SCHOOL OF ARCHITECTURE• BUILDING• DESIGN
Centre for Modern Architecture Studies in Southeast Asia (MASSA)
Bachelor of Science (Honours) in Architecture
BUILDING CONSTRUCTION 1 [ARC 1523]
PROJECT 2: CONSTRUCTION ACTIVITY AND PROCESS
JOANNE BERNICE CHUA YUNN TZE 0315905
TUTOR: AR. CHIN TUCK HING
CONSTRUCTION PROCESS
WEEK 1
Activity 1: Survey Work
Duration: 7 days
Materials: -
Equipment: Surveying tripod, Theodolite, Dumpy level, Measuring tape, Excavator
Skilled Workers: Land surveyor (1), Soil investigator (1)
Technical Information: Built environment and natural surroundings of the site is studied, analysed
and data is collected. Trial pitting is carried out to examine soil condition. Excavation boundary is
indicated.
WEEK 2
Activity 1: Mobilization and Hoarding
Duration: 2-5 days
Materials: -
Equipment: Machineries, Hoarders
Skilled Workers: General workers (4)
Technical Information: The site office and construction machineries and equipment are transported
to the site.
Activity 2: Site Clearing
Duration: 14 days
Materials: -
Equipment: Backhoe loader, Excavator, Bulldozer operator (1), Chainsaws, Tipper truck,
Skilled Workers: Backhoe Loader Operator (1), Excavator operator(1), Bulldozer operator (1),
General workers (4), Truck driver (1)
Technical Information: Specific trees are removed and 300mm of top soil is excavated. The soil is
kept away or stored well for reuse due to its high water retentive characteristic.
WEEK 3
Activity 1: Site Clearing
Duration: 14 days
Materials: -
Equipment: Backhoe loader, Excavator, Bulldozer operator (1), Chainsaws, Tipper truck,
Skilled Workers: Backhoe Loader Operator (1), Excavator operator(1), Bulldozer operator (1),
General workers (4), Truck driver (1)
Technical Information: Specific trees are removed and 300mm of top soil is excavated. The soil is
kept away or stored well for reuse due to its high water retentive characteristic.
WEEK 4
Activity 1: Earthwork
Duration: 3-5 days
Materials: -
Equipment: Excavator, Compactor, Tipper truck
Skilled Workers: Excavator operator (1), Compactor operator (1), Truck driver (1)
technical information: The uneven land area is either compacted or filled with earth excavated from
site or transferred in to level the ground.
Activity 2: Setting Out
Duration: 3 days
Materials: Nails, Wooden pegs, Profile boards, Stakes, Builder’s line
Equipment: Hammer, Measuring tape, Theodolite, Dumpy level
Skilled Workers: Site Contractor (1), Site Engineer (1)
Technical Information: Measurements are taken and the boundary lines of the building are marked
clearly.
WEEK 5
Activity 1: Piling (Grid 5-6)
Duration: 10-14 days
Materials: Pre-Cast reinforced concrete piles
Equipment: Hydraulic piling hammer, Pile integrity tester
Skilled Workers: Hydraulic Piling Hammer Operator (1), General workers (6)
Technical Information: The first half of the piles are driven down The Pile integrity test (Load test) is
carried out to ensure the strength meet the requirement.
WEEK 6
Activity 1: Piling (Grid 1-4)
Duration: 10-14 days
Materials: Pre-Cast reinforced concrete piles
Equipment: Hydraulic piling hammer, Pile integrity tester
Skilled Workers: Hydraulic Piling Hammer Operator (1), General workers (6)
Technical Information: The second half of the piles are driven down The Pile integrity test (Load test)
is carried out to ensure the strength meet the requirement.
Activity 2: Pile capping (Grid 5-6)
Duration: 10-14 days
Materials: Concrete Grade 30, Steel Rebar reinforcement, Timber formwork
Equipment: Rebar bending machine (1), Cement mixer (1),
Skilled Workers: Rebar benders (2), General workers (6)
Technical Information: Steel rebar are bended to form a cage and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
WEEK 7
Activity 1: Pile capping (Grid 1-4)
Duration: 10-14 days
Materials: Concrete Grade 30, Steel Rebar reinforcement, Timber formwork
Equipment: Rebar bending machine (1), Cement mixer (1),
Skilled Workers: Rebar benders (2), General workers (6)
Technical Information: Steel rebar are bended to form a cage and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
Activity 2: Stump on pile cap (Grid 5-6 )
Duration: 7–14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formwork
Equipment: Concrete Vibrator (1), Rebar bending machine(1), Carpentry equipment, Theodolite
Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4), Land surveyor (1)
Technical Information: The height of the stump is adjusted to keep the floor levelled. Steel rebar are
bended to form a cage and put into position with starter bar protruding outwards. Concrete is
poured into the erected formwork and is left to cure.
WEEK 8
Activity 1: Stump on pile cap (Grid 1-4 )
Duration: 7–14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formwork
Equipment: Concrete Vibrator (1), Rebar bending machine (1), Carpentry equipment, Theodolite
Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4), Land surveyor (1)
Technical Information: The height of the stump is adjusted to keep the floor levelled. Steel rebar are
bended to form a cage and put into position with starter bar protruding outwards. Concrete is
poured into the erected formwork and is left to cure.
Activity 2: Ground beam (Grid 5-6 )
Duration: 7–14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks,
Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry
equipment
Skilled Workers: Carpenter (2), Rebar Bender (1), General workers (3)
Technical Information: Steel rebar are bended to form a cage and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
WEEK 9
Activity 1: Ground beam (Grid 1-4 )
Duration: 7–14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks,
Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry
equipment
Skilled Workers: Carpenter (2), Rebar Bender (1), General workers (3)
Technical Information: Steel rebar are bended to form a cage and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
Activity 2: Ground floor slab (Grid 4-6)
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks, Damp Proof
Membrane (DPM), Screed
Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry
equipment
Skilled Workers: Carpenters (2), Rebar Bender (1), General workers (4)
Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure. Next, a layer
of DPM is applied on the top of the concrete and was covered with a layer of screed to level the slab.
WEEK 10
Activity 1: Ground floor slab (Grid 1-4)
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks, Damp Proof
Membrane (DPM), Screed
Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry
equipment
Skilled Workers: Carpenters (2), Rebar Bender (1), General workers (4)
Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure. Next, a layer
of DPM is applied on the top of the concrete and was covered with a layer of screed to level the slab.
Activity 2: Ground floor columns (Grid 4-6)
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks
Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry
equipment
Skilled worker: Carpenter (2) , Rebar bender (2), General worker (4)
Technical information: Steel rebar are bended to form a cage and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
WEEK 11
Activity 1: Ground floor columns (Grid 1-4)
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks
Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry
equipment
Skilled worker: Carpenter (2) , Rebar bender (2), General worker (4)
Technical information: Steel rebar are bended to form a cage and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
Activity 2: First floor beam (4-6)
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks,
Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry
equipment
Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3)
Technical Information: Steel rebar are bended to form a cage and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
WEEK 13
Activity 1: First floor beam (1-4)
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks,
Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry
equipment
Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3)
Technical Information: Steel rebar are bended to form a cage and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
Activity 2: First floor slab (Grid 4-6 )
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks
Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry
equipment
Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4)
Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
WEEK 13
Activity 1: First floor slab (Grid 1-4)
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks
Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry
equipment
Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4)
Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
Activity 2: First floor columns (Grid 4-6)
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks
Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry
equipment
Skilled worker: Carpenter (2) , Bar bender (2), General worker (4)
Technical information: Steel rebar are bended to form a cage and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
WEEK 14
Activity 1: First floor columns (Grid 1-4)
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks
Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry
equipment
Skilled worker: Carpenter (2) , Bar bender (2), General worker (4)
Technical information: Steel rebar are bended to form a cage and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
Activity 2: Second floor beam (Grid 4-6)
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks,
Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry
equipment
Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3)
Technical Information: Steel rebar are bended to form a cage and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
WEEK 15
Activity 1: Second floor beam (Grid 1-4)
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks,
Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry
equipment
Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3)
Technical Information: Steel rebar are bended to form a cage and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
Activity 2: Second floor slab (Grid 4-6)
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks
Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry
equipment
Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4)
Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
WEEK 16
Activity 1: Second floor slab (Grid 2-4)
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks
Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry
equipment
Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4)
Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure
WEEK 17
Activity 1: Second floor columns (Grid 2-6)
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks
Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry
equipment
Skilled worker: Carpenter (2) , Bar bender (2), General worker (4)
Technical information: Steel rebar are bended to form a cage and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
WEEK 17
Activity 1: Second floor columns (Grid 2-6)
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks
Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry
equipment
Skilled worker: Carpenter (2) , Bar bender (2), General worker (4)
Technical information: Steel rebar are bended to form a cage and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
WEEK 18
Activity 1: Third floor beam (Grid 2-6)
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks,
Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry
equipment
Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3)
Technical Information: Steel rebar are bended to form a cage and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
WEEK 19
Activity 1: Third floor beam (Grid 2-6)
Duration: 14 days
Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks,
Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry
equipment
Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3)
Technical Information: Steel rebar are bended to form a cage and put into position with starter bar
protruding outwards. Concrete is poured into the erected formwork and is left to cure.
Activity 2: Ground floor staircase
Duration: 14 days
