THERMAL POWER PLANT
OPERATIONS
Simulator Part 8- Day 5
MANOHAR TATWAWADI
Director, tops
A2-806, PALLADION, BALEWADI, PUNE 411045
Mob: 9372167165, Email:-mtatwawadi@gmail.com
01-Nov-19 total output power solutions 1
COVERAGE
• Checking the Drip Diversion
• Cold, Warm and Hot start of the Unit
• Temperature matching with respect
to Turbine for raising of steam
temperature
• Checklist and operations for Hot
Start.
HP-LP HEATERS DRIP DIVERSION
Observe the Drip Diversion on MIMICS “LP DRAIN & HP DRAIN
SYSTEM”
Withdraw any Mill and observe the Drip Diversion with load
reduction
For Loads < 165 MW
HD30, HD21 – Open and HD29, HD31 – Close
(HPH6 to Deairator and HPH5 to LPH4)
Extraction Position
ES6 Open
For Loads > 165 MW
HD30, HD21 – Close and HD29, HD31 – Open
(HPH6 to HPH5 to Deairator)
Extraction Position
ES7 Open
For Loads < 100 MW
HD30, HD21 – Open and HD29, HD31 - Close
Extraction Position
ES6 Open/PRDS
COLD START UP OF 210 MW UNIT
• All lines and metal temperatures of boiler and turbine are
at atmospheric temperatures.
• All unit auxiliaries checked and tested for proper running.
• All commissioning trials are over.
• All work permits are cleared with men and material.
• All safety measures are implemented.
• The increase in boiler/steam/turbine temperatures are as
per the startup chart given by the manufacturer.
• Clean air flow measurement for all coal mills has been
carried out and as per the manufacturer.
• Procedure for cold startup already discussed in Parts 1 to 7
Recommended Cold Startup Curve for 210MW
Warm & Hot Rolling of Turbine
• Decide the type of Start depending on the HPT Casing Metal
Temp.
• Above 3500C Hot Rolling
• Between 150 to 3500C Warm Rolling
• Below 1500C Cold Rolling
• Cold Rolling has been already done in parts 1 to 7
• Procedure for Warm rolling is the same as Cold rolling.
• Rolling is done through HP Cylinder as is done in Cold Rolling
• In warm rolling steam temperature required is more in
comparison to cold rolling and hence more No of Oil Guns will
have to be taken in service as per the requirement.
• The Main Steam temp required will be calculated from the
matching Chart Provided.
TEMPERATURE MATCHING CHART
Case:- If the HPT Metal
Temp is 380 Deg C shown
as dotted line on X Axis
then
1. The exact matching
Main Steam temp
would be 4700C and
Pressure would be
70Kg/sqcm.
2. The +ve mismatch
temp would be 5150C
at 70 Kg/sqcm
3. The -ve mismatch
Temp would be
minimum 4250C at a
pressure of 70
Kg/sqcm.
HOT ROLLING OF TURBINE
• If the machine trips on full load and the fault is located
and cleared immediately, the machine can be rolled
again.
• The Main Steam Temperatures can be increased by using
HPLP Bypass and HOT ROLLING can be done.
• For this type of start up HP Casing Metal Temperature
should be more than 350 Deg C.
• If the fault is located and cleared after some period and
still if the HPT Casing Metal Temperature is more than
350 Deg C, then also it’s a condition of HOT ROLLING.
• Generally in a short period after machine trips (maybe a
period of 12 to 16 Hrs) HOT ROLLING condition prevails.
HOT ROLLING STARTUP CURVE
CHECKLIST & OPERATION
• Note down TA Set Tripping Time/Date/Load at the time of
Tripping
• Confirm Generator all 3 Phases currents have come to
ZERO.
• Check the tripping of field breaker, trip it if not tripped.
• Start SOP Immediately and check observe Lub. oil and relay
oil pressure.
• Confirm ESV / IV Closed and machine speed starts reducing.
• Confirm MS1, MS2 closed on Interlock.
• Confirm LP / HP Heaters Extraction Valves closed and
Deairator Heating Change over to PRDS
• Confirm Tripping of Boiler with all fuel tripped (All Oil
Elevations, all coal Mills and coal feeders tripped)
CHECKLIST & OPERATION…….
