SlideShare une entreprise Scribd logo
1  sur  27
Project Management Professional
PMP® Exam Prep – Week 4
Quality Management
Prof. Muzette Charles, PMP | mcharles2@pace.edu
Quality Management
Chapter 8
“… works to ensure the project requirements, including product requirements are met & validated.”
• “Project is completed with no deviations from the project requirements.”
• Customer satisfaction – project meets the defined customer needs
• Continuous improvement: Plan-Do-Check-Act (PDCA) is the basis for quality improvement
• Prevention over inspection
• Management responsibility
Process Process Group Key Deliverables
8.1 Plan Quality Management Planning Quality Management Plan
8.2 Manage Quality Executing Change Requests
8.3 Control Quality Monitoring & Control Validated Changes
QA vs. QC
Quality Assurance
 Process-oriented
 Is project being
implemented
according to plan?
 Are project processes
as efficient and
effective as possible?
Quality Control
 Deliverable-oriented
 Does the deliverable
conform to customer-
agreed, measurable
quality characteristics?
Quality Management
Chapter 8
Quality Pioneers
Shewhart Statistical process control (SPC) and control charts
Deming Plan, Do, Check, Act (PDCA) model
Commitment to continuous improvement as a way to effect
organizational transformation
Juran Fitness for use—meeting customer’s requirements
Cost of quality, Pareto principle, quality trilogy
Crosby Conforming to customer needs and preventing defects (zero
defects)
“Quality is free.”
Feigenbaum Total quality management (leadership, use of technology,
commitment to customer needs)
Ishikawa Seven quality tools and quality circles (worker involvement)
Taguchi Focus on designing quality into a product or service
Shingo and
Ohno
Just-in-time (JIT) manufacturing and “lean”—focusing on
efficiency and value-producing activity
What quality expert championed the concept
of continuous improvement as integral to
quality management?
A. Deming
B. Juran
C. Crosby
D. Feigenbaum
Discussion Question
Answer: A
On the exam, you may be asked to define specific
quality theories or identify quality gurus by their
ideas. Chapter 8, Topic 1
Quality Initiatives in Organizations
TQM • Ancestor of many initiatives
Six Sigma
• Certified “black belt” practitioners
• Integration of quality in all business processes
ISO
• International Organization for Standardization
• ISO 9000 series
Baldrige
• Self-assessment and improvement program
• Malcolm Baldrige National Quality Award
CMMI
• Capability Maturity Model Integration
• Software project–oriented
How do organizational quality initiatives affect project
teams?
A. Only indirectly, through operations.
B. They may shape project quality processes and
objectives.
C. They are secondary to PMO processes.
D. They affect project managers but not team members.
Discussion Question
Answer: B
Quality initiatives can potentially affect the entire
organization, shaping project management processes and
affecting the way project success is defined. Most quality
initiatives emphasize the involvement of the entire team.
Chapter 8, Topic 1
Key Elements of Quality Management
Customer
Satisfaction
Prevention
over
Inspection
Continuous
Improvement
Management
Responsibility
Cost of
Quality
Quality Management
Chapter 8
Plan Quality Management
Process 1 Key Points
 “… identifying quality requirements and/or standards for the project & its deliverables & documenting how the
project will demonstrate compliance with quality requirements and/or standards.”
 Conformance to requirements: Customer Satisfaction & Fitness for use
 Quality vs Grade: It does what you NEED it to do vs people VALUE the product
 Baseline key inputs: Scope/WBS, deliverables, Acceptance Criteria, Cost/approving funding, budget per period,
Schedule/milestone dates
Quality vs. Grade
 Quality: Degree to which a thing fulfills its requirements
 Grade: Way to distinguish items with same use but different quality
requirements
Quality Management
Chapter 8
Plan Quality Management
Process 1
Cost of Quality
Cost of Conformance
Prevention Costs
Designing
quality and
conformanc
e to
require-
ments from
the start
Providing
adequate
training, equip-
ment, and time
to build it right
Appraisal
Costs
Testing and
inspections
Cost of
Nonconformance
Internal
Failure
Costs
Rework and
scrap
External
Failure
Costs
Warranty,
liabilities,
loss of
customers
Source: Adapted from Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Sixth Edition, Project Management
Institute, Inc., 2013, Figure 8-5, Page 283. Material from this publication has been reproduced with the permission of PMI.
Quality Management
Chapter 8Plan Quality Management
Process 1
What expense would be considered a cost of
nonconformance?
A. An action must be corrected because of
incomplete project communication.
B. All components are subjected to rigorous
inspections.
C. Engineers must be trained in a new process.
Discussion Question
Answer: A
A is the result of noncompliance with the project’s
internal communication processes. B and C are both
associated with preventing quality issues from reaching
the customer or from occurring in the first place.
Chapter 8, Topic 2
Quality Management
Chapter 8
Plan Quality Management
Process 1
Key Points
