SlideShare une entreprise Scribd logo
1  sur  73
Télécharger pour lire hors ligne
Smooth Rock Falls Mining
Prefeasibility Study
Battenberg Consultancy
1
Executive Summary
2
Life of mine 7Years 3 Months
Mined tonnes ore 4089281
Average grade 4.37
Ounces produced 574539
Net PresentValue (DCR 5%) 178
Net PresentValue inc.Tax (DCR
5%)
117
Scope
 Located in North-Eastern Ontario
 Low Sulphide Gold Deposit
 Well established mining area
 Commissioned by CSM Resources
to produce a PEA
 Designed around existing
underground infrastructure3
Property Description and Location
 1017.5km2 area
 49.125N, 81.75W
 Extremely close to the
Trans-Canada
Highway/Ontario 11
 Access to the site is
currently a small dirt road
 Cochrane Airport is 87.5km
to the east
 Timmins city is 128km to
the south
 Moderate-low relief
4
Existing Infrastructure and Power
 Two existing shafts
 Development Level at 365m
 Fully refurbished haulage
shaft
 Haulage capacity of 1600 t/d
 Over 60% of Ontario’s energy
is generated from Nuclear
Power
 115kV power line is situated
close to the site
 Diesel generators will
continue to be utilised
5
History
 CSM Resources are the second owners of the claim, and thus will have to pay a 2.5%
royalty
 Mining in theTimmins district has been a prevalent industry since the early C20th
 60.8 million oz’s of gold have been produced in the Timmins district to date
 32 Gold producing mines in the Timmins District
6
Geology
Regional Geology
The site is located on
part of the Canadian
Shield
 Superior Province
 Southern Province
 Grenville Province
7
Property Geology
Glacial till is the main surficial deposit, with bedrock also compromising a
significant amount. The three main types of glacial till are:
 Lower Till
 Barlow-Ojibway Formation
 Cochrane Formation
8
Deposit Geology
 Dominated by Greenschists
 Quartz and Sericite are common wall rock minerals
 Deposits generally contain around 2/3% sulphide
minerals
 Acid Mine Drainage needs to be considered
9
Mineral Resource Estimates
Category Tonnes Capped Grade (g/t Au) Capped Oz (Au)
Measured 1,499,000 3.89 187,300
Indicated 2,661,000 5.56 475,500
Measured & Indicated 4,160,000 4.96 662,800
Inferred 239,000 2.61 20,100
Based on historic diamond drilling , the following table represents the
Mineral Resource estimate.
10
Geotechnical Considerations
11
12
 What we knew
Initial data consisted of rock types, rock strengths and joint information
 What we found
Hanging wall weakest rock type
Stress environment of the deposit
Generally this case is assumed to be a dry excavation therefore groundwater
effects are negligible in
 What it means
Stopes designed to be stable
Limited support needed on critical surfaces
Rock Mass and Stress Situation
13
 In-situ stress profile
established.
 Induced stress due to the
openings established using
Examine2D.
 Stress distributions around the
excavation and state at the
center on opening.
Induced stress contours
of excavation orientation
looking E-W
Induced stress
contours of excavation
orientation looking N-S
Joint Sets
14
 Core log data.
 Stereographic analysis
displayed the joint
situation at smooth rock
falls deposit.
 Major discontinuity
orientations and joint
sets determined.
Stereographic analysis for smooth rock underground
mapping data
Stope Design Approach
15
Four Components:
 Initial stope dimensions assumed
 Stability number equation factors derived
N’=Q’×A×B×C
 N’ used on stability graph to obtain Hydraulic radius of proposed stope
 Hydraulic radius and stability numbers modified in line with stope stability
requirements
16
Stability graph highlighting the recommended HR to obtain suitable stope dimensions (Brady, 1993)
Ground Support
17
 Very conservative estimates of
support requirements due to
uncertainties and time dependent
behavior of rock mas.
 Preliminary analysis showed
support requirements are mostly
unsupported with spot bolting
required in a few areas
 Intersections require systematic
bolting and some unreinforced
shortcrete in critical intersections
 Underground crusher chamber
requires fibre reinforced concrete
and bolting
Estimated support categories based on the tunneling
index Q (Hoek 1995)
Crown pillar Analysis
18
t = 19.6m  25m
Critical Span
3.3 × 𝑄0.43 × 𝑠𝑖𝑛ℎ0.0016 𝑄
9.015
Scaled Span
𝑆(
𝛾
𝑡 1 + 𝑆 𝑅 1 − 0.4 cos 𝜃
)0.5
Footwall drive stress analysis
19
Recommendations
20
 Further geotechnical data collection is required to ensure that
the rock types and geotechnical domains are tackled.
 Stope dimensions of 10 m x 20 m high with respect to
changing strike lengths as mining depth in the ore body
increases are suggested.
 Stope dimensions must not exceed the maximum size until
detailed geotechnical data is available to support the rock mass
quality and economic analysis.
 A ground control program should be implemented at the mine
in the early stages of development in order to support and
address mine design and safety issues.
Mine Design
21
Comparison of mining methods
22
Cost type Cost per
unit
Obtained from Affected quantities Cost difference between
Transverse and in ore
development ($)
Development 1410 $/m Cost of a 6.1m x 4.6m
excavation in 2011 adjusted for a
4m x 4m excavation and 5%
inflation.
190m footwall drive
10 x 10m crosscuts
+536000
Stope
production
including backfill
39.40 $/t Eagle Mine stope and backfill
costs adjusted for inflation.
Sill pillar tonnage +834000
Processing cost 29.40 $/t Interpolating between given
values.
Sill pillar tonnage +622000
Development in ore
• 3.5m thick sill pillar required
• Total gold value of $5.5m
locked up
• Reduced need for backfill
Transverse bench
and fill
• Skin to skin mining
• Stopes must be
completely
backfilled
Longitudinal
Stoping
• Ore body too
thick
$5490000 − $536000 − $834000 − $622000 = $3.5 𝑀𝑖𝑙𝑙𝑖𝑜𝑛
Mineral Reserve Estimates
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
1 282,773 940,742 724,088 928,732 974,383 1,039,849 970,272 910,601 579,015 403,063 220,024
2 42,219 1,292,944 1,942,219 2,003,058 1,843,961 1,794,040 1,801,523 1,627,938 1,197,906 554,096 21,611
3 317,510 1,226,909 1,248,329 1,279,423 1,041,831 794,418 586,132 544,258 230,794 149,808
4 320,946 1,638,025 1,760,762 1,818,870 1,958,702 1,925,224 1,740,737 1,612,302 876,247 307,548
5 329,459 1,326,475 2,860,425 3,046,113 3,074,388 2,612,758 2,329,543 1,844,880 1,310,670
6 126,923 739,810 584,725 427,932 105,169 77,930 466,302 640,943 113,316 382,729 1,040,046 1,229,441 906,531 796,073 894,972 496,504
7 88,187 339,820 458,016 600,452 517,174 479,744 606,624 767,152 654,993 386,748 592,059 153,564
8 379,076 1,015,658 1,486,553 1,376,784 1,316,619 1,768,692 2,179,170 1,410,383 1,659,261 1,642,672 1,228,422 1,366,560 612,038 28,453 706,937 1,081,916 398,592 16,818
9 748,991 1,644,262 2,388,486 2,626,576 1,965,456 1,948,405 1,472,442 714,692 1,148,337 1,694,511 959,588 1,000,999 918,835 129,665
10 982,410 2,284,504 2,650,553 3,161,174 3,115,796 3,936,575 2,336,473 1,191,856 919,604 1,097,341 1,239,612 3,092,503 1,905,190 489,283 187,539 112,704 358,831 557,007 523,101 102,633
