SlideShare une entreprise Scribd logo
1  sur  47
Télécharger pour lire hors ligne
Earthing
IEEE 80 2000IEEE 80 2000
A Review
safety thru design 1
Essentials of Earthing DesignEssentials of Earthing Design
Crossection Area Current Density Dangerous 
Potentials
Resistance
The Crossection of Continuous Step potential Horizontal Plane
F
The Crossection of 
the conductor to 
be sufficient for 
carrying GRID
Continuous 
surface current 
density
Step potential Horizontal Plane 
Touch potential Vertical Plane
O
R
carrying GRID
fault current
Instantaneous
Surface current
Mesh Potential Mutual resistance
G
O
Surface current 
density
GPR
T
T
Transfer PotentialE
N
safety thru design 2
PASS PASS PASSPASS OK
Crossection areaCrossection area
• Equation 37 of IEEE 80 2000
• This formulae is good for above ground 
conductorconductor
• Enthalpy of vaporization decreases with 
increase in temperature.
• For a large grid the fault current getsFor a large grid the fault current gets 
multiple parallel paths hence Tm 
doesn’t pose a problem.
• If the Tm is allowed to rise beyond a y
limit in smaller grids or pits the water 
molecules beyond a point water 
instantaneously vaporizes and escapes 
from the soil surrounding theC d
Heat of  Heat of  from the soil surrounding the 
conductor.
• Tm also applies to surface layer coating 
or cover.
Compound
At 1000C
vaporization
(kJ mol‐1)
vaporization
(kJ kg−1)
Water 40.65 2257 or cover.
safety thru design 3
Evaluation of CrossectionEvaluation of Crossection
M h i l El t i lMechanical Electrical
Tm 1510 99
T 20 20Ta 20 20
TCAP 3.28 3.28
tc 1 0.3c
αr 0.0016 0.0016
ρr 15.9 15.9
I 25 25
K0 605 605
A 199 41 349 54A 199.41 349.54
safety thru design 4
Surface current density as per BS7340 
clause 15
If surface current densities are not maintained, junction 
between  electrode and soil, will heat up above 
1000C failing the electrode or grid
Long term surface Currents Short Term surface currents
1000C failing the electrode or grid.
g
• Long term Surface current 
densit is 40A/m2
• Given by the formula 
1000*Sqrt(57 7/(ρ*t))density is 40A/m2
• Independent of soil 
resistivity
1000*Sqrt(57.7/(ρ*t))
• Dependent on soil resistivity 
and time of clearance ofresistivity and time of clearance of 
fault
safety thru design 5
Long term Surface Current DensityLong term Surface Current Density
Th l t f t tl t th• The long term surface currents are seen mostly at the 
following points
– Neutral pitsp
– Harmonic filters
– PT’s and CT’s etc…
• The surface area of few electrodes are as follows• The surface area of few electrodes are as follows
– 600X600 mm plate     =0.72 m2 Capacity= 28.8 A
– 1000X1000 mm plate = 2.0  m2 Capacity= 80.0 Ap p y
– 40mm 3m length pipe=0.37m2 Capacity= 14.5 A
• If the unbalance current in a large system is 68A, the 2Nos. 
Of 600X600mm plate will be insufficient Heat will beOf 600X600mm plate will be insufficient. Heat will be 
generated in the neutral pit and it will deteriorate. We may 
need larger plate size, or the 3rd plate.
safety thru design 6
Short Term Surface Current DensityShort Term Surface Current Density
I h id f ll• In case the grid parameters are as follows:
– 15m X 12m grid, with 3m spacing
147 t 30 d i d d t– 147mt 30mm rod is used as conductor
– The surface area of the conductor thus is 13.85m2
If the soil resistivity is 100 Ωm and clearing time is 0 3sec– If the soil resistivity is 100 Ωm and clearing time is 0.3sec 
the max IG the grid can handle is only 1387A/m2.
– Hence the maximum possible fault current the grid can p g
handle in 13.85m2 is 19KA.
• If the fault current IG is more than 19 KA then the grid 
will fail, as the temperature around the conductor will 
rise and steam the water.
safety thru design 7
Symbol unit Value
Fault Current  IG KA 23000 Input
Diameter of electrode d m 0.04 Input
Length of Electrode
Soil ls m 37 Input
l 1 IWater lw m 1 Input
Resistivity
Soil ρs Ωm 360 Input
Water ρ Ωm 2 InputWater ρw Ωm 2 Input
Resistance
Soil Rs Ω 12.25394 Equation 55 IEEE 80 2000
Water R Ω 1 368891 Equation 55 IEEE 80 2000Water Rw Ω 1.368891 Equation 55 IEEE 80 2000
Combined Rc Ω 1.231338
Permissible Current Density
Soil σ A/m2 730.9304 Clause 15.2 BS7340σs A/m 730.9304 Clause 15.2 BS7340
Water σw A/m2 9806.46 Clause 15.2 BS7341
Area
Soil As m2 4.6472 πdlss s
Water Aw m2 0.1256 πdlw
Current Division Resistance Capacity Design
Soil 2311.1568 3396.779785 1
Water 20688.843 1231.691433 17
safety thru design 8
Polar Curve for Single PointPolar Curve for Single Point
safety thru design 9
Polar curve
•Resistivity taken in min 8 
directions
•Angular distance between 
readings 450
C ti l I t l t th•Cautiously Interpolate the 
readings  to 7.50
•Join the Points to form a 
polar curvepolar curve
•Calculate the area of the 
polar curve
•Draw equivalent Circular q
area
•Radius of the circle is the 
average soil resistivity
h h d l l•This method is particularly 
beneficial when the 
resistivity varies significantly 
in different directions
safety thru design 10
Variation in Resistivity in horizontal 
plane
safety thru design 11
3D Plot of Soil Resistivity3D Plot of Soil Resistivity
safety thru design 12
Equal Earth Conductor SpacingEqual Earth Conductor Spacing 
EARTHING LAYOUT EVALUATION Grid1 Grid 2 Grid3 Grid4 Total Values
Real Soil resistivity σs 724.25 724.25 724.25 724.25
Soil resistivity after TEREC+ Application σ 307.81 307.81 307.81 307.81y pp
Soil resistivity of washed 0.025  to 0.050m in gravel σs 5000.00 5000.00 5000.00 5000.00
Length of the earth mat Lx 125.00 175.00 175.00 25.00 200.00
Breadth of the earth mat Ly 75.00 100.00 50.00 150.00 150.00
Assumed spacing for the conductors D 5.50 5.50 5.50 5.50
Area of earth mat AG 9375.00 8125.00 8125.00 4375.00 30000.00
Permissible step voltage Estep 4019.71 4019.71 4019.71 4019.71
E step Es 1341.19 1390.38 1210.15 1168.07