• Slowly reduce the total air flow to minimum i. e. 300 TPH.
• Control the drum level by operating Feed water Valve / BFP
scoop positions.
• Check the opening of condenser spray MC39, MC57 on
interlock
• Confirm all SH Spray Valves closed on AUTO.
• Bring Burner Tilt Position to Horizontal. 50%
• Bypass T.T.B.T. switch (Turbine Trip to Boiler Trip on manual)
• Check the Boiler Drum Level NORMAL
• Check PURGE READY indication and give command for Purging
• After Purge Complete and the boiler is reset, open the trip
valves for Ignitor, Warm up Oil and Heavy Oil.
CHECKLIST & OPERATION…….
• Select Heavy Oil for AB Elevation
• Take Oil Support in AB, CD and EF Elevations one by
one
• Check and maintain the drum level.
• Check that the IGV of PA fans on Manual and close
them.
• Start PA Fans one by one and put the IG vanes on AUTO
to maintain Header Pressure 800mm.
• Check Vacuum, Condenser Level.
Break Vacuum if
• The machine has tripped on “Low Lub Oil Pressure”
• Axial Shift very High
• Any other abnormality such as sound from Turbine
CHECKLIST & OPERATION…….
• Open Gland Steam Valves of HPT/IPT if they are closed and
watch vacuum.
• Watch Differential Pressure between Hydrogen and Seal Oil
during coasting down of the machine.
• Maintain Lub Oil Temp not less than 40 Deg C.
• Note down the Axial Shift and Expansions of HPT IPT and LPT.
• When the speed of turbine comes to zero put Machine on
Barring Gear.
• Note down the HPT and IPT Casing Metal temperatures.
• Open HP LP Bypass Drain, Open HP/LP Heaters Drains.
• Ensure CR5, CR6 valves are open before charging of HP/LP
Bypass.
CHECKLIST & OPERATION…….
• Open LP Bypass min 4%, Open HP Bypass also 8%.
• Watch condenser level and maintain.
• Watch Main Steam Pressure and maintain it by
operating HP Bypass Valves.
• Maintain the Pressure in Reheater to 6-7kg/sqcm.
• Open HPT and IPT casing drains by 5%.
• Open Main steam Valves MS1 and MS2.
• Start opening the Speeder gear. At 6.820 mm IV and
ESV will open.
• Open the speeder gear further to 7.120, Control valves
of IPT will start opening.
CHECKLIST & OPERATION…….
• Observe the speed of the turbine increasing, watch
expansions, if the expansions are going towards –ve side
give rotor heating.
• When the turbine speed reaches more than 2800 RPM stop
SOP.
• Raise the speed to 3000RPM without stopping at the
critical speeds by operating the HPLP Bypass.
• Make the field flashing supply ON.
• Make the field breaker ON.
• Changeover AVR from AUTO to MANUAL. Raise the
Generator Voltage to 15.75 KV.
• Make the synchroscope ON.
CHECKLIST & OPERATION…….
• Synchronise the generator with the grid by closing the
Generator breaker from the control desk when
synchroscope is moving from 11 to 12 position slowly.
• Check the Voltage error for ZERO and put AVR on AUTO.
• As soon as the unit is synchronized, open the CVSM further
and close LP Bypass fully, HP Bypass may be open.
• Observe the increase in Generator load as all the steam is
now flowing through the IP Turbine.
• Check the HPT first stage pressure and check that HPT
Control valves are open.
• Ensuring that the HPT Control Valves are OPEN, close the
HP Bypass valves.
CHECKLIST & OPERATION…….
• Stop Rotor heating if it is in service.
• Close all drains
• Maintain Boiler Drum Level from control desk 4
• Similarly maintain the M.S. Pressure by increasing the fuel
input to the boiler. (Increase HO pressure and/or take coal
mill in service.)
• Normalise TT/BT switch. (Turbine Trip to Boiler Trip switch)
• Changeover Station Supply to UAT Supply when load is
more than 50 MW.
• Take LP/HP Heaters in service and increase the load to 210
MW as per the Ramp rate as per Chart
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine

Contenu connexe

Tendances

Tendances (20)

Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbines
 
Unit lightup synchronisation &amp; shutdown
Unit lightup synchronisation &amp; shutdownUnit lightup synchronisation &amp; shutdown
Unit lightup synchronisation &amp; shutdown
 
Boiler light up & loading
Boiler light up & loadingBoiler light up & loading
Boiler light up & loading
 
turbine governing oil system
turbine governing oil systemturbine governing oil system
turbine governing oil system
 
Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5Power Plant Simulator Day 3 Part 5
Power Plant Simulator Day 3 Part 5
 
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
 
Boiler safety protection
Boiler  safety protectionBoiler  safety protection
Boiler safety protection
 
Turbine governing system an overview
Turbine governing system an overviewTurbine governing system an overview
Turbine governing system an overview
 
HP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam TurbineHP LP Bypass system of 110 MW Steam Turbine
HP LP Bypass system of 110 MW Steam Turbine
 
Handling of turbine side emergencies
Handling of turbine side emergenciesHandling of turbine side emergencies
Handling of turbine side emergencies
 
210 mw LMZ Turbine rolling and its GOVERNING
210 mw LMZ Turbine rolling and its GOVERNING 210 mw LMZ Turbine rolling and its GOVERNING
210 mw LMZ Turbine rolling and its GOVERNING
 
Electrohydraulic governing system
Electrohydraulic governing systemElectrohydraulic governing system
Electrohydraulic governing system
 
Turbine Stress Control Logic, Calculation & Working
Turbine Stress Control Logic, Calculation & WorkingTurbine Stress Control Logic, Calculation & Working
Turbine Stress Control Logic, Calculation & Working
 
POWER PLANT SIMULATOR 210 MW
POWER PLANT SIMULATOR 210 MW POWER PLANT SIMULATOR 210 MW
POWER PLANT SIMULATOR 210 MW
 
Unit protection scheme
Unit protection schemeUnit protection scheme
Unit protection scheme
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedure
 
Turbine safety protection
Turbine safety protectionTurbine safety protection
Turbine safety protection
 
Thermal Power Plant - Emergency situations
Thermal Power Plant   -   Emergency situations Thermal Power Plant   -   Emergency situations
Thermal Power Plant - Emergency situations
 
Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)Furnace Guard Supervisory System (FSSS)
Furnace Guard Supervisory System (FSSS)
 
Boiler -Emergency Handling
 Boiler -Emergency Handling Boiler -Emergency Handling
Boiler -Emergency Handling
 

Similaire à Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine

pulverizedcoalfiredboiler.pptx
pulverizedcoalfiredboiler.pptxpulverizedcoalfiredboiler.pptx
pulverizedcoalfiredboiler.pptx
Narhari1
 

Similaire à Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine (20)

POWER PLANT SIMULATOR 210 MW LMW TURBINE
POWER PLANT SIMULATOR 210 MW LMW TURBINEPOWER PLANT SIMULATOR 210 MW LMW TURBINE
POWER PLANT SIMULATOR 210 MW LMW TURBINE
 
Turbine Start Up.pptx
Turbine Start Up.pptxTurbine Start Up.pptx
Turbine Start Up.pptx
 
Turbine operation.pptx
Turbine operation.pptxTurbine operation.pptx
Turbine operation.pptx
 
Power Plant Simulator, Unloading and shutting the Turbogenerator
Power Plant Simulator, Unloading and shutting the TurbogeneratorPower Plant Simulator, Unloading and shutting the Turbogenerator
Power Plant Simulator, Unloading and shutting the Turbogenerator
 
THERMAL POWER PLANT OPERATIONS
THERMAL POWER PLANT OPERATIONSTHERMAL POWER PLANT OPERATIONS
THERMAL POWER PLANT OPERATIONS
 
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdfEC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
EC8DE5D2-3B41-4599-8A5D-AB833F9397F5.pdf
 
Cfbc boiler startup and shutdown
Cfbc boiler startup and shutdownCfbc boiler startup and shutdown
Cfbc boiler startup and shutdown
 
PUMPS.ppt
PUMPS.pptPUMPS.ppt
PUMPS.ppt
 
Thermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations TrainingThermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations Training
 
Hplpbp
HplpbpHplpbp
Hplpbp
 
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
Starting & Recommended Interlocks for AH,ID,FD,PA Fans & BD Valves for 270 MW...
 