11 1,625,526 2,461,996 2,984,710 2,183,937 2,578,829 3,870,008 2,410,298 1,449,307 1,311,383 1,696,215 1,888,614 2,768,192 1,622,327 961,286 472,521 654,444 977,846 1,397,393 350,991 44,198
12 109,474 546,926 1,288,857 1,657,073 1,727,298 1,622,981 2,251,593 2,814,457 2,981,764 2,324,196 2,069,610 1,672,101 1,468,196 2,348,827 4,236,356 3,788,554 3,686,252 1,888,480 117,967
13 292,882 602,050 674,002 411,724 121,762 858,481 3,182,288 3,648,045 3,800,538 3,285,720 2,996,216 2,627,685 2,389,098 5,635,369 5,342,662 4,640,915 3,801,491 2,966,958 1,176,470 331,991 365,199
14 372,351 473,185 697,061 482,270 374,953 2,968,279 4,635,951 4,735,040 3,814,222 1,796,683 1,398,340 968,372 637,951 2,689,531 3,612,316 3,086,434 2,697,794 2,152,637 450,443 145,176 72,163
15 378,297 1,112,085 1,916,620 4,372,256 4,140,148 2,216,233 4,815,657 5,470,674 4,604,316 1,642,527 962,796 763,883 221,875
16 1,803,499 4,283,245 4,518,315 1,852,240 488,735 973,555 720,373 258,382 95,224 666,885 1,605,958 2,796,534 2,886,579 433,284
17 428,299 305,668 84,230 1,249,770 7,052,300 10,891,552 7,513,716 4,574,594
18 378,294 465,937 501,893
19
20
21
22
23Level
Column
• Based on the measured and indicated resource
• A cut off grade of 3.0 g/t was calculated
• Preliminary stopes that were not profitable were cut
from the design
23
Mine Design
Level Access
Foot-wall Drive
Decline
Cross Cuts
Level Access
 Transverse Bench and Fill stoping design based on the geotechnical constraints
 Foot-wall drive hugs the ore body
 Ramp and decline developed off the existing level
 Stopes designed on their economic return
24
ORE
1 11 1 1
2
3
2 2
3
2
3
2
33
4 44 4 4
5 5
6 6 6
7
Back-Fill Sequence
Stoping Process
25
26
Mine Development
Initial development will be driving the ramp towards surface
27
28
Additional
Development
• Ore pass to crusher hall
• Fuel bay
• Machine workshop
29
Mine Production
 Total LOM tonnes are 4.09 million
 Production peaks in year 2 at 785439Tonnes
 Average LOM grade of 4.37 g/t
 Grade peaks in year 3 at 5.17 g/t0
100000
200000
300000
400000
500000
600000
700000
800000
900000
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8
Tonnes
Year
0
20000
40000
60000
80000
100000
120000
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8
Ounces
Year
30
Ventilation
• 200m3/s of air is required by the proposed design and equipment quantities
• Booster fans will be required in certain districts, with a power circa 20kW
• Auxiliary fans will provide the headings with clean fresh air
• Air way will act as a second means of egress
31
32
Mine Heating
Ventilation on Demand
A mine heating system will be utilised to provide the mine with 22 MBTU to the mine. It
will be applied as followed;
 2 months per year at 100% of heating capacity.
 2 months per year at 50% of heating capacity.
 2 months per year at 25% of heating capacity.
 VOD will be used as different sections of the mine don’t need to be accessed.
 When development of the upper section of the ore body has been fully mined, then it can
be fully closed off.
 Can save an approximated 10-15% on the operational ventilation costs.
33
Backfill
Paste Fill Unconsolidated rock fill
34
 Primary stopes and level 9
 65 microns particle size
 85% tails
 High strength - 5.5% binder
 Regular strength – 4%
binder
 Total volume – 684000m^3
 Estimated cost per tonne
$10
 Secondary stopes
 Reduced need to hoist
waste
 Trucked and dumped into
place
 Total volume –
600000m^3
 Estimated cost per tonne
0.05$/t
35
Mining Equipment
36
Unit No. Specification
Production Drill 1 Sand. DL321
LHD 3 Sand. LH307
Horizontal
Development Jumbo 2 SAND DD321
Raise Borer 0
Primary Hauler - Rear
Dump 5 Sand. TH320
Explosive Truck 1
Service Vehicles 4 Landcrusier
Rock Bolter 1 Sand. DS311
Scissor Lift 2
Personnel Carrier 1 Normet Utimec
Grader 1 CAT 12M
Mineral Processing and Disposal
37
Mineral Processing
38
Regri
nd
Cyanide
Destruction
Tailings
39
 The total mill throughput: 8.8 million tonnes
 Tailings ~55% solids by volume.
 0.5 million m^3 consumed by backfill
8.8 𝑚𝑖𝑙𝑙𝑖𝑜𝑛
2.7
×
100
55
− 0.5 = 5.5 𝑚𝑖𝑙𝑙𝑖𝑜𝑛 𝑚3
Tailings dam design
40
Design stage Year Height (m) Cross sectional area (m^2)
Initial 0 20 700
Lift 1 3 26 1170
Lift 2 5 32 1770
Perimeter – 300 x 650m Slope angle – 30 degrees
Tailings location
41
Climate change
42
How the Mine is Impacted by Climate
Change
43
Mitigation
 Energy conservation
 Improved fuel efficiency &
Green transport
 Reducing CO2 emissions
Adaptation
 Flood controls
 Altering design to adapt to
changing climate trends
 Increasing FoS of design to
reduce risk
Current Climate of Project Site
44
 Continental Climate
 Relatively dry Climate
 Very hot Summer
 Very coldWinters
45
46
Model
A2 B2
Summer Months 2°C 2°C
Winter Months 3.5°C 3°C
47
48
Model
A2 B2
Summer Months 10% Decrease 5% Decrease
Winter Months 30% Decrease 20% Decrease
Key Areas of Concern
49
 Temperature Increase
 Increased evaporation
 Demand for heating/cooling of ventilation
 Dust pollution
 Rainfall
 Flood Risk
 Precipitation
 Water Supply
 Increase surface water
 Extreme Weather Events
 Flash floods
 Forest Fires
Effects of Climate Change on Mining the Timmins region of Ontario
Event Hazards and Risks Controls
1 Temperature change 1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
Reduced precipitation.
Increased evaporation.
Increased demand on ventilation.
Heating and cooling of ventilation.
Lower lake levels.
Water quality.
Dust.
Freezing of ground and water
1.1.1
1.1.2
1.2.3
1.3.1
1.3.2
1.4.1
1.4.2
1.5.1
1.5.2
1.6.1
1.6.2
1.7.1
1.8.1
Look at alternative sources of water supply.
Increase depth of boreholes.
Cover water storage facilities.
Install versatile fans that can increase demand.
Install booster fans in areas with low ventilation.
Heating has been installed in the mine ventilation
already so can be used when required.
Models indicate that only an increase in
temperature will be seen, therefore no cooling will
be required.
If boreholes cannot supply full amount of the
water and local lakes are used these need to be
assessed to determine the effect on local wildlife,
and the local community supply of water.
Pumping may be required from a greater
distance.
Not used as drinking water.
Water goes through gravel treatment before use
in the mill or sent underground.
Water is used to supress dust from becoming
airborne underground.
Water supply affected, pumping from greater
distance may be required.
2 Rainfall 2.1
2.1a
2.1b
2.1c
2.2
Damage of water supply, effecting:
Quality of water.
Amount of water.
Conflict with locals.
Flooding on surface.
2.1a.1
2.1a.2
2.1b.1
2.1c.1
2.1c.2
2.2.1
2.2.2
2.2.3
2.2.4
Not used as drinking water.
Water goes through gravel treatment before use
in the mill or sent underground.
Water stored in surface water bowsers.
Collecting water supply from boreholes, thus not
effecting local water supply.
Low local population.
Tailings dam has additional pumping capacity.
Size of tailings dam has been designed to always
have available additional capacity in case of
flooding.
Surface mine services will be insured.
