SlideShare une entreprise Scribd logo
1  sur  64
FOCUS ON THIS
You will be rewarded
PROCUREMENT
STRATEGIES
Methods of Procurements
PROCUREMENT
The process of acquiring a building
(You)
(Contractor)
The Procurement Triangle
Feasibility
Design
Tendering
Construction
Operation
Tendering
Fixed Price Contract
Traditional Procurement
Fixed Price Contract
■ Firm Price Contract
■ Based on complete Bills of Quantities
■ Quantities + Unit Rates
■ Complete design is needed before Contract can be formed
Fixed Price Contract
Advantages
■ Clear picture of
commitments
■ Unit rates provide a basis
for valuation of variations
What is a Variation?
■ PAM Contract 2006 Clause 11.1:
– Addition, Omission, or Substitution of any Work;
– Alteration of the kind/standard of any materials or goods
used in the Works;
– Removal of any works/materials from the Site
– Changes to:
■ Working hours
■ Working space
■ Access/Utilisation of the Site
■ Execution of works in a specific order
Fixed Price Contract
Advantages
■ Clear picture of
commitments
■ Unit rates provide a basis
for valuation of variations
■ Detailed breakdown of
tender sum
Disadvantages
■ Time needed for
preparation of a complete
BoQ
■ Large amount of
variations to be
processed
Contract Sum
■ PAM Contract 2006 Article 2
■ PAM Contract 2006 Clause 13.1:
“The Contract Sum shall not be adjusted or altered in any
way whatsoever, other than in accordance with the express
provisions of the Contract…”
Why Fixed Price Contract?
■ There is sufficient time to prepare complete designs +
measure accurate quantities
■ Client’s total commitment must be known (to make borrowing
arrangements)
The Procurement Triangle
Fixed Price Contract
Traditional Procurement
Remeasurement
Contract
Remeasurement Contract
■ Based on Approximate Bills of Quantities
■ Also called ‘Measurement Contract’
■ Quantities are not exact (Subject to ‘Remeasurement’)
■ Works may commence before design is completed
Remeasurement Contract
Advantages
■ Construction process
begins earlier
■ Lower cost and time
during preparation of
BoQ
Disadvantages
■ Less certainty of the
extent of commitment
■ Remeasurements incur
extra costs
■ Design-related decisions
may not need to be made
prematurely
Why Remeasurement
Contract?
■ Complete design is available but insufficient time for the
measurement of quantities
■ Design can not be completed soon enough for taking off to be
done
■ A BoQ is desired without the cost in terms of time and money
(therefore BoAQ)
BoQ vs BoAQ
Bills of Quantities
■ Accurately measured
quantities
■ Establishes a firm cost
■ Small amount of
Provisional Sums
Bills of Approximate
Quantities
■ Can be prepared earlier
■ Large amount of
Provisional Sums
The Procurement Triangle
Fixed Price Contract
Traditional Procurement
Drawings and
Specifications
Remeasurement
Contract
Drawings & Specifications
■ Based on Drawings and Full Specifications (No BoQ)
■ Schedule of Rates
■ Bill of Quantities is not provided
■ Works may commence before design is completed
Drawings & Specifications
Advantages
■ Construction process
begins earlier
■ Lower cost and time
during pre-tender stage
Disadvantages
■ No breakdown of tender
sum provided
■ No reference for the
valuation of variations
Why Drawings &
Specifications?
■ The project is fairly small and simple in nature (School, public
restrooms, etc.)
The Procurement Triangle
Fixed Price Contract
Traditional Procurement
Cost
Reimbursement
Contract
Drawing and
Specifications
Remeasurement
Contract
Cost Reimbursement
■ The most UNCERTAIN contract type
■ No contract sum, difficult to estimate final cost
■ Only used if Time > Cost
■ No on-site measurement necessary
Cost Reimbursement
Advantages
■ Construction process
begins earlier
■ Lower cost and time
during preparation of
BoQ
Disadvantages
■ Least certainty of the
extent of commitment
■ Likely greater
construction costs
■ Verification of cost
incurred is tedious
Why Cost Reimbursement?
■ Cost < Time
■ Client is willing to pay a higher cost to a trusted contractor
■ Emergency cases such as repairing a damaged structure
Types of Cost Reimbursement
Cost + Percentage Fee
Cost + Fixed Fee
Target Cost
Cost Plus Percentage Fee
■ Contractor is paid a fee equal to an agreed percentage of
prime costs
■ To cover overhead and profit
■ Disadvantage (to client):
Inefficient contractor’s
operations
Resources
waste
Fee paid to
contractor
Example
$ $
Total prime cost
(Labor, plant and
materials)
50000
15% addition for
overheads
7500
5% addition for profit 2500 10000
Total cost of contract 60000
20%
Cost Plus Percentage Fee
■ Due to uneconomic organization of contract, inefficiency and
excessive waste
$
Total prime cost 55000
20% addition for overheads and profit 11000
Total cost of contract 66000
Profits
Disincentive to
contractor to work
efficiently
Prime cost
Cost Plus Fixed Fee
■ The fee paid to contractor is a fixed sum (irrespective of prime
cost).
■ As contractor’s profit
■ Lower fee in percentage terms if prime cost is higher
$ $
Total prime cost 55000
Overheads 7500 10000
Profit 2500
Total cost of
contract
65000
Target Cost
(Cost + Fluctuating Fee)
• Act as an incentive to reduce total prime cost
• Provides for a bonus to be paid to contractor ( total cost <
‘target’ )
• A penalty if total cost > agreed sum
ProfitTotal prime cost
Example: Penalty
$
Total prime cost 55000
Fixed fee 10000
65000
Deduct penalty, being 50% of
excess
Over $60000 -2500
Amount of final payment 62500
Example: Bonus
$
Total prime cost 48000
Fixed fee 10000
58000
Add bonus, being 50% of saving
Over $60000 +1000
Amount of final payment 59000
The Procurement Triangle
RISKS ALLOCATION
Client vs Contractor
Risks Allocation
■ The Contractor takes the risks that his anticipated profit will be