Materials: Concrete Grade 35, Steel rebar reinforcement, Timber formworks, Adjustable steel rod
Equipment: Concrete mixer (1), Concrete Vibrator (1), Rebar bending machine (1), Carpentry
equipment
Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (4)
Technical Information: Steel rebar is bended forming a mesh and put into position and tied with the
starter bar. Pre-mixed grade 35 concrete is ordered and poured into the formwork in one time. A
concrete test is carried out to ensure the strength meet the requirements after it was left to cure for
7 days.
WEEK 20
Activity 1: Ground floor staircase
Duration: 14 days
Materials: Concrete Grade 35, Steel rebar reinforcement, Timber formworks, Adjustable steel rod
Equipment: Concrete mixer (1), Concrete Vibrator (1), Rebar bending machine (1), Carpentry
equipment
Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (4)
Technical Information: Steel rebar is bended forming a mesh and put into position and tied with the
starter bar. Pre-mixed grade 35 concrete is ordered and poured into the formwork in one time. A
concrete test is carried out to ensure the strength meet the requirements after it was left to cure for
7 days.
Activity 2: First floor staircase
Duration: 14 days
Materials: Concrete Grade 35, Steel rebar reinforcement, Timber formworks, Adjustable steel rod
Equipment: Concrete mixer (1), Concrete Vibrator (1), Rebar bending machine (1), Carpentry
equipment
Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (4)
Technical Information: Steel rebar is bended forming a mesh and put into position and tied with the
starter bar. Pre-mixed grade 35 concrete is ordered and poured into the formwork in one time. A
concrete test is carried out to ensure the strength meet the requirements after it was left to cure for
7 days.
WEEK 21
Activity 1: First floor staircase
Duration: 14 days
Materials: Concrete Grade 35, Steel rebar reinforcement, Timber formworks, Adjustable steel rod
Equipment: Concrete mixer (1), Concrete Vibrator (1), Rebar bending machine (1), Carpentry
equipment
Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (4)
Technical Information: Steel rebar is bended forming a mesh and put into position and tied with the
starter bar. Pre-mixed grade 35 concrete is ordered and poured into the formwork in one time. A
concrete test is carried out to ensure the strength meet the requirements after it was left to cure for
7 days.
WEEK 22
Activity 1: Roof truss assembling
Duration: 7-14 days
Materials: Aluminum roof truss components, Bolts and Nuts
Equipment: Steel Cutter (2), Welding machine (1)
Skilled Workers: General worker (2), Welding worker (2)
Technical information: After detailed calculation, the aluminum truss is ordered and is cut into
selected dimension and welded together at selected point.
WEEK 23
Activity 1: Roof truss assembling (continue)
Duration: 7-14 days
Materials: Aluminum roof truss components, Bolts and Nuts
Equipment: Steel Cutter (2), Welding machine (1)
Skilled Workers: General worker (2), Welding worker (2)
Technical information: After detailed calculation, the aluminum truss is ordered and is cut into
selected dimension and welded together at selected point.
Activity 2: Ground floor wall
Duration: 14-21 days
Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of
mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in
certain layer interval as reinforcement.
WEEK 24
Activity 1: Ground floor wall (cont)
Duration: 14-21 days
Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of
mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in
certain layer interval as reinforcement.
WEEK 25
Activity 1: Ground floor wall (cont)
Duration: 14-21 days
Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of
mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in
certain layer interval as reinforcement.
Activity 2: First floor wall
Duration: 14-21 days
Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of
mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in
certain layer interval as reinforcement.
WEEK 26
Activity 1: First floor wall (cont)
Duration: 14-21 days
Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of
mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in
certain layer interval as reinforcement.
WEEK 27
Activity 1: First floor wall (cont)
Duration: 14-21 days
Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of
mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in
certain layer interval as reinforcement.
Activity 1: Ground floor plastering
Duration: 14 -21 days
Material: Cementitious plaster
Equipment: Scaffolding, Plaster spray (1)
Skilled Worker: General worker (1), Plasterer (2)
Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain
from penetrating the walls. Smooth surface plastering shows up defect more easily than rough
surface hence, it is used indoor. Plaster is left to dry for a week.
WEEK 28
Activity 1: Second floor wall
Duration: 14-21 days
Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of
mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in
certain layer interval as reinforcement.
Activity 2: Ground floor plastering (cont)
Duration: 14 -21 days
Material: Cementitious plaster
Equipment: Scaffolding, Plaster spray (1)
Skilled Worker: General worker (1), Plasterer (2)
Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain
from penetrating the walls. Smooth surface plastering shows up defect more easily than rough
surface hence, it is used indoor. Plaster is left to dry for a week.
WEEk 29
Activity 1: Second floor wall (cont)
Duration: 14-21 days
Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of
mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in
certain layer interval as reinforcement.
Activity 2: First floor plastering
Duration: 14 -21 days
Material: Cementitious plaster
Equipment: Scaffolding, Plaster spray (1)
Skilled Worker: General worker (1), Plasterer (2)
Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain
from penetrating the walls. Smooth surface plastering shows up defect more easily than rough
surface hence, it is used indoor. Plaster is left to dry for a week.
WEEk 30
Activity 1: Second floor wall (cont)
Duration: 14-21 days
Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of
mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in
certain layer interval as reinforcement.
Activity 2: First floor plastering (cont)
Duration: 14 -21 days
Material: Cementitious plaster
Equipment: Scaffolding, Plaster spray (1)
Skilled Worker: General worker (1), Plasterer (2)
Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain
from penetrating the walls. Smooth surface plastering shows up defect more easily than rough
surface hence, it is used indoor. Plaster is left to dry for a week.
WEEk 31
Activity 1: Roof installation (1st
Floor)
Duration: 7- 14 days
Materials: Concrete, EDPM rubber, insulation, vapour control layer, timber formwork
Equipment: Mobile Crane
Skilled Workers: General worker (4), Mobile crane operator (1)
Technical information: The roof is inclined for the rain water to flow off the roof. Vapour control
layers are normally considered essential under insulation in warm roof constructions to reduce the
risk of condensation. Thermal insulation reduces heat from going into the building. EPDM rubber act
as a waterproofing membrane.
Activity 2: Second floor plastering
Duration: 14 -21 days
Material: Cementitious plaster
Equipment: Scaffolding, Plaster spray (1)
Skilled Worker: General worker (1), Plasterer (2)
Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain
from penetrating the walls. Smooth surface plastering shows up defect more easily than rough
surface hence, it is used indoor. Plaster is left to dry for a week.
Activity 3: Ground Floor Tiling
Duration: 14-21 days
Materials: Ceramic tiles, Cement mortar, Silicone sealant
Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)
Skilled Worker: General worker (2)
Technical Information: The dimensions of the place is taken and calculated and tiles are cut into
suitable shapes before placing.
WEEk 32
Activity 1: Second floor plastering (cont)
Duration: 14 -21 days
Material: Cementitious plaster
Equipment: Scaffolding, Plaster spray (1)
Skilled Worker: General worker (1), Plasterer (2)
Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain
from penetrating the walls. Smooth surface plastering shows up defect more easily than rough
surface hence, it is used indoor. Plaster is left to dry for a week.
Activity 2: Ground Floor Tiling (cont)
Duration: 14-21 days
Materials: Ceramic tiles, Cement mortar, Silicone sealant
Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)
Skilled Worker: General worker (2)
Technical Information: The dimensions of the place is taken and calculated and tiles are cut into
suitable shapes before placing.
WEEK 33
Activity 1: Ground Floor Tiling (cont)
Duration: 14-21 days
Materials: Ceramic tiles, Cement mortar, Silicone sealant
Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)
Skilled Worker: General worker (2)
Technical Information: The dimensions of the place is taken and calculated and tiles are cut into
suitable shapes before placing.
Activity 2: First floor tiling
Duration: 14-21 days
Materials: Ceramic tiles, Cement mortar, Silicone sealant
Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)
Skilled Worker: General worker (2)
Technical Information: The dimensions of the place is taken and calculated and tiles are cut into
suitable shapes before placing.
Activity 1: Roof installation (2nd
Floor)
Duration: 7- 14 days
Materials: Concrete, EDPM rubber, insulation, vapour control layer, timber formwork
Equipment: Mobile Crane
Skilled Workers: General worker (4), Mobile crane operator (1)
Technical information: The roof is inclined for the rain water to flow off the roof. Vapour control
layers are normally considered essential under insulation in warm roof constructions to reduce the
risk of condensation. Thermal insulation reduces heat from going into the building. EPDM rubber act
as a waterproofing membrane.
WEEK 34
Activity 1: First floor tiling (cont)
Duration: 14-21 days
Materials: Ceramic tiles, Cement mortar, Silicone sealant
Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)
Skilled Worker: General worker (2)
Technical Information: The dimensions of the place is taken and calculated and tiles are cut into
suitable shapes before placing.
Activity 2: Ground floor Painting – undercoat
Duration: 21 days
Materials: Wall Sealer
Equipment: Paint brush (3), Point roller (3)
Skilled Worker: Painter (5)
Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent
absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for
the paint to stick on firmly without having bubbling and waterborne stain.
WEEK 35
Activity 2: First floor tiling (cont)
Duration: 14-21 days
Materials: Ceramic tiles, Cement mortar, Silicone sealant
Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)
Skilled Worker: General worker (2)
Technical Information: The dimensions of the place is taken and calculated and tiles are cut into
suitable shapes before placing.
Activity 3: Ground floor Painting – undercoat (cont)
Duration: 21 days
Materials: Wall Sealer
Equipment: Paint brush (3), Point roller (3)
Skilled Worker: Painter (5)
Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent
absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for
the paint to stick on firmly without having bubbling and waterborne stain.
WEEK 36
Activity 1: Second floor tiling
Duration: 14-21 days
Materials: Ceramic tiles, Cement mortar, Silicone sealant
Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)
Skilled Worker: General worker (2)
Technical Information: The dimensions of the place is taken and calculated and tiles are cut into
suitable shapes before placing.
Activity 2: Ground floor Painting – undercoat (cont)
Duration: 21 days
Materials: Wall Sealer
Equipment: Paint brush (3), Point roller (3)
Skilled Worker: Painter (5)
Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent
absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for
the paint to stick on firmly without having bubbling and waterborne stain.
WEEK 37
Activity 1: Second floor tiling (cont)
Duration: 14-21 days
Materials: Ceramic tiles, Cement mortar, Silicone sealant
Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)
Skilled Worker: General worker (2)
Technical Information: The dimensions of the place is taken and calculated and tiles are cut into
suitable shapes before placing.
Activity 2: First floor Painting – undercoat
Duration: 21 days
Materials: Wall Sealer
Equipment: Paint brush (3), Point roller (3)
Skilled Worker: Painter (5)
Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent
absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for
the paint to stick on firmly without having bubbling and waterborne stain.
WEEK 38
Activity 1: Second floor tiling (cont)
Duration: 14-21 days
Materials: Ceramic tiles, Cement mortar, Silicone sealant
Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)
Skilled Worker: General worker (2)
Technical Information: The dimensions of the place is taken and calculated and tiles are cut into
suitable shapes before placing.
Activity 2: First floor Painting – undercoat (cont)
Duration: 21 days
Materials: Wall Sealer
Equipment: Paint brush (3), Point roller (3)
Skilled Worker: Painter (5)
Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent
absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for
the paint to stick on firmly without having bubbling and waterborne stain.
WEEK 39
Activity 1: First floor Painting – undercoat (cont)
Duration: 21 days
Materials: Wall Sealer
Equipment: Paint brush (3), Point roller (3)
Skilled Worker: Painter (5)
Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent
absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for
the paint to stick on firmly without having bubbling and waterborne stain.
Activity 2: Ground floor Painting – First coat
Duration: 14 days
Materials: First coat
Equipment: Paint brush (3), Point roller (3), Scaffolding
Skilled Worker: Painter (5)
Technical Information: Painting for finishing should be done after the plastering and undercoating
are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few
layers for better surface finishes.
WEEK 40
Activity 2: Ground floor Painting – First coat (cont)
Duration: 14 days
Materials: First coat
Equipment: Paint brush (3), Point roller (3), Scaffolding
Skilled Worker: Painter (5)
Technical Information: Painting for finishing should be done after the plastering and undercoating
are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few
layers for better surface finishes.
Activity 1: Second floor Painting – undercoat
Duration: 21 days
Materials: Wall Sealer
Equipment: Paint brush (3), Point roller (3)
Skilled Worker: Painter (5)
Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent
absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for
the paint to stick on firmly without having bubbling and waterborne stain.
WEEK 41
Activity 1: Second floor Painting – undercoat (cont)
Duration: 21 days
Materials: Wall Sealer
Equipment: Paint brush (3), Point roller (3)
Skilled Worker: Painter (5)
Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent
absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for
the paint to stick on firmly without having bubbling and waterborne stain.
Activity 2: First floor Painting – First coat
Duration: 14 days
Materials: First coat
Equipment: Paint brush (3), Point roller (3), Scaffolding
Skilled Worker: Painter (5)
Technical Information: Painting for finishing should be done after the plastering and undercoating
are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few
layers for better surface finishes.
WEEK 42
Activity 1: Second floor Painting – undercoat (cont)
Duration: 21 days
Materials: Wall Sealer
Equipment: Paint brush (3), Point roller (3)
Skilled Worker: Painter (5)
Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent
absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for
the paint to stick on firmly without having bubbling and waterborne stain.
Activity 2: First floor Painting – First coat (cont)
Duration: 14 days
Materials: First coat
Equipment: Paint brush (3), Point roller (3), Scaffolding
Skilled Worker: Painter (5)
Technical Information: Painting for finishing should be done after the plastering and undercoating
are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few
layers for better surface finishes.
WEEK 43
Activity 1: Second floor Painting – First coat
Duration: 14 days
Materials: First coat
Equipment: Paint brush (3), Point roller (3), Scaffolding
Skilled Worker: Painter (5)
Technical Information: Painting for finishing should be done after the plastering and undercoating
are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few
layers for better surface finishes.
WEEK 44
Activity 1: Second floor Painting – First coat
Duration: 14 days
Materials: First coat
Equipment: Paint brush (3), Point roller (3), Scaffolding
Skilled Worker: Painter (5)
Technical Information: Painting for finishing should be done after the plastering and undercoating
are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few
layers for better surface finishes.
Activity 2: Ground floor openings
Durations: 7 days
Materials: Door & window frame
Equipment: Spirit level, Measuring tape
Skilled Workers: General Workers (4)
Technical Information: The door frame is placed in position and aligned after the brick wall is done.
Architrave is added after the door/window frame is added.
WEEK 45
Activity 1: Ground floor Railings, Doors and Windows installation
Durations: 7 days
Materials: Variety of doors and windows, railings
Equipment: Bolts and Nuts, Screwdriver and related toolkit.
Skilled worker: General workers (4)
Technical information: The doors and windows are mounted to ensure the house is lockable before
the fittings is installed
Activity 2: First floor openings
Durations: 7 days
Materials: Door & window frame
Equipment: Spirit level, Measuring tape
Skilled Workers: General Workers (4)
Technical Information: The door frame is placed in position and aligned after the brick wall is done.
Architrave is added after the door/window frame is added.
WEEK 46
Activity 1: First floor Railings, Doors and Windows installation
Durations: 7 days
Materials: Variety of doors and windows, railings
Equipment: Bolts and Nuts, Screwdriver and related toolkit.
Skilled worker: General workers (4)
Technical information: The doors and windows are mounted to ensure the house is lockable before
the fittings is installed
Activity 2: Second floor openings
Durations: 7 days
Materials: Door & window frame
Equipment: Spirit level, Measuring tape
Skilled Workers: General Workers (4)
Technical Information: The door frame is placed in position and aligned after the brick wall is done.
Architrave is added after the door/window frame is added.
WEEK 47
Activity 1: Second floor Doors and Windows installation
Durations: 7 days
Materials: Variety of doors and windows, railings
Equipment: Bolts and Nuts, Screwdriver and related toolkit.
Skilled worker: General workers (4)
Technical information: The doors and windows are mounted to ensure the house is lockable before
the fittings is installed.
WEEK 48
Activity 1: Electrical Supply
Duration: 14 days
Materials: Copper Cables (different sizes), Kilowatt hour meter
Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts,
Skilled Workers: Electric Technician (2), Plumbers (2)
Technical Information: Incoming electricity cables are brought into the house and connected to a
circuit box in the house to facilitate the electricity works later on.
Activity 2: Water Supply
Duration: 14 days
Materials: PVC pipes (different sizes), Water flow meter
Equipment: Spanner, Plyers, Pipe cutter
Skilled Workers: Plumbers (2)
Technical Information: Incoming water supply are brought into the house and connected to the
water flow meter to facilitate the plumbing works later on.
WEEK 49
Activity 1: Electrical Supply
Duration: 14 days
Materials: Copper Cables (different sizes), Kilowatt hour meter
Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts,
Skilled Workers: Electric Technician (2), Plumbers (2)
Technical Information: Incoming electricity cables are brought into the house and connected to a
circuit box in the house to facilitate the electricity works later on.
Activity 2: Water Supply
Duration: 14 days
Materials: PVC pipes (different sizes), Water flow meter
Equipment: Spanner, Plyers, Pipe cutter
Skilled Workers: Plumbers (2)
Technical Information: Incoming water supply are brought into the house and connected to the
water flow meter to facilitate the plumbing works later on.
Activity 3: Ground Floor Electrical Plumbing (First - Fix)
Duration: 14 days
Materials: Copper Cables (different sizes), PVC pipes, socket box
Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine
Skilled Workers: Electrician Plumbers (2)
Technical Information: The brick wall is hacked to hide the wiring pipe which runs perpendicularly
from the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done.
WEEK 50
Activity 1: Ground Floor Electrical Plumbing (First - Fix)
Duration: 14 days
Materials: Copper Cables (different sizes), PVC pipes, socket box
Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine
Skilled Workers: Electrician Plumbers (2)
Technical Information: The brick wall is hacked to hide the wiring pipe which runs perpendicularly
from the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done.
Activity 2: First Floor Electrical Plumbing (First - Fix)
Duration: 14 days
Materials: Copper Cables (different sizes), PVC pipes, socket box
Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine
Skilled Workers: Electrician Plumbers (2)
Technical Information: Brick wall is hacked to hide the wiring pipe which runs perpendicularly from
the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done.
Activity 3: Second Floor Electrical Plumbing (First - Fix)
Duration: 14 days
Materials: Copper Cables (different sizes), PVC pipes, Socket box, Junction box
Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine
Skilled Workers: Electrician Plumbers (2)
Technical Information: Brick wall is hacked to hide the wiring pipe which runs perpendicularly from
the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done.
Activity 4: Plumbing – Kitchens and Toilets
Duration: 14 days
Materials: PVC pipes (different sizes), Pipe joints,
Equipment: Spanner, Plyers, Pipe cutter
Skilled Workers: Plumbers (2)
WEEK 51
Activity 1: First Floor Electrical Plumbing (First - Fix)
Duration: 14 days
Materials: Copper Cables (different sizes), PVC pipes, socket box
Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine
Skilled Workers: Electrician Plumbers (2)
Technical Information: Brick wall is hacked to hide the wiring pipe which runs perpendicularly from
the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done.
Activity 2: Second Floor Electrical Plumbing (First - Fix)
Duration: 14 days
Materials: Copper Cables (different sizes), PVC pipes, Socket box, Junction box
Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine
Skilled Workers: Electrician Plumbers (2)
Technical Information:Brick wall is hacked to hide the wiring pipe which runs perpendicularly from
the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done.
Activity 3: Plumbing – Kitchens and Toilets
Duration: 14 days
Materials: PVC pipes (different sizes), Pipe joints,
Equipment: Spanner, Plyers, Pipe cutter
Skilled Workers: Plumbers (2)
WEEK 52
Activity 1: Electrical & Sanitary fittings
Durations: 14 days
Materials: Wall sockets, Wall plugs and bathroom porcelain appliances
Equipment: Bolts and Nuts, Screwdriver and related toolkit.
Skilled worker: General worker (4)
WEEK 53
Activity 1: Grass turfing – External work
Duration: 7 days Materials: lawn turf rolls ( depends on the size of garden), bricks
Equipment: wheel barrow, gardening tool kits, water pipes
Skilled Workers: lawn turf layers(2), general workers (2)
Technical information: Soil preparation is done before laying the rolls of grass turf on the soil
surfaces. Previously excavated soil can be reused as the base of the courtyard. Loose stones and
building rubble will prevent the turves roots from making contact with the soil and could make the
turf die in patches. The top soil should then be thoroughly rotivated down to about the first 6 inches
to aerate it properly. It is then raked level and gently treaded down.
- END OF REPORT -