7 Basic Quality Tools:
 Fishbone aka Ishikawa (Cause & Effect Diagram): see all defect causes by categories or see all
requirements & the factors that may cause defects
 Pareto Diagram: sorts frequency of defects in descending order – 80/20 Rule
 Histogram: vertical bar chart of potential problems
 Control Cart: if a process is stable or has predictable performance with upper/lower limits, Heuristic 7
 Scatter Diagram (Correlation charts): compares 2 types of data
 Flowcharts (Process Map): visualize how tasks/phases are interrelated/depend on each other SIPOC
model (supplier, input, process, output, customer)
 Checksheet (Tally Sheet): gathers data of product being tested
Quality Management
Chapter 8
Cause-and-
effect diagram
Ishikawa or
fishbone diagram
5 Whys
Flowchart
Identify inter-
dependencies in
complex processes
Checksheet
Summarize
and categorize
events
Seven Basic Quality Tools
Plan Quality Management
Process 1
Quality Management
Chapter 8
Seven Basic Quality Tools
Plan Quality Management
Process 1
Histogram
Bar chart
Sort and compare
data
Pareto
diagram
80/20 cut
Distinguish the
“vital few” causes
Scatter
diagram
Plot data from
two variables to
detect
associations
Quality Management
Chapter 8
Seven Basic Quality Tools
Plan Quality Management
Process 1
 Plot a series of data points
against specifications to detect if
a process is out of control
– Single data point above or
below control limits
– Rule of 7: 7 consecutive points
above or 7 consecutive points
below the mean
Control Charts
What quality tool is being used?
Needs collected during successive customer
workshops are grouped by type.
A. Scatter diagram
B. Pareto diagram
C. Control chart
D. Histogram
Discussion Question
Answer: D
A histogram can be used to display the relative sizes of
these groups. For example, each group might be
represented by one bar that is subdivided into the top
categories of needs.Chapter 8, Topic 2
Quality management plan
How the team will achieve
its quality objectives
Quality metrics
What will be measured,
target values, tolerances
Project Management Plan
updates
Risk management plan
and scope baseline
Project documents
updates
Lessons learned, risk, and
stakeholder registers and
requirements traceability
matrix
Quality Management
Chapter 8Plan Quality Management
Process 1
Plan Quality Management Outputs
Is this a difference of quality or grade?
Two sun lotions have the same SPF factor, but
one’s protective effects last longer than the other’s.
Discussion Question
Answer: Grade
Both products fulfill the same requirement
to protect against the sun. One may have
additional ingredients that extend its
effectiveness. Chapter 8, Topic 2
Quality Management
Chapter 8
Manage Quality
Process 2
Key Points
 “…. The process of auditing the quality requirements & the results from quality control measurements to ensure
appropriate quality standards are used.”
 Assurance seeks confidence that a future or unfinished output will be completed in a manner to meet requirements
 Unfinished Output = Work in progress
Quality Management
Chapter 8
Manage Quality
Process 2
Affinity
diagram
Sort data before
problem solving
Process decision
program chart
(PDPC)
Identify problem
nodes
Inter-
relationship
digraph
Show cause/
effect
Quality Tools
Quality Management
Chapter 8
Manage Quality
Process 2
Quality Tools
Tree
diagram
Decompose
into
components
Prioritiza-
tion matrix
Assess items
by weighted
criteria
Activity
network
diagram
Sequence
events and
their
relationships
Matrix
diagram
Score items
against
categories
Quality Management
Chapter 8
Manage Quality
Process 2
Quality Tools
Quality Audits
 Structured process to determine conformance
with policies, processes, and procedures
 Could be independent and external
 Uses quality tools
 Results in report
Checklists
 Gather data and verify that specific steps
have been performed.
Design for X
 Follow technical guidelines to control and
improve a product’s final characteristics.
A project manager receives a report with
recommendations from an internal QA department
about changes to team procedures. What should the
project manager do?
A. Disregard the recommendations since they are
internal and will have negative effects.
B. Implement the recommendations since the team is
committed to process improvement.
C. Analyze the impact of the changes on project
baselines.
D. Initiate a change request.
Discussion Question
Answer: C
If possible, the improvements should be made, but the
project manager must first assess their impact so that a
change request can be initiated if necessary.
Chapter 8, Topic 3
Quality Management
Chapter 8
Control Quality
Process 3
Key Points
 “… identifying causes of poor process or product quality & recommending and/or taking action to eliminate them.”
 “Validating that project deliverables meet the stakeholder’s requirements necessary for final acceptance.”
 Defects: Prevention (monitor quality) is ALWAYS better than Inspection (checking deliverables for defects)
 Cost-Benefit Analysis: Decreased Rework vs. Increased Production, Efficiency & Satisfaction
Quality Management
Chapter 8
Key Elements of Quality Management
Customer
Satisfaction
Prevention
over
Inspection
Continuous
Improvement
Management
Responsibility
Cost of
Quality