reduced or converted into a loss as a result of the outworking of
the conditions under which the contract is carried out
■ The Employer takes the risk that he will become liable for a
greater total cost when initianting the project
■ Generally speaking, the contractor’s risk increases as the
Employer’s risk reduces and vice versa
Drawings & Specifications
■ Contractor bears a high degree of risk
Reasons:
1) It is a lump sum contract, he must estimate his expected costs as
accurately as possible ( any adverse mistake will reduce his profit )
2) No bill of quantities provided for tendering purposes
Drawings & Specifications
■ Employer’s risk is small
Reasons:
1) He knows at the outset what his financial liability will be
2) He is under no contractual obligation to reimburse the contractor for
any errors
Cost Reimbusement
■ The Contractor’s risk is reduced because he is paid his full
costs and a fee in addition
■ However, Employer bears the risk of the prime cost becoming
much higher than estimated ( owing to an inefficient site agent
or to wastage of resources )
Risks Allocation
DESIGN AND BUILD
PROCUREMENT
A procurement route where the main contractor is appointed to design
and construct the works
Design and Build
 Contractor accept responsibility for some or all of the designs
 Client’s requirements are stated briefly and simply
 Offers certainty on contract sum and brings cost benefits
 Construction works can start early
Design and Build
■ Advantages
 Reduce the need to commit resources and time
 Price certainty is obtained before construction commences
 Overlap of design and construction activities reduce project
time
 Constructability improves
Design and Build
■ Disadvantages
 Difficulties experienced by client in preparing brief
 Client changes to project scope is expensive
 Difficulty in comparing bids since different designs
 Client need to commit to a concept design at early stage and
before detailed designs are completed
 Design liability is limited to the standard contracts available
Variations of Design & Build
I. Direct
- No competition is obtained in tenders
- Some appraisals of possible competitors may be made
II. Competitive
- Tenders are obtained from documents prepared
- Enabling contractors to offer in designs and prices
Variations of Design & Build
III. Develop and construct
- Consultants design the building to a partial stage ( ‘scope
design’ )
- Contractor develop and complete the design, and
construct the building
IV. Package deal
- When the contactors competing use significant part of
building system/ they will be constructing different theme
- Eg. Offer to find site/ sell, mortgage or lease products
Variations of Design & Build
V. Novation
- Refer to a design, novate and construct
- Contractors take over from client a previous contract for
design work, completes the design and constructs the
works.
Why Design & Build?
 Building is simple and functional
 Brief for scope design is likely to change
 Programme can be accelerated by overlapping design and
construction activities
 Single point of responsibility (Contractor)
The Procurement Triangle
MANAGEMENT FEE
PROCUREMENT
Management Contracting vs Construction Management
Management Fee
■ Based upon client employing a professional team to advise him on
design and cost issues & management consultant to advise on and
supervise the construction aspects of the project
■ Construction work is broken down into individual packages and let
out to sub-contractors
Management Fee
■ There are 2 main variations of management fee approach
Management
Contracting
Construction
Management
Management Contracting
■ Management contractor does none of the construction work
■ He provides construction management service on a fee basis as part
of the client’s management team
■ He provides and maintains all the necessary site facilities and
dealing with labour-related matters
Management Contracting
Advantages
• Work can begin on site as
soon as works packages
have been designed
• Reduce time requirement,
earlier return on client’s
investment
• Contractor is able to identify
with client’s needs and
interests
Disadvantages
• Uncertainty to the final cost
of project
• No. of variations & amount of
re-measurement required >
traditional contracts
Construction Management
■ Similar to management contracting
■ Construction manager is responsible for the organization and
planning of the construction work on site
■ Construction work is carried out by a number of contractors, each
contractor is responsible for a defined trade package
Construction Management
Advantages
• Close liaison between the
construction manager and
design manager
• Trade packages being let as
the design of each is
completed, thus shortening
the project time
• Privity of contract between
client and each of the trade
contractors
Disadvantages
• Client has one more
consultant and a number of
contractors to deal instead
of only one main contractor
• Client’s financial
commitment is uncertain
until the last of the works
contracts has been signed
Construction Management >
Management Contracting
■ In construction management the trade contractors contract directly
with the client whereas in management contracting all the works
contractors are in a direct contractual relationship with the
management contractor
■ Although construction management causes the client much more
administration and possibly a greater level of risk by contacting
directly with the trade contractors
■ It is claimed that the closer arrangement and involvement of the
client with the trade contractor is generally beneficial to the building
process
The Procurement Triangle
YOU CAN CHILL NOW
And thank you for your attention :D