Contenu connexe

Tendances

Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surface
Minh Bui Si
 
Tender Evaluation Process Notes
Tender Evaluation Process NotesTender Evaluation Process Notes
Tender Evaluation Process Notes
Alan McSweeney
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
Awanish Shukla
 
Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0
Minh Bui Si
 
CERAMIC WASTE CONCRETE
CERAMIC WASTE CONCRETECERAMIC WASTE CONCRETE
CERAMIC WASTE CONCRETE
seminarppts
 

Tendances (20)

Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surface
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
BUILDING CONSTRUCTION PROJECT 1
BUILDING CONSTRUCTION PROJECT 1BUILDING CONSTRUCTION PROJECT 1
BUILDING CONSTRUCTION PROJECT 1
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 
Manual plastering
Manual plasteringManual plastering
Manual plastering
 
Labour Productivity for construction projects
Labour Productivity for construction projectsLabour Productivity for construction projects
Labour Productivity for construction projects
 
Tender Evaluation Process Notes
Tender Evaluation Process NotesTender Evaluation Process Notes
Tender Evaluation Process Notes
 
Metode kerja pierhead
Metode kerja pierheadMetode kerja pierhead
Metode kerja pierhead
 
Bridge defects
Bridge defectsBridge defects
Bridge defects
 
Building construction
Building constructionBuilding construction
Building construction
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge Construction
 
Structural audit
Structural auditStructural audit
Structural audit
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
 
Advanced Material for Construction
Advanced Material for ConstructionAdvanced Material for Construction
Advanced Material for Construction
 
BASICS OF CIVIL ENGINEERING
BASICS OF CIVIL ENGINEERINGBASICS OF CIVIL ENGINEERING
BASICS OF CIVIL ENGINEERING
 
Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1
 
Defects in buildings
Defects in buildingsDefects in buildings
Defects in buildings
 