Hrsg startup proceudre
Hrsg startup proceudreHrsg startup proceudre
Hrsg startup proceudre
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdf
 
Compressor operation.pdf
Compressor operation.pdfCompressor operation.pdf
Compressor operation.pdf
 
pulverizedcoalfiredboiler.pptx
pulverizedcoalfiredboiler.pptxpulverizedcoalfiredboiler.pptx
pulverizedcoalfiredboiler.pptx
 
Energy Centre
Energy CentreEnergy Centre
Energy Centre
 
new prentation.pptx
new prentation.pptxnew prentation.pptx
new prentation.pptx
 
TG_AUX_TRG_PowerPoint Presentation 3.ppt
TG_AUX_TRG_PowerPoint Presentation 3.pptTG_AUX_TRG_PowerPoint Presentation 3.ppt
TG_AUX_TRG_PowerPoint Presentation 3.ppt
 
Final Turbine rolling ppt Akshay.pptx
Final Turbine rolling ppt Akshay.pptxFinal Turbine rolling ppt Akshay.pptx
Final Turbine rolling ppt Akshay.pptx
 
Rankine
RankineRankine
Rankine
 

Plus de Manohar Tatwawadi

Plus de Manohar Tatwawadi (20)

Power Plant Operations.pdf
Power Plant Operations.pdfPower Plant Operations.pdf
Power Plant Operations.pdf
 
Frequently Asked Questions on TURBINE Part 3
Frequently Asked Questions on TURBINE Part 3Frequently Asked Questions on TURBINE Part 3
Frequently Asked Questions on TURBINE Part 3
 
Green building concepts and good building practices
Green building concepts and good building practicesGreen building concepts and good building practices
Green building concepts and good building practices
 
Auxiliary Consumption and Saving due to Increase in Boiler Efficiency
Auxiliary Consumption and Saving due to Increase in Boiler EfficiencyAuxiliary Consumption and Saving due to Increase in Boiler Efficiency
Auxiliary Consumption and Saving due to Increase in Boiler Efficiency
 
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIES
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIESCOMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIES
COMPRESSED AIR SYSTEM . ENERGY CONSERVATION OPPORTUNITIES
 
FAQ on Turbines Part 2
FAQ on Turbines Part 2FAQ on Turbines Part 2
FAQ on Turbines Part 2
 
Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1
 
Cooling towers in thermal power plants
Cooling towers in thermal power plantsCooling towers in thermal power plants
Cooling towers in thermal power plants
 
Electrical safety in power stations
Electrical safety in power stationsElectrical safety in power stations
Electrical safety in power stations
 
Cost accounting, cost control and cost reduction in TPS
Cost accounting, cost control and cost reduction in TPSCost accounting, cost control and cost reduction in TPS
Cost accounting, cost control and cost reduction in TPS
 
Environmental and pollution control in Thermal Power Stations
Environmental and pollution control in Thermal Power StationsEnvironmental and pollution control in Thermal Power Stations
Environmental and pollution control in Thermal Power Stations
 
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...Energy Audit & Energy  Conservation  Opportunities in  Electrical Equipments ...
Energy Audit & Energy Conservation Opportunities in Electrical Equipments ...
 
Fuels and Combustion Equations
Fuels and Combustion EquationsFuels and Combustion Equations
Fuels and Combustion Equations
 
Basics of thermal power stations
Basics of thermal power stationsBasics of thermal power stations
Basics of thermal power stations
 
Effect of Coal Quality and Performance of Coal pulverisers / Mills
Effect of Coal Quality and Performance of Coal pulverisers / MillsEffect of Coal Quality and Performance of Coal pulverisers / Mills
Effect of Coal Quality and Performance of Coal pulverisers / Mills
 
Thermal power plant efficiency
Thermal power plant efficiencyThermal power plant efficiency
Thermal power plant efficiency
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rate
 
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANTENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
ENERGY AUDIT METHODOLOGY FOR TURBINE CYCLE IN A POWER PLANT
 