Contenu connexe

Tendances

Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in MalaysiaDayat Mohamad
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-completeYong Sy
 
Contract - Construction Contracts and Specification
Contract - Construction Contracts and SpecificationContract - Construction Contracts and Specification
Contract - Construction Contracts and SpecificationMANNU KUMAR
 
Contract Conditions
Contract ConditionsContract Conditions
Contract ConditionsDr K M SONI
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contractsKheng Hoe Advocates
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Kipcon Inc.
 
An introduction to taking off building quantities
An introduction to taking off building quantities An introduction to taking off building quantities
An introduction to taking off building quantities Arshad Mohanut
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Felix Vong
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentationTimun Loh
 

Tendances (20)

Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
ACH 231 Lecture 07 (Contract Documents) Part 1
ACH 231 Lecture 07 (Contract Documents) Part 1ACH 231 Lecture 07 (Contract Documents) Part 1
ACH 231 Lecture 07 (Contract Documents) Part 1
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
 
Contract - Construction Contracts and Specification
Contract - Construction Contracts and SpecificationContract - Construction Contracts and Specification
Contract - Construction Contracts and Specification
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Contracts
ContractsContracts
Contracts
 
PP1 report
PP1 reportPP1 report
PP1 report
 
Contracts
ContractsContracts
Contracts
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Retention fund
Retention fundRetention fund
Retention fund
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Procurement system
Procurement systemProcurement system
Procurement system
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
 
An introduction to taking off building quantities
An introduction to taking off building quantities An introduction to taking off building quantities
An introduction to taking off building quantities
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 