Permissible touch voltage Etouch 1127 96 1127 96 1127 96 1127 96Permissible touch voltage Etouch 1127.96 1127.96 1127.96 1127.96
Emesh Em 1051.41 1116.88 1016.25 1126.61
Total quantity of conductors laid Lc 3602.74 3134.82 3134.82 1723.20 11595.58
Grid Resistance (Schwarz) Rg 1.33 1.39 1.43 1.90 0.37
safety thru design 13
Variable Earth conductor SpacingVariable Earth conductor Spacing
EARTHING LAYOUT EVALUATION G id1 G id 2 G id3 G id4 T t l V lEARTHING LAYOUT EVALUATION Grid1 Grid 2 Grid3 Grid4 Total Values
Real Soil resistivity σs 535.00 679.00 744.00 939.00
Soil resistivity after TEREC+ Application σ 227 38 288 58 316 20 399 08Soil resistivity after TEREC+ Application σ 227.38 288.58 316.20 399.08
Soil resistivity of washed 0.025  to 
0.050m in gravel
σs 5000.00 5000.00 5000.00 5000.00
Length of the earth mat Lx 125.00 175.00 175.00 25.00 200.00
Breadth of the earth mat Ly 75.00 100.00 50.00 150.00 150.00
A d i f th d t D 6 10 5 70 6 20 5 80 5 95Assumed spacing for the conductors D 6.10 5.70 6.20 5.80 5.95
Area of earth mat AG 9375.00 8125.00 8125.00 4375.00 30000
Permissible step voltage Estep 4001.44 4015.34 4021.61 4040.44
E step Es 1254.24 1319.35 1131.73 1108.32
Permissible touch voltage Etouch 1123.40 1126.87 1128.44 1133.15
Emesh Em 1115 98 1107 60 1091 72 1131 89
safety thru design 14
Emesh Em 1115.98 1107.60 1091.72 1131.89
Total quantity of conductors laid Lc 3267.42 3031.15 2801.25 1640.91 10740.73
Grid Resistance (Schwarz) Rg 0.99 1.31 1.49 2.49 0.35
ComparisonComparison
S C G id i bl G idSI.No. Constant Grid Variable Grid
Conductor Length 11595 m 10740 m
Difference in Mesh 110 V 40 VDifference in Mesh 
Potential
110 V 40 V
Difference in Step
Potential
222 V 180 V
Potential
Grid Resistance 0.37 0.35
Economics 94 Lcs 82 Lcs
Variable grid may be Techno commercially more Viable compared to an equal spacing grid
safety thru design 15
Variation in ResistivityVariation in Resistivity
safety thru design 16
IEEE 80 2000 Clause 14 5 dIEEE 80 2000 Clause 14.5 d
safety thru design 17
TEREC+TEREC+
safety thru design 18
Practical ApplicationPractical Application
safety thru design 19
CPRI Stability ReportCPRI Stability Report
safety thru design 20
NABL Certified LABNABL Certified LAB
safety thru design 21
Formulae to Calculate ResistanceFormulae to Calculate Resistance
f l t thi• for plate earthing
R = (ρ/4)* sqrt(π/2A) 
• for pipe earthingfor pipe earthing
R = (ρ/2πL)* [ln(8L/d)‐1]
• for strip earthing
R=(ρ/PπL)* [ln(2L2 /(wh))+ Q]
• for grid earthing
R ρ[(1/L )+ (1/sqrt(20A) (1+ (1/1+h) sqrt(20A)R=ρ[(1/LT)+ (1/sqrt(20A) (1+ (1/1+h) sqrt(20A)
Is Material of the grid important for achieving resistance?Is Material of the grid important for achieving resistance?
No. If corrosion factor is taken care of
safety thru design 22
Relook at Alternating CurrentRelook at Alternating Current
C i f• Current is not movement of 
charge or holes. 
• In Alternating Current theIn Alternating Current, the 
charge actually does not 
travel at all. It only vibrates 
i i i iin its mean position. 
• Across a Cross section area, 
the vibration begins withthe vibration begins with 
one charge and increases to 
the maximum number of 
h i if icharges signifying 
amplitude of the sinusoidal 
AC waveform.
safety thru design 23
Relook at Alternating TensionRelook at Alternating Tension
• The extent of movement 
of the charge from the 
iti i d tmean position is due to a 
prevailing Tension (similar 
to force) exerted duringto force) exerted during 
positive or negative cycle.
• More tension creates• More tension creates 
greater displacement of 
the particle from thethe particle from the 
Crossection surface. 
safety thru design 24
Relook at Alternating EnergyRelook at Alternating Energy
• It is the ENERGY that is• It is the ENERGY that is 
transferred thru vibrating charges 
across a Crossection to the next 
adjoining Crossection. j g
• Current is the movement of the 
disturbance and not the charge. 
The Energy transferred is 
lproportional to 
• the number charges vibrating, 
• the displacement of the charges 
f h i i dfrom the mean position and 
• the number of vibrations per 
second
Thi i f d h• This energy is transferred thru 
series and parallel circuits to 
obtain desired results
safety thru design 25
EarthEarth
E th i h ith• Earth is a huge mass with 
enormous amount of 
charges. 
• Energy is applied to earth, 
spreads, the displacement 
of charge from the mean g
position progressively 
reduces. 
• Finally the displacement orFinally the displacement or 
tension becomes 
infinitesimal. In normal 
condition charges in EARTHcondition charges in EARTH 
appear stable with hardly 
any tension. 
safety thru design 26
LightningLightning
safety thru design 27
Attachment to opposite fieldAttachment to opposite field
safety thru design 28
What is LPSWhat is LPS
safety thru design 29
Selection of LPSSelection of LPS
3KV        11KV            45KV
safety thru design 30
safety thru design 31
Resistivity and PermittivityResistivity and Permittivity
safety thru design 32
Tackling Different FrequenciesTackling Different Frequencies
f d d• Dissipation of  energy depends on 
Earth loop impedance.
• High frequency signals encounter g q y g
high inductive impedance if the 
loop length is long. Hence the 
Ground path needs to be as shortGround path needs to be as short 
as physically possible.
• As ground is a dielectric, it is also 
d h l l d fgood to have a plate electrode for 
higher displacement current.
• Higher frequencies do not enter g q
deep earth, hence it is imperative 
to have more number of shallow 
earthearth
• Use Earth Bond
safety thru design 33
Revisit your Earth GridRevisit your Earth Grid
D h th E th id d d b t• Do you have the Earth grid drg. and subsequent 
record of changes conducted in your premises
• Is Earth pit reading in the grid different at• Is Earth pit reading in the grid different at 