Contenu connexe

Tendances

Project quality management (1)
Project quality management (1)Project quality management (1)
Project quality management (1)CQU
 
Quality management strategy example
Quality management strategy exampleQuality management strategy example
Quality management strategy exampleselinasimpson1201
 
Ch26 - software engineering 9
Ch26 - software engineering 9Ch26 - software engineering 9
Ch26 - software engineering 9Ian Sommerville
 
9.process improvement chapter 9
9.process improvement chapter 99.process improvement chapter 9
9.process improvement chapter 9Warui Maina
 
The Implementation of QMS in construction industry
The Implementation of QMS in construction industryThe Implementation of QMS in construction industry
The Implementation of QMS in construction industryRaghavendra Rachamadugu
 
Project Health Check
Project Health CheckProject Health Check
Project Health Checkihoudane
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Managementasim78
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project managementselinasimpson1601
 
Quality management templates
Quality management templatesQuality management templates
Quality management templatesselinasimpson371
 
Quality assurance review check list
Quality assurance review check listQuality assurance review check list
Quality assurance review check listzeitgeistr2
 

Tendances (20)

Project managment 7
Project managment  7Project managment  7
Project managment 7
 
Project quality management (1)
Project quality management (1)Project quality management (1)
Project quality management (1)
 
Introduction to CMMI-DEV v1.3 - Day 2
Introduction to CMMI-DEV v1.3  - Day 2Introduction to CMMI-DEV v1.3  - Day 2
Introduction to CMMI-DEV v1.3 - Day 2
 
Quality management strategy example
Quality management strategy exampleQuality management strategy example
Quality management strategy example
 
Ch26 - software engineering 9
Ch26 - software engineering 9Ch26 - software engineering 9
Ch26 - software engineering 9
 
Introduction to CMMI-DEV v1.3 - Day 3
Introduction to CMMI-DEV v1.3  - Day 3Introduction to CMMI-DEV v1.3  - Day 3
Introduction to CMMI-DEV v1.3 - Day 3
 
Testing & Quality Assurance
Testing & Quality AssuranceTesting & Quality Assurance
Testing & Quality Assurance
 
9.process improvement chapter 9
9.process improvement chapter 99.process improvement chapter 9
9.process improvement chapter 9
 
Introduction to CMMI-DEV v1.3 - Day 4
Introduction to CMMI-DEV v1.3  - Day 4Introduction to CMMI-DEV v1.3  - Day 4
Introduction to CMMI-DEV v1.3 - Day 4
 
My MBA Course on Project Quality Management
My MBA Course on Project Quality ManagementMy MBA Course on Project Quality Management
My MBA Course on Project Quality Management
 
The Implementation of QMS in construction industry
The Implementation of QMS in construction industryThe Implementation of QMS in construction industry
The Implementation of QMS in construction industry
 
08 project quality management
08 project quality management08 project quality management
08 project quality management
 
Project Health Check
Project Health CheckProject Health Check
Project Health Check
 
Ch28
Ch28Ch28
Ch28
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Management
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
Quality management templates
Quality management templatesQuality management templates
Quality management templates
 
Quality assurance review check list
Quality assurance review check listQuality assurance review check list
Quality assurance review check list
 
Cmmi (2)
Cmmi (2)Cmmi (2)
Cmmi (2)
 
5. project quality management
5. project quality management5. project quality management
5. project quality management
 

Similaire à PMP Muzette Charles_Spring2019_Week4_Chapter8

Product quality management
Product quality managementProduct quality management
Product quality managementSunil Meena
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8Muzette Charles, PMP
 
Methodologies for quality management
Methodologies for quality managementMethodologies for quality management
Methodologies for quality managementAsamHussain3
 