Similaire à FOCUS ON PROCUREMENT STRATEGIES

PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction CostingManish Kandpal
 
Construction Work Schedule Proposal PowerPoint Presentation Slides
Construction Work Schedule Proposal PowerPoint Presentation SlidesConstruction Work Schedule Proposal PowerPoint Presentation Slides
Construction Work Schedule Proposal PowerPoint Presentation SlidesSlideTeam
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionWaleed Liaqat
 
Cost effective construction and green building
Cost effective construction and green buildingCost effective construction and green building
Cost effective construction and green buildingManjunath N V
 
M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3Project Controls Expo
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview WorkshopRae Davies
 
Construction Bid Proposal Template PowerPoint Presentation Slides
Construction Bid Proposal Template PowerPoint Presentation SlidesConstruction Bid Proposal Template PowerPoint Presentation Slides
Construction Bid Proposal Template PowerPoint Presentation SlidesSlideTeam
 
Rev207 matrixexcelfile
Rev207 matrixexcelfileRev207 matrixexcelfile
Rev207 matrixexcelfilejbonvier
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contractsAnil Kumar(6)
 

Similaire à FOCUS ON PROCUREMENT STRATEGIES (20)

Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction Costing
 
Construction Work Schedule Proposal PowerPoint Presentation Slides
Construction Work Schedule Proposal PowerPoint Presentation SlidesConstruction Work Schedule Proposal PowerPoint Presentation Slides
Construction Work Schedule Proposal PowerPoint Presentation Slides
 
contract procedure
contract procedurecontract procedure
contract procedure
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
Final pp1
Final pp1Final pp1
Final pp1
 
EstimatesPresentation.pptx
EstimatesPresentation.pptxEstimatesPresentation.pptx
EstimatesPresentation.pptx
 
Cost effective construction and green building
Cost effective construction and green buildingCost effective construction and green building
Cost effective construction and green building
 
M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview Workshop
 
Lecture 1.pptx
Lecture 1.pptxLecture 1.pptx
Lecture 1.pptx
 
Construction Bid Proposal Template PowerPoint Presentation Slides
Construction Bid Proposal Template PowerPoint Presentation SlidesConstruction Bid Proposal Template PowerPoint Presentation Slides
Construction Bid Proposal Template PowerPoint Presentation Slides
 
Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)
 
Rev207 matrixexcelfile
Rev207 matrixexcelfileRev207 matrixexcelfile
Rev207 matrixexcelfile
 
CV-Sounder
CV-SounderCV-Sounder
CV-Sounder
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 

Plus de Pang Khai Shuen

Value Management Assignment (Report)
Value Management Assignment (Report)Value Management Assignment (Report)
Value Management Assignment (Report)Pang Khai Shuen
 
Value Management Assignment (Slides)
Value Management Assignment (Slides)Value Management Assignment (Slides)
Value Management Assignment (Slides)Pang Khai Shuen
 
Project Management and Development Economics Project (Slides)
Project Management and Development Economics Project (Slides)Project Management and Development Economics Project (Slides)
Project Management and Development Economics Project (Slides)Pang Khai Shuen
 
Project Management and Development Economics Project (DE)
Project Management and Development Economics Project (DE)Project Management and Development Economics Project (DE)
Project Management and Development Economics Project (DE)Pang Khai Shuen
 
Project Management and Development Economics Project (PM)
Project Management and Development Economics Project (PM)Project Management and Development Economics Project (PM)
Project Management and Development Economics Project (PM)Pang Khai Shuen
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityPang Khai Shuen
 
Construction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of ContractConstruction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of ContractPang Khai Shuen
 
BE benchmark project cost allocation
BE benchmark project cost allocationBE benchmark project cost allocation
BE benchmark project cost allocationPang Khai Shuen
 
BE Assignment brief aug 17
BE Assignment brief aug 17BE Assignment brief aug 17
BE Assignment brief aug 17Pang Khai Shuen
 
CSI Personal reflective journal
CSI Personal reflective journalCSI Personal reflective journal
CSI Personal reflective journalPang Khai Shuen
 
Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708Pang Khai Shuen
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides Pang Khai Shuen
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 

Plus de Pang Khai Shuen (20)

Value Management Assignment (Report)
Value Management Assignment (Report)Value Management Assignment (Report)
Value Management Assignment (Report)
 
Value Management Assignment (Slides)
Value Management Assignment (Slides)Value Management Assignment (Slides)
Value Management Assignment (Slides)
 
Project Management and Development Economics Project (Slides)
Project Management and Development Economics Project (Slides)Project Management and Development Economics Project (Slides)
Project Management and Development Economics Project (Slides)
 
Project Management and Development Economics Project (DE)
Project Management and Development Economics Project (DE)Project Management and Development Economics Project (DE)
Project Management and Development Economics Project (DE)
 
Project Management and Development Economics Project (PM)
Project Management and Development Economics Project (PM)Project Management and Development Economics Project (PM)
Project Management and Development Economics Project (PM)
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's University
 
Construction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of ContractConstruction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of Contract
 
BE Slides updated
 BE Slides updated BE Slides updated
BE Slides updated
 
BE Presentation Slides
BE Presentation SlidesBE Presentation Slides
BE Presentation Slides
 
BE COST APPRAISAL
BE COST APPRAISALBE COST APPRAISAL
BE COST APPRAISAL
 
BE benchmark project cost allocation
BE benchmark project cost allocationBE benchmark project cost allocation
BE benchmark project cost allocation
 
BE Compiled
BE Compiled BE Compiled
BE Compiled
 
BE Assignment brief aug 17
BE Assignment brief aug 17BE Assignment brief aug 17
BE Assignment brief aug 17
 
CSI Personal reflective journal
CSI Personal reflective journalCSI Personal reflective journal
CSI Personal reflective journal
 
pp2 Final account-1
pp2 Final account-1pp2 Final account-1
pp2 Final account-1
 
Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
 
M4 presentation slides
M4 presentation slidesM4 presentation slides
M4 presentation slides
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 

Dernier

Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...Sapna Thakur
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 

Dernier (20)

Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 

FOCUS ON PROCUREMENT STRATEGIES

  • 1. FOCUS ON THIS You will be rewarded
  • 3. PROCUREMENT The process of acquiring a building
  • 9. Fixed Price Contract ■ Firm Price Contract ■ Based on complete Bills of Quantities ■ Quantities + Unit Rates ■ Complete design is needed before Contract can be formed
  • 10. Fixed Price Contract Advantages ■ Clear picture of commitments ■ Unit rates provide a basis for valuation of variations
  • 11. What is a Variation? ■ PAM Contract 2006 Clause 11.1: – Addition, Omission, or Substitution of any Work; – Alteration of the kind/standard of any materials or goods used in the Works; – Removal of any works/materials from the Site – Changes to: ■ Working hours ■ Working space ■ Access/Utilisation of the Site ■ Execution of works in a specific order
  • 12. Fixed Price Contract Advantages ■ Clear picture of commitments ■ Unit rates provide a basis for valuation of variations ■ Detailed breakdown of tender sum Disadvantages ■ Time needed for preparation of a complete BoQ ■ Large amount of variations to be processed
  • 13. Contract Sum ■ PAM Contract 2006 Article 2 ■ PAM Contract 2006 Clause 13.1: “The Contract Sum shall not be adjusted or altered in any way whatsoever, other than in accordance with the express provisions of the Contract…”
  • 14. Why Fixed Price Contract? ■ There is sufficient time to prepare complete designs + measure accurate quantities ■ Client’s total commitment must be known (to make borrowing arrangements)
  • 16. Fixed Price Contract Traditional Procurement Remeasurement Contract
  • 17. Remeasurement Contract ■ Based on Approximate Bills of Quantities ■ Also called ‘Measurement Contract’ ■ Quantities are not exact (Subject to ‘Remeasurement’) ■ Works may commence before design is completed
  • 18. Remeasurement Contract Advantages ■ Construction process begins earlier ■ Lower cost and time during preparation of BoQ Disadvantages ■ Less certainty of the extent of commitment ■ Remeasurements incur extra costs ■ Design-related decisions may not need to be made prematurely
  • 19. Why Remeasurement Contract? ■ Complete design is available but insufficient time for the measurement of quantities ■ Design can not be completed soon enough for taking off to be done ■ A BoQ is desired without the cost in terms of time and money (therefore BoAQ)
  • 20. BoQ vs BoAQ Bills of Quantities ■ Accurately measured quantities ■ Establishes a firm cost ■ Small amount of Provisional Sums Bills of Approximate Quantities ■ Can be prepared earlier ■ Large amount of Provisional Sums
  • 22. Fixed Price Contract Traditional Procurement Drawings and Specifications Remeasurement Contract
  • 23. Drawings & Specifications ■ Based on Drawings and Full Specifications (No BoQ) ■ Schedule of Rates ■ Bill of Quantities is not provided ■ Works may commence before design is completed
  • 24. Drawings & Specifications Advantages ■ Construction process begins earlier ■ Lower cost and time during pre-tender stage Disadvantages ■ No breakdown of tender sum provided ■ No reference for the valuation of variations
  • 25. Why Drawings & Specifications? ■ The project is fairly small and simple in nature (School, public restrooms, etc.)
  • 27. Fixed Price Contract Traditional Procurement Cost Reimbursement Contract Drawing and Specifications Remeasurement Contract
  • 28. Cost Reimbursement ■ The most UNCERTAIN contract type ■ No contract sum, difficult to estimate final cost ■ Only used if Time > Cost ■ No on-site measurement necessary
  • 29. Cost Reimbursement Advantages ■ Construction process begins earlier ■ Lower cost and time during preparation of BoQ Disadvantages ■ Least certainty of the extent of commitment ■ Likely greater construction costs ■ Verification of cost incurred is tedious
  • 30. Why Cost Reimbursement? ■ Cost < Time ■ Client is willing to pay a higher cost to a trusted contractor ■ Emergency cases such as repairing a damaged structure
  • 31. Types of Cost Reimbursement Cost + Percentage Fee Cost + Fixed Fee Target Cost
  • 32. Cost Plus Percentage Fee ■ Contractor is paid a fee equal to an agreed percentage of prime costs ■ To cover overhead and profit ■ Disadvantage (to client): Inefficient contractor’s operations Resources waste Fee paid to contractor
  • 33. Example $ $ Total prime cost (Labor, plant and materials) 50000 15% addition for overheads 7500 5% addition for profit 2500 10000 Total cost of contract 60000 20%
  • 34. Cost Plus Percentage Fee ■ Due to uneconomic organization of contract, inefficiency and excessive waste $ Total prime cost 55000 20% addition for overheads and profit 11000 Total cost of contract 66000 Profits Disincentive to contractor to work efficiently Prime cost
  • 35. Cost Plus Fixed Fee ■ The fee paid to contractor is a fixed sum (irrespective of prime cost). ■ As contractor’s profit ■ Lower fee in percentage terms if prime cost is higher $ $ Total prime cost 55000 Overheads 7500 10000 Profit 2500 Total cost of contract 65000
  • 36. Target Cost (Cost + Fluctuating Fee) • Act as an incentive to reduce total prime cost • Provides for a bonus to be paid to contractor ( total cost < ‘target’ ) • A penalty if total cost > agreed sum ProfitTotal prime cost
  • 37. Example: Penalty $ Total prime cost 55000 Fixed fee 10000 65000 Deduct penalty, being 50% of excess Over $60000 -2500 Amount of final payment 62500
  • 38. Example: Bonus $ Total prime cost 48000 Fixed fee 10000 58000 Add bonus, being 50% of saving Over $60000 +1000 Amount of final payment 59000
