SlideShare une entreprise Scribd logo
1  sur  16
Construction of Primary School
PROJECT CHARTER
BY
Hashir Khan & Usama Rasheed
Project Introduction
• This is a project of constructing a single storied building infrastructure
for a primary school comprising of 7 classrooms, toilets, office and a
playground. This is project is to be developed in Chechen (AJ&K),
where education facilities are not available because of earth quake
destroyed the area. As in recent surveys we all are well aware of
destructions caused by environmental changes in Pakistan. Therefore,
in such areas there are collapsed buildings unable to accommodate
students, so they have no option but to go other schools located at
far distances or abandon their education. Therefore, this project is of
utmost importance.
Project Scope
• Cost efficient and quick to build
• Novel Design and Unique
• Environment friendly
• Durability and safe
• Fast Back Engineering
• Recyclability
• Design flexibility
• Easy Manage
• Earth quake proof
• Secure Location
• Time saving
• Low Risk
Project Objectives
• To ensure the quality of the project by mitigating the risk.
• Rebuild the primary school
• Provide the infrastructure for quality education to the increasing number of
children
• Construct a single-storied building on the foreseen plot (accommodating 7
class rooms, 4 toilets, 1 office, 1 fully furnished library, facilitated recreational
hall).
• Fence the school area and to build a school compound considering the safety
of the students
• To deliver the project on defined time.
• To deliver the project according to scope and specifications defined by the
NGO.
Project Phases & their Scope
Initiation
• Business case development (project development and approval)
• Permits (all the legal permissions required for the construction)
• Procurement (electrical, plumbing, tender period)
• evaluation (site inspection, interior and exterior survey to avoid any risk in
future)
Planning
• Drawings/ designs (development architectural design and its approval)
• Project plan (development of whole plan)
Construction
• Foundation (land grading and levelling)
• Interior (includes wall painting, design, structure)
• Exterior (includes fencing, playground design, cafeteria)
• Finishing (floor finishing, installation of electrical goods etc.)
Turnover
• Walk through
• School transferred to NGO
• Closing (hand it over the building to concerned authorities)
Major Deliverables
• Project charter
• Project Planning documents
• proposals
• Design drawings
• Design documents
• A site investigation report
• Progress report
• Product quality enhancement
• Any design reviews
• Project completion by handing over the fully furnished building
Human Resources
• Architect/Civil Engineer
• Procurement Officer
• Site Supervisors
• Surveyor / Quantity survey
• Masson
• Finance Manager
• Accountant
• Labors (Digging)
• Plumbers
• Electrician
• Carpenters
• Team of Painting and ceiling
• Drivers
• Security Guard
• Safety officer
Project Budget & Schedule
WBS phase start date end date budget
1. DESigN 1-3-22 10-3-22 50,000 RS
1. SUBSTRUcTURE 11-3-22 28-3-22 15,00000 RS
1. SUPERSTRUCTURE 29-3-22 20-4-22 60,00000 RS
5.
FINISHING WORK
END OF THE PROJECT
21-4-22
31-5-22
30-5-22
7-6-22
25,00000 RS
50,000 RS
total 100,00000 RS
Business needs & strategic goals
As we are doing this project with an NGO (Khidmat foundation) that is serving
and delivering many projects for the welfare of the people of Pakistan. One of
the major goals of this NGO is to rebuild the primary schools that have been
destroyed through devastated flood and earth quake in recent years. Therefore,
they are not only providing the land for the construction but also providing the
budget for the whole infrastructure. So, they are the stakeholders of this
project and therefore business needs and strategic goals of this project are as
follows:
• To serve the humanity
• To provide education to those who survived after the natural disasters in
Pakistan
Project Constraints
no. category constraints
1 material shortage or unavailability of building material
2 volunteers unavailability of enough staff and volunteers
3 admin approval / licencing inefficent practices and processes of local government administrators
4 road closure road closure due to weather and other unforeseen conditions
Assumptions & Risks
• No adverse weather is expected
• Stable and safe environment
• Material unavailability
• Political instability
• Weather conditions
• Unexpected situation during construction
Project Mile stones
wbs activity description estimated complettion
1. charter signed and approved --------
2. obtain all required legal document --------
3. award contract --------
4. schematic desgin approve --------
5. footing/ foundation completed and inspected --------
6. exterior and interior walls completed and expected --------
7. roofing completed and inspected --------
8. all finishing work completed --------
9. ownership transfer to ngo --------
10. stake holder project closed --------
Project Success Criteria
• Completion of project in estimated time
• Completion of project in given budget
• Delivery of the project within scope, ensuring the quality as well.
Project Stakeholders
• all the legal entities related to khidmat foundation.
• All the concerned authorities that are involved in each phase of the
project.
• Students who will get quality education and better facilities on
completion of this project.
WBS for each phase
CONSTRUCTION OF A
PRIMARY SCHOOL
DESGIN SUPER
STRUCTURE
SUB
STRUETURE
FINISHING
WORK
END OF THE
PROJECRT
Site Visit Inspection Of
Everything
Plaster
Column and
Beam
Layout of
foundation
Site
Documentation
Hand Over
Utility of
Electricity/Water
Brick Masonry
Work
Excavation
Building plan &
technical drawing
Roof ceiling
Lintel over
Door Window
Levelling &
P.C.C
Back filling of
excavated
earth
Flooring
Door and
Window Framing
R.C.C. Up to
plinth level
Estimate and
budget
Paint
Roofing
R.C.C. for
foundation
Report
Soil testing
Electrical Wiring
and Plumbing
Woodwork
Install Doors
And Windows
Light and fans
Cleaning and
final touch
Signoff