8.0 Project Quality Management Overview
8.0 Project Quality Management Overview8.0 Project Quality Management Overview
8.0 Project Quality Management OverviewDavidMcLachlan1
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality ManagementSerdar Temiz
 
4S Akademi - QAI - Software Testing Principles and Concepts
4S Akademi - QAI - Software Testing Principles and Concepts4S Akademi - QAI - Software Testing Principles and Concepts
4S Akademi - QAI - Software Testing Principles and ConceptsSerdar Zeybek
 
projectqualitymanagement-140816235544-phpapp02.pptx
projectqualitymanagement-140816235544-phpapp02.pptxprojectqualitymanagement-140816235544-phpapp02.pptx
projectqualitymanagement-140816235544-phpapp02.pptxHamzaKhawar4
 
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaOnline PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaGlobalSkillup
 
Quality management slides
Quality management slidesQuality management slides
Quality management slidesSaba Afaq
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality managementejlp12
 
Topic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfTopic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfHuyNguyen657394
 
08 projectqualitymanagement
08 projectqualitymanagement08 projectqualitymanagement
08 projectqualitymanagementDhamo daran
 

Similaire à PMP Muzette Charles_Spring2019_Week4_Chapter8 (20)

Product quality management
Product quality managementProduct quality management
Product quality management
 
Session 12 4th edition PMP
Session  12 4th edition PMPSession  12 4th edition PMP
Session 12 4th edition PMP
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8
 
8.2 Manage Quality
8.2 Manage Quality8.2 Manage Quality
8.2 Manage Quality
 
Methodologies for quality management
Methodologies for quality managementMethodologies for quality management
Methodologies for quality management
 
8.0 Project Quality Management Overview
8.0 Project Quality Management Overview8.0 Project Quality Management Overview
8.0 Project Quality Management Overview
 
Project quality management
Project quality managementProject quality management
Project quality management
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality Management
 
CAPM Week 3 Chapter 8
CAPM Week 3 Chapter 8CAPM Week 3 Chapter 8
CAPM Week 3 Chapter 8
 
4S Akademi - QAI - Software Testing Principles and Concepts
4S Akademi - QAI - Software Testing Principles and Concepts4S Akademi - QAI - Software Testing Principles and Concepts
4S Akademi - QAI - Software Testing Principles and Concepts
 
Pmb
PmbPmb
Pmb
 
Project quality management
Project quality managementProject quality management
Project quality management
 
projectqualitymanagement-140816235544-phpapp02.pptx
projectqualitymanagement-140816235544-phpapp02.pptxprojectqualitymanagement-140816235544-phpapp02.pptx
projectqualitymanagement-140816235544-phpapp02.pptx
 
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaOnline PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
 
Quality management slides
Quality management slidesQuality management slides
Quality management slides
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality management
 
Topic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfTopic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdf
 
5) PQM.pptx
5) PQM.pptx5) PQM.pptx
5) PQM.pptx
 
Pmp quality chapter 8
Pmp quality chapter 8Pmp quality chapter 8
Pmp quality chapter 8
 
08 projectqualitymanagement
08 projectqualitymanagement08 projectqualitymanagement
08 projectqualitymanagement
 

Plus de Muzette Charles, PMP

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewMuzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderMuzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskMuzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10Muzette Charles, PMP
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3Muzette Charles, PMP
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewMuzette Charles, PMP
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10Muzette Charles, PMP
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2Muzette Charles, PMP
 

Plus de Muzette Charles, PMP (20)

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics Review
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_Review
 
CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
 
CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2
 
CAPM Week 6 Final Review
CAPM Week 6 Final ReviewCAPM Week 6 Final Review
CAPM Week 6 Final Review
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
 
CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12
 
CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11
 
CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10
 
CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9
 

Dernier

Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jisc
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and ModificationsMJDuyan
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxEsquimalt MFRC
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentationcamerronhm
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxCeline George
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxJisc
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfNirmal Dwivedi
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...pradhanghanshyam7136
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structuredhanjurrannsibayan2
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...Nguyen Thanh Tu Collection
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Jisc
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibitjbellavia9
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.MaryamAhmad92
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsKarakKing
 

Dernier (20)

Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 

PMP Muzette Charles_Spring2019_Week4_Chapter8

  • 1. Project Management Professional PMP® Exam Prep – Week 4 Quality Management Prof. Muzette Charles, PMP | mcharles2@pace.edu
  • 2. Quality Management Chapter 8 “… works to ensure the project requirements, including product requirements are met & validated.” • “Project is completed with no deviations from the project requirements.” • Customer satisfaction – project meets the defined customer needs • Continuous improvement: Plan-Do-Check-Act (PDCA) is the basis for quality improvement • Prevention over inspection • Management responsibility Process Process Group Key Deliverables 8.1 Plan Quality Management Planning Quality Management Plan 8.2 Manage Quality Executing Change Requests 8.3 Control Quality Monitoring & Control Validated Changes
  • 3. QA vs. QC Quality Assurance  Process-oriented  Is project being implemented according to plan?  Are project processes as efficient and effective as possible? Quality Control  Deliverable-oriented  Does the deliverable conform to customer- agreed, measurable quality characteristics? Quality Management Chapter 8
  • 4. Quality Pioneers Shewhart Statistical process control (SPC) and control charts Deming Plan, Do, Check, Act (PDCA) model Commitment to continuous improvement as a way to effect organizational transformation Juran Fitness for use—meeting customer’s requirements Cost of quality, Pareto principle, quality trilogy Crosby Conforming to customer needs and preventing defects (zero defects) “Quality is free.” Feigenbaum Total quality management (leadership, use of technology, commitment to customer needs) Ishikawa Seven quality tools and quality circles (worker involvement) Taguchi Focus on designing quality into a product or service Shingo and Ohno Just-in-time (JIT) manufacturing and “lean”—focusing on efficiency and value-producing activity
  • 5. What quality expert championed the concept of continuous improvement as integral to quality management? A. Deming B. Juran C. Crosby D. Feigenbaum Discussion Question Answer: A On the exam, you may be asked to define specific quality theories or identify quality gurus by their ideas. Chapter 8, Topic 1
  • 6. Quality Initiatives in Organizations TQM • Ancestor of many initiatives Six Sigma • Certified “black belt” practitioners • Integration of quality in all business processes ISO • International Organization for Standardization • ISO 9000 series Baldrige • Self-assessment and improvement program • Malcolm Baldrige National Quality Award CMMI • Capability Maturity Model Integration • Software project–oriented
  • 7. How do organizational quality initiatives affect project teams? A. Only indirectly, through operations. B. They may shape project quality processes and objectives. C. They are secondary to PMO processes. D. They affect project managers but not team members. Discussion Question Answer: B Quality initiatives can potentially affect the entire organization, shaping project management processes and affecting the way project success is defined. Most quality initiatives emphasize the involvement of the entire team. Chapter 8, Topic 1
  • 8. Key Elements of Quality Management Customer Satisfaction Prevention over Inspection Continuous Improvement Management Responsibility Cost of Quality
  • 9. Quality Management Chapter 8 Plan Quality Management Process 1 Key Points  “… identifying quality requirements and/or standards for the project & its deliverables & documenting how the project will demonstrate compliance with quality requirements and/or standards.”  Conformance to requirements: Customer Satisfaction & Fitness for use  Quality vs Grade: It does what you NEED it to do vs people VALUE the product  Baseline key inputs: Scope/WBS, deliverables, Acceptance Criteria, Cost/approving funding, budget per period, Schedule/milestone dates
  • 10. Quality vs. Grade  Quality: Degree to which a thing fulfills its requirements  Grade: Way to distinguish items with same use but different quality requirements Quality Management Chapter 8 Plan Quality Management Process 1
  • 11. Cost of Quality Cost of Conformance Prevention Costs Designing quality and conformanc e to require- ments from the start Providing adequate training, equip- ment, and time to build it right Appraisal Costs Testing and inspections Cost of Nonconformance Internal Failure Costs Rework and scrap External Failure Costs Warranty, liabilities, loss of customers Source: Adapted from Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Sixth Edition, Project Management Institute, Inc., 2013, Figure 8-5, Page 283. Material from this publication has been reproduced with the permission of PMI. Quality Management Chapter 8Plan Quality Management Process 1
  • 12. What expense would be considered a cost of nonconformance? A. An action must be corrected because of incomplete project communication. B. All components are subjected to rigorous inspections. C. Engineers must be trained in a new process. Discussion Question Answer: A A is the result of noncompliance with the project’s internal communication processes. B and C are both associated with preventing quality issues from reaching the customer or from occurring in the first place. Chapter 8, Topic 2