  • 41. Risks Allocation ■ The Contractor takes the risks that his anticipated profit will be reduced or converted into a loss as a result of the outworking of the conditions under which the contract is carried out ■ The Employer takes the risk that he will become liable for a greater total cost when initianting the project ■ Generally speaking, the contractor’s risk increases as the Employer’s risk reduces and vice versa
  • 42. Drawings & Specifications ■ Contractor bears a high degree of risk Reasons: 1) It is a lump sum contract, he must estimate his expected costs as accurately as possible ( any adverse mistake will reduce his profit ) 2) No bill of quantities provided for tendering purposes
  • 43. Drawings & Specifications ■ Employer’s risk is small Reasons: 1) He knows at the outset what his financial liability will be 2) He is under no contractual obligation to reimburse the contractor for any errors
  • 44. Cost Reimbusement ■ The Contractor’s risk is reduced because he is paid his full costs and a fee in addition ■ However, Employer bears the risk of the prime cost becoming much higher than estimated ( owing to an inefficient site agent or to wastage of resources )
  • 46. DESIGN AND BUILD PROCUREMENT A procurement route where the main contractor is appointed to design and construct the works
  • 47. Design and Build  Contractor accept responsibility for some or all of the designs  Client’s requirements are stated briefly and simply  Offers certainty on contract sum and brings cost benefits  Construction works can start early
  • 48. Design and Build ■ Advantages  Reduce the need to commit resources and time  Price certainty is obtained before construction commences  Overlap of design and construction activities reduce project time  Constructability improves
  • 49. Design and Build ■ Disadvantages  Difficulties experienced by client in preparing brief  Client changes to project scope is expensive  Difficulty in comparing bids since different designs  Client need to commit to a concept design at early stage and before detailed designs are completed  Design liability is limited to the standard contracts available
  • 50. Variations of Design & Build I. Direct - No competition is obtained in tenders - Some appraisals of possible competitors may be made II. Competitive - Tenders are obtained from documents prepared - Enabling contractors to offer in designs and prices
  • 51. Variations of Design & Build III. Develop and construct - Consultants design the building to a partial stage ( ‘scope design’ ) - Contractor develop and complete the design, and construct the building IV. Package deal - When the contactors competing use significant part of building system/ they will be constructing different theme - Eg. Offer to find site/ sell, mortgage or lease products
  • 52. Variations of Design & Build V. Novation - Refer to a design, novate and construct - Contractors take over from client a previous contract for design work, completes the design and constructs the works.
  • 53. Why Design & Build?  Building is simple and functional  Brief for scope design is likely to change  Programme can be accelerated by overlapping design and construction activities  Single point of responsibility (Contractor)
  • 56. Management Fee ■ Based upon client employing a professional team to advise him on design and cost issues & management consultant to advise on and supervise the construction aspects of the project ■ Construction work is broken down into individual packages and let out to sub-contractors
  • 57. Management Fee ■ There are 2 main variations of management fee approach Management Contracting Construction Management
  • 58. Management Contracting ■ Management contractor does none of the construction work ■ He provides construction management service on a fee basis as part of the client’s management team ■ He provides and maintains all the necessary site facilities and dealing with labour-related matters
  • 59. Management Contracting Advantages • Work can begin on site as soon as works packages have been designed • Reduce time requirement, earlier return on client’s investment • Contractor is able to identify with client’s needs and interests Disadvantages • Uncertainty to the final cost of project • No. of variations & amount of re-measurement required > traditional contracts
  • 60. Construction Management ■ Similar to management contracting ■ Construction manager is responsible for the organization and planning of the construction work on site ■ Construction work is carried out by a number of contractors, each contractor is responsible for a defined trade package
  • 61. Construction Management Advantages • Close liaison between the construction manager and design manager • Trade packages being let as the design of each is completed, thus shortening the project time • Privity of contract between client and each of the trade contractors Disadvantages • Client has one more consultant and a number of contractors to deal instead of only one main contractor • Client’s financial commitment is uncertain until the last of the works contracts has been signed
  • 62. Construction Management > Management Contracting ■ In construction management the trade contractors contract directly with the client whereas in management contracting all the works contractors are in a direct contractual relationship with the management contractor ■ Although construction management causes the client much more administration and possibly a greater level of risk by contacting directly with the trade contractors ■ It is claimed that the closer arrangement and involvement of the client with the trade contractor is generally beneficial to the building process
  • 64. YOU CAN CHILL NOW And thank you for your attention :D