different places
• Has the Source increased• Has the Source  increased
• Has number of feeders or distributors changed
A U b l d H i b i ti f• Are Unbalances and Harmonics been existing for 
a long time.
• Is off schedule maintenance a regular feature• Is off schedule maintenance a regular feature
• GET YOUR SELF AUDITED
safety thru design 34
Who can be an AuditorWho can be an Auditor
• H i K l d f• Having Knowledge of 
– IEEE 80 2000 for substation
– IEEE 665 1995 for Generating Station
– IEEE 142 1991 for Industrial establishment
f h– IEEE 81 1993 for Earthing Measurements
– IEEE 1100 for powering and grounding electronic equipments.
– IEEE 575 for sheath bonding and induced voltages
– BS 7340 1998 Code of practice for Earthing
IEC 62305 P t 1 t P t 4– IEC 62305 Part 1 to Part 4
– NFPA 70 and NFPA 780
– API RP 2003 for statics and lightning protection
– And many more ref. texts
H i R i it i t t h k it l t i t• Having Requisite equipments to check vital parameters using stray 
current filters.
• Has the desired National and International Experience to Audit
Refineries– Refineries
– Power Stations etc.
• Should be a Solution providerp
safety thru design 35
Rejuvenation of Live gridRejuvenation of Live grid
safety thru design 36
Rejuvenation of live gridRejuvenation of live grid
• Measure the soil resistivity with• Measure the soil resistivity with
– Stray current filter
– Variable frequency
High and low current injection probe– High and low current injection probe
• Make polar graph for accurate soil resistivity
• Design the earth grid as per IEEE 80 2000 as if it was for the new grid
Th f f iti th it b l 1 7% f th f• The surface area of exiting earth pit may be only 1‐7% of the surface area 
of the entire Earth grid.
• May involve multiple layer/tier of peripheral correction. 
U i li d t i d t k li d t ti• Use specialized manpower trained to work on live yard or station
• New trenching can be very tedious. It may cut across existing HV, LV or 
control cables
At th d f ti All th th it h ld h l t• At the end of correction,  All the earth pits should have almost same 
resistance value without any pit correction
safety thru design 37
Tier EarthTier Earth
safety thru design 38
Proper and Permanent JointingProper and Permanent  Jointing 
safety thru design 39
Electrode Resistance
safety thru design 40
Sigma EarthSigma Earth
•The  Energy after leaving the  electrode encounters  different 
k d f l h fl f lkinds of soil where reflection factor comes into play
•Sigma earth ensures that  artificial treatment compounds are 
laid in a specific  geometric pattern to minimize the reflection
•Thru proper calculation, can achieve less than 1 ohm in veryThru proper calculation, can achieve less than 1 ohm in very 
hard soil.
•Used for Independent Electronic Earth  or reference earth 
safety thru design 41
Iris earthIris earth
• One earth sensor is put inside an old• One earth sensor is put inside an old 
or new pit.
• Various parameters like date, 
location, value etc are logged in every 
sensor.
• The sensor is programmed to alarm 
on few criteria’s.
• There is multiple level of alarm• There is multiple level of alarm.
• A peripheral command center (PCC) 
can talk to approximately 100 earth 
pits.
• A hand held tester is provided to 
check the earth pit conditions 
remotely
• The PCC can be locally connected to a• The PCC can be locally connected to a 
local Laptop and a remote Server on 
LAN or GSM.
safety thru design 42
Geomagnetic Storms caused by Solar 
Flares or CME
• Earth’s magnetic field being
pushed out of the way by the
nuclear explosion or solar storm
f ffollowed by the field being restored
to its natural place.
•This process can produce geo‐
magnetically induced currents in
long electrical conductors (like
power lines) which can damage or
d l fdestroy power line transformers.
safety thru design 43
Nasa warns solar flares 'huge 
space storm'cause devastation
• According to VERY rough• According to VERY rough 
calculations, that solar flare was 
approximately 250,640 km tall, 
and 342,050 km wide. ,
• To put that in perspective, the 
Earth is about 12,756 km in 
diameter. That means it was 
b h ll dabout 19.6 Earths tall and 27 
Earths wide.
• In a new warning, Nasa said the 
super storm nearing 2013 wouldsuper storm nearing 2013 would 
hit like “a bolt of lightning” and 
could cause catastrophic 
consequences for the world’s 
• March 1989 (Quebec)
– 480nT/min, Knocked out power 
to 6 million people in 92 seconds
• May 1921q
health, emergency services and 
national security unless 
precautions are taken
– Up to 4,800nT/min
• Sept. 1859 (Carrington event)
– 2,000 to 5,000nT/min
• NOW 2013‐2023
safety thru design 44
NOW 2013 2023
– Expected 5000nT/min
What will happen to our GridsWhat will happen to our Grids
• All long transmission lines, 
Railway lines, Pipelines will 
withstand the impact of GICwithstand the impact of GIC
• Incorporation of 
– Neutral
• Resistors
• Capacitors with shunt 
switch
– Series Capacitors
safety thru design 45
Operational SolutionOperational Solution
• Build command and control centre to receive satellite data in to 
initiate requisite action. We have approximately 60 ‐90 min to 
initiate and complete operational procedures including discharginginitiate and complete operational procedures including discharging
• Break down the power system into small islands and earth the 
surge created using automated star point switch connections and 
disconnections.
• Creating an efficient maintenance free and monitorable earthing 
systemsystem
• Predicting static accumulations, and BMS enabled lightning 
protection systemp y
• The entire infrastructure needs to be grounded as much as 'possible 
without forming Earth loops
It is Either Now Or Never
WE ARE RESPONSIBLE
It is Either Now Or Never
safety thru design 47

