industries principles, we
would be following 4 steps to draw the new
line,
a. Step 1: Start with a simple, straight-line
sketch of workstations
Design the line so the operator can flow as
intended not necessarily to scale yet
Design the line independent of the number
of operators, as shown in fig 9.
Fig 9: Rough Line step 1
b. Step 2: Write the operator cycle times above each station as shown in fig 10
Fig 10: Rough Line step 2
c. Step 3: list the parts needed under each station as shown in fig 11
d. Step 4: list cycle time of automatic process underneath the station as shown in fig 11
Fig 11: Rough Line step 3 & 4
B. Detailing and Finalizing the Layout
With knowledge of operator flow, rough line layout and supply of components we can detail the
layout and draw to scale
ISSN: 2278 – 1323
International Journal of Advanced Research in Computer Engineering & Technology (IJARCET)
Volume 2, Issue 6, June 2013
www.ijarcet.org 2182
Fig 12: Integrated detailed layout
C. Developing Work Distribution
a. Calculating Number of Operator
Finally we calculate the target number of
operators as in table 10, which will help us to
know how many number of operator‟s are
required to complete the task at the given
time. The equation 3 shows how to calculate
the number of operator
E.q. 3: Number of operator
Total Operator Time
(A)
Planned Cycle Time
(B)
Avg no of operator =
A / B
A 74.5 52 1.433
B 88.6 612 0.145
Table 10: Number of operator calculation
b. Creating of Operator Balance Chart
(OBC)
Distribution of work content to operators
(target), take stack diagram as in table 11
and 12 and cut to fit to planned cycle time
to draw OBC as in fig 12 and 13. Hand-off
points can be inside a station
Assign walk paths according to
distribution of work content on layout as
in fig 14
1A In Seconds
Station Manual Auto
Station A1 2.2 0
Station A2 4.9 0
Station A3 24.6 0.6
Station A4 8.7 0
Station A5 4.1 2
Station A6 15.2 0.5
Station A7 2.6 3.5
Station A8 12.3 0
Total 74.6 6.7
Table 11: Stack for OBC for A line
2B In Seconds
Station Manual Auto
Station B1 &
B2 50.2 0
Station B3 3.5 0
Station B4 35 3.5
Total 88.6 3.6
Table 12: Stack for OBC for B line
Fig 12: OBC of ‘A’ assembly line
Fig 13: OBC of ‘B’ assembly line
Operator
utilized to
other task
Better utilization of
operator compared
to is condition (fig
7)
ISSN: 2278 – 1323
International Journal of Advanced Research in Computer Engineering & Technology (IJARCET)
Volume 2, Issue 6, June 2013
www.ijarcet.org 2183
Interpretation form fig 12, it‟s clearly visible
from the line balancing that the operator 1 is
better utilized compared to is condition and
operator 2 can be utilized for other task
completion. From fig 8 the operator can be
utilized for other task completion
Fig 14: Walk path
Interpretation from fig 14: The walk path
specifies only the movement of the operator
which is recursive in nature i.e. once the
operator 1 finish his work then his work again
starts from the scratch
VII. Implementation
Work with Equipment Vendor
o Think of equipment vendors as machine
builders, and yourself as the line/flow
designer. The flow is your responsibility.
o Design the line in a way that allows further
refinement after installation. Improvement
will continue -- build the line accordingly.
o Involve the machine vendor in the process
design steps. He will better understand
your concept and get trained at the same
time.
o Work with the equipment vendor during
his process, in order to avoid surprises.
This is not a hand off.
Realization
o new concept should be realized as fast as
possible
VIII. Standardized Work and CIP
A. Standardized Work
Standardization is an important principle that
has to be implemented in any of the
manufacturing industry. Standardized Work
creates transparency in the workflow and thus
provides the basis for the continuous
improvement process. Stab sheets are
prepared so that we can get the idea how the
operator flow is, the Stab sheets are shown in
fig 15 and 16, its shown only for 1 operator,
rest can be created as same as fig 15 and 16
Preparation
of Work Sheets:
ISSN: 2278 – 1323
International Journal of Advanced Research in Computer Engineering & Technology (IJARCET)
Volume 2, Issue 6, June 2013
www.ijarcet.org 2184
Fig 15: Data input for worksheet
Fig 16: STAB
B. Point CIP
Continuous improvement process (CIP),
description of the work sequence according to
the current standard need to be implemented
which can be carried out by informing and
training of the employees of the line based on
the operator time. Fig 17 shows us the
implementation of the point-CIP.
Fig 17: Point CIP
ISSN: 2278 – 1323
International Journal of Advanced Research in Computer Engineering & Technology (IJARCET)
Volume 2, Issue 6, June 2013
www.ijarcet.org 2185
IX. Results
The results of integrating the 2 lines A and B
are as shown in the table 13
SL
No
Action
Existi
ng
Integrat
ed
1
Area in sq
meters
A 618
B 311.4
Total 929.4 481.2
2
Material
Movement
in meters
A 938
B 360
Total 1298 800
3
Operator
Cycle Time
A 86.5
B 96
Total 182.5 157.1
4
Number of
Operators
A 3 2
B 1 1
Total 4 3
6 Productivity
A 24.8 37.1
B 10 10
Table 13: Results
X. Conclusion
The aim of the paper to integrate 2 lines by
reducing space and operator results in
effectively utilization of space by 48% and
the manpower by 33% was achieved.
Different tools like takt time, line balancing,
MTM/UAS analysis etc. were used under
LLD technique. The integration carried out on
parameters like number of operators, cycle
time, space. Integrated layout is simulated and
validated through trial runs. The project
yielded good results in terms of space and
manpower utilization.
References
[1]. Process Cycle Efficiency Improvement
through Lean: A Case Study, Author: D.
Rajentbirakumar; P.V. Mohanram; S.G.
Harikarthik, Journal: International Journal
of Lean Thinking, Year: 2011 Vol: 2
Issue: 1 Pages/record No.: 46-58.
[2]. Designing of an Assembly Line based on
Reliability Approach, Author: Dilip Roy;
Debdip Khan, Journal: International
Journal of Optimization and Control:
Theories & Applications, Year: 2011 Vol:
1 Issue: 1 Pages/record No.: 45-52
[3]. Bosch Ltd, “BPS manual”, 2005, Bosch
Ltd, “Industrial Engineering hand book”,
2007
[4]. References: Bosch Norms - N62C, MTM
Grundlehrgang material of DMTMV,
MTM Basic Course material of MICO, I
E Handbook of MICO/BanW
[5]. http://www.linkedin.com/answers/busines
s-operations/supply-chain
management/OPS_SCH/260818-2596096
By: Alvis Lazarus A. Country Manager -
All India Distribution Ops (Logistics,
Warehousing, Transportation & Supply
chain)
[6]. http://www.productivity.in/knowledgebas
e/Industrial%20Engineering%20Docs/b.
%20Methods%20Engineering/2.1%20Wo
rk%20Study.pdf
1
MTech (MEM) Student, Department of
Industrial Engineering and Management,
DSCE, Kumarswamy Layout, Bangalore-78,
India.
2
Professor, Department of Industrial
Engineering and Management, DSCE,
Kumarswamy Layout, Bangalore-78, India.
3
Deputy Manager, Industrial Engineering,
Bosch Ltd., Bangalore

