SlideShare une entreprise Scribd logo
1  sur  14
MUHAMMAD HUSNAIN SIDDIQI
B.E INDUSTRIAL ENGINEERING AND MANAGEMENT
DAWOOD UNIVERSITY OF ENGINEERING & TECHNOLOGY
2nd Multi-disciplinary Students Research Conference 16-17th November, 2016
2nd MDSR Conference 2016 1

 Introduction
 Literature Reviews
 Problem Statement
 Research Objectives
 Methodology
 Results and discussion
 Conclusions
OUTLINE
2nd MDSR Conference 2016 2

PRODUCTIVITY
ITS NOT JUST DOING MORE. ITS ABOUT
CREATING
MORE IMPACT WITH LESS WORK
INTRODUCTION
2nd MDSR Conference 2016 3

SMED
(Single-Minute Exchange of Dies) is a system for dramatically reducing the time it takes to
complete equipment changeovers.
CHANGE OVER
The process of switching from the production of one product or part number to another in a
machine or a series of linked machines by changing parts, dies, molds or fixtures.
INTRODUCTION
2nd MDSR Conference 2016 4

Change over consist of two Elements:
1. INTERNAL ELEMENTS: Operations that can be carried out when the machine is
stopped at the time of working.
2. EXTERNAL ELEMENTS: External setup can be defined as the tasks that can be
carried out while the machine is in performing the operation.
INTRODUCTION
2nd MDSR Conference 2016 5
Author / Year Title of Paper Outcomes
Jonalee D. Bajpai/2014 SMED in Garment Manufacturing Industry.
Case study to reduce change over time.
Style Change over time can be greatly reduced by
application of SMED methodology with minimum
financial implication.
Pablo Guzmán Ferradás/ 2013 Improving changeover time: a tailored
SMED approach for welding cells
The validation of the method resulted in 33%
reduction of the changeover time of the welding
cell
Vipan Kumar, Amit Bajaj/ 2012 The Implementation of Single Minute
Exchange of Die with 5’S in Machining
Processes for reduction of Setup Time
Reduction in Setup time by eliminating no value
adding.
Ana Sofia Alves et.al/ 2009 Single Minute Exchange of Dies: Literature
Review
Top management support increase the potential
of SMED and SEMD can be applied in any industry
Cakmakci/ 2008 Performance analysis of the setup time
reduction-smed in the automobile
industry
SMED is still a suitable method not only for
manufacturing improvement but also for
equipment/die design development.
LITERATURE REVIEWS
2nd MDSR Conference 2016 6

“In textile industry huge time is wasted during change over activity of printing
rotaries. In order to reduce change over time there is a need to effective method to
reduce change over time. Thus this study proposed the SMED methodology to
over come this problem”
PROBLEM STATEMENT
2nd MDSR Conference 2016 7
MAIN OBJECTIVE
 To reduce the change over time using SMED.
SUB-OBJECTIVES
 To provide SOP for change over process
 To develop work culture according to JD (Job Description).
 Lower manufacturing cost
 Improved responsiveness to customer demand
RESEARCH OBJECTIVES
2nd MDSR Conference 2016 8

RESEARCH METHODOLOGY
• DURATION
• VARIATION
• OPPORTUNITY
IDENTIFY THE PILOT
AREA.
• DESCRIPTION
• COST IN TIME
• ELEMENTS
• MAN AND
MACHINE
• OBSEREVE
IDENTIFY ELEMENTS.
• Recognize
external elements
and internal
elements
SEPARATE EXTERNAL
ELEMENTS.
• Examine process
and convert
internal elements
to external
CONVERT INTERNAL
ELEMENTS TO EXTERNAL.
•ADJUSTMENTS
•MOTION
•WAITING
•STANDARDIZING
•OPERATIONS.
•MECHANIZE
STREAMLINE REMAINING
ELEMENTS.
9
Figure 1: Steps of SMED methodology