Contenu connexe

Tendances

Good grounding practices
Good grounding practicesGood grounding practices
Good grounding practicesNarinder Singh
 
Earthing Arrangements
Earthing  ArrangementsEarthing  Arrangements
Earthing ArrangementsPaul Holden
 
NAPS Tank Grounding Lightning and Static Protection
NAPS Tank Grounding Lightning and Static ProtectionNAPS Tank Grounding Lightning and Static Protection
NAPS Tank Grounding Lightning and Static ProtectionRobert Sammons - FSE
 
Substation Earthing Design
Substation Earthing DesignSubstation Earthing Design
Substation Earthing DesignIOSRJEEE
 
Protection against overvoltages
Protection against overvoltagesProtection against overvoltages
Protection against overvoltagesMaryam Nawaz
 
Earth Resistance Calculation
Earth Resistance CalculationEarth Resistance Calculation
Earth Resistance Calculationabdullah ali
 
Basics of earthing
Basics of earthingBasics of earthing
Basics of earthingAsif Eqbal
 
Substation lightning protection and earthing standard(august 2019)
Substation lightning protection and earthing standard(august 2019)Substation lightning protection and earthing standard(august 2019)
Substation lightning protection and earthing standard(august 2019)Mahesh Chandra Manav
 
Protection Devices and the Lightning
Protection Devices and the LightningProtection Devices and the Lightning
Protection Devices and the LightningAmeen San
 
**Lightning Arrester Presentation**
**Lightning Arrester Presentation****Lightning Arrester Presentation**
**Lightning Arrester Presentation**SKPAMB
 
Vignettes in Grounding
Vignettes in GroundingVignettes in Grounding
Vignettes in Groundingmichaeljmack
 
Electrical Earthing and types
Electrical Earthing and typesElectrical Earthing and types
Electrical Earthing and typesManjunath Kh
 
Lightning protection and ground solutions for wireless networks
Lightning protection and ground solutions for wireless networksLightning protection and ground solutions for wireless networks
Lightning protection and ground solutions for wireless networksComms Connect
 
Grounding, neutral & earthing
Grounding, neutral & earthingGrounding, neutral & earthing
Grounding, neutral & earthingEngr Muhammad Imran
 
Tiga Earth Mat Presentation
Tiga Earth Mat Presentation Tiga Earth Mat Presentation
Tiga Earth Mat Presentation SOURAV GHOSH
 
Lightning, Surge Protection & Earthing of Electrical & Electronic Systems in ...
Lightning, Surge Protection & Earthing of Electrical & Electronic Systems in ...Lightning, Surge Protection & Earthing of Electrical & Electronic Systems in ...
Lightning, Surge Protection & Earthing of Electrical & Electronic Systems in ...Living Online
 

Tendances (20)

Good grounding practices
Good grounding practicesGood grounding practices
Good grounding practices
 
Earthing Arrangements
Earthing  ArrangementsEarthing  Arrangements
Earthing Arrangements
 
Earthing system
Earthing system   Earthing system
Earthing system
 
NAPS Tank Grounding Lightning and Static Protection
NAPS Tank Grounding Lightning and Static ProtectionNAPS Tank Grounding Lightning and Static Protection
NAPS Tank Grounding Lightning and Static Protection
 
Substation Earthing Design
Substation Earthing DesignSubstation Earthing Design
Substation Earthing Design
 
Protection against overvoltages
Protection against overvoltagesProtection against overvoltages
Protection against overvoltages
 
Earth Resistance Calculation
Earth Resistance CalculationEarth Resistance Calculation
Earth Resistance Calculation
 
earth mat design for metro station
earth mat design for metro stationearth mat design for metro station
earth mat design for metro station
 
Basics of earthing
Basics of earthingBasics of earthing
Basics of earthing
 
Substation lightning protection and earthing standard(august 2019)
Substation lightning protection and earthing standard(august 2019)Substation lightning protection and earthing standard(august 2019)
Substation lightning protection and earthing standard(august 2019)
 
Protection Devices and the Lightning
Protection Devices and the LightningProtection Devices and the Lightning
Protection Devices and the Lightning
 
**Lightning Arrester Presentation**
**Lightning Arrester Presentation****Lightning Arrester Presentation**
**Lightning Arrester Presentation**
 
Earthing
EarthingEarthing
Earthing
 
Earthing
EarthingEarthing
Earthing
 
Vignettes in Grounding
Vignettes in GroundingVignettes in Grounding
Vignettes in Grounding
 
Electrical Earthing and types
Electrical Earthing and typesElectrical Earthing and types
Electrical Earthing and types
 
Lightning protection and ground solutions for wireless networks
Lightning protection and ground solutions for wireless networksLightning protection and ground solutions for wireless networks
Lightning protection and ground solutions for wireless networks
 
Grounding, neutral & earthing
Grounding, neutral & earthingGrounding, neutral & earthing
Grounding, neutral & earthing
 
Tiga Earth Mat Presentation
Tiga Earth Mat Presentation Tiga Earth Mat Presentation
Tiga Earth Mat Presentation
 
Lightning, Surge Protection & Earthing of Electrical & Electronic Systems in ...
Lightning, Surge Protection & Earthing of Electrical & Electronic Systems in ...Lightning, Surge Protection & Earthing of Electrical & Electronic Systems in ...
Lightning, Surge Protection & Earthing of Electrical & Electronic Systems in ...
 

En vedette

Erico Eritech Lightning Protection - IEC62305 Earthing Design Guide
Erico Eritech Lightning Protection - IEC62305 Earthing Design GuideErico Eritech Lightning Protection - IEC62305 Earthing Design Guide
Erico Eritech Lightning Protection - IEC62305 Earthing Design GuideThorne & Derrick International
 
Example kitchen ventilation calculation
Example kitchen ventilation calculationExample kitchen ventilation calculation
Example kitchen ventilation calculationwilliammana
 
Guide to Surge Protection Devices
Guide to Surge Protection DevicesGuide to Surge Protection Devices
Guide to Surge Protection DevicesJason Koffler
 
Earthing in electrical network
Earthing in electrical networkEarthing in electrical network
Earthing in electrical networkBHAGWAN PRASAD
 
Stone columns - an overview(Ground improvement)
Stone columns -  an overview(Ground improvement)Stone columns -  an overview(Ground improvement)
Stone columns - an overview(Ground improvement)Tarachand Veeragattapu
 
Electrical earthing
Electrical earthingElectrical earthing
Electrical earthingDenuka
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systemsBiswajit Pratihari
 

En vedette (9)

Erico Eritech Lightning Protection - IEC62305 Earthing Design Guide
Erico Eritech Lightning Protection - IEC62305 Earthing Design GuideErico Eritech Lightning Protection - IEC62305 Earthing Design Guide
Erico Eritech Lightning Protection - IEC62305 Earthing Design Guide
 