Contenu connexe

Tendances

Chapter 7 automation techniques
Chapter 7  automation techniquesChapter 7  automation techniques
Chapter 7 automation techniques
Mohamad Sahiedan
 
Layout Case Study
Layout Case StudyLayout Case Study
Layout Case Study
Nilam Kabra
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materials
pikuoec
 

Tendances (19)

Team5_-_Final_Report
Team5_-_Final_ReportTeam5_-_Final_Report
Team5_-_Final_Report
 
DESIGN AND CONTROL OF ATC FOR SHORTER TIME INTERVAL IN CNC MACHINES
DESIGN AND CONTROL OF ATC FOR SHORTER TIME INTERVAL IN CNC MACHINESDESIGN AND CONTROL OF ATC FOR SHORTER TIME INTERVAL IN CNC MACHINES
DESIGN AND CONTROL OF ATC FOR SHORTER TIME INTERVAL IN CNC MACHINES
 
Chapter 7 automation techniques
Chapter 7  automation techniquesChapter 7  automation techniques
Chapter 7 automation techniques
 
Shelikhov2017
Shelikhov2017Shelikhov2017
Shelikhov2017
 
Chapter 1 fundamentals of cam
Chapter 1 fundamentals of camChapter 1 fundamentals of cam
Chapter 1 fundamentals of cam
 
Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)Computer – Aided process planning (CAPP)
Computer – Aided process planning (CAPP)
 
Unit 1 cim
Unit 1 cimUnit 1 cim
Unit 1 cim
 
Cnc intro
Cnc introCnc intro
Cnc intro
 
Layout Case Study
Layout Case StudyLayout Case Study
Layout Case Study
 
FLUID FLOW ANALYSIS OF CENTRIFUGAL FAN BY USING FEM
FLUID FLOW ANALYSIS OF CENTRIFUGAL FAN BY USING FEMFLUID FLOW ANALYSIS OF CENTRIFUGAL FAN BY USING FEM
FLUID FLOW ANALYSIS OF CENTRIFUGAL FAN BY USING FEM
 