S.NO ACTIVITY ACTIVITY TIME
BEFORE
SMED
AFTER SMED TIME SAVED
1. Operator Goes to Engraving 1min35sec External External 00
2. Engraving Supervisor Handed Over Screens to Operator 35sec/screen External External 00
3. Operator Collect Screens from Engraving 1min21sec/screen External External 00
4. Screen Sequencing as Per Design 10sec/screen External External 00
5. As Per Program Quantity Fabric Material Availability to M/C 2min 12sec/ batcher Internal External 2min12sec
6. Squeegee Preparation 1min41sec/ squeegee Internal External 1min41sec
7. Lead Clothes Trolley to Fabric 56sec Internal External 56sec
8 Fabric Stitched to Lead Clothes 55sec Internal External 55sec
9. Temperature Maintaining 4min54sec Internal Internal
10. Sensor wire removed 3sec Internal Internal
11. Sensor removed 6sec Internal Internal
12. screen removed 32sec Internal Internal
13. Squeeze removed 25sec Internal Internal
14. removed colour pump 4sec Internal Internal
15. Clean of head 1min18sec Internal Internal
16. screen took in to machine and fit 57sec Internal Internal
17. squeeze took into screen 24sec Internal Internal
18. Squeeze levelling 1min17sec Internal Internal
19. cleaning of pump 46sec Internal Parallel to 16,17,18 46sec
20. sensor took and sensor wire 1min12sec Internal Parallel to 18. 1min12sec
21. colour pump insert 9sec Internal Internal
TOTAL 20mints 7min42sec
Table 2: Changeover activity time
RESULT AND DISCUSSION
Operator Goes to
Engraving, 1.58, 7%
Engraving Supervisor Handed
Over Screens to Operator, 0.58,
3%
Operator Collect Screens from
Engraving, 1.35, 6%
Screen Sequencing as Per
Design, 0.16, 1%
As Per Program
Quantity Fabric
Material Availability
to M/C, 2.2, 10%
Squeegee
Preparation, 1.68,
8%
Lead Clothes Trolley to Fabric,
0.93, 4%
Fabric Stitched to Lead Clothes,
0.91, 4%
Temperature Maintaining, 4.9,
23%
Sensor wire removed, 0.05, 0%
Sensor removed, 0.1, 0%
screen removed, 0.53, 2%
Squeeze removed, 0.41,
2%
removed colour
pump, 0.06, 0%
Clean of head, 1.3, 6%
screen took in to machine
and fit, 0.95, 4%
squeeze took into screen, 0.4, 2%
Squeeze levelling, 1.28, 6%
cleaning of pump, 0.76, 4% sensor took and sensor
wire, 1.2, 6%
TIME CONSUMPTION BY ACTIVITIES IN MINUTES
Figure 2: Pie chart of activities
11

SETUP TIME COMPARISON
BEFORE & AFTER SMED
20
12.3
0
5
10
15
20
25
TIMEINMINUTES
Before SMED After SMED
Setup time
Before SMED After SMED Time saved
20mints 12mints 18sec 7mints 42sec
12
Table 2: Set up time (Before and after SMED applied)
 The implementation of SMED technique has given the favorable outcomes for
the reduction of setup time.
 Changeover time is reduced up to 36%.
 The productivity increased by 2.21%.
 We concluded that SMED technique is very helpful for setup time reduction
and it direct causes to increase the productivity of industry.
CONCLUSION
2nd MDSR Conference 2016 13

THANK YOU
QUESTIONS & COMMENTS
2nd MDSR Conference 2016 14

Contenu connexe

Tendances

Method study(abhishekkumar)
Method study(abhishekkumar)Method study(abhishekkumar)
Method study(abhishekkumar)Abhishek Kumar
 
Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudybejayrocks
 
Implementation of Lean Manufacturing Tools in Garment Industry
Implementation of Lean Manufacturing Tools in Garment IndustryImplementation of Lean Manufacturing Tools in Garment Industry
Implementation of Lean Manufacturing Tools in Garment IndustryIJLT EMAS
 
Productivity Improvement using Lean Manufacturing '“ A Case Study at Muththam...
Productivity Improvement using Lean Manufacturing '“ A Case Study at Muththam...Productivity Improvement using Lean Manufacturing '“ A Case Study at Muththam...
Productivity Improvement using Lean Manufacturing '“ A Case Study at Muththam...ijtsrd
 
Roll of IE in Garments in Bangladesh
Roll of IE in Garments in BangladeshRoll of IE in Garments in Bangladesh
Roll of IE in Garments in BangladeshAriful Islam
 
Application of lean manufacturing tools in garments production
Application of lean manufacturing tools in garments productionApplication of lean manufacturing tools in garments production
Application of lean manufacturing tools in garments productionRazib Mahmud
 
Application of industrial engineering in garments sewing floor
Application of industrial engineering in garments sewing floorApplication of industrial engineering in garments sewing floor
Application of industrial engineering in garments sewing floorRakibul Hasan
 