Example kitchen ventilation calculation
Example kitchen ventilation calculationExample kitchen ventilation calculation
Example kitchen ventilation calculation
 
Guide to Surge Protection Devices
Guide to Surge Protection DevicesGuide to Surge Protection Devices
Guide to Surge Protection Devices
 
Earth MAT design for Metro Station
Earth MAT design for Metro StationEarth MAT design for Metro Station
Earth MAT design for Metro Station
 
Kitchen Exhaust India
Kitchen Exhaust IndiaKitchen Exhaust India
Kitchen Exhaust India
 
Earthing in electrical network
Earthing in electrical networkEarthing in electrical network
Earthing in electrical network
 
Stone columns - an overview(Ground improvement)
Stone columns -  an overview(Ground improvement)Stone columns -  an overview(Ground improvement)
Stone columns - an overview(Ground improvement)
 
Electrical earthing
Electrical earthingElectrical earthing
Electrical earthing
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systems
 

Similaire à Tce presentation

Grounding System Analysis
Grounding System AnalysisGrounding System Analysis
Grounding System Analysisijtsrd
 
Bsf earthing system calculation-1
Bsf earthing system calculation-1Bsf earthing system calculation-1
Bsf earthing system calculation-1Raymund Cortez
 
transmission line
transmission line transmission line
transmission line singh1515
 
MOS Process and Single Stage Amplifiers.pptx
MOS Process and Single Stage Amplifiers.pptxMOS Process and Single Stage Amplifiers.pptx
MOS Process and Single Stage Amplifiers.pptxPrateek718260
 
Transmission Line presentation______.ppt
Transmission Line presentation______.pptTransmission Line presentation______.ppt
Transmission Line presentation______.pptssuserc3b807
 
Design of Grounding System for Substation
Design of Grounding System for SubstationDesign of Grounding System for Substation
Design of Grounding System for Substationijtsrd
 
Performance Analysis of Actual Step and Mesh Voltage of Substation Grounding ...
Performance Analysis of Actual Step and Mesh Voltage of Substation Grounding ...Performance Analysis of Actual Step and Mesh Voltage of Substation Grounding ...
Performance Analysis of Actual Step and Mesh Voltage of Substation Grounding ...Editor IJCATR
 
Analysis of transient enclosure voltages in gis (emtp simulation studies)
Analysis of transient enclosure voltages in gis (emtp simulation studies)Analysis of transient enclosure voltages in gis (emtp simulation studies)
Analysis of transient enclosure voltages in gis (emtp simulation studies)eSAT Journals
 
Analysis of transient enclosure voltages in gis (emtp simulation studies)
Analysis of transient enclosure voltages in gis (emtp simulation studies)Analysis of transient enclosure voltages in gis (emtp simulation studies)
Analysis of transient enclosure voltages in gis (emtp simulation studies)eSAT Publishing House
 
Geotechnical information and its application to ground resistance calculations
Geotechnical information and its application to ground resistance calculationsGeotechnical information and its application to ground resistance calculations
Geotechnical information and its application to ground resistance calculationsDavid Nowicki, PE, P Eng.
 
Original Mosfet IRF1404 1404 202A 40V TO-220 New IR
Original Mosfet IRF1404 1404 202A 40V TO-220 New IROriginal Mosfet IRF1404 1404 202A 40V TO-220 New IR
Original Mosfet IRF1404 1404 202A 40V TO-220 New IRAUTHELECTRONIC
 
2102311_Electrical_Measurement_and_Instr.pdf
2102311_Electrical_Measurement_and_Instr.pdf2102311_Electrical_Measurement_and_Instr.pdf
2102311_Electrical_Measurement_and_Instr.pdfabdallahbarakat663
 
Design of transformer and chock coil
Design of transformer and chock coilDesign of transformer and chock coil
Design of transformer and chock coilShubham Champaneri
 
Grounding and bonding testing
Grounding and bonding testingGrounding and bonding testing
Grounding and bonding testingmichaeljmack
 
High Speed Amplifiers Part 2
High Speed Amplifiers Part 2High Speed Amplifiers Part 2
High Speed Amplifiers Part 2Premier Farnell
 

Similaire à Tce presentation (20)

Grounding System Analysis
Grounding System AnalysisGrounding System Analysis
Grounding System Analysis
 
Bsf earthing system calculation-1
Bsf earthing system calculation-1Bsf earthing system calculation-1
Bsf earthing system calculation-1
 
Akt tl design01
Akt tl design01Akt tl design01
Akt tl design01
 
transmission line
transmission line transmission line
transmission line
 
Hi speed board design for signal integrity and emc- intro-2021 by shlomi zigdon
Hi speed board design for signal integrity and emc- intro-2021 by shlomi zigdonHi speed board design for signal integrity and emc- intro-2021 by shlomi zigdon
Hi speed board design for signal integrity and emc- intro-2021 by shlomi zigdon
 
MOS Process and Single Stage Amplifiers.pptx
MOS Process and Single Stage Amplifiers.pptxMOS Process and Single Stage Amplifiers.pptx
MOS Process and Single Stage Amplifiers.pptx
 
ملزمة
ملزمةملزمة
ملزمة
 
Transmission Line presentation______.ppt
Transmission Line presentation______.pptTransmission Line presentation______.ppt
Transmission Line presentation______.ppt
 
10.1.1.192.9435(1)
10.1.1.192.9435(1)10.1.1.192.9435(1)
10.1.1.192.9435(1)
 
Design of Grounding System for Substation
Design of Grounding System for SubstationDesign of Grounding System for Substation
Design of Grounding System for Substation
 
AC and DC BridgePPT for engineering students
AC and DC BridgePPT for engineering studentsAC and DC BridgePPT for engineering students
AC and DC BridgePPT for engineering students
 
Performance Analysis of Actual Step and Mesh Voltage of Substation Grounding ...
Performance Analysis of Actual Step and Mesh Voltage of Substation Grounding ...Performance Analysis of Actual Step and Mesh Voltage of Substation Grounding ...
Performance Analysis of Actual Step and Mesh Voltage of Substation Grounding ...
 