GROUP TECHNOLOGY AND CAPP
GROUP TECHNOLOGY AND CAPPGROUP TECHNOLOGY AND CAPP
GROUP TECHNOLOGY AND CAPP
 
Robotics and Automation
Robotics and AutomationRobotics and Automation
Robotics and Automation
 
Unit 2
Unit 2Unit 2
Unit 2
 
Me6703 cim systems
Me6703 cim systemsMe6703 cim systems
Me6703 cim systems
 
Unit 4 cim
Unit 4 cimUnit 4 cim
Unit 4 cim
 
Role of computers in mfg
Role of computers in mfgRole of computers in mfg
Role of computers in mfg
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materials
 
Efficiency of bond graph and external model integration for alarm processing ...
Efficiency of bond graph and external model integration for alarm processing ...Efficiency of bond graph and external model integration for alarm processing ...
Efficiency of bond graph and external model integration for alarm processing ...
 
Apt programming
Apt programmingApt programming
Apt programming
 

En vedette (9)

1811 1815
1811 18151811 1815
1811 1815
 
1670 1673
1670 16731670 1673
1670 1673
 
Volume 2-issue-6-2081-2084
Volume 2-issue-6-2081-2084Volume 2-issue-6-2081-2084
Volume 2-issue-6-2081-2084
 
Volume 2-issue-6-2056-2060
Volume 2-issue-6-2056-2060Volume 2-issue-6-2056-2060
Volume 2-issue-6-2056-2060
 
Volume 2-issue-6-2108-2113
Volume 2-issue-6-2108-2113Volume 2-issue-6-2108-2113
Volume 2-issue-6-2108-2113
 
Volume 2-issue-6-2098-2101
Volume 2-issue-6-2098-2101Volume 2-issue-6-2098-2101
Volume 2-issue-6-2098-2101
 
1725 1731
1725 17311725 1731
1725 1731
 
Volume 2-issue-6-2046-2051
Volume 2-issue-6-2046-2051Volume 2-issue-6-2046-2051
Volume 2-issue-6-2046-2051
 
1725 1731
1725 17311725 1731
1725 1731
 

Similaire à Volume 2-issue-6-2177-2185

PALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPINGPALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPING
FuratAj
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
Praveen S R
 

Similaire à Volume 2-issue-6-2177-2185 (20)

Balancing the line by using heuristic method based on cpm in salbp –a case study
Balancing the line by using heuristic method based on cpm in salbp –a case studyBalancing the line by using heuristic method based on cpm in salbp –a case study
Balancing the line by using heuristic method based on cpm in salbp –a case study
 
IRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
IRJET- A Case Study Approach of Quality Tools in Manufacturing IndustryIRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
IRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
 
PALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPINGPALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPING
 
PORTFOLIO_MJ
PORTFOLIO_MJPORTFOLIO_MJ
PORTFOLIO_MJ
 
O0123190100
O0123190100O0123190100
O0123190100
 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM Report
CIM ReportCIM Report
CIM Report
 
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCINGPRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
 
K012556370
K012556370K012556370
K012556370
 
K012556370
K012556370K012556370
K012556370
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materials
 
J012647278
J012647278J012647278
J012647278
 
Linking design and manufacturing on a PLM platform
Linking design and manufacturing on a PLM platformLinking design and manufacturing on a PLM platform
Linking design and manufacturing on a PLM platform
 
J012647278
J012647278J012647278
J012647278
 
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENTTIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
 
Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant
 
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET-  	  Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...IRJET-  	  Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
 
Systems modelling and simulation
Systems modelling and simulationSystems modelling and simulation
Systems modelling and simulation
 

Plus de Editor IJARCET

Volume 2-issue-6-2205-2207
Volume 2-issue-6-2205-2207Volume 2-issue-6-2205-2207
Volume 2-issue-6-2205-2207
Editor IJARCET
 
Volume 2-issue-6-2195-2199
Volume 2-issue-6-2195-2199Volume 2-issue-6-2195-2199
Volume 2-issue-6-2195-2199
Editor IJARCET
 
Volume 2-issue-6-2200-2204
Volume 2-issue-6-2200-2204Volume 2-issue-6-2200-2204
Volume 2-issue-6-2200-2204
Editor IJARCET
 
Volume 2-issue-6-2190-2194
Volume 2-issue-6-2190-2194Volume 2-issue-6-2190-2194
Volume 2-issue-6-2190-2194
Editor IJARCET
 
Volume 2-issue-6-2186-2189
Volume 2-issue-6-2186-2189Volume 2-issue-6-2186-2189
Volume 2-issue-6-2186-2189
Editor IJARCET
 
Volume 2-issue-6-2177-2185
Volume 2-issue-6-2177-2185Volume 2-issue-6-2177-2185
Volume 2-issue-6-2177-2185
Editor IJARCET
 