Assumed open pit is designed so slopes cope
50
Environmental and Social
Assessment
51
EIS Requirements
52
An EIS is necessary in order to proceed with the operation. It
entails:
 Scope of the project and purpose
 An identification of the potential negative environmental
impacts of the project, with all components at all project
stages
 An identification of technical and economically feasible
mitigation measures to reduce or eliminate these impacts
 Government/Public Consultation
 Aboriginal Concerns
 Consideration of the physical, biological and human
environment
Stages of an EIS
53
 Permits
 Consultation with Public and First Nations communities
 Existing Environment and Baseline Studies
 Socio-economic and cultural resource considerations
 Impact Assessment on Existing Environment (Including
Mitigation Procedures)
 Alternatives
 Closure Plan
Impact Assessment Summary and
Mitigation
54
 The following areas in which the way the project will
affect the environment are as follows:
 Impact onWater supply and water management/water
quality
 Impact onTerrestrial and aquatic environment
 Impact on Air Quality and Acoustic environment
 Potential Acid Mine Drainage
 Transportation effects
 Greenhouse Gas Emissions
Existing Environment
55
 A requirement of beginning mine production is
Consultation, which must be held with a full array of
stakeholders, including public, project, and First Nations.
 Baseline studies of the following are to be undertaken:
-Atmospheric Environment,Aquatic Environment,Terrestrial
Environment,Wildlife, Species at Risk and Socioeconomic
status
Alternatives to Project Implementation
56
 Also considered were some ways the project could be
implemented
 The potential different modes of implementation
considered were Project Location, Mining method,
Processing plant location, tailings dam location/disposal,
access routes into the mine, electrical transmission
routes, and site closure
Mine Closure and Remediation Plan
57
 Following the Ontario provincial regulations of 240/00,
we have addressed the following concerns:
- Site Access Restriction
- Closure of Mine openings
- Continuation of physical, chemical and biological
monitoring programs
- Waste management, securing of petroleum products,
chemicals and waste
- Ensuring ongoing stability of rock piles, overburden piles
and tailings storage dam
- Rehabilitation of the site
Site Access and Openings Closure
58
 Upon completion of post-closure monitoring, access
roads will be deconstructed
 North and South shafts will be capped with either
concrete or steel caps
 Maintenance of Chainlink fence surrounding tailings dam
will continue until backfilled.
Open Pit and Underground Closure
59
 Backfill has been chosen as the method of rehabilitation
 Backfilling on the surface cannot commence until the
completion of underground mining and rehabilitation
 Underground, Backfilling is due to begin as soon as a stope
is fully excavated, so throughout the mine life backfilling will
be part of the mining process
 Any disturbed surface locations will be shaped and
resurfaced with topsoil from the stockpile, and re-vegetated
 It is anticipated that there will be no ore stockpiles left
 Waste rock stockpiles will be graded, sloped and
vegetated for rehabilitation
General Site Rehabilitation
60
 The aim is to restore the site to its original state before
the project began
 All plant equipment not necessary to continue water
treatment will be removed
 All vehicles and buildings/surface infrastructure will be
dismantled or sold
 Surplus materials such as sheet metal, insulation will be
collected and recycled/sold
 Removal and Clean-up of waste present on site
Tailings Storage Dam
61
 It is anticipated there will be some Tailings left in the dam
after production ceases
 Monitoring will continue until results indicate that runoff
and seepage from the tailings storage dam is of sufficient
quality for untreated discharge as according to GCDWQ
standards
 Maintenance of geotechnical and water quality
instruments will continue
 Once tailings have been rehabilitated the tailings storage
dam will be backfilled
Post-Closure Activities
62
 Monitoring and maintenance of this equipment will
continue for around 10 years after mine closure,
including:
-Physical stability of underground excavations
-Physical stability of the backfilled Crown Pillar
-Water quality and inflow from various points
 Operation of water treatment facility
 Upkeep of recycling pumps to collect seepage/runoff near
the tailings dam
 Upkeep of buildings and roadways necessary for post-
closure
Financial Analysis
63
Gold Price History
64
y = 0.0616x - 1606.1
0
200
400
600
800
1000
1200
1400
1600
1800
2000
1969 1980 1991 2002 2013
USDollarsperTozAu
50Year Gold Price y = 0.191x - 6627.3
0
200
400
600
800
1000
1200
1400
1600
1800
2000
1995 2005 2016
USDollarsperTozAu
20Year Gold Price
y = -0.1465x + 7470
0
200
400
600
800
1000
1200
1400
1600
1800
2000
06/07/2009 18/11/2010 01/04/2012 14/08/2013 27/12/2014 10/05/2016
USDollarsperTOZ
5Year History y = -0.5182x + 22941
0
200
400
600
800
1000
1200
1400
1600
1800
2000
01/04/2012 18/10/2012 06/05/2013 22/11/2013 10/06/2014 27/12/2014 15/07/2015
USDollarsperTOZ
3Year History
Gold Price Selection
65
0
200
400
600
800
1000
1200
1400
1600
05101520253035404550
USDollarsperTozAu
Years in Trailing Average
Trailing Average Model Price
72,400,000
12,000,000
29,100,000
72,100,000
8,400,000
12,600,000
-
74,600,000
5,600,000
Mining
Mining - Development
OP Mining
Milling
Road
Infrastructure
Contingency
Sustaining Capital
CAPEX Breakdown
66
Shows proportion of CAPEX on total LOM totals.
OPEX Breakdown
67
7.35
6.46
0.41
1.74
2.17
11.27
Mineral Process $/t
Comminution CIP Leaching
Solid Liquid Separation General Operations
Administration Supplies
5.78
5.77
14.71
9.80
3.32
Mining $/t
Equipment Supplies
Hourly Labour Admisistration
Sundries
US$ 29.40
US$39.38
Payback Period
68
Payback period of 4.6 years
-200
-150
-100
-50
-
50
100
150
200
250
2,014 2,015 2,016 2,017 2,018 2,019 2,020 2,021 2,022 2,023
MUS$
NPV Optimisation
69
 Ore blending.
 Spreading cash outgoings.
 Staged purchasing.
 Equipment matching.
 High grade stopes prioritised.
Sensitivity Analysis
70
-250
-200
-150
-100
-50
0
50
100
150
200
90.0% 100.0% 110.0%
NPV(MILLION$)
% OF MODELED VALUE
Sensitivity at 10% Discount Rate
Sensitivity to Copper Grade Sensitivity to Copper Price
Sensitivity to Process Recovery Sensitivity to Silver Price
Sensitivity to OPEX
Business risks
71
Summary
• The key business risks for the project are presented by First Nation regulation in
the region.
• Reduced risk due to access to infrastructure and a skilled work force.
• Battenberg Consultancy predict that from a risk stand point the project is an
attractive one for investors.
In Conclusion
72
 NPV at 7.5%
 Pre-Tax: US$152M
 Post-Tax: US$98M
 IRR
 Pre-Tax: 24%
 Post-Tax: 20%
 The Company recommends that this project be taken
forward to BFS
 Consideration of surface mining only.
73
Making your mining needs a piece of cake