CURRICULUM_VITAE__NHAI_latest
CURRICULUM_VITAE__NHAI_latestCURRICULUM_VITAE__NHAI_latest
CURRICULUM_VITAE__NHAI_latest
 
CERAMIC WASTE CONCRETE
CERAMIC WASTE CONCRETECERAMIC WASTE CONCRETE
CERAMIC WASTE CONCRETE
 

En vedette

Construction process
Construction processConstruction process
Construction process
Mazen Al-Qadi
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)
Soh Shing
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
Wilden How
 
Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1
Dexter Ng
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building Construction
Hamdija Velagic
 
building materials
building materialsbuilding materials
building materials
nicocarlos
 
Building Structures Report
Building Structures ReportBuilding Structures Report
Building Structures Report
Joanne Yunn Tze
 
Chapter 1.3 properties of glass crystalline mixtures
Chapter 1.3 properties of glass crystalline mixturesChapter 1.3 properties of glass crystalline mixtures
Chapter 1.3 properties of glass crystalline mixtures
Gawewat Dechaapinun
 

En vedette (20)

Construction process
Construction processConstruction process
Construction process
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)
 
Book Bulding Process
Book Bulding ProcessBook Bulding Process
Book Bulding Process
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Building construction
Building constructionBuilding construction
Building construction
 
Internship Report on Building Construction
Internship Report on Building ConstructionInternship Report on Building Construction
Internship Report on Building Construction
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.
 
Building construction
Building constructionBuilding construction
Building construction
 
Plastic use as building material ppt
Plastic use as building material pptPlastic use as building material ppt
Plastic use as building material ppt
 
Building construction ppt
Building construction pptBuilding construction ppt
Building construction ppt
 
Foundation
FoundationFoundation
Foundation
 
Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1
 
Construction Materials
Construction MaterialsConstruction Materials
Construction Materials
 
5. construction equipment Building Construction
5. construction equipment Building Construction5. construction equipment Building Construction
5. construction equipment Building Construction
 
building materials
building materialsbuilding materials
building materials
 
IPO/FPO : Book building process
IPO/FPO : Book building processIPO/FPO : Book building process
IPO/FPO : Book building process
 
Building Structures Report
Building Structures ReportBuilding Structures Report
Building Structures Report
 
Business plan on fly ash (final)
Business plan on fly ash (final)Business plan on fly ash (final)
Business plan on fly ash (final)
 
Chapter 1.3 properties of glass crystalline mixtures
Chapter 1.3 properties of glass crystalline mixturesChapter 1.3 properties of glass crystalline mixtures
Chapter 1.3 properties of glass crystalline mixtures
 

Similaire à Building Construction process

Bcon final report
Bcon final reportBcon final report
Bcon final report
Qing Cheng
 
Ae 372 Project 1 Final
Ae 372   Project 1   FinalAe 372   Project 1   Final
Ae 372 Project 1 Final
Josh Wentz
 

Similaire à Building Construction process (14)

Bcon final report
Bcon final reportBcon final report
Bcon final report
 
MCB Final report
MCB Final reportMCB Final report
MCB Final report
 
Building Construction 1 - Final Project
Building Construction 1 - Final ProjectBuilding Construction 1 - Final Project
Building Construction 1 - Final Project
 
M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1
 
Integrated site vite report
Integrated site vite reportIntegrated site vite report
Integrated site vite report
 
SITE REPORT
SITE REPORTSITE REPORT
SITE REPORT
 
Ae 372 Project 1 Final
Ae 372   Project 1   FinalAe 372   Project 1   Final
Ae 372 Project 1 Final
 
Final Document
Final DocumentFinal Document
Final Document
 
Building Construction Project 2 Report
Building Construction Project 2 ReportBuilding Construction Project 2 Report
Building Construction Project 2 Report
 
Project Report - CECL
Project Report - CECLProject Report - CECL
Project Report - CECL
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
 
Construction maintenance
Construction maintenanceConstruction maintenance
Construction maintenance
 
1. introduction (materials and method of constrcution)
1. introduction (materials and method of constrcution)1. introduction (materials and method of constrcution)
1. introduction (materials and method of constrcution)
 
Unit 2 - Site Investigation.ppt
Unit 2 - Site Investigation.pptUnit 2 - Site Investigation.ppt
Unit 2 - Site Investigation.ppt
 

Plus de Joanne Yunn Tze (9)

Building Science 2 Report
Building Science 2 ReportBuilding Science 2 Report
Building Science 2 Report
 
Theories of Architecture & Urbanism
Theories of Architecture & UrbanismTheories of Architecture & Urbanism
Theories of Architecture & Urbanism
 
Theories of Architecture & Urbanism
Theories of Architecture & UrbanismTheories of Architecture & Urbanism
Theories of Architecture & Urbanism
 
Bioclimatic Architecture
Bioclimatic ArchitectureBioclimatic Architecture
Bioclimatic Architecture
 
Building Structures (Individual)
Building Structures (Individual)Building Structures (Individual)
Building Structures (Individual)
 
Building Services Report
Building Services ReportBuilding Services Report
Building Services Report
 
Fettucine Bridge Report
Fettucine Bridge ReportFettucine Bridge Report
Fettucine Bridge Report
 
Building construction project 1
Building construction project 1Building construction project 1
Building construction project 1
 
Final History Report
Final History ReportFinal History Report
Final History Report
 

Dernier

Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
ssuserdda66b
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
QucHHunhnh
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
KarakKing
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 

Dernier (20)

Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptx
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 