Contenu connexe

Tendances

Cavity walls, Building construction, passive cooling
Cavity walls, Building construction, passive coolingCavity walls, Building construction, passive cooling
Cavity walls, Building construction, passive cooling
DhvaniR2
 
Advantages and disadvantages of Prestressed concrete
Advantages and disadvantages of Prestressed concreteAdvantages and disadvantages of Prestressed concrete
Advantages and disadvantages of Prestressed concrete
Baruti Balinda Jonathan
 
Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2
saibabu48
 
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESEXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
A Makwana
 

Tendances (20)

Advanced construction equipments and techniques
Advanced construction equipments and techniquesAdvanced construction equipments and techniques
Advanced construction equipments and techniques
 
Defects in buildings & remedies
Defects in buildings & remediesDefects in buildings & remedies
Defects in buildings & remedies
 
Site distance in highway engineering
Site distance in highway engineeringSite distance in highway engineering
Site distance in highway engineering
 
Internship Report on Building Construction
Internship Report on Building ConstructionInternship Report on Building Construction
Internship Report on Building Construction
 
Environmental engineering 2
Environmental engineering   2Environmental engineering   2
Environmental engineering 2
 
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
 
Water proofing in buildings
Water proofing in buildingsWater proofing in buildings
Water proofing in buildings
 
Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000
 
TYPES OF SPILLWAYS & PROMINENT FEATURES
TYPES OF SPILLWAYS & PROMINENT FEATURESTYPES OF SPILLWAYS & PROMINENT FEATURES
TYPES OF SPILLWAYS & PROMINENT FEATURES
 
Under reamed pile construction (usefulsearch.org) (useful search)
Under reamed pile construction (usefulsearch.org)  (useful search)Under reamed pile construction (usefulsearch.org)  (useful search)
Under reamed pile construction (usefulsearch.org) (useful search)
 
Cavity walls, Building construction, passive cooling
Cavity walls, Building construction, passive coolingCavity walls, Building construction, passive cooling
Cavity walls, Building construction, passive cooling
 
Retaining wall
Retaining wallRetaining wall
Retaining wall
 
Advantages and disadvantages of Prestressed concrete
Advantages and disadvantages of Prestressed concreteAdvantages and disadvantages of Prestressed concrete
Advantages and disadvantages of Prestressed concrete
 
Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2Iii design-of-steel-structures-unit-2
Iii design-of-steel-structures-unit-2
 
Retaining wall
 Retaining wall  Retaining wall
Retaining wall
 
Diaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignDiaphragm wall: Construction and Design
Diaphragm wall: Construction and Design
 
Highway failure & their maintenance ppt
 Highway failure & their maintenance ppt Highway failure & their maintenance ppt
Highway failure & their maintenance ppt
 
Doors,Windows & Ventilator in Building Construction
Doors,Windows & Ventilator in Building ConstructionDoors,Windows & Ventilator in Building Construction
Doors,Windows & Ventilator in Building Construction
 
Type of structural joints
Type of structural joints Type of structural joints
Type of structural joints
 
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESEXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
 

Similaire à Construction of Primary School slides-1.pptx

Muhammad Hamid Bashir CV
Muhammad Hamid Bashir CVMuhammad Hamid Bashir CV
Muhammad Hamid Bashir CV
Hamid Bashir
 
ZAKI Michael_CV 042014
ZAKI Michael_CV 042014ZAKI Michael_CV 042014
ZAKI Michael_CV 042014
Michael Khalil
 
latest.MLYS. murali.cv.april2014 (3)
latest.MLYS. murali.cv.april2014 (3)latest.MLYS. murali.cv.april2014 (3)
latest.MLYS. murali.cv.april2014 (3)
murali perianan
 
latest.MLYS. murali.cv.april2014 (3)
latest.MLYS. murali.cv.april2014 (3)latest.MLYS. murali.cv.april2014 (3)
latest.MLYS. murali.cv.april2014 (3)
murali perianan
 
building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENT
RiyaVerma238431
 
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docxBUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx
Sudas Duddey
 