Contenu connexe

En vedette

Concept_note_11May_High-Level_Thematic_Debate_side-event
Concept_note_11May_High-Level_Thematic_Debate_side-eventConcept_note_11May_High-Level_Thematic_Debate_side-event
Concept_note_11May_High-Level_Thematic_Debate_side-eventSherie Amor
 
What do we celebrate at Halloween?
What do we celebrate at Halloween?What do we celebrate at Halloween?
What do we celebrate at Halloween?ateixidoca1
 
World class digital transformation - keynote 2016
World class digital transformation - keynote 2016World class digital transformation - keynote 2016
World class digital transformation - keynote 2016Janet Granger
 
1 - Revision of Y11 Mechanics
1 - Revision of Y11 Mechanics1 - Revision of Y11 Mechanics
1 - Revision of Y11 Mechanicsmatcol
 
23-May_HL-Thematic-Debate-Conclussions-and-Observations-Achieving-the-SDGs-23...
23-May_HL-Thematic-Debate-Conclussions-and-Observations-Achieving-the-SDGs-23...23-May_HL-Thematic-Debate-Conclussions-and-Observations-Achieving-the-SDGs-23...
23-May_HL-Thematic-Debate-Conclussions-and-Observations-Achieving-the-SDGs-23...Sherie Amor
 
Harappan civi
Harappan civiHarappan civi
Harappan civiDlgltsbm
 
mock-set-plus presentation
mock-set-plus presentationmock-set-plus presentation
mock-set-plus presentationquestionbang
 
Sujiko plan marketing
Sujiko plan marketingSujiko plan marketing
Sujiko plan marketingSarif Salleh
 
Island Gold Mine - Sept. 30 2015 Site Tour
Island Gold Mine - Sept. 30 2015 Site TourIsland Gold Mine - Sept. 30 2015 Site Tour
Island Gold Mine - Sept. 30 2015 Site TourRichmontIR
 
Distance time graphs
Distance time graphsDistance time graphs
Distance time graphscoreorama
 
Making Effective Posters
Making Effective PostersMaking Effective Posters
Making Effective Posterskmmuelle
 
Face Recognition Technology
Face Recognition TechnologyFace Recognition Technology
Face Recognition TechnologyAgrani Rastogi
 
Déjeuner du GATE : Témoignage employeur remarquable
Déjeuner du GATE : Témoignage employeur remarquableDéjeuner du GATE : Témoignage employeur remarquable
Déjeuner du GATE : Témoignage employeur remarquableBenoit des Ligneris
 
Chemical Reactions
Chemical ReactionsChemical Reactions
Chemical Reactionsmatcol
 
La refonte d’un intranet : 10 cles pour reussir votre projet
La refonte d’un intranet : 10 cles pour reussir votre projetLa refonte d’un intranet : 10 cles pour reussir votre projet
La refonte d’un intranet : 10 cles pour reussir votre projetPhilippeC
 

En vedette (18)

PinkLINK Asia First Quarter 2016
PinkLINK Asia First Quarter 2016PinkLINK Asia First Quarter 2016
PinkLINK Asia First Quarter 2016
 
Concept_note_11May_High-Level_Thematic_Debate_side-event
Concept_note_11May_High-Level_Thematic_Debate_side-eventConcept_note_11May_High-Level_Thematic_Debate_side-event
Concept_note_11May_High-Level_Thematic_Debate_side-event
 
What do we celebrate at Halloween?
What do we celebrate at Halloween?What do we celebrate at Halloween?
What do we celebrate at Halloween?
 
World class digital transformation - keynote 2016
World class digital transformation - keynote 2016World class digital transformation - keynote 2016
World class digital transformation - keynote 2016
 
1 - Revision of Y11 Mechanics
1 - Revision of Y11 Mechanics1 - Revision of Y11 Mechanics
1 - Revision of Y11 Mechanics
 
23-May_HL-Thematic-Debate-Conclussions-and-Observations-Achieving-the-SDGs-23...
23-May_HL-Thematic-Debate-Conclussions-and-Observations-Achieving-the-SDGs-23...23-May_HL-Thematic-Debate-Conclussions-and-Observations-Achieving-the-SDGs-23...
23-May_HL-Thematic-Debate-Conclussions-and-Observations-Achieving-the-SDGs-23...
 
Harappan civi
Harappan civiHarappan civi
Harappan civi
 
Business Plan Gaias Gift
Business Plan Gaias GiftBusiness Plan Gaias Gift
Business Plan Gaias Gift
 
Alia Bhatt November Fashion
Alia Bhatt November FashionAlia Bhatt November Fashion
Alia Bhatt November Fashion
 
mock-set-plus presentation
mock-set-plus presentationmock-set-plus presentation
mock-set-plus presentation
 
Sujiko plan marketing
Sujiko plan marketingSujiko plan marketing
Sujiko plan marketing
 
Island Gold Mine - Sept. 30 2015 Site Tour
Island Gold Mine - Sept. 30 2015 Site TourIsland Gold Mine - Sept. 30 2015 Site Tour
Island Gold Mine - Sept. 30 2015 Site Tour
 
Distance time graphs
Distance time graphsDistance time graphs
Distance time graphs
 
Making Effective Posters
Making Effective PostersMaking Effective Posters
Making Effective Posters
 
Face Recognition Technology
Face Recognition TechnologyFace Recognition Technology
Face Recognition Technology
 
Déjeuner du GATE : Témoignage employeur remarquable
Déjeuner du GATE : Témoignage employeur remarquableDéjeuner du GATE : Témoignage employeur remarquable
Déjeuner du GATE : Témoignage employeur remarquable
 
Chemical Reactions
Chemical ReactionsChemical Reactions
Chemical Reactions
 
La refonte d’un intranet : 10 cles pour reussir votre projet
La refonte d’un intranet : 10 cles pour reussir votre projetLa refonte d’un intranet : 10 cles pour reussir votre projet
La refonte d’un intranet : 10 cles pour reussir votre projet
 

Similaire à Group 3 Presentation

The university of zambia presentation (immanuel 2016)
The university of zambia presentation (immanuel 2016)The university of zambia presentation (immanuel 2016)
The university of zambia presentation (immanuel 2016)immanuel91
 
Feasibility and Economic Design of Pumped Storage Hydropower Station
Feasibility and Economic Design of Pumped Storage Hydropower StationFeasibility and Economic Design of Pumped Storage Hydropower Station
Feasibility and Economic Design of Pumped Storage Hydropower StationAwais Marwat
 