Analysis of transient enclosure voltages in gis (emtp simulation studies)
Analysis of transient enclosure voltages in gis (emtp simulation studies)Analysis of transient enclosure voltages in gis (emtp simulation studies)
Analysis of transient enclosure voltages in gis (emtp simulation studies)
 
Analysis of transient enclosure voltages in gis (emtp simulation studies)
Analysis of transient enclosure voltages in gis (emtp simulation studies)Analysis of transient enclosure voltages in gis (emtp simulation studies)
Analysis of transient enclosure voltages in gis (emtp simulation studies)
 
Geotechnical information and its application to ground resistance calculations
Geotechnical information and its application to ground resistance calculationsGeotechnical information and its application to ground resistance calculations
Geotechnical information and its application to ground resistance calculations
 
Original Mosfet IRF1404 1404 202A 40V TO-220 New IR
Original Mosfet IRF1404 1404 202A 40V TO-220 New IROriginal Mosfet IRF1404 1404 202A 40V TO-220 New IR
Original Mosfet IRF1404 1404 202A 40V TO-220 New IR
 
2102311_Electrical_Measurement_and_Instr.pdf
2102311_Electrical_Measurement_and_Instr.pdf2102311_Electrical_Measurement_and_Instr.pdf
2102311_Electrical_Measurement_and_Instr.pdf
 
Design of transformer and chock coil
Design of transformer and chock coilDesign of transformer and chock coil
Design of transformer and chock coil
 
Grounding and bonding testing
Grounding and bonding testingGrounding and bonding testing
Grounding and bonding testing
 
High Speed Amplifiers Part 2
High Speed Amplifiers Part 2High Speed Amplifiers Part 2
High Speed Amplifiers Part 2
 

Dernier

Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)wesley chun
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slidespraypatel2
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CVKhem
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessPixlogix Infotech
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsJoaquim Jorge
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 

Dernier (20)

Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your Business
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 