  • 13. Quality Management Chapter 8 Plan Quality Management Process 1 Key Points 7 Basic Quality Tools:  Fishbone aka Ishikawa (Cause & Effect Diagram): see all defect causes by categories or see all requirements & the factors that may cause defects  Pareto Diagram: sorts frequency of defects in descending order – 80/20 Rule  Histogram: vertical bar chart of potential problems  Control Cart: if a process is stable or has predictable performance with upper/lower limits, Heuristic 7  Scatter Diagram (Correlation charts): compares 2 types of data  Flowcharts (Process Map): visualize how tasks/phases are interrelated/depend on each other SIPOC model (supplier, input, process, output, customer)  Checksheet (Tally Sheet): gathers data of product being tested
  • 14. Quality Management Chapter 8 Cause-and- effect diagram Ishikawa or fishbone diagram 5 Whys Flowchart Identify inter- dependencies in complex processes Checksheet Summarize and categorize events Seven Basic Quality Tools Plan Quality Management Process 1
  • 15. Quality Management Chapter 8 Seven Basic Quality Tools Plan Quality Management Process 1 Histogram Bar chart Sort and compare data Pareto diagram 80/20 cut Distinguish the “vital few” causes Scatter diagram Plot data from two variables to detect associations
  • 16. Quality Management Chapter 8 Seven Basic Quality Tools Plan Quality Management Process 1  Plot a series of data points against specifications to detect if a process is out of control – Single data point above or below control limits – Rule of 7: 7 consecutive points above or 7 consecutive points below the mean Control Charts
  • 17. What quality tool is being used? Needs collected during successive customer workshops are grouped by type. A. Scatter diagram B. Pareto diagram C. Control chart D. Histogram Discussion Question Answer: D A histogram can be used to display the relative sizes of these groups. For example, each group might be represented by one bar that is subdivided into the top categories of needs.Chapter 8, Topic 2
  • 18. Quality management plan How the team will achieve its quality objectives Quality metrics What will be measured, target values, tolerances Project Management Plan updates Risk management plan and scope baseline Project documents updates Lessons learned, risk, and stakeholder registers and requirements traceability matrix Quality Management Chapter 8Plan Quality Management Process 1 Plan Quality Management Outputs
  • 19. Is this a difference of quality or grade? Two sun lotions have the same SPF factor, but one’s protective effects last longer than the other’s. Discussion Question Answer: Grade Both products fulfill the same requirement to protect against the sun. One may have additional ingredients that extend its effectiveness. Chapter 8, Topic 2
  • 20. Quality Management Chapter 8 Manage Quality Process 2 Key Points  “…. The process of auditing the quality requirements & the results from quality control measurements to ensure appropriate quality standards are used.”  Assurance seeks confidence that a future or unfinished output will be completed in a manner to meet requirements  Unfinished Output = Work in progress
  • 21. Quality Management Chapter 8 Manage Quality Process 2 Affinity diagram Sort data before problem solving Process decision program chart (PDPC) Identify problem nodes Inter- relationship digraph Show cause/ effect Quality Tools
  • 22. Quality Management Chapter 8 Manage Quality Process 2 Quality Tools Tree diagram Decompose into components Prioritiza- tion matrix Assess items by weighted criteria Activity network diagram Sequence events and their relationships Matrix diagram Score items against categories
  • 23. Quality Management Chapter 8 Manage Quality Process 2 Quality Tools Quality Audits  Structured process to determine conformance with policies, processes, and procedures  Could be independent and external  Uses quality tools  Results in report Checklists  Gather data and verify that specific steps have been performed. Design for X  Follow technical guidelines to control and improve a product’s final characteristics.
  • 24. A project manager receives a report with recommendations from an internal QA department about changes to team procedures. What should the project manager do? A. Disregard the recommendations since they are internal and will have negative effects. B. Implement the recommendations since the team is committed to process improvement. C. Analyze the impact of the changes on project baselines. D. Initiate a change request. Discussion Question Answer: C If possible, the improvements should be made, but the project manager must first assess their impact so that a change request can be initiated if necessary. Chapter 8, Topic 3
  • 25. Quality Management Chapter 8 Control Quality Process 3 Key Points  “… identifying causes of poor process or product quality & recommending and/or taking action to eliminate them.”  “Validating that project deliverables meet the stakeholder’s requirements necessary for final acceptance.”  Defects: Prevention (monitor quality) is ALWAYS better than Inspection (checking deliverables for defects)  Cost-Benefit Analysis: Decreased Rework vs. Increased Production, Efficiency & Satisfaction
  • 27. Key Elements of Quality Management Customer Satisfaction Prevention over Inspection Continuous Improvement Management Responsibility Cost of Quality