Drilling efficiency optimization at hassai site
Drilling efficiency optimization at hassai siteDrilling efficiency optimization at hassai site
Drilling efficiency optimization at hassai siteAhmad Elsir
 
326074628-FDP-Presentation-Slide.pptx
326074628-FDP-Presentation-Slide.pptx326074628-FDP-Presentation-Slide.pptx
326074628-FDP-Presentation-Slide.pptxmohdsuriamohdsuhaimi
 
Optimization of waste handling in surface mines
Optimization of waste handling in surface minesOptimization of waste handling in surface mines
Optimization of waste handling in surface minesSafdar Ali
 
Expo Presentation Poster FINAL
Expo Presentation Poster FINALExpo Presentation Poster FINAL
Expo Presentation Poster FINALBenjamin Kramka
 
Investor Presentation | Evolution Mining (ASX:EVN) | Gold Investment Symposiu...
Investor Presentation | Evolution Mining (ASX:EVN) | Gold Investment Symposiu...Investor Presentation | Evolution Mining (ASX:EVN) | Gold Investment Symposiu...
Investor Presentation | Evolution Mining (ASX:EVN) | Gold Investment Symposiu...Symposium
 
Hard Rock Mine Design Project
Hard Rock Mine Design ProjectHard Rock Mine Design Project
Hard Rock Mine Design ProjectAshishKumar3265
 
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...Roshan Kumar Patel
 
TerraX Corporate Presentation Oct 2013
TerraX Corporate Presentation Oct 2013TerraX Corporate Presentation Oct 2013
TerraX Corporate Presentation Oct 2013Company Spotlight
 
TerraX Corporate Presentation Oct 2013
TerraX Corporate Presentation Oct 2013TerraX Corporate Presentation Oct 2013
TerraX Corporate Presentation Oct 2013Company Spotlight
 
Undurnaran for Investor 01_Apr ENG
Undurnaran for Investor 01_Apr ENGUndurnaran for Investor 01_Apr ENG
Undurnaran for Investor 01_Apr ENGTaivan Bayasaa
 
Investor Presentation | Mutiny Gold (ASX:MYG) | Gold Investment Symposium 2014
Investor Presentation | Mutiny Gold (ASX:MYG) | Gold Investment Symposium 2014Investor Presentation | Mutiny Gold (ASX:MYG) | Gold Investment Symposium 2014
Investor Presentation | Mutiny Gold (ASX:MYG) | Gold Investment Symposium 2014Symposium
 
Term Project Paper on Design of Shallow and Deep Foundation for a cement plan...
Term Project Paper on Design of Shallow and Deep Foundation for a cement plan...Term Project Paper on Design of Shallow and Deep Foundation for a cement plan...
Term Project Paper on Design of Shallow and Deep Foundation for a cement plan...Rakibul Hasan,MEng,EIT
 
30042010 asx-mar-10-quarterly
30042010 asx-mar-10-quarterly30042010 asx-mar-10-quarterly
30042010 asx-mar-10-quarterlyMark Clark
 
Field Development Project : Gelama Merah
Field Development Project : Gelama MerahField Development Project : Gelama Merah
Field Development Project : Gelama MerahHami Asma'i
 
Review of blue duck claims by Rio Zim
Review of blue duck claims by Rio ZimReview of blue duck claims by Rio Zim
Review of blue duck claims by Rio ZimTawandaWaited
 
BORED pile and pile cap design.ppt
BORED pile and pile cap design.pptBORED pile and pile cap design.ppt
BORED pile and pile cap design.pptkarsapersada
 

Similaire à Group 3 Presentation (20)

The university of zambia presentation (immanuel 2016)
The university of zambia presentation (immanuel 2016)The university of zambia presentation (immanuel 2016)
The university of zambia presentation (immanuel 2016)
 
Feasibility and Economic Design of Pumped Storage Hydropower Station
Feasibility and Economic Design of Pumped Storage Hydropower StationFeasibility and Economic Design of Pumped Storage Hydropower Station
Feasibility and Economic Design of Pumped Storage Hydropower Station
 
BAR MIB
BAR MIBBAR MIB
BAR MIB
 
Drilling efficiency optimization at hassai site
Drilling efficiency optimization at hassai siteDrilling efficiency optimization at hassai site
Drilling efficiency optimization at hassai site
 
326074628-FDP-Presentation-Slide.pptx
326074628-FDP-Presentation-Slide.pptx326074628-FDP-Presentation-Slide.pptx
326074628-FDP-Presentation-Slide.pptx
 
Optimization of waste handling in surface mines
Optimization of waste handling in surface minesOptimization of waste handling in surface mines
Optimization of waste handling in surface mines
 
Expo Presentation Poster FINAL
Expo Presentation Poster FINALExpo Presentation Poster FINAL
Expo Presentation Poster FINAL
 
Investor Presentation | Evolution Mining (ASX:EVN) | Gold Investment Symposiu...
Investor Presentation | Evolution Mining (ASX:EVN) | Gold Investment Symposiu...Investor Presentation | Evolution Mining (ASX:EVN) | Gold Investment Symposiu...
Investor Presentation | Evolution Mining (ASX:EVN) | Gold Investment Symposiu...
 
Hard Rock Mine Design Project
Hard Rock Mine Design ProjectHard Rock Mine Design Project
Hard Rock Mine Design Project
 
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
 
TerraX Corporate Presentation Oct 2013
TerraX Corporate Presentation Oct 2013TerraX Corporate Presentation Oct 2013
TerraX Corporate Presentation Oct 2013
 
TerraX Corporate Presentation Oct 2013
TerraX Corporate Presentation Oct 2013TerraX Corporate Presentation Oct 2013
TerraX Corporate Presentation Oct 2013
 
Undurnaran for Investor 01_Apr ENG
Undurnaran for Investor 01_Apr ENGUndurnaran for Investor 01_Apr ENG
Undurnaran for Investor 01_Apr ENG
 
Investor Presentation | Mutiny Gold (ASX:MYG) | Gold Investment Symposium 2014
Investor Presentation | Mutiny Gold (ASX:MYG) | Gold Investment Symposium 2014Investor Presentation | Mutiny Gold (ASX:MYG) | Gold Investment Symposium 2014
Investor Presentation | Mutiny Gold (ASX:MYG) | Gold Investment Symposium 2014
 
Term Project Paper on Design of Shallow and Deep Foundation for a cement plan...
Term Project Paper on Design of Shallow and Deep Foundation for a cement plan...Term Project Paper on Design of Shallow and Deep Foundation for a cement plan...
Term Project Paper on Design of Shallow and Deep Foundation for a cement plan...
 