Volume 2-issue-6-2173-2176
Volume 2-issue-6-2173-2176Volume 2-issue-6-2173-2176
Volume 2-issue-6-2173-2176
Editor IJARCET
 
Volume 2-issue-6-2165-2172
Volume 2-issue-6-2165-2172Volume 2-issue-6-2165-2172
Volume 2-issue-6-2165-2172
Editor IJARCET
 
Volume 2-issue-6-2159-2164
Volume 2-issue-6-2159-2164Volume 2-issue-6-2159-2164
Volume 2-issue-6-2159-2164
Editor IJARCET
 
Volume 2-issue-6-2155-2158
Volume 2-issue-6-2155-2158Volume 2-issue-6-2155-2158
Volume 2-issue-6-2155-2158
Editor IJARCET
 
Volume 2-issue-6-2148-2154
Volume 2-issue-6-2148-2154Volume 2-issue-6-2148-2154
Volume 2-issue-6-2148-2154
Editor IJARCET
 
Volume 2-issue-6-2143-2147
Volume 2-issue-6-2143-2147Volume 2-issue-6-2143-2147
Volume 2-issue-6-2143-2147
Editor IJARCET
 
Volume 2-issue-6-2119-2124
Volume 2-issue-6-2119-2124Volume 2-issue-6-2119-2124
Volume 2-issue-6-2119-2124
Editor IJARCET
 
Volume 2-issue-6-2139-2142
Volume 2-issue-6-2139-2142Volume 2-issue-6-2139-2142
Volume 2-issue-6-2139-2142
Editor IJARCET
 
Volume 2-issue-6-2130-2138
Volume 2-issue-6-2130-2138Volume 2-issue-6-2130-2138
Volume 2-issue-6-2130-2138
Editor IJARCET
 
Volume 2-issue-6-2125-2129
Volume 2-issue-6-2125-2129Volume 2-issue-6-2125-2129
Volume 2-issue-6-2125-2129
Editor IJARCET
 
Volume 2-issue-6-2114-2118
Volume 2-issue-6-2114-2118Volume 2-issue-6-2114-2118
Volume 2-issue-6-2114-2118
Editor IJARCET
 
Volume 2-issue-6-2108-2113
Volume 2-issue-6-2108-2113Volume 2-issue-6-2108-2113
Volume 2-issue-6-2108-2113
Editor IJARCET
 
Volume 2-issue-6-2102-2107
Volume 2-issue-6-2102-2107Volume 2-issue-6-2102-2107
Volume 2-issue-6-2102-2107
Editor IJARCET
 

Plus de Editor IJARCET (20)

Electrically small antennas: The art of miniaturization
Electrically small antennas: The art of miniaturizationElectrically small antennas: The art of miniaturization
Electrically small antennas: The art of miniaturization
 
Volume 2-issue-6-2205-2207
Volume 2-issue-6-2205-2207Volume 2-issue-6-2205-2207
Volume 2-issue-6-2205-2207
 
Volume 2-issue-6-2195-2199
Volume 2-issue-6-2195-2199Volume 2-issue-6-2195-2199
Volume 2-issue-6-2195-2199
 
Volume 2-issue-6-2200-2204
Volume 2-issue-6-2200-2204Volume 2-issue-6-2200-2204
Volume 2-issue-6-2200-2204
 
Volume 2-issue-6-2190-2194
Volume 2-issue-6-2190-2194Volume 2-issue-6-2190-2194
Volume 2-issue-6-2190-2194
 
Volume 2-issue-6-2186-2189
Volume 2-issue-6-2186-2189Volume 2-issue-6-2186-2189
Volume 2-issue-6-2186-2189
 
Volume 2-issue-6-2177-2185
Volume 2-issue-6-2177-2185Volume 2-issue-6-2177-2185
Volume 2-issue-6-2177-2185
 
Volume 2-issue-6-2173-2176
Volume 2-issue-6-2173-2176Volume 2-issue-6-2173-2176
Volume 2-issue-6-2173-2176
 
Volume 2-issue-6-2165-2172
Volume 2-issue-6-2165-2172Volume 2-issue-6-2165-2172
Volume 2-issue-6-2165-2172
 
Volume 2-issue-6-2159-2164
Volume 2-issue-6-2159-2164Volume 2-issue-6-2159-2164
Volume 2-issue-6-2159-2164
 
Volume 2-issue-6-2155-2158
Volume 2-issue-6-2155-2158Volume 2-issue-6-2155-2158
Volume 2-issue-6-2155-2158
 
Volume 2-issue-6-2148-2154
Volume 2-issue-6-2148-2154Volume 2-issue-6-2148-2154
Volume 2-issue-6-2148-2154
 