Lean manufacturing tools for garment industry
Lean manufacturing tools for garment industryLean manufacturing tools for garment industry
Lean manufacturing tools for garment industryAzmir Latif Beg
 
Productivity improvement technique using work study in rmg sector
Productivity improvement technique using work study in rmg sectorProductivity improvement technique using work study in rmg sector
Productivity improvement technique using work study in rmg sectorEmdadul Haque
 
industrial engineering in sewing department
industrial engineering in sewing department industrial engineering in sewing department
industrial engineering in sewing department ShivamSagar13
 
Implementation of Lean Strategies in a Furniture Manufacturing Factory
Implementation of Lean Strategies in a Furniture Manufacturing Factory Implementation of Lean Strategies in a Furniture Manufacturing Factory
Implementation of Lean Strategies in a Furniture Manufacturing Factory IOSR Journals
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryijmech
 
Standardization & digitalization of sewing operations
Standardization & digitalization of sewing operationsStandardization & digitalization of sewing operations
Standardization & digitalization of sewing operationsArpan Mahato
 
Lean manufacturing
Lean manufacturingLean manufacturing
Lean manufacturingAnuj Shah
 

Tendances (20)

IE working procedure
IE working procedureIE working procedure
IE working procedure
 
Method study(abhishekkumar)
Method study(abhishekkumar)Method study(abhishekkumar)
Method study(abhishekkumar)
 
Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudy
 
Lean manufacturing
Lean manufacturingLean manufacturing
Lean manufacturing
 
Implementation of Lean Manufacturing Tools in Garment Industry
Implementation of Lean Manufacturing Tools in Garment IndustryImplementation of Lean Manufacturing Tools in Garment Industry
Implementation of Lean Manufacturing Tools in Garment Industry
 
Productivity Improvement using Lean Manufacturing '“ A Case Study at Muththam...
Productivity Improvement using Lean Manufacturing '“ A Case Study at Muththam...Productivity Improvement using Lean Manufacturing '“ A Case Study at Muththam...
Productivity Improvement using Lean Manufacturing '“ A Case Study at Muththam...
 
Roll of IE in Garments in Bangladesh
Roll of IE in Garments in BangladeshRoll of IE in Garments in Bangladesh
Roll of IE in Garments in Bangladesh
 
Application of lean manufacturing tools in garments production
Application of lean manufacturing tools in garments productionApplication of lean manufacturing tools in garments production
Application of lean manufacturing tools in garments production
 
Application of industrial engineering in garments sewing floor
Application of industrial engineering in garments sewing floorApplication of industrial engineering in garments sewing floor
Application of industrial engineering in garments sewing floor
 
Lean manufacturing tools for garment industry
Lean manufacturing tools for garment industryLean manufacturing tools for garment industry
Lean manufacturing tools for garment industry
 
Productivity improvement technique using work study in rmg sector
Productivity improvement technique using work study in rmg sectorProductivity improvement technique using work study in rmg sector
Productivity improvement technique using work study in rmg sector
 
PROJECT
PROJECTPROJECT
PROJECT
 
industrial engineering in sewing department
industrial engineering in sewing department industrial engineering in sewing department
industrial engineering in sewing department
 
Implementation of Lean Strategies in a Furniture Manufacturing Factory
Implementation of Lean Strategies in a Furniture Manufacturing Factory Implementation of Lean Strategies in a Furniture Manufacturing Factory
Implementation of Lean Strategies in a Furniture Manufacturing Factory
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
 
How to Improve Productivity
How to Improve ProductivityHow to Improve Productivity
How to Improve Productivity
 
Lean Manufacturing
Lean ManufacturingLean Manufacturing
Lean Manufacturing
 
Standardization & digitalization of sewing operations
Standardization & digitalization of sewing operationsStandardization & digitalization of sewing operations
Standardization & digitalization of sewing operations
 
Executive Summary El
Executive Summary ElExecutive Summary El
Executive Summary El
 
Lean manufacturing
Lean manufacturingLean manufacturing
Lean manufacturing
 

En vedette (9)

Penggunaan radio button dan checkbox dalam vb.net
Penggunaan radio button dan checkbox dalam vb.netPenggunaan radio button dan checkbox dalam vb.net
Penggunaan radio button dan checkbox dalam vb.net
 