30042010 asx-mar-10-quarterly
30042010 asx-mar-10-quarterly30042010 asx-mar-10-quarterly
30042010 asx-mar-10-quarterly
 
Field Development Project : Gelama Merah
Field Development Project : Gelama MerahField Development Project : Gelama Merah
Field Development Project : Gelama Merah
 
Review of blue duck claims by Rio Zim
Review of blue duck claims by Rio ZimReview of blue duck claims by Rio Zim
Review of blue duck claims by Rio Zim
 
BORED pile and pile cap design.ppt
BORED pile and pile cap design.pptBORED pile and pile cap design.ppt
BORED pile and pile cap design.ppt
 
1Malaysia Cabin
1Malaysia Cabin1Malaysia Cabin
1Malaysia Cabin
 

Group 3 Presentation

  • 1. Smooth Rock Falls Mining Prefeasibility Study Battenberg Consultancy 1
  • 2. Executive Summary 2 Life of mine 7Years 3 Months Mined tonnes ore 4089281 Average grade 4.37 Ounces produced 574539 Net PresentValue (DCR 5%) 178 Net PresentValue inc.Tax (DCR 5%) 117
  • 3. Scope  Located in North-Eastern Ontario  Low Sulphide Gold Deposit  Well established mining area  Commissioned by CSM Resources to produce a PEA  Designed around existing underground infrastructure3
  • 4. Property Description and Location  1017.5km2 area  49.125N, 81.75W  Extremely close to the Trans-Canada Highway/Ontario 11  Access to the site is currently a small dirt road  Cochrane Airport is 87.5km to the east  Timmins city is 128km to the south  Moderate-low relief 4
  • 5. Existing Infrastructure and Power  Two existing shafts  Development Level at 365m  Fully refurbished haulage shaft  Haulage capacity of 1600 t/d  Over 60% of Ontario’s energy is generated from Nuclear Power  115kV power line is situated close to the site  Diesel generators will continue to be utilised 5
  • 6. History  CSM Resources are the second owners of the claim, and thus will have to pay a 2.5% royalty  Mining in theTimmins district has been a prevalent industry since the early C20th  60.8 million oz’s of gold have been produced in the Timmins district to date  32 Gold producing mines in the Timmins District 6
  • 7. Geology Regional Geology The site is located on part of the Canadian Shield  Superior Province  Southern Province  Grenville Province 7
  • 8. Property Geology Glacial till is the main surficial deposit, with bedrock also compromising a significant amount. The three main types of glacial till are:  Lower Till  Barlow-Ojibway Formation  Cochrane Formation 8
  • 9. Deposit Geology  Dominated by Greenschists  Quartz and Sericite are common wall rock minerals  Deposits generally contain around 2/3% sulphide minerals  Acid Mine Drainage needs to be considered 9
  • 10. Mineral Resource Estimates Category Tonnes Capped Grade (g/t Au) Capped Oz (Au) Measured 1,499,000 3.89 187,300 Indicated 2,661,000 5.56 475,500 Measured & Indicated 4,160,000 4.96 662,800 Inferred 239,000 2.61 20,100 Based on historic diamond drilling , the following table represents the Mineral Resource estimate. 10
  • 12. 12  What we knew Initial data consisted of rock types, rock strengths and joint information  What we found Hanging wall weakest rock type Stress environment of the deposit Generally this case is assumed to be a dry excavation therefore groundwater effects are negligible in  What it means Stopes designed to be stable Limited support needed on critical surfaces
  • 13. Rock Mass and Stress Situation 13  In-situ stress profile established.  Induced stress due to the openings established using Examine2D.  Stress distributions around the excavation and state at the center on opening. Induced stress contours of excavation orientation looking E-W Induced stress contours of excavation orientation looking N-S
  • 14. Joint Sets 14  Core log data.  Stereographic analysis displayed the joint situation at smooth rock falls deposit.  Major discontinuity orientations and joint sets determined. Stereographic analysis for smooth rock underground mapping data
  • 15. Stope Design Approach 15 Four Components:  Initial stope dimensions assumed  Stability number equation factors derived N’=Q’×A×B×C  N’ used on stability graph to obtain Hydraulic radius of proposed stope  Hydraulic radius and stability numbers modified in line with stope stability requirements
  • 16. 16 Stability graph highlighting the recommended HR to obtain suitable stope dimensions (Brady, 1993)
  • 17. Ground Support 17  Very conservative estimates of support requirements due to uncertainties and time dependent behavior of rock mas.  Preliminary analysis showed support requirements are mostly unsupported with spot bolting required in a few areas  Intersections require systematic bolting and some unreinforced shortcrete in critical intersections  Underground crusher chamber requires fibre reinforced concrete and bolting Estimated support categories based on the tunneling index Q (Hoek 1995)
  • 18. Crown pillar Analysis 18 t = 19.6m  25m Critical Span 3.3 × 𝑄0.43 × 𝑠𝑖𝑛ℎ0.0016 𝑄 9.015 Scaled Span 𝑆( 𝛾 𝑡 1 + 𝑆 𝑅 1 − 0.4 cos 𝜃 )0.5
  • 19. Footwall drive stress analysis 19
  • 20. Recommendations 20  Further geotechnical data collection is required to ensure that the rock types and geotechnical domains are tackled.  Stope dimensions of 10 m x 20 m high with respect to changing strike lengths as mining depth in the ore body increases are suggested.  Stope dimensions must not exceed the maximum size until detailed geotechnical data is available to support the rock mass quality and economic analysis.  A ground control program should be implemented at the mine in the early stages of development in order to support and address mine design and safety issues.
  • 22. Comparison of mining methods 22 Cost type Cost per unit Obtained from Affected quantities Cost difference between Transverse and in ore development ($) Development 1410 $/m Cost of a 6.1m x 4.6m excavation in 2011 adjusted for a 4m x 4m excavation and 5% inflation. 190m footwall drive 10 x 10m crosscuts +536000 Stope production including backfill 39.40 $/t Eagle Mine stope and backfill costs adjusted for inflation. Sill pillar tonnage +834000 Processing cost 29.40 $/t Interpolating between given values. Sill pillar tonnage +622000 Development in ore • 3.5m thick sill pillar required • Total gold value of $5.5m locked up • Reduced need for backfill Transverse bench and fill • Skin to skin mining • Stopes must be completely backfilled Longitudinal Stoping • Ore body too thick $5490000 − $536000 − $834000 − $622000 = $3.5 𝑀𝑖𝑙𝑙𝑖𝑜𝑛