Volume 2-issue-6-2143-2147
Volume 2-issue-6-2143-2147Volume 2-issue-6-2143-2147
Volume 2-issue-6-2143-2147
 
Volume 2-issue-6-2119-2124
Volume 2-issue-6-2119-2124Volume 2-issue-6-2119-2124
Volume 2-issue-6-2119-2124
 
Volume 2-issue-6-2139-2142
Volume 2-issue-6-2139-2142Volume 2-issue-6-2139-2142
Volume 2-issue-6-2139-2142
 
Volume 2-issue-6-2130-2138
Volume 2-issue-6-2130-2138Volume 2-issue-6-2130-2138
Volume 2-issue-6-2130-2138
 
Volume 2-issue-6-2125-2129
Volume 2-issue-6-2125-2129Volume 2-issue-6-2125-2129
Volume 2-issue-6-2125-2129
 
Volume 2-issue-6-2114-2118
Volume 2-issue-6-2114-2118Volume 2-issue-6-2114-2118
Volume 2-issue-6-2114-2118
 
Volume 2-issue-6-2108-2113
Volume 2-issue-6-2108-2113Volume 2-issue-6-2108-2113
Volume 2-issue-6-2108-2113
 
Volume 2-issue-6-2102-2107
Volume 2-issue-6-2102-2107Volume 2-issue-6-2102-2107
Volume 2-issue-6-2102-2107
 

Dernier

Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
amitlee9823
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
lizamodels9
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
lizamodels9
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
Matteo Carbone
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
dlhescort
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
dollysharma2066
 

Dernier (20)

Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 

Volume 2-issue-6-2177-2185

  • 1. ISSN: 2278 – 1323 International Journal of Advanced Research in Computer Engineering & Technology (IJARCET) Volume 2, Issue 6, June 2013 www.ijarcet.org 2177 Integrating Assembly Lines based on Lean Line Design Concept Ms. Surekha. S1 , Dr. R. V Praveena Gowda2 , Mr. Manoj Kulkarni3 Abstract In today‟s competitive business scenario manufacturing industries are under the pressure to reduce cost and cycle time. It is a lean manufacturing concept with a systematic approach to identify and eliminate waste through continuous and sustained improvements by manufacturing the product at the pull of the customer in pursuit of perfection. This paper is to Design and Integrate Assembly Lines „A‟ and „B‟ based on „Lean Concept‟ using MTM/UAS analysis for determine the time and to identify the improvement. The study was carried out in 2 assembly lines in a reputed manufacturing industry. The paper concentrates only on assembly line and where assembly line „B‟ is to be accommodated into assembly line „A‟. The main focus of the paper is to study the existing system and designing the new solution based on Lean Line Design concept which would follow the standards of the manufacturing industry Keywords: Integration, manual work system, line balancing, manual time. Abbreviations: LLD- Lean line design CTT– Customer takt time OEE- Overall equipment effectiveness PC/T- Planned cycle time OBC- Operator balance chart SW- Standardized work CIP- Continuous improvement process I. Introduction The aim of the paper to integrate 2 assembly lines by reducing space and operator which results in effectively utilization of space and the manpower. Different tools like takt time, line balancing, and MTM/UAS analysis are used to achieve the purpose. The integration of the 2 lines is based on the LLD technique. [4] The expected benefit is to effectively utilize the space and manpower by 50% and 30%. A. Method time measurement (MTM) and universal analysis system (UAS) - is a “Predetermined Time Systems” used primarily in industrial settings to analyze the methods used to perform any manual operations or task & as a product of that analysis, let the standard time in which a worker should complete the task. B. Lean Line Design- Lean Line Design is a method for implementing manufacturing industries principles like process orientation, perfect quality, standardization, flexibility, waste elimination, transparent process, associate involvement etc. LLD technique is as shown in fig 1 while planning the new design of manual and semi-automated work systems this LLD technique is required to result in the better line. The qualitative aim is to redesign production and logistics according to manufacturing industries criteria. The quantitative aim is to increase productivity and flexibility, as well as lowering the investment ratio, space requirements and through-put times. Fig 1: LLD Technique C. Approaches to LLD- Designing the lean line means to rearrange the stations in the existing line which would be meeting the manufacturing industries standards. [3] LLD which is used for rearranging is a step by step approach, the approaches flow is shown in fig 2. Fig 2: Flow chart of LLD approaches
  • 2. ISSN: 2278 – 1323 International Journal of Advanced Research in Computer Engineering & Technology (IJARCET) Volume 2, Issue 6, June 2013 www.ijarcet.org 2178 II. Problem Statement In recent days „A‟ elements has encountered with a fluctuation in demand i.e., from high demand to moderate demand, and there is a moderate demand for „B‟ elements, therefore there is no effective utilization of the line and the man power in both the Pumps. III. Initial Calculation A. Customer Takt Time (CTT) - It is the rate at which products or parts must be produced to fulfill customer orders. Equation to calculate CTT is as below in e.q. 1. E.q. 1: CTT B. Planned Cycle Time (PC/T) - It is the Customer Takt Time taking into accounts C. all influencing parameters and losses (included in OEE) at maximum capacity of the line. Equation to calculate CTT is as below in e.q. 2. E.q. 2: PC/T Note: Planned cycle time need to be at least 10% less than CTT, so that the product could be delivered on time The CTT and the PC/T for the A and B line is calculated as shown in the table 1. Which shows us how the CTT and PC/T for A and B line is done. Planned Operating Time / day Volume A Working days B Demand per day = A/B CTT PC/T A 25200 seconds 9812 units 24 days 409 units 62 Seconds 52 Seconds B 25200 seconds 840 units 24 days 35 units 720 Seconds 612 Seconds Table 1: CTT and PC/T calculation for A and B line IV. Asses Current Condition A. Current Layout Current layout of „A‟ and „B‟ elements can be referred to the fig 3 and 4 shows the current layout, where B line need to be accommodated into A line Fig 3: Existing layout of ‘A’ assembly line Fig 4: Existing layout of ‘B’ assembly line B. Process Flow Process flow would help us to know the flow carried out in the assembly line. [1] The below fig 5 and fig 6 shows us the process flow currently carried out in „A‟ and „B‟ lines respectively.