Building Construction process

  • 1. SCHOOL OF ARCHITECTURE• BUILDING• DESIGN Centre for Modern Architecture Studies in Southeast Asia (MASSA) Bachelor of Science (Honours) in Architecture BUILDING CONSTRUCTION 1 [ARC 1523] PROJECT 2: CONSTRUCTION ACTIVITY AND PROCESS JOANNE BERNICE CHUA YUNN TZE 0315905 TUTOR: AR. CHIN TUCK HING
  • 2. CONSTRUCTION PROCESS WEEK 1 Activity 1: Survey Work Duration: 7 days Materials: - Equipment: Surveying tripod, Theodolite, Dumpy level, Measuring tape, Excavator Skilled Workers: Land surveyor (1), Soil investigator (1) Technical Information: Built environment and natural surroundings of the site is studied, analysed and data is collected. Trial pitting is carried out to examine soil condition. Excavation boundary is indicated. WEEK 2 Activity 1: Mobilization and Hoarding Duration: 2-5 days Materials: -
  • 3. Equipment: Machineries, Hoarders Skilled Workers: General workers (4) Technical Information: The site office and construction machineries and equipment are transported to the site. Activity 2: Site Clearing Duration: 14 days Materials: - Equipment: Backhoe loader, Excavator, Bulldozer operator (1), Chainsaws, Tipper truck, Skilled Workers: Backhoe Loader Operator (1), Excavator operator(1), Bulldozer operator (1), General workers (4), Truck driver (1) Technical Information: Specific trees are removed and 300mm of top soil is excavated. The soil is kept away or stored well for reuse due to its high water retentive characteristic. WEEK 3 Activity 1: Site Clearing Duration: 14 days Materials: - Equipment: Backhoe loader, Excavator, Bulldozer operator (1), Chainsaws, Tipper truck, Skilled Workers: Backhoe Loader Operator (1), Excavator operator(1), Bulldozer operator (1), General workers (4), Truck driver (1) Technical Information: Specific trees are removed and 300mm of top soil is excavated. The soil is kept away or stored well for reuse due to its high water retentive characteristic.
  • 4. WEEK 4 Activity 1: Earthwork Duration: 3-5 days Materials: - Equipment: Excavator, Compactor, Tipper truck Skilled Workers: Excavator operator (1), Compactor operator (1), Truck driver (1) technical information: The uneven land area is either compacted or filled with earth excavated from site or transferred in to level the ground. Activity 2: Setting Out Duration: 3 days Materials: Nails, Wooden pegs, Profile boards, Stakes, Builder’s line Equipment: Hammer, Measuring tape, Theodolite, Dumpy level Skilled Workers: Site Contractor (1), Site Engineer (1)
  • 5. Technical Information: Measurements are taken and the boundary lines of the building are marked clearly. WEEK 5 Activity 1: Piling (Grid 5-6) Duration: 10-14 days Materials: Pre-Cast reinforced concrete piles Equipment: Hydraulic piling hammer, Pile integrity tester Skilled Workers: Hydraulic Piling Hammer Operator (1), General workers (6) Technical Information: The first half of the piles are driven down The Pile integrity test (Load test) is carried out to ensure the strength meet the requirement.
  • 6. WEEK 6 Activity 1: Piling (Grid 1-4) Duration: 10-14 days Materials: Pre-Cast reinforced concrete piles Equipment: Hydraulic piling hammer, Pile integrity tester Skilled Workers: Hydraulic Piling Hammer Operator (1), General workers (6) Technical Information: The second half of the piles are driven down The Pile integrity test (Load test) is carried out to ensure the strength meet the requirement. Activity 2: Pile capping (Grid 5-6) Duration: 10-14 days Materials: Concrete Grade 30, Steel Rebar reinforcement, Timber formwork Equipment: Rebar bending machine (1), Cement mixer (1), Skilled Workers: Rebar benders (2), General workers (6) Technical Information: Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure.
  • 7. WEEK 7 Activity 1: Pile capping (Grid 1-4) Duration: 10-14 days Materials: Concrete Grade 30, Steel Rebar reinforcement, Timber formwork Equipment: Rebar bending machine (1), Cement mixer (1), Skilled Workers: Rebar benders (2), General workers (6) Technical Information: Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure. Activity 2: Stump on pile cap (Grid 5-6 ) Duration: 7–14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formwork Equipment: Concrete Vibrator (1), Rebar bending machine(1), Carpentry equipment, Theodolite Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4), Land surveyor (1) Technical Information: The height of the stump is adjusted to keep the floor levelled. Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure.
  • 8. WEEK 8 Activity 1: Stump on pile cap (Grid 1-4 ) Duration: 7–14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formwork Equipment: Concrete Vibrator (1), Rebar bending machine (1), Carpentry equipment, Theodolite Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4), Land surveyor (1) Technical Information: The height of the stump is adjusted to keep the floor levelled. Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure. Activity 2: Ground beam (Grid 5-6 ) Duration: 7–14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks, Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry equipment Skilled Workers: Carpenter (2), Rebar Bender (1), General workers (3) Technical Information: Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure.
  • 9. WEEK 9 Activity 1: Ground beam (Grid 1-4 ) Duration: 7–14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks, Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry equipment Skilled Workers: Carpenter (2), Rebar Bender (1), General workers (3) Technical Information: Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure. Activity 2: Ground floor slab (Grid 4-6) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks, Damp Proof Membrane (DPM), Screed Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry equipment Skilled Workers: Carpenters (2), Rebar Bender (1), General workers (4) Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure. Next, a layer of DPM is applied on the top of the concrete and was covered with a layer of screed to level the slab.
  • 10. WEEK 10 Activity 1: Ground floor slab (Grid 1-4) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks, Damp Proof Membrane (DPM), Screed Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry equipment Skilled Workers: Carpenters (2), Rebar Bender (1), General workers (4) Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure. Next, a layer of DPM is applied on the top of the concrete and was covered with a layer of screed to level the slab. Activity 2: Ground floor columns (Grid 4-6) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry equipment Skilled worker: Carpenter (2) , Rebar bender (2), General worker (4) Technical information: Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure.
  • 11. WEEK 11 Activity 1: Ground floor columns (Grid 1-4) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry equipment Skilled worker: Carpenter (2) , Rebar bender (2), General worker (4) Technical information: Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure. Activity 2: First floor beam (4-6) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks, Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry equipment Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3) Technical Information: Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure.
  • 12. WEEK 13 Activity 1: First floor beam (1-4) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks, Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry equipment Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3) Technical Information: Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure. Activity 2: First floor slab (Grid 4-6 ) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry equipment Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4) Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure.
  • 13. WEEK 13 Activity 1: First floor slab (Grid 1-4) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry equipment Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4) Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure. Activity 2: First floor columns (Grid 4-6) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry equipment Skilled worker: Carpenter (2) , Bar bender (2), General worker (4) Technical information: Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure.
  • 14. WEEK 14 Activity 1: First floor columns (Grid 1-4) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry equipment Skilled worker: Carpenter (2) , Bar bender (2), General worker (4) Technical information: Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure. Activity 2: Second floor beam (Grid 4-6) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks, Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry equipment Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3) Technical Information: Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure.
  • 15. WEEK 15 Activity 1: Second floor beam (Grid 1-4) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks, Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry equipment Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3) Technical Information: Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure. Activity 2: Second floor slab (Grid 4-6) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry equipment Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4) Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure.
  • 16. WEEK 16 Activity 1: Second floor slab (Grid 2-4) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry equipment Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4) Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure WEEK 17 Activity 1: Second floor columns (Grid 2-6) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry equipment Skilled worker: Carpenter (2) , Bar bender (2), General worker (4) Technical information: Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure.
  • 17. WEEK 17 Activity 1: Second floor columns (Grid 2-6) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry equipment Skilled worker: Carpenter (2) , Bar bender (2), General worker (4) Technical information: Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure. WEEK 18 Activity 1: Third floor beam (Grid 2-6) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks, Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry equipment Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3) Technical Information: Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure.
  • 18. WEEK 19 Activity 1: Third floor beam (Grid 2-6) Duration: 14 days Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks, Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry equipment Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3) Technical Information: Steel rebar are bended to form a cage and put into position with starter bar protruding outwards. Concrete is poured into the erected formwork and is left to cure. Activity 2: Ground floor staircase Duration: 14 days Materials: Concrete Grade 35, Steel rebar reinforcement, Timber formworks, Adjustable steel rod Equipment: Concrete mixer (1), Concrete Vibrator (1), Rebar bending machine (1), Carpentry equipment Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (4) Technical Information: Steel rebar is bended forming a mesh and put into position and tied with the starter bar. Pre-mixed grade 35 concrete is ordered and poured into the formwork in one time. A concrete test is carried out to ensure the strength meet the requirements after it was left to cure for 7 days.