Tce presentation

  • 2. Essentials of Earthing DesignEssentials of Earthing Design Crossection Area Current Density Dangerous  Potentials Resistance The Crossection of Continuous Step potential Horizontal Plane F The Crossection of  the conductor to  be sufficient for  carrying GRID Continuous  surface current  density Step potential Horizontal Plane  Touch potential Vertical Plane O R carrying GRID fault current Instantaneous Surface current Mesh Potential Mutual resistance G O Surface current  density GPR T T Transfer PotentialE N safety thru design 2 PASS PASS PASSPASS OK
  • 3. Crossection areaCrossection area • Equation 37 of IEEE 80 2000 • This formulae is good for above ground  conductorconductor • Enthalpy of vaporization decreases with  increase in temperature. • For a large grid the fault current getsFor a large grid the fault current gets  multiple parallel paths hence Tm  doesn’t pose a problem. • If the Tm is allowed to rise beyond a y limit in smaller grids or pits the water  molecules beyond a point water  instantaneously vaporizes and escapes  from the soil surrounding theC d Heat of  Heat of  from the soil surrounding the  conductor. • Tm also applies to surface layer coating  or cover. Compound At 1000C vaporization (kJ mol‐1) vaporization (kJ kg−1) Water 40.65 2257 or cover. safety thru design 3
  • 4. Evaluation of CrossectionEvaluation of Crossection M h i l El t i lMechanical Electrical Tm 1510 99 T 20 20Ta 20 20 TCAP 3.28 3.28 tc 1 0.3c αr 0.0016 0.0016 ρr 15.9 15.9 I 25 25 K0 605 605 A 199 41 349 54A 199.41 349.54 safety thru design 4
  • 5. Surface current density as per BS7340  clause 15 If surface current densities are not maintained, junction  between  electrode and soil, will heat up above  1000C failing the electrode or grid Long term surface Currents Short Term surface currents 1000C failing the electrode or grid. g • Long term Surface current  densit is 40A/m2 • Given by the formula  1000*Sqrt(57 7/(ρ*t))density is 40A/m2 • Independent of soil  resistivity 1000*Sqrt(57.7/(ρ*t)) • Dependent on soil resistivity  and time of clearance ofresistivity and time of clearance of  fault safety thru design 5
  • 6. Long term Surface Current DensityLong term Surface Current Density Th l t f t tl t th• The long term surface currents are seen mostly at the  following points – Neutral pitsp – Harmonic filters – PT’s and CT’s etc… • The surface area of few electrodes are as follows• The surface area of few electrodes are as follows – 600X600 mm plate     =0.72 m2 Capacity= 28.8 A – 1000X1000 mm plate = 2.0  m2 Capacity= 80.0 Ap p y – 40mm 3m length pipe=0.37m2 Capacity= 14.5 A • If the unbalance current in a large system is 68A, the 2Nos.  Of 600X600mm plate will be insufficient Heat will beOf 600X600mm plate will be insufficient. Heat will be  generated in the neutral pit and it will deteriorate. We may  need larger plate size, or the 3rd plate. safety thru design 6
  • 7. Short Term Surface Current DensityShort Term Surface Current Density I h id f ll• In case the grid parameters are as follows: – 15m X 12m grid, with 3m spacing 147 t 30 d i d d t– 147mt 30mm rod is used as conductor – The surface area of the conductor thus is 13.85m2 If the soil resistivity is 100 Ωm and clearing time is 0 3sec– If the soil resistivity is 100 Ωm and clearing time is 0.3sec  the max IG the grid can handle is only 1387A/m2. – Hence the maximum possible fault current the grid can p g handle in 13.85m2 is 19KA. • If the fault current IG is more than 19 KA then the grid  will fail, as the temperature around the conductor will  rise and steam the water. safety thru design 7
  • 8. Symbol unit Value Fault Current  IG KA 23000 Input Diameter of electrode d m 0.04 Input Length of Electrode Soil ls m 37 Input l 1 IWater lw m 1 Input Resistivity Soil ρs Ωm 360 Input Water ρ Ωm 2 InputWater ρw Ωm 2 Input Resistance Soil Rs Ω 12.25394 Equation 55 IEEE 80 2000 Water R Ω 1 368891 Equation 55 IEEE 80 2000Water Rw Ω 1.368891 Equation 55 IEEE 80 2000 Combined Rc Ω 1.231338 Permissible Current Density Soil σ A/m2 730.9304 Clause 15.2 BS7340σs A/m 730.9304 Clause 15.2 BS7340 Water σw A/m2 9806.46 Clause 15.2 BS7341 Area Soil As m2 4.6472 πdlss s Water Aw m2 0.1256 πdlw Current Division Resistance Capacity Design Soil 2311.1568 3396.779785 1 Water 20688.843 1231.691433 17 safety thru design 8
  • 9. Polar Curve for Single PointPolar Curve for Single Point safety thru design 9
  • 10. Polar curve •Resistivity taken in min 8  directions •Angular distance between  readings 450 C ti l I t l t th•Cautiously Interpolate the  readings  to 7.50 •Join the Points to form a  polar curvepolar curve •Calculate the area of the  polar curve •Draw equivalent Circular q area •Radius of the circle is the  average soil resistivity h h d l l•This method is particularly  beneficial when the  resistivity varies significantly  in different directions safety thru design 10
  • 12. 3D Plot of Soil Resistivity3D Plot of Soil Resistivity safety thru design 12
  • 13. Equal Earth Conductor SpacingEqual Earth Conductor Spacing  EARTHING LAYOUT EVALUATION Grid1 Grid 2 Grid3 Grid4 Total Values Real Soil resistivity σs 724.25 724.25 724.25 724.25 Soil resistivity after TEREC+ Application σ 307.81 307.81 307.81 307.81y pp Soil resistivity of washed 0.025  to 0.050m in gravel σs 5000.00 5000.00 5000.00 5000.00 Length of the earth mat Lx 125.00 175.00 175.00 25.00 200.00 Breadth of the earth mat Ly 75.00 100.00 50.00 150.00 150.00 Assumed spacing for the conductors D 5.50 5.50 5.50 5.50 Area of earth mat AG 9375.00 8125.00 8125.00 4375.00 30000.00 Permissible step voltage Estep 4019.71 4019.71 4019.71 4019.71 E step Es 1341.19 1390.38 1210.15 1168.07 Permissible touch voltage Etouch 1127 96 1127 96 1127 96 1127 96Permissible touch voltage Etouch 1127.96 1127.96 1127.96 1127.96 Emesh Em 1051.41 1116.88 1016.25 1126.61 Total quantity of conductors laid Lc 3602.74 3134.82 3134.82 1723.20 11595.58 Grid Resistance (Schwarz) Rg 1.33 1.39 1.43 1.90 0.37 safety thru design 13
  • 14. Variable Earth conductor SpacingVariable Earth conductor Spacing EARTHING LAYOUT EVALUATION G id1 G id 2 G id3 G id4 T t l V lEARTHING LAYOUT EVALUATION Grid1 Grid 2 Grid3 Grid4 Total Values Real Soil resistivity σs 535.00 679.00 744.00 939.00 Soil resistivity after TEREC+ Application σ 227 38 288 58 316 20 399 08Soil resistivity after TEREC+ Application σ 227.38 288.58 316.20 399.08 Soil resistivity of washed 0.025  to  0.050m in gravel σs 5000.00 5000.00 5000.00 5000.00 Length of the earth mat Lx 125.00 175.00 175.00 25.00 200.00 Breadth of the earth mat Ly 75.00 100.00 50.00 150.00 150.00 A d i f th d t D 6 10 5 70 6 20 5 80 5 95Assumed spacing for the conductors D 6.10 5.70 6.20 5.80 5.95 Area of earth mat AG 9375.00 8125.00 8125.00 4375.00 30000 Permissible step voltage Estep 4001.44 4015.34 4021.61 4040.44 E step Es 1254.24 1319.35 1131.73 1108.32 Permissible touch voltage Etouch 1123.40 1126.87 1128.44 1133.15 Emesh Em 1115 98 1107 60 1091 72 1131 89 safety thru design 14 Emesh Em 1115.98 1107.60 1091.72 1131.89 Total quantity of conductors laid Lc 3267.42 3031.15 2801.25 1640.91 10740.73 Grid Resistance (Schwarz) Rg 0.99 1.31 1.49 2.49 0.35
  • 15. ComparisonComparison S C G id i bl G idSI.No. Constant Grid Variable Grid Conductor Length 11595 m 10740 m Difference in Mesh 110 V 40 VDifference in Mesh  Potential 110 V 40 V Difference in Step Potential 222 V 180 V Potential Grid Resistance 0.37 0.35 Economics 94 Lcs 82 Lcs Variable grid may be Techno commercially more Viable compared to an equal spacing grid safety thru design 15
  • 17. IEEE 80 2000 Clause 14 5 dIEEE 80 2000 Clause 14.5 d safety thru design 17
  • 22. Formulae to Calculate ResistanceFormulae to Calculate Resistance f l t thi• for plate earthing R = (ρ/4)* sqrt(π/2A)  • for pipe earthingfor pipe earthing R = (ρ/2πL)* [ln(8L/d)‐1] • for strip earthing R=(ρ/PπL)* [ln(2L2 /(wh))+ Q] • for grid earthing R ρ[(1/L )+ (1/sqrt(20A) (1+ (1/1+h) sqrt(20A)R=ρ[(1/LT)+ (1/sqrt(20A) (1+ (1/1+h) sqrt(20A) Is Material of the grid important for achieving resistance?Is Material of the grid important for achieving resistance? No. If corrosion factor is taken care of safety thru design 22
  • 23. Relook at Alternating CurrentRelook at Alternating Current C i f• Current is not movement of  charge or holes.  • In Alternating Current theIn Alternating Current, the  charge actually does not  travel at all. It only vibrates  i i i iin its mean position.  • Across a Cross section area,  the vibration begins withthe vibration begins with  one charge and increases to  the maximum number of  h i if icharges signifying  amplitude of the sinusoidal  AC waveform. safety thru design 23