  • 23. Mineral Reserve Estimates 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 1 282,773 940,742 724,088 928,732 974,383 1,039,849 970,272 910,601 579,015 403,063 220,024 2 42,219 1,292,944 1,942,219 2,003,058 1,843,961 1,794,040 1,801,523 1,627,938 1,197,906 554,096 21,611 3 317,510 1,226,909 1,248,329 1,279,423 1,041,831 794,418 586,132 544,258 230,794 149,808 4 320,946 1,638,025 1,760,762 1,818,870 1,958,702 1,925,224 1,740,737 1,612,302 876,247 307,548 5 329,459 1,326,475 2,860,425 3,046,113 3,074,388 2,612,758 2,329,543 1,844,880 1,310,670 6 126,923 739,810 584,725 427,932 105,169 77,930 466,302 640,943 113,316 382,729 1,040,046 1,229,441 906,531 796,073 894,972 496,504 7 88,187 339,820 458,016 600,452 517,174 479,744 606,624 767,152 654,993 386,748 592,059 153,564 8 379,076 1,015,658 1,486,553 1,376,784 1,316,619 1,768,692 2,179,170 1,410,383 1,659,261 1,642,672 1,228,422 1,366,560 612,038 28,453 706,937 1,081,916 398,592 16,818 9 748,991 1,644,262 2,388,486 2,626,576 1,965,456 1,948,405 1,472,442 714,692 1,148,337 1,694,511 959,588 1,000,999 918,835 129,665 10 982,410 2,284,504 2,650,553 3,161,174 3,115,796 3,936,575 2,336,473 1,191,856 919,604 1,097,341 1,239,612 3,092,503 1,905,190 489,283 187,539 112,704 358,831 557,007 523,101 102,633 11 1,625,526 2,461,996 2,984,710 2,183,937 2,578,829 3,870,008 2,410,298 1,449,307 1,311,383 1,696,215 1,888,614 2,768,192 1,622,327 961,286 472,521 654,444 977,846 1,397,393 350,991 44,198 12 109,474 546,926 1,288,857 1,657,073 1,727,298 1,622,981 2,251,593 2,814,457 2,981,764 2,324,196 2,069,610 1,672,101 1,468,196 2,348,827 4,236,356 3,788,554 3,686,252 1,888,480 117,967 13 292,882 602,050 674,002 411,724 121,762 858,481 3,182,288 3,648,045 3,800,538 3,285,720 2,996,216 2,627,685 2,389,098 5,635,369 5,342,662 4,640,915 3,801,491 2,966,958 1,176,470 331,991 365,199 14 372,351 473,185 697,061 482,270 374,953 2,968,279 4,635,951 4,735,040 3,814,222 1,796,683 1,398,340 968,372 637,951 2,689,531 3,612,316 3,086,434 2,697,794 2,152,637 450,443 145,176 72,163 15 378,297 1,112,085 1,916,620 4,372,256 4,140,148 2,216,233 4,815,657 5,470,674 4,604,316 1,642,527 962,796 763,883 221,875 16 1,803,499 4,283,245 4,518,315 1,852,240 488,735 973,555 720,373 258,382 95,224 666,885 1,605,958 2,796,534 2,886,579 433,284 17 428,299 305,668 84,230 1,249,770 7,052,300 10,891,552 7,513,716 4,574,594 18 378,294 465,937 501,893 19 20 21 22 23Level Column • Based on the measured and indicated resource • A cut off grade of 3.0 g/t was calculated • Preliminary stopes that were not profitable were cut from the design 23
  • 24. Mine Design Level Access Foot-wall Drive Decline Cross Cuts Level Access  Transverse Bench and Fill stoping design based on the geotechnical constraints  Foot-wall drive hugs the ore body  Ramp and decline developed off the existing level  Stopes designed on their economic return 24
  • 25. ORE 1 11 1 1 2 3 2 2 3 2 3 2 33 4 44 4 4 5 5 6 6 6 7 Back-Fill Sequence Stoping Process 25
  • 26. 26
  • 27. Mine Development Initial development will be driving the ramp towards surface 27
  • 28. 28
  • 29. Additional Development • Ore pass to crusher hall • Fuel bay • Machine workshop 29
  • 30. Mine Production  Total LOM tonnes are 4.09 million  Production peaks in year 2 at 785439Tonnes  Average LOM grade of 4.37 g/t  Grade peaks in year 3 at 5.17 g/t0 100000 200000 300000 400000 500000 600000 700000 800000 900000 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Tonnes Year 0 20000 40000 60000 80000 100000 120000 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Ounces Year 30
  • 31. Ventilation • 200m3/s of air is required by the proposed design and equipment quantities • Booster fans will be required in certain districts, with a power circa 20kW • Auxiliary fans will provide the headings with clean fresh air • Air way will act as a second means of egress 31
  • 32. 32
  • 33. Mine Heating Ventilation on Demand A mine heating system will be utilised to provide the mine with 22 MBTU to the mine. It will be applied as followed;  2 months per year at 100% of heating capacity.  2 months per year at 50% of heating capacity.  2 months per year at 25% of heating capacity.  VOD will be used as different sections of the mine don’t need to be accessed.  When development of the upper section of the ore body has been fully mined, then it can be fully closed off.  Can save an approximated 10-15% on the operational ventilation costs. 33
  • 34. Backfill Paste Fill Unconsolidated rock fill 34  Primary stopes and level 9  65 microns particle size  85% tails  High strength - 5.5% binder  Regular strength – 4% binder  Total volume – 684000m^3  Estimated cost per tonne $10  Secondary stopes  Reduced need to hoist waste  Trucked and dumped into place  Total volume – 600000m^3  Estimated cost per tonne 0.05$/t
  • 35. 35
  • 36. Mining Equipment 36 Unit No. Specification Production Drill 1 Sand. DL321 LHD 3 Sand. LH307 Horizontal Development Jumbo 2 SAND DD321 Raise Borer 0 Primary Hauler - Rear Dump 5 Sand. TH320 Explosive Truck 1 Service Vehicles 4 Landcrusier Rock Bolter 1 Sand. DS311 Scissor Lift 2 Personnel Carrier 1 Normet Utimec Grader 1 CAT 12M
  • 37. Mineral Processing and Disposal 37
  • 39. Tailings 39  The total mill throughput: 8.8 million tonnes  Tailings ~55% solids by volume.  0.5 million m^3 consumed by backfill 8.8 𝑚𝑖𝑙𝑙𝑖𝑜𝑛 2.7 × 100 55 − 0.5 = 5.5 𝑚𝑖𝑙𝑙𝑖𝑜𝑛 𝑚3
  • 40. Tailings dam design 40 Design stage Year Height (m) Cross sectional area (m^2) Initial 0 20 700 Lift 1 3 26 1170 Lift 2 5 32 1770 Perimeter – 300 x 650m Slope angle – 30 degrees
  • 43. How the Mine is Impacted by Climate Change 43 Mitigation  Energy conservation  Improved fuel efficiency & Green transport  Reducing CO2 emissions Adaptation  Flood controls  Altering design to adapt to changing climate trends  Increasing FoS of design to reduce risk
  • 44. Current Climate of Project Site 44  Continental Climate  Relatively dry Climate  Very hot Summer  Very coldWinters
  • 45. 45
  • 46. 46 Model A2 B2 Summer Months 2°C 2°C Winter Months 3.5°C 3°C
  • 47. 47
  • 48. 48 Model A2 B2 Summer Months 10% Decrease 5% Decrease Winter Months 30% Decrease 20% Decrease
  • 49. Key Areas of Concern 49  Temperature Increase  Increased evaporation  Demand for heating/cooling of ventilation  Dust pollution  Rainfall  Flood Risk  Precipitation  Water Supply  Increase surface water  Extreme Weather Events  Flash floods  Forest Fires
  • 50. Effects of Climate Change on Mining the Timmins region of Ontario Event Hazards and Risks Controls 1 Temperature change 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 Reduced precipitation. Increased evaporation. Increased demand on ventilation. Heating and cooling of ventilation. Lower lake levels. Water quality. Dust. Freezing of ground and water 1.1.1 1.1.2 1.2.3 1.3.1 1.3.2 1.4.1 1.4.2 1.5.1 1.5.2 1.6.1 1.6.2 1.7.1 1.8.1 Look at alternative sources of water supply. Increase depth of boreholes. Cover water storage facilities. Install versatile fans that can increase demand. Install booster fans in areas with low ventilation. Heating has been installed in the mine ventilation already so can be used when required. Models indicate that only an increase in temperature will be seen, therefore no cooling will be required. If boreholes cannot supply full amount of the water and local lakes are used these need to be assessed to determine the effect on local wildlife, and the local community supply of water. Pumping may be required from a greater distance. Not used as drinking water. Water goes through gravel treatment before use in the mill or sent underground. Water is used to supress dust from becoming airborne underground. Water supply affected, pumping from greater distance may be required. 2 Rainfall 2.1 2.1a 2.1b 2.1c 2.2 Damage of water supply, effecting: Quality of water. Amount of water. Conflict with locals. Flooding on surface. 2.1a.1 2.1a.2 2.1b.1 2.1c.1 2.1c.2 2.2.1 2.2.2 2.2.3 2.2.4 Not used as drinking water. Water goes through gravel treatment before use in the mill or sent underground. Water stored in surface water bowsers. Collecting water supply from boreholes, thus not effecting local water supply. Low local population. Tailings dam has additional pumping capacity. Size of tailings dam has been designed to always have available additional capacity in case of flooding. Surface mine services will be insured. Assumed open pit is designed so slopes cope 50