  • 3. ISSN: 2278 – 1323 International Journal of Advanced Research in Computer Engineering & Technology (IJARCET) Volume 2, Issue 6, June 2013 www.ijarcet.org 2179 C. Work Distribution Diagram Time studies of manual times and process times for each station/operator will be copied into the operator balance chart. The time studies can be obtained by time study method or method time measurement/ universal analysis system (MTM/UAS) methods. MTM Method (Method Time Measurement) - Time determination MTM basic method is a “Predetermined Time Systems” that is used primarily in industrial settings to analyze the methods used to perform any manual operations or task & as a product of that analysis, let the standard time in which a worker should complete the task UAS (Universal Analysis System) - UAS is a procedure for dividing a manual task into so called basic procedures, which consists of a combination of frequently recurring basic sequences of motion. The basic procedures are assigned standards time values, the amount of which is equal to the mean value to the mean value of the MTM basic sequences of motion included. The time measurement unit for the MTM and UAS is in TMU (Time measurement unit) it‟s converted to seconds using the following table 2 Time Units- TMU (Time Measurement Unit) → TMU Sec Min Hrs TMU 1 0.036 0.0006 0.00001 Sec 27.8 1 0.0167 0.000278 Min 1666.7 60 1 0.0167 Hrs 100000 3600 60 1 Table 2: Conversion of TMU to Seconds a. Stack Diagram A stack diagram is prepared for all manual operations in „A‟ and „B‟ elements assembly line, which are put in a stack in a scaled manner completely independent from the physical work station, the MTM study of each station is carried out an example of some station using MTM and UAS is shown in the table 2A (not covering all the station) and arranged in stack diagram as shown in table 3A and 3B. Each loop is identified in different color. Manual Time Line Station Type In TMU In Sec A Station A2 MTM 135.1 4.9 A Station A7 UAS 117.7 4.2 B Station B2 MTM 510.1 18.3 B Station B3 UAS 1005 36.2 Table 2A: Example of MTM and UAS analysis A In Seconds Station Manual Auto Station A1 2.2 0 Station A2 4.9 0 Station A3 30 0.6 Station A4 8.7 0 Station A5 4.3 2 Station A6 17.1 0.5 Station A9 4.2 0.1 Station A7 2.6 3.5 Station A8 12.3 0 Total 86.5 6.7 Table 3A: A line operator time B In Seconds Station Manual Auto Station B1 20.5 0 Station B2 36.2 0 Station B3 4.2 0.1 Station B4 35 3.5 Total 96 3.6 Table 3B: B line operator time b. OBC Operator Balance Chart, time studies of manual times and process times for each station/operators result will be copied into the operator balance chart as shown in the fig 7 and 8. Note: target cycle time is 15%less than the CTT so that the product could be delivered within the time
  • 4. ISSN: 2278 – 1323 International Journal of Advanced Research in Computer Engineering & Technology (IJARCET) Volume 2, Issue 6, June 2013 www.ijarcet.org 2180 Fig 7: OBC of ‘A’ line Fig 8: OBC of ‘B’ line Interpretation form fig 7, it‟s clearly visible from the line balancing that the operator 1 and 2 are not utilized completely and operator 3 can be utilized for other task completion. From fig 8 the operator can be utilized for other task completion V. Developing Operator flow vision A. Paper Kaizen and Timing the work Element Improvements were identified to eliminate the waste in the manual operations; improvements were identified based on the MTM/UAS analysis and observation. Improvements are classified into 4 types they are. Ergonomic improvement Workplace arrangement Method Out sourcing The improvements identified are summarized in the table 4 and 5 SLNO Types for A line No 1 Methods improvement 8 2 Workplace arrangement 4 3 Ergonomic improvement 2 4 Outsourcing of operation 5 Table 4: A line improvements SLNO Types for B line No 1 Methods improvement 11 2 Workplace arrangement 2 3 Ergonomic improvement 2 4 Outsourcing of operation 0 Table 5: B line improvements The improvements identified are considered and the work elements are timed as shown in the table 6 and 7. In the table below we are comparing the before and after Kaizen value where „before‟ refer to initial manual time and „after‟ refers to the manual time after the elimination of waste i.e. after paper Kaizen. A In Seconds Station Before After Station A1 2.2 2.2 Station A2 4.9 4.9 Station A3 30 24.6 Station A4 8.7 8.7 Station A5 4.3 4.1 Station A6 17.1 15.2 Station A9 4.2 Station A7 2.6 2.6 Station A8 12.3 12.3 Total 86.5 74.6 Table 6: Timed work element for A line B In Seconds Station Before After Station B1 20.5 50.2 Station B2 36.2 Station B3 4.2 3.5 Station B4 35 35 Total 96 88.6 Table 7: Timed work element for B line B. Creating Single Operator Stack Description of sequence for 1 operator like recording of work contents at each station, listing them to scale (regarding time) in sequence of building one part (one-operator flow), the single operator is created as in the table 8 and 9. No proper utilization of the operator Operator utilized to other task
  • 5. ISSN: 2278 – 1323 International Journal of Advanced Research in Computer Engineering & Technology (IJARCET) Volume 2, Issue 6, June 2013 www.ijarcet.org 2181 1A In Seconds Station Manual Auto Station A1 2.2 0 Station A2 4.9 0 Station A3 24.6 0.6 Station A4 8.7 0 Station A5 4.1 2 Station A6 15.2 0.5 Station A7 2.6 3.5 Station A8 12.3 0 Total 74.6 6.7 Table 8: Single operator stack for A line 2B In Seconds Station Manual Auto Station B1 & B2 50.2 0 Station B3 3.5 0 Station B4 35 3.5 Total 88.6 3.6 Table 9: Single operator stack for B line VI. Line Design A. Rough Line Concept Rough line concepts helps us to plan and design the new line according to the manufacturing industries principles, we would be following 4 steps to draw the new line, a. Step 1: Start with a simple, straight-line sketch of workstations Design the line so the operator can flow as intended not necessarily to scale yet Design the line independent of the number of operators, as shown in fig 9. Fig 9: Rough Line step 1 b. Step 2: Write the operator cycle times above each station as shown in fig 10 Fig 10: Rough Line step 2 c. Step 3: list the parts needed under each station as shown in fig 11 d. Step 4: list cycle time of automatic process underneath the station as shown in fig 11 Fig 11: Rough Line step 3 & 4 B. Detailing and Finalizing the Layout With knowledge of operator flow, rough line layout and supply of components we can detail the layout and draw to scale