  • 24. Relook at Alternating TensionRelook at Alternating Tension • The extent of movement  of the charge from the  iti i d tmean position is due to a  prevailing Tension (similar  to force) exerted duringto force) exerted during  positive or negative cycle. • More tension creates• More tension creates  greater displacement of  the particle from thethe particle from the  Crossection surface.  safety thru design 24
  • 25. Relook at Alternating EnergyRelook at Alternating Energy • It is the ENERGY that is• It is the ENERGY that is  transferred thru vibrating charges  across a Crossection to the next  adjoining Crossection. j g • Current is the movement of the  disturbance and not the charge.  The Energy transferred is  lproportional to  • the number charges vibrating,  • the displacement of the charges  f h i i dfrom the mean position and  • the number of vibrations per  second Thi i f d h• This energy is transferred thru  series and parallel circuits to  obtain desired results safety thru design 25
  • 26. EarthEarth E th i h ith• Earth is a huge mass with  enormous amount of  charges.  • Energy is applied to earth,  spreads, the displacement  of charge from the mean g position progressively  reduces.  • Finally the displacement orFinally the displacement or  tension becomes  infinitesimal. In normal  condition charges in EARTHcondition charges in EARTH  appear stable with hardly  any tension.  safety thru design 26
  • 28. Attachment to opposite fieldAttachment to opposite field safety thru design 28
  • 33. Tackling Different FrequenciesTackling Different Frequencies f d d• Dissipation of  energy depends on  Earth loop impedance. • High frequency signals encounter g q y g high inductive impedance if the  loop length is long. Hence the  Ground path needs to be as shortGround path needs to be as short  as physically possible. • As ground is a dielectric, it is also  d h l l d fgood to have a plate electrode for  higher displacement current. • Higher frequencies do not enter g q deep earth, hence it is imperative  to have more number of shallow  earthearth • Use Earth Bond safety thru design 33
  • 34. Revisit your Earth GridRevisit your Earth Grid D h th E th id d d b t• Do you have the Earth grid drg. and subsequent  record of changes conducted in your premises • Is Earth pit reading in the grid different at• Is Earth pit reading in the grid different at  different places • Has the Source increased• Has the Source  increased • Has number of feeders or distributors changed A U b l d H i b i ti f• Are Unbalances and Harmonics been existing for  a long time. • Is off schedule maintenance a regular feature• Is off schedule maintenance a regular feature • GET YOUR SELF AUDITED safety thru design 34
  • 35. Who can be an AuditorWho can be an Auditor • H i K l d f• Having Knowledge of  – IEEE 80 2000 for substation – IEEE 665 1995 for Generating Station – IEEE 142 1991 for Industrial establishment f h– IEEE 81 1993 for Earthing Measurements – IEEE 1100 for powering and grounding electronic equipments. – IEEE 575 for sheath bonding and induced voltages – BS 7340 1998 Code of practice for Earthing IEC 62305 P t 1 t P t 4– IEC 62305 Part 1 to Part 4 – NFPA 70 and NFPA 780 – API RP 2003 for statics and lightning protection – And many more ref. texts H i R i it i t t h k it l t i t• Having Requisite equipments to check vital parameters using stray  current filters. • Has the desired National and International Experience to Audit Refineries– Refineries – Power Stations etc. • Should be a Solution providerp safety thru design 35
  • 36. Rejuvenation of Live gridRejuvenation of Live grid safety thru design 36
  • 37. Rejuvenation of live gridRejuvenation of live grid • Measure the soil resistivity with• Measure the soil resistivity with – Stray current filter – Variable frequency High and low current injection probe– High and low current injection probe • Make polar graph for accurate soil resistivity • Design the earth grid as per IEEE 80 2000 as if it was for the new grid Th f f iti th it b l 1 7% f th f• The surface area of exiting earth pit may be only 1‐7% of the surface area  of the entire Earth grid. • May involve multiple layer/tier of peripheral correction.  U i li d t i d t k li d t ti• Use specialized manpower trained to work on live yard or station • New trenching can be very tedious. It may cut across existing HV, LV or  control cables At th d f ti All th th it h ld h l t• At the end of correction,  All the earth pits should have almost same  resistance value without any pit correction safety thru design 37
  • 39. Proper and Permanent JointingProper and Permanent  Jointing  safety thru design 39
  • 41. Sigma EarthSigma Earth •The  Energy after leaving the  electrode encounters  different  k d f l h fl f lkinds of soil where reflection factor comes into play •Sigma earth ensures that  artificial treatment compounds are  laid in a specific  geometric pattern to minimize the reflection •Thru proper calculation, can achieve less than 1 ohm in veryThru proper calculation, can achieve less than 1 ohm in very  hard soil. •Used for Independent Electronic Earth  or reference earth  safety thru design 41
  • 42. Iris earthIris earth • One earth sensor is put inside an old• One earth sensor is put inside an old  or new pit. • Various parameters like date,  location, value etc are logged in every  sensor. • The sensor is programmed to alarm  on few criteria’s. • There is multiple level of alarm• There is multiple level of alarm. • A peripheral command center (PCC)  can talk to approximately 100 earth  pits. • A hand held tester is provided to  check the earth pit conditions  remotely • The PCC can be locally connected to a• The PCC can be locally connected to a  local Laptop and a remote Server on  LAN or GSM. safety thru design 42
  • 43. Geomagnetic Storms caused by Solar  Flares or CME • Earth’s magnetic field being pushed out of the way by the nuclear explosion or solar storm f ffollowed by the field being restored to its natural place. •This process can produce geo‐ magnetically induced currents in long electrical conductors (like power lines) which can damage or d l fdestroy power line transformers. safety thru design 43
  • 44. Nasa warns solar flares 'huge  space storm'cause devastation • According to VERY rough• According to VERY rough  calculations, that solar flare was  approximately 250,640 km tall,  and 342,050 km wide. , • To put that in perspective, the  Earth is about 12,756 km in  diameter. That means it was  b h ll dabout 19.6 Earths tall and 27  Earths wide. • In a new warning, Nasa said the  super storm nearing 2013 wouldsuper storm nearing 2013 would  hit like “a bolt of lightning” and  could cause catastrophic  consequences for the world’s  • March 1989 (Quebec) – 480nT/min, Knocked out power  to 6 million people in 92 seconds • May 1921q health, emergency services and  national security unless  precautions are taken – Up to 4,800nT/min • Sept. 1859 (Carrington event) – 2,000 to 5,000nT/min • NOW 2013‐2023 safety thru design 44 NOW 2013 2023 – Expected 5000nT/min
  • 45. What will happen to our GridsWhat will happen to our Grids • All long transmission lines,  Railway lines, Pipelines will  withstand the impact of GICwithstand the impact of GIC • Incorporation of  – Neutral • Resistors • Capacitors with shunt  switch – Series Capacitors safety thru design 45
  • 46. Operational SolutionOperational Solution • Build command and control centre to receive satellite data in to  initiate requisite action. We have approximately 60 ‐90 min to  initiate and complete operational procedures including discharginginitiate and complete operational procedures including discharging • Break down the power system into small islands and earth the  surge created using automated star point switch connections and  disconnections. • Creating an efficient maintenance free and monitorable earthing  systemsystem • Predicting static accumulations, and BMS enabled lightning  protection systemp y • The entire infrastructure needs to be grounded as much as 'possible  without forming Earth loops
  • 47. It is Either Now Or Never WE ARE RESPONSIBLE It is Either Now Or Never safety thru design 47