  • 19. WEEK 20 Activity 1: Ground floor staircase Duration: 14 days Materials: Concrete Grade 35, Steel rebar reinforcement, Timber formworks, Adjustable steel rod Equipment: Concrete mixer (1), Concrete Vibrator (1), Rebar bending machine (1), Carpentry equipment Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (4) Technical Information: Steel rebar is bended forming a mesh and put into position and tied with the starter bar. Pre-mixed grade 35 concrete is ordered and poured into the formwork in one time. A concrete test is carried out to ensure the strength meet the requirements after it was left to cure for 7 days. Activity 2: First floor staircase Duration: 14 days Materials: Concrete Grade 35, Steel rebar reinforcement, Timber formworks, Adjustable steel rod Equipment: Concrete mixer (1), Concrete Vibrator (1), Rebar bending machine (1), Carpentry equipment Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (4) Technical Information: Steel rebar is bended forming a mesh and put into position and tied with the starter bar. Pre-mixed grade 35 concrete is ordered and poured into the formwork in one time. A concrete test is carried out to ensure the strength meet the requirements after it was left to cure for 7 days.
  • 20. WEEK 21 Activity 1: First floor staircase Duration: 14 days Materials: Concrete Grade 35, Steel rebar reinforcement, Timber formworks, Adjustable steel rod Equipment: Concrete mixer (1), Concrete Vibrator (1), Rebar bending machine (1), Carpentry equipment Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (4) Technical Information: Steel rebar is bended forming a mesh and put into position and tied with the starter bar. Pre-mixed grade 35 concrete is ordered and poured into the formwork in one time. A concrete test is carried out to ensure the strength meet the requirements after it was left to cure for 7 days. WEEK 22 Activity 1: Roof truss assembling Duration: 7-14 days Materials: Aluminum roof truss components, Bolts and Nuts Equipment: Steel Cutter (2), Welding machine (1) Skilled Workers: General worker (2), Welding worker (2) Technical information: After detailed calculation, the aluminum truss is ordered and is cut into selected dimension and welded together at selected point.
  • 21. WEEK 23 Activity 1: Roof truss assembling (continue) Duration: 7-14 days Materials: Aluminum roof truss components, Bolts and Nuts Equipment: Steel Cutter (2), Welding machine (1) Skilled Workers: General worker (2), Welding worker (2) Technical information: After detailed calculation, the aluminum truss is ordered and is cut into selected dimension and welded together at selected point. Activity 2: Ground floor wall Duration: 14-21 days Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in certain layer interval as reinforcement.
  • 22. WEEK 24 Activity 1: Ground floor wall (cont) Duration: 14-21 days Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in certain layer interval as reinforcement. WEEK 25 Activity 1: Ground floor wall (cont) Duration: 14-21 days Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in certain layer interval as reinforcement. Activity 2: First floor wall Duration: 14-21 days Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in certain layer interval as reinforcement.
  • 23. WEEK 26 Activity 1: First floor wall (cont) Duration: 14-21 days Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in certain layer interval as reinforcement. WEEK 27 Activity 1: First floor wall (cont) Duration: 14-21 days Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in certain layer interval as reinforcement. Activity 1: Ground floor plastering Duration: 14 -21 days Material: Cementitious plaster Equipment: Scaffolding, Plaster spray (1) Skilled Worker: General worker (1), Plasterer (2)
  • 24. Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain from penetrating the walls. Smooth surface plastering shows up defect more easily than rough surface hence, it is used indoor. Plaster is left to dry for a week. WEEK 28 Activity 1: Second floor wall Duration: 14-21 days Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in certain layer interval as reinforcement. Activity 2: Ground floor plastering (cont) Duration: 14 -21 days Material: Cementitious plaster Equipment: Scaffolding, Plaster spray (1) Skilled Worker: General worker (1), Plasterer (2) Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain from penetrating the walls. Smooth surface plastering shows up defect more easily than rough surface hence, it is used indoor. Plaster is left to dry for a week.
  • 25. WEEk 29 Activity 1: Second floor wall (cont) Duration: 14-21 days Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in certain layer interval as reinforcement. Activity 2: First floor plastering Duration: 14 -21 days Material: Cementitious plaster Equipment: Scaffolding, Plaster spray (1) Skilled Worker: General worker (1), Plasterer (2) Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain from penetrating the walls. Smooth surface plastering shows up defect more easily than rough surface hence, it is used indoor. Plaster is left to dry for a week. WEEk 30 Activity 1: Second floor wall (cont) Duration: 14-21 days Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6)
  • 26. Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in certain layer interval as reinforcement. Activity 2: First floor plastering (cont) Duration: 14 -21 days Material: Cementitious plaster Equipment: Scaffolding, Plaster spray (1) Skilled Worker: General worker (1), Plasterer (2) Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain from penetrating the walls. Smooth surface plastering shows up defect more easily than rough surface hence, it is used indoor. Plaster is left to dry for a week. WEEk 31 Activity 1: Roof installation (1st Floor) Duration: 7- 14 days Materials: Concrete, EDPM rubber, insulation, vapour control layer, timber formwork Equipment: Mobile Crane Skilled Workers: General worker (4), Mobile crane operator (1) Technical information: The roof is inclined for the rain water to flow off the roof. Vapour control layers are normally considered essential under insulation in warm roof constructions to reduce the risk of condensation. Thermal insulation reduces heat from going into the building. EPDM rubber act as a waterproofing membrane. Activity 2: Second floor plastering Duration: 14 -21 days Material: Cementitious plaster Equipment: Scaffolding, Plaster spray (1)
  • 27. Skilled Worker: General worker (1), Plasterer (2) Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain from penetrating the walls. Smooth surface plastering shows up defect more easily than rough surface hence, it is used indoor. Plaster is left to dry for a week. Activity 3: Ground Floor Tiling Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: The dimensions of the place is taken and calculated and tiles are cut into suitable shapes before placing. WEEk 32 Activity 1: Second floor plastering (cont) Duration: 14 -21 days Material: Cementitious plaster Equipment: Scaffolding, Plaster spray (1) Skilled Worker: General worker (1), Plasterer (2) Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain from penetrating the walls. Smooth surface plastering shows up defect more easily than rough surface hence, it is used indoor. Plaster is left to dry for a week. Activity 2: Ground Floor Tiling (cont) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: The dimensions of the place is taken and calculated and tiles are cut into suitable shapes before placing. WEEK 33 Activity 1: Ground Floor Tiling (cont) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2)
  • 28. Technical Information: The dimensions of the place is taken and calculated and tiles are cut into suitable shapes before placing. Activity 2: First floor tiling Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: The dimensions of the place is taken and calculated and tiles are cut into suitable shapes before placing. Activity 1: Roof installation (2nd Floor) Duration: 7- 14 days Materials: Concrete, EDPM rubber, insulation, vapour control layer, timber formwork Equipment: Mobile Crane Skilled Workers: General worker (4), Mobile crane operator (1) Technical information: The roof is inclined for the rain water to flow off the roof. Vapour control layers are normally considered essential under insulation in warm roof constructions to reduce the risk of condensation. Thermal insulation reduces heat from going into the building. EPDM rubber act as a waterproofing membrane.
  • 29. WEEK 34 Activity 1: First floor tiling (cont) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: The dimensions of the place is taken and calculated and tiles are cut into suitable shapes before placing. Activity 2: Ground floor Painting – undercoat Duration: 21 days Materials: Wall Sealer Equipment: Paint brush (3), Point roller (3) Skilled Worker: Painter (5) Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for the paint to stick on firmly without having bubbling and waterborne stain.
  • 30. WEEK 35 Activity 2: First floor tiling (cont) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: The dimensions of the place is taken and calculated and tiles are cut into suitable shapes before placing. Activity 3: Ground floor Painting – undercoat (cont) Duration: 21 days Materials: Wall Sealer Equipment: Paint brush (3), Point roller (3) Skilled Worker: Painter (5) Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for the paint to stick on firmly without having bubbling and waterborne stain. WEEK 36 Activity 1: Second floor tiling Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: The dimensions of the place is taken and calculated and tiles are cut into suitable shapes before placing. Activity 2: Ground floor Painting – undercoat (cont) Duration: 21 days Materials: Wall Sealer Equipment: Paint brush (3), Point roller (3) Skilled Worker: Painter (5) Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for the paint to stick on firmly without having bubbling and waterborne stain.
  • 31. WEEK 37 Activity 1: Second floor tiling (cont) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: The dimensions of the place is taken and calculated and tiles are cut into suitable shapes before placing. Activity 2: First floor Painting – undercoat Duration: 21 days Materials: Wall Sealer Equipment: Paint brush (3), Point roller (3) Skilled Worker: Painter (5) Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for the paint to stick on firmly without having bubbling and waterborne stain. WEEK 38 Activity 1: Second floor tiling (cont) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: The dimensions of the place is taken and calculated and tiles are cut into suitable shapes before placing.