  • 52. EIS Requirements 52 An EIS is necessary in order to proceed with the operation. It entails:  Scope of the project and purpose  An identification of the potential negative environmental impacts of the project, with all components at all project stages  An identification of technical and economically feasible mitigation measures to reduce or eliminate these impacts  Government/Public Consultation  Aboriginal Concerns  Consideration of the physical, biological and human environment
  • 53. Stages of an EIS 53  Permits  Consultation with Public and First Nations communities  Existing Environment and Baseline Studies  Socio-economic and cultural resource considerations  Impact Assessment on Existing Environment (Including Mitigation Procedures)  Alternatives  Closure Plan
  • 54. Impact Assessment Summary and Mitigation 54  The following areas in which the way the project will affect the environment are as follows:  Impact onWater supply and water management/water quality  Impact onTerrestrial and aquatic environment  Impact on Air Quality and Acoustic environment  Potential Acid Mine Drainage  Transportation effects  Greenhouse Gas Emissions
  • 55. Existing Environment 55  A requirement of beginning mine production is Consultation, which must be held with a full array of stakeholders, including public, project, and First Nations.  Baseline studies of the following are to be undertaken: -Atmospheric Environment,Aquatic Environment,Terrestrial Environment,Wildlife, Species at Risk and Socioeconomic status
  • 56. Alternatives to Project Implementation 56  Also considered were some ways the project could be implemented  The potential different modes of implementation considered were Project Location, Mining method, Processing plant location, tailings dam location/disposal, access routes into the mine, electrical transmission routes, and site closure
  • 57. Mine Closure and Remediation Plan 57  Following the Ontario provincial regulations of 240/00, we have addressed the following concerns: - Site Access Restriction - Closure of Mine openings - Continuation of physical, chemical and biological monitoring programs - Waste management, securing of petroleum products, chemicals and waste - Ensuring ongoing stability of rock piles, overburden piles and tailings storage dam - Rehabilitation of the site
  • 58. Site Access and Openings Closure 58  Upon completion of post-closure monitoring, access roads will be deconstructed  North and South shafts will be capped with either concrete or steel caps  Maintenance of Chainlink fence surrounding tailings dam will continue until backfilled.
  • 59. Open Pit and Underground Closure 59  Backfill has been chosen as the method of rehabilitation  Backfilling on the surface cannot commence until the completion of underground mining and rehabilitation  Underground, Backfilling is due to begin as soon as a stope is fully excavated, so throughout the mine life backfilling will be part of the mining process  Any disturbed surface locations will be shaped and resurfaced with topsoil from the stockpile, and re-vegetated  It is anticipated that there will be no ore stockpiles left  Waste rock stockpiles will be graded, sloped and vegetated for rehabilitation
  • 60. General Site Rehabilitation 60  The aim is to restore the site to its original state before the project began  All plant equipment not necessary to continue water treatment will be removed  All vehicles and buildings/surface infrastructure will be dismantled or sold  Surplus materials such as sheet metal, insulation will be collected and recycled/sold  Removal and Clean-up of waste present on site
  • 61. Tailings Storage Dam 61  It is anticipated there will be some Tailings left in the dam after production ceases  Monitoring will continue until results indicate that runoff and seepage from the tailings storage dam is of sufficient quality for untreated discharge as according to GCDWQ standards  Maintenance of geotechnical and water quality instruments will continue  Once tailings have been rehabilitated the tailings storage dam will be backfilled
  • 62. Post-Closure Activities 62  Monitoring and maintenance of this equipment will continue for around 10 years after mine closure, including: -Physical stability of underground excavations -Physical stability of the backfilled Crown Pillar -Water quality and inflow from various points  Operation of water treatment facility  Upkeep of recycling pumps to collect seepage/runoff near the tailings dam  Upkeep of buildings and roadways necessary for post- closure
  • 64. Gold Price History 64 y = 0.0616x - 1606.1 0 200 400 600 800 1000 1200 1400 1600 1800 2000 1969 1980 1991 2002 2013 USDollarsperTozAu 50Year Gold Price y = 0.191x - 6627.3 0 200 400 600 800 1000 1200 1400 1600 1800 2000 1995 2005 2016 USDollarsperTozAu 20Year Gold Price y = -0.1465x + 7470 0 200 400 600 800 1000 1200 1400 1600 1800 2000 06/07/2009 18/11/2010 01/04/2012 14/08/2013 27/12/2014 10/05/2016 USDollarsperTOZ 5Year History y = -0.5182x + 22941 0 200 400 600 800 1000 1200 1400 1600 1800 2000 01/04/2012 18/10/2012 06/05/2013 22/11/2013 10/06/2014 27/12/2014 15/07/2015 USDollarsperTOZ 3Year History
  • 66. 72,400,000 12,000,000 29,100,000 72,100,000 8,400,000 12,600,000 - 74,600,000 5,600,000 Mining Mining - Development OP Mining Milling Road Infrastructure Contingency Sustaining Capital CAPEX Breakdown 66 Shows proportion of CAPEX on total LOM totals.
  • 67. OPEX Breakdown 67 7.35 6.46 0.41 1.74 2.17 11.27 Mineral Process $/t Comminution CIP Leaching Solid Liquid Separation General Operations Administration Supplies 5.78 5.77 14.71 9.80 3.32 Mining $/t Equipment Supplies Hourly Labour Admisistration Sundries US$ 29.40 US$39.38
  • 68. Payback Period 68 Payback period of 4.6 years -200 -150 -100 -50 - 50 100 150 200 250 2,014 2,015 2,016 2,017 2,018 2,019 2,020 2,021 2,022 2,023 MUS$
  • 69. NPV Optimisation 69  Ore blending.  Spreading cash outgoings.  Staged purchasing.  Equipment matching.  High grade stopes prioritised.
  • 70. Sensitivity Analysis 70 -250 -200 -150 -100 -50 0 50 100 150 200 90.0% 100.0% 110.0% NPV(MILLION$) % OF MODELED VALUE Sensitivity at 10% Discount Rate Sensitivity to Copper Grade Sensitivity to Copper Price Sensitivity to Process Recovery Sensitivity to Silver Price Sensitivity to OPEX
  • 71. Business risks 71 Summary • The key business risks for the project are presented by First Nation regulation in the region. • Reduced risk due to access to infrastructure and a skilled work force. • Battenberg Consultancy predict that from a risk stand point the project is an attractive one for investors.
  • 72. In Conclusion 72  NPV at 7.5%  Pre-Tax: US$152M  Post-Tax: US$98M  IRR  Pre-Tax: 24%  Post-Tax: 20%  The Company recommends that this project be taken forward to BFS  Consideration of surface mining only.
  • 73. 73 Making your mining needs a piece of cake