Animaciones
AnimacionesAnimaciones
Animaciones
 
Bolsos2016
Bolsos2016Bolsos2016
Bolsos2016
 
Computacion diapos
Computacion diaposComputacion diapos
Computacion diapos
 
Escritura1
Escritura1Escritura1
Escritura1
 
Computacion diapositivas 2
Computacion diapositivas 2Computacion diapositivas 2
Computacion diapositivas 2
 
PrimeTime Magazine - July 2009
PrimeTime Magazine - July 2009PrimeTime Magazine - July 2009
PrimeTime Magazine - July 2009
 
General uses of wall putty
General uses of wall puttyGeneral uses of wall putty
General uses of wall putty
 
Tribus urbanas
Tribus urbanasTribus urbanas
Tribus urbanas
 

Similaire à paper-presentation

thesis-presentation (1)
thesis-presentation (1)thesis-presentation (1)
thesis-presentation (1)Asim Aslam
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTFASI93
 
Just in time Manufacturing
Just in time ManufacturingJust in time Manufacturing
Just in time ManufacturingKiran Girase
 
Project Report on Textile Industrial Engineering
Project Report on Textile Industrial EngineeringProject Report on Textile Industrial Engineering
Project Report on Textile Industrial EngineeringAmanuzzaman Aman
 
IRJET- Single Minute Exchange of Dies (SMED) Concept
IRJET-  	  Single Minute Exchange of Dies (SMED) ConceptIRJET-  	  Single Minute Exchange of Dies (SMED) Concept
IRJET- Single Minute Exchange of Dies (SMED) ConceptIRJET Journal
 
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...IRJET Journal
 
applicationof vsm
applicationof vsmapplicationof vsm
applicationof vsmAro Ephrem
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...Karina Islam
 
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET Journal
 
Production management
Production managementProduction management
Production managementAntony Raj
 
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...IRJET Journal
 
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean PrinciplesIRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean PrinciplesIRJET Journal
 
DESIGN AND MANUFACTURING OF SPM FOR BRAKE WHEEL CYLINDER
DESIGN AND MANUFACTURING OF SPM FOR BRAKE WHEEL CYLINDERDESIGN AND MANUFACTURING OF SPM FOR BRAKE WHEEL CYLINDER
DESIGN AND MANUFACTURING OF SPM FOR BRAKE WHEEL CYLINDERAkshay Deshpande
 
Paper cutting & rewinding machine project report sreesangh p ghosh
Paper cutting & rewinding machine   project report sreesangh p ghoshPaper cutting & rewinding machine   project report sreesangh p ghosh
Paper cutting & rewinding machine project report sreesangh p ghoshSreesangh P Ghosh
 
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON ENGINE COOLING ASSEMBLY
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON  ENGINE COOLING ASSEMBLYPRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON  ENGINE COOLING ASSEMBLY
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON ENGINE COOLING ASSEMBLYDIPRANJAN GUPTA
 
IRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET Journal
 
Production management
Production managementProduction management
Production managementAntony Raj
 
Final year project report on Value stream mapping and Smed
Final year project report on Value stream mapping and SmedFinal year project report on Value stream mapping and Smed
Final year project report on Value stream mapping and SmedUmar Yazdani
 
Paper cutting & rewinding machine project report sreesangh p ghosh
Paper cutting & rewinding machine   project report sreesangh p ghoshPaper cutting & rewinding machine   project report sreesangh p ghosh
Paper cutting & rewinding machine project report sreesangh p ghoshSreesangh P Ghosh
 
production_mgmt.ppt
production_mgmt.pptproduction_mgmt.ppt
production_mgmt.pptMbabba2
 

Similaire à paper-presentation (20)

thesis-presentation (1)
thesis-presentation (1)thesis-presentation (1)
thesis-presentation (1)
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPT
 
Just in time Manufacturing
Just in time ManufacturingJust in time Manufacturing
Just in time Manufacturing
 
Project Report on Textile Industrial Engineering
Project Report on Textile Industrial EngineeringProject Report on Textile Industrial Engineering
Project Report on Textile Industrial Engineering
 
IRJET- Single Minute Exchange of Dies (SMED) Concept
IRJET-  	  Single Minute Exchange of Dies (SMED) ConceptIRJET-  	  Single Minute Exchange of Dies (SMED) Concept
IRJET- Single Minute Exchange of Dies (SMED) Concept
 
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
 
applicationof vsm
applicationof vsmapplicationof vsm
applicationof vsm
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
 
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
 
Production management
Production managementProduction management
Production management
 
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
IRJET - Analysis of Process Re-Engineering to Reduce Lead Time in Apparel Ind...
 