  • 32. Activity 2: First floor Painting – undercoat (cont) Duration: 21 days Materials: Wall Sealer Equipment: Paint brush (3), Point roller (3) Skilled Worker: Painter (5) Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for the paint to stick on firmly without having bubbling and waterborne stain. WEEK 39 Activity 1: First floor Painting – undercoat (cont) Duration: 21 days Materials: Wall Sealer Equipment: Paint brush (3), Point roller (3) Skilled Worker: Painter (5) Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for the paint to stick on firmly without having bubbling and waterborne stain. Activity 2: Ground floor Painting – First coat Duration: 14 days Materials: First coat Equipment: Paint brush (3), Point roller (3), Scaffolding Skilled Worker: Painter (5) Technical Information: Painting for finishing should be done after the plastering and undercoating are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few layers for better surface finishes. WEEK 40 Activity 2: Ground floor Painting – First coat (cont) Duration: 14 days Materials: First coat Equipment: Paint brush (3), Point roller (3), Scaffolding Skilled Worker: Painter (5) Technical Information: Painting for finishing should be done after the plastering and undercoating are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few layers for better surface finishes.
  • 33. Activity 1: Second floor Painting – undercoat Duration: 21 days Materials: Wall Sealer Equipment: Paint brush (3), Point roller (3) Skilled Worker: Painter (5) Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for the paint to stick on firmly without having bubbling and waterborne stain. WEEK 41 Activity 1: Second floor Painting – undercoat (cont) Duration: 21 days Materials: Wall Sealer Equipment: Paint brush (3), Point roller (3) Skilled Worker: Painter (5) Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for the paint to stick on firmly without having bubbling and waterborne stain. Activity 2: First floor Painting – First coat Duration: 14 days Materials: First coat Equipment: Paint brush (3), Point roller (3), Scaffolding Skilled Worker: Painter (5)
  • 34. Technical Information: Painting for finishing should be done after the plastering and undercoating are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few layers for better surface finishes. WEEK 42 Activity 1: Second floor Painting – undercoat (cont) Duration: 21 days Materials: Wall Sealer Equipment: Paint brush (3), Point roller (3) Skilled Worker: Painter (5) Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for the paint to stick on firmly without having bubbling and waterborne stain. Activity 2: First floor Painting – First coat (cont) Duration: 14 days Materials: First coat Equipment: Paint brush (3), Point roller (3), Scaffolding Skilled Worker: Painter (5) Technical Information: Painting for finishing should be done after the plastering and undercoating are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few layers for better surface finishes.
  • 35. WEEK 43 Activity 1: Second floor Painting – First coat Duration: 14 days Materials: First coat Equipment: Paint brush (3), Point roller (3), Scaffolding Skilled Worker: Painter (5) Technical Information: Painting for finishing should be done after the plastering and undercoating are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few layers for better surface finishes. WEEK 44 Activity 1: Second floor Painting – First coat Duration: 14 days Materials: First coat Equipment: Paint brush (3), Point roller (3), Scaffolding Skilled Worker: Painter (5) Technical Information: Painting for finishing should be done after the plastering and undercoating are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few layers for better surface finishes. Activity 2: Ground floor openings Durations: 7 days Materials: Door & window frame Equipment: Spirit level, Measuring tape Skilled Workers: General Workers (4) Technical Information: The door frame is placed in position and aligned after the brick wall is done. Architrave is added after the door/window frame is added.
  • 36. WEEK 45 Activity 1: Ground floor Railings, Doors and Windows installation Durations: 7 days Materials: Variety of doors and windows, railings Equipment: Bolts and Nuts, Screwdriver and related toolkit. Skilled worker: General workers (4) Technical information: The doors and windows are mounted to ensure the house is lockable before the fittings is installed Activity 2: First floor openings Durations: 7 days Materials: Door & window frame Equipment: Spirit level, Measuring tape Skilled Workers: General Workers (4) Technical Information: The door frame is placed in position and aligned after the brick wall is done. Architrave is added after the door/window frame is added.
  • 37. WEEK 46 Activity 1: First floor Railings, Doors and Windows installation Durations: 7 days Materials: Variety of doors and windows, railings Equipment: Bolts and Nuts, Screwdriver and related toolkit. Skilled worker: General workers (4) Technical information: The doors and windows are mounted to ensure the house is lockable before the fittings is installed Activity 2: Second floor openings Durations: 7 days Materials: Door & window frame Equipment: Spirit level, Measuring tape Skilled Workers: General Workers (4) Technical Information: The door frame is placed in position and aligned after the brick wall is done. Architrave is added after the door/window frame is added.
  • 38. WEEK 47 Activity 1: Second floor Doors and Windows installation Durations: 7 days Materials: Variety of doors and windows, railings Equipment: Bolts and Nuts, Screwdriver and related toolkit. Skilled worker: General workers (4) Technical information: The doors and windows are mounted to ensure the house is lockable before the fittings is installed. WEEK 48 Activity 1: Electrical Supply Duration: 14 days Materials: Copper Cables (different sizes), Kilowatt hour meter Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Skilled Workers: Electric Technician (2), Plumbers (2) Technical Information: Incoming electricity cables are brought into the house and connected to a circuit box in the house to facilitate the electricity works later on. Activity 2: Water Supply Duration: 14 days Materials: PVC pipes (different sizes), Water flow meter Equipment: Spanner, Plyers, Pipe cutter Skilled Workers: Plumbers (2) Technical Information: Incoming water supply are brought into the house and connected to the water flow meter to facilitate the plumbing works later on.
  • 39. WEEK 49 Activity 1: Electrical Supply Duration: 14 days Materials: Copper Cables (different sizes), Kilowatt hour meter Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Skilled Workers: Electric Technician (2), Plumbers (2) Technical Information: Incoming electricity cables are brought into the house and connected to a circuit box in the house to facilitate the electricity works later on. Activity 2: Water Supply Duration: 14 days Materials: PVC pipes (different sizes), Water flow meter Equipment: Spanner, Plyers, Pipe cutter Skilled Workers: Plumbers (2) Technical Information: Incoming water supply are brought into the house and connected to the water flow meter to facilitate the plumbing works later on. Activity 3: Ground Floor Electrical Plumbing (First - Fix) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, socket box Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electrician Plumbers (2) Technical Information: The brick wall is hacked to hide the wiring pipe which runs perpendicularly from the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done.
  • 40. WEEK 50 Activity 1: Ground Floor Electrical Plumbing (First - Fix) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, socket box Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electrician Plumbers (2) Technical Information: The brick wall is hacked to hide the wiring pipe which runs perpendicularly from the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done. Activity 2: First Floor Electrical Plumbing (First - Fix) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, socket box Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electrician Plumbers (2) Technical Information: Brick wall is hacked to hide the wiring pipe which runs perpendicularly from the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done. Activity 3: Second Floor Electrical Plumbing (First - Fix) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, Socket box, Junction box Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electrician Plumbers (2) Technical Information: Brick wall is hacked to hide the wiring pipe which runs perpendicularly from the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done. Activity 4: Plumbing – Kitchens and Toilets Duration: 14 days Materials: PVC pipes (different sizes), Pipe joints, Equipment: Spanner, Plyers, Pipe cutter Skilled Workers: Plumbers (2)
  • 41. WEEK 51 Activity 1: First Floor Electrical Plumbing (First - Fix) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, socket box Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electrician Plumbers (2) Technical Information: Brick wall is hacked to hide the wiring pipe which runs perpendicularly from the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done. Activity 2: Second Floor Electrical Plumbing (First - Fix) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, Socket box, Junction box Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electrician Plumbers (2) Technical Information:Brick wall is hacked to hide the wiring pipe which runs perpendicularly from the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done. Activity 3: Plumbing – Kitchens and Toilets Duration: 14 days Materials: PVC pipes (different sizes), Pipe joints, Equipment: Spanner, Plyers, Pipe cutter Skilled Workers: Plumbers (2) WEEK 52
  • 42. Activity 1: Electrical & Sanitary fittings Durations: 14 days Materials: Wall sockets, Wall plugs and bathroom porcelain appliances Equipment: Bolts and Nuts, Screwdriver and related toolkit. Skilled worker: General worker (4) WEEK 53 Activity 1: Grass turfing – External work Duration: 7 days Materials: lawn turf rolls ( depends on the size of garden), bricks Equipment: wheel barrow, gardening tool kits, water pipes Skilled Workers: lawn turf layers(2), general workers (2) Technical information: Soil preparation is done before laying the rolls of grass turf on the soil surfaces. Previously excavated soil can be reused as the base of the courtyard. Loose stones and building rubble will prevent the turves roots from making contact with the soil and could make the turf die in patches. The top soil should then be thoroughly rotivated down to about the first 6 inches to aerate it properly. It is then raked level and gently treaded down. - END OF REPORT -