Jha Ajachi_NIT Jamshedpur_CV
Jha Ajachi_NIT Jamshedpur_CVJha Ajachi_NIT Jamshedpur_CV
Jha Ajachi_NIT Jamshedpur_CV
Ajachi Jha
 
CVnz - Andrew Nash
CVnz - Andrew NashCVnz - Andrew Nash
CVnz - Andrew Nash
Andrew Nash
 
WEC CV_2016 09 06
WEC CV_2016 09 06WEC CV_2016 09 06
WEC CV_2016 09 06
Wauren Cruz
 
Civil Engineer CV
Civil Engineer CVCivil Engineer CV
Civil Engineer CV
Afzal Khan
 
engr ijaz 1 qc civil engineer I did civil engineering from University peshawar
engr ijaz 1 qc  civil engineer I did civil engineering from University peshawarengr ijaz 1 qc  civil engineer I did civil engineering from University peshawar
engr ijaz 1 qc civil engineer I did civil engineering from University peshawar
engrijaz727
 

Similaire à Construction of Primary School slides-1.pptx (20)

final ppt.pptx
final ppt.pptxfinal ppt.pptx
final ppt.pptx
 
Muhammad Hamid Bashir CV
Muhammad Hamid Bashir CVMuhammad Hamid Bashir CV
Muhammad Hamid Bashir CV
 
Santhan CV-2016
Santhan CV-2016Santhan CV-2016
Santhan CV-2016
 
ZAKI Michael_CV 042014
ZAKI Michael_CV 042014ZAKI Michael_CV 042014
ZAKI Michael_CV 042014
 
Summer training project by surendra
Summer training project by surendraSummer training project by surendra
Summer training project by surendra
 
Project
Project Project
Project
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
E SQUARE GROUP A1-6.pptx
E SQUARE GROUP A1-6.pptxE SQUARE GROUP A1-6.pptx
E SQUARE GROUP A1-6.pptx
 
latest.MLYS. murali.cv.april2014 (3)
latest.MLYS. murali.cv.april2014 (3)latest.MLYS. murali.cv.april2014 (3)
latest.MLYS. murali.cv.april2014 (3)
 
latest.MLYS. murali.cv.april2014 (3)
latest.MLYS. murali.cv.april2014 (3)latest.MLYS. murali.cv.april2014 (3)
latest.MLYS. murali.cv.april2014 (3)
 
building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENT
 
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docxBUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx
 
Jha Ajachi_NIT Jamshedpur_CV
Jha Ajachi_NIT Jamshedpur_CVJha Ajachi_NIT Jamshedpur_CV
Jha Ajachi_NIT Jamshedpur_CV
 
CVnz - Andrew Nash
CVnz - Andrew NashCVnz - Andrew Nash
CVnz - Andrew Nash
 
25 years of Projects in a Nutshell
25 years of Projects in a Nutshell25 years of Projects in a Nutshell
25 years of Projects in a Nutshell
 
WEC CV_2016 09 06
WEC CV_2016 09 06WEC CV_2016 09 06
WEC CV_2016 09 06
 
KN
KNKN
KN
 
Andrew Quilaneta CV
Andrew Quilaneta CVAndrew Quilaneta CV
Andrew Quilaneta CV
 
Civil Engineer CV
Civil Engineer CVCivil Engineer CV
Civil Engineer CV
 
engr ijaz 1 qc civil engineer I did civil engineering from University peshawar
engr ijaz 1 qc  civil engineer I did civil engineering from University peshawarengr ijaz 1 qc  civil engineer I did civil engineering from University peshawar
engr ijaz 1 qc civil engineer I did civil engineering from University peshawar
 

Dernier

Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
rknatarajan
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
Tonystark477637
 

Dernier (20)

Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 

Construction of Primary School slides-1.pptx

  • 1. Construction of Primary School PROJECT CHARTER BY Hashir Khan & Usama Rasheed
  • 2. Project Introduction • This is a project of constructing a single storied building infrastructure for a primary school comprising of 7 classrooms, toilets, office and a playground. This is project is to be developed in Chechen (AJ&K), where education facilities are not available because of earth quake destroyed the area. As in recent surveys we all are well aware of destructions caused by environmental changes in Pakistan. Therefore, in such areas there are collapsed buildings unable to accommodate students, so they have no option but to go other schools located at far distances or abandon their education. Therefore, this project is of utmost importance.
  • 3. Project Scope • Cost efficient and quick to build • Novel Design and Unique • Environment friendly • Durability and safe • Fast Back Engineering • Recyclability • Design flexibility • Easy Manage • Earth quake proof • Secure Location • Time saving • Low Risk
  • 4. Project Objectives • To ensure the quality of the project by mitigating the risk. • Rebuild the primary school • Provide the infrastructure for quality education to the increasing number of children • Construct a single-storied building on the foreseen plot (accommodating 7 class rooms, 4 toilets, 1 office, 1 fully furnished library, facilitated recreational hall). • Fence the school area and to build a school compound considering the safety of the students • To deliver the project on defined time. • To deliver the project according to scope and specifications defined by the NGO.
  • 5. Project Phases & their Scope Initiation • Business case development (project development and approval) • Permits (all the legal permissions required for the construction) • Procurement (electrical, plumbing, tender period) • evaluation (site inspection, interior and exterior survey to avoid any risk in future) Planning • Drawings/ designs (development architectural design and its approval) • Project plan (development of whole plan)
  • 6. Construction • Foundation (land grading and levelling) • Interior (includes wall painting, design, structure) • Exterior (includes fencing, playground design, cafeteria) • Finishing (floor finishing, installation of electrical goods etc.) Turnover • Walk through • School transferred to NGO • Closing (hand it over the building to concerned authorities)
  • 7. Major Deliverables • Project charter • Project Planning documents • proposals • Design drawings • Design documents • A site investigation report • Progress report • Product quality enhancement • Any design reviews • Project completion by handing over the fully furnished building
  • 8. Human Resources • Architect/Civil Engineer • Procurement Officer • Site Supervisors • Surveyor / Quantity survey • Masson • Finance Manager • Accountant • Labors (Digging) • Plumbers • Electrician • Carpenters • Team of Painting and ceiling • Drivers • Security Guard • Safety officer
  • 9. Project Budget & Schedule WBS phase start date end date budget 1. DESigN 1-3-22 10-3-22 50,000 RS 1. SUBSTRUcTURE 11-3-22 28-3-22 15,00000 RS 1. SUPERSTRUCTURE 29-3-22 20-4-22 60,00000 RS 5. FINISHING WORK END OF THE PROJECT 21-4-22 31-5-22 30-5-22 7-6-22 25,00000 RS 50,000 RS total 100,00000 RS
  • 10. Business needs & strategic goals As we are doing this project with an NGO (Khidmat foundation) that is serving and delivering many projects for the welfare of the people of Pakistan. One of the major goals of this NGO is to rebuild the primary schools that have been destroyed through devastated flood and earth quake in recent years. Therefore, they are not only providing the land for the construction but also providing the budget for the whole infrastructure. So, they are the stakeholders of this project and therefore business needs and strategic goals of this project are as follows: • To serve the humanity • To provide education to those who survived after the natural disasters in Pakistan
  • 11. Project Constraints no. category constraints 1 material shortage or unavailability of building material 2 volunteers unavailability of enough staff and volunteers 3 admin approval / licencing inefficent practices and processes of local government administrators 4 road closure road closure due to weather and other unforeseen conditions
  • 12. Assumptions & Risks • No adverse weather is expected • Stable and safe environment • Material unavailability • Political instability • Weather conditions • Unexpected situation during construction
  • 13. Project Mile stones wbs activity description estimated complettion 1. charter signed and approved -------- 2. obtain all required legal document -------- 3. award contract -------- 4. schematic desgin approve -------- 5. footing/ foundation completed and inspected -------- 6. exterior and interior walls completed and expected -------- 7. roofing completed and inspected -------- 8. all finishing work completed -------- 9. ownership transfer to ngo -------- 10. stake holder project closed --------
  • 14. Project Success Criteria • Completion of project in estimated time • Completion of project in given budget • Delivery of the project within scope, ensuring the quality as well.
  • 15. Project Stakeholders • all the legal entities related to khidmat foundation. • All the concerned authorities that are involved in each phase of the project. • Students who will get quality education and better facilities on completion of this project.
  • 16. WBS for each phase CONSTRUCTION OF A PRIMARY SCHOOL DESGIN SUPER STRUCTURE SUB STRUETURE FINISHING WORK END OF THE PROJECRT Site Visit Inspection Of Everything Plaster Column and Beam Layout of foundation Site Documentation Hand Over Utility of Electricity/Water Brick Masonry Work Excavation Building plan & technical drawing Roof ceiling Lintel over Door Window Levelling & P.C.C Back filling of excavated earth Flooring Door and Window Framing R.C.C. Up to plinth level Estimate and budget Paint Roofing R.C.C. for foundation Report Soil testing Electrical Wiring and Plumbing Woodwork Install Doors And Windows Light and fans Cleaning and final touch Signoff