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean PrinciplesIRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
 
DESIGN AND MANUFACTURING OF SPM FOR BRAKE WHEEL CYLINDER
DESIGN AND MANUFACTURING OF SPM FOR BRAKE WHEEL CYLINDERDESIGN AND MANUFACTURING OF SPM FOR BRAKE WHEEL CYLINDER
DESIGN AND MANUFACTURING OF SPM FOR BRAKE WHEEL CYLINDER
 
Paper cutting & rewinding machine project report sreesangh p ghosh
Paper cutting & rewinding machine   project report sreesangh p ghoshPaper cutting & rewinding machine   project report sreesangh p ghosh
Paper cutting & rewinding machine project report sreesangh p ghosh
 
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON ENGINE COOLING ASSEMBLY
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON  ENGINE COOLING ASSEMBLYPRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON  ENGINE COOLING ASSEMBLY
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON ENGINE COOLING ASSEMBLY
 
IRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall Productivity
 
Production management
Production managementProduction management
Production management
 
Final year project report on Value stream mapping and Smed
Final year project report on Value stream mapping and SmedFinal year project report on Value stream mapping and Smed
Final year project report on Value stream mapping and Smed
 
Paper cutting & rewinding machine project report sreesangh p ghosh
Paper cutting & rewinding machine   project report sreesangh p ghoshPaper cutting & rewinding machine   project report sreesangh p ghosh
Paper cutting & rewinding machine project report sreesangh p ghosh
 