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATETHERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
 
Biomass Power Plants
Biomass Power PlantsBiomass Power Plants
Biomass Power Plants
 

Dernier

Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
dharasingh5698
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
amitlee9823
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 

Dernier (20)

Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 

Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine

  • 1. THERMAL POWER PLANT OPERATIONS Simulator Part 8- Day 5 MANOHAR TATWAWADI Director, tops A2-806, PALLADION, BALEWADI, PUNE 411045 Mob: 9372167165, Email:-mtatwawadi@gmail.com 01-Nov-19 total output power solutions 1
  • 2. COVERAGE • Checking the Drip Diversion • Cold, Warm and Hot start of the Unit • Temperature matching with respect to Turbine for raising of steam temperature • Checklist and operations for Hot Start.
  • 3. HP-LP HEATERS DRIP DIVERSION Observe the Drip Diversion on MIMICS “LP DRAIN & HP DRAIN SYSTEM” Withdraw any Mill and observe the Drip Diversion with load reduction For Loads < 165 MW HD30, HD21 – Open and HD29, HD31 – Close (HPH6 to Deairator and HPH5 to LPH4) Extraction Position ES6 Open For Loads > 165 MW HD30, HD21 – Close and HD29, HD31 – Open (HPH6 to HPH5 to Deairator) Extraction Position ES7 Open For Loads < 100 MW HD30, HD21 – Open and HD29, HD31 - Close Extraction Position ES6 Open/PRDS
  • 4. COLD START UP OF 210 MW UNIT • All lines and metal temperatures of boiler and turbine are at atmospheric temperatures. • All unit auxiliaries checked and tested for proper running. • All commissioning trials are over. • All work permits are cleared with men and material. • All safety measures are implemented. • The increase in boiler/steam/turbine temperatures are as per the startup chart given by the manufacturer. • Clean air flow measurement for all coal mills has been carried out and as per the manufacturer. • Procedure for cold startup already discussed in Parts 1 to 7
  • 5. Recommended Cold Startup Curve for 210MW
  • 6. Warm & Hot Rolling of Turbine • Decide the type of Start depending on the HPT Casing Metal Temp. • Above 3500C Hot Rolling • Between 150 to 3500C Warm Rolling • Below 1500C Cold Rolling • Cold Rolling has been already done in parts 1 to 7 • Procedure for Warm rolling is the same as Cold rolling. • Rolling is done through HP Cylinder as is done in Cold Rolling • In warm rolling steam temperature required is more in comparison to cold rolling and hence more No of Oil Guns will have to be taken in service as per the requirement. • The Main Steam temp required will be calculated from the matching Chart Provided.
  • 7. TEMPERATURE MATCHING CHART Case:- If the HPT Metal Temp is 380 Deg C shown as dotted line on X Axis then 1. The exact matching Main Steam temp would be 4700C and Pressure would be 70Kg/sqcm. 2. The +ve mismatch temp would be 5150C at 70 Kg/sqcm 3. The -ve mismatch Temp would be minimum 4250C at a pressure of 70 Kg/sqcm.
  • 8. HOT ROLLING OF TURBINE • If the machine trips on full load and the fault is located and cleared immediately, the machine can be rolled again. • The Main Steam Temperatures can be increased by using HPLP Bypass and HOT ROLLING can be done. • For this type of start up HP Casing Metal Temperature should be more than 350 Deg C. • If the fault is located and cleared after some period and still if the HPT Casing Metal Temperature is more than 350 Deg C, then also it’s a condition of HOT ROLLING. • Generally in a short period after machine trips (maybe a period of 12 to 16 Hrs) HOT ROLLING condition prevails.
  • 10. CHECKLIST & OPERATION • Note down TA Set Tripping Time/Date/Load at the time of Tripping • Confirm Generator all 3 Phases currents have come to ZERO. • Check the tripping of field breaker, trip it if not tripped. • Start SOP Immediately and check observe Lub. oil and relay oil pressure. • Confirm ESV / IV Closed and machine speed starts reducing. • Confirm MS1, MS2 closed on Interlock. • Confirm LP / HP Heaters Extraction Valves closed and Deairator Heating Change over to PRDS • Confirm Tripping of Boiler with all fuel tripped (All Oil Elevations, all coal Mills and coal feeders tripped)