  • 6. ISSN: 2278 – 1323 International Journal of Advanced Research in Computer Engineering & Technology (IJARCET) Volume 2, Issue 6, June 2013 www.ijarcet.org 2182 Fig 12: Integrated detailed layout C. Developing Work Distribution a. Calculating Number of Operator Finally we calculate the target number of operators as in table 10, which will help us to know how many number of operator‟s are required to complete the task at the given time. The equation 3 shows how to calculate the number of operator E.q. 3: Number of operator Total Operator Time (A) Planned Cycle Time (B) Avg no of operator = A / B A 74.5 52 1.433 B 88.6 612 0.145 Table 10: Number of operator calculation b. Creating of Operator Balance Chart (OBC) Distribution of work content to operators (target), take stack diagram as in table 11 and 12 and cut to fit to planned cycle time to draw OBC as in fig 12 and 13. Hand-off points can be inside a station Assign walk paths according to distribution of work content on layout as in fig 14 1A In Seconds Station Manual Auto Station A1 2.2 0 Station A2 4.9 0 Station A3 24.6 0.6 Station A4 8.7 0 Station A5 4.1 2 Station A6 15.2 0.5 Station A7 2.6 3.5 Station A8 12.3 0 Total 74.6 6.7 Table 11: Stack for OBC for A line 2B In Seconds Station Manual Auto Station B1 & B2 50.2 0 Station B3 3.5 0 Station B4 35 3.5 Total 88.6 3.6 Table 12: Stack for OBC for B line Fig 12: OBC of ‘A’ assembly line Fig 13: OBC of ‘B’ assembly line Operator utilized to other task Better utilization of operator compared to is condition (fig 7)
  • 7. ISSN: 2278 – 1323 International Journal of Advanced Research in Computer Engineering & Technology (IJARCET) Volume 2, Issue 6, June 2013 www.ijarcet.org 2183 Interpretation form fig 12, it‟s clearly visible from the line balancing that the operator 1 is better utilized compared to is condition and operator 2 can be utilized for other task completion. From fig 8 the operator can be utilized for other task completion Fig 14: Walk path Interpretation from fig 14: The walk path specifies only the movement of the operator which is recursive in nature i.e. once the operator 1 finish his work then his work again starts from the scratch VII. Implementation Work with Equipment Vendor o Think of equipment vendors as machine builders, and yourself as the line/flow designer. The flow is your responsibility. o Design the line in a way that allows further refinement after installation. Improvement will continue -- build the line accordingly. o Involve the machine vendor in the process design steps. He will better understand your concept and get trained at the same time. o Work with the equipment vendor during his process, in order to avoid surprises. This is not a hand off. Realization o new concept should be realized as fast as possible VIII. Standardized Work and CIP A. Standardized Work Standardization is an important principle that has to be implemented in any of the manufacturing industry. Standardized Work creates transparency in the workflow and thus provides the basis for the continuous improvement process. Stab sheets are prepared so that we can get the idea how the operator flow is, the Stab sheets are shown in fig 15 and 16, its shown only for 1 operator, rest can be created as same as fig 15 and 16 Preparation of Work Sheets:
  • 8. ISSN: 2278 – 1323 International Journal of Advanced Research in Computer Engineering & Technology (IJARCET) Volume 2, Issue 6, June 2013 www.ijarcet.org 2184 Fig 15: Data input for worksheet Fig 16: STAB B. Point CIP Continuous improvement process (CIP), description of the work sequence according to the current standard need to be implemented which can be carried out by informing and training of the employees of the line based on the operator time. Fig 17 shows us the implementation of the point-CIP. Fig 17: Point CIP
  • 9. ISSN: 2278 – 1323 International Journal of Advanced Research in Computer Engineering & Technology (IJARCET) Volume 2, Issue 6, June 2013 www.ijarcet.org 2185 IX. Results The results of integrating the 2 lines A and B are as shown in the table 13 SL No Action Existi ng Integrat ed 1 Area in sq meters A 618 B 311.4 Total 929.4 481.2 2 Material Movement in meters A 938 B 360 Total 1298 800 3 Operator Cycle Time A 86.5 B 96 Total 182.5 157.1 4 Number of Operators A 3 2 B 1 1 Total 4 3 6 Productivity A 24.8 37.1 B 10 10 Table 13: Results X. Conclusion The aim of the paper to integrate 2 lines by reducing space and operator results in effectively utilization of space by 48% and the manpower by 33% was achieved. Different tools like takt time, line balancing, MTM/UAS analysis etc. were used under LLD technique. The integration carried out on parameters like number of operators, cycle time, space. Integrated layout is simulated and validated through trial runs. The project yielded good results in terms of space and manpower utilization. References [1]. Process Cycle Efficiency Improvement through Lean: A Case Study, Author: D. Rajentbirakumar; P.V. Mohanram; S.G. Harikarthik, Journal: International Journal of Lean Thinking, Year: 2011 Vol: 2 Issue: 1 Pages/record No.: 46-58. [2]. Designing of an Assembly Line based on Reliability Approach, Author: Dilip Roy; Debdip Khan, Journal: International Journal of Optimization and Control: Theories & Applications, Year: 2011 Vol: 1 Issue: 1 Pages/record No.: 45-52 [3]. Bosch Ltd, “BPS manual”, 2005, Bosch Ltd, “Industrial Engineering hand book”, 2007 [4]. References: Bosch Norms - N62C, MTM Grundlehrgang material of DMTMV, MTM Basic Course material of MICO, I E Handbook of MICO/BanW [5]. http://www.linkedin.com/answers/busines s-operations/supply-chain management/OPS_SCH/260818-2596096 By: Alvis Lazarus A. Country Manager - All India Distribution Ops (Logistics, Warehousing, Transportation & Supply chain) [6]. http://www.productivity.in/knowledgebas e/Industrial%20Engineering%20Docs/b. %20Methods%20Engineering/2.1%20Wo rk%20Study.pdf 1 MTech (MEM) Student, Department of Industrial Engineering and Management, DSCE, Kumarswamy Layout, Bangalore-78, India. 2 Professor, Department of Industrial Engineering and Management, DSCE, Kumarswamy Layout, Bangalore-78, India. 3 Deputy Manager, Industrial Engineering, Bosch Ltd., Bangalore