production_mgmt.ppt
production_mgmt.pptproduction_mgmt.ppt
production_mgmt.ppt
 

paper-presentation

  • 1. MUHAMMAD HUSNAIN SIDDIQI B.E INDUSTRIAL ENGINEERING AND MANAGEMENT DAWOOD UNIVERSITY OF ENGINEERING & TECHNOLOGY 2nd Multi-disciplinary Students Research Conference 16-17th November, 2016 2nd MDSR Conference 2016 1
  • 2.   Introduction  Literature Reviews  Problem Statement  Research Objectives  Methodology  Results and discussion  Conclusions OUTLINE 2nd MDSR Conference 2016 2
  • 3.  PRODUCTIVITY ITS NOT JUST DOING MORE. ITS ABOUT CREATING MORE IMPACT WITH LESS WORK INTRODUCTION 2nd MDSR Conference 2016 3
  • 4.  SMED (Single-Minute Exchange of Dies) is a system for dramatically reducing the time it takes to complete equipment changeovers. CHANGE OVER The process of switching from the production of one product or part number to another in a machine or a series of linked machines by changing parts, dies, molds or fixtures. INTRODUCTION 2nd MDSR Conference 2016 4
  • 5.  Change over consist of two Elements: 1. INTERNAL ELEMENTS: Operations that can be carried out when the machine is stopped at the time of working. 2. EXTERNAL ELEMENTS: External setup can be defined as the tasks that can be carried out while the machine is in performing the operation. INTRODUCTION 2nd MDSR Conference 2016 5
  • 6. Author / Year Title of Paper Outcomes Jonalee D. Bajpai/2014 SMED in Garment Manufacturing Industry. Case study to reduce change over time. Style Change over time can be greatly reduced by application of SMED methodology with minimum financial implication. Pablo Guzmán Ferradás/ 2013 Improving changeover time: a tailored SMED approach for welding cells The validation of the method resulted in 33% reduction of the changeover time of the welding cell Vipan Kumar, Amit Bajaj/ 2012 The Implementation of Single Minute Exchange of Die with 5’S in Machining Processes for reduction of Setup Time Reduction in Setup time by eliminating no value adding. Ana Sofia Alves et.al/ 2009 Single Minute Exchange of Dies: Literature Review Top management support increase the potential of SMED and SEMD can be applied in any industry Cakmakci/ 2008 Performance analysis of the setup time reduction-smed in the automobile industry SMED is still a suitable method not only for manufacturing improvement but also for equipment/die design development. LITERATURE REVIEWS 2nd MDSR Conference 2016 6
  • 7.  “In textile industry huge time is wasted during change over activity of printing rotaries. In order to reduce change over time there is a need to effective method to reduce change over time. Thus this study proposed the SMED methodology to over come this problem” PROBLEM STATEMENT 2nd MDSR Conference 2016 7
  • 8. MAIN OBJECTIVE  To reduce the change over time using SMED. SUB-OBJECTIVES  To provide SOP for change over process  To develop work culture according to JD (Job Description).  Lower manufacturing cost  Improved responsiveness to customer demand RESEARCH OBJECTIVES 2nd MDSR Conference 2016 8
  • 9.  RESEARCH METHODOLOGY • DURATION • VARIATION • OPPORTUNITY IDENTIFY THE PILOT AREA. • DESCRIPTION • COST IN TIME • ELEMENTS • MAN AND MACHINE • OBSEREVE IDENTIFY ELEMENTS. • Recognize external elements and internal elements SEPARATE EXTERNAL ELEMENTS. • Examine process and convert internal elements to external CONVERT INTERNAL ELEMENTS TO EXTERNAL. •ADJUSTMENTS •MOTION •WAITING •STANDARDIZING •OPERATIONS. •MECHANIZE STREAMLINE REMAINING ELEMENTS. 9 Figure 1: Steps of SMED methodology
  • 10.  S.NO ACTIVITY ACTIVITY TIME BEFORE SMED AFTER SMED TIME SAVED 1. Operator Goes to Engraving 1min35sec External External 00 2. Engraving Supervisor Handed Over Screens to Operator 35sec/screen External External 00 3. Operator Collect Screens from Engraving 1min21sec/screen External External 00 4. Screen Sequencing as Per Design 10sec/screen External External 00 5. As Per Program Quantity Fabric Material Availability to M/C 2min 12sec/ batcher Internal External 2min12sec 6. Squeegee Preparation 1min41sec/ squeegee Internal External 1min41sec 7. Lead Clothes Trolley to Fabric 56sec Internal External 56sec 8 Fabric Stitched to Lead Clothes 55sec Internal External 55sec 9. Temperature Maintaining 4min54sec Internal Internal 10. Sensor wire removed 3sec Internal Internal 11. Sensor removed 6sec Internal Internal 12. screen removed 32sec Internal Internal 13. Squeeze removed 25sec Internal Internal 14. removed colour pump 4sec Internal Internal 15. Clean of head 1min18sec Internal Internal 16. screen took in to machine and fit 57sec Internal Internal 17. squeeze took into screen 24sec Internal Internal 18. Squeeze levelling 1min17sec Internal Internal 19. cleaning of pump 46sec Internal Parallel to 16,17,18 46sec 20. sensor took and sensor wire 1min12sec Internal Parallel to 18. 1min12sec 21. colour pump insert 9sec Internal Internal TOTAL 20mints 7min42sec Table 2: Changeover activity time RESULT AND DISCUSSION
  • 11. Operator Goes to Engraving, 1.58, 7% Engraving Supervisor Handed Over Screens to Operator, 0.58, 3% Operator Collect Screens from Engraving, 1.35, 6% Screen Sequencing as Per Design, 0.16, 1% As Per Program Quantity Fabric Material Availability to M/C, 2.2, 10% Squeegee Preparation, 1.68, 8% Lead Clothes Trolley to Fabric, 0.93, 4% Fabric Stitched to Lead Clothes, 0.91, 4% Temperature Maintaining, 4.9, 23% Sensor wire removed, 0.05, 0% Sensor removed, 0.1, 0% screen removed, 0.53, 2% Squeeze removed, 0.41, 2% removed colour pump, 0.06, 0% Clean of head, 1.3, 6% screen took in to machine and fit, 0.95, 4% squeeze took into screen, 0.4, 2% Squeeze levelling, 1.28, 6% cleaning of pump, 0.76, 4% sensor took and sensor wire, 1.2, 6% TIME CONSUMPTION BY ACTIVITIES IN MINUTES Figure 2: Pie chart of activities 11
  • 12.  SETUP TIME COMPARISON BEFORE & AFTER SMED 20 12.3 0 5 10 15 20 25 TIMEINMINUTES Before SMED After SMED Setup time Before SMED After SMED Time saved 20mints 12mints 18sec 7mints 42sec 12 Table 2: Set up time (Before and after SMED applied)
  • 13.  The implementation of SMED technique has given the favorable outcomes for the reduction of setup time.  Changeover time is reduced up to 36%.  The productivity increased by 2.21%.  We concluded that SMED technique is very helpful for setup time reduction and it direct causes to increase the productivity of industry. CONCLUSION 2nd MDSR Conference 2016 13
  • 14.  THANK YOU QUESTIONS & COMMENTS 2nd MDSR Conference 2016 14