  • 11. CHECKLIST & OPERATION……. • Slowly reduce the total air flow to minimum i. e. 300 TPH. • Control the drum level by operating Feed water Valve / BFP scoop positions. • Check the opening of condenser spray MC39, MC57 on interlock • Confirm all SH Spray Valves closed on AUTO. • Bring Burner Tilt Position to Horizontal. 50% • Bypass T.T.B.T. switch (Turbine Trip to Boiler Trip on manual) • Check the Boiler Drum Level NORMAL • Check PURGE READY indication and give command for Purging • After Purge Complete and the boiler is reset, open the trip valves for Ignitor, Warm up Oil and Heavy Oil.
  • 12. CHECKLIST & OPERATION……. • Select Heavy Oil for AB Elevation • Take Oil Support in AB, CD and EF Elevations one by one • Check and maintain the drum level. • Check that the IGV of PA fans on Manual and close them. • Start PA Fans one by one and put the IG vanes on AUTO to maintain Header Pressure 800mm. • Check Vacuum, Condenser Level. Break Vacuum if • The machine has tripped on “Low Lub Oil Pressure” • Axial Shift very High • Any other abnormality such as sound from Turbine
  • 13. CHECKLIST & OPERATION……. • Open Gland Steam Valves of HPT/IPT if they are closed and watch vacuum. • Watch Differential Pressure between Hydrogen and Seal Oil during coasting down of the machine. • Maintain Lub Oil Temp not less than 40 Deg C. • Note down the Axial Shift and Expansions of HPT IPT and LPT. • When the speed of turbine comes to zero put Machine on Barring Gear. • Note down the HPT and IPT Casing Metal temperatures. • Open HP LP Bypass Drain, Open HP/LP Heaters Drains. • Ensure CR5, CR6 valves are open before charging of HP/LP Bypass.
  • 14. CHECKLIST & OPERATION……. • Open LP Bypass min 4%, Open HP Bypass also 8%. • Watch condenser level and maintain. • Watch Main Steam Pressure and maintain it by operating HP Bypass Valves. • Maintain the Pressure in Reheater to 6-7kg/sqcm. • Open HPT and IPT casing drains by 5%. • Open Main steam Valves MS1 and MS2. • Start opening the Speeder gear. At 6.820 mm IV and ESV will open. • Open the speeder gear further to 7.120, Control valves of IPT will start opening.
  • 15. CHECKLIST & OPERATION……. • Observe the speed of the turbine increasing, watch expansions, if the expansions are going towards –ve side give rotor heating. • When the turbine speed reaches more than 2800 RPM stop SOP. • Raise the speed to 3000RPM without stopping at the critical speeds by operating the HPLP Bypass. • Make the field flashing supply ON. • Make the field breaker ON. • Changeover AVR from AUTO to MANUAL. Raise the Generator Voltage to 15.75 KV. • Make the synchroscope ON.
  • 16. CHECKLIST & OPERATION……. • Synchronise the generator with the grid by closing the Generator breaker from the control desk when synchroscope is moving from 11 to 12 position slowly. • Check the Voltage error for ZERO and put AVR on AUTO. • As soon as the unit is synchronized, open the CVSM further and close LP Bypass fully, HP Bypass may be open. • Observe the increase in Generator load as all the steam is now flowing through the IP Turbine. • Check the HPT first stage pressure and check that HPT Control valves are open. • Ensuring that the HPT Control Valves are OPEN, close the HP Bypass valves.
  • 17. CHECKLIST & OPERATION……. • Stop Rotor heating if it is in service. • Close all drains • Maintain Boiler Drum Level from control desk 4 • Similarly maintain the M.S. Pressure by increasing the fuel input to the boiler. (Increase HO pressure and/or take coal mill in service.) • Normalise TT/BT switch. (Turbine Trip to Boiler Trip switch) • Changeover Station Supply to UAT Supply when load is more than 50 MW. • Take LP/HP Heaters in service and increase the load to 210 MW as per the Ramp rate as per Chart